196
Georgia 0 College of Engineering June 14, 2002 Office of the Dean Docket No. 50-160 United States Nuclear Regulatory Commission Mail Stop 012-G13 Washington, D.C. 20555-0001 Attention: Mr. Daniel E. Hughes, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Subject: Transmittal of Final Survey Report, Georgia Tech Research Reactor (GTRR) D&D Project References: 1. Georgia Tech Research Reactor NRC Amendment 14 to Facility License No. R-97. 2. NRC Docket No. 50-160 Dear Mr. Hughes: We are pleased to transmit the "Final Survey Report for the Georgia Institute of Technology Research Reactor Facility, NRC License No. R-97", Revision 0, June 2002, submitted by Shaw Environmental & Infrastructure, Inc., as prepared by Duratek, Inc. This Report serves as the basis by which we ask the United States Nuclear Regulatory Commission to grant full and unrestricted release of the Georgia Tech Research Reactor, and termination of NRC Facility License No. R-97. In transmitting this Final Survey Report, Georgia Institute of Technology neither approves nor disapproves the Report. We have worked closely with the Decommissioning Contractor throughout the decommissioning project, but ultimately the Decommissioning Contractor is obligated under its contract with the State of Georgia to submit a Final Survey Report that is acceptable to the USNRC. If you have any questions regarding this transmittal, please contact me at (404) 894-2982, or Dr. Nolan E. Hertel, Director, Neely Nuclear Research Center, (404) 894-3601. Sincerely, J. Narl Davidson Interim Dean College of Engineering Chair, Technical Safety Review Committee Enclosure: Final Survey Report for the Georgia Institute of Technology Research Reactor Facility, Revision 0, dated June 2002, four volumes. Cc: Dr. G. Wayne Clough, President, Georgia Institute of Technology Mr. Robert K. Thompson, SVP, Georgia Institute of Technology Ms. Amelia Gambino, Georgia Tech Office of Communications Mr. Stephen Holmes, USNRC Inspector Mr. Jon M. Richards, USEPA, Region IV Mr. Thomas Hill, Georgia Department of Natural Resources Members, Technical Safety Review Committee College of Engineering Atlanta, Georgia 30332-0360 U.S.A. PHONE 404.894.3350 FAX 404-894-0168 AU)it of the Univzersity Systen of Georgia An Equal Education and Eniployment Opportunity histitttit.o.. A(0 (

Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Georgia 0 College of Engineering

June 14, 2002 Office of the Dean Docket No. 50-160

United States Nuclear Regulatory Commission Mail Stop 012-G13 Washington, D.C. 20555-0001

Attention: Mr. Daniel E. Hughes, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation

Subject: Transmittal of Final Survey Report, Georgia Tech Research Reactor (GTRR) D&D Project

References: 1. Georgia Tech Research Reactor NRC Amendment 14 to Facility License No. R-97.

2. NRC Docket No. 50-160

Dear Mr. Hughes:

We are pleased to transmit the "Final Survey Report for the Georgia Institute of Technology Research Reactor

Facility, NRC License No. R-97", Revision 0, June 2002, submitted by Shaw Environmental & Infrastructure,

Inc., as prepared by Duratek, Inc. This Report serves as the basis by which we ask the United States Nuclear

Regulatory Commission to grant full and unrestricted release of the Georgia Tech Research Reactor, and

termination of NRC Facility License No. R-97.

In transmitting this Final Survey Report, Georgia Institute of Technology neither approves nor disapproves the

Report. We have worked closely with the Decommissioning Contractor throughout the decommissioning

project, but ultimately the Decommissioning Contractor is obligated under its contract with the State of

Georgia to submit a Final Survey Report that is acceptable to the USNRC.

If you have any questions regarding this transmittal, please contact me at (404) 894-2982, or Dr. Nolan E.

Hertel, Director, Neely Nuclear Research Center, (404) 894-3601.

Sincerely,

J. Narl Davidson Interim Dean College of Engineering Chair, Technical Safety Review Committee

Enclosure: Final Survey Report for the Georgia Institute of Technology Research Reactor Facility, Revision 0,

dated June 2002, four volumes.

Cc: Dr. G. Wayne Clough, President, Georgia Institute of Technology Mr. Robert K. Thompson, SVP, Georgia Institute of Technology Ms. Amelia Gambino, Georgia Tech Office of Communications Mr. Stephen Holmes, USNRC Inspector Mr. Jon M. Richards, USEPA, Region IV Mr. Thomas Hill, Georgia Department of Natural Resources Members, Technical Safety Review Committee

College of Engineering Atlanta, Georgia 30332-0360 U.S.A. PHONE 404.894.3350 FAX 404-894-0168

AU)it of the Univzersity Systen of Georgia An Equal Education and Eniployment Opportunity histitttit.o.. A(0 (

Page 2: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Shaw Environmental & Infrastructure, Inc.

11560 Great Oaks Way, Suite 500

Alpharetta, GA 30022-2424 770.475.8994

Fax 770.777.9545

Sh~awThe Shaw Group Inc.

June 10, 2002

Mr. Bob Eby

Executive Engineer, GSFIC Project 1-47

CH2M Hill

151 Lafayette Dr. Suite 110

Oak Ridge, TN 37830

Re: GSFIC Project No. 1-47

Ga. Tech Research Reactor Decommissioning

Final Survey Report Rev. 0

Dear Mr. Eby,

Please find enclosed five copies of the Final Survey Report Rev. 0, dated June 2002.

This marks the completion of all work on the contract for the Georgia Tech Research Reactor

Decommissioning. In accordance with Article E-41- Notice of Readiness for Final Inspection, Shaw

Environmental & Infrastructure, Inc. hereby requests that a final inspection be made promptly by the

Engineer and the United States Nuclear Regulatory Commission (USNRC). It is our understanding that

a 3 to 6 month period will be required for the USNRC to perform the necessary survey work to allow

unrestricted free release of the facility.

If you should have any questions, please contact me at (770) 663-1452 or via e-mail at

gkalinauskas(dtheitgroup.com.

Sincerely yours, Shaw Environmental & Infrastructure, Inc.

Gede Kalinauskas

Project Engineer

Enclosure

Page 3: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Shaw Environmental & Infrastructure, Inc.

Mr. Bob Eby, June 10, 2002 Page 2 of 2

Cc: Butch Daniels, Shaw E&I, (w/o enc.)

Gunnar Jones, Shaw E&I, (w/o enc.)

Paul Jones, Duratek, (w enc.)

Steve Marske, CH2M HILL, (w enc.)

v/Dr. Rod Ice, Ga. Tech, (w enc.)

Doug Ivey, GSFIC, (w enc.)

Shaw E&I file: 784357

Page 4: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

L Shiaw Shaw Environmental & Infrastructure, Inc.

FINAL SURVEY REPORT

for the Georgia Institute of Technology

Research Reactor Facility NRC License No. R-97

GSFIC Project 1-47

Revision 0 June 2002

Client Approvals:

Executive Engineer

Technical Safety Review Committee

Shaw Shaw Environmental & Infrastructure, Inc.

11560 Great Oaks Way, Suite 500 Alpharetta, Georgia 30022

628 Gallaher Road Kingston, Tennessee 37763

Date

Date

*Duratek'

B

Page 5: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

ShawShaw Environmental & Infrastructure, Inc.

FINAL SURVEY REPORT

for the Georgia Institute of Technology

Research Reactor Facility

NRC License Number R-97

GSFIC Project 1-47

Document Number GT-PL-FR-001 Shaw E&I Project No. 784357

Duratek, Inc. / Shaw E&I, Inc.

Prepared By

Revision 0 Date: June 2002

June 2002

Date

wJ�7

Quality Assurance

Engineering

Manager Approval

6D/ate /Zo Date

Date1

Date

Date

Date

Date

Page 6: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

for the

GEORGIA INSTITUTE OF TECHNOLOGY RESEARCH REACTOR FACILITY

NRC LICENSE NUMBER R-97

Revision 0 June 2002

Prepared by:

Reviewed by:

Approved by:

Paul Jones, Survey Supervisor Radiological Engineering and Field Services

Doug Sedult, CHP, Senior Radiological Engineer Radiological Engineering and Field Services

Robert Hornbeck, Operations Manager, Commercial Operations Radiological Engineering and Field Services

Date.-o4 .

Date66O

D ate

Prepared By: Duratek, Inc.

Commercial Operations 628 Gallaher Road Kingston, TN 37763

Page 7: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TABLE OF CONTENTS

1.0 INTR O D U CTIO N A N D SCO PE ..................................................................................... 1

1.1 Introduction ...................................................................................................... 1 1.2 Project Scope ....................................................................................................... 2

2.0 BACKGROUND INFORMATION ............................................................................ 2

2.1 Facility D escription ............................................................................................ 2 2.1.1 B asem ent ................................................................................................. 2 2.1.2 First Floor ................................................................................................ 3 2.1.3 Second Floor ............................................................................................ 4 2.1.4 Reactor Y ard ............................................................................................ 4

2.2 Operating H istory ................................................................................................. 4 2.3 M anagem ent Approach ....................................................................................... 9 2.4 D ecom m issioning Activities .............................................................................. 9

3.0 FIN AL SUR V EY ............................................................................................................. 20

3.1 Introduction ....................................................................................................... 20 3.2 Survey Guideline V alues .................................................................................. 21

3.2.1 Criteria for Release for Unrestricted Use for Building Surfaces ....... 21 3.2.2 Site Specific Guideline V alues, SPGLs ................................................. 23 3.2.3 Criteria for Release for Unrestricted Use of Open Land Areas ............ 24

3.3 Instrum entation ................................................................................................ 25 3.3.1 Instrum ent Calibration .......................................................................... 27 3.3.2 Sources ................................................................................................... 27 3.3.3 M inim um D etectable Activity .............................................................. 27

3.4 Survey Organization ......................................................................................... 29 3.5 Survey D esign ................................................................................................... 29

3.5.1 U naffected Areas .................................................................................. 29 3.5.2 N on-Suspect A ffected Areas ................................................................. 29 3.5.3 Suspect A ffected Areas ....................................................................... 30 3.5.4 Survey Area Breakdow n ....................................................................... 30

3.6 A rea Re-Classification and Investigation ......................................................... 31 3.7 Survey Package D evelopm ent ......................................................................... 31 3.8 Survey R equirem ents ....................................................................................... 31

3.8.1 Suspect A ffected Areas .......................................................................... 32 3.8.2 N on-Suspect Affected Areas ................................................................. 32 3.8.3 U naffected Areas ..................................................................................... 32

3.9 Gridding ............................................................................................................... 33 3.10 Quality A ssurance and Quality Control ............................................................ 33

3.10.1 Selection of Personnel .......................................................................... 34 3.10.2 W ritten Procedures ................................................................................. 34 3.10.3 Instrumentation Selection, Calibration and Operation .......................... 34

3.11 D ocum entation ................................................................................................... 35 3.12 D ata R eduction and Statistical Evaluation ........................................................ 36

3.12.1 D ata A nalysis ....................................................................................... 36

i REVISION 0

Page 8: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

3.12.2 B ackground .......................................................................................... 36 3.12.3 Measurements of Total Beta Activity ................................................... 36 3.12.4 Measurements of Removable Alpha and Beta Activity ........................ 37 3.12.5 Measurements of Removable H-3 Activity ......................................... 38 3.12.6 Exposure Rate Measurements .............................................................. 38 3.12.7 Samples of Open Land Areas of Reactor Yard ..................................... 4P

4.0 SURVEY RESULTS ................................................................................................... 41

4.1 Background Results Summ ary .......................................................................... 41 4.2 Package 1 - Helium and Lead Tank Cooling Water Lines ............................... 42 4.3 Package 2 - Reactor Building 2nd Floor Below 2 Meters ................................. 47

4.4 Package 3 - Reactor Building 2nd Floor Above 2 Meters ................................. 54 4.5 Package 4 - Reactor Building 1 st Floor Below 2 Meters ................................. 60 4.6 Package 5 - Reactor Building 1st Floor Above 2 Meters ................................. 67 4.7 Package 6 - Reactor Building Ventilation Hold-Up Duct ................................ 72 4.8 Package 7 - Reactor Building Ventilation ....................................................... 77 4.9 Package 8 - Suspect Affected Yard Areas ....................................................... 84 4.10 Package 9 - Unaffected Asphalt and Concrete Yard Areas ............................. 91 4.11 Package 10 - Reactor Building and Stack ....................................................... 97 4.12 Package 11 - Reactor Building Basement Drain Lines ...................................... 102

4.13 Package 12 - Process Equipment Room Below 2 Meters .................................. 108

4.14 Package 13 - Process Equipment Room Above 2 Meters .................................. 115 4.15 Package 14 - Yard Open Land Areas ................................................................. 120 4.16 Package 15 - Basement Air Compressor Room ................................................. 124 4.17 Package 16 - Areas Outside Process Equipment Room Below 2 Meters .......... 130

4.18 Package 17 - Areas Outside Process Equipment Room Above 2 Meters .......... 137

4.19 Package 18 - Reactor Vessel Tunnel .................................................................. 142

4.20 Package 19 - Bism uth Leak Area ....................................................................... 149 4.21 Package 20 - Reactor Ventilation Above 2 Meters ............................................ 156 4.22 Package 21 - Elevator Equipment Room and Shaft ........................................... 161 4.23 Package 22 - Misc. Pipes and Penetrations ........................................................ 167

5.0 CO NCLUSIO NS ........................................................................................................... 174

6.0 REFEREN CES .............................................................................................................. 174

7.0 ATTACH M ENTS ......................................................................................................... 174

Attachment A Worksheets for Calculations of Site Specific Guideline Values Attachment B Final Survey Packages 1 through 22

REVISION 0ii

Page 9: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

LIST OF FIGURES AND TABLES

FIGURE NUMBER

Figure 2.1

Figure 2.2

Figure 2.3

Figure 2.4

Figure 2.5

Figure 4-lA

Figure 4-1B

Figure 4-1C

Figure 4-4D

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

4-2A

4-2B

4-2C

4-2D

4-2E

4-3A

4-3B

4-3C

4-3D

4-4A

4-4B

4-4C

4-4D

4-4E

4-5A

4-5B

4-5C

Figure 4-5D

TITLE PAGE

R eactor Y ard .................................................................. 5

Containment Building Basement ........................................ 6

Containment Building First Floor .......................................... 7

Containment Building Second Floor .................................... 8

Site L ayout ................................................................... 19

Helium and Lead Tank Cooling Water Lines - Map .................. 43

Helium and Lead Tank Cooling Water Lines Direct Beta Activity.... 44

Helium and Lead Tank Cooling Water Lines Removable Beta A ctivity ........................................................................ 45

Helium and Lead Tank Cooling Water Lines Removable H-3

A ctivity ...................................................................... 46

Reactor Building 2 nd Floor Below 2 Meters - Map .................... 49

2'• Floor Below 2 Meters Direct Beta Activity ......................... 50

2 nd Floor Below 2 Meters Exposure Rate Measurements .............. 51

2 nd Floor Below 2 Meters Removable Beta Activity .................. 52

2 nd Floor Below 2 Meters Removable H-3 Activity ................... 53

Reactor Building 2 nd Floor Above 2 Meters - Map ...................... 56

2nd Floor Above 2 Meters Direct Beta Activity ........................... 57 2nd Floor Above 2 Meters Removable Beta Activity ..................... 58

2 nd Floor Above 2 Meters Removable H-3 Activity ...................... 59

Reactor Building 1st Floor Below 2 Meters - Map ..................... 62

1st Floor Below 2 Meters Direct Beta Activity ......................... 63

1st Floor Below 2 Meters Exposure Rate Measurements ............... 64

1"t Floor Below 2 Meters Removable Beta Activity ................... 65

1 st Floor Below 2 Meters Removable H-3 Activity .................... 66

Reactor Building 1 st Floor Above 2 Meters - Map ....................... 68

1st Floor Above 2 Meters Direct Beta Activity ......................... 69

1 st Floor Above 2 Meters Removable Beta Activity .................... 70

1st Floor Above 2 Meters Removable H-3 Activity .................... 71

REVISION 0.°.

Page 10: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure

Figure

Figure

Figure

Figure

Figure

Figure

4-6A

4-6B

4-6C

4-6D

4-7A

4-7B

4-7C

Figure 4-7D

Figure 4-7E

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

Figure

4-8A

4-8B

4-8C

4-8D

4-8E

4-9A

4-9B

4-9C

4-9D

4-9E

4-10A

4-10B

4-10C

4-1OD

4-1 1A

4-1iB

4-11C

4-1ID

4-12A

4-12B

Reactor Building Ventilation Hold-Up Duct - Map ................... 73

Hold-Up Duct Direct Beta Activity ...................................... 74

Hold-Up Duct Removable Beta Activity ............................... 75

Hold-Up Duct Removable H-3 Activity .................................... 76

Reactor Building Ventilation Room and Stack - Map .................. 79

Reactor Building Ventilation Below 2 Meters Direct Beta Activity... 80

Reactor Building Ventilation Below 2 Meters Exposure Rate M easurem ents .................................................................. 81

Reactor Building Ventilation Below 2 Meters Removable Beta A ctivity ...................................................................... 82

Reactor Building Ventilation Below 2 Meters Removable H-3 A ctivity ...................................................................... 83

Yard Suspect Affected Areas - Map ........................................ 86

Yard Suspect Affected Areas Direct Beta Activity ........................ 87

Yard Suspect Affected Areas Exposure Rate Measurements ............ 88

Yard Suspect Affected Areas Removable Beta Activity .......... 89

Yard Suspect Affected Areas Removable H-3 Activity .................. 90

Yard Unaffected Areas - Map ............................................... 92

Yard Unaffected Areas Direct Beta Activity ............................ 93

Yard Unaffected Areas Exposure Rate Measurements .................. 94

Yard Unaffected Areas Removable Beta Activity ......................... 95

Yard Unaffected Areas Removable H-3 Activity ......................... 96

Reactor Building Exterior - Map ............................................ 98

Reactor Building and Stack Exterior Direct Beta Activity ............... 99

Reactor Building and Stack Exterior Removable Beta Activity ......... 100

Reactor Building and Stack Exterior Removable H-3 Activity ......... 101

Basement Drain Lines - Map .............................................. 104

Basement Drain Lines Direct Beta Activity ............................... 105

Basement Drain Lines Removable Beta Activity ......................... 106

Basement Drain Lines Removable H-3 Activity .......................... 107

Process Equipment Room Below 2 Meters - Map ........................ 110

Process Equipment Room Below 2 Meters Direct Beta Activity ....... 111

REVISION 0iv

Page 11: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-12C Process Equipment Room Below 2 Meters Exposure Rate M easurem ents .................................................................. 112

Figure 4-12D Process Equipment Room Below 2 Meters Removable Beta A ctivity ......................................................................... 113

Figure 4-12E Process Equipment Room Below 2 Meters Removable H-3 A ctivity ......................................................................... 114

Figure 4-13A Process Equipment Room Above 2 Meters - Map ........................ 116

Figure 4-13B Process Equipment Room Above 2 Meters Direct Beta Activity ...... 117

Figure 4-13C Process Equipment Room Above 2 Meters Removable Beta A ctivity .......................................................................... 118

Figure 4-13D Process Equipment Room Above 2 Meters Removable H-3 A ctivity ......................................................................... 119

Figure 4-14A Yard Open Land Areas - Map ............................................... 122

Figure 4-14B Yard Open Land Areas Exposure Rate Measurements .................. 123

Figure 4-15A Air Compressor Room - Map ............................................... 125

Figure 4-15B Air Compressor Room Direct Beta Activity .............................. 126

Figure 4-15C Air Compressor Room Exposure Rate Measurements ................... 127

Figure 4-15D Air Compressor Room Removable Beta Activity ........................ 128

Figure 4-15E Air Compressor Room Removable H-3 Activity ......................... 129

Figure 4-16A Areas Outside Process Equipment Room Below 2 Meters - Map...... 132

Figure 4-16B Areas Outside Process Equipment Room Below 2 Meters Direct B eta A ctivity ................................................................... 133

Figure 4-16C Areas Outside Process Equipment Room Below 2 Meters Exposure R ate M easurem ents ........................................................... 134

Figure 4-16D Areas Outside Process Equipment Room Below 2 Meters Rem ovable Beta A ctivity ..................................................... 135

Figure 4-16E Areas Outside Process Equipment Room Below 2 Meters Removable H-3 Activity ............................... 136

Figure 4-17A Areas Outside Process Equipment Room Above 2 Meters - Map...... 138

Figure 4-17B Areas Outside Process Equipment Room Above 2 Meters Direct B eta A ctivity ................................................................... 139

Figure 4-17C Areas Outside Process Equipment Room Above 2 Meters Rem ovable Beta Activity ..................................................... 140

Figure 4-17D Areas Outside Process Equipment Room Above 2 Meters Rem ovable H-3 A ctivity ...................................................... 141

Figure 4-18A Vessel Tunnel - M ap ......................................................... 144

REVISION 0V

Page 12: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-18B Vessel Tunnel Direct Beta Activity ........................................ 145

Figure 4-18C Vessel Tunnel Exposure Rate Measurements ............................. 146

Figure 4-18D Vessel Tunnel Removable Beta Activity ................................... 147

Figure 4-18E Vessel Tunnel Removable H-3 Activity .................................... 148

Figure 4-19A Bismuth Leak Area - Map ................................................... 151

Figure 4-19B Bismuth Leak Area Direct Beta Activity ................................... 152

Figure 4-19C Bismuth Leak Area Exposure Rate Measurements ....................... 153

Figure 4-19D Bismuth Leak Area Removable Beta Activity ............................ 154

Figure 4-19E Bismuth Leak Area Removable H-3 Activity ............................. 155

Figure 4-20A Reactor Ventilation Above 2 Meters - Map ............................... 157

Figure 4-20B Reactor Ventilation Above 2 Meters Direct Beta Activity .............. 158

Figure 4-20C Reactor Ventilation Above 2 Meters Removable Beta Activity ........ 159

Figure 4-20D Reactor Ventilation Above 2 Meters Removable H-3 Activity......... 160

