    Road

    length=12.7

    District : Ganderbal Block :- Ganderbal

    S.No. Item Unit Qty. Rate Amount

    (In Laces.)A) i)Dismantling of dry stone walls

    (country type)

    cum 400 100 0.4

    ii)Reconstruction of dry stone

    (country type)

    cum 400 250 1.00

    B) Tree Cutting (details Enclosed ) no. 5.08

    1) Earth work

    a Earth work in cuttin cum 9630 108.52 10.45

    b) Earthwork in f illing (available) cum 4815 35 1.69

    c) Earth work in filling from

    (Barrow pits )

    cum 31087 382.99 119.06

    2 Pavement 0.00

    a)GSB Cum 5242.00 979..58 51.35

    b) WBM -GII cum 1965.75 1868 36.72

    c) Primer coat Sqm 70660.00 57.62 40.71

    d) 50mm thick Bituminous cum 3886.30 6945.68 269.93

    e) Tack Coat Sqm 70660.00 16.24 11.48

    f) 25mm thick Semi dense Sqm 70660.00 223.25 157.75

    g) Seal Coat Cum 70660.00 57.35 40.52

    3) Cross drainages

    a) RCC pipe Crossing (300mm ) No. 26 18000 4.68

    b) RCC pipe crossing (600mm dia) No. 9 56000 5.04

    b) RCC pipe crossing (1200mm No. 7 227084 15.90

    d) Pcc drain Rm 3875 1749 67.77

    e)Pcc deep drain Rm 2620 4822 126.34

    f RCC culvertsi) 17 m bridge No. 1 70.00

    ii)1x8 m RCC culvert (3m ext.) No. 1 18.00

    iii)1x6 m Rcc Culvert(4mt ext) No. 1 12.00

    iv)1x4m Rcc culvert (4mt ext) No 1 9.00

    v)1x2m Rcc Culvert No 2 3.95 7.90

    4) Protection Works

    a) R/Wall & B/Wall (avg 2 M height Rm 1500 7391 110.87

    b)PCC Edge wall Rm 2975 2915 86.72c) Create work Rm 3000 2826 84.78

    DPR Formulation Rm 12.7 15000 1.91

    Surveying Km 12.7 10000 1.27Road Furniture (details enclosed) 8.90

    Total amount 1377.20

    Assistant Executive Engineer Executive Engineer

    PMGSY, SD Ganderbal PMGSY Division Ganderbal

    Pro ect Costin

    Prada Mantri Gram Sadak Yojana ( PMGSY)

    Road Proposed in PMGSY for Rural ConnectivityUp gradation Of Road from

    Duderhama Rabitar Narayan bagh (Stage -U)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    2/34

    Road

    length=12.7

    District : Ganderbal Block :- Ganderbal

    S.No. Item Unit Qty. Rate Amount

    (In Laces.)

    Pro ect Costin

    Prada Mantri Gram Sadak Yojana ( PMGSY)

    Road Proposed in PMGSY for Rural ConnectivityUp gradation Of Road from

    Duderhama Rabitar Narayan bagh (Stage -U)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    3/34

    S.

    No

    Name

    of Block

    Type of

    Proposa

    l

    Propos

    ed

    length

    Cost of

    Paveme

    nt

    No.of

    C.D

    works.

    Cost of

    C.D

    works.

    Misc.

    cost.Total

    estimated

    cost

    Averege

    cost

    per Km.

    From To N/U Km (In Lacs) No's (In Lacs) In Lacs (In Lacs) (In lacs)

    1 Lar Dub Khanpora N 1.90 121.29 10 2.3 0.29 123.88 65.20

    (Stage II of Phase VII th Scheme Package No JK1351)

    123.88 Lacs9.29 Lacs

    133.17 Lacs

    N = New Connectivety.

    U = Upgradiation.

    Technical scrutiny done by:

    Prepared by: Signature:

    Name: Nmae:

    Designation: Designation:

    Checked by: Signature:

    Name:

    Designation:

    Scrutnized by: Signature: Signature:

    Name: Name:

    Designation: Designation:

    Pradhan Mantri Gram Sadak Yojana(PMGSY)PACKAGE SUMMARY

    State: Jammu & Kashmir. Profarma-B

    Signature:

    Coodinator STA:

    District: Srinagar. Package No: JK-13

    Name of Road

    Total Estimated cost of the Package = Rs:Routine Maintenance for 5 years= Rs.

    Grand Total = Rs.

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    4/34

    1. Location : State: J&K District : Srinagar :

    2.Package No:-

    3. Name of the Road: From To

    4. Total Length (Km) - 1.9 In Built up area - 0.7 Km In Open Area - 1.20 Km

    5. Estimated Cost Rs

    6.Type of proposal:- New connectivity

    T - or L- 0 3 8

    - If the proposal is for up gradation

    - is the road a part of the core network

    - is it associated Through Route or Not

    - PCI value

    - Age of the road

    Flexible Pavement

    65.20

    Others

    63.65

    Average Cost :

    Total

    NA

    - Is it certified that there are no other unconnected

    Eligible Habitations in the district.

    PRADHAN MANTRI GRAM SADAK YOJANA ( PMGSY)

    CHECK LIST FOR P.I.U. & S.T.A.

