Upload
phungdung
View
222
Download
8
Embed Size (px)
Citation preview
Naracoorte Lucindale Council 23/10/20143:33 PM Major Projects 2014‐15 Program
GL Code Project Name From To
2014-15Approved
Budget (excl. GST)
External Funding
Contribution
TOTALProject Cost(excl. GST) Actual Cost Project Description
Project Sponsor
Project Manager
Supervisor/
Team Leader
Proposed Start Date
Proposed completion
date Status
UNSEALED ROAD CONSTRUCTION $ 55,000 $ - $ 55,000
50760UF090 Fern St Peasron St Cameron St $ 15,000 $ 15,000 Design only 2014-15
Steve Tom Peter Bud On Target50760UC530 Coles-Killanoolla Rd End of Seal Start of Seal $ 10,000 $ 10,000 Design only 2014-15 Steve Tom On Target50760UL330 Lochaber North Rd Kilmorey Rd Boundary $ 10,000 $ 10,000 Design only 2014-15 RSA Tonkins Steve Tom On Target
50760UR190 Reid Rd RealigmentNear
DiGiogio's $ 10,000 $ 10,000 Road safety audit 2014-15, consultation RSA Tonkins Steve Tom On Target50760UJ070 Janz St Fifth Av sixth $ 10,000 $ 10,000 Design only 2014-15 Steve Tom On Target
NEW West Avenue Extension $ - RSA Tonkins $ 55,000 $ - $ 55,000
UNSEALED ROAD RESHEET $ 1,411,000 $ - $ 1,411,000
50700GM400 Messamurray Rd2520m from end of seal
5740m from end of seal $ 255,000 $ 255,000 Resheet of 3.2km and culvert replacement. School bus route. Steve Harry Benny On Target
50700GC310 Charcutt RdColes
KillanoolaApprox 6.5kms
West $ 512,257 $ 512,257 In poor condition and badly degraded due to blue gum harvest by ABP. Road is being maintained by ABP contractors during harvest. Steve Harry Peter On Target
50700GP450 Petchs Rd Chappels Boddingtons $ 70,000 $ 70,000 Grade and monitor un-made section - resheet southern end in 2014-15 Steve Harry Peter 14-Sep 23-Sep Completed
50700GD250 Diagonal Rd, CallendaleCallendale
Rd Border $ 274,500 $ 274,500 3km to be resheeted. 1km from VA lane heading north plus 2km south from Jindalee. Possible patching in other sections. Steve Harry Peter Completed
50700GH700 Jessie RdMiddle Section $ 62,500 $ 62,500 Patching and stablisation with polycom Steve Harry Peter 24-Sep 8-Oct Completed
50700GE150 Ellisons Road $ 4,000 RSA Tonkins Steve Tom $ 1,174,257 $ - $ 1,174,257
available $ 236,743 Other projects to be considered once the above are completedSEALED ROAD RECONSTRUCTION $ 3,259,000 $ 1,233,299 $ 3,259,000
50720SB550 Butler Tce, Naracoorte Gordon St Smith St $ 1,400,000 $ 565,737 $ 1,400,000
Major reconstruction incluidng; kerb replacement, shared use path, off street parking, pavement suitable for b-doubles. Close off McCoy to b-doubles. Widen intersections for improved turning movements. Upgrade stormwater drainage and improve landscaping and lighting. Contract and dependant on funding application Steve Harry Contract On Target
50720SS330 Shepherds Rd, Kyby Jessie Rd Border $ 680,000 $ 352,562 $ 680,000 Stage 1 - Border to Jessie. Contracted to Gambier Earth Movers, carried forward from 2013-14 . - includes $550K of carry forward amount Steve Harry Contract 22-Sep 20-Dec Slipping
50720SB320 Bool Lagoon West Rd Maauope Rd Dual Lane Seal $ 635,000 $ 315,000 $ 635,000
Stage 1 - Bool Lagoon Rd to Moyhall Rd part constructed in 2013-14 Stage 2 - Moyhall Rd to Existing 2 lane seal. Includes $245k carry forward from 2013-14 Construction by Council. Steve Harry Peter 29-Sep 20-Dec On Target
50720SG010 Gap Rd, Frances 4.9km east $ 10,000 $ 10,000 Design only Steve Tom Peter Bud 29-Sep 13-Oct On Target
50720SO070 Old Caves Rd
Approx 1.2kms South of
Pistol Club new Caves Rd $ 25,000 $ 25,000 Design only Steve Tom Peter Bud 14-Oct 14-Nov On Target
50720SE010 East Settlement Rd
910m North of Sydney
Road $ 80,000 To be reviewed Steve Harry Benny 30-Sep On Target50720SS070 Schinckels Rd Cadgee Rd Menhennits Rd $ 15,000 $ 15,000 Design only Steve Tom Peter Bud 5-Jan 23-Jan On Target
50720SS190 Second St, Frances Fourth St East Tce $ 204,000 $ 204,000 Consultation suggests Fourth St a higher priority, consider changing. Council construction Steve Harry On Target
50720SB230 Binnum-Benayeo Rd
440m east Hynam
Frances Road Railway Line $ 50,000 $ 50,000 Short section requiring soil tests and design. Council construction Steve Harry On Target50720SC110 Campbell St, Naracoorte Rolland St End $ 15,000 $ 15,000 Design only Steve Tom On Target
50720SB310 Bool Lagoon RdBool Lagoon
West Rd 3.6km east $ 15,000 $ 15,000 Design only 2014-15 Steve Tom Peter Bud 17-Nov 5-Dec On TargetMoyhall Road $ 3,000 $ 3,000 Design only 2014-15 Steve Tom Peter Bud 8-Dec 19-Dec On Target
50720SR390 Robertson St, Naracoorte Rolland St Jones Street $ 265,000 $ 265,000 Part of PLEC project includes landscaping, kerb and water table, pavements. Contract Steve Daniel Slipping
$ 3,049,000 $ 1,233,299 $ 3,397,000 Design only SteveAvailable $ - $ (138,000)
SEALED ROAD RESEALS $ 860,500 $ - $ 860,500 50680RC010 Cadgee Road Playford Dr Burkes Rd $ 122,103 $ 122,103 Scrub Coat AC 7 Asphalt with 14mm Crumb Rubber Reseal Tom David G Contract On Target
50680RH670 Hynam Caves RoadVictoria
Fossil Road Langkoop Road $ 55,670 $ 55,670 10mm C170 reseal cracking under trees with some parts of the seal breaking away on the cracks. Road still smooth and sound Tom David G Contract On Target
50680RL051 Langkoop RoadYelloch Bridge 100m East $ 19,580 $ 19,580
Bad cracking and some depressions on approach to bridge fom Eastern side. Needs shape correction and sealing. Tom David G Contract On Target
50680RS810 Struan - Joanna RdOld Riddoch
Highway end of bitumen $ 30,663 $ 30,663 7mm C170 Reseal
Tom David G Contract On Target
50680RC090 Cameron St Park Terrace Creek $ 12,212 $ 12,212 7mm S35E Reseal plus spoon drain replacement -see 50640KC090 Tom David G Contract On Target
50680RO170 Oliver Street Park Terrace Freeling St $ 6,145 $ 6,145 7mm S35E Reseal Tom David G Contract On Target
50680RE010 East SettlementWrattonbully
Rd End $ 44,545 $ 44,545 10mm C170. Combine with construction. Tom David G Contract On Target50680RB290 Boddingtons Rd Cadgee Rd Hazels Rd $ 124,538 $ 124,538 10mm Crumb Rubber Stage 1 - Cadgee Rd to Hazels Rd Stage Tom David G Contract On Target50680RB470 Brown Av Smith St End $ 3,596 $ 3,596 7mm S35E Tom David G Contract On Target
50680RO070 Old Caves Road Pinkerton RdEnd of Primer
Seal $ 72,783 $ 72,783 7mm S35E Tom David G Contract On TargetPage 1
Naracoorte Lucindale Council 23/10/20143:33 PM Major Projects 2014‐15 Program
GL Code Project Name From To
2014-15Approved
Budget (excl. GST)
External Funding
Contribution
TOTALProject Cost(excl. GST) Actual Cost Project Description
Project Sponsor
Project Manager
Supervisor/
Team Leader
Proposed Start Date
Proposed completion
date Status
50680RS670 Stewart Terrace Gum Avenue Field Avenue $ 36,605 $ 36,605 7mm S35E Tom David G Contract On Target
50680RR430 Roberston StreetRolland Street Jones Street $ 100,042 $ 100,042 7mm S35E Tom David G Contract On Target
50680RF090 Fern Street Oliver StreetCameron
Street $ 2,371 $ 2,371 7mm S35E Tom David G Contract On Target50680RT170 Thomson Street Bates Lane End of Seal $ 10,060 $ 10,060 7mm S35E Tom David G Contract On Target
50680RL050 Langkoop Road Pinkerton Rd Bells Road $ 143,490 $ 143,490 7mm S35E Tom David G Contract On TargetPavy Drive Review
$ 784,403 $ - $ 784,403 Available $ - $ 76,097
INTERSECTIONS $ 265,000 $ - $ 265,000
50660IA003Langkoop Rd and Concrete Bridge Rd $ 10,000 $ 10,000
Road safety report 13-14. Design 14-15. Possible grant application to Road Safety Fund grant application submitted Steve Tom On Target
50660IA004 Pinkerton Rd and Old Caves Rd $ 20,000 $ 20,000 Design 14-15 Steve Tom On Target
50660IA005 Robertson St and Jones St $ 200,000 $ 200,000 Needs to be incorporated with Robertson Street PLEC project and CBD drainage. If projects don’t align, may need to be held over to 2015-16. Steve Daniel Contract On Target
50660IA006Wrattonbully and East Settlement Rd $ 5,000 $ 5,000 Road safety Audit awarded to Tonkins Steve Tom Contract On Target
50660IA007Woolumbool and Fairview Rd Intersection $ 26,040 $ 26,040 reseal of intersection Steve David G Contract On Target
50660IA001 Cedar Av and Jenkins Tce $ 20,000 $ 20,000 Road safety audit followed by concept design for public consultation. awarded to Tonkins Steve Tom Contract On Target
50660IA002Church St and McRae St, Naracoorte $ 10,000 $ 10,000
Design only 2014-15 Dangerous intersection. Subject to Church St design.Steve Tom On Target
$ 291,040 $ - $ 291,040 Available $ - $ (26,040)
KERB AND WATERTABLE $ 355,000 $ - $ 355,000 50640KL270 Livingston St, Naracoorte McCoy Butler $ 275,000 $ 275,000 Kerb and water table, pavement replacement, driveway crossovers 230m Tom Harry On Target
50640KA230 Attiwill St
Opposite Longridge Retirement
Village $ 57,348 $ 57,348 establishment of carpark opposite Longridge.
Tom Shane On Target
50640KC250 Cedar Av, Naracoorte Schinckel Rd End of Housing $ 10,000 $ 10,000 design 2014-15 Tom Shane Peter Bud 26-Jan 30-Jan On Target50640KA231 Attiwil St Spoon Drain $ 10,000 $ 10,000 includes pram cross overs and minor pavement work Tom Shane Completed50640KC090 Cameron St Spoon Drain $ 10,000 $ 10,000 Linked to reseal 50680RC090 Tom Shane Benny 14-Sep 21-Sep Completed
$ 362,348 $ - $ 362,348 Available $ - $ (7,348)
FOOTPATHS $ 420,000 $ - $ 420,000
50780WC270 Centenary Avenue, Lucindale
Balharry Memorial
Kindergarten Gum Avenue $ 20,000 $ 20,000 Requested change by LINC to proposed footpath project in Lucindale Steve Shane Pip 29-Sep 30-Sep Completed
50780WS670 Stewart Tce Smith St MacDonnell St $ 140,000 $ 140,000
Repair path surface as identified in Local Area Bicycle Plan. Connection to school. Includes replacing fencing, signage and new connection to Butler Terrace. Refer to designs for 50720SB550. Steve Shane Benny Dec-14 Jan-15 On Target
50780WP550 Pethick St Gordon Foster Street $ 20,000 $ 20,000 connecting exisiting footpaths. Seeking DPTI contribution for removal of rail crossing Steve Shane Benny On Target
50780WP070Panorama Cres Walkway Reserve Pine Grove Panorama Crs $ 10,000 $ 10,000 Easy care rubble pathway Steve Shane Benny 25-Sep 26-Sep On Target
$ 190,000 $ - $ 190,000 available $ - $ 230,000 several projects under review with CBD drainage project
STORMWATER DRAINAGE $ 1,585,000 $ 714,000 $ 1,585,000
50740DA002 Naracoorte CBD Arthur St
Naracoorte Creek Via
Smith $ 1,500,000 $ 714,000 $ 1,500,000 Stage one 2014-15 from Creek to Jones and Robertson Street intersection Steve Daniel Contract Slipping
50740DA001 Adelaide Av and Gordon StCnr Gordon
St $ 45,000 $ 45,000 Designed 2013-14. Review required before proceeding On Target50740DA005 Loveday St Detention Basin $ 40,000 $ 40,000 Cleaning and lifting of bore casing. Work with DEWNR On Target
$ 1,585,000 $ 714,000 $ 1,585,000
BRIDGES AND MAJOR CULVERTS $ 260,000 $ 170,000 $ 410,000 50620BS070 Schinckels Rd Culvert $ 30,000 $ 30,000 Guard rail installation Contract Tom Harry Benny 28-Sep Completed
50620BM540 Moyhall Rd Culverts
1200m north of Limberts
Ln100m South of
Limberts Ln $ 170,000 $ 170,000 $ 340,000 Submitting application to Aust Govt Bridges grants program, if unsuccessful only one bridge culvert will be replaced Tom Harry Peter On Target
50620BR050 Radfords Rd Culvert $ 20,000 $ 20,000 Guard rail installation Contract Tom Harry Benny 28-Sep Completed
50620BM030 MacDonnell St Bridge - Railing $ 10,000 $ 10,000 Replacement of fence Steve Harry Benny On Target
50620BS010 Sandstone Av Culvert Widening Across Drain $ 10,000 $ 10,000 Design Steve Tom On TargetPage 2
Naracoorte Lucindale Council 23/10/20143:33 PM Major Projects 2014‐15 Program
GL Code Project Name From To
2014-15Approved
Budget (excl. GST)
External Funding
Contribution
TOTALProject Cost(excl. GST) Actual Cost Project Description
Project Sponsor
Project Manager
Supervisor/
Team Leader
Proposed Start Date
Proposed completion
date Status50620BM440 Mill Road culverts $ 20,000 $ 20,000 Guard rail installation Contract Tom Harry Benny 28-Sep Completed
$ 260,000 $ 170,000 $ 410,000 note: seeking $170,000 grant funding $ (150,000)
SPORT AND RECREATION $ 349,603 $ 78,902 $ -
50880ZA021 Swim Lake Shade Sail $ 25,000 $ 25,000 New shade sail on SE end of grass to replace shade lost by removing large pine tree. Includes removal of tree and establishment of turf. Steve Shane 13-Sep On Target
50880ZA020Swimming Lake Crime Prevention $ 75,000 $ - $ 75,000
Replace security cameras and improve traffic management through carpark and roadways. Budget ($20k) transferred to implementation of cycling network in Naracoorte. Try again for grant in 2014-15 as security system needs replacing. Steve David G Contract Pending
50541SA541Lucindale Basketball Court, Railway Tce $ 40,000 $ 40,000
Existing asphalt surface badly deteriorated. Edge repair and stabilsation required. Spray seal or asphalt overlay TBD. Steve David G On Target
50540SA491Gwladys McTernan Park Upgrade $ 5,000 $ 5,000 Working group to be established Steve Shane On Target
50540SA492 BMX Track - Market Square $ 5,000 $ 5,000 Remove BMX track. Steve Shane Completed
50540SA493Landscaping and Paths - Market Square $ 15,000 $ 15,000
Open space would be retained in the centre of the Square, with a proposal to construct a pergola linking a shelter at the BMX track and the Square’s centre. All elements will be linked via a hardened path network. Sink bore and supply irrigation. Steve Daniel On Target
20241227Vegetation Plan - Memorial Parklands $ 5,000 $ 5,000
Replant native veg areas on eastern side and on sandy ridge near Memorial Av. Prepare sites, weed removal, tree guards, etc. Trees for Life. Removal of trees at end of life. Steve Shane Paul On Target
50540SA495BBQ and Shelter - Memorial Parklands $ 35,000 $ 35,000
Install new shelter and BBQ facility adjacent carpark. Extend power from toilet block. Concrete pad. Two BBQ's fully covered with seating and table. Steve Shane Paul On Target
50540SA392Creek Walk Upgrade at Duck Pond $ 20,000 $ 20,000
Realign the creek walk around the duck pond to improve safety. Replace pontoon with recycled plastic product for longer life. New crossing on Park Tce. Landscaping Steve Shane Benny On Target
20281501 Update Bike Strategy $ 25,000 $ 12,500 $ 25,000 Update 2007 Bike Strategy On Target50720SC010 Cadgee Road bike lanes Higgs Road Burkes Road $ 99,603 $ 66,402 $ 99,603 widen Cadgee Road by 1.5m to create bike lanes On Target
$ 349,603 $ 78,902 $ 349,603
WASTE TRANSFER STATIONS $ 35,000 $ - $ 35,000
50515BA311Waste Transfer Station Evaporation Pond $ 5,000 $ 5,000
Establish a larger evaporation pond for the waste water from the compactor shed tor reduce the annual costs of pumping out the evaporation pit. Subject to EPA Tom David G On Target
50515BA312Waste Transfer Station Fencing Replacement $ 10,000 $ 10,000
Replacement 1.8m high secure fencing on Blackwell Rd. Includes gates. Existing fence badly degraded. Tom David G Contract Completed
20184290 Closure of Naracoorte Landfill $ 20,000 $ - $ 20,000 Staged over two years. Includes construction of clay capping, topsoil layer, revegetation and preparation of ongoing management plan. Tom Harry Peter On Target
$ 35,000 $ - $ 35,000
COMMUNITY WASTEWATER MANAGEMENT SCHEMES (STEDS) $ 55,000 $ - $ 55,000 50840CA001 Pump Replacement - Urbrae $ 15,000 $ 15,000 Pump replacements Tom Michael On Target50840CA003 CWMS Lagoon Roadway $ 20,000 $ 20,000 Roadway to lagoons in Lucindale to be improved for all weather access. Tom Michael Completed
50840CA002CWMS Pump Station Telemetry Upgrade $ 20,000 $ 20,000 project cancelled, funds to be retained in CWMS fund Tom Michael Withdrawn
$ 55,000 $ - $ 55,000
LAND AND BUILDINGS $ 528,000 $ 100,000 $ 528,000
50515BA250Market Square Public Conveniences and Park Upgrade $ 200,000 $ 100,000 $ 200,000
The old toilets and current clubrooms of the SEDRA to be removed to make way for the new toilets and carpark access. Includes $200,000 Carry forward amount from 2013-14 Steve Daniel On Target
50880ZA001Swim Lake Changerooms Upgrade $ 150,000 $ 150,000
Upgrade internal fit out of change room facilities and provide hot water to showers. Disabled access to changerooms. Paved sitting area outside kiosk for patrons to enjoy food. Steve Daniel On Target
50515BA090Naracoorte Town Hall Roof Plumbing $ 40,000 $ 40,000
Design and implement new roof plumbing system which may include replacement of gutters and downpipes to address water issues Steve Daniel On Target
50541SA542Naracoorte Sports Centre Traffic Plan $ 50,000 $ 50,000
Removal of inappropriate trees, repair kerbing, WSUD, new drainage to west, increase parking capacity and improve traffic flows Steve Paul On Target
50515BA170 Naracoorte Cemetery Upgrade $ 20,000 $ 20,000 Long term plan developed for cemetery. Upgrade roadways and drainage to prevent erosion. Steve Shane Paul On Target