Figure 4-21A Elevator Equipment Room and Shaft - Map ................................ 162

Figure 4-21B Elevator Equipment Room and Shaft Direct Beta Activity .............. 163

Figure 4-21C Elevator Equipment Room and Shaft Exposure Rate M easurem ent .................................................................. 164

Figure 4-21D Elevator Equipment Room and Shaft Removable Beta Activity ....... 165

Figure 4-21E Elevator Equipment Room and Shaft - Removable H-3 Activity...... 166

Figure 4-22A Misc. Pipes and Penetrations First Floor (01PO0) Map ................... 168

Figure 4-22B Misc. Pipes and Penetrations First Floor (02P00) Map ................... 169

Figure 4-22C Misc. Pipes and Penetrations Basement (02P00) Map ................... 170

Figure 4-22D Misc. Pipes and Penetrations Direct Beta Activity ........................ 171

Figure 4-22E Misc. Pipes and Penetrations Removable Beta Activity .......... 172

Figure 4-22F Misc. Pipes and Penetrations Removable H-3 Activity .................. 173

TABLE TITLE PAGE

NUMBER

Table 2.1 Georgia Tech Waste Disposition ........................................ 18

Table 3.1 Radionuclide Specific Guideline Values ................................ 22

Table 3.2 Site Specific Guideline Values for Total Beta Activity and Removable Beta Activity ................................................. 24

Table 3.3 Radionuclide Specific Soil Guideline Values .......................... 25

REVISION 0vi

Page 13: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Table

"Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

Table

.Table

REVISION 0

3.4

3.5

4.1

4.2

4.3

4.4

4.5

4.6

4.7

4.8

4.9

4.10

4.11

4.12

4.13

4.14

4.15

4.16

4.17

4.18

4.19

4.20

4.21

4.22

4.23

4.24

Final Survey Instrumentation ............................................... 26

Field and Laboratory Instrumentation MDA's ......................... 28

Direct Beta Background Study of Concrete and Asphalt ............... 41

Survey Package 1 Final Survey Results ................................... 42

Survey Package 2 Final Survey Results ................................ 48

Survey Package 3 Final Survey Results ................................. 54

Survey Package 4 Final Survey Results ................................. 61

Survey Package 5 Final Survey Results ................................. 67

Survey Package 6 Final Survey Results ................................. 72

Survey Package 7 Final Survey Results .................................... 77

Survey Package 8 Final Survey Results ................................. 84

Survey Package 9 Final Survey Results ................................. 91

Survey Package 10 Final Survey Results ................................... 97

Survey Package 11 Final Survey Results .................................. 102

Survey Package 12 Final Survey Results .................................. 109

Survey Package 13 Final Survey Results .................................. 115

Survey Package 14 Final Exposure Rate Results ......................... 120

Yard Open Land Areas Soil Sample Gamma Spectroscopy Results .... 121

Survey Package 15 Final Survey Results................................... 124

Survey Package 16 Final Survey Results .................................. 131

Survey Package 17 Final Survey Results .................................. 137

Survey Package 18 Final Survey Results ................................... 142

Survey Package 19 Final Survey Results .................................. 149

Survey Package 20 Final Survey Results .................................. 156

Survey Package 21 Final Survey Results ...................... I ........... 161

Survey Package 22 Final Survey Results .................................. 167

vii

Page 14: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

1.0 INTRODUCTION AND SCOPE

1.1 Introduction

IT Corporation (IT) is under contract to the Georgia State Financing and Investment Commission (GSFIC) to decommission the Georgia Institute of Technology Research Reactor (GTRR) and its associated systems. IT upon completion of the decommissioning activities is contracted to issue a Final Survey Report (FSR). Duratek executed the Final Survey under subcontract to IT with oversight and support from IT Corporation.

The GTRR was located within the Neely Nuclear Research Center (NNRC) on the campus of the Georgia Institute of Technology (Ga. Tech). The GTRR was built in the early 1960's as a research and training reactor. It was used to explore the frontiers of biology and material sciences as well as to teach engineers the principles of nuclear power plant operation. It first went critical on December 31, 1964. The reactor was operated under the United States Nuclear Regulatory Commission (NRC) License, Number R-97. It was originally designed for 1 MW thermal (t) output and upgraded to produce 5 MW (t) in 1974. Reactor operation ceased on November 17, 1995.

No single factor led to the GTRR decommissioning. However, there was one factor that catalyzed the decision process - the 1996 Summer Olympic Games. The Ga. Tech campus was home to over ten thousand athletes from over 160 countries. The high visibility of the Olympic Games led to increased questions about reactor security and also heightened public interest in reactor operations. In addition, the reactor had reached its 30-year design lifetime. It was time to reevaluate operating systems and upgrade areas within the containment building. Student enrollment in nuclear engineering and reactor utilization had significantly decreased. Thus, a combination of all these factors led the administration of Ga. Tech to decide to decommission th6 GTRR.

All nuclear fuel was removed from the facility in February, 1996 prior to the Olympic Games. At that time the NRC amended Ga. Tech's license and granted Ga. Tech a Possession-Only-License (POL). A short time later, the Ga. Tech administration decided to decommission the nuclear reactor. In 1999, the NRC approved a license amendment to the POL to dismantle the GTRR in accordance with the GTRR Decommissioning Plan prepared by NES, Inc. (Document No. 82A9083 Rev. 3, dated June, 1998). IT began decommissioning activities in November, 1999. The work involved the dismantlement and removal of all NRClicensable materials, equipment and structures from the site.

REVISION 0

FINAL SURVEY REPORT

1

Page 15: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

1.2 Project Scope

The ultimate goal of the Final Survey was to attain release of the GTRR facility for unrestricted use and the termination of NRC License Number R-97. The NRC approved GTRR Decommissioning Plan states, that for building surfaces, the criteria for release for unrestricted use shall be as specified in NRC Regulatory Guide 1.86, Termination of Operating Licenses for Nuclear Reactors, Table 1 "Acceptable Surface Contamination Levels". The GTRR decommissioning contract also states that the exposure rate from residual radioactivity can not exceed ambient background levels by more than 5 uR/hr (average) at 1 meter. The Final Survey was conducted in accordance with the Final Survey Plan which incorporated guidance contained in NUREG/CR-5849, Manual for Conducting Surveys in Support of License Termination (as referenced in the GTRR Decommissioning Plan).

2.0 BACKGROUND INFORMATION

2.1 Facility Description

The Neely Nuclear Research Center is located in the north-central part of the Ga. Tech campus in the city of Atlanta, Georgia. The NNRC is comprised of a containment building, hot cell, support laboratories, classrooms and offices. The GTRR was located inside the containment building which is situated on the southeast side of the NNRC.

The reactor containment building consists of three floors. The building is a cylindrical welded steel tank with a diameter of 82 feet and a 12-inch-thick internal concrete wall. The roof is a torispherical dome, approximately 50 feet above ground level. The reactor yard surrounds the containment building. It consists of both paved and open land areas. The containment building and reactor yard are shown in Figure 2.1.

2.1.1 Basement

The basement of the containment building housed the reactor process system equipment, the exhaust ventilation equipment and the electrical load center for the building. It can be reached by elevator or stairway from the first floor of the containment building. There is no direct personnel access from the basement of the containment building to the adjoining basement of the NNRC. The reactor process equipment was located within a room surrounded by 2-foot thick concrete walls. This room contained the primary coolant system and heat exchangers, reactor overflow and purification system, heavy water storage tank, heavy water recombiner, helium makeup system, secondary water system, and thermal shield cooling water system. Adjacent to the process equipment room is the containment building exhaust system blower and High Efficiency Particulate Air (HEPA) filters. Cast into the basement slab is a large

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

2

Page 16: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

holdup volume for the exhaust air. Another large void in this concrete slab provided an expansion chamber, which was connected to the helium/nitrogen space above the reactor core through a rupture disk.

The basement also contained the reactor sump, the Motor Control Center (MCC) electrical panel, the biomedical facility door hydraulic system, an elevator equipment room, a cooling water system for the bismuth blocks and three rooms, which housed the service air compressors, pneumatic transfer systems (rabbit systems) and an experimental area. The basement plan is shown in Figure 2.2.

2.1.2 First Floor

The first floor of the containment building, which is also the ground elevation, contained the reactor and its bioshield. The GTRR was a 5 MW thermal, heavy water moderated, cooled and reflected reactor that was fueled with uranium aluminum alloy plates. As stated earlier, the fuel elements were removed from the facility in February, 1996. The reactor was equipped with numerous horizontal and vertical experimental ports for access to fast and slow neutron beams. The reactor vessel was an aluminum, cylindrical tank approximately 6 feet in diameter and 10.4 feet high. The reactor's neutron flux was controlled by four aluminum-clad cadmium shim safety blades and an aluminum-clad cadmium regulating rod. The reactor vessel sat on a steel support structure and was suspended within a 2-foot thick graphite reflector. Graphite stringers surrounded the reactor from beneath the vessel and in a radial direction. A 0.25 inch thick cylindrical boral sleeve encompassed the graphite stringers. The nuclear reactor and graphite reflector were housed inside a lead shield tank. The lead shield tank consisted of 3.5 inches of lead sandwiched between two layers of steel. All of the above was enclosed within a 4.75 foot thick concrete and iron aggregate biological shield.

The first floor also contained a vertical water-filled spent fuel storage hole which was approximately 19 feet long and extended into the basement slab. This spent fuel storage hole was located inside one of the first floor structural support columns. A Plug Storage Vault with 18 horizontal storage tubes was set into the outside wall of the containment building on the first floor.

The first floor of the containment building can be accessed by one of three routes: the main air lock leading from the NNRC building; a smaller personnel air lock leading from the outside yard; and a truck door. There was plenty of space available on this floor to conduct experiments using one of the many horizontal beam ports. A thermal column was located on one side of the reactor while a shielded irradiation room (the biomedical facility) was situated on the opposite side immediately adjacent to the reactor. Figure 2.3 shows the first floor plan.

REVISION 03

FINAL SURVEY REPORT

Page 17: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

2.1.3 Second Floor

The second floor is 15 feet above the first floor and provided access to the top of the reactor. It can be reached by either using an elevator or stairs. A walkway (catwalk) runs completely around the circumference of the building on this elevation. The reactor control room occupies much of the second floor. An Emergency Core Cooling System (ECCS) tank was located on the second floor above the catwalk. Air was supplied to the containment building through an air-conditioning unit, which was located on top of the control room. An overhead 20-ton capacity polar crane that services the reactor building is supported by rails approximately 15 feet above the second floor. Figure 2.4 provides a plan of the second floor.

2.1.4 Reactor Yard

The grounds surrounding the containment building consist of an asphalt surface extending from the access gate around the containment building to a metal storage building, concrete surfaces adjacent to the containment building, gravel in the southwest comer formerly occupied by the cooling tower, and grass in the remaining areas.

2.2 Operating History

The GTRR was built in the 1960's as a component part of the Neely Nuclear Research Center. The reactor first went critical on December 31, 1964. It was licensed to operate at 1 MW (t) output for a thirty year period. In 1974 the license was amended and the reactor was upgraded to produce 5 MW (t). It continued to operate at this level until reactor operations ceased on November 17, 1995. The GTRR logged approximately 40,000 MW-hrs of operation.

The reactor was designed to accommodate many different research applications. The reactor produced a thermal flux of greater than 1014 neutrons/cm2/sec at a power of 5 MW(t). There were ten horizontal beam ports, two horizontal through ports (one above the reactor core and one below the reactor core), fourteen vertical ports, two large troughs located below the reactor, and a pneumatic tube conveyance system that could be used for research activities. Experiments were performed utilizing high intensity neutron beams, gamma ray beams, as well as a uniform thermal neutron flux through a large sized beam. The pneumatic tube system provided the ability to perform short irradiations or irradiations that required rapid sample recovery. Students and researchers employed the reactor to investigate materials science properties, to study nuclear physics and other frontiers of nuclear research.

Although there was a biomedical irradiation facility, no biomedical experiments were ever performed.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

4

Page 18: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

Figure 2.1 Reactor Yard

REVISION 0

AOCM8

FENCE LINE

N-4

GA TECH RESEARCH REACTOR

5

Page 19: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FTh�AL SURVEY REPORT

Figure 2.2 Containment Building Basement

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

6

Page 20: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

Figure 2.3 Containment Building First Floor

REVISION 0

GA TECH RESEARCH REACTOR

7

Page 21: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

Figure 2.4 Containment Building Second Floor

REVISION 0

FINAL SURVEY REPORT

8

Page 22: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

2.3 Management Approach

The GSFIC, as the owner, and on behalf of the using agency, Ga. Tech, contracted IT Corporation to decommission the GTRR in accordance with the NRC approved GTRR Decommissioning Plan. IT Corporation was responsible for the management and execution of all decommissioning activities. In addition to performing site work tasks, IT provided site radiation protection, health and safety, and quality assurance personnel. IT's primary subcontractor for this project was GTS Duratek (Duratek) which was responsible for the initial survey, all waste management activities, including packaging and transportation, and the final survey of the facility.

The Ga. Tech Radiation Safety Officer, who is responsible for all radiation safety matters on campus, reviewed and approved all Radiation Work Permits (RWPs) and radioactive waste shipping documents for the project. As the licensee, the Radiation Safety Office monitored the radiation exposure of all decommissioning personnel.

The GSFIC contracted CH2M HILL to serve as the Executive Engineer for this project. CH2M HILL personnel provided technical oversight and consultation to Ga. Tech during the course of the project. They coordinated the review of various project documents, monitored daily decommissioning activities and performed independent audits of the work.

A Technical Safety Review Committee (TSRC), consisting of six members appointed by the president of Ga. Tech from the faculty and the private sector, reviewed and approved all plans and procedures for the decommissioning project. Any deviations from the GTRR Decommissioning Plan, were screened by a Title 10 Code of Federal Regulations Chapter 50.59 (10 CFR 50.59) safety screening and evaluation process, and approved by the TSRC prior to implementation.

2.4 Decommissioning Activities

IT's decommissioning activities began with the development of necessary site specific plans and procedures. Once approved, personnel and equipment were mobilized to the project site in November, 1999. Two temporary office trailers were located in the southwest comer of the yard outside the containment building (see Figure 2.5). These trailers housed the management and technical support personnel. Project files and site logs were maintained in the larger site office trailer. A laboratory trailer, equipped with the necessary radiological analysis / counting equipment, was located at the north end of the yard adjacent to the NNRC. A decon trailer was situated next to the containment building's secondary personnel air lock and it served as the main access control point into the containment building during decommissioning activities. The decon trailer contained personnel protective equipment and clothing, a change area, lockers, showers, and wash sinks. Radiation Work Permits and Work Packages were

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

9

Page 23: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

located in the decon trailer for personnel review prior to entering the containment building.

After completing all required training and orientation classes, site personnel commenced the initial site survey. The purpose of this survey was to assess the existing radiological conditions of the facility. The radiation levels and radioactive contamination levels were compared with those described in the report entitled GTRR Decommissioning Project Radiological Characterization Report, prepared by NES, Inc. This data was used to prepare RWPs and perform ALARA reviews for the decommissioning work packages. In addition to surveys, two core borings were obtained from the biological shield. These borings were sectioned and sent to an off-site laboratory for radiation analysis to determine the extent of activation in the bioshield concrete.

A detailed site inventory of radioactive materials was compiled during the initial site survey. Most of these items were located on the first floor and occupied floor space necessary for decommissioning operations. Empty sealand containers, received from Duratek, were brought into the containment building through the truck door. Radioactive materials that could not be decontaminated to radiological free release limits were packaged and placed in these containers. Once the containers were full they were sealed and transported out of the containment building through the truck door using the polar crane, rollers and a forklift truck. Full sealand containers were temporarily stored on paved or concrete surfaces within the controlled area of the site. A flatbed trailer was used to ship the full sealand containers from the NNRC to Duratek's Bear Creek, Tennessee Facility. Radioactive materials that were received at the Bear Creek facility were either processed for disposal at Envirocare's disposal site in Utah, processed through Duratek's Green Is Clean Safecheck Program for disposal at the Carter's Valley Landfill in Churchhill, TN, or recycled by Duratek. Items in the containment building that were surveyed after decontamination and found to meet radiological free release criteria were removed from the building and placed adjacent to the metal storage building on site.

Reactor dismantlement operations commenced in January 2000. All nonessential electrical components were disconnected at the motor control center, located in the basement. The only components considered essential were the building HEPA filtered ventilation system, the polar crane, and the stack fan. These components remained operational throughout the decommissioning operation. Once power was disconnected from the nonessential components, electricians detached all electrical wire terminations to allow for safe removal of these items by decontamination technicians.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

10

Page 24: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Auxiliary systems, such as the space heating hot water, domestic hot water, chilled water and city water systems, were isolated and tagged out-of-service on the NNRC side of the containment building. Meanwhile, the cold water supply line from the NNRC remained energized while its return line was tagged closed. In addition, the interconnecting compressed air line from the NNRC to the containment building remained open. After these systems were isolated, dismantling operations began in the basement with the removal of three air conditioning units which were contaminated above release limits. These units were cut free from their chilled water lines, transported to the first floor and placed in a sealand container.

In order to provide access to the primary coolant system in the process equipment room, the secondary water system components and piping spool pieces were

unbolted at convenient flange connections and separated from the system. These items were either rigged to the polar crane and lifted out of the basement through the equipment hatch and placed in a sealand container or placed directly in a B-25 box in the basement. The entire secondary water system was removed up to the flange connections adjacent to the containment building penetrations. A blind flange was bolted to the secondary cooling water supply line to minimize water leakage into the process equipment room.

Other systems in the process equipment room, such as the heavy water recombiner, helium makeup system, the overflow return and purification system and the thermal shield cooling system were dismantled by first cutting small bore pipes into manageable sections or unbolting components and pipes at flange connections. Drip containments were used to collect any residual water in the piping systems. Larger components were transported by forklift to the equipment hatch then lifted by polar crane out of the basement and placed directly in sealand containers, while smaller pipe sections or components were placed in B-25 boxes. Once the B-25 boxes were full, they were brought up to the first floor and emptied into an appropriate sealand container.

The primary coolant system was dismantled in a similar fashion. However, the stainless steel components from this system were segregated from other steel components and placed in a separate sealand container. Residual heavy water collected from this system was poured into a separate stainless steel drum and returned to the Department of Energy's Savannah River Site. The large primary coolant system components, such as the heavy water tank and heat exchangers, were rigged to anchors installed in the ceiling and carefully moved with chains and come-alongs to the equipment hatch opening. At this point, these components were rigged to the polar crane, lifted out of the basement and placed in sealand containers for shipment to Duratek's metal melt facility in Bear Creek, Tennessee.

REVISION 0

GA TECH RESEARCH REACTOR FINA-L SURVEY REPORT

11

Page 25: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Primary coolant system piping extended from the process equipment room into the reactor pipe tunnel through a temporary concrete shield wall. This shield wall was demolished with the use of expandable grout and handheld jackhammers. Local HEPA filtered ventilation systems were used to control dust in this area during demolition operations. Concrete pieces were collected by hand and with shovels and then placed in B-25 boxes for future disposal.

The other radioactively contaminated systems located in basement rooms or areas adjacent to the process equipment room were disassembled as described above. The two pneumatic transfer systems (rabbit systems) were separated from their pneumatic tubing and power supplies. Each of these systems was packaged for shipment and transported to a sealand container on the first floor. The bismuth cooling system was cut into manageable pieces, carried to the first floor by elevator or polar crane and placed in the appropriate sealand container.

Wooden timbers were placed under each comer of the biomedical room door to provide support while the door's hydraulic system was disengaged and removed. Hydraulic fluid was drained from the system and collected in clean 55 gallon drums. The hydraulic system was disassembled and removed from the basement area to a sealand container.

On the first floor of the containment building, a neutron diffractometer and a water transfer system (guppy system) were still attached to the reactor. The neutron diffractometer was disassembled by rigging various pieces to the polar crane and placing them in a sealand container. Water was drained from the guppy system and placed in a 55 gallon drum for disposal. The guppy system piping was removed from the horizontal beam port and cut into manageable sections for disposal. Other parts of this system were disassembled and placed in a sealand container.

The air conditioning unit on top of the control room on the second floor of the containment building was cut free from its chilled water lines. It was rigged to the polar crane and transferred from the top of the control room to a sealand container. An auxiliary fan which provided additional cooling air flow to the control room was disassembled and removed. An Emergency Core Cooling System (ECCS) which was connected to the reactor was also located on the second floor of the containment building. The ECCS tank was situated on a platform above the second floor catwalk. Piping to this tank was cut and the tank was lifted off the platform with the polar crane. Piping from the ECCS tank to the reactor was cut into manageable lengths and placed in a sealand container along with the ECCS tank.

Dismantlement of the reactor itself commenced in March, 2000, once all the connecting pipes and components were removed. The horizontal beam port plugs were pulled out of each of the horizontal beam ports. The horizontal beam gates were lifted from the top of the reactor with the polar crane and all graphite plugs

REVISION 0

FINAL SURVEY REPORTGA TECHt RESEARCH REACTOR

12

Page 26: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

were removed from the horizontal beam ports with long handle tools. The horizontal beam port aluminum thimbles were extracted with long handle tools or chains and come-alongs. Fission chambers and other nuclear instruments were removed from their horizontal ports around the base of the reactor. The polar crane was used to lift plugs and aluminum thimbles out of each of the vertical experimental ports from the top of the reactor. Graphite plugs were placed in B-25 boxes and the fission chambers were stored in a 55 gallon drum, while all other metal items were placed in sealand containers.

A nuclear startup source was located within one of the vertical experimental ports. It was removed from the reactor with the assistance of the fuel transfer cask in order to minimize radiation exposure to personnel. The fuel transfer cask was transported by polar crane to the top of the reactor and situated over the vertical port. The sliding door of the cask was opened and a hook was lowered to retrieve the startup source. Once the startup source was engaged, it was raised into the fuel transfer cask and the entire assembly was lowered to the first floor by polar crane. At this point, the startup source was lowered just enough to allow the very end of the assembly to be cut and placed in a shielded lead container for temporary storage. The remainder of the assembly was retrieved from the fuel transfer cask and placed in a sealand container.