    To be filled by PIU.

    ( For Indvidual Road Works )

    Total Cost

    in Rs.

    Duderhama Via Gadoora Umar Hair

    Cost per

    Km. Lakhs

    33.50

    Item

    -If the proposed road is a New connectivity

    Rigid PavementStage -II

    123.88

    31.7060.23

    YES

    In the Built Up Area (m)

    7. a) Whether the Proposed Road has thedesired carriage way width,Roadway width and

    Road Land Width (RLW )

    a) Carriageway

    INDEX MAP (not to scale ) : Attached

    5.50b) Roadway

    6.5

    5.5

    6.50

    - Is the road a part of core network

    - Does the proposed Road connect the unconnected

    Habitation to

    -a) Another habitation having All- weather road.

    -b) Directly to an All weather road.

    If ( b) indicate the nature of road to which the proposed

    road leads.

    If Yes Through Route/ Link Route No.

    - Population sub served by the proposed road.

    - Name of the unconnected Target Habitation (s) (to

    be crosschecked with CN-6)

    - Does the Proposed Road lead up to the Habitation for

    which it is supposed to provide connectivity (In other words

    are you sure that the road is not being made partially?)

    3.0

    b) Indicates the actual widths of the

    following for the proposed road

    Proforma C

    3.00

    In the Open Area

    (m)

    b)

    VR

    Yes

    Yes

    c) Road Land Width

    Attached

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    5/34

    Cross Section details

    a) Cross Section of The Existing road showing different component layers.

    b) Cross Section of The Proposed road showing different component layers

    Day 1 316 326 93 76 70 45 42 7 8 198 18 0 30

    Day 2 326 336 96 79 72 58 54 9 6 253 25 0 26

    Day 3 377 389 111 91 83 48 45 8 7 209 23 0 25

    Average 340 350 100 82 75 0 50 47 0 8 7 0 220 22 0 27

    Growth rate adopted (%) =6%

    10 Years AADT = 930

    2

    No. of Days in Each Harvesting Season (t) = 75

    Value of (n) assumed = 1

    Construction Period From Base Year=2 Years Traffic Category =

    9 Subgrade CBR ( for Different Sections ) =Chainage

    CBR %

    A.

    Cost of Preparation of DPR

    930.00Base Year Traffic AADT ( After 2 years) =

    Pneumatic

    Tyred

    L

    CyclesDays Cars,Jeep,

    Vans,Three

    Wheelers

    Km 1 to KM 13

    8.00%

    Recommended CBR

    L

    T 7

    BusesTrucks

    828x(1.06)=

    7.00%

    29000

    Cost Rs.

    15263

    Design Life =

    Name of Road : Dub to Khanpora (Stage -II)

    Cycle

    Ricksha

    wa

    U OL

    10. Cost Details

    U

    General Costs

    OL L

    AADT =T+1.2*n*t*T/365, Take n =1& t=75 days ,AADT =664+(1.2*1*75*664)/365 = 828

    Number of Harvesting Seasons =

    (Should be as per Actual Provisions of DPR)

    8. Base year traffic volume

    Agricultural Tractors,

    Trailers,small trucks

    Light

    Commercial

    Vehicle(mata

    dors,Sumos

    etc)SWC

    Non Motorised Traffic

    OL

    Animal Drawn

    Vechicle

    U

    Cost /km (Rs)

    ADT in the year of Traffic Count(non-peak season) = ADT in peak season/2 =1328/2 =664

    Cumulative ESAL = 4811*T*L ,Here L =0.75 = 7,59,212

    ESAL Per Day(T) =210.41

    X-Section Attached

    X-Section Attached

    Motoris

    ed two

    Wheel

    ers

    Motorised Traffic

    Month & Year of Traffic Volume Count =

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    6/34

    B. Pavement Components Dub to Khanpora (Stage -II)

    C.Bituminous Layers

    Pavement Quality Concrete (M30 )

    G. Pucca Side Drains (if Provided)Length

    H. Road Logo, other Road Furniture

    I. Any other Provisions (Please Specify)

    6078

    Seal Coat

    If yes, their Number and Cost of improvement

    No. of Existing CD Works

    Do they require any improvement- specify the nature

    of improvement proposed

    Prime Coat

    M P M / B B M

    Semidense

    Surface

    125

    4730001425

    Earth Work - in Excavation/ Cutting

    Description of layer Cost/ km (Rs)Cost Rs.

