31
Patrick O’Neill, Foreshore Unit, Department of the Environment, Community and Local Government, Newtown Road, Wexford. 24 th March 2015 Your ref. FS006446 Re: Application for a foreshore license for geotechnical and environmental investigation of the proposed survey route for feasibility studies by EirGrid and Rté (Réseau de transport d’électricité) for the Celtic Interconnector. Dear Patrick, With reference to your email of 19 th February 2015, please find enclosed EirGrids response to the public submissions received on foot of the public consultation to the above referenced foreshore licence application. If you have any further questions relating to this application then please do not hesitate to contact me. Yours sincerely, _____________________ Eoghan Tuite Project Engineer, Grid Development EirGrid plc

Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Patrick O’Neill,

Foreshore Unit,

Department of the Environment, Community and Local Government,

Newtown Road,

Wexford.

24th

March 2015

Your ref. FS006446

Re: Application for a foreshore license for geotechnical and environmental investigation

of the proposed survey route for feasibility studies by EirGrid and Rté (Réseau de

transport d’électricité) for the Celtic Interconnector.

Dear Patrick,

With reference to your email of 19th

February 2015, please find enclosed EirGrid’s response

to the public submissions received on foot of the public consultation to the above referenced

foreshore licence application.

If you have any further questions relating to this application then please do not hesitate to

contact me.

Yours sincerely,

_____________________

Eoghan Tuite

Project Engineer, Grid Development

EirGrid plc

Page 2: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Submission 1 Anonymous

Interconnector not needed

EirGrid has a statutory obligation to explore options for interconnection between Ireland and

other countries. Further interconnection includes many potential benefits, including

integration of electricity markets, security of supply and reduction in electricity prices for

consumers. On this occasion, EirGrid and Rté have conducted initial joint studies which

indicate that an interconnector between Ireland and France could be beneficial for electricity

customers in Ireland and France.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Damages to beaches

There will be no permanent or significant impact on the beach, though survey equipment and

personnel will be present on the beach for a short duration (approximately 7 days). It is

possible that the work will cause localised disturbance to beach users and may be a minor

inconvenience. Given the short duration of these works and the restricted survey area it is not

anticipated that the disturbance will be significant.

---

Submission 2 Ballymacoda Ladysbridge community council

Weakened coastline

The equipment that will be used for the geotechnical testing on the beach in Ireland is very

unlikely to have any long term influence on the beaches. A small track-mounted rig will be

used (tracking width 1m, tracking length 4.5m, height, 2.1m, working width 2m, working

height 4.5m) for the intertidal boreholes which is self-propelled and has a very low bearing

pressure on the ground. If a support vehicle is required it is likely to be a standard 4x4. The

contractor will drill a water lubricated 5m borehole which typically has a diameter of about

10cm and will naturally backfill on the following tide. Any impacts to the beach from drilling

are therefore anticipated to be negligible.

Impact to wildlife/Environment on the beach

The potential impacts of the geotechnical and environmental survey works on the Ballycotton

Bay SPA have been assessed in the supporting document (attachment A of the foreshore

application) and in the Screening for Appropriate Assessment (attachment E of the foreshore

application). Both assessments found there are no significant impacts anticipated from the

proposed survey works. The designated birds from the Ballycotton Bay SPA are

overwintering waders and waterfowl which are shore birds. Given the survey at Ballinwilling

is outside the SPA and is planned to take place in spring/summer any interactions between

Page 3: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

these birds and the survey works are likely to be minimal. At each landfall the intertidal

works will involve: drilling a maximum of 2 boreholes (10cm diameter, maximum of 5m

depth) which will naturally backfill on the following tide and 3 trial pits (each 3m x 1m)

which will be dug by an excavator, logged and backfilled within an hour. Any survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are unlikely to have any impact on natural streams running from land to the beach.

Impact on beach car park

It is not envisaged that the proposed survey will have any impact on the car park in the

survey area.

Connection to the National Grid

Though no decision has yet been made on whether or not to proceed with the Celtic

Interconnector, previous studies identified two substations on the transmission system which

would be capable of accommodating the connection of an interconnector and which would be

geographically closest to the south coast. These are Knockraha in Co. Cork and Great Island

in Co. Wexford.

Lack of consultation with local stakeholders

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation of all aspects of the project, including the landfall route. Interested parties

will be encouraged to provide their views, which will influence how we move forward on

each stage of the project.

Results of the 2014 geophysical survey available

An information document based on the 2014 geophysical survey can be made available on

request.

Page 4: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Local national school to be informed of the survey

We will consider any requests from local schools to present the findings from our studies in

an appropriate, student-friendly format.

---

Submission 3 Owners of the Garryvoe Hotel and the Bayview Hotel

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys

Impact on Tourism

The survey works are of a very short duration, comprising approximately 7 days on

Ballinwilling Beach and 7 days on Ballycroneen Beach. It is not envisaged that the proposed

survey will have any impact on tourism in the survey area.

---

Submission 4 Ballymacoda Ladysbridge Community Council

Impact on Tourism

The survey works are of a very short duration, comprising approximately 7 days on

Ballinwilling Beach and 7 days on Ballycroneen Beach. It is not envisaged that the proposed

survey will have any impact on tourism in the survey area.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Impact on Fishing/Angling

It is not anticipated that there will be any impact on the fishing industry as a result of these

surveys. The execution of the proposed offshore surveys will increase the volume of shipping

traffic by a negligible amount. Therefore there will be no additional navigational safety

implications. However, established marine navigation practices will be adhered to and

maintained by the survey vessels involved. Consultation with representative bodies and issue

of advice notices will ensure minimum effect on all parties. Well established marine survey

activity procedures will be followed for the survey works. These will include:

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

Page 5: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

It is emphasised that this foreshore application is for survey works only and designed to

inform the feasibility of the route options. Potential impacts of the installation and operation

of the proposed Celtic Interconnector cable would be assessed within an Environmental

Impact Assessment only if the project moved beyond the feasibility stage. Both The Sea

Fisheries Protection Agency and Inland Fisheries Ireland have been of part of the

consultation process.

Weakened coastline

The equipment that will be used for the geotechnical testing on the beach in Ireland is very

unlikely to have any long term influence on the beaches. A small track-mounted rig will be

used (tracking width 1m, tracking length 4.5m, height, 2.1m, working width 2m, working

height 4.5m) for the intertidal boreholes which is self-propelled and has a very low bearing

pressure on the ground. If a support vehicle is required it is likely to be a standard 4x4. The

contractor will drill a water lubricated 5m borehole which typically has a diameter of about

10cm and will naturally backfill on the following tide. Any impacts to the beach from drilling

are therefore anticipated to be negligible.

Damage to beaches

There will be no significant impact on the beach, though survey equipment and personnel

will be present on the beach for a short duration (approximately 7 days). It is possible that the

work will cause localised disturbance to beach users and may be a minor inconvenience.

Given the short duration of these works and the restricted survey area it is not anticipated that

the disturbance will be significant.

Converter station location

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

---

Submission 5 Board of Management of Ballycroneen N.S.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Page 6: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Contribution to national school

We are open to receiving applications for sponsorship, and we regularly consider sponsorship

requests from local and national organisations. All applications will be considered on their

merits, and in line with our corporate sponsorship policy.

---

Submission 6 Anonymous

As the issues raised in this submission do not relate to the specific subject of our application

we have no response to make at this time. Should a decision be made to proceed with the

Celtic Interconnector, we will carry out a full public consultation of all aspects of the project,

including the landfall route. Interested parties will be encouraged to provide their views,

which will influence how we move forward on each stage of the project.

---

Submission 7 Anonymous (for the 4 families residing next to Ballycroneen strand)

Impacts on local marine environment and terrestrial environment

The works undertaken during the offshore survey works will cause minimal disturbance to

the offshore marine environment. The vessel used for the offshore works will only

occasionally use its anchor, causing little direct interference to the surrounding marine

environment. In addition we would like to draw your attention to the Stage 1 Screening for

Appropriate Assessment which has been provided under section E of the application and the

Marine Mammal Risk Assessment, provided under section F of the application.

At each landfall the intertidal survey works will involve drilling a maximum of 2 boreholes

(10cm diameter, maximum of 5m depth) which will naturally backfill on the following tide

and 3 trial pits (each 3m x 1m) which will be dug by an excavator, logged and backfilled

within an hour. The equipment will be driven onto the beach via public access points. Survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are very unlikely to impact livestock, local dwellings and roadway infrastructure.

Lack of consultation with locals / More information required

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

Page 7: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation of all aspects of the project, including the landfall route. Interested parties

will be encouraged to provide their views, which will influence how we move forward on

each stage of the project.

Impact on car park and public access

It is not envisaged that the proposed survey will have any impact on the car park in the

survey area.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Substation location:

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Consultation with local fishermen

It is not anticipated that there will be any impact on the fishing industry as a result of these

surveys. As part of the public consultation on our current foreshore application, we reached

out to Ballycotton Angling Club and The Irish South & West Fish Producers Org. Ltd.

Additionally, a fishing liaison officer will be provided by the project as support to inform

fisherman of the survey works, vessel movement and ensure all relevant notices are post in

advance of the survey works.

---

Page 8: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Submission 8 Anonymous

Weakened coastline

The equipment that will be used for the geotechnical testing on the beach in Ireland is very

unlikely to have any long term influence on the beaches. A small track-mounted rig will be

used (tracking width 1m, tracking length 4.5m, height, 2.1m, working width 2m, working

height 4.5m) for the intertidal boreholes which is self-propelled and has a very low bearing

pressure on the ground. If a support vehicle is required it is likely to be a standard 4x4. The

contractor will drill a water lubricated 5m borehole which typically has a diameter of about

10cm and will naturally backfill on the following tide. Any impacts to the beach from drilling

are therefore anticipated to be negligible.

Impact on the beach

The potential impacts of the geotechnical and environmental survey works on the Ballycotton

Bay SPA have been assessed in the supporting document (attachment A of the foreshore

application) and in the Screening for Appropriate Assessment (attachment E of the foreshore

application). Both assessments found there are no significant impacts anticipated from the

proposed survey works. The designated birds from the Ballycotton Bay SPA are

overwintering waders and waterfowl which are shore birds. Given the survey at Ballinwilling

is outside the SPA and is planned to take place in spring/summer any interactions between

these birds and the survey works are likely to be minimal. At each landfall the intertidal

works will involve drilling a maximum of 2 boreholes (10cm diameter, maximum of 5m

depth) which will naturally backfill on the following tide and 3 trial pits (each 3m x 1m)

which will be dug by an excavator, logged and backfilled within an hour. Any survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are unlikely to have any impact on natural streams running from land to the beach.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid’s policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

Page 9: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

Pipes Onshore

No physical infrastructure will be constructed anywhere as part of these survey works.

---

Submission 9 Adriana Hegarty (On behalf of Ballycroneen coastal Alliance)

Couldn't view application at Garda Station

A copy of the application, and the relevant maps, plans, report and drawings, was available

for inspection for 21 working days from 16th

January until 12th

February 2015, at Middleton

Garda Station, Middleton, Co. Cork. The application was stamped by the Gardaí on the date

of submission (16th

January) and withdrawal (12th

February). The stamped foreshore licence

application has been forwarded to DECLG as part of the application process.

More information required

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation of all aspects of the project, including the landfall route. Interested parties

will be encouraged to provide their views, which will influence how we move forward on

each stage of the project.

---

Page 10: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Submission 10 Anonymous (Resident of the community of Ballycroneen)

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid’s policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Substation location

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

Page 11: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 11 Knockraha Community Association Ltd

Ballycotton Bay SPA

The potential impacts of the geotechnical and environmental survey works on the Ballycotton

Bay SPA have been assessed in the supporting document (attachment A of the foreshore

application) and in the Screening for Appropriate Assessment (attachment E of the foreshore

application). Both assessments found there are no significant impacts anticipated from the

proposed survey works. The designated birds from the Ballycotton Bay SPA are

overwintering waders and waterfowl which are shore birds. Given the survey at Ballinwilling

is outside the SPA and is planned to take place in spring/summer any interactions between

these birds and the survey works are likely to be minimal. The survey vessel will operate

under international standards (MARPOL) with respect to black and grey waste water and

food waste discharges, which are designed to eliminate impacts to coastal waters, and reduce

the levels of discharge in offshore waters. Any waste arising from geotechnical and

environmental sediment sampling will be disposed of in a licensed facility. The geotechnical

and environmental marine surveys will involve the removal of a limited number of core and

sediment grab samples, both of which will disturb a discrete and very limited area of the

seabed.

Discharge of grey water/sediment disturbances

There will be no disposal of grey water from the survey vessel, as all survey vessels will have

holding tanks for grey water.

Converter station location

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Inadequate Public Consultation / Main landfall route chosen without public consultation

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation of all aspects of the project, including the landfall route. Interested parties

will be encouraged to provide their views, which will influence how we move forward on

each stage of the project.

Page 12: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

The public notice was placed in one national newspaper (The Examiner) and one regional

newspaper (The Southern Star). These placements were not the decision of EirGrid, but

rather were requested as part of the application process by Department of the Environment,

Community & Local Government (DECLG).

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 12 Anonymous (Resident of the community of Ballycotton)

Impacts on Fishing Industry and Tourism

The execution of the proposed offshore surveys will increase the volume of shipping traffic

by a negligible amount. Therefore there will be no additional navigational safety

implications. However, established marine navigation practices will be adhered to and

maintained by the survey vessels involved. Consultation with representative bodies and issue

of advice notices will ensure minimum effect on all parties. Well established marine survey

activity procedures will be followed for the survey works. These will include:

Page 13: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

It is emphasised that this foreshore application is for survey works only, designed to inform

the feasibility of the route options. Potential impacts of the installation and operation of the

proposed Celtic Interconnector cable would be assessed within an Environmental Impact

Assessment only if the project moved beyond the feasibility stage.

Lack of consultation with locals

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation on all aspects of the project, including the landfall route. Interested

parties will be encouraged to provide their views, which will influence how we move

forward on each stage of the project.

Converter station location

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Impact on the beach

The potential impacts of the geotechnical and environmental survey works on the Ballycotton

Bay SPA have been assessed in the supporting document (attachment A of the foreshore

application) and in the Screening for Appropriate Assessment (attachment E of the foreshore

application). Both assessments found there are no significant impacts anticipated from the

proposed survey works. The designated birds from the Ballycotton Bay SPA are

overwintering waders and waterfowl which are shore birds. Given the survey at Ballinwilling

Page 14: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

is outside the SPA and is planned to take place in spring/summer any interactions between

these birds and the survey works are likely to be minimal. At each landfall the intertidal

works will involve: drilling a maximum of 2 boreholes (10cm diameter, maximum of 5m

depth) which will naturally backfill on the following tide and 3 trial pits (each 3m x 1m)

which will be dug by an excavator, logged and backfilled within an hour. Any survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are unlikely to have any impact on natural streams running from land to the beach.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

Page 15: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 13 Anonymous (Resident of the community of Ballycotton)

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Converter stations

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Impacts on Fishing Industry and Tourism

The execution of the proposed offshore surveys will increase the volume of shipping traffic

by a negligible amount. Therefore there will be no additional navigational safety

implications. However, established marine navigation practices will be adhered to and

maintained by the survey vessels involved. Consultation with representative bodies and issue

of advice notices will ensure minimum effect on all parties. Well established marine survey

activity procedures will be followed for the survey works. These will include:

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

It is emphasised that this foreshore application is for survey works only, designed to inform

the feasibility of the route options. Potential impacts of the installation and operation of the

proposed Celtic Interconnector cable would be assessed within an Environmental Impact

Assessment only if the project moved beyond the feasibility stage.

Page 16: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impacts

There will be no permanent visual impact as a result of these surveys.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 14 Ballycotton shop and Post office owner

Impacts on Fishing Industry and Tourism

The execution of the proposed offshore surveys will increase the volume of shipping traffic

by a negligible amount. Therefore there will be no additional navigational safety

implications. However, established marine navigation practices will be adhered to and

maintained by the survey vessels involved. Consultation with representative bodies and issue

of advice notices will ensure minimum effect on all parties. Well established marine survey

activity procedures will be followed for the survey works. These will include:

Page 17: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

It is emphasised that this foreshore application is for survey works only, designed to inform

the feasibility of the route options. Potential impacts of the installation and operation of the

proposed Celtic Interconnector cable would be assessed within an Environmental Impact

Assessment only if the project moved beyond the feasibility stage.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impacts

There will be no permanent visual impact as a result of these surveys.

---

Submission 15 Anonymous (Resident near Ballycroneen Strand)

Further information required/Lack of consultation with locals/No direct communication with

locals during August-September 2014 Survey

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation on all aspects of the project, including the landfall route. Interested

parties will be encouraged to provide their views, which will influence how we move

forward on each stage of the project.

Impact to wildlife/Environment on the beach

The intertidal survey areas do not overlap with any areas protected for wildlife. Although

Ballycotton Bay SPA, is close to the Ballinwilling Strand intertidal survey area, the SPA is

Page 18: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

protected for over wintering waders and waterfowl which are shore birds. Since the survey is

planned to take place in the spring/summer any interaction between the birds and the survey

works are likely to be minimal. At each landfall the intertidal works will involve: drilling a

maximum of 2 boreholes (10cm diameter, maximum of 5m depth) which will naturally

backfill on the following tide and 3 trial pits (each 3m x 1m) which will be dug by an

excavator, logged and backfilled within an hour. Any survey equipment and personnel will

be present on the beach for a short duration (approximately 7 days) and are unlikely to have

any impact on natural streams running from land to the beach.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Impact on car park foreshore

It is not envisaged that the proposed survey will have any impact on the car park in the

survey area.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Location of substations

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Public access

It is not envisaged that there will be any impact on public access to the beach during the

proposed survey.

Damages to beaches

There will be no significant impact on the beach, though survey equipment and personnel

will be present on the beach for a short duration (approximately 7 days). It is possible that the

work will cause localised disturbance to beach users and may be a minor inconvenience.

Given the short duration of these works and the restricted survey area it is not anticipated that

the disturbance will be significant.

Page 19: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Visual impact

There will be no permanent visual impact as a result of these surveys.

---

Submission 16 Scoil reality an Mara, Ballycotton, Parents council

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Damages to beaches

There will be no significant impact on the beach, though survey equipment and personnel

will be present on the beach for a short duration (approximately 7 days). It is possible that the

work will cause localised disturbance to beach users and may be a minor inconvenience.

Given the short duration of these works and the restricted survey area it is not anticipated that

the disturbance will be significant.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Impacts on Fishing Industry and Tourism

The execution of the proposed offshore surveys will increase the volume of shipping traffic

by a negligible amount. Therefore there will be no additional navigational safety

implications. However, established marine navigation practices will be adhered to and

maintained by the survey vessels involved. Consultation with representative bodies and issue

of advice notices will ensure minimum effect on all parties. Well established marine survey

activity procedures will be followed for the survey works. These will include:

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

It is emphasised that this foreshore application is for survey works only, designed to inform

the feasibility of the route options. Potential impacts of the installation and operation of the

Page 20: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

proposed Celtic Interconnector cable would be assessed within an Environmental Impact

Assessment only if the project moved beyond the feasibility stage.

Request updates

A dedicated webpage has been established with further information on the Celtic

Interconnector. This is available at www.eirgid.com. If members of the public would like

further information, they can email [email protected], call +353 (0)1 702

6642 or send a letter to c/o Celtic Interconnector Project Manager, EirGrid Plc, The Oval,

160 Shelbourne Road, Ballsbridge, Dublin 4.

---

Submission 17 Anonymous

Visual impact

There will be no permanent visual impact as a result of these surveys.

Impacts on local marine environment and terrestrial environment

The works undertaken during the offshore survey works will cause minimal disturbance to

the offshore marine environment. The vessel used for the offshore works will only

occasionally use its anchor, causing little direct interference to the surrounding marine

environment. In addition we would like to draw your attention to the Stage 1 Screening for

Appropriate Assessment which has been provided under section E of the application and the

Marine Mammal Risk Assessment, provided under section F of the application.

At each landfall the intertidal survey works will involve drilling a maximum of 2 boreholes

(10cm diameter, maximum of 5m depth) which will naturally backfill on the following tide

and 3 trial pits (each 3m x 1m) which will be dug by an excavator, logged and backfilled

within an hour. The equipment will be driven onto the beach via public access points. Survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are very unlikely to impact livestock, local dwellings and roadway infrastructure.

Impact on Tourism

It is not envisaged that the proposed survey will have any impact on tourism in the survey

area.

---

Page 21: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Submission 18 Anonymous

Damages to beaches

There will be no significant impact on the beach, though survey equipment and personnel

will be present on the beach for a short duration (approximately 7 days). It is possible that the

work will cause localised disturbance to beach users and may be a minor inconvenience.

Given the short duration of these works and the restricted survey area it is not anticipated that

the disturbance will be significant.

Impact on Tourism

It is not envisaged that the proposed survey will have any impact on tourism in the survey

area.

Impact on Fishing/Angling/Agriculture

It is not anticipated that there will be any impact on the fishing and agricultural industries as

a result of these surveys. The execution of the proposed offshore surveys will increase the

volume of shipping traffic by a negligible amount. Therefore there will be no additional

navigational safety implications. However, established marine navigation practices will be

adhered to and maintained by the survey vessels involved. Consultation with representative

bodies and issue of advice notices will ensure minimum effect on all parties. Well

established marine survey activity procedures will be followed for the survey works. These

will include:

Notice to Mariners will be issued to the Marine Safety Directorate and local sailing

clubs informing them of the offshore survey works programme.

A Fisheries Liaison Officer will be appointed.

It is emphasised that this foreshore application is for survey works only, designed to inform

the feasibility of the route options. Potential impacts of the installation and operation of the

proposed Celtic Interconnector cable would be assessed within an Environmental Impact

Assessment only if the project moved beyond the feasibility stage.

---

Submission 19 Anonymous

Impacts on local marine environment and terrestrial environment

The works undertaken during the offshore survey works will cause minimal disturbance to

the offshore marine environment. The vessel used for the offshore works will only

occasionally use its anchor, causing little direct interference to the surrounding marine

environment. In addition we would like to draw your attention to the Stage 1 Screening for

Page 22: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Appropriate Assessment which has been provided under section E of the application and the

Marine Mammal Risk Assessment, provided under section F of the application.

At each landfall the intertidal survey works will involve drilling a maximum of 2 boreholes

(10cm diameter, maximum of 5m depth) which will naturally backfill on the following tide

and 3 trial pits (each 3m x 1m) which will be dug by an excavator, logged and backfilled

within an hour. The equipment will be driven onto the beach via public access points. Survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are very unlikely to impact livestock, local dwellings and roadway infrastructure.

Damages to beaches

There will be no significant impact on the beach, though survey equipment and personnel

will be present on the beach for a short duration (approximately 7 days). It is possible that the

work will cause localised disturbance to beach users and may be a minor inconvenience.

Given the short duration of these works and the restricted survey area it is not anticipated that

the disturbance will be significant.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

---

Submission 20 Anonymous

Location of substations

It is likely that a converter station would be constructed to connect the Celtic Interconnector

to the national grid, should the project proceed. As part of our feasibility study, Knockraha in

Cork and Great Island in Wexford are being evaluated as possible sites for a single converter

station where the interconnector would connect to the national grid.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Page 23: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission21 Anonymous (Resident of Cloyne, Co Cork)

HVDC Converter stations

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Page 24: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Impacts on local marine environment and terrestrial environment

The works undertaken during the offshore survey works will cause minimal disturbance to

the offshore marine environment. The vessel used for the offshore works will only

occasionally use its anchor, causing little direct interference to the surrounding marine

environment. In addition we would like to draw your attention to the Stage 1 Screening for

Appropriate Assessment which has been provided under section E of the application and the

Marine Mammal Risk Assessment, provided under section F of the application.

At each landfall the intertidal survey works will involve drilling a maximum of 2 boreholes

(10cm diameter, maximum of 5m depth) which will naturally backfill on the following tide

and 3 trial pits (each 3m x 1m) which will be dug by an excavator, logged and backfilled

within an hour. The equipment will be driven onto the beach via public access points. Survey

equipment and personnel will be present on the beach for a short duration (approximately 7

days) and are very unlikely to impact livestock, local dwellings and roadway infrastructure.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

Page 25: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 22 Anonymous (Resident of Ballycotton)

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Impact on Tourism

It is not envisaged that the proposed survey will have any impact on tourism in the survey

area.

---

Submission 23 Anonymous (Resident of Ballycroneen strand)

Lack of consultation with locals/Inadequate public consultation/More information required

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Page 26: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses. Should a decision be made to proceed with the Celtic

Interconnector, we will carry out a full public consultation on all aspects of the project,

including the landfall route. Interested parties will be encouraged to provide their views,

which will influence how we move forward on each stage of the project.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

HVDC Converter stations

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Health and safety

EirGrid regards the protection of the health, safety and welfare of its staff and the general

public as a core company value. It is EirGrid's policy to design and operate the transmission

network to the highest safety standards and to comply with the most up-to-date international

guidelines and recommendations. Currently, only feasibility studies are being undertaken. In

the event that the project proceeds, it will be fully assessed to ensure that any health and

safety or other risks are dealt with.

Impact on Tourism

It is not envisaged that the proposed survey will have any impact on tourism in the survey

area.

Impact on Agriculture

It is not envisaged that the proposed survey will have any impact on agriculture in the survey

area.

Page 27: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.

---

Submission 24 Anonymous

Inadequate public consultation

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

Page 28: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation on all aspects of the project, including the landfall route. Interested

parties will be encouraged to provide their views, which will influence how we move

forward on each stage of the project.

The public notice was placed in one national newspaper (The Examiner) and one regional

newspaper (The Southern Star). These placements were not the decision of EirGrid, but

rather were requested as part of the application process by Department of the Environment,

Community & Local Government (DECLG).

A copy of the application, and the relevant maps, plans, report and drawings, was available

for inspection for 21 working days from 16th

January until 12th

February 2015, at Middleton

Garda Station, Middleton, Co. Cork. The application was stamped by the Gardaí on the date

of submission (16th

January) and withdrawal (12th

February). The stamped foreshore licence

application has been forwarded to DECLG as part of the application process.

Foreshore application considered illegal as project splitting, should be carried out under 1

National Strategic Infrastructure Application/Cumulative effect of all projects (listed in

response) should be assessed together

The current application is for a foreshore licence to carry out survey works. No decision has

been made to proceed with the project as the project is currently only in feasibility stage. If

the project does proceed, it is anticipated that the project would comprise strategic

infrastructure development. Assessment of the cumulative impact of the project, were it to

proceed, would form part of any application for statutory consent to construct the project.

Surveys being carried out without cost benefit analysis of the project

It is not possible to determine what the costs and benefits of the project will be until surveys

are carried out.

Interconnectors extremely expensive and unreliable

The East-West Interconnector has provided for a net reduction in wholesale energy prices in

Ireland, providing a direct benefit to the electricity consumer. Further, the interconnector is

currently operating at close to 100% availability.

Ireland has enough energy/Import nuclear energy/Import dirty electricity with CO2 emissions

bills

The electricity we use in Ireland is sourced both locally and from imports over the two

existing interconnectors between Ireland and Britain. The fuel mix includes wind, tidal,

Page 29: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

biomass, hydropower, gas, coal and nuclear. As such, the Celtic Interconnector would draw

on the same sources to supply Ireland's electricity consumers.

Interconnector not needed/inefficient

EirGrid has a statutory obligation to explore options for interconnection between Ireland and

other countries. Further interconnections includes many potential benefits. On this occasion,

EirGrid and Rté have conducted initial joint studies which indicate that an interconnector

between the two countries could be beneficial for electricity customers in Ireland and France.

---

Submission 25 Anonymous

Inadequate public consultation/Lack of consultation with locals

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation of all aspects of the project, including the landfall route. Interested parties

will be encouraged to provide their views, which will influence how we move forward on

each stage of the project.

HVDC Converter stations

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Submission 26 Anonymous

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Visual impact

There will be no permanent visual impact as a result of these surveys.

Impact on countryside

It is not envisaged that the proposed survey will have any impact on the

countryside/landscape in the survey area.

---

Page 30: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Submission 27 Wayne Halloran (Cork Renewable Energy Group)

Require further information/Public Consultation

Public consultation was carried out before our summer 2014 marine surveys, and again in

January and February 2015 ahead of proposed marine surveys in spring 2015.

Local representatives (including County Councillors and TDs) in east Cork were contacted

ahead of the 2014 marine surveys. Over January and February 2015, we were in contact by

phone, email and post with over 40 stakeholders in east Cork, including public

representatives and community groups in the area. We also reached out to fishing, tourism

and business groups, and have been in touch with several local residents who have contacted

us.

It is envisaged that we will continue to develop a strong dialogue with the public as the

feasibility study progresses.

Should a decision be made to proceed with the Celtic Interconnector, we will carry out a full

public consultation on all aspects of the project, including the landfall route. Interested

parties will be encouraged to provide their views, which will influence how we move

forward on each stage of the project.

A dedicated webpage has been established with further information on the Celtic

Interconnector. This is available at www.eirgrid.com.

If members of the public would like further information, they can email

[email protected], call +353 (0)1 702 6642 or send a letter to c/o Celtic

Interconnector Project Manager, EirGrid Plc, The Oval, 160 Shelbourne Road, Ballsbridge,

Dublin 4.

Converter station location

It is likely that a converter station would be constructed to allow connection of the Celtic

Interconnector to the national grid, should the project proceed. As part of our feasibility

study, Knockraha in Cork and Great Island in Wexford are being evaluated as possible points

on the existing transmission system where the interconnector could connect to the national

grid.

Noise pollution from the converter stations

This is currently unknown, and will be assessed as part of the feasibility study. Ultimately,

were the interconnector to be constructed, it would be subject to relevant regulations and the

public planning process.

Page 31: Patrick O’Neill, Newtown Road, 24...Dear Patrick, With reference to your email of 19th February 2015, please find enclosed EirGrid’s response to the public submissions received

Erection of pylons

No pylons will be constructed anywhere as a result of these surveys.

Onshore route

In fulfilling our role as the state-owned electricity transmission system operator, EirGrid are

undertaking a joint feasibility study with our French counterparts, Rté, to investigate the

viability of an electricity interconnector between Ireland and France (the Celtic

Interconnector).

The Celtic Interconnector is at a very early stage and no decision has yet been made on

whether or not to proceed with the project. The feasibility study will help to inform this

decision, which will not be made until at least mid-2016.

An interconnection may include High Voltage Direct Current (HVDC) submarine power

cables for which EirGrid and Rté intend to carry out geophysical, environmental and

geotechnical surveys to determine whether such a connection is feasible. The geophysical

surveys were undertaken during the summer of 2014 with the geotechnical and

environmental surveys planned for this year in 2015. The surveys will provide a baseline

description of the seabed which could be used to inform future environmental reports.

We have carried out initial pre-feasibility desktop studies identifying a number of potential

landfall locations along the south coast of Ireland and the northwest coast of France. The

desktop studies also identified a number of possible submarine cable routes between the two

coastlines. These were assessed from a technical and environmental viewpoint and a feasible

survey corridor between the southeast Cork and northwest Brittany was identified as suitable

for further investigation. Two landfall areas that are currently being surveyed in Ireland are

Ballycroneen Beach and Ballinwilling Strand, if required other Irish landfall locations maybe

surveyed as part of further studies.