Eyebolts were installed in the reactor lead cover plate. It was rigged to the polar crane and removed from the top of the reactor. The reactor's upper top shield was rigged in a similar fashion and hoisted by the polar crane. Both of these components were placed in sealand containers for shipment to Duratek.

The drive mechanism for the regulating rod, which was located on the outside wall of the bioshield, was electrically disconnected and mechanically disassembled. Once the regulating rod was released from its drive mechanism, it was slowly extracted with the polar crane, from the reactor vessel, through the lower top shield. The regulating rod was placed on top of the reactor and covered with lead blankets to reduce radiation exposure. It was cut into two sections with a band saw. The lower section, which contained cadmium was transferred to the plug storage vault for temporary storage, while the upper section was placed in a sealand container.

Eyebolts were inserted into the lower top shield and it was rigged to the polar crane., The lower top shield was carefully raised from the reactor and lowered through the equipment hatch into a containment area built in the process equipment room in the basement. IT Corporation subcontracted Bluegrass Concrete Cutting Inc. to cut the lower top shield into two sections with a diamond wire saw within this containment area. The bottom section, which contained approximately 8 inches of lead shielding material and had a significant radiation dose rate associated with the bottom plate, was separated from the remaining nonradioactive section. After the cut was completed, the two pieces of the lower top shield were placed in appropriate sealand containers for shipment to Duratek.

REVISION 0

FINAL SURVEY REPORT

13

Page 27: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

The shim safety drive mechanisms were uncoupled from the shim safety blades in

the same fashion as the regulating rod. Once each shim safety blade was released

from its drive mechanism, it was extracted from the reactor vessel and placed under lead blankets on top of the bioshield. The lower section of each shim safety

blade, which contained cadmium, was separated from the remainder of the rod and placed in the plug storage vault for temporary storage. The upper section was

transferred to a sealand container.

Three biomedical room shutter shield blocks were pulled out of their shaft enclosure using eyebolts and the polar crane. Prior to lifting the last shield block, the hydraulic cylinder, which operated the biomedical room shutter, was disconnected from the bottom of this block. Once this shield block was removed, hydraulic fluid was drained from the cylinder and collected in a clean 55 gallon

drum. The cylinder was disassembled and placed in a sealand container. Bismuth shield blocks were extracted from the biomedical room window with a special

lifting tool supported by the polar crane. The bismuth shield cooling water

system pipes were cut and placed in the appropriate sealand container.

After completion of an inspection to verify that the reactor vessel's horizontal ports, pipe extensions and other connections were free from any obstruction, the

vessel was rigged to the polar crane. The reactor vessel was slowly pulled out of

the bioshield and surveyed. Since the top portion of the vessel was not activated, it was cut with a circular saw and transferred into a sealand container. The

remaining bottom section of the reactor vessel was subsequently pulled completely out of the bioshield and laid on its side in an empty sealand container.

The reactor vessel's pipe extensions were carefully cut with a long handle tool

close to the bottom of the vessel. Meanwhile, the graphite retaining sleeve was

removed from the bioshield cavity. It was immediately transferred into a radioactive waste shipping liner. The shipping liner was located behind a temporary shield wall to minimize radiation exposure to personnel, as this liner

was to receive all the highly radioactive components. Once the pipe extensions were removed from the bottom of the reactor vessel, the vessel was rigged to the

polar crane and transferred from the sealand container to the radioactive waste

shipping liner. The above pipe extensions, the startup source and other highly

radioactive components were retrieved from various temporary storage containers

and placed inside the shipping liner. After the shipping liner was filled, it was

sealed and prepared for shipment to Chem Nuclear's (CNSI) Barnwell, South

Carolina disposal facility. A separate shielded cask shipment was made for this purpose.

Decommissioning activities continued in April, 2000, with the mechanical

removal of the thermal column doors. Once the graphite blocks and stringers

were uncovered, a containment tent complete with HEPA filtered ventilation was

constructed around the thermal column opening to minimize the spread of

graphite dust and radioactive contamination. Graphite blocks and graphite

stringers were removed by hand from the thermal column opening toward the

REVISION 0

FINqAL SURVEY REPORT

14

Page 28: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

center of the bioshield. The graphite stringers were packaged in B-25 boxes inside the containment tent. When the boxes were full, graphite removal operations were temporarily suspended to allow replacement of full boxes with empty ones inside the containment tent. It was discovered that the graphite closest to the reactor vessel was activated and required segregation from other graphite for disposal purposes. These graphite stringers, with higher radiation levels, were placed in separate B-25 boxes and shipped directly to Chem Nuclear's Barnwell, South Carolina disposal site.

In June, 2000, the outer steel plate walls of the bioshield were sectioned into 4' x

8' or 4' x 4' pieces. A needle gun was used to scrape the lead based paint off the

steel plate surfaces along anticipated cut lines. The steel plate was cut with an oxy-gasoline torch and pried loose from the bioshield concrete with a hoe-ram and placed in sealand containers. Other metal items that were temporarily stored in the plug storage vault, such as the cadmium ends of the shim safety blades and regulating rod were also placed in this sealand container and shipped to Duratek's metal melt facility.

Once the steel plate was removed from the concrete bioshield, a containment tent was constructed inside the containment building. The purpose of this tent was to minimize the spread of concrete dust and contamination during subsequent bioshield concrete demolition operations. The containment tent roof was supported by the polar crane hook, while the tent walls hung from the second floor catwalk railing down to the first floor. The tent surrounded the entire concrete bioshield and provided enough space on the first floor for heavy concrete demolition equipment. The containment tent was equipped with five HEPA filtered ventilation units and a water mist system for dust suppression. An exhaust system was also installed inside the tent to remove combustion gases from the operating equipment and minimize the buildup of carbon monoxide (CO) gas. A track hoe and a back hoe each equipped with a hoe-ram attachment were employed to demolish the bioshield concrete. Based on the bioshield core sample analytical results, concrete was removed in layers. The bioshield outer concrete, extending to the center line of the horizontal beam gate vertical inserts, was demolished first. This concrete contained very little radioactivity. The second pass with the hoe-ram demolished the remaining concrete up to the outer walls of the lead shield tank. Once a pile of concrete rubble was produced by the hoe-rams, a front end loader mounted on a Bobcat scooped up the rubble and placed it in B-25 boxes. The boxes were sealed, weighed and removed from the containment building by forklift for future shipment to Duratek. At Duratek's Bear Creek, Tennessee facility the B-25 boxes were analyzed for radioactivity and segregated for disposal either at Envirocare's site in Utah or at a local approved Tennessee landfill.

When most of the bioshield concrete was removed, a hydraulic shear attachment was mounted on the track hoe. The hydraulic shear cut and detached the remaining metal components of the horizontal beam ports, vertical experimental

REVISION 0

FINAL SURVEY REPORT

15

Page 29: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

ports, spent fuel holes, reactor vessel support structure and any other structural steel from the top and outer walls of the lead shield tank. All these metal items were stockpiled in the containment tent until a sealand container was brought into the building. Any residual concrete that was hidden by these components was

removed by the back hoe mounted hoe-ram. Upon completion of the bioshield concrete demolition, the containment tent was removed along with the heavy

construction equipment to allow the polar crane to load metal debris into a sealand container.

Bolts that held the lead shield tank lid in place were cut with a portable saw. The

lead shield tank lid was rigged to the polar crane and transferred to the floor. It

was shrink wrapped in plastic and prepared for shipment to Duratek.

IT Corporation subcontracted the Barnhart Crane and Rigging Co. (Barnhart) in October, 2000 to remove the lead shield tank from the containment building. Barnhart installed a gantry hydraulic lift system on the first floor. The lead shield

tank was rigged to the gantry and slowly hoisted out of the depression in the first

floor. Once it was above the floor elevation, the lead shield tank was carried by

the gantry lift along the system tracks towards the truck door. At this location, the

lead shield tank was surveyed, prepared for shipment and shrink wrapped in

plastic. The tank was rotated 90 degrees and transferred out of the containment building with forklift trucks. After it was brought outside, it was wrapped once

again in plastic and transported by two heavy lift forklifts to an overweight load bearing lowboy trailer. The lead shield tank was placed on the trailer and transported to Duratek's facility in Tennessee.

Activated concrete in the area beneath the lead shield tank was removed with the

back hoe mounted hoe-ram. Local HEPA filtered ventilation was used to control

dust during this concrete demolition. A steel template that aligned the reactor

bottom nozzles was removed from this area by the hoe-ram. This created a large opening into the reactor pipe tunnel. Concrete debris was retrieved from the reactor pipe tunnel area and placed in a B-25 box while the metal plate was placed in a sealand container.

The plug storage vault was examined to insure that all holes were empty and clean. Caps were secured to each vault hole. The entire plug storage vault was

extracted from its wall cavity in November 2000 with a forklift truck and the

polar crane. The vault was prepared for shipment and transferred out of the

building through the truck door. It was shipped on a flatbed truck to Duratek.

The spent fuel storage hole located within a structural column in the process equipment room was contaminated above the site release limits. This hole

extended 19' 3t" from the first floor into the basement concrete slab. A chemical

decontamination process was tested in a NNRC laboratory to check its effectiveness on the stainless steel surfaces of the spent fuel storage hole. The test

results were promising, so a chemical decontamination loop was built in the

REVISION 0

FINAL SURVEY REPORT

16

Page 30: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

process equipment room complete with chemical injection tanks, a heater and a recirculation pump. Chemicals were mixed in the chemical tanks and injected into the spent fuel storage hole. The solution was heated and circulated for a short period of time. The acidic chemical decontamination process was applied a total of three times. The spent chemical solution was neutralized with caustic and pumped into 55-gallon drums for shipment to Duratek. Radiation survey results, however, indicated that the very bottom plate of the spent fuel storage hole was still above the site release limits. Mechanical decontamination methods were attempted but proved ineffective on the very bottom plate. A remotely operated electrical hoe-ram was employed to break up the concrete floor in the area adjacent to the column to gain access to the bottom plate. The hoe-ram successfully punctured the outer wall of the spent fuel storage hole pipe and severed the bottom plate from the remainder of the pipe. This plate was retrieved and transferred to an appropriate sealand container, while the concrete debris was placed in B-25 boxes.

The reactor building sump was tagged out-of -service and disconnected from the low-level radioactive waste system. The sump pump and discharge piping were removed from the basement elevation. The remaining sludge in the sump was pumped into 55-gallon drums for disposal by Duratek. Basement drain lines that directed water to the sump were flushed with high pressure water to remove any residual contamination and debris. This water was collected in 55 gallon drums and processed for disposal by Duratek.

Sections of the ventilation system were removed during demolition activities to allow future access for survey instruments. All ducts that were removed were placed in sealand containers, except for the elbow that connected the holdup duct to the HEPA filtered ventilation system. This elbow was detached, surveyed and left in the building for future reuse.

When decommissioning activities were complete, Duratek commenced informational radiation surveys of floor and wall surfaces to verify that these surfaces met the final release criteria. Several locations throughout the containment building required further concrete removal in order to achieve the release criteria. These areas included portions of the process equipment room floor and walls, the heavy water storage tank pit floor and walls, the reactor pipe tunnel floor and wall surfaces, the rupture disk pipe tunnel area, the biomedical facility shutter block shaft and floor area, the biomedical facility door hydraulic sump area, the biomedical room floor and spots on the first and second floors of the containment building. Angel grinders, needle guns and, as necessary, jack hammers were employed to remove concrete from these contaminated areas. Local HEPA filtered ventilation was used during these operations to minimize the spread of contamination and suppress concrete dust.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

17

Page 31: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

During the informational survey of the reactor pipe tunnel in January, 2001, Duratek discovered that the overpressure pipe chase walls were above the site release criteria. It was determined that the concrete in these walls was activated. Expandable grout was used to fracture the concrete and assist with its removal. Electric chisels and hammers were utilized to complete the concrete demolition in this area. Up to an additional 12 inches of concrete was taken out of the walls in the overpressure pipe chase.

When all decommissioning activities in the containment building were complete, the containment building's service air system was dismantled. The interconnecting service air pipe was isolated on the NNRC side of the containment building and capped in the basement. The containment building air isolation valves were placed in an open position, to allow air to circulate through the building, while the service air operators for these valves were removed. The air receiver tanks were depressurized and transported to a sealand container. The service air compressors located in the basement were dismantled and transferred to the first floor. Service air pipe was cut into manageable pieces and removed from the containment building in B-25 boxes. The inflatable rubber seals of the main air lock, the personnel air lock and the truck door were unbolted and removed.

Fifty-six (56) total radioactive waste shipments were made during the GTRR decommissioning. The final waste shipment occurred on August 3, 2001. All radioactive waste was sent to one of four consignees. The radioactive waste consignees were Duratek Inc., CNSI Barnwell, Envirocare of Utah, and Westinghouse Savannah River Site. Table 2.1 shows the total weight shipped to each of the four consignees.

Final Surveys began in May, 2001. The survey method and results are presented in the following sections.

TABLE 2.1 Georgia Tech Waste Disposition

WASTE COSIGNEE WASTE WEIGHT (LBS) Duratek 1,574,865 lbs

CNSI-Barnwell 59,364 lbs Envirocare 840 lbs

Westinghouse SRS 500 lbs

REVISION 0

FINAL SURVEY REPORT

18

Page 32: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

FIGURE 2.5 SITE LAYOUT

ACCESS GATE

OFFICE 1 TRAILERS

RETAINING

REVISION 0

FINAL SURVEY REPORT

19

Page 33: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

3.0 FINAL SURVEY

3.1 Introduction

The purpose of the Final Survey Report is to demonstrate that the GTRR facility meets the guideline values established for release for unrestricted use. This required the collection of accurate and reliable data to determine residual activity levels. The Final Survey was performed in accordance with GTRR projectspecific procedures and the Final Survey Plan.

Implementation of the Final Survey included the following:

" Duratek supervisory personnel performed a preliminary inspection of the survey areas to identify survey requirements, including special survey situations, and to provide specific survey instructions.

"* A survey package was prepared for each survey area.

"* Suspect Affected survey areas were gridded to provide a systematic method for the collection of survey data.

"* Each survey area had a sufficient number of measurements taken to accurately represent the surface being surveyed.

"* Survey locations were marked and mapped in all non-gridded areas.

" Survey measurements were performed and samples analyzed using appropriately calibrated instrumentation. Daily source and background checks were carried out before and after each day's work.

"* Survey data collected during the final survey was downloaded from the survey instrument into a database for storage and processing.

" Completed survey packages were reviewed by supervisory personnel to ensure that all required surveys were performed and that the packages contained all necessary information.

" Survey results were reviewed by supervisory personnel to verify that the criteria for release for unrestricted use were not exceeded. Areas of residual activity were identified, evaluated, and reclassified as required.

REVISION 0

FINAL SURVEY REPORT

20

Page 34: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

3.2 Survey Guideline Values

3.2.1 Criteria for Release for Unrestricted Use for Building Surfaces

Site Specific Guideline Values, SPGLs, were derived for use in demonstrating that the Georgia Tech Research Reactor met the criteria for release for unrestricted use. These SPGLs were based on the radionuclide specific guideline values contained in NRC Regulatory Guide 1.86 except for H-3 and Fe-55. The guideline values for H-3 and Fe-55 were increased based on instructions from the Executive Engineer for this project (Reference 6.4). The increase in guideline values for H-3 and Fe-55 was consistent with previous NRC policy contained in NRC Policy Memorandum SECY-94-145. Although higher than the NRC Regulatory Guide 1.86 limits, these increased guideline values are orders of magnitude lower than the current guideline values for H-3 and Fe-55 specified in the NRC License Termination Rule. Table 3.1 lists the radionuclide specific guidelines used in deriving the SPGLs. With the exception of footnote "f', the footnotes to Table 3.1 are identical to those associated with Table 1 of Regulatory Guide 1.86.

REVISION 021

GA TECH RESEARCH REACTOR

Page 35: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Table 3.1 Radionuclide Specific Guideline Values

u-.NaT, u-/.5), u-zia, ana associaTea decay products

'Where surface contamination by both alpha and beta-gamma emitting nuclides exists, the limits established for alpha and beta-gamma emitting nuclides should apply independently. bAs used in this table, dpm (disintegrations per minute) means the rate of emissions by radioactive material as determined by correcting the counts per minute observed by an appropriate detector for background, efficiency, and geometric factors associated with the instrumentation. cMeasurements of average contaminant should not be averaged over more than 1 square meter. For objects of less surface area, the average should be derived for each object. dThe maximum contamination level applies to an area of not more than 100 cm 2. eThe amount of removable radioactive material per 100 cm2 of surface area should be determined by wiping that

area with dry filter or soft absorbent paper, applying moderate pressure, and assessing the amount of radioactive material on the wipe with an appropriate instrument of known efficiency. When removable contamination on objects of less surface area is determined, the pertinent levels should be reduced proportionally and the entire surface should be wiped. f Letter from Executive Engineer to IT Corporation dated 4/18/00 providing alternate H-3 and Fe-55 guidelines for the Ga Tech Research Reactor Decommissioning (Reference 6. 4). Removable contamination to be assessed as described in Footnote e, except using a wet smear.

REVISION 0

Transuranics, Ra-226, Ra-228, 100 dpm/100 cm 2 300 dpm/100 cm 2 20 dpm/100 cm 2

Th-230, Th-228, Pa-231, Ac-227, I125, 1-129 Th-Nat, Th-232, Sr-90, Ra-223, 1,000 dpm/100 cm 2 3,000 dpm/100 cm 2 200 dpm/100 cm 2

Ra-224, U-232, 1-126, 1-131, 1-133 H-3 and Fe-55f 200,000 dpm/100 cm 2 600,000 dprr/100 cm 2 10,000 dpm/100 cm 2

Beta-gamma emitters (nuclides with 5,000 dpm /100 cm 2 15,000 dpm /100 cm 2 1,000 dpm /100 cm 2

decay modes other than alpha emission or spontaneous fission) except Sr-90 and others mentioned above

22

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Page 36: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

3.2.2 Site Specific Guideline Values, SPGLs

The site specific guideline values for demonstrating that the Georgia Tech Research Reactor facility met the criteria for release for unrestricted use were derived based on guidance contained in NUREG/CR-5849, the radionuclide specific guideline values listed in Table 3.1, and the actual radionuclide mix as determined by sample analysis. The SPGLs were calculated using the following formula:

F SPGL = n fi

i~i

Where: F = the fraction of the assumed radionuclide mix that is

considered detectable, unitless.

fi = the relative fraction of radionuclide i, unitless.

GLi = the radionuclide specific guideline value for radionuclide i taken from Table 3.1, dpm/100 cm2 .

n - the number of radionuclides present in the radionuclide mix.

Site specific guideline values for total beta activity and removable beta activity were calculated according to the above formula using the sample analysis results from three samples collected within the Georgia Tech Research Reactor Containment Building. Attachment A contains the spreadsheets used to perform these calculations. The results of these calculations are summarized in Table 3.2.

REVISION 023

Page 37: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Table 3.2 Site Specific Guideline Values

for Total Beta Activity and Removable Beta Activity

Sapl Dscitiu PG dpm7100 cm) SPGL (dpmi/1O CM2)

GEL- 1, Concrete Sample From 1,500 104 Under Reactor Vessel

GEL-2, Concrete Sample From Pit 3,800 688 Beneath Door To Biomedical

Room GEL-3, Primary Coolant Resin 2,000 148

Sample AVERAGE 2,400 313

In order to demonstrate compliance with the criteria for release for unrestricted use, the three sample SPGL's listed in Table 3.2 were averaged for a site SPGL.

3.2.3 Criteria for Release for Unrestricted Use of Open Land Areas

Under Subpart E, of 10 CFR 20.1402, NRC licenses may be terminated and a site released for unrestricted use if the residual radioactivity that is distinguishable from background results in a total effective dose equivalent, TEDE, that does not exceed 25 mrem/yr and the residual radioactivity has been reduced to levels that are as low as reasonably achievable, ALARA. NRC has published (Federal Register Vol. 64 page 68396, December 7, 1999) screening values for selected radionuclides in surface soils. Open land areas with activity concentrations less than the screening values are deemed to be in compliance with the 25 mrem/yr unrestricted release dose limit in 10 CFR 20.1402.

Table 3.3 lists screening values for the GTRR radionuclides of interest. These values were either published by the NRC or calculated using NRC methodology. These screening values were used as the site specific guideline values for open land areas. Surface soil samples (0-6 inches) were collected from open land areas within the reactor yard and compared to the criteria listed in Table 3.3. These soil samples were used to confirm the results of the characterization survey and demonstrate that the open land areas within the reactor yard fence met the criteria for release for unrestricted use and that the levels are ALARA.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

24

Page 38: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

r-A TECH RESE ARCH REACTORFNASUVYRPT

Table 3.3 Radionuclide Specific Soil GuidelineValues

H-3 110

Fe-55 10,000

Pu-239/240 2.3

U-233/234 13.0

U-238 14.0

Ni-59 5,500

Cs-134 5.7

Cs-137 11.0

Co-60 3.8

Eu-152 8.7

Eu-154 8.0

Mn-54 15.0

Ag-ll0m 3.9

Zn-65 6.2

Sr-90 1.7

C-14 12.0

Ni-63 2,100

Tc-99 19.0

3.3 Instrumentation

Selection and use of instrumentation ensured sensitivities were sufficient to detect the radionuclides of interest at the required minimum detectable activities. A list

of the instruments, types of radiation detected, and their calibration sources is provided in Table 3.4.

The Ludlum Model 2350 Data Logger and various detectors were used for direct surface and exposure rate measurements. The data logger is a micro-processor computer based counting instrument designed for use with a wide range of detectors. NaI(T1) scintillation, gas-flow proportional detectors, and GM detectors were used to obtain field measurements for Final Surveys.

REVISION 0

FINAL SURVEY REPORT

25

Page 39: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

Detector selection depended on the survey to be performed, surface contour and survey area size. For direct measurements, the 126 cm 2 gas-flow proportional detector was normally used. A 1" x 1" NaI(Tl) gamma scintillation detector was used for gamma exposure rate measurements.