    995000

    75

    6078

    6078

    E: C D

    455.85

    Shoulders (If not considered in the Earthwork)

    1056

    Earthwork- in Filling (Embankment)

    Subgrade (if provided seperately)

    WBM Gr -I I

    WBM Gr -I I I

    Scarifying

    Soil + Aggregate Mix

    Granular Sub base

    Tack Coat

    D. Cement Concrete Road

    Cost in Rs Cost /Km (Rs)

    337368641000

    6078

    712632

    350000

    523684

    348000 183158

    52105

    600mm dia PC

    248947

    184211

    300mm dia PC

    121211Total Cost of Proposed CD works

    88300.00

    1614421F. Protection works

    230300

    1419474

    600 RM

    1000 RM

    Thickness in mm Quantity inCum/Sqm

    0

    Total Cost of the Project (Rs)

    99000

    1354000

    2697000

    12388700

    3067400

    51.24

    3.00

    7.00

    21.96

    Type of CD & their

    NosCost in Rs.Location - Chainage ( Similar Type of CD's may be

    grouped together)

    2105000

    Total Length of

    Bridge/ Culvert

    142000.00

    1107895303.9

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    7/34

    J. Five Year Routine Maintenance

    14. Sources and the Lead distances of Materials are as under

    Source

    Zazna

    SafaporaGanderbal

    Saderkote

    Prepared By

    (Name)

    19602

    22869

    6534

    13068

    35938

    Checked By

    33

    12.Whether C.D.works / Protection works are provided as perRRM /

    Latest Circulars of NRRDA/ Respective Codes.

    1.75

    % Cost

    0.5

    Sand

    Murrum

    61943.5

    Np3 pipes

    Year

    Name of the road Dub to Khanpora (Stage -II)

    Cost /km

    340689.25

    Total Maintenance Cost

    13. Whether the Cost etimates are as per standerd data analysis and S.S.R.

    Lead

    Distance

    15

    Earth

    Material

    12

    929152.5

    Certified that information provided is true

    15 34

    Counter Signatures of

    15

    Scrutinized By

    Material

    Steel

    Source

    Co-ordinator STA :

    Pampore

    Cement

    Yes

    Yes

    Yes

    Lead Distance

    34

    185830.5

    Cost in lakhs

    I

    2.75

    30

    IV

    11. Whether the road has Geometrics as per Rural Roads Mannual RRM / Latest

    Circulars of NRRDA.

    V

    II 1.0123887

    Srinagar

    Macadam

    Mec stores pamp

    216802.25

    III

    ZankoteStones

    Aggregate

    1.5

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    8/34

    15

    16

    b) If such Unconnected Habitation eligble Under PMGSY Yes/ No

    17

    Engineering Surveys

    Hydraulic Studies.

    18

    19

    20

    Alignment & Geometrics

    Side drains

    Integration for Cross and longitudinal Drainage

    21

    22

    23PMGSY Logo Sign Boards and Information Board

    Km/Hm Stones

    Guard Stones (where necessary )

    Traffic Sign Boards (as necessary)

    24

    Signature

    Name Signature

    Date Name

    Is the design of flexible Pavement as per IRC SP: 72- 2007 and design of Rigid

    Pavement as per IRC SP:62- 2004 .

    Location and type of CD works and

    ( CBR, Density, LL, PI, Gradation to be verified)Traffic Surveys / Estimation

    ( Catchment for structures with more than 2 Vents to be verified from topo sheet.

    Location and requirement of all CD structures to be verified from L section )

    Yes / No

    In case, sub grade CBR is less than 3; has Soil Stabilisation etc. been proposed

    Is the design of the following elements as per Rural Roads Manul / Circulars of NRRDA:

    Yes / No

    Yes / No

    Protection Works

    Yes / No

    ( If not , specific Reasons given by PIU)

    Yes / No

    Certified that the Design and Estimation for the Proposed Road work are based on the data and SSR provided by

    PIU Engineers . The Proposal after final Correction is entered on the OMMS.The Propasal may be considered for

    clearance.

    Does the proposal have provisions for

    Secific Remarks, if any, by STA( Specific remarks of STA about the overall project are necessary on each DPR)

    Yes / No

    Yes / No

    Yes / No

    Yes / No

    To be filled b State Technical A enc

    Are you satisfied with the following

    (Data entries to be verified by STA before Clicking the Propopsal)

    Yes / NoDoes the Estimation Conform to Standard Rate Analysis and SSR generated for

    the current Phase

    Yes / No

    Yes / No

    In case , Traffic is projected beyond T 4 Category are you satisfied with the reason given

    by PIU

    a) If No, the name of Unconected Habitation up to which it is connected Yes / No

    Yes / No

    If the Proposal is for new connectivity

    Yes/ No

    Co-ordinator STA:

    Soil/ Material Investigation

    Date

    Have you satisfied yourself that the proposed road is a part of Core Network

    Technical Scrutiny at STA done

    Yes / No

    (L section, X section must be verified)

    Yes / No

    Name of the STA: Dr F.A.Mir

    Name of Road :Dub to Khanpora (Stage II)

    Is the unconnected habitation (s) part of list of unconnected Habitations as per CN-6

    Is the Proposed Road entered on the OMMS :

    Yes / NoYes / No

    Does the Proposal ensure full connectivity to Target Habitation

    Yes / No

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    9/34

    District :- Srinagar (Ganderbal) Block:- Lar

    From To N U Detai

    ls

    50 mm

    thick

    Macadam

    Earth

    Work

    Earthe

    n

    should

    er

    Sub Grade

    Preparation

    GSB/

    Draina

    ge

    layer

    WBM

    -II

    WBM-

    III

    Tack

    Coats

    s

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

    1 Dub Khanpora N D 1.90 FW 21.05 4.73 9.95 6.4 4.49

    Existing

    Surface

    Type

    S.No.

