Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Part L of Building Regulations 2017-Buildings other than
Dwellings
Seán Armstrong,
Housing/Building Standards Section,
DHPCLG
Outline
• Implementing the Energy Performance of Buildings Directive and NZEB
– Dwellings
– Buildings other than Dwellings
• Next Steps
• Member states to ensure that all new buildings are “Nearly Zero Energy Buildings” by 31st Dec 2020
• Member states to ensure that all new buildings owned and occupied by Public Authorities are `Nearly Zero Energy Buildings’ after 31st Dec 2018
• Major Renovations to be at Cost Optimal Level in Building Codes .
Recommendations on NZEB issued by Commission in July 2016
• Member states should take account of “the period of validity of building permits, the length of construction and completion of building works” to avoid falling short of the NZEB target dates in the EPBD.
Energy Performance of Buildings Directive (EPBD) and NZEB
EPBD Definition- Nearly Zero Energy Building
‘nearly zero-energy building’ means a building that has a very high energy performance, as determined in accordance with Annex I. The nearly zero or very low amount of energy required should be covered to a very significant extent by energy from renewable sources, including energy from renewable sources produced on-site or nearby;
RTE PV Array
Implementation of NZEB-Dwellings
• SI 4 of 2017 has amended Building Regulations to include the definition of NZEB on 17th Jan 2017
• TGD L 2011-Dwellings has been amended to include numerical indicators for NZEB Dwellings on the 22nd Feb 2017. The numerical indicators provide MPEPC of 0.30 and MPCPC of 0.35 for dwellings completed after 31st Dec 2020.
• It is planned to complete full review of Part L for NZEB Dwellings and Major Renovations in 2018 to apply from 2019
Part L Development Dwellings
0
20
40
60
80
100
120
140
160
180
200
1991 2005 2007 2011 2018
kW
h/m
2/y
r 40%ImprovementBER=B1
60%ImprovementBER=A3
70%ImprovementBER=A2NZEB
BERD1/C3
BERC1
Implementation of EPBD-Buildings other than Dwellings• TGD L Buildings other than Dwellings
is currently under review to provide detailed NZEB guidance and include Major Renovations performance requirement:
– Public Consultation –Start March 24th 2017 –Finish Friday 26th May
– Final Publication-Oct 2017
– Application- planned for early 2019
– NEAP to be revised in parallel
• NZEB Interim Specification for Public buildings owned and occupied by Public Authorities issued 23rd Dec 2016 for buildings commencing design in early 2017
• Consultation with Stakeholders:– OPW,DES,HSE,SEAI, Construction Industry
Council (RIAI,SCS,EI,ACEI,CIF),CIBSE,
– Public Sector workshop approx. 200 attendees
Key Components of performance requirement TGD L Buildings other than Dwellings
• Provides an improvement in performance in the order of 60% over 2008 TGD L
• Improved Fabric Specification
• Advanced Services and Lighting specification
• Renewable Energy Ratio of 20% (flexibility of 10%)
.
Proposed Performance requirements for Buildings other than Dwellings Specification- Reference Building-Fabric
Parameter Current reference values-TGD L 2008
Reference values-TGD L Public Consultation
Total Floor Area and Building Volume
Same as actual building Same as actual building
Opening Areas Offices and Shops –windows and pedestrian doors are 40% of the total area of exposed walls
Offices and Shops –windows and pedestrian doors are 40% of the total area of exposed walls
Walls U=0.27 W/m2K U=0.18 W/m2K
Roofs U=0.16 W/m2K U=0.15 W/m2K
Floor U=0.25 W/m2K U=0.15 W/m2K
Thermal bridging Add 16% to fabric heat loss Actual Length of Key Junctions xAdvanced psi value
Air Permeability 10m3/(hr.m2) 5m3/(hr.m2) Floor area <250m2
3m3/(hr.m2) Floor area >250m2
Window U ValueSolar energy transmittance
2.2 W/(m2K)0.72
1.4 W/(m2K)0.40
ServicesParameter Current reference values-
TGD L 2008Proposed reference values-TGD L 2017/PublicSector Specification
Heating efficiency (heating and hot water)%
0.73 CoP 91% Gas Boiler
Cooling Seasonal Energy Efficiency Air conditioned buildingRatio (SEER)
SEER=1.67 SEER=4.5
Lighting divide the illuminanceby 100, then multiply by 3.75 W/m2 per 100 lux
65 lm/circuit watt
Occupancy Control Local Manual Switching Automated
Daylight Control Local Manual Switching Automated
Central Ventilation SFP 2 (W/(l/s)) 1.8 (W/(l/s))
Variable speed control of fans
No Yes
Renewable Energy Ratio None 20% using photovoltaics
• Renewables requirement will be included in TGD L Buildings other than Dwellings as Renewable Energy Ratio (RER)-20%
• The following represents a very significant level of energy provision from renewable energy technologies in order to satisfy Regulation L6 (b); -
– · Where the MPEPC of 1.0 and MPCPC of 1.15 is achieved an RER of 0.20 represents a very significant level of energy provision from renewable energy technologies
– · Where the MPEPC of 0.9 and MPCPC of 1.04 is achieved an RER of 0.10 represents a very significant level of energy provision from renewable energy technologies
• Renewable energy sources include Photovoltaics, Heat Pumps (Air source and ground source), Biomass, Solar Thermal ,Primary Energy Savings from Combined Heat and Power (CHP), Renewable district heating
TGD L Buildings other than Dwellings- Renewable Energy Ratio (RER)
Building typePrimary energy
CO2 emissions
Building Energy Rating
%Improveme
nt Energy
%Improvement C02 emissions
kWh/yr/m² kg/yr/m² Indicator BER % %
Office NV 2F: LMF 62.8 12.6 0.3 A2 65 65
Office AC 2F: LMF 100.1 20.7 0.5 A3 66 67
Office NV 4F: MC 60.1 12.1 0.3 A2 63 64Office AC 4F: MC - 98.6 20.5 0.5 A3 65 66
Office NV 4F: LMF 60.1 12.1 0.3 A2 63 64
Office AC 4F: LMF 98.6 20.5 0.5 A3 65 66
Hotel AC MC 348.1 65.3 0.5 B1 66 67
Retail AC LMF 178.3 38.2 0.4 A3 68 67
Mixed Use LMF 89.3 18.2 0.3 A2 69 60
School Prim. MC 57.6 11.2 0.4 A3 50 51
Proposed Energy and Carbon Dioxide emissions performance for NZEB Office Buildings
Minimum Performance Requirements-New Buildings
• Table 1- Backstop U-Values (W/m2K)-as per Dwellings –Pitched Roofs 0.16, Walls 0.21, Windows 1.6, Flat roofs 0.20
• Par 1.3.5.3 Overheating-Limiting Solar Gain(a) For every space that is defined in NEAP database as being side lit, the reference case is an east-facing façade with full width glazing to a height of 1.0m. having a framing factor of 10 per cent and a normal solar energy transmittance (g-value) of 0.68.
• Par 1.3.6-overheating assessment The designer should specify what the indoor comfort specification and perform an overheating assessment in accordance with CIBSE Guide A Chapter 5 and CIBSE TM 52 to ensure overheating is avoided.
• Tables 2,4,6 Minimimum Efficiencies-Boilers, Specific Fan Powers, Cooling EERs
• Par 1.4.2.4 and Table 3 Boilers over 100kW to have Building Management System controls
• Par 1.4.3.15 and Table 7-AC systems over 200m2 to have Building Management System controls
• Par 1.4.5.5 Lighting-Table 8 lms/cct watt or Table 9 LENI
Backstop U valuesTable 1 Maximum elemental U-value 1,2 (W/m2)
Column 1
Fabric Elements
Column 2
Area – weighted
Average
Column 3 Elemental U-value
Individual element or section
of element
Roofs
Pitched roof
- Insulation at ceiling
- Insulation on slope
Flat roof
0.16
0.16
0.20
0.3
Walls 0.21 0.6
Ground Floors3 0.21 0.6
Other exposed floors 0.21 0.6
External personnel doors,
windows and rooflights4,5,6,
1.6 3.0
Opaque Curtain Walling7 0.21 3.0
Vehicle access and similar large
doors1.5 3.0
Airtightness 5m3/hr/m2
Controls-HeatingTable 3 Recommended minimum controls packages for new boilers and multiple
boiler systems
Boiler Plant output Package Minimum Controls
<100kW A (a) Timing and temperature demand control which should be zone specific where the building floor area is greater than 150m2
(b) Weather compensation except where a constant temperature supply is required
100kW to 500kW B (a) The BMS should include:
(a) Controls package A above.
(b) Optimum start/stop control with either night set-back or frost protection outside occupied periods.
(c) Two stage high/low firing facility in boiler or multiple boilers with sequence control to provide efficient part load performance.
Note: The heat loss from non-firing boiler
modules should be limited by design or
application. For boilers that do not have low
standing losses it may be necessary to install
isolation valves or dampers
> 500kW individual
boilers
C (a) Controls Package A and controls package B
For gas-fired boilers and multi-stage oil-fired
boilers, fully modulating boiler controls
1.4.2.4For buildings with a heat demand of more than 100kW a full building management system should be installed to control the boiler(s). A full BMS linked to the heating plant will provide sequential controls of multiple boilers, full zoned time control and weather compensation where applicable, frost protection or night set-back optimization and monitoring and targeting.
Controls –air conditioning1.4.3.15 A minimum controls package should be provided as in Table 7. Where the floor area to be air conditioned is greater than 200m2 a Building Management System should be installed which provides centralized control for air conditioning systems. In larger or more complex buildings, the guidance contained in CIBSE Guide H: Building Control Systems may also be followed.
Table 7 Recommended minimum controls for air distribution systems from I.S. EN 15232:2012
System type Controls package
Central mechanical
ventilation with heating,
cooling or heat recovery
Air flow control at room level Time control
Air flow control at air handler level On/Off time control
Heat exchanger defrosting control Defrost control so that during cold periods ice does
not form on the heat exchanger
Heat exchanger-overheating control Overheating control so that when the system is
cooling and heat recovery is undesirable, the heat
exchanger is stopped modulated ore bypassed
Supply temperature control Variable setpoint with outdoor temperature
compensation
Central Mechanical
ventilation with heating or
heat recovery
Air flow control at room level Time control
Air flow control at air handler level On/off time control
Heat exchanger defrosting control Defrost control so that during cold periods ice does
not form on the heat exchanger
Heat exchanger overheating control Overheating control so that when the system is
cooling and heat recovery is undesirable, the heat
exchanger is stopped, modulated or bypassed
Supply Temperature Control Demand control
Zonal Air flow control at room level On/off time control
Air flow control at handler level No Control
Supply temperature control No control
Local Air flow control at room level On/off
Air flow control at air handler level No Control
Supply temperature control No Control
Fan Power & Cooling EfficienciesTable 4 Maximum specific fan power in air
distribution systems
System type SFP (W/(l/s)
Central balanced mechanical ventilation
system with heating and cooling
1.6
Central balanced mechanical ventilation
system with heating only
1.5
All other central balanced mechanical
ventilation systems
1.1
Zonal supply system where fan is remote
from zone, such as ceiling void or roof-
mounted units
1.1
Zonal extract system where fan is remote
from zone
0.5
Zonal supply and extract ventilation units,
such as ceiling void or roof units serving
single area with heat recovery
1.9
Local balanced supply and extract
ventilation system such as wall/roof units
serving single area with heat recovery
1.6
Local supply or extract ventilation units
such as window/wall/roof units serving
single area (e.g. toilet extract)
0.3
Other local ventilation supply or extract
units
0.5
Fan assisted terminal VAV unit 1.1
Fan coil unit (rating weighted average1,2) 0.5
Kitchen extract, fan remote from zone
with grease filter
1.0
Table 6 Minimum Energy Efficiency Ratio (EER) for cooling
Type Cooling unit full load
EER
Packaged Air
Conditioners
Single-Duct type 2.6
Other Types 2.6
Split and multi-split air conditioners >12
kW
2.6
Split and multi-split air conditioners <12
kW
SCOP “D” rating for
median temperature
range in I.S.
EN14825:2013
Variable Refrigerant Flow Systems 2.6
Vapour Compression cycle chillers, water
cooled < 750 kW
3.9
Vapour Compression cycle chillers, water
cooled >750 kW
4.7
Vapour Compression cycle chillers, air
cooled < 750 kW
2.55
Vapour Compression cycle chillers, water
cooled >750 kW
2.65
Water loop heat pump 3.2
Absorption cycle chillers 0.7
Gas engine-driven variable refrigerant
flow
1.0
Lighting1.4.5.5 Lighting in new buildings should meet the minimum recommended standards for:
efficacy (averaged over the whole area of the applicable type of space in the building) and controls in Table 8
OR
maximum Lighting Energy Numeric Indicator (LENI) (kWh/m2/year) listed in Table 9. LENI is based on BS EN 15193:2007 Energy Performance of Buildings. Energy Requirements for Lighting.. The LENI should be calculated using the procedure in Table 9. The procedure for designing to LENI is provided in Appendix G.
Table 8
General lighting in office industrial
and storage spaces
Initial luminaire
lumens/circuit watt
60
Controls Control
Factor
Reduced luminaire
lumens/circuit-watt
a. daylight space with photo-switching with or without override
0.90 54
a. daylit space withphoto-switching anddimming with orwithout override
0.85 51
a. unoccupied spacewith auto on and off
0.90 54
a. unoccupied spacewith manual on andauto off
0.85 51
space not daylit dimmed
for constant illuminance
0.90 54
a + c 0.80 48
a + d 0.75 45
b + c 0.75 45
b + d 0.70 42
e + c 0.8 48
e + d 0.75 45
General lighting in other types of
space
The average initial
efficacy should be not
less than 60 lamp
lumens/circuit watt
Display lighting The average initial
efficacy should be not
less than 22 lamp
lumens/circuit watt
Table 9 Recommended maximum LENI (kWh per square metre per year) in new buildings
Hours Illuminance (lux) Display lighting
Tota
l
Day Night 50 100 150 200 300 500 750 1000 Normal Shop
window
1000 821 179 1.11 1.92 2.73 3.54 5.17 8.41 12.47 16.52 10.00
1500 1277 223 1.66 2.87 4.07 5.28 7.70 12.53 18.57 24.62 15.00
2000 1726 274 2.21 3.81 5.42 7.03 10.24 16.67 24.70 32.73 20.00
2500 2164 336 2.76 4.76 6.77 8.78 12.79 20.82 30.86 40.89 25.00
3000 2585 415 3.31 5.72 8.13 10.54 15.37 25.01 37.06 49.12 30.00
3700 3133 567 4.09 7.08 10.06 13.04 19.01 30.95 45.87 60.78 37.00
4400 3621 779 4.89 8.46 12.02 15.59 22.73 37.00 54.84 72.68 44.00 96.80
5400 4184 1216 6.05 10.47 14.90 19.33 28.18 45.89 68.03 90.17 54.00
6400 4547 1853 7.24 12.57 17.89 23.22 33.87 55.16 81.79 108.41 64.00
8760 4380 4380 10.26 17.89 25.53 33.16 48.43 78.96 117.12 155.29 87.60 192.72
Commissioning/HandoverPar 1.5.5 Commissioning
The key elements of a commissioning plan, identifying the systems that need to be tested and the tests that will be carried out and should be developed at the design stage. The BSRIA Job Book A project framework for engineering services BG1/2009 provides further useful information on Commissioning of Buildings other than Dwellings.
Airtightness testing
1.5.4.2, air pressure testing should be carried on all development sites, as outlined in paragraphs 1.5.4.3 to 1.5.4.6 to show attainment of backstop value of 5 m3/hr/m2. The tests should be carried out by a person certified by an independent third party to carry out this work, e.g. National Standards Authority of Ireland certified or equivalent. The test report should contain at least the information specified in Section 7 of I.S. EN ISO 9972: 2015.
Ductwork leakage testing1.5.6.1 Ductwork leakage testing should be carried out on Class C and Class D ductwork where required by and in accordance with the procedures set out in B&ES DW/143 and B&ES DW/144 on systems served by fans with a design flow greater than 1m3/s.
Handover
Par 1.6.1 The owner of the building should be provided with sufficient information about the building, the fixed building services and their maintenance requirements so that the building can be operated in such a manner as to use no more fuel and energy than is reasonable in the circumstances.
TGD L-Draft Major Renovation proposal
• Define as “more than 25% of the surface area of the building envelope undergoes renovation”
• Provide menu of measures to bring to cost optimal when more than 25% of surface area being renovated:
– Upgrade inefficient heating systems
– Upgrade inefficient cooling systems
– Upgrade inefficient lighting systems
TGD L Major RenovationsPar 2.3.2 When calculating the proportion of surface area undergoing renovation the area of the whole building external envelope should be taken into account including i.e. external walls, roofs, floors, windows, doors , and roof windows and lights
Works to the surface area of the building include the following:
• Cladding the external surface of the element
• Drylining the internal surface of an element
• Replacing windows
• Stripping down the element to expose the basic structural components (brickwork/blockwork, timberframe steelframe, joists, rafters etc.) and then rebuilding to achieve all the necessary performance requirements. Painting, replastering or rendering are not considered a major renovation for this part of the regulation.
Par 2.3.4 The following improvements are normally considered to be cost optimal and will typically be economically feasible when more than 25% of the surface area of a building is being upgraded
• Upgrading heating systems more than 15 years old and with an efficiency of less than that shown in in table 10
• Upgrading cooling and ventilation systems more than 15 years old and a cooling unit Energy Efficiency Ration less than that in Table 14 and/or Specific Fan Power greater than that in Table 12 and by the provision of new plant and
• Upgrading general lighting systems that have an average lamp efficacy of less than 40 lamp-lumens per circuit-watt and that serves greater than 100m2 to the guidance in section 2.2.7.
TGD L Major Renovations-alternative approach
Table 20 Whole Building Cost Optimal Level
Building Type Major Renovation - Cost Optimal
Performance kWh/m2/yr
Retail
Air Conditioned
338
Office
Natural Ventilated offices and other
Buildings
124
Office
Air Conditioned
180
Hotel
Air Conditioned
342
Schools 60
Other Air Conditioned Buildings 338
Other Naturally Ventilated Buildings 124
Costs• Performance requirements are based on cost optimal
reports published in accordance with EPBD:Table 5.3a of Residential and Non Residential Cost Optimal Report1 provides Initial Investment Costs for the energy related costs for different performance levels for 5 buildings.
• Consultant appointed for TGD L 2017 Buildings other than Dwellings and costs will be available for Public Consultation.
• 1http://www.housing.gov.ie/housing/building-standards/energy-performance-buildings/energy-performance-buildings
Training• NZEB building design ,Ventilation design, Renewables-Heat
pumps, CHP, PV, District Heating, Non Residential Lighting, Onsite skills, Solar gains/overheating, Optimsing fabric
• Working with Dublin Institute of Technology, Qualibuild, NZEBRA
• DIT School of Mechanical & Design Engineering CPD modules which will be available part time in Bolton Street from September 2017
• DIT School of Architecture online MSc modules developed under the H2020 MEnS project available from Sept 2017
Next Steps
• Part L/TGD L 2017-Buildings other than dwellings– Public Consultation of TGD L and Regulatory Impact Assessment
Start 24th Mar. 2017
– Close of TGD L 2017 Public Consultation 26th May
– Publication of TGD L by Q3 2017
– TGD L 2017 planned to apply by start of 2019 (subject to regulatory process)
• Part L Dwellings 2018– Public Consultation early 2018
– Application 2019 (subject to regulatory process)
www.housing.gov.ieemail:[email protected]
New Build:- Walls 0.13 W/m2K- Windows 0.82W/m2K- Roof 0.11W/m2K- Renewables-Pellet boiler
and 938m2 PV
EU Study CT5 Report Selected Examples of NZEBhttp://www.epbd-ca.eu/wp-content/uploads/2011/05/CT5_Report_Selected_examples_of_NZEBs-final.pdf
Efficiency House Plus with E-mobility in Berlin
Project aim: This pilot building generates its own energy and makes it available to the users and the electric vehicles. Excess energy is fed back into the grid or stored in a battery. An annual positive energy balance is required for primary and final energy use.
Building address: Fasanenstraße 87a, 10623 Berlin
Building type: Residential Non-residential Public New Renovated
X X
Single-family house with 2 floors
Building size: 203 m² useful floor area (AN, with AN=0.32*Vgross), 138 m² living area
Building envelope construction:
The floor, the walls and the roof are made of timber panels filled with up to 52 cm cellulose insulation. The windows have triple glazing. Thermal bridges have been minimised. Photovoltaic modules cover the roof and the façade. All house elements can be separated and moved to another location or be disposed of after the lifetime of the building.
Building envelope U-values:
Wall 0.11 W/m²K
Window 0.70 W/m²K
Roof/ceiling to the attic 0.11 W/m²K
Cellar ceiling/ground slab 0.11 W/m²KBuilding service systems:
The house is heated by a central heating system with an air-to-water heat pump and floor heating. A balanced mechanical ventilation system with 80 % heat recovery and a building energy management system with touch pads are installed. The PV systems on the roof and facades generate electricity that is used by the building, fed into the grid or stored in a battery. The battery, with a capacity of 40 kWh, is made of 7,250 single second-hand battery cells formerly used in electric cars.
Minimum Boiler Efficiency Provisions
Table 2 Recommended minimum energy efficiency standards for building services1
Gas, oil and biomass-fired boilers new buildings Seasonal efficiency (gross)2
Natural Gas Single boiler system< 2MW
output
90%
Single boiler system> 2MW
output
86%
Multiple boiler system 82% for any individual boiler
86% for overall multi-boiler
system
LPG Single boiler system< 2MW
output
93%
Single boiler system>2MW
output
87%
Multiple boiler system 82% for any individual boiler
86% for overall multi-boiler
system
Oil Single Boiler System 84%
Multiple Boiler System 82% for any individual boiler
86% for overall multi-boiler
system
Biomass-independent, automatic, pellet/woodchip 75%
Comparison with other Countries