Specialized gas-flow proportional and GM pipe detectors were used in conjunction with a Ludlum Model 2350 to survey the interior surfaces of drains, piping, and penetrations remaining in the GTRR facility.

Smears for removable alpha and beta contamination were analyzed using a Protean Low Background Alpha/Beta Counter or equivalent.

Smears for removable low energy beta emitters such as H-3 were analyzed using a Beckman Liquid Scintillation System.

An EG&G Ortec Gamma Spectroscopy System, or equivalent, was used for gamma isotopic identification and quantification.

Table 3.4 Final Survey Instrumentation

REVISION 0

Detector TRadiatin 1Clbation Instrument/Detector jType jDetecte Souce jUse

Ludlum Model 2350/43-68 Gas-flow proportional Beta 99Tc ([) Direct measurements (126 cm2)

Ludlum Model 2350/44-2 NaI scintillator Gamma 137 Cs Gamma exposure rate

Ludlum Model 2350/44-40 Shielded GM (15.5 cm2) Beta 99Tc ([) Direct measurements

Ludlum Model 2350/43-94 and Gas-flow proportional pipe Beta 9 9Tc (•) Direct measurements Ludlum Model 2350/43-98 detectors inside pipes

Protean Low Background Gas-Proportional Alpha and 230Th (C) Smear counting Planchet Counter Beta 99Tc (P)

Beckman Liquid Scintillation Liquid Scintillation Beta 3H ([) Tritium Analysis

System Low Energy

Gamma Spectroscopy System HPGe Gamma Mixed Nuclide identification Gamma and quantification

FINAL SURVEY REPORT

26

Page 40: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

3.3.1 Instrument Calibration

Data loggers and associated detectors were calibrated on a semi-annual basis using National Institute of Standards and Technology (NIST) traceable sources and calibration equipment.

The data logger calibration included:

* High Voltage calibration * Discriminator/threshold calibration * Window calibration * Alarm operation verification * Scaler calibration verification

The detector calibration included:

* Operating voltage determination * Calibration constant determination * Dead time correction determination

Calibration labels showing instrument identification number, calibration date and calibration due date were attached to all field instrumentation. The presence of a current calibration label was verified by the user before each use.

3.3.2 Sources

All sources used for calibration or efficiency determinations for the survey were selected to be representative of the instrument's response to the identified nuclides and were traceable to NIST.

Radioactive sources used for instrument response checks and efficiency determination were controlled by health physics technicians. Sources were stored securely and were issued to survey technicians as needed in the field.

3.3.3 Minimum Detectable Activity

Minimum Detectable Activity (MDA) is defined as the smallest amount or concentration of radioactive material in a sample that will yield a net positive count with a 5% probability of falsely interpreting background responses as true activity. The MDA value is dependent upon the counting time, geometry, sample size, detector efficiency and background count rate. The equation used for calculating the MDA for field instrumentation is:

REVISION 0

GA TECH RESEARCH REACTOR

27

Page 41: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

2.71 +32 Rbb MDA- tS ts tb

A

100

Where: MDA =

Rb =

tb =

ts

E A -

Minimum Detectable Activity (dpm/100 cm) Background Count Rate (cpm) Background Count Time (min) Sample Count Time (min) Detector Efficiency (counts/disintegration) Detector Area (cm2)

The a priori MDAs for the final survey were set at, or less than, 25% of the Site Specific Guideline Value. Table 3.5 provides the a priori MDA's that were established for the GTRR Final Survey. Count times were established up to a maximum of I minute, such that, in areas where background exposure rates allowed, these MDA's were achieved.

Table 3.5 Field and Laboratory Instrumentation MDA's

Direct Beta Surveys 600 dpm/1 O0 cm2

Removable Beta Surveys 75 dpm/100 cm2

Removable Alpha Surveys 15 dpm/1 00 cm2

Gamma Spec (Co-60, Cs-137) 0.1 pCi/g

Removable H-3 Surveys 200 dpm/1 00 cm2

Note ': Actual values varied based on count times, background, efficiency, etc. Refer to the individual survey packages for an estimate of the MDAs achieved.

The a priori MDAs for laboratory instruments were established at the 95% confidence level. MDAs were determined from the instrument supplied software algorithms or analysis spreadsheets using the above MDA equation. Count times used for the Protean Alpha-Beta Counter, the Ortek Gamma Spectroscopy System, and the Beckman Liquid Scintillation Counter were established to ensure that the desired MDA sensitivity was achieved. Background analysis and QC checks were performed daily to monitor for changes that would affect the MDA.

REVISION 0

FINAL SURVEY REPORT

28

Page 42: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

3.4 Survey Organization

The Duratek Survey Supervisor reported to the IT Project Manager, who in turn reported to the Executive Engineer technically, and the Georgia State Financing and Investment Commission (GSFIC) contractually.

The on-site project survey team was supported by the resources of Duratek's Corporate Office. Additional oversight and support from Duratek's professional engineering and quality assurance staff was provided, as necessary, to the Duratek Survey Supervisor. Independent oversight was provided by the IT Quality Assurance Manager in accordance with the Quality Assurance Project Plan & Quality Assurance Procedures for the Georgia Institute of Technology Research Reactor Decommissioning Project.

Survey teams consisted of personnel trained, qualified, and experienced in field radiological survey procedures.

3.5 Survey Design

For the purpose of conducting the Final Survey at the GTRR facility, the survey areas were classified into three different categories. First, the survey areas were divided into Affected and Unaffected Areas based upon the initial characterization surveys, remedial actions, and historical information. Affected Areas were then subdivided into Suspect and Non-Suspect Areas. Each area was designated as a specific survey area and subdivided as necessary to facilitate the performance of Final Surveys. Large areas were subdivided into several survey units, and small like areas located on the same floor were combined into one survey unit. Equipment present in a survey area would normally be included within that area and was classified accordingly. However, each piece of equipment was evaluated and appropriately classified as determined by the Survey Supervisor based on initial survey and post-remediation survey data.

3.5.1 Unaffected Areas

An Unaffected Area was defined as any area where there was no known history of the storage or use of unsealed licensed radioactive material. Survey results that indicate the presence of radioactive material or contamination precluded an area from being classified as Unaffected.

3.5.2 Non-Suspect Affected Areas

A Non-Suspect Affected Area was defined as upper walls and overhead areas above two meters in an Affected area with minimal contamination potential based upon a review of the processes, history of the area, and characterization survey results. Survey results in excess of 25% of the

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

29

Page 43: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

site-specific guideline values (SPGLs) precluded an area from being classified as Non-Suspect Affected.

3.5.3 Suspect Affected Areas

A Suspect Affected Area was defined as an area not meeting the requirements specified for Unaffected and Non- Suspect Affected areas. Upper walls and overhead surfaces above two meters with survey results in excess of 25% the SPGLs were classified as Suspect Affected, except for the containment ceiling insulation which was reclassified if the survey results were in excess of 50% of the SPGLs.

3.5.4 Survey Area Breakdown

The following is the survey area breakdown for the performance of final surveys at the Ga. Tech Research Facility.

* Unaffected Areas

- Reactor yard areas not classified as affected (package 9) - Exterior surfaces of the Reactor Building (package 10) - Reactor yard open land areas (package 14) - Elevator equipment room and elevator shaft (package 21)

* Non-Suspect Affected Areas

- Reactor building 2nd floor upper walls (above 2 meters) and dome (package 3)

- Reactor building 1lt floor upper walls (package 5) - Reactor building basement, process equipment room upper walls

and ceiling (package 13) - Reactor building basement outside the process equipment room

above 2 meters (package 17) - Reactor building ventilation system and stack above 2 meters

(package 20)

0 Suspect Affected Areas

- Helium and reactor cooling water lines (package 1) - Reactor building 2nd floor and walls below 2 meters (package 2) - Reactor building 1lt floor and lower walls (package 4) - Reactor building ventilation hold-up duct (package 6) - Reactor building ventilation system and stack below 2 meters

(package 7) - Reactor yard areas used for the storage of radioactive materials

(package 8)

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

30

Page 44: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

- Basement drain lines (package 11) - Reactor building basement, process equipment room, floor and

lower walls (package 12) - Compressor Room (package 15) - Reactor building basement outside the process equipment room

floor and lower walls, including the reactor building sump (package 16)

- Vessel Tunnel (package 18) - Bismuth Leak Area (package 19) - Miscellaneous piping and penetrations inside reactor building

(package 22)

3.6 Area Re-Classification and Investigation

If during performance of the Final Survey, survey results indicated the presence of contamination in excess of 25% of the SPGL in an unaffected area, or survey results in excess of 50% of the SPGL on the containment ceiling insulation, or in excess of 25% of the SPGL in any additional non-suspect affected areas, the area, or a part thereof, was classified as a suspect affected area and an investigative survey performed. The investigative survey consisted of surveying the surrounding 9 square meters of the elevated survey point as if it were a suspect affected area.

3.7 Survey Package Development

A survey package was developed for each survey area. A walk-down of the area was performed, and a worksheet prepared containing a description of the survey area, historical information (as available), general survey instructions, location codes, specific survey instructions for any abnormal conditions within the survey area, and completion and review signature blocks.

During the survey, the packages were updated with direct and removable contamination survey data, exposure rate survey data, and results of any special surveys or sample analyses performed. These survey packages are summarized in section 4.0 Survey Results. The completed packages can be found in Attachment B of this report.

3.8 Survey Requirements

The Final Survey protocol was designed in part with NUREG/CR-5849 and other NRC approved final survey plans used at other Decommissioning and Decontamination projects as follows.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

31

Page 45: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

3.8.1 Suspect Affected Areas

* 100% scan of the affected surface for beta contamination to identify areas of elevated activity requiring further investigation.

0 One direct measurement for each 1 m2 of area for total beta contamination. The floors and lower walls were gridded depending upon the number of interferences in the areas.

One measurement for each 1 m2 of area for removable beta and alpha contamination.

One exposure rate measurement at 1 meter above the floor at corresponding direct measurement locations to identify any areas with elevated radiation levels relative to the normal background that required additional investigation. Exposure rate measurements were not collected above obstructed measurement locations (obstructions due to equipment, permanent structures, etc.).

3.8.2 Non-Suspect Affected Areas

"* A 10% scan for beta contamination on building surfaces to identify areas of elevated activity requiring further investigation. The actual scanning coverage required for each non-suspect affected survey area (i.e. upper walls and ceilings) was dependent upon the contamination potential for these surfaces and was specified by the Survey Supervisor to the Survey Technician. The locations for scanning were chosen by the technician performing the survey, and were based on most probable areas for contamination.

"* Minimum of one measurement for fixed beta, and removable alpha and beta contamination per 20 M2, or 30 measurements, whichever was the greater for each survey area.

"* Additional measurements for direct beta, and removable alpha and

beta contamination on area equipment and structures, if applicable.

3.8.3 Unaffected Areas

A 10% scan for beta contamination on building surfaces to identify areas of elevated activity requiring further investigation. The locations for scanning were chosen by the technician performing the survey, and were based on most probable areas for contamination.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

32

Page 46: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

"* Minimum of one measurement for fixed beta, and removable alpha and beta contamination per 50 M2 , or 30 measurements, whichever was the greater for each survey area.

"* One exposure rate measurement at 1 meter above the floor at corresponding direct measurement locations to identify any areas with elevated radiation levels relative to the normal background that required additional investigation. Exposure rate measurements were not collected above obstructed measurement locations (obstructions due to equipment, permanent structures, etc.).

"* Random measurements for direct beta, and removable alpha and beta contamination on area equipment and structures, including measurements in locations where contamination could likely accumulate.

"* Open land areas in the yard received a gamma scan covering at least

10% of the accessible areas. In addition, a minimum of 30 surface (0-6 inches) soil samples were collected at biased locations. The

RSO and EE approved the biased soil sample locations prior to collection of samples.

3.9 Gridding

The Final Survey Plan specified a gridded survey method for affected area floors

and lower walls. For affected areas where gridding could not be performed, the

areas were measured and evenly spaced measurements taken and marked at a

frequency of 1 measurement per square meter.

Unaffected and Non-Suspected Affected areas were not gridded. Each survey

point location was marked and mapped identifying the approximate survey location.

3.10 Quality Assurance and Quality Control

The GTRR project Quality Assurance Program was constructed to ensure that all

quality and regulatory requirements were satisfied. All activities affecting quality

were controlled by project procedures and the Project Quality Assurance Plan.

These procedures ensured that the appropriate equipment, environmental conditions, quality controls and prerequisites for any given activity were met. The

following Quality Control measures were implemented as an integral part of the

final release survey process.

REVISION 0

FINAL SURVEY REPORT

33

Page 47: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

3.10.1 Selection of Personnel

Final Survey supervisory personnel were required to have extensive experience and familiarity with survey procedures and processes, including NUREG/CR-5849 and the Final Survey Plan. They were required to have prior experience with the radionuclide(s) of concern and a working knowledge of the instruments used to detect the radionuclides on site. The Survey Supervisor had to have a minimum of five years of experience in performing and supervising final release surveys where NUREG/CR-5849 guidelines were implemented.

The selection of supervisory personnel to direct the survey was based upon their experience and familiarity with the survey procedures and processes. Likewise, Health Physics Technicians who performed the surveys were selected based upon their qualifications and experience.

3.10.2 Written Procedures

All survey tasks which were essential to survey data quality were controlled by project procedures.

3.10.3 Instrumentation Selection, Calibration and Operation

Duratek selected instruments proven to reliably detect the radionuclides present at the GTRR. Laboratory counting instruments (i.e. Protean Alpha/Beta Counter, Beckman Liquid Scintillation Unit, and EG&G Ortec Gamma Spectroscopy System) were calibrated on-site using calibrated sources traceable to National Institute of Standards and Technology (NIST). All other instruments were calibrated off-site by Duratek or qualified vendors under approved procedures using calibration sources traceable to the National Institute of Standards and Technology (NIST). All instruments brought to the GTRR project site had current calibration certificates.

All detectors were subject to daily response checks when in use. Measurements were performed using approved written procedures for each instrument. Issue, control and accountability of all survey instrumentation were established by an instrumentation control procedure. Procedures for calibration, maintenance, accountability, operation and quality control of radiation detection instruments were written to implement the guidelines established in American National Standard Institute (ANSI) standard ANSI N323-1978 and ANSI N42.17A-1989.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

34

Page 48: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

3.11 Documentation

Records of surveys were maintained in a separate survey package for each survey area in accordance with project procedures. The specific records that were compiled in a survey package were:

" Survey Package Worksheet giving the package identification, survey location information, historical information of area surveyed, general survey instructions and any specific survey instructions.

" Survey Comment Addendum provided for comments from the survey technician regarding any unusual situation that was encountered while surveying, as applicable.

"* The Survey Unit Diagram of the area that was surveyed, as available. Survey grids were represented on the drawing.

"* Printouts of laboratory analysis results.

"* Ludlum Model 2350 data files and Paradox® converted values for all radiation survey measurements.

Survey measurements were taken using the Ludlum Model 2350 Data Logger system. Upon completion of an individual survey unit or combination of units, the contents of the data logger's memory were downloaded to a Paradox® Database. The download process utilized a proprietary program developed by Ludlum Measurements, Inc., and revised by Duratek to fit specific survey needs.

A printed report, referred to as a Survey Report, was then generated for review. All raw data, converted data, and information by survey location code were presented in the report. This report was reviewed by the survey technician, survey supervisor and Certified Health Physicist for completeness, accuracy, any suspect entries and comparison to the site specific guideline values.

Any changes to the database tables such as detector efficiency, background, etc., that could affect survey results required the survey supervisor's approval. In addition, changes to data in the primary table required a written explanation on a change request attached to the survey report and maintained as a permanent record.

Data and document control included maintaining raw data files, translated data files (Paradox@ data files) and corrected data files showing documentation of all corrections. Paradox® program scripts and related data and information, including modifications, used for the development of the report were identified and controlled to ensure accurate identification. The databases were backed-up daily,

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

35

Page 49: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

and archived on a weekly basis. All survey records will be turned over to GA Tech with the issuance of this Final Survey Report.

3.12 Data Reduction and Statistical Evaluation

3.12.1 Data Analysis

Data collected during the Final Survey of the Georgia Tech Research Reactor was analyzed in accordance with the guidance contained in the Final Survey Plan. Survey data, for measurements of total beta activity, removable beta activity, removable H-3 activity, and exposure rate was grouped by survey unit or survey area as appropriate. Survey results were corrected as appropriate to account for background, including naturally occurring radioactive material present in building materials and as a result of instrument noise.

3.12.2 Background

In order to analyze the survey results associated with total beta activity measurements and exposure rate measurements, the analyses accounted for the naturally occurring radioactive background. For the analysis of the total beta activity measurement, this required a background study in an area representative of the areas surveyed during the final survey, using the same instrumentation and survey protocols that are used during the final survey. For exposure rate measurements, an alternative approach for defining background was required. This alternative approach is discussed in more detail in Section 3.12.6.

3.12.3 Measurements of Total Beta Activity

Measurement results for total beta activity from each survey unit, once corrected for background, were compared directly to the site specific guideline value for total beta activity. If any individual measurement result exceeded this value, then the measurement result was compared to the average and maximum criteria as defined in the footnotes to Table 3.1 as follows:

Individual measurement results less than 3 times the site specific guideline value for total beta activity were accepted provided that the affected area was limited to less than approximately 100 cm2.

NOTE: For the purpose of assessing the size of the contaminated area, an area of 126 cm2 corresponding to the size of the open window on the Ludlum Model 43-68 gas flow proportional detector was used.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

36

Page 50: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

If any individual measurement result, in any square meter, was between 1

and 3 times the site specific guideline value for total beta activity the average beta activity in the square meter was evaluated. The average beta activity in the square meter, weighted by sizes of the areas of elevated activity, was accepted provided that the average was less than the site specific guideline value for total beta activity.

Once the individual measurements results for total beta activity from a

given survey unit were determined to meet the site specific guideline value

or the average and maximum criteria as defined in the footnotes to Table

3.1, the 95 percent confidence level of the mean for the survey unit was evaluated using the following equation:

Sx Ux X x+ t(o.a, df)

Where: Ux = 95 percent confidence level of the mean, dpm/100 cm

x = mean to-a, df) = 95 percent confidence level for n-I degrees of

freedom, unitless Sx = standard deviation n = number of individual measurement results used to

calculate the mean and the standard deviation

Values of Ux less than the site specific guideline value provide assurance, at the 95% confidence level, that the true mean for a given survey unit is

less than the site specific guideline value.

Measurement results of total beta activity are presented graphically by survey unit. Included with each graph are the following statistics: the

maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the number of measurements in the

survey unit, and the 95 percent confidence level of the mean for the survey unit.

3.12.4 Measurements of Removable Alpha and Beta Activity

Measurement results for removable beta activity from each survey unit were compared directly with the site specific guideline value for removable beta activity.

REVISION 037

Page 51: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Measurement results of removable beta activity are presented graphically by survey unit. Included with each graph are the following statistics: the maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit.

All measurement results for removable alpha activity were verified to be less than MDA. Therefore, no statistics were performed for removable alpha activity.

3.12.5 Measurements of Removable H-3 Activity

Measurement results for removable H-3 activity from each survey unit were compared directly to the radionuclide specific guideline value for removable H-3 discussed in Section 3.2.1 and provided in Table 3.1. Tritium was the predominate radionuclide in the assumed radionuclide mixes used to calculate the site specific guideline values. Thus, such a comparison aids in the validation of the derivation of the site specific guideline values.

Measurement results of removable H-3 activity are presented graphically by survey unit. Included with each graph are the following statistics: the maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit.

3.12.6 Exposure Rate Measurements

The Final Survey Plan required that exposure rate measurements from each survey unit be compared to the background exposure rate established for that survey unit. Exposure rate measurement results that exceeded the established background by more than 5.0 uR/hr required investigation. While on the surface this sounded like a relatively straight forward requirement, the unique design of the Georgia Tech Reactor Building made it next to impossible to find a similar structure, not associated with the use of licensed radioactive material, for use in establishing background exposure rates. Exposure rates from naturally occurring sources in a relatively small area often vary by a factor of 2 or more due to geometry considerations and differences in materials of construction. Background exposure rate measurements collected in buildings on the Georgia Tech Campus, not associated with the use of licensed radioactive material, varied by a factor of 3.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

38

Page 52: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

The difficulty in identifying suitable background exposure rates for evaluating the final survey data was not unexpected and was discussed briefly in Section 4.9.1 of the Final Survey Plan. Since a structure, not associated with the use of licensed radioactive materials, similar in

structure to the Reactor Building could not be identified for the purposes of establishing background exposure rates, an alternative means of estimating background exposure rates was proposed. The alternative means of estimating background exposure rates was discussed in detail with the Georgia Tech RSO and the Executive Engineer during a meeting on March 1, 2002.

The alternative approach, adopted for this Final Survey Report, for establishing background exposure rates for the various survey units within the Reactor Building stipulated that the background exposure rate would be estimated from the mean of all of the exposure rate measurements in a given survey unit once outliers were accounted for. However, prior to using the exposure rate from a given survey unit to estimate the background exposure rate, the survey unit must not exceed the Site Specific Guideline Values for both total (scans and direct measurements) and removable (smears) beta activity.

For a given survey unit the background exposure rate was established as follows:

"* Initially the mean exposure rate for the survey unit was established using all available exposure rate measurements.

"* The standard deviation of the exposure rates for the survey unit was established using all available exposure rate measurements.

"* Those exposure rates that exceeded the initial mean exposure rate by more that 2 standard deviations (outliers) were removed from the data set and the mean exposure rate re-established.

The re-established mean exposure rate (with potential outliers removed) was used as the best estimate of the background exposure rate for a given survey unit.