    PMGSY, SD Ganderbal

    Assistant Executive Engineer

    PMGSY Division

    Executive En

    Pradhan Mantri Gram Sadak Yojana (PMGSY)

    Name of Place / tourist place

    Connected by Road.

    New Const./

    Upgradation

    (Use N/U)

    Details of thickness & Cost for pavemen

    Road Proposed in PMGSY for Rural Connectivity (Pavement Layers)

    Facility

    Accessed

    (Use

    A/B/C/D)

    Road

    Length

    (KM)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    10/34

    Form F-6

    District :- Srinagar (Ganderbal)

    No Dia No L No L No Dia No dia No L No L

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

    1Dub to

    KhanporaN 1.90 3 600

    7 300

    Assistant Executive Engineer

    PMGSY, SD Ganderbal

    Pradhan Mantri Gram Sadak Yojana (PMGSY)

    H.P Culvert

    S.No. Name of

    Road

    New Const./

    Upgradation

    (Use N/U)

    Road

    Length

    (KM)

    PMGSY Division Gan

    Detalis of Proposed CD structures by Type

    Pipe Culvert M Bridge

    Details

    Executive Engine

    H. P Culvert Causeway

    Existing CD structures by Type

    Road Proposed in PMGSY for Rural Connectivity (X-Drainage Structures)Packag

    B.Arch

    Culvert

    Block:- Lar

    M Bridge

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    11/34

    Form F-I

    >1000 500-999 250-500

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    12/34

    Package No.: JK-13District : Srinagar(Ganderbal) Block : Ganderbal

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Rate

    (Rs)

    1 2 3 4 5 6 7 81 Granular sub-base / base / surface course with local materials (Table

    400.13)by mix in place method normal Construction of granular sub-base

    by providing local material spreading in uniform layers with motor grader

    on prepared surface , mixing by mix in place method with rotavator at

    once & compacting with smooth wheel roller to acheive the desired

    density complete as per clause 401.4 as per techinical specifications

    clause 408.( 5% provision for curves & passes.)

    1) Using naturally occuring gravel.

    12700 2 0.200 Cm 5080.00

    Add for extra widening at 30 number of curves and adda 900 0.90 0.200 CM 162.00Total CM 5242.00 799.36

    Carriage with an average lead of 10 Kms from Nallah Sindh TKm 10379 79.71

    Loading Cum 5242.00 22.42

    2 WBM Grading 2 :WBM Grading 2 : P/L, spreading & compacting stone

    aggregates of specific sizes to water bound macadam specification incld.

    spreading in uniform thickness, hand packing, rolling with three wheel roller

    80-100kN static roller in stages to proper grade and camber, applying &

    brooming with crushable, stone screening, binding materials to f ill up the

    interstices of coarse agg., watering and compacting to the required density

    grade 2 as per technical specification clause 405.manual means.including cost

    and carriage of all materials from approved source to site of work,with all

    leads, lif ts, loading unloading and octori. (Finished work to be measured,

    complete .) . .) .

    12700 2.0 0.075 Cm 1905.00

    Add for extra widening at 30 number of curves and adda 900 0.90 0.075 CM 60.75

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)Cost Estimate for Construction of

    PAVEMENT.

    Length Of Road 1.90 KM

    Construction Of Road from D.Q.N Upgradation

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    13/34

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Rate

    (Rs)

    1 2 3 4 5 6 7 8Total CM 1965.75 1249.8

    Carriage with an average lead of 20 Kms TKm 5110.95 209.3Loading 1965.75 73.95

    3 Prime Coat :- Providing and applying Primer coat with bitumen emulsion

    (SS-1) on prepared surface of granular base including cleaning of road

    surface and spraying primer at the rate of 0.70-1.00 kg/sqm using

    mechnical means as per Technical Specification Clause 502 including

    providing & applying tack coat with Bitumen emulsion (RS 1.00) using

    emulsion distributar @ 0.2 to 0.25kg / sqm on the prepared bituminious

    cleaned with hydraulic broom as per technical specification clause 503.

    12700 5.50 Sqm 69850.00

    Add for extra widening at 30 number of curves and adda 900 0.90 Sqm 810.00

    Total 70660.00 57.50

    Carriage with an average lead of 36 Kms Tkm 60.06 145.0

    4 Bituminous Macadam :- P/L Bituminous Macadam with Hot mix plant

    using crushed aggregate of grading as per Table 500.4 premixed with

    bituminous binder, transported to site upto a lead of 1000 m laid over apreviously prepared surface with paver finisher to the requried grade ,

    level & alignment & rolled to acheive the desired compaction as per

    techinical specification clause 504.

    12700 5.50 0.05 Cum 3492.50

    Add for extra widening at 30 number of curves and adda 900 0.90 0.05 Cum 40.50

    Add for Surface correction, Camber modification, super elevation

    etc. @10%353.3 353.30

    Total 3886.30 6626.7

    Carriage with an avg lead of 36 Kms Tkm 8549.86 145.0

    5 Tack Coat: Providing & applying tack coat with Bitumen emulsion (RS-1)

    using emulsion distributar @ 0.20 to 0.25 Kg per Sqm on the prepared

    bituminous surface cleaned with Hydraul ic broom ar per technical

    specification clause 503.

