Agenda 1. Introductions 2.New Regulated Market SoR Process 3.Standard Interconect Agreement Review 4. Service Level Commitments 5.A.O.B 6.Next Steps 7.Date of Next meeting
Paul Hanson
Wholesale Markets
Regulated SoR Process
Contents
Outline new regulated SoR process
BT Guidelines to meet requirements
Comments on Guidelines
General Discussion
Key Points from New Requirements
Requests for information to formulate SoR.
Respond to SoR in 15 days as follows:-Confirm will make an make initial offerFeasibility required to assessSoR not sufficiently well formulated. Defects
highlightedRejected with reasons for rejection
If agree to provide initial offer, provide within 35 days
If feasibility required, provide offer or rejection in 60 days
Can extend to 85 days or beyond for complex cases
Extended timescales if need for feasibility not initially identified
Provide voluntary KPIs on performance
BT Guidelines
New Services Manual Updated to meet regulatory obligations
Contains:-
Standards Forms for SoR Requests and Requests for Information to prepare SoR
Regulated Process & Timescales
Format of voluntary KPIs reports
Publication Timetable
19th December Draft Circulated to Industry
14th January Comments Received from industry
20th January Discussion of draft & comments
28th January Published to meet regulatory requirement
Comments
Amendments to align with Ofcom wording
Templates
KPI Reporting Proposals
Response to Information Requests
Simplified outline of process.
Change to T&C from initial offer
Inclusion in agreement
Review of Process
B2.1.3.3.3 the request is insufficient for proper consideration, detailing the insufficiencies; and offering to discuss constructively the content of the request: or
B2.1.3.3.4 the request is refused on the basis that it is not
reasonable, detailing the reasons for refusal B 2.1.3.7 If the Requested Party has responded in accordance
with paragraph B2.1.3.3.1, and due to a genuine error of fact, subsequently discovers that a feasibility study is reasonably required, not later than 35 Working Days after receipt by the Requested Party of the statement of requirements, the Requested Party shall so inform the Requesting Party in writing, stating the nature of the error and giving the reason for such study. Subject to paragraph B2.1.3.8, not later than 45 Working Days after giving such notice the Requested Party shall respond in writing:
B2.1.3.9 If a request has been found to be insufficient for proper
consideration by the Requested Party under paragraph B 2.1.3.3.3, or rejected by the Requested Party under paragraphs B2.1.3.3.4, B2.1.3.5.2 or B2.1.3.7.2, and the Requesting Party re-submits that request such resubmitted request shall be considered as a new request for the purposes of this paragraph B2.1.3.
NSM Amendments
NSM Amendments
Revised versions of B2.1.3.7.2 and Paragraph B2.1.3.5.2 below. that the request is refused, detailing the reasons for refusal, and providing to the Requesting Party a copy of the feasibility study, taking account of reasonable confidentiality requirements. The Requested Party shall have the right to reasonably disclose such copy to third parties subject to equivalent confidentiality requirements, provided that the Requested Party shall not identify the Requesting Party. A copy identifying the requestor and which does not contain confidentiality exclusions will be provided by BT to Ofcom. Template B Q 2 A written description of the product or service. Where relevant, this should include references to appropriate industry standards (E.G. ETSI, ITU) as well as any relevant BT SIN or other BT specifications on which the new service is based.
Report 1 – Response to Request for Information pre-submission of SoR.
Provision/Rejection within 15 days
Provision/Rejection greater 15 days
Report 2 - Response to Initial SoR
Response within 15 days
Response Greater than 15 days
Rejection
Request not sufficiently formulated
•Initial offer to be prepared
Feasibility required
KPIs
KPIs
Report 3 Preparation of Initial Offer without Feasibility
Initial Offer made within 35 days
Initial Offer exceeds 35 days
Report 4 Initial Offer /Rejection following Feasibility Study
Response within 60 days
Response 61 – 85 days
Response exceeds 85 days
Rejection
Initial Offer Made
Comments not Addressed by NSM Amendments
Templates
Forecasting Combine Template A & B
Response to Information Requests
Simplified outline of process.
Change to T&C from initial offer
Inclusion in agreement
Review of Process