When using this alternative approach to establish background exposure rates, an alternative approach for identifying individual exposure rates that require investigation was also required. This latter alternative approach stated that individual exposure rates that exceeded the established background by more than 5 uR/hr and exceeded the initial mean exposure rate by more than 2 standard deviations require investigation. Individual exposure rates that do not exceed the mean by more than 2 standard deviations are used to estimate the mean and are considered representative of background.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

39

Page 53: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

All exposure rate measurements collected as part of the final survey that exceeded the established background by more than a 5 uR/hr and exceeded the initial mean by more than 2 standard deviations were identified and investigated as part of the final survey.

Exposure rate measurement results are presented graphically by survey unit. Included with each graph are the following statistics: The maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the mean plus 2 standard deviations, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit. The background level, as calculated by the above alternate approach, is presented as the "Baseline" on the Exposure Rate graphs.

3.12.7 Samples of Open Land Areas of Reactor Yard

Based on the fact that the open land areas of the reactor yard were classified as unaffected, the sample results were compared to individual radionuclide guideline values shown in Table 3.3. No analysis results were found greater than 10% of the individual radionuclide specific concentration and none of the sum of fractions of the gamma emitting nuclides exceeded 25%, therefore, no additional sample analysis was required.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

40

Page 54: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.0 SURVEY RESULTS

The final survey data was evaluated on a survey unit basis for each area and is presented

graphically in the following sections along with a brief description of the area which was

surveyed. The data is presented graphically for easy comparison to the release guideline

values/levels. Included with the figures are summary statistics including the number of

measurements, survey unit mean and maximum, standard deviation of the data

population, and the 95% confidence level of the mean. The MDA for each individual

measurement is also provided on the graphs as an MDA line.

The survey packages containing the survey data download files, smear analysis sheets,

sample analysis results and the survey package worksheets are provided in Attachment B.

The data presented in the following sections is a summary of the data provided in these

survey packages.

4.1 Background Results Summary

Ideally, background measurements are taken on materials from a similar building

that was constructed during the same time frame and known to be free of licensed

radioactive material. The Georgia Institute of Technology Facilities Building

located at 915 Atlantic Drive was used to estimate background for the purpose of evaluating direct beta activity measurements. Table 4.1 provides a summary of

the direct beta background study of concrete and asphalt.

Table 4.1 Direct Beta Background Study of

Concrete and Asphalt

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

41

Page 55: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

4.2 Package 1 - Helium and Lead Tank Cooling Water Lines

Classification: Suspect Affected

Survey Package 1 encompassed the reactor building ground floor helium and lead tank cooling water lines. These lines travel between the first floor and the basement inner wall of the reactor building. Figure 4-1A provides the locations of lines H-1 through H-22. Lines H-1 through H-14 were helium lines and lines H15 through H-22 were lead tank cooling water lines. Each pipe was originally swiped using a small cloth that was pulled through the entire length of pipe to verify that there was no loose activity present. There were decontamination activities performed on the inside of the piping. Decontamination consisted of using industrial strength drain cleaners. The final survey included 100 % beta scans on the inside of the piping, three direct beta measurement for each pipe, two smears for removable surface contamination (beta and alpha) for each pipe, and two smears on the inside of each pipe to assess H-3 contamination levels.

Survey Package 1 was divided into 22 survey units they are numbered HI through H22.

The final survey results for Survey Package 1 are summarized below and presented graphically in Figures 4-1 B, 4-1 C, and 4-1D.

Table 4.2 Survey Package 1

Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean

Measurement dpm/100 cm2 dpm!100 cm 2 dpm/100 cm 2 dpm/100 cm2

Direct Beta 66 570 2036 469 683 *Removable Alpha 44 N/A N/A N/A N/A

Removable Beta 44 7 125 32 17 Removable H-3 44 140 417 68 163 * = All results < MDA ( Highest MDA 8.60 dpm/1OOCm 2)

As can be seen from the above table, none of the final survey results for Survey Package 1 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 1 demonstrate that the helium and lead tank cooling water lines meet the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR

42

Page 56: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-4A Package 1

Map

Georgia Tech Research Reactor Package 01 Helium & Lead Tank Cooling Water Lines

0 H #k- Denotes L7 number and approximate location of helium and lead tank cooling water lines.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

43

Page 57: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAIL SUJRVEY REPORTGA. 'ECH RESEARCH REACTOR

Figure 4-1B Package 1

Direct Beta Activity

Helium and Lead Tank Cooling Water Lines Direct Beta Activity7000

6000

5000

4000

3000

2000

1000

0

-1000H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-8 H-9 H-1O H-i1 H-12 H-13 H-14 H-15 H-16 H-17 H-i8 H-19 H-20 H-21 H-22

Coolant Line Number

REVISION 0

MDA

0 0

$

z

(

44,

Page 58: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

rECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-4C Package 1

Removable Beta Activity

Helium and Lead Tank Cooling 'Water Lines

600

500

400

300

200

100

0

-100

Removable Beta

MDA

H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-8 H-9 H-10 H-11 H-12 H-13 H-14 H-15 H-16 H-17 H-18 H-19 H-20 H-21 H-22

Coolant Line Number

REVISION 0

0

0

I.

45

Page 59: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA - tCf RESEARCH REACTOR

0 0-

/

F

Figure 4-1D Package 1

Removable H-3 Activity

Helium and Lead Tank Cooling Water Lines Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

Measurements: 44 Mean: 140 dpm/100 din2 Maximum: 417 dpm/100 cra2 Std Deviation: 68 dpm/100 cm2 95% CL on Mean: 163 dpmn/100 cm2

S1iiiK - INi elm .Uiil-100 _ .. .. . . . . . . .. .. .. ... .. .

MDA

REVISION 0

H-1 11-2 11-3 H-4 H-5 H1-6 H-7 H-8 H-9 H-JO 11-11 H-12 H-13 11-14 H-15 11-16 H-17 H-18 H-19 H-20 11-21 H-22

Coolant Line Number

46

I-

Page 60: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.3 Package 2 - Reactor Building 2nd Floor Below 2 Meters

Classification: Suspect Affected

Survey Package 2 encompassed the second floor of the reactor building. See Figure 4-2A for an overview. The second floor of the reactor building is composed of a small floor area that extends to the top of the reactor and a walkway that runs completely around the circumference of the reactor building. The floor area includes the reactor control room.

The need to perform decontamination activities on the second floor of the reactor building resulted in Survey Package 2 being classified as suspect affected for purposes of the final survey. Where practical, accessible surfaces were gridded. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 2 was divided into the following survey units:

"• Walkway floor "* Outer Reactor Building wall (below 2 meters from the top of the walkway) "* ECCS tank platform "* Walkway Handrail "* Floor outside of the Control Room (CR) "* Floor inside Control Room "* Control Room wall 1 "* Control Room wall 2 "* Control Room wall 3 "* Control Room wall 4 "* Control Room electrical panel "* Ventilation Ducting

The final survey results for Survey Package 2 are summarized below and presented graphically in Figures 4-2B, 4-2C, 4-2D, and 4-2E.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

47

Page 61: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Table 4.3 Survey Package 2

Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean

Measurement dpm/100 cm 2 dpM/100 cm 2 dpmlr100 cm2 dpml1 00 cm 2

Direct Beta 440 40 1396 234 62 *Removable Alpha 443 N/A N/A N/A N/A

Removable Beta 443 5 37 8 6 Exposure Rate 151 11.8 uR/hr 15.1 uR/hr 1.2 uR/hr 12 uR/hr

Removable H-3 31 191 839 137 247 * = All results < MDA (maximum MDA is 10 dpm/100cm2).

As can be seen from the above table, none of the final survey results for Survey Package 2 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 2 demonstrate that the second floor of the reactor building meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

48

Page 62: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-2A Package 2

Map

REACTOR BUILDING 2nd FLOOR BELOW 2 METERS

01 SO1-ECCs Tank Platform

N

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

49

Page 63: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

Figure 4-2B Package 2

Direct Beta Activity

2nd Floor Below 2 Meters Direct Beta Activity

MDA

Surface

REVISION 0

7000

6000

5000

4000

3o00

2000

1000

0

0wm

$

z

0

-1000

50

Page 64: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-2 C Package 2

Exposure Rate Measurements

'-4

0

20.0 19.0 18.0 17.0 16.0 15.0

14.0 13.0 12.0 11.0 10.0

9.0

8.0 7.0 6.0 5.0

4.0 3.0 2.0 1.0 0.0

2nd Floor Below 2 Meters Exposure Rate Measurements Measurements: 151 Mean: 11.8 pR/hr

Std Deviation: 1.2 p4R/hr

Baseline + 2 Std. Dev: 14.2 tR/hr Maximum: 15.1 tR/hr 95% CL on Mean: 12.0 IR/hr

- ------ J

Baseline

........

Surface

REVISION 0

. ... ... .. ....ll l l l

51

Page 65: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( Gt) LECH RESEARCH REACTOR K ( FINAL SURVEY REPORT

Figure 4-2D Package 2

Removable Beta Activity

2nd Floor Below 2 Meters Removable Beta Activity

MDA

Surface

REVISION 0

0

0•

$

600

500

Ann

300

200

100

0

-100

Measurements: 443 Mean: 5 dpm/100 cm2 Maximum: 37 dpm/100 c-m2 Std Deviation: 8 dpm/100 crn2 95% CL on Mean: 6 dpm/100 cm2

FINA SURVEY REPORT

1" .. m I- ,0 1 I- 1 41ImIA1t_. 1011,Nl " 111 SI il''l l''ll . . .. H// - " IMW IIII111,0 M M 0M"'"" HM• II..

52

Page 66: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA fECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-2E Package 2

Removable H-3 Activity

2nd Floor Below 2 Meters Removable H-3 Activity

MDA

Surface

REVISION 0

4700

4300

0 0

$ 4b C.)

Q)

0

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

FINAL SURVEY REPORTGA fECH RESEARCH REACTOR

% .1 %N %,ý %'ý 11 %N1 0

53

Page 67: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

4.4 Package 3 - Reactor Building 2nd Floor Above 2 Meters

Classification: Non-Suspect Affected

Survey Package 3 encompassed the second floor of the reactor building above 2 meters. See Figure 4-3A for an overview. The second floor of the reactor building consisted of the ceiling and wall areas 2 meters above the 2 'd floor. The wall proceeds vertically until reaching the crane rail. The roof then projects torispherically and peaks -15' above the crane rail.

There was no decontamination required in these areas. The final survey included 10 % biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.

Survey Package 3 was divided into the following survey units:

"* Walls from 2 meters to crane rail and top of the Control Room "* Overhead above crane rail "* Crane hoists "* Overhead inside of Control Room "* Reactor building intake vent "* Control Room intake

The final survey results for Survey Package 3 are summarized below and presented graphically in Figures 4-3B, 4-3C, and 4-3D

Table 4.4 Survey Package 3

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/l00 cm2 dpm/100 cm 2

Direct Beta 85 120 517 243 172 *Removable Alpha 85 N/A N/A N/A N/A

Removable Beta 85 6 40 8 8 Removable H-3 35 223 752 178 291

* = All results < MDA (Highest MDA is 8.60 dpm/100cm2 )

REVISION 0

FINAL SURVEY REPORT

54

Page 68: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

As can be seen from the above table, none of the final survey results for Survey Package 3 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was

exceeded, derivation of the SPGL based on the site radionuclide mix has been

validated. The final survey results for Survey Package 3 demonstrate that the

second floor of the reactor building above 2 meters meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

55

Page 69: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

Figure 4-3A Package 3

Map

REACTOR BUILDING 2nd FLOOR ABOVE 2 METERS

ýýT' 01V01-Reactor Building Intake Vent 020H1-Inside Overhead of Control Room

./ 01OH1-Walls from 2 meters to crane rail 010H2-Overhead above Crane Rail

REVISION 0

FINAL SURVEY REPORT

56

Page 70: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA.t'ECH RESEARCH REACTORFINAL SURVEY REPORT

Figure 4-3B Package 3

Direct Beta Activity

2nd Floor Above 2 Meters Direct Beta Activity7000

6000

5000

4000

3000

2000

1000

0

-1000

Surface

REVISION 0

Measurements: 85 Mean: 120 dpm/100 cm2 Maximum: 517 dpm/100 cm2

Std Deviation: 243 dpm/100 cm2 95% CL on Mean: 172 dpm/100 cm2

-- - - - - - - - ----- - -- -----

0

z- MDA

57

Page 71: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA IECH RESEARCH REACTOR( (

FINAL SURVEY REPORT

Figure 4-3C Package 3

Removable Beta Activity

2nd Floor Above 2 Meters Removable Beta Activity

Measurements: 85 Mean: 6 dpm/100 cm2 Maximum: 40 dpmrl00 cm2

Std Deviation: 8 dpm/100 cm2 95% CL on Mean: 8 dpm/100 c=2

600

500

400

300

200

100

0

-100

Surface

REVISION 0

0<

MDA

58

Page 72: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR

FINAL SURVEY REPORT

Figure 4-3D Package 3

Removable H-3 Activity

2nd Floor Above 2 Meters Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300MDA

-100

Grid Row

REVISION 0

0<

0D

FINAL SURVEY REPORT(

59

Page 73: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.5 Package 4 - Reactor Building 1st Floor Below 2 Meters

Classification: Suspect Affected

Survey Package 4 consisted of the entire 1 st floor and all wall surfaces below 2 meters of the reactor building. See Figure 4-4A for an overview. This includes the main floor, biomedical room and the plug storage vault.

For the purpose of the Final survey, Survey Package 4 was classified as suspect affected. Decontamination was required on - 40% of the main floor. The walls of the I" floor and the plug storage vault did not require any decontamination. All accessible surfaces were gridded.

The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear for removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 4 was divided into the following survey units:

"* Floor "* Wall 1 (grids 48-50 do not exist) "* Walls 2,4,5 "* Wall 3 (grid A-3 does not exist) "* Stairwell from 2 nd floor to basement "* Heaters 1-4 "* Trenches 1-8 "* Fuel storage pit "* Pressure relief valves "* Vent duct "* Inside elevator "* Secondary personnel hatch "* Airlock to lab building "* Biomedical room

"* Floor "* Walls 1-4 (grid A2 does not exist) "* Overhead (above 2 meters) "* Floor drain

"* Plug storage vault "* Floor "* Wall 1 (gridded as continuous wall) "* Ceiling (not above 2 meters)

REVISION 060

FINAL SURVEY REPORT

Page 74: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

The final survey results for Survey Package 4 are summarized below and presented graphically in Figures 4-4B, 4-4C, 4-4D, and 4-4E.

Table 4.5 Survey Package 4

Final Survey Results

Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm2

Direct Beta 1027 209 2457 394 233 *Removable Alpha 1022 N/A N/A N/A N/A

Removable Beta 1022 6 170 12 6 Exposure Rate 520 13.1 uRihr 21.4 uRihr 2.4 uRihr 13.5 uR/hr

Removable H-3 75 324 4243 524 461

* = All results < MDA (Highest MIDA is 13.68 dpm/100cm 2 )

During the initial Final Survey of Trench 6, one direct beta measurement exceeded the Site Specific Guideline Value, SPGL. A follow-up investigation (see Attachment B, package 4, file 213) did not result in any additional direct beta measurement in excess of the SPGL. For the grid in question, the average contamination level, including the one measurement result that exceeded the SPGL, did not exceed the SPGL.

One exposure rate measurement exceeded the SPGL. This measurement result can be attributed to the proximity to the Neely Building Hot Cell and source storage vault.

As can be seen from the above table, none of the Final Survey results with the exception of the one direct beta measurement and the one exposure rate measurement exceeded the SPGL's. In addition, based on the result of the H-3 measurements, there is no reason to question the derivation of the SPGL's. The Final Survey results for Survey Package 4 demonstrate that the 1 st floor of the reactor building below 2 meters meets the criteria for release for unrestricted use.

REVISION 061

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Page 75: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-4A Package 4

Map

REACTOR BUILDING 1 ST FLOOR BELOW 2 METERS

Vent 1 (01VO1) no longer connected.

REVISION 0

GA TECH RESEARCH REACTOR FI:NAL SURVEY REPORT

62

Page 76: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( G• 1'ECH RESEARCH REACTOR(

FINAL SURVEY REPORT

Figure 4-4B Package 4

Direct Beta Activity I

1 st Floor Below 2 Meters Direct Beta Activity

Measurements: 1027 Mean: 209 dpm/100 cm2 Maximum: 2457 dpm/100 cm2 Std Deviation: 394 dpm/100 cm2 95% CL on Mean: 233 dpm/100 cm2

Surface.

REVISION 0

7000

6000

5000

4000

21iN1IJYVuV -

Pz 2000

1000

0

-1000

- MDAit it III

ju 1

11 --- --------- "T F

63

Page 77: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

C)

4.1

Cf)

(-i ý4 Cý Cý 016 t-: wi 4 Iýi ýli 14 C; Cý 06 t-: wi 4 rý (Ii 14 6 eq r4 N

aliell ainsodxa

m

cod

Page 78: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(•. TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-4D Package 4

Removable Beta Activity

1st Floor Below 2 Meters Removable Beta Activity

.... ... ... . A. . , [ MDA

0

-100

Surface

REVISION 0

600

500

4

0p

Measurements: 1022 Mean: 6 dpmrl00 cm2 Maximum: 170 dpmlO00 cm2 Std Deviation: 12 dpm/100 cm2 95% CL on Mean: 6 dpm/100 cm2

400

300

200

100

65

Page 79: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA fECH RESEARCH REACTOR

( FINAL SURVEY REPORT

Figure 4-4E Package 4

Removable H-3 Activity

1st Floor Below 2 Meters Removable H-3 Activity4700

Measurements: 75

4300 Mean: 324 dpm/100 dn2 Maximum: 4243 dpm/100 cm2 Std Deviation: 524 dpm/100 cmI2

3900 95 % CL on Mean: 461 dpm/100 cm2

3500

3100

2700

2300

1900

1500

1100

700

300MDA

-100 .............

Surface

REVISION 0

0

0<

41 ip V"o-Ok", ", ̀ 5 "1 %, %N %N, %4P %-ý %040,

66

Page 80: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.6 Package 5 - Reactor Building 1 st Floor Above 2 Meters

Classification: Non-Suspect Affected

Survey Package 5 encompassed the first floor of the reactor building above 2 meters. See Figure 4-5A for an overview. The first floor of the reactor building consisted of the outer wall areas from 2 meters vertically - 12' to the bottom of the 2 nd floor catwalk, (includes bottom of the catwalk) and the outside of the biomedical room above 2 meters to the bottom of the 2 nd floor.

There was no decontamination required in these areas. The final survey included 10 % biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.

Survey Package 5 was divided into the following survey units:

"* Outer wall from 2 meters to the bottom of the 2 nd floor walkway "* Outside of biomedical room from 2 meters to the bottom of the 2nd floor

The final survey results for Survey Package 5 are summarized below and presented graphically in Figures 4-5B, 4-5C, and 4-5D.

Table 4.6 Survey Package 5

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm 2 dpm/100 cm2 dpm/100 cm2

Direct Beta 50 63 830 257 139 *Removable Alpha 50 N/A N/A N/A N/A

Removable Beta 50 2 49 9 4 Removable H-3 30 182 1889 318 313 • = All results < MDA (Highest MDA is 5.17 dpm/100cm2 )

During the final survey of the outer wall overhead, one direct beta measurement (830 dpm/100cm 2) exceeded the non-suspect affected action level of 600 dpm/100 cm2 . A follow-up investigation (see Attachment B, package 5, file 163) did not result in any activity in excess of 600 dpm/1 00 cm 2, therefore, no further action was required.

As can be seen from the above table, none of the final survey results for Survey Package 5 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 5 demonstrate that the first floor of the reactor building above 2 meters meets the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

67

Page 81: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-5A Package 5

Map

Reactor Building 1 st Floor Areas Above 2 Meters

01 OH1 - Outer Wall from 2 meters to bottom of 2nd floor walkway.

01OH2 - Outside of biomedical room from 2 meters to bottom of 2nd floor walkway.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

68

Page 82: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

, L.. TECH RESEARCH REACTOR.(

FINAL SIIUVr�V 1�EPO1�T

Figure 4-5B Package 5

Direct Beta Activity

1st floor Above 2 Meters Direct Beta Activity

MDA

'0

Surface

REVISION 0

7000

6000

5000

4000

3000

2000

1000z

0

-1000

FINAL SURV E, Y -P UPOR T

69

Page 83: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA t'ECH RESEARCH REACTOR\'

FINAL SURVEY REPORT

Figure 4-5C Package 5

Removable Beta Activity

1st floor Above 2 Meters Removable Beta Activity

Measurements: 50 Mean: 2 dpm/100 cnm2

Maximum: 49 dpm/100 crn2 Std Deviation: 9 dpm/100 cm2

95% CL on Mean: 4 dpm/100 cm2

+±++r-.i--i~n+..±-++ +u ni -.+MDA

Surface

REVISION 0

, 600

500

0•

0

400

300

200

.100

0

-100

70

Page 84: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

""L [ECH RESEARCH REACTOR

0

(FINAL SURVEY REPORT

Figure 4-5D Package 5

Removable H-3 Activity

1st Floor Above 2 Meters Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

-1I

Location 20

in' ,,,,snm n~~~ml m .1n0~m| 11,m5 5. 1 1LI 1

01OH1

MDA

01OH2

Surface

REVISION 0

Measurements: 30 Mean: 182 dpm/100 dm2 Maximum: 1889 dpmlO00 cm2 Std Deviation:318 dpm/100 cm2 95% CL on Mean: 313 dpm/100 cm2

71

Page 85: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.7 Package 6 - Reactor Building Ventilation Hold-Up Duct

Classification: Suspect Affected

Survey Package 6 consisted of the hold-up duct that is located directly below the floor in the basement of the reactor building. The hold-up duct is part of the reactor building ventilation system on the intake side of the HEPA filters. See Figure 4-6A for an overview of this area.

There was a small amount of decontamination activities in the hold-up duct. The damper louvers were removed and disposed of as radioactive waste. A small amount of aggressive decon was required on the floor. The surfaces were gridded into 1 m2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear for removable surface contamination (beta and alpha) for each m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. Exposure rate readings were not required in the hold-up duct due to its unique geometry. The ducts geometry is such that any reading one meter above the floor surface is within one foot from the ceiling and approximately one foot from at least two walls.