    12700 5.50 Sqm 69850.00

    Add for extra widening at 30 number of curves and adda 900 0.90 Sqm 810.00

    Total 70660 16.2Carriage with an avg lead of 36 Kms Tkm 17.67 145.0

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    14/34

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Rate

    (Rs)

    1 2 3 4 5 6 7 86 25mm thick Semidense :- Providing, laying and rolling of semidense

    bitumenous concrete of 25mm thickness composed of 13.20 mm to

    5.60mm aggregates of sepecified grade with bitumenous binder @ 4.5%

    to 5 % of mix & filler by weight,mixing in suitable plant transporting the hot

    mix work site,laid with paver finisher to required grade,levell and

    alignment,rol ling with smooth wheeled rol lers to achieve desired

    conpaction followed by seal coat ,including carriage of materials,loading

    unloading and all taxes

    Bitiumen (S- 90)

    12700 5.50 Sqm 69850.00

    Add for extra widening at 30 number of curves and adda 900 0.90 Sqm 810.00

    Total 70660.00 215.27

    Carriage with an avg lead of 36 Kms Tkm 3886.30 145.08

    7 Seal Coat :- Providing and laying seal coat sealing the voids in a

    bituminous surface laid to the specified levels, grade and cross fall using

    Type A ,Type B and Type C as per Technical Specification Clause 510.

    Type B bitumen (S-90).

    12700 5.50 Sqm 69850.00

    Add for extra widening at 30 number of curves and adda 900 0.90 Sqm 810.00

    Total 70660.00 55.45Carriage with an avg lead of 36 Kms Tkm 932.71 145.08

    8 Earthen Shoulders :- Construction of subgrade and earthen shoulders

    with material got obtained from cutting along the si te with all lifts and

    leads , transporting to site, spreading, grading to required slope and

    compacted to meet requirement of Table 300.2 with lead upto 1000m as

    per technical specifications clause 303.1.

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRDA) Div

    Executive E

    ITEM INCLUDED IN EARTH FILLING EST

    Total

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    15/34

    S.No. Description of Items Nos. L (M) B (M) D (M) Unit Qty. Rate

    (items)

    (Rs)

    Rate

    carria

    deta

    encl

    (Rs

    1 Earthwork in excavation for structures as per drawing and technical

    specifications Clause 305.1 including setting out, construction of shoring

    and bracing, removal of stumps and other deleter ious material and

    disposal upto a lead of 50 m, dressing of side and bottom and backfilling

    in trenches with excavated suitable material.(Ordinary soil upto 3m depth)

    3 2.44 0.50 1.00 Cum 3.66 183.10

    2 Bedding:

    Type B (First Class) Bedding, Laying (First Class) bedding on wellcompacted sand, moorum or approved granular material as per Clause

    1105 (ii)

    3 2.44 0.50 0.20 Cum 0.73 651.18 138.4

    3 Providing and laying reinforced cement concrete pipe NP3 for culverts on

    first class bedding of granular material in single row including fixing collar

    with cement mortar 1:2 but excluding excavation, protection works,

    backfilling, concrete and masonry works in head walls and parapets as

    per Clause 1106.(300 mm dia)

    3 2.44 Rm 7.32 1473.85 69.9

    TOTAL Total

    Rate per Pipe Crossing of 300mm dia = Rs

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRDA) Division G

    District :Srinagar (Ganderbal)

    12549

    Block:-Lar

    Executive Engineer

    Length 1.90 KMs

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost Estimate for Laying of 300mm dia cross drainage pipes

    Construction Of Road from Dub to Khanpora

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    16/34

    S.No. Description of Items Nos. L (M) B (M) D (M) Qty. T Q

    1 Earthwork in excavation for structures as per drawing and technical specifications

    Clause 305.1 including setting out, construction of shoring and bracing, removal of

    stumps and other deleterious material and disposal upto a lead of 50 m, dressing of

    side and bottom and backfilling in trenches with excavated suitable

    material.(Ordinary soil upto 3m depth)

    4 2.44 3.50 1.90 Cum 64.90

    2 3.00 1.35 2.00 Cum 16.20

    2 Bedding:

    4 2.44 3.50 0.20 Cum 6.83

    2 3.00 1.35 0.20 Cum 1.62

    4 2.44 2.35 0.70 Cum 16.05

    2 3.00 1.35 0.20 Cum 1.62

    Deduct pipes 1 3.721/2

    *.6*.6Cum 2.10

    3

    Polygonal Random Rubble massonary,uncoursed brought to course in cement

    sand mortar 1:6 with quarry stone in foundation and plinth incl cost of bond stones

    and levelling up at specified levels with M15(stone aggregate 20 mm size)

    2 3(1.35+0.

    6)/22.5 Cum 14.625

    Parapet Walls 2 3 0.6 0.6 Cum 2.16

    Deduct pipes 2 0.97( x.6x..

    6)Cum 2.1

    4Back fillingbehind abutment, wingwall and return wall complete as per drawings

    &technical specifications Clause 1204.3.8

    4 2.44 3.5 1 Cum 34.16

    Deduct pipes 1 3.721/2( x.