50540SA494Memorial Parklands Entrance and Sealed Car Park $ 60,000 $ 60,000
Reseal entrance and car park park near kindergarten. Improve stormwater drainage at bottom of car park with the addition of a new sump. Replace post and Steve Shane David G On Target
50540SA391 Brim Reserve Boundary Fencing $ 8,000 $ 8,000 Rural type fencing to prevent unauthorised public access and illegal dumping Tom David G Completed
$ 528,000 $ 100,000 $ 528,000
NARACOORTE REGIONAL LIVESTOCK EXCHANGE (NRLE) $ 526,000 $ 225,000 $ 526,000 50860YA050 Loading Ramps $ 486,000 $ 225,000 $ 486,000 Installation of three new cattle loading ramps and lead up yards Steve Megan Richard Slipping
50860YA051 D Yards $ 40,000 $ 40,000 To concrete raceways in D Yards and provide lighting to improve safety of this section of the yards Steve Richard Richard Completed
$ 526,000 $ 225,000 $ 526,000
AERODROMES $ 5,000 $ - $ 5,000 50600AA051 Runway 02/20 Upgrade North end 300m south $ 5,000 $ 5,000 Design for rubble surface of grass runway Tom Tom On Target
Page 3
Naracoorte Lucindale Council 23/10/20143:33 PM Major Projects 2014‐15 Program
GL Code Project Name From To
2014-15Approved
Budget (excl. GST)
External Funding
Contribution
TOTALProject Cost(excl. GST) Actual Cost Project Description
Project Sponsor
Project Manager
Supervisor/
Team Leader
Proposed Start Date
Proposed completion
date Status $ 5,000 $ - $ 5,000
OTHER $ 392,500 $ 100,000 $ 392,500
20285378Undergrounding of Powerlines in Robertson St Rolland St McCrae St $ 150,000 $ 258,000 Stage 1 - Underground power lines from Rolland St to just past Jones St. Steve Daniel On Target
20003214Implementation of Asset Management Strategy $ 15,000 $ 15,000 Refer to Asset Management Strategy Steve Michael Slipping
20184393 Waste Management Strategy $ 7,500 $ 7,500
Preparation of a regional waste management strategy to determine the most effective way to collect, process and dispose of waste with the aim of making waste management more sustainable both environmentally and financially. Helen Steve On Target
50780WD001 Accessability Action Plan $ 160,000 $ 80,000 $ 160,000 As per DDA legislation.Implementation of working group priorities Steve Daniel On Target
20285205Long Vehicle Parking in Naracoorte $ 10,000 $ 10,000 Consult with Naracoorte B&T Helen Steve Pending
20027297 Review of Council Operations $ 20,000 $ 20,000
As per Council resolution, review the effectiveness and efficiency of Council operations. Seek external expertise to assist with review with the aim of increasing productivity. Helen Steve On Target
20027363 Naracoorte Trails Network $ 10,000 $ 20,000 $ 10,000 Establish a trail network and trail head for cycling and walking. Incoporates heritage trail. Carried forward from 12-13. $20k from open spaces grant. Helen Paul Slipping
20540SA393 Smith St Roundabout Upgrade $ 20,000 $ 20,000 Install base for christmas tree, artificial grass and planting boxes. Steve Shane On Target
$ 392,500 $ 100,000 $ 500,500
LANDSCAPING AND STREET TREES $ 52,000 $ - $ 52,000 20241341 Foster St Loveday St Pethick St $ 9,500 $ 9,500 Street tree planting Steve Shane Paul On Target20241341 Gordon St Pethick St Loveday St $ 10,000 $ 10,000 Street tree planting Steve Shane Paul On Target20241341 Pavy St Cedar Av Merino St $ 5,000 $ 5,000 Street tree planting Steve Shane Paul On Target20241341 Stewart Tce Roundabout $ 2,500 $ 2,500 Landscaping Steve Shane Paul On Target20241341 Pethick St Gordon St Jenkins Tce $ 5,000 $ 5,000 Street tree planting Steve Shane Paul On Target20241341 Loveday St Gordon St Jenkins Tce $ 10,000 $ 10,000 Street tree planting Steve Shane Paul On Target
20241341 Smith St Lagunaria Trees Goodchild Pl McCrae St $ 10,000 $ 10,000 Tree removal as per Council resolution. Steve Shane Paul On Target
$ 52,000 $ - $ 52,000
CARRY FORWARD FIGURES $ - $ - $ - Unsealed Road Reconstruction $ - $ - $ - 50760UG110 Globe Street $ 15,000 $ 15,000 Design only 2013-1550760UF270 Flinders Lane $ 10,000 $ 10,000 Design only 2013-1550760UB290 Boddingtons Road West $ 40,000 $ 40,000 Design only 2013-15
Sealed Road Reconstruction $ - $ - $ - 50720SG230 Graham Street $ 20,000 $ 20,000 Design only 2013-1550720SM540 Moyhall $ 15,000 $ 15,000 Design only 2013-1550720SM440 Mill Road $ 10,000 $ 10,000 Design only 2013-1550720SC220 Caves Road $ 20,000 $ 20,000 Design only 2013-1550720SF170 Fifth Street, Frances $ 15,400 $ 15,400 Design only 2013-1550720SS190 Second Street, Frances $ 5,800 $ 5,800 Design only 2013-15 (added to 2014-15 GL)
50720SB321 Bool Lagoon West Road (CF) $ 245,000 $ 245,000 Not to be transferred into current Bool Lagoon West Road GL due to SLRP Grant Reporting
$ - Stormwater Drainage $ - $ - $ - 50740DA007 Cameron Street $ 328,000 $ 328,000 add to existing GL - identified as freeling street50740DA003 Deviation Road $ 5,000 $ 5,000 Design only 2013-15
50740DA009Gordon Street and Alexander Drive $ 20,000 $ 20,000 Design only 2013-15
50740DA010 Musgrave Avenue $ 5,000 $ 5,000 Design only 2013-15$ -
Bridges and Major Culvers $ - $ - $ - 50620BC010 Cadgee Road Culverts $ 10,000 $ 10,000 Design only 2013-15
$ - Kerb and Watertable $ - $ - $ - 50640KP250 Pavy Drive $ 10,000 $ 10,000
Other $ - $ - $ - 50780WD001 Accessability Action Plan $ 10,000 $ 10,000 add to existing GL50540SA900 Avenue Range Water Point $ 20,000 $ 20,000 new GL
Page 4
NARACOORTE LUCINDALE COUNCIL
BANK RECONCILIATION STATEMENT
AS AT 20 OCTOBER 2014
BANK STATEMENT
Balance as at 18 October 2014 343,667.66
PLUS
Unpresented Deposits - Banking 13,314.80
LESS
Outstanding Cheques 410,852.25
BALANCE AS AT 20 October 2014 53,869.79-
ACCOUNT - "CASH AT BANK"
Balance as at 20 October 2014 55,505.66-
PLUS
Unprocessed Deposits 8,439.92
Returned Deposit/EFT 154.00
LESS
Direct Debit not Processed 6,958.05
Returned Cheque
BALANCE AS AT 20 October 2014 53,869.79-
PLUS
INVESTMENTS
General Investment - CWMS 80,534.28
General Investment - Open Space 24,762.00
General Investment - NRLE 175.44
General Investment - LGFA 2,326,504.27
Term Deposit - LGFA 4,000,000.00
BankSA - Term Deposit 1,053,159.48
LESS
LIABILITIES
Cash Draw Down No. 3
Cash Draw Down No. 6 - NRLE
CASH POSITION 7,431,265.68
-
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
1 2 3 4 5 6 7 8 9 10 11 12
NARACOORTE LUCINDALE COUNCIL - CASH FLOWS
11/12
12/13
13/14
14/15
NARACOORTE LUCINDALE COUNCIL CASH FLOW
AS AT 20 OCTOBER 2014
July August September October November December January February March April May June
Cash at Bank (Bank)
Opening Balance 437,500.98 562,889.88 1,009,424.74 160,044.39
Plus
Receipts 413,714.10 1,734,047.11 2,061,075.00 258,698.03
Transfers in 1,000,000.00 300,000.00 100,000.00 380,000.00
Interest 0.00 478.95 955.26 1,424.15
Less
Cheques Raised 13,440.39 152,316.25 125,102.89 39,063.31
Transfers Out 0.00 0.00 1,500,000.00
Direct Debits 1,272,367.12 1,434,999.20 1,382,932.62 811,935.10
Bank Charges 2,517.69 675.75 3,375.10 3,037.95
Closing Balance 562,889.88 1,009,424.74 160,044.39 -53,869.79
Cash Advance (LGFA)
Opening Balance 0.00 0.00 0.00 0.00
Plus
Drawdowns 0.00 0.00 0.00 0.00
Less
Payments 0.00 0.00 0.00 0.00
Closing Balance 0.00 0.00 0.00 0.00
Term Deposit - BankSA 1,043,009.88 1,043,010.88 1,046,466.67 1,046,467.67
Plus
Deposits 1.00 3,455.79 1.00 6,691.81
Less
Transfers Out 0.00 0.00 0.00 0.00
Closing Balance 1,043,010.88 1,046,466.67 1,046,467.67 1,053,159.48
General Invest (LGFA)
Opening Balance 5,946,100.87 4,991,006.60 4,691,006.60 6,811,975.99
Plus
Deposits 44,905.73 0.00 2,220,969.39 0.00
Less
Transfers Out 1,000,000.00 300,000.00 100,000.00 380,000.00
Closing Balance 4,991,006.60 4,691,006.60 6,811,975.99 6,431,975.99
Closing Balance 6,596,907.36 6,746,898.01 8,018,488.05 7,431,265.68
Loan Original Principal Owing Payments** Principal Owing Finalisation
Number Purpose Value 30/06/2014 2014-2015 30/09/2014 Date
Council Loans
16 Public Toilets 283,015 164,944.03 14,786.64 155,410.86 16/01/2021
17 Fleet Loan 800,000 524,736.64 43,225.01 499,615.04 15/03/2022
19 Road Works - McRae Ormerod 302,000 198,088.11 16,317.44 188,604.71 15/03/2022
20 Sewerage Works Clover Cres 243,350 159,618.29 13,148.51 151,976.61 15/03/2022
21 Sewerage Works Stewart Tce 247,276 162,193.55 13,360.63 154,428.60 15/03/2022
22 Concrete Bridge 860,000 564,802.89 564,802.89 16/04/2022
Commitment
2,735,641 1,774,383.51 100,838.23 1,714,838.71
Saleyards23 Saleyard - Truck Wash 543,615 357,017.93 357,017.93 16/04/202224 Saleyards Project - Stage 1 2,000,000 1,863,002.98 97,476.63 1,814,895.93 17/09/2027
Commitment
2,543,615 2,220,020.91 97,476.63 2,171,913.86
Self Servicing Loans
5 Ncte RSL Bowls Club 50,000 5,439.23 2,882.73 2,882.73 17/01/2015
Commitment
50,000 5,439.23 2,882.73 2,882.73
5,329,256 3,999,843.65 201,197.59 3,889,635.30
** Note: Payments (except in relation to Cash Advances) Include Interest. Payments are year to date.
* Total Loan Commitment as at 30/09/2014 3,889,635.30
* Total Loan Commitment as at 30/09/2014 (excluding NRLE & Self Servicing) 1,714,838.71
* Total NRLE Loan Commitment as at 30/09/2014 2,171,913.86
* Total Self Servicing Loan Commitment as at 30/09/2014 2,882.73
* 2014/2015 Budgeted General Rate Revenue 9,813,880
* 2014/2015 Budgeted Total Revenue 16,988,680
Actual Funding Policy
Limit
* Percentage of self servicing loan commitments to
general rate revenue as at 30/09/2014 0.03% 4.00% Community Loans
* Percentage of loans total to
general rate revenue as at 30/09/2014 39.63% 80.00% Total Loans
* Percentage of NRLE loans to
general rate revenue as at 30/09/2014 22.13% NRLE Total Loans
* Percentage of total loan servicing
commitment to general rates 2014/2015 (estimate) 5.65% 25.00% Actual Payments Forecast 14/15
* Percentage of total loan servicing (Principal & Interest)
commitment to general rates 2015/2016 (estimate) 5.59% 25.00% Actual Payments Forecast 15/16
(Principal & Interest)
NARACOORTE LUCINDALE COUNCIL
LOAN SUMMARY AS AT 30 SEPTEMBER 2014
CAPITAL
RENEWAL &
REPLACEMENT NEW CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES & LOAN
INCOME
RESERVE TRANSFER
CAPITAL CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES &
LOAN INCOME
RESERVE
TRANSFER
CAPITAL
STRATEGIC
-$ -$ -$ -$ -$ GENERAL OPERATIONS -$ -$ -$ -$
20,900$ -$ -$ -$ -$ ELECTED MEMBERS -$ -$ -$ -$
20,900$ -$ -$ -$ -$ -$ -$ -$ -$
OPERATIONS & TECHNICAL SERVICES
-$ -$ -$ -$ -$ OPERATIONS ADMINISTRATION -$ -$ -$ -$
-$ -$ -$ -$ -$ EMPLOYEE SAFETY -$ -$ -$ -$
-$ -$ -$ -$ -$ PROJECT MANAGEMENT -$ -$ -$ -$
-$ -$ -$ -$ -$ PURCHASING -$ -$ -$ -$
HEALTH
-$ -$ -$ -$ -$ LUCINDALE HEALTH CENTRE -$ -$ -$ -$
SOCIAL SECURITY & WELFARE
-$ -$ -$ -$ -$ SENIOR CITIZENS -$ -$ -$ -$
HOUSING & COMMUNITY AMENITIES
10,000$ 10,000$ -$ -$ -$ CEMETERIES 8,780$ -$ -$ -$
15,000$ 40,000$ -$ -$ -$ EFFLUENT DISPOSAL - CWMS 131$ 15,407$ -$ -$
-$ -$ 31,345$ 3,348-$ -$ EFFLUENT DISPOSAL - OTHER -$ -$ 5,456-$ -$
150,000$ 50,000$ 19,370$ -$ -$ PUBLIC CONVENIENCES 34,277$ 9,533$ -$ -$
10,000$ 5,000$ -$ -$ -$ SANITATION & GARBAGE -$ -$ -$ -$
STREET CLEANING -$ -$ -$ -$
STREET LIGHTING -$ -$ -$ -$
SPORT & RECREATION
105,000$ 70,000$ -$ -$ -$ PARKS & GARDENS 15,903$ -$ -$ -$
131,250$ 118,750$ -$ -$ -$ SWIMMING FACILITIES 3,973$ -$ -$ -$
77,500$ 12,500$ -$ -$ -$ SPORT & RECREATION 348$ -$ -$ -$
ARTS -$ -$ -$ -$
MUSEUMS -$ -$ -$ -$
TRANSPORT & COMMUNICATION
-$ -$ -$ -$ -$ QUARRIES -$ -$ -$ -$
-$ -$ -$ 475,000-$ -$ ROAD MAINTENANCE -$ -$ -$ -$
1,533,750$ 51,250$ -$ -$ -$ STORMWATER DRAINAGE 9,384$ -$ -$ -$
5,000$ -$ -$ -$ -$ AERODROMES -$ -$ -$ -$
6,084,250$ 961,250$ 74,204$ -$ -$ ROAD CONSTRUCTION 129,965$ 9,483$ -$ -$
ECONOMIC AFFAIRS
YEAR-TO-DATE 2014-2015 (CAPITAL)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
NARACOORTE LUCINDALE COUNCIL
Page 1
CAPITAL
RENEWAL &
REPLACEMENT NEW CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES & LOAN
INCOME
RESERVE TRANSFER
CAPITAL CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES &
LOAN INCOME
RESERVE
TRANSFER
CAPITAL
YEAR-TO-DATE 2014-2015 (CAPITAL)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
NARACOORTE LUCINDALE COUNCIL
PLANTATIONS -$ -$ -$ -$
LAND DEVELOPMENT -$ -$ -$ -$
CARAVAN PARKS -$ -$ -$ -$
OTHER PURPOSES
VANDALISM -$ -$ -$ -$
ASSET MANAGEMENT -$ -$ -$ -$
OTHER PROPERTIES & SERVICES -$ -$ -$ -$
OTHER GENERAL PURPOSES -$ -$ -$ -$
365,030$ -$ 51,110$ -$ -$ PLANT OPERATIONS -$ 43,225$ -$ -$
12,000$ -$ -$ -$ -$ DEPOT EXPENSES 4,020$ -$ -$ -$
-$ -$ TECHNICAL SERVICES -$ -$ -$ -$
-$ -$ PLANT CAPITAL -$ -$ -$ -$
8,498,780$ 1,318,750$ 176,029$ 478,348-$ -$ 206,781$ 77,648$ 5,456-$ -$
Page 2
CAPITAL
RENEWAL &
REPLACEMENT NEW CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES & LOAN
INCOME
RESERVE TRANSFER
CAPITAL CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES &
LOAN INCOME
RESERVE
TRANSFER
CAPITAL
YEAR-TO-DATE 2014-2015 (CAPITAL)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
NARACOORTE LUCINDALE COUNCIL
PLANNING AND DEVELOPMENT
-$ -$ -$ -$ -$ -$ -$ -$ -$
GOVERNANCE & COMMUNITY DEVELOPMENT
SPORT & RECREATION
41,400$ -$ -$ -$ -$ HALLS (Naracoorte) 3,230$ -$ -$ -$
2,000$ -$ -$ -$ -$ HALLS (Lucindale) -$ -$ -$ -$
32,500$ -$ -$ -$ -$ LIBRARIES 545$ -$ -$ -$
ECONOMIC AFFAIRS
1,200$ -$ -$ -$ -$ VISITOR INFORMATION CENTRE -$ -$ -$ -$
77,100$ -$ -$ -$ -$ 3,775$ -$ -$ -$
CORPORATE SERVICES
ADMINISTRATION
10,100$ -$ -$ -$ -$ COMPUTER OPERATIONS -$ -$ -$ -$
8,200$ 2,000$ -$ -$ -$ COUNCIL OFFICES - NARACOORTE -$ -$ -$ -$
HOUSING & COMMUNITY
-$ 3,500$ -$ -$ -$ HOUSES -$ -$ -$ -$
OTHER PURPOSES
-$ -$ 5,439$ 15,647-$ PUBLIC DEBT -$ 2,667$ 216-$ -$
156,000$ -$ -$ 41,000-$ -$ FLEET OPERATIONS -$ -$ -$ -$
174,300$ 5,500$ 5,439$ 56,647-$ -$ -$ 2,667$ 216-$ -$
8,771,080$ 1,324,250$ 181,468$ 534,995-$ -$ TOTALS 206,781$ 80,315$ 5,672-$ -$
Page 3
CAPITAL
RENEWAL &
REPLACEMENT NEW CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES & LOAN
INCOME
RESERVE TRANSFER
CAPITAL CAPITAL
LOAN
PRINCIPAL
PAYMENTS
CAPITAL GRANTS,
ASSET SALES &
LOAN INCOME
RESERVE
TRANSFER
CAPITAL
YEAR-TO-DATE 2014-2015 (CAPITAL)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
NARACOORTE LUCINDALE COUNCIL
42,000$ -$ 132,199$ -$ -$ NARACOORTE REGIONAL 218,852$ 48,107$ -$ -$
LIVESTOCK EXCHANGE
8,813,080$ 1,324,250$ 313,667$ 534,995-$ -$ TOTALS 425,633$ 128,422$ 5,672-$ -$
9,916,002$ 548,383$
Page 4
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
OPERATING INCOME STRATEGIC
-$ -$
OPERATIONS & TECHNICAL SERVICES
-$ 33,948 OPERATIONS ADMINISTRATION -$
-$ 4,448 PROJECT MANAGEMENT -$
HEALTH
-$ 5,000 LUCINDALE HEALTH CENTRE $ -
HOUSING & COMMUNITY
-$ 60,100 CEMETERIES -$ 7,938
-$ 85,374 EFFLUENT DISPOSAL - CWMS -$ 84,059
-$ 2,108 EFFLUENT DISPOSAL - OTHER $ -
-$ 1,369,188 SANITATION & GARBAGE -$ 987,161
SPORT & RECREATION
-$ 150 SWIMMING FACILITIES $ -
-$ 4,194 SPORT & RECREATION -$ 4,195
TRANSPORT & COMMUNICATION
$ - QUARRIES $ -
-$ 821,902 ROAD MAINTENANCE -$ 118,020
-$ 500 STORMWATER DRAINAGE $ -
-$ 26,395 AERODROMES -$ 23,875
$ - ROAD CONSTRUCTION $ -
OTHER PURPOSES
-$ 37,032 OTHER PROPERTIES & SERVICES -$ 35,340
$ - OTHER GENERAL PURPOSES -$ 20
-$ 50,000 PLANT OPERATIONS $ -
$ - DEPOT EXPENSES -$ 315,362
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
Page 1
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
2,500,339-$ 1,575,970-$
PLANNING AND DEVELOPMENT
HEALTH
-$ 5,000 HEALTH INSPECTION -$ 1,799
PUBLIC ORDER & SAFETY
-$ 42,890 DOG CONTROL -$ 39,778
-$ 9,000 FIRE PREVENTION -$ 5,200
$ - LIVESTOCK CONTROL $ -
-$ 100 GENERAL INSPECTION -$ 18
MINING & CONSTRUCTION
-$ 96,500 BUILDING AND PLANNING CONTROLS -$ 31,833
TRANSPORT & COMMUNICATION
-$ 3,500 PARKING CONTROLS -$ 3,971
156,990-$ 82,599-$
GOVERNANCE & COMMUNITY DEVELOPMENT
SOCIAL SECURITY & WELFARE
-$ 1,000 SENIOR CITIZENS -$ 491
HOUSING & COMMUNITY
-$ 5,950 COMMUNITY & MULTICULTURAL CENTRE -$ 675
-$ 59,733 VOLUNTEERS -$ 29,867
SPORT & RECREATION
-$ 35,700 HALLS (Naracoorte) -$ 5,409
-$ 2,000 HALLS (Lucindale) $ -
Page 2
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
-$ 56,000 LIBRARIES -$ 1,756
ECONOMIC AFFAIRS
-$ 33,850 VISITOR INFORMATION CENTRE -$ 8,421
194,233-$ 46,619-$
CORPORATE SERVICES
ADMINISTRATION
-$ 3,000 COMPUTER OPERATIONS -$
-$ 10,406 PAYROLL -$
-$ 124,790 GENERAL OPERATIONS 80,234-$
SOCIAL SECURITY & WELFARE
-$ 29,320 AGED HOMES 4,680-$
HOUSING & COMMUNITY
-$ 13,000 HOUSES 3,500-$
OTHER PURPOSES
-$ 156,726 PUBLIC DEBT 49,816-$
-$ 500 FLEET OPERATIONS 513-$
-$ 70,000 OTHER GENERAL PURPOSES 46,285-$
RATES & GRANTS
-$ 9,948,880 RATES 9,950,649-$
-$ 239,093 FINES, LEVIES & NRM 163,765-$
Page 3
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
-$ 2,210,481 GRANTS 561,927-$
12,806,196-$ 10,861,369-$
15,657,758-$ TOTAL OPERATING INCOME (excluding NRLE) 12,566,557-$
1,467,822-$ NARACOORTE REGIONAL 299,491-$
LIVESTOCK EXCHANGE
17,125,580-$ TOTAL OPERATING INCOME (including NRLE) 12,866,048-$
OPERATING EXPENDITURE
STRATEGIC
$ 350,008 GENERAL OPERATIONS $ 143,816
$ 245,279 ELECTED MEMBERS 37,098$
595,287$ 180,914$
OPERATIONS & TECHNICAL SERVICES
$ 287,962 OPERATIONS ADMINISTRATION 77,780$
$ 54,384 EMPLOYEE SAFETY 14,407$
$ 22,305 PROJECT MANAGEMENT 1,805$
$ 86,266 PURCHASING 22,805$
HEALTH
$ 12,157 LUCINDALE HEALTH CENTRE 935$
SOCIAL SECURITY & WELFARE
$ 9,130 SENIOR CITIZENS 1,730$
HOUSING & COMMUNITY
$ 125,188 CEMETERIES 27,454$
$ 71,386 EFFLUENT DISPOSAL - CWMS 4,447$
Page 4
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
$ 21,674 EFFLUENT DISPOSAL - OTHER 11,103$
$ 116,434 PUBLIC CONVENIENCES 22,876$
$ 1,787,376 SANITATION & GARBAGE 380,351$
$ 156,430 STREET CLEANING 29,279$
$ 108,000 STREET LIGHTING 18,758$
SPORT & RECREATION
$ 671,720 PARKS & GARDENS 120,799$
$ 256,250 SWIMMING FACILITIES 11,438$
$ 56,488 SPORT & RECREATION 13,168$
$ 65,368 ARTS 15,540$
$ 1,954 MUSEUMS 1,406$
TRANSPORT & COMMUNICATION
$ - QUARRIES 76,976$
$ 6,316,657 ROAD MAINTENANCE 417,110$
$ 221,335 STORMWATER DRAINAGE 14,114$
$ 114,030 AERODROMES 14,154$
$ - ROAD CONSTRUCTION -$
ECONOMIC AFFAIRS
$ 2,000 PLANTATIONS -$
$ - LAND DEVELOPMENT -$
$ 8,627 CARAVAN PARKS 656$
OTHER PURPOSES
$ 12,000 VANDALISM 2,132$
$ 203,705 ASSET MANAGEMENT 72,037$
$ 21,801 OTHER PROPERTIES & SERVICES 3,578$
$ - OTHER GENERAL PURPOSES 4,252$
$ 78,000 PLANT OPERATIONS 355,762$
$ - DEPOT EXPENSES 377,475$
Page 5
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
$ 234,680 TECHNICAL SERVICES 59,386$
$ - PLANT CAPITAL -$
11,123,307$ 2,173,713$
PLANNING AND DEVELOPMENT
ADMINISTRATION
$ 129,445 PLANNING 37,718$
HEALTH
$ 59,950 HEALTH INSPECTION 14,719$
SPORT & RECREATION
$ 20,000 HERITAGE 5,086$
PUBLIC ORDER & SAFETY
$ 58,371 DOG CONTROL 13,326$
$ 115,341 FIRE PREVENTION 38,225$
$ 6,624 LIVESTOCK CONTROL 1,110$
$ 47,476 GENERAL INSPECTION 15,520$
MINING & CONSTRUCTION
$ 210,148 BUILDING AND PLANNING CONTROLS 26,706$
TRANSPORT & COMMUNICATION
$ 7,750 PARKING CONTROLS 2,396$
655,105$ 154,806$
GOVERNANCE & COMMUNITY DEVELOPMENT
ADMINISTRATION
$ 163,588 GOVERNANCE 40,884$
$ 47,450 MEDIA, COMMUNICATION AND PUBLIC FUNCTIONS 5,921$
Page 6
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
SOCIAL SECURITY & WELFARE
$ 5,000 SENIOR CITIZENS 1,452$
HOUSING & COMMUNITY
$ 53,787 COMMUNITY & MULTICULTURAL CENTRE 818$
$ 59,733 VOLUNTEERS 8,534$
Page 7
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
SPORT & RECREATION
$ 232,502 HALLS (Naracoorte) 38,126$
$ 50,424 HALLS (Lucindale) 5,471$
$ 25,550 HALLS (Other) 309$
$ 380,989 LIBRARIES 82,506$
ECONOMIC AFFAIRS
$ 250,685 VISITOR INFORMATION CENTRE 51,152$
1,269,708$ 235,173$
CORPORATE SERVICES
ADMINISTRATION
$ 306,998 FINANCE 75,974$
$ 90,922 CREDITORS 19,945$
$ 17,786 DEBTORS 3,787$
$ 131,141 RATES & PROPERTY 53,120$
$ 207,009 COMPUTER OPERATIONS 85,200$
$ 125,546 PAYROLL 32,586$
$ 115,747 HUMAN RESOURCES 13,135$
$ 103,144 RECORDS MANAGEMENT 20,232$
$ 101,535 CUSTOMER SERVICE / RECEPTION 28,803$
$ 165,905 COUNCIL OFFICES - NARACOORTE 25,581$
$ 26,400 COUNCIL OFFICES - LUCINDALE 3,516$
$ 256,996 GENERAL OPERATIONS 137,767$
SOCIAL SECURITY & WELFARE
Page 8
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
$ 61,940 AGED HOMES 5,370$
HOUSING & COMMUNITY
$ 21,110 HOUSES 1,378$
$ 71,570 COMMUNITY SUPPORT 12,390$
Page 9
ADOPTED BUDGET
2014-2015
ACTUALS AS AT 30
SEPTEMBER 2014
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
OTHER PURPOSES
$ 327 PUBLIC DEBT 216$
-$ 27,500 FLEET OPERATIONS 1,574$
$ 70,000 OTHER GENERAL PURPOSES 25,697$
RATES & GRANTS
$ 135,000 RATES 118,792$
$ 188,593 FINES, LEVIES & NRM 46,606$
$ - GRANTS -$
2,170,169$ 711,669$
15,813,576$ TOTAL OPERATING EXPENDITURE (excluding NRLE) 3,456,275$
1,585,493$ NARACOORTE REGIONAL 319,624$
LIVESTOCK EXCHANGE
17,399,069$ TOTAL OPERATING EXPENDITURE (including NRLE) 3,775,899$
155,818$ TOTAL OPERATING (SURPLUS)/DEFICIT (excluding NRLE) 9,110,282-$
273,489$ TOTAL OPERATING (SURPLUS)/DEFICIT (including NRLE) 9,090,149-$
Page 10
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
STRATEGIC
500$ -$ 5,301$ 344,207$ GENERAL OPERATIONS -$ -$ -$ 143,816$
1,100$ -$ 6,824$ 237,355$ ELECTED MEMBERS -$ -$ -$ 37,098$
1,600$ -$ 12,125$ 581,562$ -$ -$ -$ 180,914$
OPERATIONS & TECHNICAL SERVICES
1,000$ 33,948-$ 6,781$ 280,181$ OPERATIONS ADMINISTRATION -$ -$ -$ 77,780$
550$ -$ -$ 53,834$ EMPLOYEE SAFETY -$ -$ -$ 14,407$
250$ 4,448-$ -$ 22,055$ PROJECT MANAGEMENT -$ -$ -$ 1,805$
500$ -$ -$ 85,766$ PURCHASING -$ -$ -$ 22,805$
HEALTH
1,046$ 5,000-$ 7,157$ 3,954$ LUCINDALE HEALTH CENTRE -$ -$ -$ 935$
SOCIAL SECURITY & WELFARE
-$ -$ 4,755$ 4,375$ SENIOR CITIZENS -$ -$ -$ 1,730$
HOUSING & COMMUNITY
-$ 60,100-$ 3,557$ 121,631$ CEMETERIES -$ 7,938-$ -$ 27,454$
1,943-$ 85,374-$ 41,012$ 32,317$ EFFLUENT DISPOSAL - CWMS -$ 84,059-$ -$ 4,447$
-$ 2,108-$ -$ 21,674$ EFFLUENT DISPOSAL - OTHER -$ -$ -$ 11,103$
-$ -$ 22,250$ 94,184$ PUBLIC CONVENIENCES -$ -$ -$ 22,876$
-$ 1,369,188-$ 31,582$ 1,755,794$ SANITATION & GARBAGE -$ 987,161-$ -$ 380,351$
-$ -$ -$ 156,430$ STREET CLEANING -$ -$ -$ 29,279$
-$ -$ -$ 108,000$ STREET LIGHTING -$ -$ -$ 18,758$
SPORT & RECREATION
-$ -$ 35,290$ 636,430$ PARKS & GARDENS -$ -$ -$ 120,799$
-$ 150-$ 48,294$ 207,956$ SWIMMING FACILITIES -$ -$ -$ 11,438$
-$ 4,194-$ 11,808$ 44,680$ SPORT & RECREATION -$ 4,195-$ -$ 13,168$
-$ -$ 39,749$ 25,619$ ARTS -$ -$ -$ 15,540$
-$ -$ -$ 1,954$ MUSEUMS -$ -$ -$ 1,406$
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
Page 1
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
TRANSPORT & COMMUNICATION
-$ -$ -$ -$ QUARRIES -$ -$ -$ 76,976$
-$ 821,902-$ 3,900,000$ 2,416,657$ ROAD MAINTENANCE -$ 118,020-$ -$ 417,110$
-$ 500-$ 140,000$ 81,335$ STORMWATER DRAINAGE -$ -$ -$ 14,114$
-$ 26,395-$ 47,856$ 66,174$ AERODROMES -$ 23,875-$ -$ 14,154$
ROAD CONSTRUCTION
ECONOMIC AFFAIRS
-$ -$ -$ 2,000$ PLANTATIONS -$ -$ -$ -$
LAND DEVELOPMENT -$ -$
-$ -$ 3,959$ 4,668$ CARAVAN PARKS -$ -$ -$ 656$
OTHER PURPOSES
-$ -$ -$ 12,000$ VANDALISM -$ -$ -$ 2,132$
500$ -$ -$ 203,205$ ASSET MANAGEMENT -$ -$ -$ 72,037$
-$ 37,032-$ 7,196$ 14,605$ OTHER PROPERTIES & SERVICES -$ 35,340-$ -$ 3,578$
-$ -$ -$ -$ OTHER GENERAL PURPOSES -$ 20-$ -$ 4,252$
28,000$ 50,000-$ 444,140$ 394,140-$ PLANT OPERATIONS -$ -$ -$ 355,762$
3,000$ -$ 57,841$ 60,841-$ DEPOT EXPENSES -$ 315,362-$ -$ 377,475$
1,000$ -$ 11,702$ 221,978$ TECHNICAL SERVICES -$ -$ -$ 59,386$
33,903$ 2,500,339-$ 4,864,929$ 6,224,475$ -$ 1,575,970-$ -$ 2,173,713$
PLANNING AND DEVELOPMENT
ADMINISTRATION
500$ -$ 5,772$ 123,173$ PLANNING -$ -$ -$ 37,718$
HEALTH
850$ 5,000-$ -$ 59,100$ HEALTH INSPECTION -$ 1,799-$ -$ 14,719$
SPORT & RECREATION
-$ -$ -$ 20,000$ HERITAGE -$ -$ -$ 5,086$
PUBLIC ORDER & SAFETY
250$ 42,890-$ 2,278$ 55,843$ DOG CONTROL -$ 39,778-$ -$ 13,326$
250$ 9,000-$ 2,278$ 112,813$ FIRE PREVENTION -$ 5,200-$ -$ 38,225$
-$ -$ 325$ 6,299$ LIVESTOCK CONTROL -$ -$ -$ 1,110$
-$ 100-$ 1,628$ 45,848$ GENERAL INSPECTION -$ 18-$ -$ 15,520$
Page 2
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
MINING & CONSTRUCTION
750$ 96,500-$ 4,134$ 205,264$ BUILDING AND PLANNING CONTROLS -$ 31,833-$ -$ 26,706$
TRANSPORT & COMMUNICATION
-$ 3,500-$ -$ 7,750$ PARKING CONTROLS -$ 3,971-$ -$ 2,396$
2,600$ 156,990-$ 16,415$ 636,090$ -$ 82,599-$ -$ 154,806$
GOVERNANCE & COMMUNITY DEVELOPMENT
ADMINISTRATION
1,000$ -$ -$ 162,588$ GOVERNANCE -$ -$ -$ 40,884$
-$ -$ -$ 47,450$ MEDIA, COMMUNICATION AND PUBLIC FUNCTIONS -$ -$ -$ 5,921$
SOCIAL SECURITY & WELFARE
-$ 1,000-$ -$ 5,000$ SENIOR CITIZENS -$ 491-$ -$ 1,452$
HOUSING & COMMUNITY
-$ 5,950-$ 664$ 53,123$ COMMUNITY & MULTICULTURAL CENTRE -$ 675-$ -$ 818$
2,000$ 59,733-$ -$ 57,733$ VOLUNTEERS -$ 29,867-$ -$ 8,534$
SPORT & RECREATION
500$ 35,700-$ 103,218$ 128,784$ HALLS (Naracoorte) -$ 5,409-$ -$ 38,126$
-$ 2,000-$ 30,459$ 19,965$ HALLS (Lucindale) -$ -$ -$ 5,471$
-$ -$ 24,235$ 1,315$ HALLS (Other) -$ -$ -$ 309$
1,000$ 56,000-$ 58,550$ 321,439$ LIBRARIES -$ 1,756-$ -$ 82,506$
ECONOMIC AFFAIRS
1,000$ 33,850-$ 1,323$ 248,362$ VISITOR INFORMATION CENTRE -$ 8,421-$ -$ 51,152$
5,500$ 194,233-$ 218,449$ 1,045,759$ -$ 46,619-$ -$ 235,173$
Page 3
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
CORPORATE SERVICES
ADMINISTRATION
1,250$ -$ 7,413$ 298,335$ FINANCE -$ -$ -$ 75,974$
500$ -$ 90,422$ CREDITORS -$ -$ -$ 19,945$
250$ -$ 17,536$ DEBTORS -$ -$ -$ 3,787$
500$ -$ 130,641$ RATES & PROPERTY -$ -$ -$ 53,120$
17,728-$ 3,000-$ 224,737$ COMPUTER OPERATIONS -$ -$ -$ 85,200$
1,000$ 10,406-$ 124,546$ PAYROLL -$ -$ -$ 32,586$
250$ -$ 115,497$ HUMAN RESOURCES -$ -$ -$ 13,135$
500$ -$ 1,440$ 101,204$ RECORDS MANAGEMENT -$ -$ -$ 20,232$
750$ -$ 100,785$ CUSTOMER SERVICE / RECEPTION -$ -$ -$ 28,803$
-$ -$ 51,094$ 114,811$ COUNCIL OFFICES - NARACOORTE -$ -$ -$ 25,581$
-$ -$ 9,898$ 16,502$ COUNCIL OFFICES - LUCINDALE -$ -$ -$ 3,516$
-$ 124,790-$ -$ 256,996$ GENERAL OPERATIONS -$ 80,234-$ -$ 137,767$
SOCIAL SECURITY & WELFARE
1,520$ 29,320-$ 32,620$ 27,800$ AGED HOMES -$ 4,680-$ -$ 5,370$
HOUSING & COMMUNITY
13,000-$ 9,965$ 11,145$ HOUSES -$ 3,500-$ -$ 1,378$
1,900$ -$ -$ 69,670$ COMMUNITY SUPPORT -$ -$ -$ 12,390$
OTHER PURPOSES -$
-$ 156,726-$ 327$ PUBLIC DEBT -$ 49,816-$ -$ 216$
33,472-$ 500-$ 2,972$ 3,000$ FLEET OPERATIONS -$ 513-$ -$ 1,574$
-$ 70,000-$ 70,000$ OTHER GENERAL PURPOSES -$ 46,285-$ -$ 25,697$
RATES & GRANTS
-$ 9,948,880-$ -$ 135,000$ RATES -$ 9,950,649-$ -$ 118,792$
-$ 239,093-$ -$ 188,593$ FINES, LEVIES & NRM -$ 163,765-$ -$ 46,606$
-$ 2,210,481-$ -$ -$ GRANTS -$ 561,927-$ -$ -$
42,780-$ 12,806,196-$ 115,402$ 2,097,547$ -$ 10,861,369-$ -$ 711,669$
Page 4
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
RESERVE
TRANSFERS &
INTERNAL
RECOVERIES
OPERATING
INCOME DEPREC
OPERATING
EXPEND
NARACOORTE LUCINDALE COUNCIL
YEAR-TO-DATE 2014-2015 (OPERATING)
AS AT 30 SEPTEMBER 2014ADOPTED BUDGET 2014-2015
823$ 15,657,758-$ 5,227,320$ 10,585,433$ TOTALS (excluding NRLE) -$ 12,566,557-$ -$ 3,456,275$
229,004$ 1,467,822-$ 291,870$ 1,064,619$ NARACOORTE REGIONAL -$ 299,491-$ -$ 319,624$
LIVESTOCK EXCHANGE
229,827$ 17,125,580-$ 5,519,190$ 11,650,052$ TOTALS (including NRLE) -$ 12,866,048-$ -$ 3,775,899$
43,662$ 9,090,149-$
Page 5
$ $ $ $ $
Actual Original Adjustment Estimate Actual
30/06/2013 Budget with 30/06/13 for 30/06/14 for 30/06/14
30/06/2013 Actuals$'000 $'000 $'000 $'000 $'000
INCOME
Rates 10,496 10,769 10,769 10,830 10,839
Statutory Charges 155 176 176 176 167
User Charges & Commercial Income 1,943 2,062 2,062 2,209 2,281
Operating Grants & Subsidies 3,315 3,137 3,137 2,070 2,114
Investment Income 182 137 137 216 233
Reimbursements 404 266 266 171 163
Other Revenues 351 90 90 397 365
TOTAL INCOME 16,846 16,636 16,636 16,069 16,162
EXPENSES
Employee Costs 5,304 5,777 5,777 5,365 5,344
Contracts, Materials & Other 4,701 5,069 5,069 4,435 4,675
Depreciation 5,365 5,509 5,509 5,509 5,447
Finance Charges 273 269 269 269 255
Loss on Revaluations
TOTAL EXPENSES 15,643 16,623 16,623 15,578 15,721
OPERATING SURPLUS/(DEFICIT) 1,203 14 14 491 441
Asseet disposal & fair value adjustments (332) 77-
Amounts received for new/upgraded assets 234 1,323 1,323 799 646
NET SURPLUS/(DEFICIT) 1,105 1,336 1,336 1,290 1,010
RESULTING FROM OPERATIONS
Other Comprehensive Income - revaluations
TOTAL COMPREHENSIVE INCOME 1,105 1,336 1,336 1,290 1,010
NARACOORTE LUCINDALE COUNCIL
BUDGET vs ACTUAL
FOR THE YEAR ENDED 30TH JUNE 2014
$ $ $ $ $
Actual Original Adjustment Estimate Actual
30/06/2013 Budget with 30/06/13 for 30/06/14 for 30/06/14
30/06/2014 Actuals
$'000 $'000 $'000 $'000 $'000
CURRENT ASSETS
Cash & cash equivalents 6,564 3,356 6,492 6,518 7,428
Trade & Other receivables 1,037 728 1,064 949 961
Inventories 858 885 884 879 1,034
Other Current Assets - - - - -
TOTAL CURRENT ASSETS 8,459 4,969 8,440 8,346 9,423
NON-CURRENT ASSETS
Financial Assets 77 60 56 53 53
Infrastructure, Property, Plant & Equipment 269,812 273,283 273,936 271,716 269,387
Other Non-current Assets (WIP as June 30) 709 21 - 892
TOTAL NON-CURRENT ASSETS 270,598 273,364 273,992 271,769 270,332
TOTAL ASSETS 279,057 278,332 282,432 280,115 279,755
CURRENT LIABILITIES
Bank Overdraft - - - - -
Trade & Other Payables 1,880 2,347 2,347 1,923 1,398
Borrowings 294 392 392 314 314
Provisions 703 879 658 601 1,051
TOTAL CURRENT LIABILITIES 2,877 3,618 3,397 2,838 2,763
NON-CURRENT LIABILITIES
Borrowings 4,000 5,447 5,447 3,686 3,686
Provisions 214 170 286 335 330
TOTAL NON-CURRENT LIABILITIES 4,214 5,617 5,733 4,021 4,016
TOTAL LIABILITIES 7,091 9,235 9,130 6,859 6,779
NET ASSETS 271,966 269,097 273,302 273,256 272,976
EQUITY
Accumulated Surplus 40,903 43,352 42,239 43,079 42,600
Asset Revaluation Reserves 228,939 225,746 231,063 228,939 228,939
Other Reserves 2,124 1,238 1,437
TOTAL EQUITY 271,966 269,097 273,302 273,256 272,976
NARACOORTE LUCINDALE COUNCIL
BUDGET vs ACTUAL
FOR THE YEAR ENDED 30TH JUNE 2014
$ $ $ $ $
Actual Original Adjustment Estimate Actual
30/06/2013 Budget with 30/06/13 for 30/06/14 for 30/06/14
30/06/2014 Actuals$'000 $'000 $'000 $'000 $'000
ACCUMULATED SURPLUS
Balance at beginning of period 39,285 42,070 40,903 40,903 40,903
Net Surplus/(Deficit) for Year 1,105 1,336 1,336 1,290 1,010
Other Comprehensive Income
Transfers between Reserves 513 (54) - 886 687 Bringing to Account - Community Loan
BALANCE AT END OF PERIOD 40,903 43,352 42,239 43,079 42,600
ASSET REVALUATION RESERVE
Balance at beginning of Period 228,939 225,054 228,939 228,939 228,939
Revaluation Increment - -
Remove Asset Sale
Transfer to Reserve
BALANCE AT END OF PERIOD 228,939 225,054 228,939 228,939 228,939
RESERVE
Balance at beginning of Period 2,637 637 2,124 2,124 2,124
Transfer between Reserves (513) 54 - (886) (687)
BALANCE AT END OF PERIOD 2,124 691 2,124 1,238 1,437
TOTAL EQUITY 271,966 269,097 273,302 273,256 272,976
NARACOORTE LUCINDALE COUNCIL
BUDGET vs ACTUAL
FOR THE YEAR ENDED 30TH JUNE 2014
$ $ $ $ $
Actual Original Adjustment Estimate Actual
30/06/2013 Budget with 30/06/13 31/12/2014 for 30/06/14
30/06/2013 Actuals$'000 $'000 $'000 $'000 $'000
CASH FLOWS FROM OPERATING ACTIVITIES
Receipts 18,262 17,632 17,632 16,087 17,810
Payments (11,956) (11,670) (11,670) (10,069) (12,042)
NET CASH PROVIDED BY OPERATING 6,306 5,962 5,962 6,018 5,768
ACTIVITIES
CASH FLOWS FROM FINANCING ACTIVITIES
Receipts
Proceeds from Borrowings 2,000 1,840 1,840 - -
Proceeds from Aged Care Facility Deposits - - - - -
Payments
Repayment of Borrowings (238) (312) (312) (294) (294)
Repayment of Aged Care Facility Deposits - - - - -
NET CASH USED IN FINANCING 1,762 1,528 1,528 (294) (294)
ACTIVITIES
CASH FLOWS FROM INVESTMENT ACTIVITIES
Receipts
Amounts Specifically for New or Upgraded Assets 234 1,323 1,323 799 646
Sale of Replaced Assets 90 21 21 92 119
Repayment of Loans by Community Groups 30 38 38 26 26
Payments
Expenditure on Renewal/Replacement of Assets (3,361) (7,466) (7,466) (5,015) (3,440)
Expenditure on New/Upgraded Assets (1,189) (1,478) (1,478) (1,783) (1,961)
Loans Made to Community Groups - - - - -
NET CASH USED IN INVESTMENT (4,196) (7,562) (7,562) (5,881) (4,610)
ACTIVITIES
Movement in Provisions 110
NET INCREASE/(DECREASE) IN 3,872 (72) (72) (47) 864
CASH HELD
CASH AT THE BEGINNING OF 2,692 3,428 6,564 6,564 6,564
REPORTING PERIOD
CASH AT END OF REPORTING 6,564 3,356 6,492 6,517 7,428
PERIOD
NARACOORTE LUCINDALE COUNCIL
BUDGET vs ACTUAL
FOR THE YEAR ENDED 30TH JUNE 2014
UNIFORM PRESENTATION OF FINANCES 2010-11 2011-12 2012-13 2013-14 2013-14
Actual Actual Actual Estimate Actual
$'000 $'000 $'000 $'000 $'000
OPERATING INCOME 15,035 16,889 16,846 16,069 16,162
less OPERATING EXPENSES 15,266 16,211 15,643 15,578 15,721
Equals: Operating Surplus/(Deficit) (a) (231) 678 1,203 491 441
Less: Net Outlays on Existing Assets
Capital Expenditure on Renewal / Replacement of Existing Assets
1,881 2,161 3,361 5,015 3,440
less Depreciation 4,975 5,046 5,365 5,509 5,447
less Proceeds from Sale of Replaced Assets 14 157 90 92 119
(3,108) (3,042) (2,094) (586) (2,126)
Less: Net Outlays on New Assets
Capital Expenditure on New / Upgraded Assets
(including investment property & real estate development) 1,755 6,605 1,189 1,783 1,961
less Amounts Received Specifically for New Assets 248 2,214 234 799 646
less Proceeds from Sale of Surplus Assets - - - - -
1,507 4,391 955 984 1,315
Equals: Net Lending / (Borrowing) for Financial Year (b) 1,370 (671) 2,342 93 1,252
(a)
(b)
Naracoorte Lucindale Council
Operating Surplus / (Deficit) measures the extent to which operating revenue is or is not sufficient to meet all of the costs of providing council services, which
include depreciation. Where an operating deficit exists, some costs being incurred in the current year are not being met by today’s ratepayers.
Net Lending / (Borrowing) equals Operating Surplus / (Deficit), less Net Outlays on existing and new assets. The Net Lending / (Borrowing) result is a measure of
the Council’s overall (i.e. Operating and Capital) budget on an accrual basis. The Net Lending /(Borrowing) result can be expected to fluctuate from year to year,
given the lumpy nature of some capital expenditure. Achieving a zero result on the Net Lending /(Borrowing) measure in any one year essentially means that the
Council has met all of its expenditure (both operating and capital) from the current year’s revenues.
KEY FINANCIAL INDICATORS 2010-11 2011-12 2012-13 2013-14 2013-14
Actual Actual Actual Estimate Actual
$'000 $'000 $'000 $'000 $'000
1
Operating Surplus/(Deficit) - $'000 (231) 586 1,203 491 441
2
Operating Surplus/(Deficit) Ratio - % (2) 6 12 5 4
3
Net Financial Liabilities - $'000 (44) 1,715 (587) (660) (1,663)
4
Net Financial Liabilities Ratio - % - 10 (4) (4) (10)
5
Interest Cover Ratio - % 0.0 1.3 1.5 1.5 0.0
6
Asset Sustainability Ratio - % 38 39 61 89 61
Interest Cover Ratio
Net Interest Expense as a percentage of Total Operating Revenue less NRM levy less investment income
Asset Sustainability Ratio
Indicates whether the Council is renewing or replacing existing non-financial assets at the same rate as its overall stock of assets is wearing out.
The ratio is calculated by measuring capital expenditure on renewal and replacement of assets relative to the level of depreciation.
Naracoorte Lucindale Council
Operating Surplus/(Deficit)
Measures the extent to which operating revenue is or is not sufficient to meet all of the costs of providing Council services, which include
depreciation.
Where an operating deficit exists, some costs bing incurred in the current year are not being me by today's ratepayer.
Operating Surplus/(Deficit) Ratio - %
Expresses the operating surplus(deficit) as a percentage of general and other rates (excluding NRM Levy).
Where an operating deficit exists, this percentage indicates the percentage increase needed in rate revenue to achieve a break-even operating
result. Equally a break even operating result could be targeted by decreasing operating expenses.
Net Financial Liabilities
Equals total liabilities less financial assets, where financial assets for this purpose include cash, investments, loans to community groups,
receivables and prepayments, but excludes equity held in Council businesses and land held for resale.
Net Financial Liabilities Ratio
Expresses net financial liabilities as a percentage of Total Operating Revenue (less NRM Levy).
This measure indicates the capacity of Council to meet its financial obligations from revenue streams. Where the ratio is falling, it indicates that
a Council's capacity to meet its financial obligations from revenue streams is strengthening. Conversely, where this ratio is increasing, it
indicates that a Council's capacity to meet its financial obligations is deteriorating.
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 1
NARACOORTE LUCINDALE COUNCIL
MINUTES FOR AUDIT COMMITTEE MEETING HELD ON 21 October 2014
TABLE OF CONTENTS
ITEM NO. SUBJECT PAGE NO.
ITEM 1 COMMITTEE MEMBER’S DECLARATION OF INTEREST (IF ANY)
Section 63(1) and (2) —Code of conduct for members, Local Government Act 1999, states that Council members must observe the code of conduct prescribed by the Governor. Point 3.13 of the Code of conduct for members states the following: “Council members must be committed to making decisions without bias and in the best interests of the whole community and comply with the relevant conflict of interest provisions of the Local Government Act 1999.” Also clauses 2.15 and 2.16 require breaches under Part 3 (which includes point 3.13) to be reported: 2.15 A Council member who is of the opinion that a breach of Part
3 of this Code (Misconduct) - has occurred, or is currently occurring, must report the breach to the Principal Member of the Council or Chief Executive Officer, the Ombudsman or the Office for Public Integrity.
2.16 A failure to report an alleged or suspected breach of Part 3 of this Code is in itself a breach under this Part (Behavioural Code).
Section 74, Local Government Act, 1999 states the following: 1) A member of a council who has an interest in a matter before
the council must disclose the interest to the council. 2) A member in making a disclosure under subsection (1) must
provide full and accurate details of the relevant interest. 3) A disclosure made under subsection (1) must be recorded in the
minutes of the council (including details of the relevant interest). 4) A member of a council who has an interest in a matter before
the council must not— a) propose or second a motion relating to the matter; or b) take part in discussion by the council relating to that matter;
or c) while such discussion is taking place, be in, or in the close
vicinity of, the room in which or other place at which that matter is being discussed; or
d) vote in relation to that matter
ITEM 2 PUBLIC FORUM
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 2
ITEM 3 CONFIRMATION OF COMMITTEE MINUTES
ITEM 4 MATTERS LAID ON THE TABLE FROM PREVIOUS MEETINGS
ITEM 5 REPORTS FOR DECISION
5.1
Review Council’s Annual Financial Statements (Work Programme: Item 1.1)
5.2 Internal Controls (Work Programme: Item 6.3)
5.3 Annual Report (Work Programme: Item 7.3)
5.4 Terms of Reference (Work Programme: Item 7.4)
5.5 Financial Comparison, Budget vs Actual for Year Ending 30 June 2014 (Work Programme: Item 8.1)
5.6 Monitoring Performance of the Naracoorte Regional Livestock Exchange (Work Programme: Item 8.3)
ITEM 6
6.1 Year to Date Financial Report (Work Programme: Item 8.6)
6.2 Training Opportunities (Work Programme: Item 8.6)
ITEM 7 PUBLICATIONS / DOCUMENTS / INFORMATION FROM OTHER BODIES
ITEM 8 MATTERS RAISED BY MEMBERS
8.1 Questions with notice
8.2 Motions with notice
8.3 Questions without notice
8.4 Motions without notice
ITEM 9 MATTERS THAT MAY BE CONSIDERED IN CONFIDENCE
ITEM 10 NEXT MEETING
ITEM 11 MEETING CLOSURE
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 3
NARACOORTE LUCINDALE COUNCIL
MINUTES FOR AUDIT COMMITTEE MEETING HELD ON 21 October 2014
COMMENCED:
Meeting commenced at 5.05 pm in Naracoorte Council Chamber, DeGaris Place, Naracoorte
PRESENT: Independent Member (Presiding Member): Independent Member: Elected Members:
Jim Ker Robyn Mencel Cr Armfield Cr Flynn Cr Ross
APOLOGIES:
ON LEAVE:
OFFICERS: Chief Executive Officer Director Corporate Services
Helen Macdonald (from 6.00 pm)
Fiona Stringer
MEDIA REPRESENTATIVES:
ITEM 1 ELECTED MEMBER’S DECLARATION OF INTEREST (IF ANY)
(Section 74, Local Government Act, 1999)
ITEM 2 PUBLIC FORUM
(The Public Forum is an opportunity for community members to ask questions, or to address the Committee on matters relating to the Committee’s activities.)
ITEM 3 CONFIRMATION OF COMMITTEE MINUTES
MOVED CR ROSS SECONDED MS MENCEL That the Minutes of the Audit Committee meeting held on 9 September 2014 are taken as read and confirmed as an accurate record of the proceedings of the meeting. CARRIED 12/15
ITEM 4 MATTERS LAID ON THE TABLE FROM PREVIOUS MEETINGS
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 4
ITEM
5
REPORTS FOR DECISION
5.1
Annual Financial Statements for Year Ending 30 June 2014 (Work Programme: Item 1.1)
Audit Committee Function Review Council’s Annual Financial Statements to ensure that they present fairly the state of affairs of the Council (refer Section 125 (4) Local Government Act) REPORT Members received and reviewed the Draft Annual Financial Statements at their meeting held on 9 September 2014, prior to presentation to Council. The Audited Financial Statements, Audit Opinion and Management Letter have now been received. Dean Newbery & Partners Audit Opinion advises that they have completed the statutory audit of the Naracoorte Lucindale Council which they have signed without reference to any qualification. As is their usual practice, Dean Newbery & Associates have also issued a management letter following the formal audit. The letter advises the following:-
• An unqualified audit opinion has been provided;
• All matters raised formally via letter during the year have been actioned, or are being actioned;
• All formal audit correspondence raised during the year has been appropriately and promptly responded to and there are no outstanding matters;
• That they would welcome audit involvement during 2014/15 in discussions with staff in relation to internal controls. As Members are aware the expanded audit scope for this Council is from 1 July 2015;
• Council has appropriately included all disclosure requirements of AASB 13 for 2013/14;
• Appropriate explanations have been provided for significant variances between 2012-13 and 2013-14;
• Note that Council’s land, buildings & other structures will be revalued during the current financial year.
The correspondence also expresses appreciation for the assistance provided by finance staff during the audit.
ATTACHMENTS TO REPORT:- - Audited Financial Statements for year ending 30 June 2014 (includes Audit
Opinion and Management Letter)
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 5
MOVED MR KER SECONDED CR ARMFIELD That the Audited Financial Statements for year ending 30 June 2014; Audit Opinion and Management Letter are received and noted. CARRIED 13/15
5.2
Internal Controls (Work Programme: Item 6.3)
REPORT The Committee’s Works Programme requires it to ensure that a thorough review is undertaken to identify locally appropriate internal control and risk management policies and procedures and to ensure that identified improvement opportunities can be appropriately addressed [note – this could be undertaken progressively in stages with the locally most important and highest risk areas tackled first]. As members are aware the initial assessment is based on where we are now and what controls we have in place, with the next step of the assessment including a risk assessment based on current controls, where the risk assessment results in an “extreme” or “high” risk, additional controls will be introduced. Following the introduction of new controls the residual risk will be assessed. Initial effort will be expended in improving risks around “extreme” and “high”, then we will move down the hierarchy to see where improvements can be introduced in relation to “medium” and “low” risks as appropriate. The Control Assessment Worksheets for the following will be provided to Members under separate cover prior to the meeting: Risk Category: Liabilities Business Process: Accounts Payable, Accrued Expenditure, Borrowings,
Employee Provisions & Taxation Members have previously been provided with a copy of the risk consequence and likelihood tables used, which are the same tables used by the Senior Management Team when assessing Council’s corporate risks. If Members require another copy please contact Council’s Director Corporate Services.
ATTACHMENTS TO REPORT:- - Control Assessment Worksheets (Liabilities)
FOR MEMBERS’ INFORMATION
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 6
5.3
Annual Report (Work Programme: Item 7.3)
REPORT The Committee’s Works Programme requires it to ensure that financial information included in publications for external audiences (eg. Annual Report) accurately reflects key accrual based financial information and where appropriate sector endorsed financial targets. Section 131 of the Local Government Act, 1999 states that Council must, on or before 30 November in each year, prepare and adopt an annual report relating to the operations of the Council for the financial year ending on the proceeding 30 June. The Act is very prescriptive in relation to the contents of the Annual Report. The Draft Annual Report, excluding attachments, is provided for Members’ information prior to presentation to Council at its meeting on 28 October 2014. Discussion from Meeting Include commentary to ratio’s, in particular the asset sustainability ratio Council’s attention is drawn to recommendation 8/15 from the Audit Committee’s September meeting It was noted that the Annual Report has become increasingly user friendly and easy to read
ATTACHMENTS TO REPORT:- - Draft Annual Report
MOVED CR ARMFIELD SECONDED CR ROSS That the Audit Committee notes that the Draft Annual Report for year ending 30 June 2014 has been prepared and that the financial information included in the report accurately reflects the financial performance of the Naracoorte Lucindale Council. CARRIED 14/15
5.4
Terms of Reference (Work Programme: Item 7.4)
REPORT The Audit Committee’s Terms of Reference require that:- “at least once a year, review its own performance, constitution and terms of reference to ensure it is operating at maximum effectiveness and recommend changes it considers necessary to the Council for approval” The Committee conducted its last review in November 2013. Does the Committee wish to recommend any amendments to its Terms of Reference?
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 7
The Committee’s Works Program is closely linked to its Terms of Reference and used to monitor performance. The Program is attached for Members’ information, discussion and refining as necessary. The Committee’s Presiding Member, Mr Jim Ker, also presents a report (verbal) to Council on an annual basis in relation to the Committee’s actions and progress over the previous year. This report is generally presented in December.
ATTACHMENTS TO REPORT:- - Audit Committee Terms of Reference - Works Program
MOVED CR ROSS SECONDED MS MENCEL That it is noted that the Audit Committee has reviewed its Terms of Reference and recommends that the membership of the Committee is adjusted from “three (3) elected members” to “two (2) elected members”. CARRIED 15/15
Helen Macdonald attended the meeting at 6.00 pm.
5.5
Financial Comparison, Budget vs Actual for Year Ending 30 June 2014 (Work Programme: Item 8.1)
REPORT The Local Government (Financial Management) Regulations 2011 require Council to consider a report showing the audited financial results of the Council compared with the estimated financial results set out in the budget by 31 December each year. The actual results are shown in comparison to Council’s original budget for 2013-14 and estimate for 30 June 2014 as presented to Council during budget deliberations for the current financial year. As Members can see the final operating figures are similar to the forecast operating surplus and substantially better than the original budget adopted by Council in June 2013. Council’s Asset Sustainability Target was down on forecast and was discussed at the Committee’s September meeting.
ATTACHMENTS TO REPORT:- - Budget vs Actual for Year Ending 30 June 2014
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 8
MOVED MR KER SECONDED CR FLYNN That the Audit Committee is concerned at the relative slow progress in finalisation of the asset management plans. This has impacted on various Council performance indicators and the clarity of the long term financial plan. It is recommended that Council allocate appropriate resources to enable the asset management plans to be finalised by 30 June 2015. CARRIED 16/15
MOVED CR ARMFIELD SECONDED MS MENCEL That the report comparing the audited financial results for the year ending June 30 2014 to the budgeted financial statement for the same period is received and noted. CARRIED 17/15
5.6
Monitor Performance of the Naracoorte Regional Livestock Exchange (Work Program: Item 8.3)
REPORT The Naracoorte Regional Livestock Exchange Board met on 30 September 2014. The minutes are attached for Members’ information. The Board’s Terms of Reference also require:
“An annual report in relation to the Naracoorte Regional Livestock Exchange Strategic Plan is to be presented to the Audit Committee prior to presentation to Council.” A draft annual report was endorsed by the NRLE Board on 30 September 2014. Apart from the end of year financial report, it includes a summary of highlights, comment on significant items of interest and key issues for the NRLE. Notes from meetings Noted some corrections to dates required and repetition of data to be removed within the draft annual report. It was noted that the YTD financial report requires further refinement. General discussion in relation to health & safety of agents with consecutive markets being held on Mondays and Tuesdays.
ATTACHMENTS TO REPORT:- - NRLE Minutes 30 September 2014 - NRLE YTD Income & Expenditure as at 12 September 2014 - NRLE Draft Annual Report
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 9
MOVED MR KER SECONDED MS MENCEL That the reports relating to the performance of the Naracoorte Regional Livestock Exchange are received and noted, subject to the minor changes noted above in relation to the draft annual report. CARRIED 18/15
ITEM
6
OFFICERS’ REPORTS FOR INFORMATION
6.1
Year to Date Financial Report (Work Program: Item 8.6)
REPORT Attached for Members’ information is the year to date income and expenditure reports for operating and capital to 30 September 2014. A report in relation to Major Projects, as presented to Council’s September meeting, is also provided for Members’ information. The Committee asked that consideration was given to presenting the YTD Operating Report in a format that more aligned with the layout of an “Income Statement”. This report is also attached for Members’ information. It needs to be noted that due to the upgrade of Council’s financial system staff are still exploring reporting options and the attached reports may require further refinement.
ATTACHMENTS TO REPORT:- - YTD Operating Report - YTD Operating Report (statement format) - YTD Capital Report - Major Projects Report
FOR MEMBERS’ INFORMATION
6.2
Training Opportunities (Work Program: Item 8.6)
REPORT The Local Government Association (LGA) is offering the course listed below before 31 December 2014. Further information in relation to the session can be accessed at the associated link:-
Naracoorte Lucindale Council, Audit Committee Audit Committee Audit Committee Audit Committee MinutesMinutesMinutesMinutes
21 October 2014 Page 10
Developing & Implementing a Sound Financial Strategy (Adelaide – 26 November 2014 & 16 March 2015) http://www.training.lga.sa.gov.au/index.cfm/course/?id=8653&type=w
FOR MEMBERS’ INFORMATION
ITEM 7 PUBLICATIONS / DOCUMENTS / INFORMATION FROM OTHER BODIES
The following publications and documents or other information received during the past month are available for interested Members to view on request or by following the link:- •
ITEM 8 MATTERS RAISED BY MEMBERS
8.1
QUESTIONS WITH NOTICE
8.2
MOTIONS WITH NOTICE
8.3
QUESTIONS WITHOUT NOTICE
8.4
MOTIONS WITHOUT NOTICE
8.5
OTHER ITEMS
Mr Ker expressed his appreciation to the elected members, Crs Armfield, Flynn and Ross, for their support and dedication to the Audit Committee over the last 4 years.
ITEM 9 MATTERS THAT MAY BE CONSIDERED IN CONFIDENCE
ITEM 10 DATE OF NEXT MEETING
NEXT MEETING:
Next Ordinary Meeting:
Tuesday, 2 December 2014 at 4pm
ITEM 11 MEETING CLOSURE
CLOSURE: Meeting closed at 6.37 pm
GL Code Project Name From To
2014-15
Approved
Budget
(excl. GST)
External
Funding
Contribution
TOTAL
Project Cost
(excl. GST) Project Description
Project
Sponsor
Project
Manager
Supervisor
/
Team
Leader
Proposed
Start Date
Proposed
completion
date Status
UNSEALED ROAD CONSTRUCTION $ 55,000 $ - $ 55,000
50760UF090 Fern St Peasron St Cameron St $ 15,000 $ 15,000
Design only 2014-15
Steve Tom50760UC530 Coles-Killanoolla Rd End of Seal Start of Seal $ 10,000 $ 10,000 Design only 2014-15 Steve Tom50760UL330 Lochaber North Rd Kilmorey Rd Boundary $ 10,000 $ 10,000 Design only 2014-15 Steve Tom
50760UR190 Reid Rd Realigment
Near
DiGiogio's $ 10,000 $ 10,000 Road safety audit 2014-15, consultation Steve Tom50760UJ070 Janz St Fifth Av sixth $ 10,000 $ 10,000 Design only 2014-15 Steve Tom
$ - $ 55,000 $ - $ 55,000
UNSEALED ROAD RESHEET $ 1,411,000 $ - $ 1,411,000
50700GM400 Messamurray Rd
2520m from
end of seal
5740m from
end of seal $ 255,000 $ 255,000 Resheet of 3.2km and culvert replacement. School bus route. Steve Harry
50700GC310 Charcutt Rd
Coles
Killanoola
Approx 6.5kms
West $ 512,257 $ 512,257
In poor condition and badly degraded due to blue gum harvest by ABP. Road is
being maintained by ABP contractors during harvest. Steve Harry50700GP450 Petchs Rd Chappels Boddingtons $ 70,000 $ 70,000 Grade and monitor un-made section - resheet southern end in 2014-15 Steve Harry
50700GD250 Diagonal Rd, Callendale Callendale Rd Border $ 274,500 $ 274,500
3km to be resheeted. 1km from VA lane heading north plus 2km south from
Jindalee. Possible patching in other sections. Steve Harry
50700GH700 Jessie Rd
Middle
Section $ 62,500 $ 62,500 Patching and stablisation with polycom Steve Harry
$ 1,174,257 $ - $ 1,174,257 available $ 236,743 Other projects to be considered once the above are completed
SEALED ROAD RECONSTRUCTION $ 3,259,000 $ 1,233,299 $ 3,259,000
50720SB550 Butler Tce, Naracoorte Gordon St Smith St $ 1,400,000 $ 565,737 $ 1,400,000
Major reconstruction incluidng; kerb replacement, shared use path, off street
parking, pavement suitable for b-doubles. Close off McCoy to b-doubles. Widen
intersections for improved turning movements. Upgrade stormwater drainage and
improve landscaping and lighting. Contract and dependant on funding
application Steve Harry Contract
50720SS330 Shepherds Rd, Kyby Jessie Rd Border $ 680,000 $ 352,562 $ 680,000
Stage 1 - Border to Jessie. Contracted to Gambier Earth Movers, carried
forward from 2013-14 . Steve Harry Contract Slipping
50720SB320 Bool Lagoon West Rd Maauope Rd Dual Lane Seal $ 635,000 $ 315,000 $ 635,000
Stage 1 - Bool Lagoon Rd to Moyhall Rd part constructed in 2013-14 Stage 2 -
Moyhall Rd to Existing 2 lane seal. Includes $245k carry forward from 2013-14
Construction by Council. Steve Harry Peter50720SG010 Gap Rd, Frances 4.9km east $ 10,000 $ 10,000 Design only Steve Tom
50720SO070 Old Caves Rd
Approx
1.2kms South
of Pistol Club new Caves Rd $ 25,000 $ 25,000 Design only Steve Tom
50720SE010 East Settlement Rd
910m North
of Sydney
Road $ 80,000 To be reviewed Steve Tom50720SS070 Schinckels Rd Cadgee Rd Menhennits Rd $ 15,000 $ 15,000 Design only Steve Tom
50720SS190 Second St, Frances Fourth St East Tce $ 204,000 $ 204,000
Consultation suggests Fourth St a higher priority, consider changing. Council
construction Steve Tom
50720SB230 Binnum-Benayeo Rd
440m east
Hynam
Frances Road Railway Line $ 50,000 $ 50,000 Short section requiring soil tests and design. Council construction50720SC110 Campbell St, Naracoorte Rolland St End $ 15,000 $ 15,000 Design only Steve Tom
50720SB310 Bool Lagoon Rd
Bool Lagoon
West Rd 3.6km east $ 15,000 $ 15,000 Design only 2014-15 Steve Tom
50720SR390 Robertson St, Naracoorte Rolland St Jones Street $ 265,000 $ 265,000
Part of PLEC project includes landscaping, kerb and water table, pavements.
Contract Steve Daniel
$ 3,049,000 $ 1,233,299 $ 3,394,000 Available $ - $ (135,000)
SEALED ROAD RESEALS $ 860,500 $ - $ 860,500 NEW Cadgee Road Playford Dr Burkes Rd $ 122,103 $ 122,103 Scrub Coat AC 7 Asphalt with 14mm Crumb Rubber Reseal Tom David G Contract On Target
50680RH670 Hynam Caves Road
Victoria Fossil
Road Langkoop Road $ 55,670 $ 55,670
10mm C170 reseal cracking under trees with some parts of the seal breaking away
on the cracks. Road still smooth and sound Tom David G Contract On Target
50680RL051 Langkoop Road
Yelloch
Bridge 100m East $ 19,580 $ 19,580
Bad cracking and some depressions on approach to bridge fom Eastern side. Needs
shape correction and sealing. Tom David G Contract On Target
50680RS810 Struan - Joanna Rd
Old Riddoch
Highway end of bitumen $ 30,663 $ 30,663
7mm C170 Reseal
Tom David G Contract On Target
Page 1
GL Code Project Name From To
2014-15
Approved
Budget
(excl. GST)
External
Funding
Contribution
TOTAL
Project Cost
(excl. GST) Project Description
Project
Sponsor
Project
Manager
Supervisor
/
Team
Leader
Proposed
Start Date
Proposed
completion
date Status
50680RC090 Cameron St Park Terrace Creek $ 12,212 $ 12,212 7mm S35E Reseal plus spoon drain replacement -see 50640KC090 Tom David G Contract On Target
50680RO170 Oliver Street Park Terrace Freeling St $ 6,145 $ 6,145 7mm S35E Reseal Tom David G Contract On Target
50680RE010 East Settlement
Wrattonbully
Rd End $ 44,545 $ 44,545 10mm C170. Combine with construction. Tom David G Contract On Target50680RB290 Boddingtons Rd Cadgee Rd Hazels Rd $ 124,538 $ 124,538 10mm Crumb Rubber Stage 1 - Cadgee Rd to Hazels Rd Stage Tom David G Contract On Target50680RB470 Brown Av Smith St End $ 3,596 $ 3,596 7mm S35E Tom David G Contract On Target
NEW Old Caves Road Pinkerton Rd
End of Primer
Seal $ 72,783 $ 72,783 7mm S35E Tom David G Contract On Target
NEW Stewart Terrace Gum Avenue Field Avenue $ 36,605 $ 36,605 7mm S35E Tom David G Contract On Target
NEW Roberston Street
Rolland
Street Jones Street $ 100,042 $ 100,042 7mm S35E Tom David G Contract On Target
50680RF090 Fern Street Oliver Street Cameron Street $ 2,371 $ 2,371 7mm S35E Tom David G Contract On Target50680RT170 Thomson Street Bates Lane End of Seal $ 10,060 $ 10,060 7mm S35E Tom David G Contract On Target
50680RL050 Langkoop Road Pinkerton Rd Bells Road $ 143,490 $ 143,490 7mm S35E Tom David G Contract On Target
Pavy Drive Review $ 784,403 $ - $ 784,403
Available $ - $ 76,097 INTERSECTIONS $ 265,000 $ - $ 265,000
55660IA003
Langkoop Rd and Concrete
Bridge Rd $ 10,000 $ 10,000
Road safety report 13-14. Design 14-15. Possible grant application to Road
Safety Fund Steve Tom
50660IA004 Pinkerton Rd and Old Caves Rd $ 20,000 $ 20,000 Design 14-15 Steve Tom
50660IA005 Robertson St and Jones St $ 200,000 $ 200,000
Needs to be incorporated with Robertson Street PLEC project and CBD drainage. If
projects don’t align, may need to be held over to 2015-16. Steve Daniel Contract On Target
50660IA006
Wrattonbully and East
Settlement Rd $ 5,000 $ 5,000 Road safety Audit Steve Tom Contract
NEW
Woolumbool and Fairview Rd
Intersection $ 26,040 $ 26,040 reseal of intersection Steve Daniel50660IA001 Cedar Av and Jenkins Tce $ 20,000 $ 20,000 Road safety audit followed by concept design for public consultation. Steve Tom
50660IA002
Church St and McRae St,
Naracoorte $ 10,000 $ 10,000
Design only 2014-15 Dangerous intersection. Subject to Church St design.
Steve Tom
$ 291,040 $ - $ 291,040 Available $ - $ (26,040)
KERB AND WATERTABLE $ 355,000 $ - $ 355,000 50640KL270 Livingston St, Naracoorte McCoy Butler $ 275,000 $ 275,000 Kerb and water table, pavement replacement, driveway crossovers 230m Tom Harry
50640KA230 Attiwill St
Opposite
Longridge
Retirement
Village $ 57,348 $ 57,348
establishment of carpark opposite Longridge.
Tom Shane
50640KC250 Cedar Av, Naracoorte Schinckel Rd End of Housing $ 10,000 $ 10,000 design 2014-15 Tom Shane50640KA231 Attiwil St Spoon Drain $ 10,000 $ 10,000 includes pram cross overs and minor pavement work Tom Shane50640KC090 Cameron St Spoon Drain $ 10,000 $ 10,000 Linked to reseal 50680RC090 Tom Shane
$ 362,348 $ - $ 362,348 Available $ - $ (7,348)
FOOTPATHS $ 420,000 $ - $ 420,000
NEW Centenary Avenue, Lucindale
Balharry
Memorial
Kindergarten Gum Avenue $ 20,000 $ 20,000 Requested change by LINC to proposed footpath project in Lucindale Steve Shane Benny
50780WS670 Stewart Tce Smith St MacDonnell St $ 140,000 $ 140,000
Repair path surface as identified in Local Area Bicycle Plan. Connection to school.
Includes replacing fencing, signage and new connection to Butler Terrace. Refer to
designs for 50720SB550. Steve Shane Benny
50780WP550 Pethick St Gordon Foster Street $ 20,000 $ 20,000
connecting exisiting footpaths. Seeking DPTI contribution for removal of rail
crossing Steve Shane Benny
50780WP070
Panorama Cres Walkway
Reserve Pine Grove Panorama Crs $ 10,000 $ 10,000 Easy care rubble pathway Steve Shane Benny
$ 190,000 $ - $ 190,000 available $ - $ 230,000 several projects under review with CBD drainage project
STORMWATER DRAINAGE $ 1,585,000 $ 714,000 $ 1,585,000 Page 2
GL Code Project Name From To
2014-15
Approved
Budget
(excl. GST)
External
Funding
Contribution
TOTAL
Project Cost
(excl. GST) Project Description
Project
Sponsor
Project
Manager
Supervisor
/
Team
Leader
Proposed
Start Date
Proposed
completion
date Status
50740DA002 Naracoorte CBD Arthur St
Naracoorte
Creek Via
Smith $ 1,500,000 $ 714,000 $ 1,500,000 Stage one 2014-15 from Creek to Jones and Robertson Street intersection Steve Daniel Contract
50740DA001 Adelaide Av and Gordon St
Cnr Gordon
St $ 45,000 $ 45,000 Designed 2013-14. Review required before proceeding50740DA005 Loveday St Detention Basin $ 40,000 $ 40,000 Cleaning and lifting of bore casing. Work with DEWNR
$ 1,585,000 $ 714,000 $ 1,585,000
BRIDGES AND MAJOR CULVERTS $ 260,000 $ 170,000 $ 430,000 50620BS070 Schinckels Rd Culvert $ 50,000 $ 50,000 Guard rail installation Contract Tom Harry Peter
50620BM540 Moyhall Rd Culverts
1200m north
of Limberts
Ln
100m South of
Limberts Ln $ 170,000 $ 170,000 $ 340,000
Submitting application to Aust Govt Bridges grants program, if unsuccessful only
one bridge culvert will be replaced Tom Harry50620BR050 Radfords Rd Culvert $ 20,000 $ 20,000 Guard rails in 2014-15. Contract Tom Harry
50620BM030 MacDonnell St Bridge - Railing $ 10,000 $ 10,000 Replacement of fence Steve Harry Benny
50620BS010 Sandstone Av Culvert Widening Across Drain $ 10,000 $ 10,000 Design Steve Tom
$ 260,000 $ 170,000 $ 430,000 note: seeking $170,000 grant funding $ (170,000)
SPORT AND RECREATION $ 349,603 $ 78,902 $ -
50880ZA021 Swim Lake Shade Sail $ 25,000 $ 25,000
New shade sail on SE end of grass to replace shade lost by removing large pine
tree. Includes removal of tree and establishment of turf. Steve Shane
50880ZA020
Swimming Lake Crime
Prevention $ 75,000 $ - $ 75,000
Replace security cameras and improve traffic management through carpark and
roadways. Budget ($20k) transferred to implementation of cycling network in
Naracoorte. Try again for grant in 2014-15 as security system needs replacing. Steve David G Contract
50541SA541
Lucindale Basketball Court,
Railway Tce $ 40,000 $ 40,000
Existing asphalt surface badly deteriorated. Edge repair and stabilsation required.
Spray seal or asphalt overlay TBD. Steve David G
50540SA491
Gwladys McTernan Park
Upgrade $ 5,000 $ 5,000 Working group to be established Steve Shane50540SA492 BMX Track - Market Square $ 5,000 $ 5,000 Remove BMX track. Steve Shane
50540SA493
Landscaping and Paths - Market
Square $ 15,000 $ 15,000
Open space would be retained in the centre of the Square, with a proposal to
construct a pergola linking a shelter at the BMX track and the Square’s centre. All
elements will be linked via a hardened path network. Sink bore and supply
irrigation. Steve Daniel
20241227
Vegetation Plan - Memorial
Parklands $ 5,000 $ 5,000
Replant native veg areas on eastern side and on sandy ridge near Memorial Av.
Prepare sites, weed removal, tree guards, etc. Trees for Life. Removal of trees at
end of life. Steve Shane Paul
50540SA495
BBQ and Shelter - Memorial
Parklands $ 35,000 $ 35,000
Install new shelter and BBQ facility adjacent carpark. Extend power from toilet
block. Concrete pad. Two BBQ's fully covered with seating and table. Steve Shane Paul
50540SA392
Creek Walk Upgrade at Duck
Pond $ 20,000 $ 20,000
Realign the creek walk around the duck pond to improve safety. Replace pontoon
with recycled plastic product for longer life. New crossing on Park Tce. Landscaping Steve Shane Benny On TargetNew Update Bike Strategy $ 25,000 $ 12,500 $ 25,000 Update 2007 Bike StrategyNew Cadgee Road bike lanes Higgs Road Burkes Road $ 99,603 $ 66,402 $ 99,603 widen Cadgee Road by 1.5m to create bike lanes
$ 349,603 $ 78,902 $ 349,603
WASTE TRANSFER STATIONS $ 35,000 $ - $ 35,000
50515BA311
Waste Transfer Station
Evaporation Pond $ 5,000 $ 5,000
Establish a larger evaporation pond for the waste water from the compactor shed
tor reduce the annual costs of pumping out the evaporation pit. Subject to EPA Tom David G On Target
50515BA312
Waste Transfer Station Fencing
Replacement $ 10,000 $ 10,000
Replacement 1.8m high secure fencing on Blackwell Rd. Includes gates. Existing
fence badly degraded. Tom David G Contract Completed
1408330 Closure of Naracoorte Landfill $ 20,000 $ - $ 20,000
Staged over two years. Includes construction of clay capping, topsoil layer,
revegetation and preparation of ongoing management plan. Tom Harry Peter On Target
$ 35,000 $ - $ 35,000
COMMUNITY WASTEWATER MANAGEMENT SCHEMES (STEDS) $ 55,000 $ - $ 55,000 50840CA001 Pump Replacement - Urbrae $ 15,000 $ 15,000 Pump replacements Tom Michael50840CA003 CWMS Lagoon Roadway $ 20,000 $ 20,000 Roadway to lagoons in Lucindale to be improved for all weather access. Tom Michael
50840CA002
CWMS Pump Station Telemetry
Upgrade $ 20,000 $ 20,000 project cancelled Tom Michael Withdrawn
$ 55,000 $ - $ 55,000
LAND AND BUILDINGS $ 528,000 $ 100,000 $ 528,000 Page 3
GL Code Project Name From To
2014-15
Approved
Budget
(excl. GST)
External
Funding
Contribution
TOTAL
Project Cost
(excl. GST) Project Description
Project
Sponsor
Project
Manager
Supervisor
/
Team
Leader
Proposed
Start Date
Proposed
completion
date Status
50515BA250
Market Square Public
Conveniences and Park Upgrade $ 200,000 $ 100,000 $ 200,000
The old toilets and current clubrooms of the SEDRA to be removed to make way for
the new toilets and carpark access. Steve Daniel
50880ZA001
Swim Lake Changerooms
Upgrade $ 150,000 $ 150,000
Upgrade internal fit out of change room facilities and provide hot water to showers.
Disabled access to changerooms. Paved sitting area outside kiosk for patrons to
enjoy food. Steve Daniel On Target
50515BA090
Naracoorte Town Hall Roof
Plumbing $ 40,000 $ 40,000
Design and implement new roof plumbing system which may include replacement
of gutters and downpipes to address water issues Steve Daniel On Target
50541SA542
Naracoorte Sports Centre Traffic
Plan $ 50,000 $ 50,000
Removal of inappropriate trees, repair kerbing, WSUD, new drainage to west,
increase parking capacity and improve traffic flows Steve Paul
New Naracoorte Cemetery Upgrade $ 20,000 $ 20,000
Long term plan developed for cemetery. Upgrade roadways and drainage to
prevent erosion. Steve Shane Paul On Target
50540SA494
Memorial Parklands Entrance
and Sealed Car Park $ 60,000 $ 60,000
Reseal entrance and car park park near kindergarten. Improve stormwater drainage
at bottom of car park with the addition of a new sump. Replace post and rail Steve Shane
50540SA391 Brim Reserve Boundary Fencing $ 8,000 $ 8,000 Rural type fencing to prevent unauthorised public access and illegal dumping Tom David G Completed
$ 528,000 $ 100,000 $ 528,000
NARACOORTE REGIONAL LIVESTOCK EXCHANGE (NRLE) $ 526,000 $ 225,000 $ 526,000 50860YA050 Loading Ramps $ 486,000 $ 225,000 $ 486,000 Installation of three new cattle loading ramps and lead up yards Steve Megan Slipping
9589431 D Yards $ 40,000 $ 40,000
To concrete raceways in D Yards and provide lighting to improve safety of this
section of the yards Steve Richard Completed
$ 526,000 $ 225,000 $ 526,000
AERODROMES $ 5,000 $ - $ 5,000 50600AA051 Runway 02/20 Upgrade North end 300m south $ 5,000 $ 5,000 Design for rubble surface of grass runway Tom Tom
$ 5,000 $ - $ 5,000
OTHER $ 392,500 $ 100,000 $ 392,500
20285378
Undergrounding of Powerlines in
Robertson St Rolland St McCrae St $ 150,000 $ 258,000 Stage 1 - Underground power lines from Rolland St to just past Jones St. Steve Daniel On Target
2473761
Implementation of Asset
Management Strategy $ 15,000 $ 15,000 Refer to Asset Management Strategy Steve Michael Slipping
20184393 Waste Management Strategy $ 7,500 $ 7,500
Preparation of a regional waste management strategy to determine the most
effective way to collect, process and dispose of waste with the aim of making waste
management more sustainable both environmentally and financially. Helen Steve On Target50780WD001 Accessability Action Plan $ 160,000 $ 80,000 $ 160,000 As per DDA legislation.Implementation of working group priorities Steve Daniel On Target
20285205
Long Vehicle Parking in
Naracoorte $ 10,000 $ 10,000 Consult with Naracoorte B&T Helen Steve
20027297 Review of Council Operations $ 20,000 $ 20,000
As per Council resolution, review the effectiveness and efficiency of Council
operations. Seek external expertise to assist with review with the aim of increasing
productivity. Helen Steve On Target
20027363 Naracoorte Trails Network $ 10,000 $ 20,000 $ 10,000
Establish a trail network and trail head for cycling and walking. Incoporates heritage
trail. Carried forward from 12-13. $20k from open spaces grant. Helen Paul Slipping
20540SA393 Smith St Roundabout Upgrade $ 20,000 $ 20,000 Install base for christmas tree, artificial grass and planting boxes. Steve Shane
$ 392,500 $ 100,000 $ 500,500
LANDSCAPING AND STREET TREES $ 52,500 $ - $ 52,500 20241341 Foster St Loveday St Pethick St $ 10,000 $ 10,000 Street tree planting Steve Shane Paul20241341 Gordon St Pethick St Loveday St $ 10,000 $ 10,000 Street tree planting Steve Shane Paul20241341 Pavy St Cedar Av Merino St $ 5,000 $ 5,000 Street tree planting Steve Shane Paul20241341 Stewart Tce Roundabout $ 2,500 $ 2,500 Landscaping Steve Shane Paul20241341 Pethick St Gordon St Jenkins Tce $ 5,000 $ 5,000 Street tree planting Steve Shane Paul20241341 Loveday St Gordon St Jenkins Tce $ 10,000 $ 10,000 Street tree planting Steve Shane Paul
20241341 Smith St Lagunaria Trees Goodchild Pl McCrae St $ 10,000 $ 10,000 Tree removal as per Council resolution. Steve Shane Paul
$ 52,500 $ - $ 52,500
Page 4
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from suppliers are
reconciled to the supplier accounts in the
accounts payable subledger regularly and
differences are investigated
Core Yes Supplier statements are
reconciled monthly.
Creditors Control Account is
reconciled monthly and
discrepancies are investigated.
FO DCS
2 Invoices received are authorised and
accompanied by appropriate supporting
documentation.
Core Yes Invoices are not processed
unless they have an authorised
purchase order attached, which
is notated with goods received.
If no PO is required (refer
Council's Internal Control
Policy/Procedure) an invoice is
signed by an authorised person
as approval to pay (ie. that
goods/service have been
received).
FO DCS
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Accounts Payable
Risk No. 1 – Accounts payable amounts and disbursements are either inaccurately recorded or not recorded at all.
Description: If invoices are not entered accurately (i.e. amounts posted to incorrect creditor), accounts payable will be misstated, as will the relevant expense,
inventory, or asset accounts. Also, erroneous payments may be made to vendors.
If amounts posted to accounts payable do not represent goods or services received (due to invalid delivery address on purchase order), unauthorised payments might
be made and the organisation might incur a financial loss. If accounts payable amounts are not recorded at all, accounts payable will be understated, as will the related
inventory, expense, or asset accounts. Also, supplier payments will not be made, which may damage supplier relationships.
Possible Controls
NARACOORTE LUCINDALE COUNCIL
3
Payments (Cheques and EFT’s) are
endorsed by authorised officers separate to the
preparer who ensures that they are paid to the
specified payee.
Core Yes Payments are signed by two
authorised signatories.
Cheque/EFT listing is signed by
authorised signatories as proof
of payment.
Accounts Payable & Payroll
Officers are not authorised
signatories.
FO DCS
4
Actual expenditures are compared to budget
regularly; management reviews and
approves significant variances.
Additional Yes Fortnightly reports are made
available to Directors and staff.
Budget vs Actual reports are
presented to Council and Audit
Committee Meetings.
FO DCS
5
Creditor’s supporting documentation is
checked by an authorised officer prior to payment
for accuracy and credit note verification.
Additional Yes Part of purchase order approval
process (refer point 2 above)FO DCS
6
Predetermined variances between Purchase
Orders and Invoices are suspended and released
only after verification by the responsible officer.
Additional Yes Variance of more than 10%
between the Purchase Order
and the Invoice is referred to
authorising officer for
verification.
FO DCS
7
Goods and/or services received are matched on-
line or manually with purchase order details
and/or invoices.
Additional Yes Part of purchase order approval
process (refer point 2 above)FO DCS
8Bank statements are reconciled to the general
ledger regularly.Additional Yes Reconciled weekly FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 20/10/2014 Rating Low Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Possible Controls Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from suppliers are
reconciled to the supplier accounts in the
accounts payable subledger regularly and
differences are investigated.
Core Yes Supplier statements are
reconciled monthly.
Creditors Control Account is
reconciled monthly and
discrepancies are investigated.
FO DCS
2
Access to the supplier master file is restricted to
authorised officers.Core Partial Office practice is that the CO,
CSO & DCS can make
adjustments to the supplier
master file
Security has been enhanced
within Council's finance system,
but requires fine tuning.
Security within LGE
(windows environment)
has allowed enhanced
security to limit users to
read only access
(requires fine tuning)
Ability to exclude the
CO from changing
banking details is not
possible at this stage
Explore option of
monthly report of
changes to master file
to be signed by
authorised officers
FO DCS
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Accounts Payable
Risk No. 2 – Credit notes and other adjustments to accounts payable are either inaccurately recorded or not recorded at all.
Description: If credit notes and other adjustments are not recorded accurately, accounts payable will be misstated, as will the related expense,
inventory, or asset accounts. If adjustments are not recorded at all, accounts payable, related assets, and expenses will be misstated. For
example, if goods returned are not reflected by debits in accounts payable, accounts payable will be overstated, as will the underlying expense, inventory, or asset
accounts.
NARACOORTE LUCINDALE COUNCIL
3
Separation of Accounts Payable and
Procurement duties.Core Yes Creditor officer is excluded from
the purchasing processFO DCS
4
Invoices, credit notes, and other adjustments
related to accounts payable are batched and
batch input data is balanced; out of balance
batches are corrected promptly.
Additional Partial Balancing does not occur at
this level. However, invoices
are balanced to cheque/EFT
listing prior to payment.
Alternative checks
including independent
review of aged trial
balance and monthly
balance to statements
are viewed as adequate
controls.
FO DCS
5
Goods returned notes are matched to credit
notes; differences are investigated promptly.Additional Yes Purchasing Officer monitors
goods returned to ensure
that a credit note is issued
(this is a rare occurrence)
FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 20/10/2014 Rating Low Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
All disbursements must be approved by an
authorised officer in accordance with relevant
policies and/or Delegations of Authority
Core Yes Invoices are not processed
unless they have an authorised
purchase order attached, which
is notated with goods received.
If no PO is required (refer
Council's Internal Control
Policy/Procedure) an invoice is
signed by an authorised person
as approval to pay (ie. that
goods/service have been
received).
FO DCS
2
Purchase Orders must be raised for the purchase
of goods and services in line with the Council's
Procurement policy or over a predetermined
amount with applicable
Core Partial Refer Point 1 On-going monitoring of
Council's internal
control in relation to this
item required.
FO DCS
3
Individuals who authorise payment of
suppliers are authorised officers who are
independent of the processing of invoices.
Core Yes Payments are signed by two
authorised signatories.
Cheque/EFT listing is signed by
authorised signatories as proof
of payment.
Accounts Payable & Payroll
Officers are not authorised
signatories.
FO DCS
Control Assessment Worksheet
Risk Category – Liabilites
Business Process – Accounts Payable
Risk No. 3 – Disbursements are not authorised properly.
Description: Unauthorised disbursements could result in Council making payments to suppliers for goods and services not actually received by the organisation or
Council may expend its funds on items of a private or personal nature when reimbursing employee expense claims.
Possible Controls
NARACOORTE LUCINDALE COUNCIL
4
Cheque usage to be reconciled to stock of
cheques on a regular basis and blank
cheque held securely.
Core Yes Sequential cheque numbering
Blank cheques stored in strong
room
FO DCS
5
Employee expense claims must be approved by
authorised officer and independently verified and
include relevant substantiation
Core Yes Employee reimbursements are
authorised by Directors
Directors authorised by CEO
FO DCS
6
Creditor’s supporting documentation is checked
by an authorised officer prior to payment for
accuracy and credit note verification.
Additional Yes Creditor Officer matches
invoices to approved purchase
order prior to payment.
FO DCS
7
All delegated officers should undertake regular
training for the raising of orders, posting of goods
and services received and the requirements of
the credit process.
Additional Partial Induction process includes
internal training in relation to
purchasing requirements
Introduce annual
(minimum) refresher of
processes
FO DCS
8
Records should be maintained of all payments
with supporting documentationAdditional Yes Payments, including support
documentation, is maintained
for a period of 7 years (refer
GDS20)
FO DCS
Prepared by: FO Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Possible Likelihood Unlikely
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Medium Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from suppliers are
reconciled to the supplier accounts in the
accounts payable subledger regularly and
differences are investigated.
Core Yes Supplier statements are
reconciled monthly.
Creditors Control Account is
reconciled monthly and
discrepancies are investigated.
FO DCS
2
Authorised officer to review aged payables
listing on a predetermined basis and
investigate where appropriate.
Core Yes Monthly review as per Council's
Internal Control Policy &
Procedure
FO DCS
3
Actual expenditures are compared to budget
regularly; management reviews and approves
significant variances.
Additional Yes Fortnightly reports are made
available to Directors and staff.
Budget vs Actual reports are
presented to Council and Audit
Committee Meetings.
FO DCS
4
System automatically generates a report (based
on the due date of the suppliers invoice) detailing
all supplier invoices due for payment at any one
time.
Additional Yes Report generated weekly to
determine invoices due for
payment in following 10 days
FO DCS
Control Assessment Worksheet
Description: If supplier invoices are not paid before their due date, then Council may miss out on any available discounts (i.e. early payment) or have supply restricted.
If supplier invoices are paid well before their due date (and prior to any early payment discount) greater demands will be placed on the Council’s cashflow.
Possible Controls
Risk Category – Liabilites
Business Process – Accounts Payable
Risk No. 4 – Accounts are not paid on a timely basis.
NARACOORTE LUCINDALE COUNCIL
Prepared by: FO Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Unlikely Likelihood Unlikely
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 20/10/2014 Rating Low Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Recorded changes to the supplier master file
are compared to authorised source
documents to ensure that they were input
accurately.
Core No Creditor Officer is responsible
for inputing changes. Changes
are not verified by a second
officer.
FO DCS
2
The accounts payable system and or
supplier master file prevents users from
making unauthorised adjustments to supplier
accounts.
Core Partial Office practice is that the CO,
CSO & DCS can make
adjustments to the supplier
master file
Security has been enhanced
within Council's finance system,
but requires fine tuning.
Security within LGE
(windows environment)
has allowed enhanced
security to limit users to
read only access
(requires fine tuning)
Ability to exclude the
CO from changing
banking details is not
possible at this stage
Explore option of
monthly report of
changes to master file
to be signed by
authorised officers
FO DCS
Possible Controls
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Accounts Payable
Risk No. 5 – Supplier master file data does not remain pertinent and/or unauthorised changes are made to the supplier master file
Description: To be considered “pertinent,” the master file must reflect current conditions. In this context, pertinence relates both to master file records and to individual
data fields within those records. For example, if supplier data is not up-to-date, payments could be made to the wrong bank account. Council needs to ensure that
adequate controls are in place to ensure that no unauthorised changes to the supplier master file are made to ensure that payments are not to be made for non-
Council purposes.
NARACOORTE LUCINDALE COUNCIL
3
Separation of accounts payable and procurement
duties.Additional Yes Creditor officer is excluded from
the purchasing processFO DCS
4
Suppliers that have not been used for a
significant period of time are reviewed and
marked for deletion by the application, if
appropriate.
Additional Yes Changeover to LGE (windows
environment) involved only
'bringing across' creditors that
had been used in previous 12
months
Payment records must be kept
for 7 years, therefore deletion
prior to this time period is not
applicable.
FO DCS
5
Supplier master file data is periodically reviewed
by management for accuracy and ongoing
pertinence.
Additional No Creditor Officer is responsible
for inputing changes. Changes
are not verified by a second
officer.
FO DCS
Prepared by: FO Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Possible Likelihood Unlikely
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Medium Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Accrued expenses reconciliations are
prepared on a regular basis and are
reviewed by an independent person.
Core Yes Expenses are accrued annually
and reviewed by external
auditor.
FO DCS
2 Actual accrued expenses are compared to budget
on a regular basis.Additional No Not required - low risk FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 28/02/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 9/09/2014 Rating Low Rating LowAccept Low Accept Low
Possible Controls
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Accrued Expenses
Risk No. 1 – Accrued Expenses are either inaccurately recorded or not recorded at all.
Description: If accrued expenses are either inaccurately recorded (i.e. inaccurate estimation of accrual) or unrecorded (i.e. no invoice received and normal review of
expenses did not identify need to accrue for expenses), the management reports and financial statements will be misstated.
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
A loan register is maintained containing a
copy of Council resolution approving the loan
and a schedule of the loan liability and the
loan repayment from the lender. This also
includes details of any Cash Advanced
Debenture.
Core Yes Loan register is maintained
Support documentation,
including application, Council
resolution and loan schedule is
filed with loan register in DCS
office
Cash Advance Register
maintained
FO DCS
2
Debt repayment transactions are scrutinised
and/or reconciled to ensure complete and
consistent recording in the appropriate
accounting period.
Core Yes Reconciled as a miminum
annually
Reconcilitation included in final
audit documentation
FO DCS
3
The loan register and loan approvals is
subject to management and/or internal audit
review.
Additional Yes Loan applications completed by
DCS and include compulsory
reference to Council resolution
FO DCS
4
All loan journals are independently
authorised
Additional Yes Journals are signed by preparer
and authorised as per Council's
Internal Control Policy &
Procedures "General Journals"
FO DCS
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Borrowings
Risk No. 1 – Borrowings are either inaccurately recorded or not recorded at all.
Description: Financing may be obtained but either inaccurately recorded or not recorded at all in the general ledger or loan register, resulting in misstatement of
liabilities.
Possible Controls
NARACOORTE LUCINDALE COUNCIL
5
Loan balances regularly in the General
Ledger compared to budget, loan register
and statements from financial institutions.
Management reviews and as appropriate
approves significant variances.
Additional Yes Loan balances reconciled to GL
in January and as part of EOY
process.
Audit Certificate from LGFA
balanced as part of EOY
process.
FO DCS
6
All new loan repayment schedules and
conditions are checked prior to accepting
each loan.
Additional Yes Schedule reviewed by DCS
prior to acceptance.
All borrowings are via the
LGFA.
FO DCS
7
Repayment of loans is independently
approved prior to payment with a review
conducted to ensure payments are in line the
loan register.
Additional Partial LGFA advise of loan payment.
Authorised officer approves
direct transfer.
Process to be
documented and
included in Council's
internal control policy &
procedure.
FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Low Rating Low
Accept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Possible Controls Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
All loans are approved by Council resolution with
copy of the Council resolution held in the loan
register. All funding approvals are minuted by
Council.
Core Yes Loan register is maintained
Support documentation,
including application, Council
resolution and loan schedule is
filed with loan register in DCS
office
Cash Advance Register
maintained
FO CSO
2
The loan register and loan approvals is subject to
management and/or internal audit reviewAdditional Yes Loan applications completed by
DCS and include compulsory
reference to Council resolution
FO CSO
3
Borrowings policy dictates when borrowings
appropriate and approval mechanisms including
requirement if any for alternative quotes.
Additional No All borrowings are via LGFA. Explore option of
introducing Policy.
FO CSO
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Low Rating Low
Accept Low Accept Low
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Borrowings
Risk No. 2 – Loans are taken out without appropriate approval.
Description: Should appropriate delegations/approvals not be obtained when taking out loans, the Council may be exposed to undue financial risk and/or not obtain
the most appropriate loan terms and conditions.
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from lenders are
reconciled to the loan register and General
Ledger and differences are acted upon by
personnel independent from the process of
recording the loan.
Core Yes Loan balances reconciled to GL
in January and as part of EOY
process.
Audit Certificate from LGFA
balanced as part of EOY
process.
FO CSO
2
The loan repayment and covenant schedule,
including dates and amounts to be paid is
established when loan is setup. Management
reviews this to ensure that all payments are made
and recorded accurately and timely. Repayment
details on Cash Advanced Debentures is
recorded and checked as known.
Additional Yes Repayment schedule
established at commencement
of loan.
Refer item 3 below for review
process.
FO CSO
3
Loan balances regularly in the General
Ledger compared to budget, loan register
and statements from financial institutions.
Management reviews and as appropriate
approves significant variances.
Additional Yes Loan balances reconciled to GL
in January and as part of EOY
process.
Audit Certificate from LGFA
balanced as part of EOY
process.
FO CSO
4
Loan repayments are made via automated
direct debit, approved appropriately and
monitored for on-going relevance.
Additional Yes LGFA advise of loan payment.
Authorised officer approves
direct transfer.
FO CSO
Control Assessment Worksheet
Risk Category – Liabilites
Business Process – Borrowings
Risk No. 3 – Loans are not repaid in accordance with the agreed terms.
Description: If repayments required by the loan agreement are missed, made late, or made in the wrong amount, the lender may have the right to impose penalties or
call the loan.
Possible Controls
NARACOORTE LUCINDALE COUNCIL
5
Compliance with debt covenants is monitored by
management and compared to current budget.Additional Yes Loan balances reconciled to GL
in January and as part of EOY
process.
Audit Certificate from LGFA
balanced as part of EOY
process.
FO CSO
6Council is informed on a timely basis of any
variance with the loans' terms and conditions that
have been prior approved.
Additional Yes Quarterly loan report presented
to Council, includes payments
made YTD and current balance.
FO CSO
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Rare Likelihood Rare
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Low Rating Low
Accept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from lenders are
reconciled to the loan register and General
Ledger and differences are acted upon by
personnel independent from the process of
recording the loan.
Core Yes Monthly reconciliations refer to
Internal Control Policy and
Procedure 7.1
2
All additions, deletions, and other changes to
the loan register and loan repayment data
are independently validated and compared to
the loan agreement to ensure that they were
input accurately. Identified errors are
corrected.
Core Yes Monthly reconciliations refer to
Internal Control Policy and
Procedure 7.1
3
The loan repayment and covenant schedule,
including dates and amounts to be paid is
established when loan is setup. Management
reviews this to ensure that all payments are made
and recorded accurately and timely. Repayment
details on Cash Advanced Debentures is
recorded and checked as known.
Additional Yes The LGFA provide us with an
audit certificate and/or
Debenture loan agreement that
is signed by the Mayor. A
statutory declaration is
attached to the loan file.
Possible Controls
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Borrowings
Risk No. 4 – Loan repayments are not recorded at all or are recorded inaccurately.
Description: If loan repayments are made but not recorded, liabilities, and cash will be overstated and interest expense may be inaccurately recorded. If loan
repayments are recorded inaccurately liabilities, cash, and interest expense may be misstated. Overpayments reduce cash available for other business activities, while
underpayments may give the lender cause (and the right) to call the loan (i.e., to demand that the loan be repaid immediately) or to impose penalties.
NARACOORTE LUCINDALE COUNCIL
4
Payments are entered into the system following
verification of direct debit from the Bank
Statement.
Additional YesWe receive a letter from the
LGFA with instructions for
payment of interest & principal
instructions. The form is
completed and authorized
independently of the preparer.
5
Council is informed on a timely basis of any
variance with the loans' terms and conditions that
have been prior approved.
Additional Yes Monthly financial reports
presented to council.
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Unlikely Likelihood
Reviewed: Director Corporate Services Consequence Minor Consequence
Date: 20/10/2014 Rating Low Rating
Accept Accept
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
All loans are approved by Council resolution
with copy of the Council resolution held in the
loan register. All funding approvals are
minuted by Council.
Core Yes All loans are approved by
resolution of council and
minuted but not attached to the
loan register. A Statutory
Declaration is attached to the
loan file
2
Management reviews cash position of
Council on an on-going basis, involving
comparison to budgets; significant variances
investigated by management.
Additional Yes Bank is reconciled weekly refer
to Internal control Policy and
Procedure Item 4.2
3Cashflow budgets prepared by suitably qualified
personnel on a regular basis.
Additional Yes Budget Reporting and
Amendment Policy C1.13.
4
Loan balances regularly compared to budget;
management reviews and as appropriate
approves significant variances.
Additional Yes Budget Reporting and
Amendment Policy C1.13.
5
Details of cash requirements, particularly with
capital works, are documented and discussed by
authorised officers. Investments and borrowings
are scheduled accordingly.
Additional Yes Long Term Financial Plan will
be used to measure this
alongside the Asset
Management Plan
6Council’s treasury management policies and
procedures are to be independently reviewed on
a periodic basis.
Additional No ACTION REQUIRED.
Description: Borrowings may take many forms (i.e. loans, cash advance debentures). If these borrowing are not managed effectively, Council may run out of cash,
thereby reducing the operational efficiency of the organisation.
Possible Controls
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Borrowings
Risk No. 5 – Lack of working capital to meet Council's finanical commitments.
NARACOORTE LUCINDALE COUNCIL
Prepared by: Inherent Risk Assessment Residual Risk Assessment
Likelihood Unlikely Likelihood
Date: Consequence Consequence
Rating Rating
Accept Accept
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Statements received from lenders are
reconciled to the loan register and
differences are acted upon by personnel
independent from the process of recording
the loan.
Core Yes Monthly reconciliations refer to
Internal Control Policy and
Procedure 7.1. Also an audit
certificate is received from
LGFA. As well as statements
and Confirmation letters from
other financial institutions.
2
Management undertake a review to identify
unrecorded loan liabilities at key reporting
dates.
Core Yes Budget Reporting and
Amendment Policy C1.13.
3
Interest on loans is predetermined and journals
are checked. Interest on Cash Advanced
Debentures is checked where applicable to
relevant source documents.
Additional Yes Monthly reconciliations refer to
Internal Control Policy and
Procedure 7.1
4
Loan balances regularly compared to budget;
management reviews and as appropriate
approves significant variances.
Additional Yes Budget Reporting and
Amendment Policy C1.13.
Prepared by: Inherent Risk Assessment Residual Risk Assessment
Likelihood Unlikely Likelihood
Date: Consequence Insignificant Consequence
Rating Low Rating
Accept Accept
Description: If interest is inaccurately calculated or recorded in the wrong period, the related expense will be misstated.
Possible Controls
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Borrowings
Risk No. 6 – Interest Expense is inaccurately calculated or recorded in the wrong period.
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Standard programmed formulas perform
employee provision calculations with
management to review to ensure consistency
with statutory reporting requirements.
Core Yes Calculated (computer) leave
balance compared to manual
record to ensure accuracy on
an annual basis (anniversary of
commencement).
FO DCS
2
Management must approve all staff requests
for leave and leave taken is recorded by
somebody independent from the approval.
Additional Yes Leave forms must be signed by
authorised officer as per
Council's Internal Control Policy
& Procedure.
Payroll Officer processes
electronically and records
manually.
FO DCS
3
Reconciliation of employee provisions
performed on a regular basis and these are
independently reviewed and signed off by
managers responsible for leave approvals.
Additional Partial Calculated (computer) leave
balance compared to manual
record to ensure accuracy on
an annual basis.
Leave reports provided to Exec
Team on a regular basis
(anniversary of
commencement).
Introduction of leave
policy and leave plans
for employees with
excessive leave by 30
June 2015.
FO DCS
Possible Controls
If accruals are not calculated correctly or not at all, staff entitlements will be inaccurate and the employee provisions will be misstated.
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Employee Provisions
Risk No. 1 – Employee provisions are either inaccurately recorded or not recorded at all.
Description: If employees take leave but this leave is recorded against the incorrect employee or not recorded at all, staff entitlements will be inaccurate and the
employee provisions will be misstated.
NARACOORTE LUCINDALE COUNCIL
4
Actual balances compared to budget on a
regular basis and significant variances are
investigated.
Additional Partial Balances are not compared to
budget, rather leave taken is
monitored to ensure adequate
leave taken (average 4 weeks
each year over a rolling 2 year
period).
Current practice is
deemed satisfactory.
FO DCS
5Leave balances are recorded on pay advices
for verification by staff.
Additional Yes Payslips include details of leave
balances.FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Possible Likelihood Possible
Reviewed: Director Corporate Services Consequence Insignficant Consequence Insignficant
Date: 20/10/2014 Rating Low Rating Low
Accept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Possible Controls Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
Access to payroll/provision master file is
restricted to authorised officers only.Core Yes Access is limited to three (3)
officers. Access controlled via
financial system security
settings.
FO DCS
2
Any changes to the payroll master files are
approved by management.Core Partial All changes are supported by
written documentation, but
currently not reviewed my
management.
Explore option of
monthly report of
changes to master file
to be signed by
authorised officers
FO DCS
3
Payroll master file data is periodically reviewed
for accuracy and pertinence.Additional Partial All changes are supported by
written documentation, but
currently not reviewed my
management.
Terminated employees are
removed from "current" pay
records.
Assess whether more
frequent review is
beneficial and reduces
risk of error.
FO DCS
4
Departmental managers periodically review
listings of current employees within their
departments and notify the personnel department
of necessary changes.
Additonal Partial Small organisation. All
changes are advised by HR
in writing.
FO DCS
5
Recorded changes to the payroll master files are
compared to authorised source documents to
ensure accurate input.
Additonal Partial All changes are supported by
written documentation, but
currently not reviewed my
management.
Explore option of
monthly report of
changes to master file
to be signed by
authorised officers
FO DCS
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Employee Provisions
Risk No. 2 – Payroll master file does not remain pertinent
Description: To be deemed pertinent, the master file must reflect current conditions. In this context, pertinence relates both to master file records and to individual
data fields within the records.
NARACOORTE LUCINDALE COUNCIL
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 30/04/2014 Likelihood Unlikely Likelihood Unlikely
Reviewed: Director Corporate Services Consequence Minor Consequence Minor
Date: 20/10/2014 Rating Low Rating Low
Accept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
All lodgement statements and returns are
reviewed and approved by authorised officer
prior to being released.
Core Partial CSO, FO or DCS prepares BAS
Statements.
DCS or FO prepares FBT
Return.
Preparing Officer signs.
Statements and
Returns are reviewed
by CSO, FO or DCS
(non-preparing Officer)
prior to lodgement.
Signature to indicate
review.
Implemented January
2014.
FO DCS
2
Accounting policies and procedures specify
correct treatment for preparing the fringe
benefit tax and goods & services taxation
returns within any given financial year.
Core Partial BAS process documented
(requires review)FBT process to be
documented
FO DCS
3
Relevant staff members are provided with
regular training in order to keep up to date
with all relevant changes in tax legislation
and reporting requirements or Council
obtains tax advice from external tax advisors.
Additional Yes Training Register
DCS & FO attended FBT
training in March 2014
FO DCS
4
Management periodically reviews a selection
of transactions to ensure appropriate tax
treatment.Additional Partial
BAS process includes monthly
review of random sample of
invoices and payments
Introduce review of "non-
gst" transactions to
ensure accuracy.
FO DCS
Control Assessment WorksheetRisk Category – Liabilites
Business Process –Taxation
Risk No. 1 –: Tax liabilities are either inaccurately recorded or not recorded at all.
Description: If staff are not provided with adequate training to keep them up to date with all relevant changes in taxation or if Council does not obtain tax advice from
external tax advisors, then there is the risk that either tax liabilities will be inaccurately recorded or not recorded at all. As a result, the taxation liabilities will be
misstated in both the management reports and the financial statements and Council may be liable for late lodgement penalty fees and avoidance fees.
Possible Controls
NARACOORTE LUCINDALE COUNCIL
5
All balance sheet reconciliations for tax
liabilities are performed regularly;
reconciliations are reviewed by an
independent person.
Additional Yes Reconciled on a monthly basis
as part of the BAS preparation
process
FO DCS
6
Council has a working relationship with an
external tax advisor and contacts them for
advice when required.
Additional Yes Advice can be sought from:-
* ATO
* Kevin Smith (ATC)
FO DCS
7
Ability for ATO to conduct Audit of
transactions (GST or FBT)
Additional Possibility of Audit encourages
correct record keeping and
payment of tax liabilities
FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 19/12/2013 Likelihood Possible Likelihood Possible
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 19/12/2013 Rating Low Rating LowAccept Low Accept Low
NARACOORTE LUCINDALE COUNCIL
Possible Controls Control Type Is this
control in
place?
Proof of Control and/or
Current Practice
Action Plan
(if control not
currently in place)
Assessing
Officer -
Title
Reviewing
Officer -
Title
1
All lodgement statements and returns are
reviewed and approved by authorised officer prior
to being released.
Core Partial CSO, FO or DCS prepares BAS
Statements.
DCS or FO prepares FBT
Return.
Preparing Officer signs.
Statements and
Returns are reviewed
by CSO, FO or DCS
(non-preparing Officer)
prior to lodgement.
Signature to indicate
review.
Implemented January
2014.
FO DCS
2
Tax Compliance Register (detailing lodgement
timetable) is maintained.Additional Yes Reminder system maintained in
outlook tasksFO DCS
3
Relevant staff members are provided with regular
training in order to keep up to date with all
relevant changes in tax legislation and reporting
requirements or Council obtains tax advice from
external tax advisors.
Additional Yes Training Register
DCS & FO attended FBT
training in March 2014
FO DCS
Description: It is important that Council recognises and records statutory reporting/lodgement deadlines in order to avoid any late lodgement penalty fees. One way of
doing this is by way of a Tax Compliance Register that is kept up to date.
Control Assessment WorksheetRisk Category – Liabilites
Business Process – Taxation
Risk No. 2 – Council does not meet statutory reporting / lodgement deadlines.
NARACOORTE LUCINDALE COUNCIL
4
Management reviews reporting and lodgement of
Statements/Returns on a regular basis to ensure
compliance with statutory deadlines.
Additional Partial CSO, FO or DCS prepares BAS
Statements.
DCS prepares FBT Return.
Preparing Officer signs.
Statements and
Returns are reviewed
by CSO, FO or DCS
(non-preparing Officer)
prior to lodgement.
Signature to indicate
review.
Implemented January
2014.
FO DCS
Prepared by: Finance Officer Inherent Risk Assessment Residual Risk Assessment
Date: 19/12/2013 Likelihood Unlikely Likelihood Unlikely
Reviewed: Director Corporate Services Consequence Insignificant Consequence Insignificant
Date: 19/12/2013 Rating Low Rating LowAccept Low Accept Low
Account Total for the period
Actual for 2015 Budget for 2015
00000NRLE Management Report NRLE10324760 NRLE Income10324800 Agistment Income -$91 -$91 $010324801 Canteen Lease -$1,729 -$1,729 -$7,59210324810 Fees -$163,627 -$163,627 -$1,172,55010324811 Fees - EU Cattle -$1,060 -$1,060 -$22,60010324814 Fees - Store Cattle -$6,652 -$6,652 -$56,00010324830 Interest Received -$236 -$236 $010324839 Licence Fees (Agents) $0 $0 -$9,08010324843 NLIS Tags -$4,367 -$4,367 -$18,00010324846 Other Income $0 $0 $010324848 Paddocking Charges $0 $0 -$17,00010324885 Stock Disposal Income -$1,824 -$1,824 -$20,00010324889 Truckwash Income -$24,225 -$24,225 -$145,000Total of NRLE Income -$203,811 -$203,811 -$1,467,82220324760 NRLE Expenditure20324005 Administration Recovery $0 $0 $55,75420324006 Advertising $0 $0 $4,00020324023 Audit Services $78 $78 $1,60020324033 Board Expenses $468 $468 $3,00020324054 Cleaning & Gardening $2,987 $2,987 $20,00020324074 Consumables $474 $474 $4,50020324083 Council Rates $27,071 $27,071 $26,00020324093 Depreciation [Building] $0 $0 $265,00020324096 Depreciation [P&E] $0 $0 $26,87020324111 Electricity $0 $0 $70,00020324115 EPA Monitoring $887 $887 $8,00020324122 F&E Maintenance $0 $0 $1,50020324123 FBT Liability $0 $0 $10,00020324149 I/Protect Insurance $6,415 $6,415 $6,64520324158 Insurance $25,330 $25,330 $24,09020324160 Interest - Cash Advance $0 $0 $10,00020324161 Interest - Loan Repayment $0 $0 $121,68420324162 Internal Loan $0 $0 $17,28020324164 IT Consumables $0 $0 $5,00020324167 IT Recovery $0 $0 $3,000
Page 1 of 3
Management Report – NRLE StatementNaracoorte Lucindale Council
NLC\corbinc
12/09/2014 12:06 PM
Financial Year: 2015. Period From: Total To Total
Account Total for the period
Actual for 2015 Budget for 2015
20324171 L&B Maintenance $6,077 $6,077 $45,00020324174 L&B Maintenance - Compost Pit $1,644 $1,644 $11,50020324175 L&B Maintenance - Effluent Dams $1,600 $1,600 $15,00020324176 L&B Maintenance - Truckwash $1,747 $1,747 $20,00020324177 L&B Maintenance - Water Reuse Plant $1,934 $1,934 $10,00020324178 L&B Maintenance - Weighbridge $2,087 $2,087 $7,00020324179 L&B Maintenance - Yards $24,501 $24,501 $135,00020324187 Legal Fees $0 $0 $5,00020324192 Licences [EPA & Safework] $0 $0 $8,00020324207 LSL Liability Inc $0 $0 $6,29020324242 Other Expense $0 $0 $1,00020324244 P&E Maintenance $2,457 $2,457 $13,00020324249 Paddocking Costs $0 $0 $1,00020324268 Printing & Stationery $176 $176 $2,50020324270 Project Management $0 $0 $19,27520324272 Protective Clothing $192 $192 $5,00020324288 Refuse Collection $460 $460 $4,50020324306 Salary $17,170 $17,170 $115,00020324307 Sale Day Support $13,493 $13,493 $45,00020324308 Scanning Charges $951 $951 $23,00020324324 Soft Flooring $15,174 $15,174 $33,00020324344 Subscriptions $2,098 $2,098 $9,50020324345 Superannuation $9,186 $9,186 $41,14320324352 Telephone $768 $768 $6,50020324364 Training $2,179 $2,179 $10,00020324376 Truckwash (Avdata) $2,448 $2,448 $13,50020324381 Vehicle $377 $377 $9,50020324386 W/Comp Insurance $21,617 $21,617 $22,51820324395 Water Licence $0 $0 $12020324408 Yard Washing $8,066 $8,066 $52,000Total of NRLE Expenditure $200,111 $200,111 $1,373,76925324765 Grant Income - NLRE (New & Upgraded) $0 $0 $030394Res12 Reserve - NRLE $0 $0 $211,72450860YA000 Additions50860YA001 F&E $0 $0 $050860YA005 IT $0 $0 $2,000
Page 2 of 3
Management Report – NRLE StatementNaracoorte Lucindale Council
NLC\corbinc
12/09/2014 12:06 PM
Financial Year: 2015. Period From: Total To Total
Account Total for the period
Actual for 2015 Budget for 2015
50860YA010 Fleet $0 $0 $050860YA015 Minor Plant $0 $0 $5,00050860YA020 Plant & Machinery $31,600 $31,600 $35,00050860YA030 Buildings $6,836 $6,836 $050860YA050 Loading Ramps $146,409 $146,409 $0Total of Additions $184,845 $184,845 $42,0008094000508 Principal Payments (NRLE) $0 $0 $08094000509 Principal Payments (NRLE - Fixed) $0 $0 $34,7108094000510 Principal Payments (NRLE - Floating) $0 $0 $97,489Total of Management Report NRLE $181,145 $181,145 $291,870
Page 3 of 3
Management Report – NRLE StatementNaracoorte Lucindale Council
NLC\corbinc
12/09/2014 12:06 PM
Financial Year: 2015. Period From: Total To Total
Version3 Page1
NARACOORTE LUCINDALE COUNCIL
COMMITTEE TERMS OF REFERENCE ‐ AUDIT COMMITTEE
The AUDIT COMMITTEE is established under the provisions of Section 41 of the Local Government Act, 1999 by resolution of Council at meeting held on 27th March 2007 (resolution 408/07), having immediate effect. Council’s Audit Committee held its first meeting on the 27th November 2007.
DELEGATED PURPOSE AND AUTHORITY
FINANCIAL REPORTING
The Committee shall monitor the integrity of the financial statements of the Council, including its annual report, reviewing significant financial reporting issues and judgements which they contain;
The Committee shall review and challenge where necessary:
the consistency of, and/or any changes to, accounting policies;
the methods used to account for significant or unusual transactions where different approaches are possible;
whether the Council has followed appropriate accounting standards and made appropriate estimates and judgements, taking into account the views of the external auditor;
the clarity of disclosure in the Council’s financial reports and the context in which statements are made; and
all material information presented with the financial statements, such as the operating and financial review and the corporate governance statement (insofar as it relates to the audit and risk management).
INTERNAL CONTROLS AND RISK MANAGEMENT SYSTEMS
The Committee shall:
keep under review the effectiveness of the Council’s internal controls and risk management systems; and
review and recommend the approval, where appropriate, of statements to be included in the annual report concerning internal controls and risk management.
[Note that it is important that the Audit Committee understands the business of the Council to appreciate the risks it manages on a daily basis, and to ensure that there are appropriate management plans to manage and mitigate this business risk. This will include insurance matters, financial reporting, legal and regulatory compliance, business continuity, and statutory compliance. This can be facilitated by discussions with the internal and external auditors and by presentations by management on how business risks are identified and managed.]
WHISTLE BLOWING
The Committee shall review the Council’s arrangements for its employees to raise concerns, in confidence, about possible wrongdoing in financial reporting or other matters. The
Version3 Page2
Committee shall ensure these arrangements allow independent investigation of such matters and appropriate follow‐up action.
INTERNAL AUDIT (WHERE COUNCIL HAS A SEPARATE INTERNAL AUDIT FUNCTION)
The Committee shall:
monitor and review the effectiveness of the Council’s internal audit function in the context of the Council’s overall risk management system;
consider and make recommendation on the program of the internal audit function and the adequacy of its resources and access to information to enable it to perform its function effectively and in accordance with the relevant professional standards.
[Note that this may include the review of the areas that have been identified for review and the frequency of review. The Committee should also monitor whether the function of internal audit has adequate standing and is free from management or other restrictions. Whilst internal audit focuses on a Council’s systems and procedures, it is important that audit retains its independence and is not subject to any influence from management or Council that impedes its ability to report objectively.]
review all reports on the Council’s operations from the internal auditors;
[Note that the reports to the Audit Committee need not be the detailed reports that are presented to management for their review. Ordinarily a high level review report is all that is required detailing the work undertaken, the findings and management response.]
review and monitor management’s responsiveness to the findings and recommendations of the internal auditor; and
where appropriate, meet the “head” of internal audit (internal or outsourced) at least once a year, without management being present, to discuss any issues arising from the internal audits carried out. In addition, the head of internal audit shall be given the right of direct access to the Principal Member of the Council and to the Presiding Member of the Committee.
EXTERNAL AUDIT
The Committee shall:
develop and implement a policy on the supply of non‐audit services by the external auditor, taking into account any relevant ethical guidance on the matter;
consider and make recommendations to the Council, in relation to the appointment, re‐appointment and removal of the Council’s external auditor. The Committee shall oversee the selection process for new auditors and if an auditor resigns the Committee shall investigate the issues leading to this and decide whether any action is required;
oversee Council’s relationship with the external auditor including, but not limited to:
recommending the approval of the external auditor’s remuneration, whether fees for audit or non‐audit services, and recommending whether the level of fees is appropriate to enable an adequate audit to be conducted;
recommending the approval of the external auditor’s terms of engagement, including any engagement letter issued at the commencement of each audit and the scope of the audit;
Version3 Page3
assessing the external auditor’s independence and objectivity taking into account relevant professional and regulatory requirements and the extent of Council’s relationship with the auditor, including the provision of any non‐audit services;
satisfying itself that there are no relationships (such as family, employment, investment, financial or business) between the external auditor and the Council (other than in the ordinary course of business);
monitoring the external auditor’s compliance with legislative requirements on the rotation of audit partners; and
assessing the external auditor’s qualifications, expertise and resources and the effectiveness of the audit process;
meet as needed with the external auditor. The Committee shall meet the external auditor at least once a year, without management being present; to discuss the external auditor’s report and any issues arising from the audit;
review and make recommendations on the annual audit plan, and in particular it’s consistency with the scope of the external audit engagement;
review the findings of the audit with the external auditor. This shall include, but not be limited to, the following;
a discussion of any major issues which arose during the external audit;
any accounting and audit judgements; and
levels of errors identified during the external audit.
The Committee shall also review the effectiveness of the external audit.
review any representation letter(s) requested by the external auditor before they are signed by management;
[Note that these representation letters are a standard practice of any audit and provide the auditor confirmation from management, (in particular the Chief Financial Officer) that, amongst other matters, accounting standards have been consistently applied, that all matters that need to be disclosed have been so disclosed and that the valuation of assets has been consistently applied.];
review the management letter and management’s response to the external auditor’s findings and recommendations.
MEMBERS
Members of the Committee are appointed by the Council. The Committee shall consist of a maximum of five (5) members;
three (3) Elected Members; and
at least one independent member (as provided in s.126(2) of the Act)
Independent member(s) of the committee shall have recent and relevant financial, risk management, internal audit, governance, etc. experience.
Version3 Page4
Only members of the Committee are entitled to vote in Committee meetings. Unless otherwise required by the Act not to vote, each member must vote on every matter that is before the Committee for decision.
Other individuals such as the Chief Executive Officer, Director of Corporate Services and if applicable any other officer whose attendance is agreeable to the Committee may attend any meeting as observers or be responsible for preparing papers for the Committee.
In accordance with the principles of open, transparent and informed decision making, Committee meetings will be conducted in a place open to the public. The agenda and minutes of the Committee meetings, subject to any items that are discussed in confidence under section 90 of the Act and subsequently retained as confidential under section 91 of the Act, are also required to be made available to the public.
Council’s external auditor may be invited to attend meetings of the Committee.
Appointments to the committee shall be for a period as determined by Council. Appointees may be reappointed by Council.
PRESIDING MEMBER
The Council shall appoint the Presiding Member of the Committee. The Presiding Member may be an independent Committee Member.
ADMINISTRATIVE RESOURCES
The Chief Executive Officer shall provide sufficient administrative resources to the Committee to enable it to adequately carry out its functions.
MEETINGS
The Committee shall meet at least three times a year at appropriate times in the reporting and audit cycle and otherwise as required.
Meetings will be conducted in accordance with the provisions of Section 87, 88 and 90 of the Local Government Act, 1999, Part 3 of the Local Government (Procedures at Meetings) Regulations, 2000, and Council Policy C1.8 “Meetings of Council and Council Committees”.
QUORUM
The quorum necessary for the transaction of business shall be one elected member and one independent member. A duly convened meeting of the Committee at which a quorum is present shall be competent to exercise all or any of the authorities, powers and discretions vested in or exercised by the Committee.
NOTICE OF MEETINGS
Ordinary meetings of the Committee will be held at times and places determined by the Committee. Special meetings of the Committee may be called in accordance with the Act.
Notice of each meeting confirming the venue, time and date, together with an agenda of items to be discussed, shall be forwarded to each member of the Committee and invited observers, no later than 3 clear days before the date of the meeting. Supporting papers shall be sent to Committee members, and to other attendees as appropriate, at the same time, whenever practicable.
Version3 Page5
REPORTING REQUIREMENTS The Chief Executive Officer shall ensure that the proceedings and resolutions of all meetings of the Committee are minuted in accordance with the provisions of Section 91 of the Local Government Act, 1999 and Section 9 of the Local Government (Procedures at Meetings) Regulations 2000.
Minutes of the meetings shall be circulated in accordance with the provisions of Section 91 of the Local Government Act 1999, Section 9 of the Local Government (Procedures at Meetings) Regulations 2000, and Council Code of Practice C1.8 “Meetings of Council and Council Committees”.
The Committee will inform the Council, by the earliest practical means, of the development of any special risk arising from the performance of its delegated functions (in accordance with the Rules of the LGA Mutual Liability Scheme).
The Committee will inform the Council, by the earliest practical means, of any civil liability claim which has been made, or is likely to be made in relation to the actions of the Committee pursuant to its delegated responsibilities.
The Committee shall make whatever recommendations to the Council it deems appropriate on any area within its terms of reference where in its view action or improvement is needed.
CODE OF CONDUCT Members of the Committee shall act in accordance with the Council's Code of Conduct pursuant to the provisions of Sections 62 and 63 of the Local Government Act, 1999.
ROLE AND RESPONSIBILITIES OF COMMITTEE MEMBERS
Committee members shall:‐
strictly observe the requirements of the relevant Sections of the Local Government Act, 1999 applicable to them as Elected Members of the Council;
participate in the deliberations of the Committee with regard to the policy and business which is before it;
be mindful of the objectives and policies of the Council as they relate to the business of the Committee; and
be aware of the Council’s resources, expenditure and activities, and the need for efficiency and effectiveness in the activities for which the Committee has been established.
CONFLICT OF INTEREST Members of the Committee shall comply with the conflict of interest provisions contained within Sections 73 and 74 of the Local Government Act, 1999.
REVIEW These Terms of Reference will be reviewed annually in accordance with the provisions contained in the Local Government Act 1999.
OTHER MATTERS
The Committee shall:
have access to reasonable resources in order to carry out its duties;
be provided with appropriate and timely training, both in the form of an induction programme for new members and on an ongoing basis for all members;
Version3 Page6
give due consideration to laws and regulations of the Act;
make recommendations on co‐ordination of the internal control measures and external auditors;
oversee any investigation of activities which are within its terms of reference; and
oversee action to follow up on matters raised by the external auditors;
at least once a year, review its own performance, constitution and terms of reference to ensure it is operating at maximum effectiveness and recommend changes it considers necessary to the Council for approval.
REVISED ON 23 OCTOBER 2012 (RESOLUTION 160/13)
MAYOR
CHIEF EXECUTIVE OFFICER
Erika Vickery
Helen Macdonald
24 October 2012 24 October 2012
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act)
1 Reviewing annual financial statements to ensure that they present fairly the state of affairs of the Council
1.1 Review Council’s annual financial statements to ensure that they present fairly the state of affairs of the Council Review statements prior to adoption by Council October 2012 20.09.2012 Resolution 6/13 presented to and
endorsed by Council 28 September
2012August 2013 21.08.2013 Resolution 8/14 presented to and
endorsed by Council 27 August 2013
September 2014 9.09.2014 Resolution 9/15 presented to and
endorsed by Council September 2014
September 2015
2Proposing, and providing information relevant to, a review of the Council’s strategic management plans or
annual business plan2.1 Comment on the draft annual business plan prior to its formal consideration for adoption by Council, particularly in
terms of consistency with Council’s strategic management plans, recognising that Council is responsible and
accountable for policy positions and service level decisions but mindful also that the Audit Committee has
responsibilities to ensure Council is aware of the impact on ongoing financial sustainability of its proposals.
Review draft annual business plan and budget. June 2013 14.5.2013 Resolution 30/13 received draft
documents and noted planned release
for public consultation by Council.
11.06.2013 Resolution 32/13 noted that draft
annual business plan & budget reviewed
prior to formal adoption by Council.
June 2014 10.06.14 Resolution 32/14 noted that draft
annual business plan & budget reviewed
prior to formal adoption by Council.
June 2015
2.2 The Audit Committee should satisfy itself regarding the:-
* consistency of Council’s Strategic Plan with its long-term financial plan; * Provide comment on Council’s Strategic
Management Plan prior to adoption
November 2012 04.12.2012 Committee provided comment to
Council in relation to draft Plan.
November 2016
* consistency of Council’s long-term financial plan with its infrastructure and asset management plan
(I&);
* Review long term financial plan annually, taking
into consideration Council’s actual results from the
previous year, budget and financial targets.
April 2013 18.06.2013
10.03.2013
Resolution 34/13 That the LTFP was
reviewed and noted.
Resolution 16/14 Draft LTFP
recommended to Council for adoption
December 2014
* Joint Workshop to be held between Council and
audit Committee to discuss long term financial
planning.
November 2013 19.11.2013
June 2015
* soundness of the I& (eg. is it supported by engineering and other professional assessments regarding the
condition of Council’s infrastructure assets?
* likely impact on Council’s service levels and standards, and ongoing financial sustainability of implementation of its
suite of strategic management plans.
* Review financial targets annually February 2014 4.02.2014 Resolution 20/14 - Current targets are
approriate and relevant for the year
ending 2015February 2015
Action Timeframe Date Completed Outcomes
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act) Action Timeframe Date Completed Outcomes
3 Proposing, and reviewing, the exercise of powers under section 130A
3.1 Examine whether the Council has developed a formal policy and associated arrangements for exercising its powers
to initiate efficiency and economy audits.
Having regard to its own work program and the Council’s available resources, risks and anticipated benefits and
costs, the Audit Committee should identify whether there are key functions where it might recommend that an
efficiency and economy audit be performed.
4Liaising with the Council’s Auditor
4.1 Meet with the Council’s external auditor to: * Annual meeting with Council’s Auditor – generally
scheduled during Council’s interim audit
April 2013
April 2014
20.3.2013
14.04.2014
* invite presentation of his/her audit methodology and risk assessments within the audit plan; April 2015
* discuss any qualifications raised in the most recent audit or comments made in the accompanying audit
management letter;* assess the appropriateness of the proposed Council response to matters so raised; and
* invite comment on the financial systems and affairs of the Council having regard to comparable benchmarks.
4.2 Keep oversight of the Council’s relationship with its external auditor and develop an appropriate timeframe to
address all matters requiring consideration in the appointment/re-appointment of the external auditor and
manage this process when it falls due [note: section 128 requires the Council’s external auditor to be rotated after
no more than five years] .
* Review tender specification June 2015 9.09.2014 Proposed joint tender with DC Grant &
Wattle Range. Resolution 2/15
* Assess tenders October 2015
* Recommend appointment to Council (refer S.128
(2) LG Act)
November 2015
4.3 Ensure compliance with regulation 22 of the LG (Financial Management) Regulations 2011 which prevent a
Council from engaging its Auditor to provide any services to the Council outside the scope of the auditor’s
functions under the Local Government Act 1999
* Receipt of Auditors “Certification of
Independence”Annually prior to Audit signing
financial statements
Certification of Independence received
for the year ending 30 June 2012, 2013
& 2014
5
Reviewing the adequacy of the ACCOUNTING, internal control, reporting and other financial management
systems and practices of the Council on a regular basis
5.1 Review the following policies prior to adoption by
Council:
* C3.1 – Accounting Policy – Infrastructure, Property,
Plant & Equipment
June 2013 13.06.2013 Resolution 37/13 endorsed by Council
June 2013 (resolution /13)
June 2014
10.06.14Resolution 33/14 endorsed by Council
June 2014 (resolution 421/14)
June 2015
* C1.2 – Asset Management Policy June 2015
5.2 5.2 Ensure that asset values and depreciation rates are up to date and soundly based, including that they have
particular regard to local conditions and do not just reflect common practice elsewhere e.g.
* Presentation of Council’s Asset Management
Strategy by the Director Operations & Technical
Services* whether land values reflect the current local market;
* whether infrastructure asset values reflect local replacement costs and the condition of existing assets;
* whether an infrastructure asset condition audit has been undertaken recently to assist in making this judgement
Oral presentation of Strategy, presented
an opportunity for Committee to ask
direct questions of Council’s Director
O&TS
October 2012 09.10.2012
Identify areas of accounting treatment that are open to discretion, and in particular have material impact on
reported financial performance and position (eg. assumed asset lives, depreciation methodology, asset revaluation
frequency and techniques, capitalisation policies and overhead accounting treatments; all can have material affect
on the operating result and net asset values).
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act) Action Timeframe Date Completed Outcomes
6
Reviewing the adequacy of the accounting, INTERNAL CONTROL, reporting and other financial management
systems and practices of the Council on a regular basis
6.1 *
6.2 Establish whether locally appropriate strategies exist to minimise the likelihood of occurrence and adverse
consequence for obvious and major internal control and other risks eg:
Review the following policies prior to adoption by
Council:
Consider the range of documented internal control policies and procedures and whether they are being followed. * C3.4 – Internal Control Policy & Procedure August 2012 14.08.2012 Resolution 3/13 endorsed by Council
28th
August (resolution 84/13)
August 2013 13.08.2013 Resolution 4/14 endorsed by Council 27
August 2013 (resolution
August 2014 12.08.2014 Resolution 3/15 endorsed by Council 26
August 2014 (resolution 56/15)
August 2015
* C6.6 – Fraud and Corruption Prevention Policy October 2012 09.10.2012 Resolution 245/13 endorsed by Council
11.12.2012 (Fraud and Corruption
Prevention Policy) and Resolution
246/13 (Fraud and Corruption
Prevention Procedure)December 2014
* C3.5 – Prudential Management June 2013 11.06.2013 Resolution 38/13 endorsed by Council
25 June 2013 (resolution 465/13)
June 2015
* Develop a monitoring tool to measure compliance
with Policy No. 64
February 2014 4.02.2014
6.3 Ensure a thorough review is undertaken to identify locally appropriate internal control and risk management
policies and procedures.
* Adoption of “2012 Better Practice Model –
Financial Internal Control for South Australian
Councils”
TBD 13.08.2013 Resolution 5/14 endorsed by Council
(refer resolution
(Refer August 2012 Agenda, Item 3.2)
Ensure that identified improvement opportunities can be appropriately addressed [note – this could be
undertaken progressively in stages with the locally most important and highest risk areas tackled first]
* Assessing Officer to Conduct “Control Assessment
Worksheets” in relation to all risks included in the
2012 Better Practice Model
June 2014 Update provided at each meeting.
* Develop Action Plans where worksheets have
identified that control is currently not in place
December 2014
Note: Council’s Auditor is not required to provide a formal opinion in relation to Council’s Internal Controls until
the 2015/2016 financial year
* Reviewing Officer to review initial assessment of
controls (note the Assessing Officer and Reviewing
Officer role must not be performed by the same
employee)
June 2015
Identify whether weaknesses in internal controls have been previously identified, eg. by management or Council’s
external auditor, and if so whether action has been taken to have them addressed.
Review audit management letters and implement
recommendations as appropriate
To be determined following
receipt of lettersResolution 19/3 -That the internal
control framework and the sample list
of weaknesses identified in the External
Auditor’s letter be used to benchmark
Council’s internal control procedures
and practices, taking into account
changes to legislative requirements.
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act) Action Timeframe Date Completed Outcomes
6.4 Whether an assessment has been undertaken to identify Council’s risk exposure and actions established to
minimize their likelihood and effect.
Review the following policy prior to adoption by
Council:Whether there are significant risks identified by Council’s insurers that have not been reasonably addressed and
therefore could jeopardise insurance cover in this regard.
* C1.10 – Risk Management February 2014 12.2.2013 Resolution 20/3 endorsed by Council
February 2013
February 2015
* Annual Review of the Corporate Risk Register is
presented to the Audit Committee in the first
quarter of each calendar year (refer resolution
21/3)
April 2014 14.04.2014
April 2015
* Complete LGA Mutual Liability Self-Assessment
Annually
Annually in May May 2012 Presented to Audit Committee on the
4th December 2012
* Develop Action Plan following receipt of Self-
Assessment Results (generally received in August.
Responsibility sits with CEO)
October 2012 4.12.2012 Received by Committee
* Report to Committee detailing progress in relation
to Risk Management Action Plan
* Invite Council’s CEO, Directors and Senior
Management to address Committee Meetings in
relation to risk management
As Required Various CEO, Directors & Network Administrator
* Annual Meeting with Council’s insurers May 2013
May 2014
May 2015
May 2013
May 2014
Attended by Fiona Stringer - Director CS
6.5 Whether Council and the CEO have provided an appropriate level of delegation to Council Officer’s which while
allowing the day to day operations of Council to continue, does not unduly expose the Council to risk.
* Review the delegations register April 2013 26.03.2013 Revoked existing delegations and
adopted new delegations. Council
Resolution 335/13. * Following initial review, receive annual reports
from the Governance Officer highlighting
amendments and changes made in the previous
twelve months.
April 2014 14.04.14
6.6 Whistle blowing Review the following policy prior to adoption by
Council:
* Identify whether the Council has in place simple, readily accessible arrangements for employees to confidentially
raise concerns of alleged malpractice in accordance with legislative provisions.
* C6.9 – Whistleblowers Protection October 2012 09.10.2012 Recommended to Council for deletion as
the contents of this Policy is duplicated
in Council’s Fraud & Corruption
Prevention Policy. Council resolved to
remove from suite of policies 22 Jan
2013 (refer resolution 259/13)
* Examine whether Council’s whistleblower arrangements are well known to employees and effective having regard
to local circumstances.
* Provide training to employees in relation to
Council’s Whistleblowers Protection Policy
December 2014 May/June 2014 In-house training session conducted
by Director Corporate Services.
6.7 Explore whether an internal audit service would be beneficial to Council and could be cost-effectively provided (eg.
through an external service provider, possibly in conjunction with other Councils).
* Review on an annual basis (refer resolution 17/4) December 2013 10.12.2013
December 2014
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act) Action Timeframe Date Completed Outcomes
7Reviewing the adequacy of the accounting, internal control, REPORTING and other financial management
systems and practices of the Council on a regular basis
7.1 Meet regularly, in compliance with the Committee’s Terms of Reference to discuss items contained in the Work
Program and any additional items referred from Council.
* Develop and publish a meeting schedule for each
financial year
June 2013 11.06.2013 Resolution 39/13 to continue to meet on
the 2nd Tuesday of every second month
until June 2014
June 2014 10.06.14
Resolution 35/14 to continue to meet on
the 2nd Tuesday of every second month
until June 2015
June 2015
7.2 Ensure that significant, urgent matters identified through the Audit Committee are formally and promptly
reported to Council.
* Adoption of minutes by Council Next ordinary meeting of
Council following Committee
meeting
7.3 Ensure that financial information included in publications for external audiences (eg. Annual Report) accurately
reflects key accrual based financial information and where appropriate sector endorsed financial targets.
* Provide comment, as appropriate, on Council’s
Annual Report
November 2013 19.11.2013
November 2014
7.4 Report annually to Council:
* outlining outputs relative to the Audit Committee’s work program and the results of a self-assessment of
performance for the preceding period including whether it believes any changes to its charter are appropriate;
* Review Terms of Reference October 2012 09.10.2012
October 2013 19.11.2013
October 2014
*
*
advising future work program proposals; and
outlining any identified training needs
* Presentation of annual report, outlining Audit
Committee’s actions for preceding twelve months,
to Council
October 2012 11.12.2012
December 2013 17.12.2013
December 2014
8 Reviewing the adequacy of the accounting, internal control, reporting and OTHER FINANCIAL MANAGEMENT
SYSTEMS AND PRACTICES of the Council on a regular basis
8.1
*
*
*
Review, and where warranted suggest improvements in, the formats of budget, budget reviews, and actual
financial performance information reported to the Council to ensure they:
are succinct, easy to follow and pitched with a strategic focus;
are based on accrual accounting information and include the material required by Regulations 7,9 and 10 of the LG
(Financial Management) Regulations 2011; and
incorporate key financial sustainability information including comparision of revised forecasts and actual results,
compared with budget against targets (where they have been set by Council) for sector-endorsed financial
indicators
* Review the LGA’s Draft Policy – Budget Reporting
& Amendment Policy prior to recommending to
Council for adoption.
April 2013 09.04.2013 Resolution 24/13 endorsed by Council
April 2013 (resolution 370/13)
April 2017
* Review Mid Year Budget Review prior to
presentation to Council
April 2014 14.04.2014
April 2015
* Review Budget vs Actual December 2013 19.11.2013
December 2014
8.2 Review Council’s performance against sector wide assessment tools, eg. Good Governance Program. * Review the initial report. As Required No current reports
* Monitor achievements and progress As Required
Presiding Member presents annual
report (verbal) to Council.
No changes recommended.
NARCOORTE LUCINDALE COUNCIL
Audit Committee Work Program
[Updated 17/10/2014]
Functions of the Audit Committee
(refer to Section 126 Local Government Act) Action Timeframe Date Completed Outcomes
8.3 Monitor performance of the Naracoorte Regional Livestock Exchange (NRLE) to ensure the facility remains
commercially viable.
* Review the annual business plan and budget for
operation of the NRLE, including budgets for
capital works prior to adoption by Council.
April 2013 14.5.2013 Resolution 29/13
Provide Council with recommendations in relation to any financial risk associated with the operation and further
development of the facility.
April 2014 14.04.2014 Resolution 28/14
April 2015
* Review proposed revisions to budget prior to
adoption by Council.
As Required 4.12.2012
14.04.2014
* Review quarterly report including financials, capital
and operational expenditure, and other
information pertaining to the performance of the
Livestock Exchange prior to presentation to
Council.
On-going
* Review the NRLE Committee’s Annual Report,
which reports against the 2012-2022 Strategic
Management Plan, prior to presentation to
Council.
November 2013
November 2014
13.08.2013 Resolution 6/14
8.4 Identify areas of Council’s operations where financial and/or governance risk is perceived to be high and
recommend to Council a full analysis of all of life costs, including future replacement, expansion or removal.
* Program to be developed Operations Review undertaken and
continued to be reviewed by Council
8.5 Review the range of Council’s financial governance policies and practices to encourage best practice. * Review Council’s Policy Index, highlighting policies,
as appropriate, for the Committee to include in its
review process.
December 2012 December 2012 Completed by the Director of Corporate
Services
- Investment Policy
12.02.2013Resolution 22/13. Adopted by Council
February 2013 (resolution 311/13)
* Review Draft Policies released by the LGA and
recommend to Council for Adoption as
appropriate.
As required
8.6 Other items recommended from Council for the attention of the Audit Committee. *Leave Liability – develop and introduce leave policy
October 2014
Other items as raised for consideration by the Audit Committee.
* YTD Expenditure, Income, Capital and Major
Projects reports presented to committee on an
ongoing basis
On-going
* Review Community Chest Guidelines April 2013 9.04.2013 Resolution 28/13
* Training Opportunities - Committee Members On-going