Survey Package 6 was divided into the following survey units:

"* Floor inside hold-up duct "* Hold-up duct wall 1 through 4 "* Hold-up duct ceiling

The final survey results for Survey Package 6 are summarized below and presented graphically in Figures 4-6B, 4-6C, and 4-6D.

Table 4.7 Survey Package 6

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpmi/100 cm 2 dpm/100 cm2

Direct Beta 130 436 1396 308 489 * Removable Alpha 130 N/A N/A N/A N/A

Removable Beta 130 0 21 5 1 Removable H-3 30 184 529 102 226 • - All results < MDA (Highest MDA is 7.63 dpm/l 00Cm 2).

As can be seen from the above table, none of the final survey results for Survey Package 6 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 6 demonstrate that the hold-up duct of the reactor building meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

72

Page 86: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Figure 4-6A Package 6

Map

Reactor Building Ventillation Hold-Up Duct

N-->Wall 2 (01W02)

REVISION 0

GA TECH RESEARCH REACTOR

73

Page 87: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-6B Package 6

Direct Beta Activity

Hold-up Duct Direct Beta Activity7000

6000

5000

4000

3000

2000

1000- MDA

000

-1000-

Surface

REVISION 0

zP

1ý %

74

Page 88: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

T ( • TECH RESEARCH REACTOR(

FINAI, •qTIRVE.V RE.PORT

Figure 4-6C Package 6

Removable Beta Activity

Hold-up Duct Removable Beta Activity

Surface

REVISION 0

600

500

0

400

300

200

100

0

-100

MDA

FlNAY,.virj-Pvr,.y -ur,.PnuT

75

Page 89: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Gr. ECH RESEARCH REACTOR

Figure 4-6D Package 6

Removable H-3 Activity

FINAL SURVEY REPORT

Hold-Up Duct Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

s�xSurface

REVISION 0

MDA

0 0

�0

0

76

Page 90: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

4.8 Package 7 - Reactor Building Ventilation

Classification: Suspect Affected

Survey Package 7 encompassed the reactor ventilation unit (located in the basement of the reactor building), reactor building stack main vent room, stack kanne chamber room, and the reactor building stack. See Figure 4-7a.

Decontamination was required on the floor of the HEPA ventilation unit and the floor of the stack. Where practical, accessible surfaces were gridded. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each mn2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 7 was divided into the following survey units:

"* Inside of the reactor ventilation unit "* Floor of stack main vent room "* Walls 1 through 8 of the stack main vent room "* Floor of the instrument room "* Vent pipe chamber room "* Stack fan "* Instrumentation "* Stack floor "* Stack wall

The final survey results for Survey Package 7 are summarized below and presented graphically in Figures 4-7B, 4-7C, 4-7D, and 4-7E.

Table 4.8 Survey Package 7

Final Survey ResultsType of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm2

Direct Beta 131 136 1584 379 201

*Removable Alpha 131 N/A N/A N/A N/A

Removable Beta 131 5 122 17 7

Exposure Rate 14 15.6 uR/hr 17.5 uR/hr 1.0 uR/hr 16.2 uR/hr Removable H-3 35 371 2068 424 534

* = All results < MDA (Highest MDA is 8.60 dprr1 00cm 2 )

As can be seen from the above table, none of the final survey results for Survey Package 7 exceeded the Site Specific Guideline Values (SPGLs). Since neither

REVISION 0

GA TECH RESEARCH REACTOR

77

Page 91: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 7 demonstrate that the reactor building ventilation meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

78

Page 92: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

Figure 4-7A Package 7

Map

REACTOR BUILDING VENTILATION ROOM AND STACK Package 07 (A0207)

Roughing Filter Bank HEPA Filter Bank

Approximately 15' of pipe not shown

N VWall 9 (O1WO9) IN

REVISION 0

FINAL SURVEY REPORT

79

Page 93: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

, TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-7B Package 7

Direct Beta Activity

-1000 1

Surface

40 44% 4p p ý

REVISION 0

Pi

7000

6000

5000

4000

3000

2000

1000

0

- MDA

80

Page 94: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Gz-. tECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-7C Package 7

Exposure Rate Measurements

C

Reactor Building Ventilation Below 2 Meters Exposure Rate Measurements 23.0 22.0 - Measurements: 14

21.0 Mean: 15.6 pR/hr Std Deviation: 1.0 pR/hr

20.0 Baseline + 2 Std. Dev: 17.6 IR/hr

19.0 - Maximum: 17.5 pR/hr

180 95% CL on Mean: 16.2 pR/hr

17.0 16.0 A

15.014.013.0o 12.0-11.0 10.0

9.0 t ot 8.0

.7.0 6.0 5.04.03.02.0 1.0 0.0 4 - - II T

01FOl 01F02

Surface

Baseline

REVISION 081

Page 95: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA TECH RESEARCH REACTOR( F

FINAL SURVEY REPORT

Figure 4-7D Package 7

Removable Beta Activity

Reactor Building Ventilation Below 2 Meters Removable Beta Activity

4 4? 4? 4? 4? 4? 4 x�x�x

Surface

REVISION 0

600

500

400

300

200

100

09

0

Measurements: 131 Mean: 5 dpm/100 cm2 Maximum: 122 dpm/100 cm2 Std Deviation: 17 dpm/100 cm2 95% CL on Mean: 7 dpm/100 cm2

.49I Ii I4 Iww pI0

_1 fin

MDA

I"InnU

82

Page 96: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Gý, TECH RESEARCH REACTOR

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

REVISION 0

(

0•

0•

'U

Figure 4-7E Package 7

Removable H-3 Activity Reactor Building Ventilation Below 2 Meters

Removable H-3 Activity

Measurements: 35 Mean: 371 dpm/100 din2 Maximum: 2068 dpm/100 cm2 Std Deviation: 424 dpm/100 crn2 95 % CL on Mean: 534 dpm/100 cm2

Surface

MDA

(

83

Page 97: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.9 Package 8 - Suspect Affected Yard Areas

Classification: Suspect Affected

Survey Package 8 encompassed the reactor facility yard. The suspect affected yard areas included an asphalt paved area, and a concrete walk way that runs approximately 2700 around the reactor building. These areas were included in this package due to egress from the reactor building during normal operations and decommissioning activities. Both areas were used for storage of radioactive material in accordance with approved procedures. See Figure 4-8A for an overview of these areas. Decontamination was limited to two small (<100 cm2 each) areas located on the concrete walkway immediately outside the Neely Research Center high bay doors.

Where practical, accessible surfaces were gridded into lm2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible area, and a number of smears to assess H-3 contamination levels.

Survey Package 8 was divided into the following survey units:

* Concrete walkway * Paved radioactive material storage area 1 0 Paved radioactive material storage area 2

The final survey results for Survey Package 8 are summarized below and presented graphically in Figures 4-8B, 4-8C, 4-8D, and 4-8E.

Table 4.9 Survey Package 8

Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm' dpm/100 cm2 dpm/100 cm2

Direct Beta 643 283 1998 410 315 *Removable Alpha 643 N/A N/A N/A N/A

Removable Beta 643 0 37 4 0 Exposure Rate 643 11.7 uR/hr 17.4 uR/hr 1.2 uR/hr 11.8 uR/hr

Removable H-3 32 161 424 66 188 *- All results < MDA (Highest MDA is 3.53 dpm/lO00cm 2).

REVISION 0

GA TECH RESEARCH REACTOR

84

FINAL SURVEY REPORT

Page 98: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

As can be seen from the above table, with the exception of the exposure rate measurements, none of the final survey results for Survey Package 8 exceeded the

Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation

of the SPGL based on the site radionuclide mix has been validated. Upon frrther

investigation it was determined that the elevated exposure rate measurement results were due to the location of radioactive materials within the Neely Building immediately east of these data locations.

The final survey results for Survey Package 8 demonstrates that the reactor facility yard concrete walkway and asphalt paved areas meet the criteria for

release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

85

Page 99: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-8A Package 8

Map

Yard Suspect Afffected Areas

.ETADNETG FENCE LINE

North >S_ = Suspect Afffected Areas

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

86

Page 100: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL �TIRVEV RE�1IT

Figure 4-8B Package 8

Direct Beta Activity

7000

6000

I *

4.)

5000

4000

3000.

2000

1000

0

-1000

Affected Areas Direct Beta

MDA

Surface

REVISION 0

FINAL SURVEY REPORT

(

87

Page 101: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

C (GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-8C Package 8,

Exposure Rate Measurements

Yard Suspect Affected Areas Exposure Rate Measurements 23.0 22.0 - Measurements: 643

21.0 Mean: 11.7 /R/hr Std Dev: 1.2 uR/hr

20.0 - Baseline + 2 Std. Dev: 14.2ttR/hr

19.0 Maximum: 17.4 gR/hr

18.0 95% CL on Mean:, 11.8 /zR/lr

170 "Z 16.0

15.0

S14.0S 13.0 -'

"120 - Baseline

S10.0.

9.0 S8.01 0 7.0

6.05.0 4.0

3.02.0

1.0 0.0

Surface

REVISION 0

(

88

Page 102: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

k,ý TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-8D Package 8

Removable Beta Activity

Yard Suspect Affected Areas Removable Beta Activity600

500

400

300

200

100

0

MDA

Surface

REVISION 0

0

.0

"0

89

Page 103: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( (1 TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-8E Package 8

Removable H-3 Activity

Yard Suspect Affected Areas Removable H-3 Activity 4700 4700 ~ ~Measurements: 3218 cm

4300 Mean: 161 dpm/100 di2 Maximum: 424 dpm/100 cm2

3900- Std Deviation: 66 dpm/100 cm2 95% CL on Mean: 18dpm/lO0 m

3500

3100

", 2700

- 2300

S1900

" 1500

a 1100

S70 0

300 MDA

-100

Surface

REVISION 090

Page 104: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

4.10 Package 9 - Unaffected Asphalt and Concrete Yard Areas

Classification: Unaffected

Survey Package 9 encompassed the outside yard areas of the reactor facility. See Figure 4-9A for an overview. The unaffected asphalt paved areas and concrete walkways occupy approximately 605 square meters. This area was not used for storage of radioactive material.

There was no decontamination required in this area. The final survey included 10 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2

of accessible surface area, one exposure rate measurement for each m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.

Survey Package 9 was divided into the following survey unit:

* Asphalt or concrete paved areas.

The final survey results for Survey Package 9 are summarized below and presented graphically in Figures 4-9B, 4-9C, 4-93D, and 4-9E.

Table 4.10 Survey Package 9

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm2

Direct Beta 34 4 595 357 124 *Removable Alpha 34 N/A N/A N/A N/A

Removable Beta 34 0 10 3 1 Exposure Rate 34 12 uR/hr 16.2 uR/hr 1.4 uR/hr 12.4 uR/hr

Removable H-3 34 145 441 84 178 * = All results <MDA (Highest MDA is 5.17 dpm/100cm2).

As can be seen from the above table, none of the final survey results for Survey Package 9 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 9 demonstrate that the unaffected yard areas of the reactor facility meet the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

91

Page 105: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-9A Package 9

Map

Yard Unafffected Areas

ACCESS GATE

S_ = Unafffected Areas North >

REVISION 092

Page 106: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

ITECH RESEARCH REACTOR

FINAL SURVEY REPORT

Figure 4-9B Package 9

Direct Beta Activity

Yard Unaffected Areas Direct Beta Activity7000

6000

5000

4000

3000

2000

1000

0

-1000

Surface

REVISION 0

V

.4

z

MDA

FINAL SURVEY REPORT

93

Page 107: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

L LECH RESEARCH REACTOR( (

FINAL SURVEY REPORT

Figure 4-9C Package,9

Exposure Rate Measurements

Yard Unaffected Areas Exposure Rate Measurements Measurements: 34 Mean: 12.0 IAR/hr Std Deviation: 1.4 AR/hr Baseline + 2 Std. Dev: 14.7 IR/hr Maximum: 16.2 AR/hr 95% CL on Mean: 12.4 ttR/hr

:I' _-ý ,

Baseline

Surface

REVISION 0

23.0 22.0 21.0 20.0 19.0 18.0 17.0 16.0 15.0 14.0 13.0 12.0 11.0 10.0

9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0

C

94

Page 108: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

\ TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-9D Package 9

Removable Beta Activity

Yard Unaffected Areas Removable Beta Activity

0 0

"0

c*J

600

500

400

300

200

100

0

-100

Measurements: 34 Mean: 0 dpm/100 cm2 Maximum: 10 dpm/100 cm2 Std Deviation: 3 dpm/100 cm2 95% CL on Mean: 1 dpm/100 cm2

Surface

REVISION 0

MDA

FINAL SURVEY REPORT

95

Page 109: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

_ TECH RESEARCH REACTOR

0

C0

FINAL. �TTRVEV REPORT

Figure 4-9E Package 9

Removable H-3 Activity

Yard Unaffected Areas Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100MDA

Surface

REVISION 0

Measurements: 34

Mean: 145 dpm/100 dmi2 Maximum: 441 dpm/100 cm2 _

Std Deviation: 84 dpm/100 cm2 95 % CL on Mean: 178 dpm/100 cm2

FINAL SURVEY R1wpn12T

96

Page 110: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

4.11 Package 10 - Reactor Building and Stack

Classification: Non-Suspect Affected

Survey Package 10 encompassed the reactor building exterior walls, dome surfaces, and the stack. See Figure 4-1 GA for an overview of this area. There were no decontamination activities on the building exterior.

The final survey included a minimum of 10 % beta scans, one direct beta measurement for each 50 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 50 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.

Survey Package 10 has only one survey unit that includes both the stack and reactor building exterior.

The final survey results for Survey Package 10 are summarized below and presented graphically in Figures 4-1OB, 4-1OC, and 4-1OD.

Table 4.11 Survey Package 10

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/IOO cm dpm/100 cm2 dpm/I00 cm dpm/100 cm2

Direct Beta 30 20 483 212 95 * Removable Alpha 30 N/A N/A N/A N/A

Removable Beta 30 5 45 9 8 Removable H-3 30 142 260 51 163 * = All results < MDA (Highest MDA 5.17 dpm/100cm2).

As can be seen from the above table, none of the final survey results for Survey Package 10 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 10 demonstrates that the reactor building and stack exteriors meet the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR

97

Page 111: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

Figure 4-10A Package 10

Map

Reactor Building Exterior

North

REVISION 0

GA TECH RESEARCH REACTOR

98

Page 112: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( ( ( C. TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-10B Package 10

Direct Beta Activity

Reactor Building and Stack Exterior Direct Beta Activity

7000

Measurements: 30

Mean: 20 dpm/100 cm2 6000 Maximum: 483 dpm/100 cm2

Std Deviation: 212 dpm/100 cm2

95% CL on Mean: 95 dpm/100 cm2

S5000

S4000

3000

S2000

1000 -D SMDA

-1000

Surface

REVISION 0

/

99

Page 113: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

L•. rECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-10C Package 10

Removable Beta Activity

Reactor Building & Stack Exterior Removable Beta Activity600

500

0 0

"0

$

400

300

200

100

0

-100

MDA

N

Surface

REVISION 0

i' t\

.100

Page 114: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

L. TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-10D Package 10

Removable H-3 Activity

Reactor Building & Stack Exterior Removable H-3 Activity 4700

Smeasurements: 30

4300 mean: 142 dpm/100 dn2 Maximum: 260 dpm/100 cm2

0Std Deviation: 51 dpm/100 c392 3900 95 % CL on Mean: 163 dpm/100 -ra2

S3500

S3100

S2700

, 2300

1900 W ,•1500

S1100

S700

300 300 -M D A

-100

Surface

REVISION 0101

Page 115: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

4.12 Package 11 - Reactor Building Basement Drain Lines

Classification: Suspect Affected

Survey Package 11 encompassed the reactor building basement drain lines. Drain

lines DOI through D09 traveled to the basement floor sump. Drain line D10 traveled between the heavy water storage tank pit and the reactor vessel tunnel

shaft. See Figure 4-1 1A for a map showing the drain line layout.

Portions of the drain lines up to 20 feet upstream of the sump were contaminated

and required decontamination. Decontamination was accomplished using

industrial strength drain cleaning solutions and high pressure water spray systems.

After decontamination, the drain lines were flushed twice to ensure an absolute

minimum amount of loose debris remained for final surveys.

The Final Survey for Drain Lines DOI-D10 included:

* A 100 % beta scan of all accessible surfaces

* A minimum of three (3) direct beta measurements on each pipe

* A minimum of two (2) smears on the inside of each pipe for removable surface contamination (gross beta and gross alpha)

* A minimum of two (2) smears on the inside of each pipe to assess H-3 contamination levels (liquid scintillation analysis)

In addition, Drain Lines D03, D04 and D1O were surveyed every foot. These lines

were easily accessible and known to be contaminated prior to decontamination.

Drains DO, D02 and D05 through D09 were surveyed every foot until passing the first elbow.

The final survey results for Survey Package 11 are summarized below and presented graphically in Figures 4-1 lB, 4-11 C, and 4-1 1D.

Table 4.12 Survey Package 11

Final Survey Results

Type of # of Meas. Mean Max. Stand. Dev. 95 % CL ot mean Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm2 dpm/1OO cm 2

Direct Beta 118 264 1736 505 355

*Removable Alpha 20 A N/A N/A N/A

Removable Beta 20 3 1 5 5

Removable H-3 420 773 159 501

-= l results < MA 1( Highest MDA is 5.7 I pm/1OOcm 2)

REVISION 0102

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

Page 116: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

FINAL SURVEY REPORT

As can be seen from the above table, none of the final survey results for Survey Package 11 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 11 demonstrate that the Reactor Building Basement Drain Lines meet the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR

103

Page 117: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-11A Package 11

Map

Basement Drain Lines

Sump

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

104

Page 118: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( (,. TECH RESEARCH REACTORFINAL SURVEY REPORT

Figure 4-11B Package 11

Direct Beta Activity

7000

6000

09

z9

Basement Drain Lines Direct Beta Activity

5000

4000

3000

2000

1000

0

-1000

I- MDA

Surface

REVISION 0

(

,%S 0. %ý 0 %S llý

105

Page 119: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

L rECH RESEARCH REACTOR( (

FINAl, STIRVF VY REPORT

Figure 4-11C Package 11

Removable Beta Activity

Basement Drain Lines Removable Beta Activity

MDA

N

Surface

REVISION 0

600

500

400

300

200

100

0

0

�;I.

0

-100

FINA SURVEY REPORT

106

Page 120: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA fECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-111D Package 11

Removable H-3 Activity

Basement Drain Lines Removable H-3 Activity

300

-100

i V,$ ýp z, Z4 zo Z, 00 00 ZA ZA ý, Z% Zo

Surface

REVISION 0

I MDA

4700

4300

S3900

3500

"3100

"• 2700

S23 0'0

S1900

1500

o1100

S700

107

Page 121: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.13 Package 12 - Process Equipment Room Below 2 Meters

Classification: Suspect Affected

Survey Package 12 encompassed the reactor building process equipment room located in the basement. The floor of this room is approximately 160 m2. See Figure 4-12A for an overview. This area contained several pieces of contaminated equipment (e.g. primary coolant filtration system, two large heat exchangers, misc. coolant lines and the D20 tank). It also contained the heavy water storage tank pit.

Approximately 60% of the floor area required decontamination. The walls required only minor decontamination. The floor surface of the heavy water storage tank pit required 100% decontamination. Approximately 40% of the wall surfaces of the pit required decontamination. Where practical, accessible surfaces were gridded.

The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 12 was divided into the following survey units:

"* Process equipment room floor "* Process equipment room walls 1-3 "* Structures 1-6 "* Trench to bottom of spent fuel storage pit "* Trench at doorway "* Penetrations 1-4 "* D20 pit floor "* D20 pit walls 1-4

The final survey results for Survey Package 12 are summarized below and presented graphically in Figures 4-12B, 4-12C, 4-12D, and 4-12E.

REVISION 0

GA TECH RESEARCH REACTOR FIN-AL SURVEY REPORT

108

Page 122: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

Table 4.13 Survey Package 12

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpmlO00 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2

Direct Beta 396 553 2320 351 587 *Removable Alpha 395 N/A N/A N/A N/A

Removable Beta 395 1 109 9 1 Exposure Rate 171 18.4 uR/hr 22.2 uR/hr 1.8 uR/hr 18.7 uRJhr Removable H-3 59 158 756 117 193

* = All results < MDA (Highest MDA is 5.17 dpm/I00cm2 )

As can be seen from the above table, none of the final survey results for Survey Package 12 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 12 demonstrate that the process equipment room below 2 meters meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

109

Page 123: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-12A Package 12

Map

Process Equipment Room Below 2 Meters

REVISION 0

GA TECH RESEARCH REACTOR FIN-AL SURVIEY REPORT

110

Page 124: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

• TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-12B Package 12

Direct Beta Activity

Process Equipment Room Below 2 Meters Direct Beta Activity 7000000Measurements: 396

Mean: 553 dpm/100 cm2

6000- Maximum: 2320 dpnf100 cm2 Std Deviation: 351 dpm/100 cm2 95% CL on Mean: 587 dpm/100 -m2

5000

o 4000

S3000

oo2000-

1000

0

-1000

- MDA

Surface

REVISION 0

.......................................

/

Ill

Page 125: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA iECH RESEARCH REACTOR

30.0

25.0

rj� 0

20.0

15.0

10.0

5.0

0.0

FINAL SURVEY REPORT

Figure 4-12C Package 12

Exposure Rate Measurements

Process Equipment Room Below 2 Meters Exposure Rate Measurements

Measurements: 171 Mean: 18.4 IAR/hr Std Deviation: 1.8 IPR/hr Baseline + 2 Std. Dev: 22.0 uR/hr Maximum: 22.2 AR/hr 95% CL on Mean: 18.7 yR/hr

if

A IAAAII, ItAAAA AA.0 11 AAIi 11AL IJ nA111,l1 AA1- 1K L AI

II Hi II1n'1BU HH 1V1Hl1 ill 1 1H1H 1 H 1 111L it1111 fil 1

Surface

REVISION 0

Baseline

.. ........