    6x..6)2.1

    Type A (Concrete cradle) Bedding, Laying concrete cradle bedding with M 15

    Cement concrete as per Clause 1105 (ii)

    Type B (First Class) Bedding, Laying (First Class) bedding on well compacted

    sand, moorum or approved granular material as per Clause 1105 (ii)

    1

    8

    8

    14

    3

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost Estimate for Laying of 1200mm dia cross drainage pipe

    Construction Of Road from Dub to Khanpora

    District :Srinagar (Ganderbal) Block:-Lar

    Length 1.90 KMs

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    17/34

    5 Providing and laying reinforced cement concrete pipe NP3 for culverts on first

    class bedding of granular material in single row including fixing collar with cement

    mortar 1:2 but excluding excavation, protection works, backfilling, concrete and

    masonry works in head walls and parapets as per Clause 1106.(600 mm dia)4 2.44 Rm 9.76

    TOTAL

    Rate per Pipe Crossing of 1200mm dia = Rs

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRDA) D

    227084

    Executive Engi

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    18/34

    Block K

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Total Q

    R/Wall / Breast Wall

    1 Earthwork in excavation for structures as per drawingand technical specifications Clause 305.1 including

    sett ing out, construction of shoring and bracing,

    removal of stumps and other deleterious material and

    disposal upto a lead of 50 m, dressing of side and

    bottom and back filling in trenches with excated

    suitable material(ordinary soil up to 3 mt depth)

    15 1.32+2.5

    2Cum 43.88 2.28

    2 Providing concrete for plain/reinforced concrete inopen foundat ions complete as per drawings and

    technical specifications Clause 802, 803, 1202 & 1203

    (P.C.C Grade M-10 Nominal mix 1:3:6)

    15 1.30 0.15 Cum 2.93 2.93

    15 1/2X1.10 0.30 2.48

    151.10+.60

    22.00 25.50

    8.10

    4 Polygonal/ Random Rubble masonry, uncoursedbrought to course with quarry stones laid DRY in

    foundation and plinth incl cost of bond stones.Cum 8.1 8.10

    Cost estimate for Construction of R/Wall & Breast Wall (2M Height)Construction Of Road from Dub to Khanpora Length :1District : Srinagar ( Ganderbal)

    3

    D/d dry pannels

    4.0x3.00x.750x(1.00+0.80)/2

    Cum

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    19.88

    4.0x3.00x.750x(1.00+0.80)/2

    Polygonal/ Random Rubble masonry, uncoursed

    brought to course in cement sand mortar 1:6, with

    quarry stones in foundation and plinth incl cost of

    bond stones and levelling up at specified levels with M-

    5 grade ( stone aggregate 20mm size)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    19/34

    Block Kangan

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Total Qty Rate

    (items

    (Rs)

    R/Wall / Breast Wall

    Cost estimate for Construction of R/Wall & Breast Wall (2M Height)Construction Of Road from Dub to Khanpora Length :1.90 KmsDistrict : Srinagar ( Ganderbal)

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    5 Backfilling behind abutment, wing wall and return wallcomplete as per drawings & technical specification

    Clause 1204.3.8(Material available at site) 15 0.60 1.00 cum 9 9 834.69

    6 Providing P.C.C. M 20 50mm thick coping on top ofretaining wall/breast wall.

    15 Rm 15.00 15.00 220.21

    Total

    Assistant Executive Engineer

    PMGSY, SD Ganderbal PMGSY Division Ganderbal

    Executive Engineer

    Cost per Rm=Rs

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    20/34

    Rev

    Length 1.9 KM

    Block :-

    Kangan

    .No Description of Items L (M) B (M) D (M) Unit Qty. Total

    QtyRate

    (items

    (Rs

    Crate Appron Bund

    1 Earthwork in excavation for structures as per drawing andtechnical specifications Clause 305.1 including setting out,

    construction of shoring and bracing, removal of stumps and other

    deleterious material and disposal upto a lead of 50 m, dressing of

    side and bottom and backfilling in trenches with excavated suitable

    material. (with a lift of 3 Mtrs)

    100.00 1.20 0.30 Cum 36.00 36.00 183.1

    2Providing and Laying of Boulder Apron laid in wire Crates 4mm dia

    G I Wire conferming to IS 280 and IS 4823 in 100mm X 100mm

    mesh (woven diagonaly includiing 10% extra for laps and joints

    laid with stone Boulders weighing not less than 25 Kgs each as per

    drawing and Technical Specifications Clause 1301 excluding the

    100.00 1.20 1.20 Cum 144.00 144.00 791.9

    3 Providing and fixing of crate wire with 4mm dia Black Annealedwire confirming to IS 280 and IS 4826 in 100mm X 100mm mesh

    (woven diagonally ) including 10 per cent extra laps and joints

    excluding the cost & labour of boulders144.00 Sqm 511.20 511.20 223.0

    4 Backfilling behind Crate wall complete as per drawings & technicalspecification Clause 1204.3.8 100.00 0.60 0.60 cum 36.00 36.00 834.6

    Total Total

    Rate per RM 3035.3508

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRDA) Division Ga

    Executive Engineer

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost estimate for Construction of Crate Appron Bund

