Part 2 Drainage and Highways

Embed Size (px)

Citation preview

  • 8/3/2019 Part 2 Drainage and Highways

    1/41

    CIVL1014 Surveying and DrawingDRAWING LECTURE

    Part 2: Drainage and Highways

    THE UNIVERSITY OF HONG KONG

    Dr. Ray SuDepartment of Civil Engineering

    (office: HW 6-6, Tel. no.: 2859 2648

    Email: [email protected])

  • 8/3/2019 Part 2 Drainage and Highways

    2/41

    Surface Drain on Podium

    Grated inlet

    Gutter

    Sloping

    floor

    Fall 1 in 50-100

    1

    50 to 100

    Drain pipes (not shown)

  • 8/3/2019 Part 2 Drainage and Highways

    3/41

    Surface Drain on Road

    Grated inlet1 in 33

    Footpath

    Carriageway

    Kerb

    Gutter

    1 in 40

  • 8/3/2019 Part 2 Drainage and Highways

    4/41

    Surface Drain on Slope

    U-channels

    Berm

  • 8/3/2019 Part 2 Drainage and Highways

    5/41

    U-channels and Catchpits on Slope

    Catchpit

    CatchpitFunctions of catchpits to connect U-

    channels atdifferent levels anddirections

    to catch sedimentand debris in theflowing water

    U-channel

    U-channel

  • 8/3/2019 Part 2 Drainage and Highways

    6/41

    Nullahs or Culverts for collecting stormwater only

    illegal discharge ofwastewater into opennullah would causewater pollution

  • 8/3/2019 Part 2 Drainage and Highways

    7/41

    Manholes

    Outlet

    Cast

    iron

    steps

    Manholes:- For inspection

    andmaintenance ofunderground

    pipes- For connectionof pipes atdifferent levelsand directions

    Platform

    Platform

    Inlet

    Inlet

    Inlet

  • 8/3/2019 Part 2 Drainage and Highways

    8/41

    Manholes and Pipes

    Pipe

    ManholeManhole

    PLAN

    SECTION

    Fall : 1 in 100 to 200

  • 8/3/2019 Part 2 Drainage and Highways

    9/41

    Concrete Pipes

    Internal diameter of concrete pipes

    range from 150mm to 2100mmSpigot & socket(s & s) connection

    Y junction of pipes

    Socket

    end

    Spigot

    end

  • 8/3/2019 Part 2 Drainage and Highways

    10/41

    Level Define the vertical alignment of the drainage system Unit: meters above principal datum (mPD)

    Pipe

    Manhole

    Ground Level (G.L.)

    Invert Level (I.L.)

    Hong Kong Principal Datum is a vertical datum first defined in 1980. Its origin is1.23m below the mean of 19 years (1965-83) observations of tide levels at NorthPoint, Victoria Harbour. Hong Kong Principal Datum is a vertical datum forengineering survey.

  • 8/3/2019 Part 2 Drainage and Highways

    11/41

    Chainage

    Gives the horizontal reference

    Measures the horizontal distance from a referencepoint Unit is in meters

    CH 00

    CH 10

    CH 22 CH 29

    CH 12CH 2310m

    12m

    7m

    MH1 MH2

    MH3

    MH4

    MH5 MH6

    PLAN

  • 8/3/2019 Part 2 Drainage and Highways

    12/41

    Pipe (barrel) Installation MethodsTYPE BB

    TYPE BO

    Minimum protectionFor pipe below open ground

    Medium protection

    For pipe below pavement

    This detail is applicable for both soil and rock sites

    pipe

    Longitudinal

    section

    Y1

    Outer diameter of the sockettrench

  • 8/3/2019 Part 2 Drainage and Highways

    13/41

    TYPE AO

    Maximum protection

    For pipe below carriageway

    Pipe (barrel) Installation Methods

  • 8/3/2019 Part 2 Drainage and Highways

    14/41

    PLAN

    LONGITUDINAL SECTION

    MANHOLE DETAILS

    Inter-related

  • 8/3/2019 Part 2 Drainage and Highways

    15/41

    Drainage Plan

    Symbol

    for slopeDir.

    ofthe

    dip

    Crest of the slope

    toe of the slope

    Manhole

    mark

    Manhole

    Gutter

    Enlarged

    Undergrounddrain pipe 150

    Dia. (see thelongitudinalsection)

    Kerb

    What kinds of information cannot be found

    from this drawing?Flow direction of sewer, the types, sizes

    and levels of pipes and manholes.

    From the kerb to thecentre of manhole

  • 8/3/2019 Part 2 Drainage and Highways

    16/41

    Manhole Details

    PLAN (MH 21) A-A

    Conc. pipe

    Conc. pipe

    MH

    Foot hole

    False viewshowing the MH

    entrance above

    Ground surface

    Ground level

    I.L.