112

Page 126: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA [ECH RESEARCH REACTOR( (R FINAL SURVEY REPORT

Figure 4-12D Package 12

Removable Beta Activity

Process Equipment Room Below 2 Meters Removable Beta Activity600

500

400

300

200

100

0

-100

Surface

REVISION 0

MDA

113

Page 127: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA t'ECH RESEARCH REACTOR(

FINAL SURVEY REPORT

Figure 4-12E Package 12

Removable H-3 Activity

Process Equipment Room Below 2 Meters Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

,,,

Surface

REVISION 0

0 0

c.�J

0

MDA

Measurements: 59 Mean: 158 dpm/100 dm2 Maximum: 756 dpm/100 cm2 Std Deviation: 117 dpm/100 cm2 95% CL on Mean: 193 dpm/100 cm2

i

N 1$ $ ,ýZk 4z 4z ýslv CP CJV'

114

Page 128: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

4.14 Package 13 - Process Equipment Room Above 2 Meters

Classification: Non-Suspect Affected

Survey Package 13 encompassed the reactor building process equipment room walls above 2 meters and the ceiling located in the basement. This package also includes the equipment access hatches that are located in the ceiling of this room. See Figure 4-13A for an overview. This package excludes 3 grids of wall 1 (01W01) row C which were reclassified to suspect affect (see Attachment B, package 13, surface 01W01, grids C12 through C14).

The final survey included 10 % biased beta scans, one direct beta measurement for each 20m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each in2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.

This survey package has only one survey unit that includes the overhead areas of the process equipment room.

The final survey results for Survey Package 13 are summarized below and presented graphically in Figures 4-13B, 4-13C, and 4-13D.

Table 4.14 Survey Package 13

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 30 359 588 134 407 *Removable Alpha 30 N/A N/A N/A N/A

Removable Beta 30 -2 6 3 0 Removable H-3 30 143 458 68 .171 * - All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )

As can be seen from the above table, none of the final survey results for Survey Package 13 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 13 demonstrate that the process equipment room above two meters meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

115

Page 129: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-13A Package 13

Map

Process Equipment Above 2 Meters

REVISION 0116

Page 130: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-13B Package 13

Direct Beta Activity

Process Equipment Room Above 2 Meters Direct Beta Activity

Measurements: 30 Mean: 359 dpm/100 cm2 Maximum: 588 dpmi100 cm2 Std Deviation: 134 dpm/100 cm2 95% CL on Mean: 407 dpm/100 cm2

7000

6000

5000

4000

3000

2000

1000

MDA

Surface

REVISION 0

Ii .:. ii Iii p.m. i.Iiiii.iii� I I � p � I I I I

0

0

-1000

-1

-1

-1

(

117

Page 131: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

r ECH RESEARCH REACTOR(

li'INAT[. •ITIRVEV R1WPC1RT

Figure 4-13C Package 13

Removable Beta Activity

Process Equipment Room Above 2 Meters Removable Beta Activity

Measurements: 30 Mean: -2 dpm/100 crn2 Maximum: 6 dpm/100 era2

Std Deviation: 3 dpro/l00 cm2 95 % CL on Mean: 0 dpi/ 100 cm2

Surface

REVISION 0

600

500

400

300

200

100

Piz

44

Oh

-100

MDA

fl -1

118

Page 132: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA TECH RESEARCH REACTOR (

FINAL SURVEY REPORT

Figure 4-13D Package 13

Removable H-3 Activity

Process Equipment Room Above 2 Meters Removable H-3 ActivityMeasurements: 30 Mean: 143 dpm/100 din2 Maximum: 458 dpm/100 cm2 Std Deviation: 68 dpm/100 cm2 95 % CL on Mean: 171 dpm/100 cm2 ,

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

P.i 0 0D

0D

REVISION 0

;I I iu lip w

Surface

MDA

119

Page 133: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.15 Package 14 - Yard Open Land Areas

Classification: Unaffected

Survey package 14 encompassed 908 square meters of the Unaffected Open Land

Areas of the Reactor Facility Yard. The Open Land Areas of the Reactor Facility

Yard border the south and east sides of the reactor containment building and the

paved road as depicted in figure 4-14A titled "Yard Unaffected Open Land

Areas." The unaffected yard areas were not used for radioactive materials storage.

The survey was conducted by establishing a survey map, see Attachment B, which defined the number and sample location for each required sample. At each

sample location the following was performed:

"* A nine meter square gamma scan to identify elevated areas of activity.

"* One exposure rate measurement at one meter. "* A 0 to 6" soil sample for gamma analysis.

The exposure rate results are summarized in the table below and presented graphically in Figure 4-14B.

Table 4.15 Survey Package 14

Final Exposure Rate Results

Type of # of Meas. Mean Max Std. Dev. 95% CL of mean Measurement

Exposure Rate 30 11.6uR 14.5 uR 1.4uR 12.1uR

The soil analysis results are summarized in the accompanying Table 4.16 titled "Yard Open Land Areas Soil Sample Gamma Spectroscopy Results."

The final survey results for Survey Package 14 demonstrate that the Open Land

Areas meet the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

120

Page 134: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Gti TECH RESEARCH REACTOR FINAL SURVEY REPORT

Table 4.16 Yard Open Land Areas

Soil Sample Gamma Spectroscopy Results

Sample # Mn-54 Co-60 Zn-65 Cs-137 Eu-152

Activity Uncertainty Activity Uncertainty Activity Uncertainty Activity Uncertainty Activity Uncertainty pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g

1 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 2 <MDA N/A <MDA N/A <MDA N/A 3.3116e-1 9.462e-2 <MDA N/A 3 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 4 <MDA N/A 3.1647e- 1 7.975e-2 <MDA N/A 2.1931 e- 1 7.878e-2 <MDA N/A 5 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 6 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 7 <MDA N/A <MDA N/A <MDA N/A 2.8515e-1 9.376e-2 <MDA N/A 8 2.3105e-1 7.925e-2 <MDA N/A <MDA N/A <MDA N/A <MDA N/A 9 <MDA N/A <MDA N/A <MDA N/A 5.1734e-1 1.314e-1 <MDA N/A

9QC <MDA N/A <MDA N/A <MDA N/A 6.6839e-1 1.504e-1 <MDA N/A 10 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 11 2.894e-1 1.008e-1 <MDA N/A <MDA N/A 5.1477e-1 1.329e-1 <MDA N/A 12 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 13 <MDA N/A <MDA N/A <MDA N/A 5.1321e-1 1.372e-1 <MDA N/A 14 <MDA N/A <MDA N/A <MDA N/A 5.3419e-1 1.296e-1 <MDA N/A 15 <MDA N/A <MDA N/A <MDA N/A 6.4240e-1 1.464e-1 <MDA N/A 16 2.5035e-1 8.716e-2 <MDA N/A <MDA N/A 4.1563e-1 1.11le-1 <MDA N/A 17 2.0613e-1 7.791e-2 <MDA N/A <MDA N/A 3.3850e-1 9.875e-2 <MDA N/A

17QC <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 18 <MDA N/A <MDA N/A <MDA N/A 4.4211 e- 1 1.215e-I <MDA N/A 19 <MDA N/A <MDA N/A <MDA N/A 3.4755e-1 9.830e-2 <MDA N/A 20 <MDA N/A <MDA N/A <MDA N/A 7.8097e-1 1.302e-1 <MDA N/A 21 3.8315e-1 1.155e-1 <MDA N/A <MDA N/A 5.3670e-1 1.352e-1 <MDA N/A 22 <MDA N/A <MDA N/A <MDA N/A 3.6222e-1 1.025e-1 <MDA N/A 23 <MDA N/A <MDA N/A <MDA N/A 5.5403e-1 1.430e-l <MDA N/A 24 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 25 <MDA N/A <MDA N/A <MDA N/A 3.8700e-1 1.117e-1 <MDA N/A 26 <MDA N/A <MDA N/A <MDA N/A 3.9772e-1 1.136e-1 <MDA N/A 27 <MDA N/A <MDA N/A <MDA N/A 4.3390e-1 1.203e-1 <MDA N/A 28 <MDA N/A <MDA N/A <MDA N/A 3.8199e-1 1.103e-1 <MDA N/A 29 <MDA N/A <MDA N/A <MDA N/A 1.43e-1 2.89e-2 <MDA N/A 30 <MDA N/A <MDA N/A <MDA N/A 2.6984e-1 9.693e-2 <MDA N/A

Ag-110m and CS-134not included in nuclide library used to analyze soil samples. No unidentified photo peaks found that are associated with Ag-1 10m or Cs-134.

For each sample, none of the individual radionuclide analyses results exceeded 10% of the of the radionuclide specific guideline values listed in Table 3.3.

121 REVISION 0

Page 135: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-14A Package 14

Map

Yard Open Land Areas

FENCE LTNE

ACCESS GATE

NEELY NUCLEAR RESEARCH CENTER

S_ = Unafffected Open Land Areas North ->

REVISION 0

RETAIN'ING

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

122

Page 136: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA. iECH RESEARCH REACTOR( (

FINAL SUR VEY RE'PORT

Figure 4-14B Package 14

Exposure Rate Measurements

Yard Open Land Areas Exposure Rate Measurements

Baseline

NCZ 1,- 0 0 ~ 00 0ý (Z M t't kn ý0 t lN 000 CN Q5 . ('t kn 1f 0 t 000 Qý C 1ý Nýb N Ný! N

Cz C Cz z QýQý q :Z

Location

REVISION 0

15.0

14.0

13.0

12.0

11.0

10.0

9.0

8.0

7.0.

6.0

5.0

4.0

3.0

2.0-

0

1.0

0.0

123

Page 137: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.16 Package 15 - Basement Air Compressor Room

Classification: Suspect Affected

Survey Package 15 encompassed a small room in the basement of the reactor building that housed two air compressors. See Figure 4-15A for an overview of this area.

There was no need to perform decontamination activities in this area. Where practical, accessible surfaces were gridded into lm2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m 2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each mi2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 15 was divided into the following survey units:

"* Floor inside compressor room "* Compressor room walls 1 through 4 "* Ventilation duct 1 located in wall 3 "* Ventilation duct 2 located in wall 1

The final survey results for Survey Package 15 are summarized below and presented graphically in Figures 4-15B, 4-15C, 4-15D, and 4-15E.

Table 4.17 Survey Package 15

Final Survey Results

Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2

Direct Beta 96 879 1975 491 977

*Removable Alpha 96 N/A N/A N/A N/A

Removable Beta 96 1 32 6 2

Exposure Rate 12 34.2 uR/hr 41.6 uR/hr 4.1 uR/hr 36.6 uR/hr

Removable H-3 31 215 905 192 293

• = All results < MDA (Highest MDA is 3.91dpm/100cmL)

Two exposure rate measurement results collected in this area are slightly elevated.

However, the estimated background exposure rate in this area is also elevated. All of the exposure rate measurement results collected in this area are within 2

standard deviation of the mean and meet the criteria established for evaluating exposure rate measurement results.

As can be seen from the above table and figures 4-15A through 4-15E, none of the final survey results for Survey Package 15 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific

guideline value for removable H-3 was exceeded, derivation of the SPGL based

on the site radionuclide mix has been validated. The final survey results for

Survey Package 15 demonstrate that the compressor room of the reactor building

meets the criteria for release for unrestricted use.

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

REVISION 0124

Page 138: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(( TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-15A Package 15

Map

Air Compressor Room

AD

C

1 2

01W0Z (Wall 2)

4 5 601V0t (Ventl)

)VO021

01W03 (Wall 3)

a1Wal (Wall 1)A

D C B A 3 4 5

01(01 (Floor1)

A B C D

A

6 5 4 3

01W04 (Walla4) D - Deontes I Meter Grid

REVISION 0

3

2

125

Page 139: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

I!TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-15B Package 15

Direct Beta Activity

Air Compressor Room Direct Beta Activity 7000 7000 Measurements: 96

6000Mean: 879 dpm/100 cm2 6000 Maximum: 1975 dpm/100 cm2

Std Deviation: 491 dpm/100 cm2 95 % CL on Mean: 977 dpni/100 cm2

5000

S4000

S3000

* 2000 II

.. . . . . ..

S1000l z

- MDA

-1000

Surface

126 tP'%7T tTnrj AJA••V .LIkJ&V. V

Page 140: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA .ECH RESEARCH REACTORFINA SUREY RPO(

FINAL SURVEY REPORT

Figure 4-15C Package 15

Exposure Rate Measurements

Rate Measurements

Baseline

O1FO1

Surface

REVISION 0

1�

rj� 0

45.0

40.0

35.0

30.0

25.0

20.0

15.0

10.0

5.0

0.0

(

127

Page 141: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR

FINAL SURVEY REPORT

Figure 4-15D Package 15

Removable Beta Activity

Air Compressor Room Removable Beta Activity

0m

0

600

500

400

300

200

100

0

-100

Measurements: 96 Mean: I dpm/100 era2

Maximum: 32 dpm/100 cm2 Std Deviation: 6 dpm/100 Hm2 95 % CL on Mean: 2 dpm/100 era2

4�&44�

�\

Surface

128 REVISION 0

MDA

FINAL SURVEY REPORT

Page 142: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(- TECH RESEARCH REACTOR

FINAL SURVEY REPORT

Figure 4-15E Package 15

Removable H-3 Activity

0 0

4e�1

0

Air Compressor Room Removable H-3 Activity4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

10%N 10%v

Surface

REVISION 0

MDA

129

Page 143: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

4.17 Package 16 - Areas Outside Process Equipment Room Below 2 Meters

Classification: Suspect Affected

Survey Package 16 consisted of several areas outside the process equipment room located in the basement. See Figure 4-16A for an overview. This area contained several pieces of contaminated equipment (e.g., pneumatic transfer system, biomedical door hydraulic system, D 2 0 analysis equipment and misc. coolant system lines).

Approximately 10% of the floor area required decontamination. The walls required only minor decontamination. Where practical, accessible surfaces were gridded.

The final survey included 100 % beta scans, one direct beta measurement for each m 2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 17 was divided into the following survey units:

" Rupture disk chamber room "* Floor "* Walls 1-4 "* Ceiling

"* Rabbit room "* Floor "* Walls 1-4

" Experiment room "* Floor "* Walls 1-4

" MCC panel area "* Floor "* Walls 1-3 "* Sump "* Rx vent duct "* A/C vent duct "* Cement blocks "* MCC Panel

" Stairwell general area 0 Floor 0 Walls 1-2 * Structures 1-4 (columns) 0 Structure 5 (exterior of HEPA ventilation unit)

REVISION 0

FINAL SURVEY REPORT

130

Page 144: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

The final survey results for Survey Package 16 are summarized below and presented graphically in Figures 4-16B, 4-16C, 4-16D, and 4-16E.

Table 4.18 Survey Package 16

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 808 294 2046 414 323 *Removable Alpha 808 N/A N/A N/A N/A

Removable Beta 808 2 67 7 3

ExposureRate 348 18.4 uR/hr 35.4 uR/hr 3.3 uR/hr 18.7 uRihr Removable H-3 95 233 1760 269 296 * = All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )

During the Final Survey several of the exposure rate measurements exceeded the SPGL. These measurements were investigated and all were found to be attributed to their location immediately outside the air compressor room block walls. The air compressor room block walls were determined to be composed of materials containing elevated levels of naturally occurring radioactive materials (see package 15).

As can be seen from the above table, none of the final survey results, with the exception of the exposure rate measurements, for Survey Package 16 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 16 demonstrate that the areas outside the process area room of the basement meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

131

Page 145: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TCH RSEARH RECTORFINAL SUTRVEY R~EPORT

Figure 4-16A Package 16

Map

Areas Outside Process Equipment Room Below 2 Meters

• R•• , 055S°

'05S05 05WO1•

05S03 05F01

rocess Equipment Roo Stairwell General Area

Helium Rupture Disk Chamber * 05S02

(below slab)

0 05W02

Rabbit Roo 02 0 2W[4 05S01"

02W03 - .3W403F4

04W02 3W4 03W

03W03 Experim oom

C?04F1 CC XSp04V02

% o4wol N--

REVISION 0

GA TECH RESEARCH REACTOR

132

Page 146: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

((

-1000

Surface

133 REVISION 0

TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-16B Package 16

Direct Beta Activity

Areas Outside Process Equipment Room Below 2 Meters

Direct Beta Activity 7000

Measurements: 808

Mean: 294 dpm/100 cm2

6000 Maximum: 2046 dpm/100 cm2

Std Deviation: 414 dpm/100 cm2

95% CL on Mean: 323 dpm/100 cm2

S5 0 0 0

0I4000

$ 3000

S2000

Z 1000 MDA o 91a

0 ... .. --------

Page 147: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

~'ECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-16.C Package 16

Exposure, Rate Measurements

Areas Outside Process Equipment Room Below 2 Meters Exposure Rate Measurements 40.0

Baselie + 2 td. DvBa25.lpR/e

15.0

10.0

5.0

Surface

134 D~ T 1 f k

F- ~Eviol IN V

Page 148: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

-i .ECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-16D Package 16

Removable Beta Activity

Areas Outside Process Equipment Room Below 2 Meters Removable Beta Activity

600

Measurements: 808

Mean: 2 dpm/100 5m2 500- Maximum: 67 dpm/lO0 cmna Std Deviation: 7 dpm/100 cm2 95% CL ont Mean: 3 dpm/100 cm2

,• 400

S300

'' 200

100

00

-100

MDA

Surface

REVISION 0135

Page 149: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR F]

Figure 4-16E Package 16

Removable H-3 Activity

Areas Outside Process Equipment Room Below 2 Meters Removable H-3 Activity

W W-4

0J

<0

0

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

( INAL SURVEY REPORT

MDA

iý 0 e*1,eI,

Surface

REVISION 0

Measurements: 95 Mean: 233 dpm/ 100 dm2 Maximum: 1760 dpm/100 cm2 Std Deviation: 269 dpmi/100 rm2 95% CL on Mean: 296 dpm/100 cm2

0F001, Row F, Location 6 04V01, Locations 4 & 5

-t/,0ý1 " 160"

136

Page 150: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.18 Package 17 - Areas Outside Process Equipment Room Above 2 Meters

Classification: Non-Suspect Affected

Survey Package 17 encompassed the area outside the process equipment room above 2 meters. It is located in the basement of the reactor building. See Figure 4-17A for an overview. This area consisted of several areas outside the process equipment room and included the wall surfaces from 2 meters above the floor up to and including the ceiling.

There was no decontamination required in these areas. The final survey included 10% biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.

Survey Package 17 was divided into the following survey units:

"* Rabbit room (overhead above 2 meters) "* Experiment room (overhead above 2 meters) "* MCC panel area (overhead above 2 meters) "* Stairwell general area (overhead above 2 meters)

The final survey results for Survey Package 17 are summarized below and presented graphically in Figures 4-17B, 4-17C, and 4-17D.

Table 4.19 Survey Package 17

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 35 213 574 251] 296 *Removable Alpha 35 N/A N/A N/A N/A

Removable Beta 35 -2 73 -1 Removable H-3 35 110 153 19 117 * - All results < MDA ( Highest MDA is 5.17 dpm/1O00cm 2 )

As can be seen from the above table, none of the final survey results for Survey Package 17 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 17 demonstrate that the areas outside the process equipment room above 2 meters meet the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

137

Page 151: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-17A Package 17

Map

Areas Outside Process Equipment Room Above 2 Meters

REVISION 013 8

Page 152: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( GA IECH RESEARCH REACTOR ( FINAL SURVEY REPORT

Figure 4-17B Package 17

Direct Beta Activity

Areas Outside Process Equipment Room Above 2 Meters Direct Beta Activity

SMDA. .ImImI~I .

. . 1 -

Surface

REVISION 0

7000

6000

5000

4000

3000

2000

1000

0

Measurements: 35 Mean: 213 dpm/100 cm2 Maximum: 574 dpm/100 cm2 Std Deviation: 251 dpm/100 cm2 95% CL on Mean: 296 dpm/100 cm2

0

-1000

FINAL SURVEY REPORT

-1

139

. . . . . . . . . . . .

Page 153: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

LA TECH RESEARCH REACTOR

0

0

�0

600

500

400

300

200

100

0

-100

FINAL SURVEY REPORT

Figure 4-17C Package 17

Removable Beta Activity

Areas Outside Process Equipment Room Above 2 Meters Removable Beta Activity

Measurements: 35 Average: -2 dpm/100 din2 Maximum: 7 dpm/100 crD2 Std Deviation: 3 dpm/100 cm2 95% CL on Mean: -1 dpm/100 c=2

-*-- * m--- -* m*-* $-* * -* [ -" = - 9 - * - , n*--l9--* *+* *-* * *'dmdl

Surface

REVISION 0

- MDA

FINA SURVEY REPORT

140

Page 154: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

ý. - TECH RESEARCH REACTOR

0•

0•

$

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

FINAL SURVEY REPORT

Figure 4-17D Package 17

Removable H-3 Activity

Areas Outside Process Equipment Room Above 2 Meters Removable H-3 Activity

Measurements: 35

Mean: 110 dpm/100 din2 Maximum: 153 dpm/100 cm2 Std Deviation: 19 dpm/100 cm2

, ~95% CL on Mean: 117 dpm/1O0 =m2

MDA

Surface

REVISION 0

I

I

141

Page 155: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.19 Package 18 - Reactor Vessel Tunnel

Classification: Suspect Affected

Survey Package 18 encompassed the reactor vessel tunnel and alcove area, The tunnel is located in the basement of the reactor building. See Figure 4-18A for an overview of this area.

There were decontamination activities in this area. Decontamination consisted of concrete removal from a portion the floor and all of the walls. Where practical, accessible surfaces were gridded into lm 2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m 2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 18 was divided into the following survey units:

"* Floor inside tunnel "* Tunnel wall 1 "* Tunnel wall 2 "* Tunnel wall 3 "* Tunnel ceiling "* Tunnel trench

The final survey results for Survey Package 18 are summarized below and presented graphically in Figures 4-18B, 4-18C, 4-18D, and 4-18E.