    Construction Of Road from Dub to Khanpora

    District :- Srinagar (Ganderbal)

    3.55

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    21/34

    63.4 4.179074

    282.00

    228.29

    238.49

    3.76 11.41292

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    22/34

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Ra

    (item

    (R

    1 Earthwork in excavation for structures as per drawing and technical

    specifications Clause 305.1 including setting out, construction of shoring

    and bracing, removal of stumps and other deleterious material and

    disposal upto a lead of 50 m, dressing of side and bottom and backfilling

    in trenches with excavated suitable material. (with a lift of 3 Mtrs)

    100.00 1.05 0.60 Cum 63.00 183

    2 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,

    1202 & 1203 (P.C.C Grade M-10 Nominal mix 1:3:6)100.00 1.05 0.15 Cum 15.75 352

    3 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,

    1202 & 1203 { P.C.C grade M 15 Nominal mix (1:2.5:5)} 2x100

    0.30+0.20

    2 0.50 Cum 25.00 3598

    4 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,

    1202 & 1203 [ P.C.C. grade M 20, Nominal mix (1:2:4)]100.00 0.45 0.05 Cum 2.25 4071

    TOTAL

    Rate per Rm 1765

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRD

    Executi

    Cost estimate for Construction of C C Drain

    Construction Of Road from Dub to KhanporaDistrict :- Srinagar (Ganderbal)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    23/34

    118.2 13.63472

    14.18 8

    75.64 72.58604

    7929.36

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    24/34

    1.90 KM

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Rat

    (item

    (R

    1 Earthwork in excavation for structures as per drawing and technical

    specifications Clause 305.1 including setting out, construction of shoring

    and bracing, removal of stumps and other deleterious material and

    disposal upto a lead of 50 m, dressing of side and bottom and backfilling

    in trenches with excavated suitable material. (with a lift of 3 Mtrs)

    100.00 1.50 0.30 Cum 45.00 183

    2 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,

    1202 & 1203 (P.C.C Grade M-10 Nominal mix 1:3:6)100.00 1.50 0.15 Cum 22.50 3526

    3 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 { P.C.C grade M 15 Nominal mix (1:2.5:5)}

    100.00 0.40+0.652

    1.20 Cum 63.00 3598

    100.00 0.30 1.20 Cum 36.00 3598

    4 Providing concrete for plain/reinforced concrete in open foundations

    complete as per drawings and technical specifications Clause 802, 803,

    1202 & 1203 [ P.C.C. grade M 20, Nominal mix (1:2:4)]100.00 0.65 0.05 Cum 3.25 4071

    TOTAL

    Rate per Rm 4870

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRD

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost estimate for Construction of C C Deep drain Dr

    Length

    Construction Of Road from Dub to KhanporaDistrict :- Srinagar (Ganderbal)

    Executiv

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    25/34

    118.2 9.739089

    14.18 12

    75.64 182.9168

    11453.52

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    26/34

    S.No. Description of Items L (M) B (M) D (M) Unit Qty. Ra

    (ite

    (R

    Edge Wall

    1 Earthwork in excavation for structures as per drawingand technical specifications Clause 305.1 including

    setting out, construction of shoring and bracing,

    removal of stumps and other deleterious material and

    disposal upto a lead of 50 m, dressing of side and

    bottom and back filling in trenches with excated

    suitable material(ordinary soil up to 3 mt depth)

    100 0.9 0.30 Cum 27.00 18

    2 Type B (First Class) Bedding, Laying (First Class)bedding on well compacted sand, moorum or

    approved granular material as per Clause 1105 (ii) 100 0.80 0.15 Cum 12.00 65

    3 Providing concrete for plain/reinforced concrete inopen foundations complete as per drawings and

    technical specifications Clause 802, 803, 1202 & 1203

    (P.C.C Grade M-10 Nominal mix 1:3:6)100 0.75 0.1 Cum 7.5 352

    4 Providing concrete for plain/reinforced concrete in

    open foundations complete as per drawings and

    technical specifications Clause 802, 803, 1202 & 1203

    { P.C.C grade M 15 Nominal mix (1:2.5:5)}

    1000.75+.5

    21.00 Cum 62.00 35

    5 Backfilling behind abutment, wing wall and return wallcomplete as per drawings & technical specification

    Clause 1204.3.8(Material available at site) 100 0.30 0.50 cum 15.00 834

    Tot

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRR

    Execu

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost estimate for Construction of Edge wall (1M Heigh)

    Construction Of Road from Dub to Khanpora

    Cost per Rm=Rs

    District : Srinagar ( Ganderbal)

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    27/34

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    28/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    1 M-10 (1:3:6)] for 1 Cum

    carriage of C A Kijpora 0.9 Cum 2.05 13 4.03 t km 96.66

    Carriage of F.A

    Nallah

    sindh 0.45 Cum 1.84 25 4.03 t km 83.42

    Carriage of Cement Srinagar 0.22 t 51 4.03 t km 45.22

    Loading of C.A 0.9 Cum 22.42 Cum 20.18

    Loading of F A 0.45 Cum 22.42 Cum 10.09

    Loading & Unloading of

    cement 0.22 t 92.79 t 20.41

    Total 275.98

    2 R/R Masonary (1:6 mortar)

    Carriage of stones Saderkote 1 Cum 2.6 37 4.03 t km 387.69

    Carriage / Loading Unloading Chart

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    29/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    Carriage / Loading Unloading Chart