    Shut off board

  • 8/3/2019 Part 2 Drainage and Highways

    17/41

    PLAN (MH 11) B-B

    -5.855mPD

    -6.050mPD (from plan)

    -5.800mPD (from plan)

    -4.200mPD

    -4.600mPD

    Ground level

    Manhole Details

    Th h i nt l s l (1:200) is diff nt

  • 8/3/2019 Part 2 Drainage and Highways

    18/41

    Longitudinal Section

    Ground surface

    Concrete pipe

    Manhole

    Surface drain pipes

    Type of pipes

    and type of

    protection for

    pipes

    Horizontal reference to MHs (unit in metres)

    CH 0 is defined

    at MH11

    Vertical position of MHs (unit in mPD)

    The horizontal scale (1:200) is differentfrom the vertical scale (1:50). The mainpurpose of this drawing is to show clearlythe vertical alignments of the drainage.

    Vertical position of pipes (unit in mPD)

  • 8/3/2019 Part 2 Drainage and Highways

    19/41

    Drainage PlanSymbol

    for slopeDir.

    ofdip

    Crest of the slope

    toe of the slope

    0.000mPD Ground level

    Manhole

    mark

    Manhole

    Gutter (see the longitudinal section)

    Enlarged

    Undergrounddrain pipe 150

    Dia.

    Kerb line

    G.L. -0.250mPD of the MHI.L. 3.600mPD of the pipe

    G.L. -0.300mPD

    I.L. 3.700mPD

    G.L. -0.250mPD

    I.L. 4.000mPD

    I.L. 4.200mPD

    G.L. -0.250mPD

    I.L. 4.600mPD

    G.L. 1.000mPD

    I.L. 4.400mPD

  • 8/3/2019 Part 2 Drainage and Highways

    20/41

    CH105

    CH75 CH26

    CH0

    CH22

    49m

    2

    6m

  • 8/3/2019 Part 2 Drainage and Highways

    21/41

    Lam TsuenRiver

    Example Drainage Layout Plan

    Two networksmanaged byDSD:

    Sewerage

    (for foul water) Drainage(for stormwater)

    sewerage

    drainage

  • 8/3/2019 Part 2 Drainage and Highways

    22/41

    Highways Drawing

  • 8/3/2019 Part 2 Drainage and Highways

    23/41

    Street Furniture

    Central

    Divider

    Parapet/

    Barrier

    Noise Barrier

    Light poles

    Shoulder/

    Marginal Strip

    Direction sign gantry

    Road marks

    Carriageway with 3 lanes

  • 8/3/2019 Part 2 Drainage and Highways

    24/41

    Setting out

    Setting out line (S.O.L.)

    A curved road

    Direction forincreasing the

    chainage numbers

    CH 100

    CH 200

    CH 300

    Chainage measured along a S.O.L.

    is used to give horizontal

    references/ distances of the S.O.L.

    (unit in metres)

  • 8/3/2019 Part 2 Drainage and Highways

    25/41

    Superelevation

    Horizontal line

    Setting out line

    Crossfall/

    Superelevation

    Centrifugal

    force

    Reaction

    Weight

    Superelevation

    To counter balancethe centrifugal

    force

    Superelevation is tilting the roadway to help offset the centrifugalforce developed as the vehicle goes around a curve.

  • 8/3/2019 Part 2 Drainage and Highways

    26/41

    tilted road surface

    A

    A

    Positive

    crossfall (%)

    horiz. ref.

    S.O.L become a

    point in this

    sectional viewSection A-A

    Setting out line (S.O.L.)

    A curved road

    Direction forincreasing the

    chainage numbers

    CH 10

    CH 30

    CH 50

    h

    x

    Crossfall =(h/x)100 %

    Superelevation

    P t J i

  • 8/3/2019 Part 2 Drainage and Highways

    27/41

    Pavement

    Concrete surface

    Bituminous surface

    Joints

    longitudinal & lateral

    Rigid pavement

    Flexible pavement

    Joints are requiredfor (1) construction

    (2) Allowing movement& preventing crackingof pavements

    M t J i t

  • 8/3/2019 Part 2 Drainage and Highways

    28/41

    Movement Joint

    Movement joint

  • 8/3/2019 Part 2 Drainage and Highways

    29/41

    Verge

    Verge

    Without the verge,thesight distance can besubstantially reduced

  • 8/3/2019 Part 2 Drainage and Highways

    30/41

    Highway Verge

    A turned road

    without verge

    A turned road with

    verge (no blockage)

    Verge

    Verge can (1) increase the sight distance, (2) improve thedriving comfort, (3) enhance road safety, (4) increase thespeed limit of the road. It should be unblocked but couldprovide temporary parking space under emergency

    situations

    Very short

    sight distance

    Sight distance

    can be

    increased

    substantially

  • 8/3/2019 Part 2 Drainage and Highways

    31/41

    NOTES

    1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS

    STATED OTHERWISE,

    2. ALL COORDINATES GIVEN IN THIS DRAWING ARE

    BASED ON THE 1980 GAUSS CONFORMAL COORDINATE

    SYSTEM UNLESS STATED OTHERWISE.

    3. ALL LEVELS ARE IN METERS ABOVE PRINCIPAL DATUM

    UNLESS STATED OTHERWISE.

    4. SUPERELEVATION SHALL BE APPLIED BY PIVOTING

    ABOUT THE SETTING OUT LINE UNLESS NOTED

    OTHERWISE.

    5.

    Sectional view(Looking into the paper is)

  • 8/3/2019 Part 2 Drainage and Highways

    32/41

    6. HORIZONTAL ALIGNMENT NOTATIONS

    L = 40m => 40m SPIRAL LENGTH

    LH = 400m => 400m LEFT HAND RADIUS CURVE

    RH = 400m => 400m RIGHT HAND RADIUS CURVE

    7. VERTICAL ALIGNMENT NOTATIONS

    VIP: VERTICAL INTERSECTION POINT

    20m VC => 20m LONG VERTICAL CURVE (a smooth curve)

    10% : SETTING OUT LINE GRADIENT

    Both angles andcurvatures are

    continuous at the two

    ends of the curve

    Spiral curveRight hand

    radius curve

    Left hand

    radius curve

    Increase in the

    chainages of the

    setting out line

    R=400m R=400m

    PLAN VIEW

    Centre is at LHS

    of the SOL

    3 forms of linesStraightCircular ArcSpiral

    Curvature =1/R

    Curvature = 0=1/ NOTES

    C t Sl

  • 8/3/2019 Part 2 Drainage and Highways

    33/41

    Cut Slopes

    S i f A Sl

  • 8/3/2019 Part 2 Drainage and Highways

    34/41

    Section of A Slope

    Ground profile of an existing slope

    New platformto be created

    Soil to be excavated

    Soil to be filled

    Cut slope

    Fill slope

  • 8/3/2019 Part 2 Drainage and Highways

    35/41

    Crest ofthe slopeToe of the

    slope

    Just a thick linein a drawing

  • 8/3/2019 Part 2 Drainage and Highways

    36/41

    Settingout line(S.O.L.)

    Plan view Longitudinal Section

    Cross Sections

    Read the drawingssimultaneously

    (along the S.O.L.)

    Highway Plan

  • 8/3/2019 Part 2 Drainage and Highways

    37/41

    Highway Plan

    latitude

    longitude

    Based onthe 1980Gaussconformalcoordinatesystem

    Cut slope

    Crest

    BermToe

    Symbolshowing thenorthdirection

    Contour lines (unit:mPD) representing the

    existing ground profile

    Existing house which may

    be affected by the roadconstruction

    Chainage along theS.O.L.

    Setting out line(S.O.L.)

    central divider

    RETAININGWALL

    Cut slope

    Cut slope

    Cut slope

    Fill slope

    L n it din l S ti n ( l th tti t li )

  • 8/3/2019 Part 2 Drainage and Highways

    38/41

    Enlarged

    Gives horiz.reference

    VIP 1Elevation =36.961mPD

    VC (a parabolic curve)

    Enlarged

    Gradient of the

    SOL

    =76-54

    superelevation

    sprial sprialRight hand radius curve

    L=left carriageway

    R=right carriagewayExtent of the plan

    25.846

    =(54+22/2)0.171+25.846(270-76+11+5)0.1+36.961=

    Longitudinal Section (along the setting out line)

    Existing groundprofile

    Highway Plan

    1:500

  • 8/3/2019 Part 2 Drainage and Highways

    39/41

    Highway Plan

    latitude

    longitude

    Based onthe 1980Gaussconformalcoordinatesystem

    Cut slope

    Crest

    BermToe

    Cut slope

    Cut slope

    Cut slope

    Retaining wallSymbolshowingthe northdirection

    Contour lines (unit:mPD) representing the

    existing ground profile

    Existing house which may

    be affected by the roadconstruction

    Chainage along theS.O.L.

    Setting out line(S.O.L.)

    central divider

    RH=45m

    CH150

    CH150CH170

    CH170

    1:500

    Spiral curveLength =40m

    Straight line

    C i

  • 8/3/2019 Part 2 Drainage and Highways

    40/41

    Cross Section

    Retaining wall

    Railing

    U-channel

    U-channel

    U-channel

    U-channel U-channel

    Cut slope

    Cut slope

    Left

    carriageway

    Right

    carriageway

    Crossfall 7%Crossfall 10%

    Bedrock profile

    Vertical level in mPD

    C S i

  • 8/3/2019 Part 2 Drainage and Highways

    41/41

    Leftcarriageway

    Rightcarriageway

    Crossfall 7%Crossfall 10%

    Cross Section