CM Express Acceptance Manual
V200R015C00SPC100
Huawei Technologies Co., Ltd. Website: http://support.huawei.com
E-mail: [email protected]
All Rights Reserved.
Address: Huawei Technologies Co., Ltd., Bantian, Longgang District, Shenzhen, P. R. China
Postal Code: 518129
Version: 20140710-B-1.0
CM Express Acceptance Manual Internal Use Only
Huawei Technologies Proprietary
Content
Part I Overview ........................................................................................................................1
1 Grounds for Acceptance Tests ......................................................................................... 1
2 Contents of the Manual .................................................................................................... 1
3 Numbering of Acceptance Test Items ............................................................................... 1
4 Matters for Attention ........................................................................................................ 1
iManager U2000-CME Mobile Element Management System Acceptance Manual For internal use only
Huawei Technologies Proprietary
Part I Overview
1 Grounds for Acceptance Tests
This manual is written in conformity with recommendations and international standards, with modifications to reflect the characteristics of Huawei equipment and solutions .
Upon completion of the project, an acceptance test team that consists of the customer
and Huawei engineers shall carry out the acceptance test to ensure that the equipment or system complies with the requirements.
2 Contents of the Manual
This manual applies to Huawei CM Express V200R015C00SPC100.
This manual consists of three parts:
Part I Overview introduces the grounds for acceptance tests, contents of the manual, numbering of acceptance test items, and matters for attention.
Part II Operation Guide describes in detail the testing procedures for all items. It
serves as a reference for acceptance tests. Part III Appendix includes the dial-up access test and the cover sign-off sheets
for the acceptance tests.
3 Numbering of Acceptance Test Items
Acceptance test items are usually numbered in a six-digit format as follows:
TXX-XXXX Test sub-item
Test item
Test category
4 Matters for Attention
Pay attention to the following points for the acceptance tests:
Before starting the tests, make sure that the system is correctly installed, the software and hardware commissioning is completed, and the system runs
normally. The test items shall be agreed on by the two parties concerned. Observe the relevant rules during the tests. You can omit some items that have
been tested before delivery if the site conditions are not appropriate.
iManager U2000-CME Mobile Element Management System Acceptance Manual For internal use only
Huawei Technologies Proprietary
Note:
In the acceptance tests, observe the contracts and agreements between the two
parties concerned. This manual serves as a reference only.