    Carriage of F.A Nallah sindh 0.38 Cum 1.84 25 4.03 t km 70.44

    Carriage of Cement Srinagar 0.092 t 51 4.03 t km 18.91

    Loading of Stones(Manually) 1 Cum 73.95 Cum 73.95

    Loading of Sand 0.38 Cum 22.42 Cum 8.52

    Loading & Unloading of

    cement 0.092 t 92.79 Cum 8.54

    Total568.05

    3 R/R Masonary (dry)

    Carriage of stones Saderkote 1 Cum 2.6 37 4.03 t km 387.69

    Loading of Stones(Manually) 1 Cum 73.95 Cum 73.95

    Total 461.64

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    30/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    Carriage / Loading Unloading Chart

    4 M-20 (1:2:4)

    carriage of C A Kijpora 0.9 Cum 2.05 13 4.03 t km 96.66

    Carriage of F.A Nallah sindh 0.45 Cum 1.84 25 4.03 t km 83.42

    Carriage of Cement Srinagar 0.32 t 51 4.03 t km 65.77

    Loading of C.A 0.9 Cum 22.42 Cum 20.18

    Loading of F A 0.45 Cum 22.42 Cum 10.09

    Loading & Unloading of

    cement 0.32 t 92.79 t 29.69

    Total 305.81

    5 M-30 (1:1:2)

    carriage of C A Kijpora 0.9 Cum 2.6 13 4.03 t km 122.59

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    31/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    Carriage / Loading Unloading Chart

    Carriage of F.A Nallah sindh 0.45 Cum 1.84 25 4.03 t km 83.42

    Carriage of Cement Srinagar 0.43 t 51 4.03 t km 88.38

    Loading of C.A 0.9 Cum 22.42 Cum 20.18

    Loading of F A 0.45 Cum 22.42 Cum 10.09

    Loading & Unloading of

    cement 0.43 t 92.79 t 39.90

    Total 364.56

    6 M-15 (1:2.5:5)

    carriage of C A Kijpora 0.8 Cum 2.05 13 4.03 t km 85.92

    Carriage of F.A Nallah sindh 0.48 Cum 1.84 25 4.03 t km 88.98

    Carriage of Cement Srinagar 0.275 t 51 4.03 t km 56.52

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    32/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    Carriage / Loading Unloading Chart

    Loading of C.A 0.8 Cum 22.42 Cum 17.94

    Loading of F A 0.48 Cum 22.42 Cum 10.76

    Loading & Unloading of

    cement 0.275 t 92.79 t 25.52

    Total 285.64

    7TypB (First Class ) craddle

    Carriage of granular materialNallah

    Sindh 1 Cum 1.92 25 4.03 t km 193.44

    Loading of Granular Material 1 Cum 22.42 Cum 22.42

    Total215.86

    8

    1200mm dia NP3 pipes(for

    per mtr pipe)

    Carriage of NP3 pipes Zainakote 1.00 Cum 2.5 60 4.03 t km 603.896

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    33/34

    Length :-1.90 Kms Dub to Khanpora

    S No Particulars

    Source of

    Material

    Qty in

    Unit of

    QtyDensity

    in t/cum

    Milage

    in

    Km

    Haulage

    /Loading

    Unloading

    Rate

    Unit of

    Haulage/Lo

    ading

    Unloading

    Amount

    in

    Rs

    Carriage / Loading Unloading Chart

    Loading (by manual means) 1 per pipe 60.94 per pipe 60.94

    Unloading (by Manual means)1 per pipe 290.01 per pipe 290.01

    Total 391.33

    Assistant Executive Engineer

    PMGSY,(JKRRDA) SD Ganderbal PMGSY (JKRRDA) Division Ganderbal

    Executive Engineer

  • 7/30/2019 PAVEMENT DESIGN OF HIGHWAY IN KASHMIR.

    34/34

    Road Length= 7.80 Kms

    District :Srinagar ( Ganderbal)

    S.No. Item Unit Qty. Rate of

    items

    incl

    carriage(R

    s)

    Total

    Amount

    in Lacs.

    1 RCC KM Stone Nos 8.00 1600.00 0.13

    2 Const. of Reference Pillars Kms 7.80 5000.00 0.39

    3 Const. of Back Pillars Kms 7.80 5500.00 0.43

    4 P/Fixing of Citizen information Boards Nos 2.00 16000.00 0.32

    5 Fixing of Two Km Sign boards Nos 4.00 7000.00 0.28

    6 Provision for Traffic Sign Boards as per clause

    1701.2.3 & IRC :67

    Nos 25.00 5000.00 1.25

    2.80

    Assistant Executive Engineer Executive Engineer

    PMGSY, SD Ganderbal PMGSY Division Bandipora

    Total =

    Construction of Akhal to Hayan

    Block:- Kangan

    Pradhan Mantri Gram Sadak Yojana ( PMGSY)

    Cost Estimate for Road Furniture.

    Package No: