SAP Component: Project System Version: ECC 6.0 R/3

EHP 5.0

Partial Turn Key Scenario

Document on proposed Partial Turn Key Project as per the new guidance from MSEDCL

Page 2: Partial Turnkey Process Case1

Table of Contents1. Case 1. New process/stock available – Division /Circle.....................................................................3

1.1 Create project with partial turnkey profile....................................................................................3

1.2 Maintain material in T-code ZPS_HO_POMAT...............................................................................5

1.3 Maintain material in ZPS_MR_REQ................................................................................................5

1.4 Maintain centages amount and extra tax amount to project........................................................6

1.5 Budget allocation............................................................................................................................7

1.5.1 Copy total plan cost to TOP WBS t-code IM52...........................................................................7

1.5.2 Distribute Budget to each WBS.t-code CJ30...............................................................................7

1.5.3 Released budget t-code CJ32......................................................................................................8

1.6 Project released. T-code CJ20N...................................................................................................9

1.7 Material procurement process.................................................................................................10

1.7.1 Materials provided by MSEDCL.............................................................................................10

1.7.1.1 Stock in division /circle.............................................................................................................10

1.7.1.1.1 Create material requisition for MSEDCL materials T-code-ZMM_PROJECT_MR.................10

1.7.1.1.2 Approved MR T-code ZMM_PROJECT_MR_APPV................................................................12

1.7.1.1.3 Stock transfer – transfer material from plant storage to project storage location i.e vendor storage location T-code - ZMM_PR_STKTRF............................................................................................13

1.7.1.1.4 Gate pass – T-code - ZMM_PROJ_GATEPASS.......................................................................14

1.7.2 Materials provided by vendor T-code ZPS_PO.....................................................................16

1.7.3 Good Receipt - MRHO...........................................................................................................18

1.7.4 Stock view – MBBS................................................................................................................18

1.8 Creation of JMC.........................................................................................................................18

1.9 Creation of RABILL.....................................................................................................................19

1.10 Invoice creation T-code ZPS_INV..............................................................................................20

1.11 Invoice parking – zfi_project_invoice.......................................................................................21

1.11.1 Material parking....................................................................................................................21

1.11.2 Centages service service sheet..............................................................................................21

1.11.3 Centages invoice parking......................................................................................................22

Page 3: Partial Turnkey Process Case1

1. Case 1. New process/stock available – Division /Circle1.1 Create project with partial turnkey profile.

Here we have created three WBS, in which following are data maintains-

- In WBS IF-15-124.01Materials are supply by Vendor as well as MSEDCL.

- In WBS IF-15-124.02Materials are supply by MSEDCL

- In WBS IF-15-124.03Materials are supply by vendor only.

Page 4: Partial Turnkey Process Case1

Note : those materials which are supply by MSEDCL, only reservation are created i.e in procurement assignment WE is selected.

Maintain activity and item no for MSEDCL materials activity.

Note: if activity and item no is not maintain by user, then MSEDCL materials will be not shown while doing JMC

Page 5: Partial Turnkey Process Case1

1.2 Maintain material in T-code ZPS_HO_POMAT

Maintain project in ZPS_HO_POMAT.

Here we can edit unit price of materials which is provided by MSEDCL.

1.3 Maintain material in ZPS_MR_REQ

Here we maintain those materials which need to be generate material request.

Click on all materials as in this case, all materials need to generate material request.

Page 6: Partial Turnkey Process Case1

1.4 Maintain centages amount and extra tax amount to project

T-code- CJ40

Maintain centages amount to each WBS for those materials which are provide by MSEDCL.

If MR is require, do check (tick)

Page 7: Partial Turnkey Process Case1

1.5 Budget allocation.1.5.1 Copy total plan cost to TOP WBS t-code IM52.

1.5.2 Distribute Budget to each WBS.t-code CJ30.

Distribute budget to each wbs using select all, copy view, plan total.

Page 8: Partial Turnkey Process Case1

1.5.3 Released budget t-code CJ32.

Page 9: Partial Turnkey Process Case1

1.6 Project released. T-code CJ20N.

Released the project.

Note : PR will be created for Vendor procure materials.

Page 10: Partial Turnkey Process Case1

1.7 Material procurement process

In Partial turnkey process, there are two type of materials procure –

a) Materials provide by MSEDCLb) Materials provide by vendor

1.7.1 Materials provided by MSEDCL.

Note: In this case materials are in division/circle stock.

1.7.1.1 Stock in division /circle

1.7.1.1.1 Create material requisition for MSEDCL materials T-code-ZMM_PROJECT_MR

Note: Prior generating MR, user should check whether materials are in stock.If materials are in respective circle stock, then user should transfer circle stock to respective division.

Page 11: Partial Turnkey Process Case1

T-code MB52 for stock view with respective materials.

MR creation t-code ZMM_PROJECT_MR.

Enter supplying plant and supplying store.

Page 12: Partial Turnkey Process Case1

Click on save & print.

1.7.1.1.2 Approved MR T-code ZMM_PROJECT_MR_APPV

Enter MR number.

Page 13: Partial Turnkey Process Case1

1.7.1.1.3 Stock transfer – transfer material from plant storage to project storage location i.e vendor storage location T-code - ZMM_PR_STKTRF

Click on process

Page 14: Partial Turnkey Process Case1

1.7.1.1.4 Gate pass – T-code - ZMM_PROJ_GATEPASS.

Page 15: Partial Turnkey Process Case1

Print preview –

Page 16: Partial Turnkey Process Case1

Stock view – T-CODE MBBS

1.7.2 Materials provided by vendor T-code ZPS_PO

Note: Before PO creation, system will check, if ZPS_PO_HOMAT and ZPS_MR_REQ is maintained for MSEDCL materials.

Page 17: Partial Turnkey Process Case1

Materials PO-4630000571

Centages PO –4630000572

Note: this amount is calculated from materials provided by msedcl which is maintain ZPS_PO_HOMAT

Page 18: Partial Turnkey Process Case1

1.7.3 Good Receipt - MRHO

1.7.4 Stock view – MBBS

1.8 Creation of JMC

JMC Created with JMC number : IF-15-124-MJ0001

Page 19: Partial Turnkey Process Case1

Note: Here last two line item are material provided by MSEDCL.

1.9 Creation of RABILL

RABill Created with RABill number : IF-15-124-RA0001

Here last two materials are provided by MSEDCL which is not editable field.

Page 20: Partial Turnkey Process Case1

Note: RAbill amount is sum of materials provided by vendor only.

1.10 Invoice creation T-code ZPS_INV

Note :Here centages amount of those material which provided by MSEDCL is also included.

Page 21: Partial Turnkey Process Case1

Invoice has been Created with Invoice number : IF-15-124-IV0001

1.11 Invoice parking – zfi_project_invoice1.11.1Material parking

Document 5105601552 Has Been Parked.

1.11.2Centages service service sheet

Note: here service sheet will be created for both line item i.e for MSEDCL and vendor materials.

Page 22: Partial Turnkey Process Case1

1.11.3 Centages invoice parking

Document 5105601554 Has Been Parked