Management of legacy control systems

PaulStewart,AutomationandControlforEnergyConference,May2011

Marathon Integrated Oil and Gas Company overviewUpstream OilandGasExploration OilandGasproduction Oilsandsmining LNG Shalegas Downstream Refining Marketing Transportation Distribution2

World wide operations

3

Brae area infrastructure

4

Brae Alpha - 1984Photo

5

Brae Bravo - 1987Photo

6

East Brae - 1993Photo

7

Typical control systems on an Oil and Gas InstallationESD SafetyInstrumentedFunctionlogicsolvers F&G DCS MCS SCADA GasTurbinecontrolsystems Machinerycontrol,sequencelogic Machineryprotection,vibrationmonitoring CompressorAntiSurgeprotection FlowMetering

8

legacy control systemLegacy fromthepast Asystemwhosedevelopmentiscomplete Acontrolsystemwhichisnotacurrentproduct

9

ObsoleteAproductorsystemisconsideredobsolescentwhenanendoflifedatehas beenannounced Aproductorsystemisconsideredobsoleteonceitisnolongeravailablefrom theoriginalmanufacturer,eventhoughpartsorcomponentsmaystillbe the original manufacturer, even though parts or components may still be availableinthesupplychain Obsolescenceisinevitableandrequireseffectivemanagementtoreducethe businessimpact Ineffectiveobsolescencemanagementcanresultindifficultyobtainingspares orsupport

10

StandardsIEC62402:2007(BSEN62402)ObsolescenceManagement Applicationguide Givesguidanceonestablishingaframeworkforobsolescencemanagement Coversthefollowingareas: Designofnewproducts Newtechnologyinsertionintoexistingproducts Supportandmaintenanceoflegacyproducts

11

Reasons for keeping legacy systemsThesystemworkssatisfactorilyanditisthereforedifficulttojustify replacement. Thecostsofredesigningorreplacingthesystemareprohibitivebecauseitis largeand/orcomplex. large and/or complex. Thesystemrequirescloseto100percentavailability,soitcannotbetakenout ofservicewithoutasignificantimpactonproduction. Thewaythatthesystemworksisnotwellunderstood.Thisiscommonon legacysystemswhereitislikelythattheoriginaldesignersofthesystemhave lefttheorganisationandthesystemdesignhaseithernotbeenfully documentedordocumentationhasbeenlost.

12

Reasons for replacing a legacy control systemThesystemisunreliable. ThesystemisunsupportableeitherbytheOEMoraftermarketservice providers. Theinstallationhasaremaininglifewhichissufficientlylongtomakeit h i ll i h i i lif hi h i ffi i l l k i unlikelythatobsolescencecanbeovercomewithoutreplacementofthe system.

13

Obsolescence management processEffectivemanagementofobsolescenceisessentialtoensureanoptimum balancebetweenreliability,availabilityandcostefficiency.

Identify Criticalcontrolsystemsareassessedtoidentifyobsolescenceissues Mitigate Selectandimplementthemostappropriateobsolescencestrategy foreachsystem. Monitor Carryoutperiodicreassessments,monitoreffectivenessofstrategy

14

IdentifyControlSystemsareassessedtoidentifyanyobsolescenceissues Hardware,software,documentation,supportcontractsandcompetencyshall beassessedwithrespecttoobsolescence Anoverallassessmentiscarriedoutforeachsystembasedonaqualitative A ll i i d f h b d li i approachusingariskmatrixandshalltakeintoaccountprobabilityand severityofobsolescence.Ariskcategoryoflow,medorhighshallbeassigned toeachsystem

15

Risk Matrix

16

Mitigation strategiesAreactiveorproactiveobsolescencestrategyshallbeselectedforeachofthe controlsystems Unlikelythatonesolutionwillbeapplicabletoallsystems,likelytobea combinationofsolutionsacrossaninstallationdependingonrisktothe combination of solutions across an installation depending on risk to the business,cost,wherethesystemisinitslifecycle.replacement, migration/upgradeandlifeextension

17

Reactive obsolescence strategyDonothinguntiltheneedarises Suitableonlywhereimpactonsafety,environmentorbusinessislow Thisisapositivedecisiontodonothing Recoveryoptions: ProductsearchbycontactingOEM,aftermarketsuppliers,contactswithinthe industry(otherOilandGasOperators) Repairbyspecialistelectronicrepairers Cannibalisationfromredundantequipment Cannibalisation from redundant equipment

18

Proactive obsolescence strategiesReplacement Migration Upgrade broughtuptodatebyreplacementofobsoleteitems. Lifeextensionofexistingequipment

19

MonitorTheobsolescenceassessmentsoncriticalinstrumentationandcontrolsystems isrepeatedperiodically Activedialogwithmanufacturersandsupplierstoestablishendoflifedates forsystems for systems Monitorobsolescencestrategyforeffectiveness

20

Life extension

TheServiceLifeExtensionProgram(SLEP),wasdevelopedinthe1980sto The Service Life Extension Program (SLEP), was developed in the 1980s to extendtheservicelifeoftheUSNavysaircraftcarriers.Theconcept subsequentlyexpandedtoalloftheUSNavyslifeextensionprogramsfor ships,aircraft,andcombatsystemsincludingtheNASASpaceShuttleprogram SLEPconsidersfactorsincludingsafety,reliability,supportability,performance, andcostreduction21

Life extensionRevieweachofthefollowingareastounderstandwhatisrequiredtoextendthe lifeofthesystem Hardware Software Suppliermanagement Training Technicalsupport documentation

22

HardwareLifetimebuyfromOEM Aftermarketresellers Repair Reverseengineer

23

SoftwareBackups Abilitytomodifysoftware Softwareemulatortoovercomeobsoletesoftwareorhardware Wellconstructedandannotatedcodetoenablereverseengineering

24

Spares ManagementClearsparesmanagementstrategy Accuratebillofmaterials Onsitespares Offsitespares Periodictestingofstoredsparestoensuretheyareserviceable

25

CompetencySuitablytrainedandexperiencedstaffonsite. Mixtureofformaltraining,mentoringandhandsonexperiencetobuildupa skillsset. AgeingworkforceintheUKOilIndustry,skillsretentionisimportant A i kf i h UK Oil I d kill i i i

26

DocumentationUptodateOperationandTrainingmanuals Maintenancemanuals Asbuiltdrawings MaybeanopportunitytoobtaindesigninfoforendoflifeproductsfromOEM

27

Supplier Management Contract award and structureSolesourceortender? Goodqualitycontractstructure CRINE,LOGICstandardcontracts Contractsmustcomplywithcorporatestandards,EUprocurementregulations, OilandGasUKsupplychaincodeofconduct. Oil d G UK l h i d f d Marketconditions wheredoesthebalanceofpowerrest?

28

Supplier Management Managing PerformanceSupplierandPurchaserfeedbackthroughFPALprocess. UseofKPIs,metrics,penaltyclausesandbonusstructure Holdperiodicreviewmeetings Buildaneffectiveworkingrelationshipwithkeysuppliers

29

Compressor Vibration and Temperature control upgradeOriginalCMLsystem

30

Compressor Vibration and Temperature control upgradeReplacementRockwellXMsystemwithPanelview

31

LM5000 gas turbine control systemReplacementcontrolsystematFAT

32

DCS migration

33

East Brae metering systemOEMmigrationpathenabledreplacementofflowstreammicrocomputers withnewgenerationmicros

34

East Brae metering system

35