PCBC Block Cave Scheduling

Embed Size (px)

Citation preview

  • 7/24/2019 PCBC Block Cave Scheduling

    1/17

    1

    BLOCK CAVE PRODUCTION SCHEDULING USING PCBC

    Tony Diering, Gemcom Software International Inc., Vancouver, Canada

    Otto Richter, Gemcom Australia, Perth, Australia

    Daniel Villa, Gemcom Software International Inc., Vancouver, Canada

    Abstract

    Gemcom PCBCTMis a software package which

    has been developed over the last 22 years for the

    planning and scheduling of block cave mines. This

    paper presents an update of the various research and

    development activities done to PCBC recently. It

    also provides an overview of the current capabilities

    of the software including tools for both feasibility

    type studies as well as tools for operating mines.

    PCBC is used extensively by prospective and

    operating block cave mines and some of the recent

    applications are described.

    Introduction

    History

    PCBC was first developed in 1988 for the

    Premier Diamond Mine in South Africa(Diering,

    2000). In 1992, the first production scheduler was

    added to the system and in 1994 a significant upgradewas done for Northparkes Mine in preparation for

    their Lift 1. PCBC was upgraded to Microsoft

    Windows operating system in 1996. In 2002, the

    Cave Management System (CMS) was developed for

    Freeport DOZ mine and this was upgraded to provide

    SQL Server database support in 2003 for Finsch

    Diamond mine(Diering, 2004). A new algorithm

    called Template Mixing (Diering, 2007) was added to

    provide better and alternate flow modeling options to

    users.

    More recently, various enhancements to the

    production scheduler and other areas of the program

    have been completed some of which are describedhere.

    It is worth noting that the block cave market (in

    terms of software) is very limited. As such, it is

    difficult to fund high quality research and program

    development. We at Gemcom Software International

    Inc. have been very fortunate to have companies

    sponsor custom development activities within PCBC

    over the years. These companies are listed in the

    acknowledgements section of this paper.

    Typical project workflow

    A significant number of block cave projects

    have been studied using PCBC over its 20 year

    history. During that time, a well used work flow has

    evolved which is usually used as a guideline for new

    projects.

    Conceptually, the steps are as follows:

    Figure out what is in the ground (geological

    model)

    Work out where you want to mine (X,Y,Z limits)

    Work out the tons and grade that you will get

    from those limits

    Work out how long it will take (time)

    Optimize and iterate to add further value to the

    project.

    Repeat the whole process every time a new

    geological model is produced as the project

    evolves.

    The overall steps in the process are described

    below:

    Footprint Finder. This is an application which

    works off the geological block model and whose

    primary objective is to help assess the best

    elevation (or elevations) for the block caving

    footprint (Z extent of the mine)

    Generate draw points. Setting up draw points

    requires assessment of draw point spacing,

    tunnel orientation etc. (X,Y extents)

    Construct slice file. This is the process of

    conversion of a geological model to be aligned

    with the draw points such that each draw pointhas an in-situ (un-mixed) resource above it.

    Compute best Height of Draw (HOD). Each

    draw column is evaluated to assess the best or

    highest dollar value which can be achieved for a

    given set of mining costs and product revenue

    and recovery factors.

    Production scheduling. This is the heart of the

    PCBC system. It is important to distinguish

  • 7/24/2019 PCBC Block Cave Scheduling

    2/17

    2

    between production (tons and grade produced)

    and development scheduling (tunneling and

    development). PCBC does production

    scheduling. This provides the tons and grade

    forecasts for the project which has been

    described as the mine planners promise to the

    shareholders as to what the mine can produce.

    Advanced schedules. No schedule is ever

    complete or final. During the project evaluation

    stage, new pricing or geometrical options will be

    considered and new geological models generated

    as the exploration drilling progresses. During

    production, new schedules are generated

    whenever the actual production varies from the

    plan (which is always). So the need for a

    scheduler which can run in typically less than 20

    to 30 minutes per run is important.

    Operating mine set up. Once a mine is going

    into production, then it is possible to set up a

    database to store production tons and draw point

    assay and other observational data. The

    importance of accurately recording and

    managing the tonnages extracted from each draw

    point has long been recognized.

    CMS can be used to help manage the daily (or

    shift based) draw order. This is the daily

    tonnage target set for each draw point. This is

    essential if a managed block cave is to be

    maintained.

    Geological/geotechnical monitoring. Tools have

    been developed within PCBC to help store,

    display and analyze observed data

    Least Squares (LSQ) and grade reconciliation

    can be used to base schedules on observed assaydata instead of block model data for more

    accurate schedules

    During the above process, it is essential to have

    appropriate tools to interrogate and query the

    results generated. Over the years, a substantial

    toolbox has evolved based on project and user

    requirements.

    In this paper

    This paper describes the various components in

    the PCBC product. It is not intended to provide any

    explanation as to how these components work or are

    used.

    Components of PCBC

    The various components of PCBC have evolved

    to support the above project workflow. PCBC runs

    inside the Gemcom GEMSTMmine planning package

    developed by Gemcom Software International Inc.

    (Figure 1) The ability of PCBC to work inside of this

    framework has proven invaluable over the years and

    has allowed our development efforts to focus on the

    block cave part of the problem minimizing the need

    to develop and maintain the underlying graphical and

    database subsystems.

    Figure 1 Typical view of PCBC running inside the GEMS

    general mine planning package

    Components of PCBC are described below

    including initial assessment of footprint location,

    model set up and mineable reserve assessment, then

    scheduling and production management.

    Foundation

    This is the framework within which PCBC

    operates. The various components are summarized

    as follows:

    Graphical interface

    Blocks

    Lines

    Points

    Triangulations

    SQL database / workspaces

    Profile editors / parameter management

    Footprint Finder

    Input for Footprint Finder utility comes from a

    geological block model together with mining costs,

    revenue factors, etc. The program will look at each

    level in the block model and then construct vertical

    columns accumulating the dollar value. Vertical

    mixing is applied to each column using an algorithmbased on Laubschers mixing method (Laubscher,

    1994).

    This is very useful to obtain an initial idea of

    where to locate a footprint and what the initial

    footprint shape might be. Figure 2 shows

    accumulated columns plotted according to value.

  • 7/24/2019 PCBC Block Cave Scheduling

    3/17

    3

    Figure 2 Footprint Finder example on one level

    Repetition of this process on each level allows

    the tons and value generated to be plotted as showninFigure 3.

    -

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    -

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1,000

    2560

    2620

    2680

    2740

    2800

    2860

    2920

    2980

    3040

    3100

    3160

    3220

    3280

    3340

    3400

    3460

    3520

    3580

    3640

    DollarValue(M$)

    Tonnage(Mt)

    Elevation

    Tons Dollar value

    Figure 3 Footprint Finder : Tons and dollar value vs

    footprint elevation

    An example from Freeports DOZ mine is shown in

    Figure 4.

    Figure 4 Footprint Finder example (DOZ mine)

    The higher grade zones are shown in warmer

    colors. This type of value plot assists considerably

    with the process of defining a reasonable

    economically and geotechnically feasible outline.

    PCBC

    Overall steps of a typical project (from the

    program, not project perspective) are as follows:

    Set up the initial working environment inside a

    GEMS project.

    Slice file construction (Figure 5). This is an

    integral part of the process. Utilizing user-

    defined draw cone shapes, a column of rock

    above each draw point is simulated and stored in

    what is termed a slice file. The term slice as the

    total column is broken into slices which match

    the vertical spacing of the geological block

    model.

    Figure 5 Schematic of block model to slice file conversion

    Draw point locations are used to construct a

    vertical column which is then intersected with theblock model. The various overlaps of the draw cones

    are resolved so as to not double count material and

    this is accumulated into the slice file for each draw

    point. This is referred to as a NoMix slice file,

    since no material mixing has yet been applied.

    Figure 6 shows a section of a block model and

    the resulting NoMix slice file with one column per

    draw point.

  • 7/24/2019 PCBC Block Cave Scheduling

    4/17

    4

    Figure 6 Block model to slice file conversion

    A variety of material mixing algorithms may

    then be applied to the slice file to simulate the

    actual material mixing which takes place as

    material is extracted from the draw points.

    Best HOD. The Best HOD utility will

    accumulate tons, grade and dollar value in each

    draw column (after application of vertical

    mixing) to provide an estimate of mineable

    reserves for different footprint shapes. As this

    process uses actual draw point locations and

    assumed draw column shapes, it is generally

    considered more geometrically accurate than theFootprint Finder.

    Figure 7 Best HOD based footprint (bottom) vs Footprintfinder result (top) (Cadia East)

    Figure 7 shows that the results from Footprint

    Finder and Best HOD tools are typically quite similar

    as one would hope.

    Once the basic preparation work has been done,

    production schedules can be generated.

    A typical schedule requires input of the

    following key components (Figure 8):

    Sequence to develop the draw points (and

    undercut)

    Constraints on the maximum draw rate which

    can be applied to draw points

    Tonnages required in each scheduling period

    Information to control the cave shape. It is usual

    to look at different strategies and compare

    Numerous other inputs, constraints and reporting

    control options

    Figure 8 Production scheduling components in PCBC

    A basic schedule will open draw points

    according to the sequence and deplete tons from eachaccording the Production Rate Curve (PRC), apply

    material mixing if required and report tons and grade

    mined in a variety of formats.

    An advanced schedule could look at changing

    parameters for individual or groups of draw points,

    adjusting the schedule to past tons mined, having the

    HOD profile follow a given cave shape and adding

    information to report undercut tons separately from

    production tons.

    Experience has shown that it is very useful to

    have a clean and efficient interface between PCBC

    and Microsoft Excel. This allows reports to begenerated in a format which can quickly be further

    analyzed by engineers.

    In addition, when dozens or hundreds of

    schedules are being run, it is useful to have what is

    called a playback tool. This allows various aspects

    of the schedule to be studied visually to look for

    trends (or data input errors!)

  • 7/24/2019 PCBC Block Cave Scheduling

    5/17

    5

    The production scheduler can just as easily be

    used for forward looking schedules or for analysis of

    past performance. This is very useful for grade

    calibration and reconciliation purposes.

    Cave Management System

    CMS was originally developed for FreeportDOZ mine and then further refined for use at Finsch

    mine. Currently there are seven mines using or

    planning to use CMS. CMS aims to generate a draw

    order for each draw point every day or shift. It uses

    the recent historical (actual) tonnages to adjust and

    manage the draw and provides the supporting

    database, reporting and user interface to facilitate this

    process. At De Beers Finsch mine, CMS has been

    closely integrated with the Sandvik Automine

    system.

    Figure 9 How CMS fits in between historical tons andfuture plans

    Figure 9 shows how CMS fits in between thehistorical tons mined and the requirement to adjust

    the plan of the next few months (using PCBC

    schedules) in a process called Catch-up to fit in

    with the long term plan. (Diering, 2004)

    Figure 10 Categorization of draw points for priority

    assignment

    Each draw point can be categorized in a variety

    of ways (Figure 10), including over-draw, under-

    draw, normal, draw-bell development, wet muck

    (which is a safely concern) or as requiring special

    treatment. The tonnage for each category is set

    accordingly.

    Figure 11 Excel map format for draw point result display

    Figure 11 shows an example of daily production

    data displayed using Excel. It is important to have a

    clean interface between the CMS database and Excel

    for ease of analysis by the draw control personnel.

    LSQ

    The LSQ tool is intended for operating mines.

    Once a mine has been in operation for a few years, it

    will likely have a draw point sampling program. The

    draw point assay values can be stored and sorted per

    draw point and then composited into 10m or 15m

    intervals to provide some averaging of the highly

    variable assays.

    Subject to a variety of constraints, a least

    squares trend line is put through the composites and

    then this can be extrapolated for a short distance upthe draw column into what is essentially the un-

    mined part of the column (Figure 12).

    This becomes particularly useful when the draw

    point assays suggest that the draw point should

    remain open (usually after 100% draw) when the

    slice file values suggest that the draw point should be

    closed. For draw points where the sample trend

    differs from the slice file, then the slice file values are

    replaced with the sampled values for selected draw

    points. This is somewhat similar to the open pit

    practice of taking blast-hole samples to improve the

    local grade of a bench about to be blasted and mined.

    Figure 12 shows a single draw column with

    sampled values at various heights (HOD) above the

    draw point. The graph shows these together with the

    trend line and some extrapolated points. Maximum

    and minimum grade values are set so that steep up or

    downward trends do not generate unrealistic grade

    values.

  • 7/24/2019 PCBC Block Cave Scheduling

    6/17

    6

    Figure 12 Sample compositing and trend line analysis in

    LSQ

    The LSQ tool can either be run as a stand-alone

    tool or right within the PCBC production scheduler.

    Operations tools and reconciliation

    Once a mine is in operation, there is a variety of

    useful ways in which draw point sampling data

    (grade, geotechnical and geological) can be displayed

    and analyzed. A key reason for doing this type of

    work is so that we can better understand if or wherethere is irregular behavior with the cave itself. Some

    of the analysis types are listed below:

    Use of draw point assays for grade reconciliation

    and for calibration of the model

    Use of draw point assays for improved short

    term forecasting using the LSQ tool already

    mentioned.

    Use of geological samples to supplement the

    reconciliation process or to better understand

    horizontal and vertical migration of material

    within the cave (Figure 13)

    Use of geotechnical (fragmentation) data tobetter understand the relationship between draw

    rate at draw points and rock type or mining area.

    Use of convergence data in production tunnels to

    help prevent excessive closure (or collapse) of

    these tunnels. Freeport has shown quite

    convincingly at their DOZ mine that a diligent

    program of monitoring convergence in these

    tunnels is beneficial. In areas where high

    convergence rates are observed, adjacent draw

    points have an increased tonnage target which

    tends to relieve the high stresses.

    Seismic data and/or extensometers can be used to

    help predict the location of the cave back which

    can in turn be used to set up surfaces for

    simulation of the rilling process which

    migrates material non-vertically.

    The residual slice file model can be used to re-

    estimate a block model which can be used either

    in a multi-lift mining situation or as part of a new

    block model for a super-pit which some mines

    are considering.

    Figure 13 Example of graphical display of geological data

    Figure 14 Example of residual slice file to block modelconversion

    Figure 14 shows an example in which the

    residual slice file (after simulation of mining the full

    block cave tons) is used to re-estimate a geological

    block model. This block model can then be used for

    planning of another future mining block.

    Recent Developments

    PCBC is over 20 years old and hence should be

    considered as a mature product. As such the basicplanning and scheduling work flow is well covered.

    On the other hand, being mature and with a good

    foundation, PCBC has provided a useful foundation

    for a number of recent developments which are

    summarized in this section.

    Upgrades to material flow tools

    Playback utility

    Display tools

    Each of these is considered in more detail

    Material flow upgrades

    Material flow is an integral part of the block

    cave mining (and material depletion) process. The

    entry of dilution is a significant factor in the planning

    process and modeling of this has proven to be

    difficult. As such, a variety of different mixing tools

    have been developed within PCBC and users are then

    given the choice as to which approach they would

    like to adopt. This is summarized inTable 1.

  • 7/24/2019 PCBC Block Cave Scheduling

    7/17

    7

    Method Ease

    of use

    Linear? Comment

    No mixing Easy Yes No mixing base

    case (In-situ)

    Pre-Vertical

    mixing

    Easy Yes PCBC Default

    (includes pre-

    erosion)

    Laubscher

    mixing

    Easy Yes Uses Laubscher

    tables

    Sequential

    mixing

    Harder No Older method,

    includes

    toppling

    Template

    Mixing

    Harder No Most flexible

    option available

    REBOP

    interface

    Harder No Not yet

    generally

    available

    Table 1 Material mixing options in PCBC

    The linear methods can be applied with the Best

    HOD utility to find mineable reserves before the

    schedule is run. For the non-linear methods, the

    mineable reserve will be a function of the mining

    sequence and draw strategy. Therefore, mixing hasto be built right into the production scheduler. This is

    one of the key differentiators between PCBC and

    other commercial scheduling tools.

    The pre-mix option in PCBC was recently

    upgraded to allow for the inclusion of a draw cone

    erosion mechanism. This is useful as there is

    increasing evidence that draw cone radii may not be

    as large as is often hoped and also that the draw cone

    radius changes with time. A fraction of each slice is

    frozen and then an erosion rate is specified which

    allows this material to be mixed with material higher

    up each draw column.

    Template Mixing was introduced in to PCBC in

    2006. (Diering, 2007). It allows a variety of mixing

    mechanisms to be simulated including vertical

    mixing, rilling, toppling and fines migration. (Figure

    15)

    Figure 15 Movement mechanisms in a block cave

    It differs from other material flow algorithms

    such as discrete particle and cellular automaton

    methods. A major advantage of Template Mixing is

    its speed. Figure 16 shows a few steps in a depletion

    simulation. Blue represents dilution, yellow is ore

    and the intermediate colors represent progressive

    mixing as the ore is extracted.

    Figure 16 Template Mixing 2D example

    Figure 17 shows an example for our sand-box

    project using toppling, rilling and normal mixing.

  • 7/24/2019 PCBC Block Cave Scheduling

    8/17

    8

    Figure 17 Sandbox example with toppling, rilling andvertical mixing

    In 2008, a joint initiative was done with Rio

    Tinto, Itasca and Gemcom to provide the potential to

    combine the PCBC and REBOP programs. This was

    done using a hand-shake mechanism so as to

    minimize the changes required to each program and

    to keep them as independent as possible to facilitate

    future development.

    Figure 18 REBOP results displayed in PCBC (Markers leftand cones to right)

    Figure 18 shows two examples of REBOP

    results plotted within the PCBC program. The results

    from REBOP are used directly in the production

    scheduler and also for modification of the slice file.

    As a separate, but related project, Gemcom

    worked with Rio Tinto to calibrate PCBC and

    REBOP against one another. Figure 19 shows the

    geometry of the calibration problem. 50 fictitious

    draw points were located in this block model for

    testing purposes.

    Figure 19 Block model used for PCBC/REBOP calibration

    Results from the calibration exercise were reallyencouraging, suggesting ways to improve both the

    PCBC and REBOP modeling processes. A sample

    calibration curve of Cu grade is shown inFigure 20.

    0.000.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1.40

    1.60

    1.80

    2.00

    Jan-08

    Jul-08

    Jan-09

    Jul-09

    Jan-10

    Jul-10

    Jan-11

    Jul-11

    Jan-12

    Jul-12

    Jan-13

    Jul-13

    Jan-14

    Jul-14

    Cu%

    Cu% Rebop vs PCBC (N2E5)

    Cu%_M3P3

    Cu% Tm4

    Figure 20 Example calibration curve for PCBC (orange) vsREBOP (green)

    The original version of PCBC used what we

    term Laubscher mixing (Laubscher, 1994). This

    was replaced by pre-vertical and sequential mixing

    options in 1994 in PCBC. However, there are still

    projects (or people) who like to be able to compare

    back against the Laubscher mixing. So it was re-

    introduced into PCBC in 2008. It is also useful forcomparison against Footprint Finder results which

    use the same mixing.

  • 7/24/2019 PCBC Block Cave Scheduling

    9/17

    9

    Figure 21 Dilution entry. Pre-vertical mixing (top) vsLaubscher mixing (bottom)

    Figure 21 shows an example comparing dilution

    entry from a single draw column. PCBC pre-vertical

    mixing has more of an S-curve dilution entry where

    Laubscher mixing has a straight line dilution entry

    Playback Utility

    This tool is used to playback or study results

    from a production schedule. Display options include

    Triangular Irregular Networks (TINs), contours, pie

    charting, and 3D columns. Playback examples are

    shown in the later sections on Freeport DOZ and

    Palabora.

    Display tools

    Over the years, a variety of different graphical

    display tools have been developed. The more recent

    ones are the Excel interface which allows any draw

    point related data to be exported directly into Excel in

    the correct cell row and column positions for direct

    display in Excel as shown inFigure 22

    Figure 22 Excel map transfer utility example

    The Excel map format is useful for a single

    attribute per draw point such as HOD. However, if

    one has multiple attributes (which sum to 100%), a

    very useful display option is the pie chart. Theprogram will plot a pie chart at each draw point

    location using data directly from the underlying

    database from what is called multi-bucket format.

    (Figure 23)

    Figure 23 Example of Pie chart display

    In addition to the static displays available, a

    more dynamic display of selected information for

    individual draw points by right click or mouse

    movement over draw points can be very useful

    (Figure 24)

  • 7/24/2019 PCBC Block Cave Scheduling

    10/17

    10

    Figure 24 CMS control panel with right click anddisplay information

    Other options are size based plots (Figure 13),

    3D draw columns (Figure 14) and plotting of draw

    points in appropriate shapes.

    Project examples

    Freeport DOZ

    PT Freeport Indonesia has been using PCBC

    since around 2000. They are currently mining close

    to 80,000 t/d, making it a large block cave mine (T.

    Casten, 2008). PCBC and CMS are used extensively

    for planning and scheduling at the DOZ mine as wellas for daily draw control. Figure 25 shows a plot of

    forecast rock types at one step during a production

    schedule. Figure 26 shows a plot of HOD for the

    same mining step.

    Figure 25 Forecast rock types at Freeport DOZ minegenerated in Playback tool

    Figure 26 Height of draw profile at Freeport DOZ minefrom Playback tool

    Freeport Grasberg

    The Grasberg block cave is scheduled to start

    production as the Grasberg open pit slows down at

    the end of its life. (Figure 27) (Brannon, Casten, &Johnson, 2004) This will be a very large block cave

    with production up to 160,000t/d. Numerous

    scheduling options have been evaluated using PCBC

    and particular emphasis has been placed on effective

    modeling of large open pit failures which will

    generate additional dilution material.

    Figure 27 Grasberg block cave in close proximity to the

    large open pit

    Figure 27 shows the proximity of the block cave

    draw columns to the large open pit.

  • 7/24/2019 PCBC Block Cave Scheduling

    11/17

    11

    Figure 28 Column values from Footprint Finder used forfootprint assessment

    Figure 28 gives an idea of the variability of the

    orebody edges and also alludes to the difficulties in

    sequencing and scheduling such a large orebody (grid

    size above is 200m!).

    Northparkes

    PCBC was first used for Northparkes E26 Lift 1

    around 1994 and then for Lift 2 planning and

    currently for Lift 2 North (Figure 29) (Ross, 2008)

    and E 48. Each lift has provided surprises andchallenges from a modeling perspective.

    Figure 29Northparkes E26 mining

    Salvador

    The Salvador mine in Chile has used PCBC

    both for the detailed scheduling of individual mining

    panels (Figure 30) as well as for combined

    scheduling of multiple mining blocks (Figure 31).

    Figure 30 Slice file display and layout at Salvador Mine

    Figure 31 Scheduling of multiple mining panels at

    Salvador Mine

    As this is an older mine, current work is looking

    to re-estimate the residual grades in older mined out

    areas for use with future planning.

  • 7/24/2019 PCBC Block Cave Scheduling

    12/17

    12

    Andina

    Figure 32 View of three panels (lifts) at Andina mine

    Figure 33 Plan of Andina third panel showing grizzly andLHD sectors and existing development

    PCBC has been used extensively at Codelcos

    Andina mine for a number of years. Challenges in

    modeling this deposit include the multi-lift aspect

    together with reliable estimation of residual grades of

    mined out blocks (Figure 32), the effective

    scheduling of grizzly and LHD sectors (Figure 33),

    the sheer size of the project and caving issues related

    to primary and secondary rock types.

    Palabora

    The Rio Tinto Palabora mine in South Africa

    started block cave production in 2000. (Moss,

    Russell, & Jones, 2004)

    As the scheduler can work with historical

    tonnages as easily as forward looking tonnages, the

    playback tool can thus also be used for historical

    analysis or reconciliation purposes.

    Figure 34 Monthly tonnage display (poor draw control(top) and good draw control (bottom)

    Palabora went through a period during which it

    was difficult to achieve good draw control.

    However, more recently, the draw control has been

    much improved. (Pretorius & Ngidi, 2008) This isshown clearly inFigure 34.

    Figure 35 Seismic data display example from Palabora

    Figure 35, also from Palabora shows a plot of

    seismic events for one month together with draw

    points and the cave Height of Draw profile (which is

    different from cave back profile).

    Ridgeway

    The Ridgeway Deeps Mine of Newcrest used

    PCBC with the Template Mixing option to studyrilling and how this impacted the mineable reserve

    and overall production schedule (Burgio & Diering,

    2008) (Figure 36)

  • 7/24/2019 PCBC Block Cave Scheduling

    13/17

    13

    Figure 36 Section of Ridgeway deeps block cave modelshowing irregular cave propagation on right side

    Different scenarios were modeled to see the

    effect of limited cave propagation on the East side of

    the cave.

    Cadia East

    The Cadia East project of Newcrest provided

    interesting modeling challenges as it is a large multi-

    lift project. (Figure 37)Extensive use has been made

    of the Footprint Finder tool to assist with

    determination of elevations together with more

    accurate schedules from PCBC.

    Figure 37 Multi-lift example from Cadia East, Newcrest

    Finsch

    The Finsch Block 4 block cave is an example of

    mining beneath an old open pit (Richter & Diering,

    2004) (Figure 38). As mining progresses, additional

    pit wall material is failing into the developing cave.

    The remaining ore and ore/waste combination has to

    be continually updated as additional material fails

    into the cave.

    Figure 38 Schematic of open pit, cave zone and Block 4draw points at De Beers Finsch mine

    Figure 39 shows a section with some of the

    residual draw columns. These are trimmed against

    the known topography and the new failure material

    (red) then starts to mix with the existing material

    (blue). The mixing zone is shown by theintermediate colors.

    Figure 39 Addition of new failure material and mixing of

    this material with existing cave rock mass

    Figure 40 is similar toFigure 39 except that the

    sequential mixing in PCBC is turned off. This

    example shows the importance of being able to

    model this process in a non-linear manner. The final

    mineable reserve is required to be adjusted monthly

    or every time the failure surface is modified.

    Additional tools in PCBC allow for the addition of

    anticipated material for the remainder of the life of

    the Block 4 block cave as well.

  • 7/24/2019 PCBC Block Cave Scheduling

    14/17

    14

    Figure 40 Addition of new failure material withoutadditional mixing

    Calibration examples

    Freeport DOZ

    A detailed description of the calibration curves

    in figures Figure 41 and Figure 42 is beyond the

    scope of this paper. (Villa, Prasetyo, & Diering,

    2008) Figure 41 is for grade and it shows the extent

    to which the PCBC model can be changed to improve

    the fit actual against actual observations.

    Figure 41 Freeport DOZ. Calibration of grade

    Figure 42 is for the Marble rock type. It shows

    how the original PCBC marble curve (bottom) can be

    changed to more closely approximate the geological

    draw point observations (higher curves).

    Figure 42 Freeport DOZ. Calibration of Marble rock type

    Geological observations are made routinely at

    draw points of up to 8 different rock types. These

    were also fed into the geological block model so that

    comparisons could be made of the observed vs model

    rock types. Figure 43 shows the modeled rock types

    vs time and Figure 44 the observed rock types vs

    time. A detailed study of the differences between the

    two can be very informative and lead to ways to

    improve the model which may not be apparent from

    the grade model / assays. The geological modeling

    thus provides another dimension into the

    calibration process.

    Figure 43 Geological composition from block model andPCBC production schedule

    Figure 44 Geological composition based on draw point

    observations

    Palabora

    Work has been done at Palabora to improve the

    short term grade estimates using the LSQ tool

    described above. Figure 45 shows the improvement

    in the short term comparing the PCBC LSQ forecast

    vs Samples.

  • 7/24/2019 PCBC Block Cave Scheduling

    15/17

    15

    Figure 45 Measured vs PCBC standard and LSQ adjusted

    grades

    Figure 46 shows a similar set of graphs, but

    comparing hang up frequency. In this case, there was

    no initial model forecast for hang-ups, but based on

    the LSQ approach, a reasonable forecast for short

    term hang up frequency was achieved.

    Figure 46 Measured vs LSQ modeled Hang-ups

    Salvador

    Various calibration runs were done at Salvador

    mine. Two examples are shown in Figure 47 and

    Figure 48. A detailed explanation of the curves is

    beyond the scope of this paper, but the graphs show

    how mixing parameters were adjusted to improve

    both the model results and the confidence in other

    forecast results.

    Figure 47 Various PCBC runs vs assayed results for IWsector, Salvador mine for 8 years

    Figure 48 Various PCBC runs vs assayed results for ICE

    sector, Salvador mine for 17 months

    Example of block model adjustment

    In this example (Figure 49Figure 35), variousattempts were made to calibrate the PCBC results

    with the observed mill feed grades. However, the

    PCBC grades were too high irrespective of the

    mixing parameters used. This is an example in which

    the underlying block model is at fault. Re-

    estimation of the block model with different

    interpolation parameters has largely resolved this

    discrepancy.

    Figure 49 Calibration example in which the block modelrequired re-estimation

    Example involving old mining areas

    This example considered two separate runs. In

    the first (Figure 50), the block model was notadjusted correctly for historic mining. Once this had

    been recognized and appropriate changes made to the

    area in which mining had taken place, a much better

    fit between PCBC model grades and observed mill

    grades was obtained. (Figure 51)

  • 7/24/2019 PCBC Block Cave Scheduling

    16/17

    16

    Figure 50 Grade curves measured vs PCBC beforeadjustment for mined out area

    Figure 51 Grade curves measured vs PCBC after

    adjustment for mined out area

    Concluding remarks

    PCBC has been applied to a variety of different

    block cave projects and mines over the last 20 years.

    Every project has its own unique challenges some of

    which have been described in this paper. As the

    program has evolved to meet these new problems, its

    capability has been enhanced.A key component of the modeling and program

    development process has been the ongoing

    calibration of PCBC against observations / sampling.

    This process has clearly indicated that it is not always

    the material mixing which required the most

    adjustment. Careful attention is also required in areas

    of past mining, or for open pit failure material or

    even to the geological block model itself.

    The calibration examples also clearly show the

    benefits to be gained from doing a calibration

    exercise using both grades and rock types. In each

    case, a clearer understanding caving mechanisms is

    gained from the work. This type of calibration also

    strongly justifies the effort of taking draw point

    samples for grade and rock types.

    The development process for PCBC has been

    significantly enhanced by collaborative projects with

    key clients and this assistance is gratefully

    acknowledged.

    Acknowledgements

    The authors would like to thank the following

    mining companies for permissions to publish

    information and figures pertaining to their projects in

    this paper: Freeport-McMoRan Copper & Gold Inc.,

    Rio Tinto, Newcrest Mining Limited, De Beers

    Consolidated Mines Finsch mine, Codelco DivisinSalvador, Codelco Divisin Andina and Palabora

    Mining Company.

    The authors also gratefully acknowledge

    assistance with the development of the software from

    Freeport-McMoRan Copper & Gold Inc., PT

    Freeport Indonesia, Rio Tinto, De Beers

    Consolidated Mines Finsch mine, Codelco Divisin

    Andina and Palabora Mining Company.

    References

    1. Brannon, C., Casten, T., & Johnson, M. (2004).

    Design of the Grasberg block cave mine.

    MassMin, (pp. 623 - 628). Santiago.

    2. Burgio, N., & Diering, T. (2008). Simulating

    irregular cave propagation using PCBC.

    MassMin, (pp. 1033 - 1042). Lulea.

    3. Diering, T. (2004). Combining long term

    scheduling and daily draw control for block cave

    mines.MassMin, (pp. 486 - 490). Santiago.

    4. Diering, T. (2000). PC-BC: A block cave design

    and draw control system. MassMin, (pp. 469-

    484). Brisbane.

    5.

    Diering, T. (2007). Template Mixing: A

    Depletion Engine for Block Cave Scheduling.

    APCOM, (pp. 313 - 320). Santiago.

    6. Laubscher, D. (1994). Cave Mining: State of the

    Art. SAIMM, October, 279 - 293.

    7.

    Moss, A., Russell, F., & Jones, C. (2004).

    Caving and Fragmentation at Palabora:

  • 7/24/2019 PCBC Block Cave Scheduling

    17/17

    17

    Prediction to Production. MassMin, (pp. 585 -

    590). Santiago.

    8. Pretorius, D., & Ngidi, S. (2008). Cave

    management ensuring optimal life of mine at

    Palabora.MassMin, (pp. 63 - 72). Lulea.

    9. Richter, O., & Diering, T. (2004). Production

    Scheduling at Finsch Diamond Mine. MassMin,

    (pp. 453 - 458). Santiago.

    10. Ross, I. (2008). Northparkes E26 Lift 2 block

    cave A case study. MassMin, (pp. 25 - 34).

    Lulea.

    11. T. Casten, L. R. (2008). P.T. Freeport Indonesia's

    Deep Ore Zone mine - expanding to 80,000

    tonnes per day.MassMin.Lulea.

    12. Villa, D., Prasetyo, R., & Diering, T. (2008).

    Calibration of mixing model to predict grade at

    Freeports DOZ Mine. Massmin, (pp. 1053 -

    1062). Lulea.