Table 4.20 Survey Package 18

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cmr dpm/100 cm2 dpm/100 cm2 Direct Beta 59 778 1926 325 861

*Removable Alpha 59 N/A N/A N/A N/A

Removable Beta 59 -1 20 4 0 Exposure Rate 10 28.3 uR/hr 35.2 uR/hr 4.3 uR/hr 31 uR/hr

Removable H-3 30 176 825 150 238 *=All results < MDA (Highest MDA 1.91 dpm/1 00cm 2)

REVISION 0

GA TECH RESEARCH REACTOR

142

FINAL SURVEY REPORT

Page 156: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

As shown in Table 4.20, the exposure rate measurement results collected in this area are slightly elevated. However, the estimated background exposure rate in this area is also slightly elevated. All of the exposure rate measurement results collected in this area are within 2 standard deviation of the mean and meet the criteria established for evaluating exposure rate measurement results.

As can be seen from the above table and the following figures 4-18A through 4-18E, none of the final survey results for Survey Package 18 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. Upon further investigation it was determined that the elevated exposure rate measurement results were due to the geometry effects of the survey area i.e. immediately adjacent concrete structures.

The final survey results for Survey Package 18 demonstrate that the tunnel and alcove area of the reactor building meet the criteria for release.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

143

Page 157: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-18A Package 18

Map

Vessel Tunnel

N

Vessel Tunnel

REVISION 0144

Page 158: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( G,. T ECH RESEARCH REACTOR ( ( FINAl, NTIRVF.V RE.POIRT

Figure 4-18B Package 18

Direct Beta Activity

Vessel Tunnel Direct Beta Activity7000

6000

5000

4000

3000

2000

1000

- MDA

0

-1000

Surface

REVISION 0

40

z

FjNA1r..0%1rjPVYV -UPPOPT

(

145

Page 159: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA iECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-18C Package 18

Exposure Rate Measurements

Vessel Tunnel Exposure Rate MeasurementsMeasurements: 10 Mean: 28.3 ItR/hr Std Deviation: 4.3 dR/hr Baseline + 2 Std. Dev: 36.9 IR/hr Maximum: 35.2 AR/hr 95% CL on Mean: 31.0 ILR/hr

A A A ABaseline

O1FO1

Surface

REVISION 0

40.0

35.0

k

('

30.0

25.0

20.0

15.0

10.0 -

5.0

0.0-

FINAL SURVEY REPORT

I! A

146

Page 160: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

T , TECH RESEARCH REACTOR FINA SUREV RPORFINAL SURVEY REPORT

Figure 4-18D Package 18

Removable Beta Activity

Vessel Tunnel Removable Beta Activity

Surface

REVISION 0

600

500

0

400

300

200

100

0

-100

MDA

(

147

Page 161: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( ( • TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-18E Package 18

Removable H-3 Activity

Vessel Tunnel Removable H-3 Activity 4700

4300Measurements: 30 4300-Mean: 176 dpm/100 din2 Maximum: 825 dpm/100 era2 3900-Std Deviation: 150 dpm/100 cm2 S3900

ۥ. 95 % CL on Mean: 238 dpm/100 era2

o 3500

3100

PW 2700

+-' 2300

S1900

- 1500

1100

S700O

300_ _

SMDA -100

Surface

REVISION 0148

Page 162: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.20 Package 19 - Bismuth Leak Area

Classification: Suspect Affected

Survey Package 19 consisted of the bismuth leak area located in the basement immediately outside the experimental room. This package also includes the biomedical room door pit. This area contained the hydraulic equipment needed to raise and lower the bio-medical room shield doors. See Figure 4-19A for an overview.

This bismuth leak area and the biomedical room door pit required extensive decontamination resulting in Survey Package 19 being classified as suspect affected for purposes of the Final Survey. Approximately 60% of the floor area required decontamination. The walls of the hydraulic shaft area also required decontamination. Where practical, accessible surfaces were gridded.

The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.

Survey Package 19 was divided into the following survey units:

"* Floor "* Walls 1-3 (grid A3 does not exist, wall 4 does not exist) "* Trench 1 "* Ceiling "* Biomedical room door

The final survey results for Survey Package 19 are summarized below and presented graphically in Figures 4-19B, 4-19C, 4-19D, and 4-19E.

Table 4.21 Survey Package 19

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 89 400 1233 288 460 *Removable Alpha 89 N/A N/A N/A N/A

Removable Beta 89 1 19 5 2 Exposure Rate 20 16.9 uR/hr 19.3 uR/hr 1.0 uR/hr 17.3 uR/hr

Removable H-3 30 168 347 75 200 * = All results < MDA (Highest MDA is 8.60 dpm/100cm 2 )

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

149

Page 163: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

As can be seen from the above table, none of the final survey results for Survey Package 19 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 19 demonstrate that the bismuth leak area meets the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

150

Page 164: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-19A Package 19

Map

Bismuth Leak Area

Bismuth Leak Area

REVISION 0151

Page 165: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-9B Package 19

Direct Beta Activity

Bismuth Leak Area Direct Beta Activity 7000

Measurements: 89 Mean: 400 dpm/100 cm2

6000 Maximum: 1223 dpm/100 cu2 Std Deviation: 288 dpm/100 cm2 95 % CL on Mean: 460 dpm/ 100 cm2

5000

S 4000

"tZ 3000

2000

"• 1000- MDA

0 o HH I I I I I. Ii1-IlI!,iII I HIil I I I HI1r.HIH

-1000

Surface

REVISION 0152

Page 166: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA 'TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-19C Package 19

Exposure Rate Measurements

Bismuth Leak Area Exposure Rate Measurements

Baseline

Surface

REVISION 0

25.0 24.0 23.0 22.0 21.0 20.0 19.0 18.0 17.0 16.0 15.0 14.0 13.0 12.0

11.0 10.0

9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0

'-4

rj) 0

t

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

153

Page 167: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR(

FINAL SURVEY RE'PORT'

Figure 4-19D Package 19

Removable Beta Activity

Bismuth Leak Area Removable Beta Activity600

500

400

300

200

100

0

100

Surface

MDA

& &

REVISION 0

0

0

$

154

Page 168: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-19E Package 19

Removable H-3 Activity

Bismuth Leak Area Removable H-3 Activity

Measurements: 30 Mean: 168 dpm/100 din2 Maximum: 347 dpm/100 crn2 Std Deviation: 75 dpm/100 cm2 95 % CL on Mean: 200 dpm/100 cm2

0 0

�eI�

0

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100

C)

Surface

REVISION 0

-- -I--i - -i--- - -t I ~ I I T'I'0 I n . I 1 I I ' , I -I I I I I. MDA

155

Page 169: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.21 Package 20 - Reactor Ventilation Above 2 Meters

Classification: Non-Suspect Affected

Survey Package 20 encompassed the reactor building process ventilation system

above 2 meters, including any ceilings. See Figure 4-20A for an overview.

A small area on the floor of the stack was decontaminated since it slightly

exceeded the SPGL. This was always considered a possibility given that the floor

and lower walls of both the stack and the stack fan room were classified as

Suspect Affected.

The final survey included 10 % biased beta scans, one direct beta measurement

for each 20m2 of accessible surface area, one smear of removable surface

contamination (beta and alpha) for each m2 of accessible surface area, and a

number of smears to assess H-3 contamination levels. The biased locations were

chosen by the technician performing the survey, and were based on the most

probable areas for contamination.

Survey Package 20 was divided into the following survey units:

"* Reactor building stack main vent room "* Instrument room "* Reactor building stack

The final survey results for Survey Package 20 are summarized below and

presented graphically in Figures 4-20B, 4-20C, and 4-20D.

Table 4.22 Survey Package 20

Final Survey Results

Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 30 92 1219 352 218

*Removable Alpha 30 N/A N/A N/A N/A

Removable Beta 30 2 28 8 5

Removable H-3 30 219 1133 253 323

* All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )

As can be seen from the above table, none of the final survey results for Survey

Package 20 exceeded the Site Specific Guideline Values (SPGLs). Since neither

the SPGL nor the radionuclide specific guideline value for removable H-3 was

exceeded, derivation of the SPGL based on the site radionuclide mix has been

validated. The final survey results for Survey Package 20 demonstrate that the

reactor process ventilation system above two meters meets the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

156

Page 170: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TCH RSEARH RECTORFINAL SUR VEY REPOR~T

Figure 4-20A Package 20

Map

Reactor Ventilation Above 2 Meters

N

REVISION 0

GA TECHI RESEARCH REACTOR

157

Page 171: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTORFINAL SURVEY REPORT

Figure 4-20B Package 20

Direct Beta Activity

Reactor Ventilation, Above 2 Meters Direct Beta. Activity7000

6000

5000

4000

3000

2000

1000

0

-1000

Surface

REVISION 0

MDA

0 0

"0

z

158

Page 172: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

( JECH RESEARCH REACTOR (FINAL SURVEY REPORT

Figure 4-20C Package 20

Removable Beta Activity

Reactor Ventilation Above 2 Meters Removable Beta Activity

MDA

Surface

REVISION 0

600

500

3-4 0

400

300

200

100

0

-100

159

Page 173: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

A TECH RESEARCH REACTOR (

Figure 4-20D Package 20

Removable H113 Activity

Reactor VentilationAbove 2 Meters Removable H-3 Activity

0 0

"0

Q

0

4700

4300

3900

3500

3100

2700

2300

1900

1500

1100

700

300

-100 MDA

Surface

REVISION 0160

Page 174: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

4.22 Package 21 - Elevator Equipment Room and Shaft

Classification: Unaffected

Survey Package 21 encompassed the reactor building elevator equipment room and the elevator shaft. See Figure 4-21A for an overview.

No decontamination was required in these areas. No known radioactive materials were transported through these areas.

The final survey included 10% beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one exposure rate measurement at each corresponding direct beta measurement on the floor, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.

Survey Package 21 was divided into the following survey units:

"* Elevator shaft "• Elevator equipment room

The final survey results for Survey Package 21 are summarized below and presented graphically in Figures 4-21B, 4-21C, 4-21D and 4-21E.

Table 4.23 Survey Package 21

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2

Direct Beta 30 158 580 243 245 *Removable Alpha 30 N/A N/A N/A N/A

Removable Beta 30 9 64 16 15 Exposure Rate 6 17.9 uR/hr 19.5 uRihr 1.4 u R/hr 19 uR/hr

Removable H-3 30 307 1130 266 417 * - All results < MDA (Highest MDA is. 8.60 dpm/1 00cm2 )

As can be seen from the above table, none of the final survey results for Survey Package 21 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 21 demonstrate that elevator shaft and equipment room meet the criteria for release for unrestricted use.

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

161

Page 175: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-21A Package 21

Map

Elevator Equipment Room and Shaft

REVISION 0162

Page 176: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GI [ECH RESEARCH REACTOR FINAL SUJRVEY REPORT

Figure 4-21B Package 21

Direct Beta Activity

Elevator Equipment Room & Shaft Direct Beta Activity7000

-6000

5000

4000

3000

2000

1000

0

-1000

Surface

REVISION 0

MDA

"z:

Measurements: 30 Mean: 158 dpm/100 c=2 Maximum: 580 dpm/100 cm2 Std Deviation: 243 dprn/100 =2 95% CL on Mean: 245 dpm/100 cm2

FINAL SURVEY REPOR

163

Page 177: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA fECH RESEARCH REACTOR(

FINAL SURVEY REPORT

Figure 4-21C Package 21

Exposure Rate Measurements

Elevator Equipment Room & Shaft Exposure Rate Measurements

Measurements: 6 _____________________________________________Mean: 17.9,u/LRhr _____________

Std Deviation: 1.4 ItR/hr Baseline + 2 Std. Dey: 20.6 AzR/hr Maximum: 19.5 ItR/hr_______________

95 % CL on Mean: 19.0 /AR/hr

40.0

35.0

30.0

25.0

20.0

15.0

10.0

5.0

0.0 r.'

Baseline

Surface

REVISION 0

________ 4.'�

"0"

A A

I

164

Page 178: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

Gt& TECH RESEARCH REACTOR(

FINAL SURVEY REPORT

Figure 4-21D Package 21

Removable Beta Activity

Elevator Equipment Room & Shaft Removable Beta Activity

MDA

Surface

REVISION 0

600

500

400

300

200

100

0

0

$

-1

Measurements: 30 Mean: 9 dpm/100 cm2 Maximum: 64 dpm/100 cm2 Std Deviation: 16 dpm/100 cm2 95% CL on Mean: 15 dpm/100 cnr2

0

-100

FINAL SURVEY REPORT

-1

,, , , ' ' .. ' - , ,, - • - ,,,, -- , ,,,, , ' ' _.",'m , ,± ,,•.+-j• 4 -"+-j.±- ,,+ : -

/ (

165

Page 179: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

T GiA TECH RESEARCH REACTOR

.¶ 0

FINAL �TTflVFV 1�EPORT

Figure 4-21E Package 21

Removable H-3 Activity

Elevator Equipment Room & Shaft Removable H-3 Activity 4700

4300 Measurements: 30 Mean: 307 dpm/100 dm2 Maximum: 1130 dpm/100 cm2

3900 Std Deviation: 266 dpm/100 cm2 95% CL on Mean: 417 dpm/100 cm2

3500

3100

2700

2300

1900

1500

1100

7OO

3OO

-100-

Surface

REVISION 0

MDA

FINAL SURVEY 111 PORT

(

166

Page 180: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR

4.23 Package 22 - Misc. Pipes and Penetrations

Classification: Suspect Affected

Survey Package 22 encompassed various pipes and penetrations found on the reactor building first floor and other miscellaneous areas in the basement. See Figures 4-22A, 4-22B and 4-22C for an overview.

No decontamination was required in any of these penetrations and pipes.

The final survey included 100 % beta scans of all accessible areas, one direct beta measurement for each penetration, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, and a number of smears to assess H-3 contamination levels.

Survey Package 22 was divided into the following survey units:

"* 1 st floor plug holes

"* Other penetrations & pipes ( all areas)

The final survey results for Survey Package 22 are summarized below and presented graphically in Figures 4-22D, 4-22E, and 4-22F.

Table 4.24 Survey Package 22

Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean

Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2

Direct Beta 118 225 1767 608 335 *Removable Alpha 120 N/A N/A N/A N/A

Removable Beta 120 9 102 15 12 Removable H-3 30 210 650 129 264

* - All results < MDA (Highest MDA is. 8.60 dpm/1 00cm2 )

As can be seen from the above table, none of the final survey results for Survey Package 22 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 22 demonstrate that these penetrations and pipes meet the criteria for release for unrestricted use.

REVISION 0

FINAL SURVEY REPORT

167

Page 181: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-22A Package 22

Misc. Pipes and Penetrations First Floor (01P00)

__ (D - Denotes L8 number and approximate location of pipe or penetration.

REVISION 0

GA TECH RESEARCHJ REACTOR FINAL SURVEY REPORT

168

Page 182: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-22B Package 22

Misc. Pipes and Penetrations First Floor (02P00)

Q - Denotes L8 number and approximate location of pipe or penetration.

REVISION 0

FLNAL SURVEY REPORTGA TECH RESEARCH REACTOR

169

Page 183: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPOR~T

Figure 4-22C Package 22

Misc. Pipes and Penetrations Basement (02P00)

Elevator Equipment Room

N---

0 - Denotes L8 number and approximate location of pipe or penetration.

REVISION 0

FINAL SURVEY REPOR

170

Page 184: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

/TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-22D Package 22

Direct Beta Activity

Misc. Pipes and Penetrations Direct Beta Activity 7000

Measurements: 118 Mean: 225 dpm/100 cm2 6000 Maximum: 1767 dpm/100 cm2

Std Deviation: 608 dpm/100 cm2 95% CL on Mean: 335 dpm/100 cm2

S5000

- 4000

' 3000

2000 MDA

1000

1-11 1 111 1~II. M2I1 lil l Ijj. II11111 J 1 ,1I11 I 1 '1 1 - -H I II- I i

-1000

Surface

171 'D U:• o1,-.LN ,).. 1,V 101 k.IN V

Page 185: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

I

Misc. Pipes and Penetrations Removable Beta Activity600

500

400

300

200

100

0

-100

Surface

172

MDA

REVISION 0

34

0

Measurements: 120 Mean: 9 dpm/100 cm2 Maximum: 102 dpm/100 cm2 Std Deviation: 15 dpm/100 cm2 95% CL on Mean: 12 dpm/100 cm2

J'J•:J:l• •; JWF'~l~ •=~l•J l~l~;IJ"•tU~lJ;~lJ~~rl=;I~ • • •~ l• ii•'r;ii;••HH•----------:i•I~~iif

/TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-22E Package 22

Removable Beta Activity

/

Page 186: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

_ TECH RESEARCH REACTOR FINAL SURVEY REPORT

Figure 4-22F Package 22

Removable H-3 Activity

Misc. Pipes and Penetrations Removable H-3 Activity 4700

4300measurements: 30 4300-Mean: 210 dpm/100 d-2 Maximum: 650 dpm/100 cm2

3900 Std Deviation: 129 dpm/100 cm2 95 % CL on Mean: 264 dpm/100 cm2

S3500

- 3100

,e 2700

. 2300

S1900 1500

S1100

p4 700 300

_____"_ i__l_____ ,-_____________i____,__ ,i__ ______ _ ,!• • I• ;,1 •MDA

-100

Surface

173 1?T)VTQTC~ .1XT'- V Li 0~1

Page 187: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

5.0 CONCLUSIONS

Based on the results of the final survey presented in Section 4, the Georgia Institute of Technology Research Reactor located at 900 Atlantic Drive in Atlanta, Georgia meets the requirements for release for unrestricted use. As a result, it is recommended that the NRC radioactive material license number R-97 be terminated.

6.0 REFERENCES

6.1 NES Inc., Georgia Institute of Technology Research Reactor Decommissioning

Plan, June 1998.

6.2 USNRC Regulatory Guide 1.86, Termination of Operating Licenses for Nuclear

Reactors.

6.3 USNRC NUREG/CR-5 849, Manual for Conducting Radiological Surveys in

Support of License Termination, Draft, June, 1992

6.4 Letter from GSFIC Project 1-47 Executive Engineer (CH2MHill) to IT Corporation, Response to letter dated April 5, 2000, Final Release Survey Plan Request for Complete, Definite, and Clear Instructions (Article E-3), April 18, 2000.

6.5 10 CFR19, Notices, Instructions, and Reports to Workers; Inspections

6.6 10 CFR20, Standards for Protection Against Radiation.

6.7 American National Standard Institute, ANSI N323-1978, Radiation Protection

Instrumentation Test and Calibration

6.8 American National Standard Institute, ANSI N42.17A- 1989, Performance

Specifications for Health Physics Instrumentation - Portable Instrumentation for Use in Normal Environmental Conditions

6.9 The IT Group, Quality Assurance Project Plan & Quality Assurance Procedures for the Georgia Institute of Technology Research Reactor Decommissioning Project

7.0 ATTACHMENTS

Attachment A Worksheets for Calculations of Site Specific Guideline Values

Attachment B Final Survey Packages 1 through 22

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

174

Page 188: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Attachment A

Worksheets for Calculations of Site Specific Guideline Values

REVISION 0

FINAL SURVEY REPORTGA TECH RESEARCH REACTOR

Page 189: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

ATTACHMENT A

Calculation of Site-Specific Guideline Values (SPGLs)

The equation used to calculate the site-specific guideline value for each of the three samples is:

F SPGL =

ZL 1

Where: F = The fraction of the radionuclide mix that is considered detectable, unitless.

fi = The relative fraction of radionuclide i in the mix, unitless

GL1 = The radionuclide specific guideline, dpm/100 cm 2 from

Table 2.1

Using this equation, a site-specific guideline value (SPGL) was calculated for both average total

activity and removable activity for each of three samples selected for 10 CFR Part 61 analysis.

Average SPGLs were then calculated based on the SPGLs obtained for each sample. The

calculated SPGLs are summarized in the table below.

Calculation of Site-Specific Guideline Values

rflescrintion

Calculated guideline value for average total activity

Sam pie GEL-1 Concrete under Reactor Vessel

1�

Activity ) (dDm/100cm)

. . . .ri . . •

1,500

Sample G Concret

Biomedica Pit

Activi (dpm/100

EL-2 - Sample GEL-3 e in Primary Resin

I Door Sam pie

ty 2 Activity 1cm ) (dpm/100cm

2

3,800 2,000

48

Average of Samples

GEL-i, 2, & 3

Activity (dpm/1OOcm 2

)

2,400

313Calculated guideline value for 104 688

removable activity

Page 190: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(

SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-I (TOTAL ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cmA2

SAMPLE GEL-1 (CONCRETE SAMPLE) COLLECTED UNDER VESSEL ON 1/12/00

NUCLIDE

H-3 Fe-55

Pu-239/240 U-233/234

U-238 Ni-59

Cs-134 Cs-137 Co-60 Eu-152 Eu-154 Mn-54

Ag-I 10m Zn-65 Sr-90 C-14 Ni-63 Tc-99

Act pCi/g

3.170E+04 1.670E+02

1.71 OE+00 1.650E+00

7.560E-01 1.21 OE+00 1.530E+02 7,040E+00 1.41 OE+00

7.350E-01 2.11 OE+02 6.930E+01 1.91 OE+00

3.232E+04

HALF-LIFE years

1.228E+01 2.700E+00 2.413E+04 1.592E+05 4.460E+09 7.500E+04 2.062E+00 3.017E+01 5.271 E+00 1.360E+01 8.800E+00 8.600E-01 6.800E-01 6.700E-01 2.860E+01 5.730E+03 1.001 E+02 2.130E+05

Detectable Y/N

N N N N Y N Y Y Y Y Y N Y N Y Y N Y

GL

2.OOOE+05 2.OOOE+05 1.000E+02 5.000E+03 5.OOOE+03 5.000E+03 5.OOOE+03 5.OOOE+03 5.OOOE+03 5.OOOE÷03 5.OOOE+03 5.OOOE+03 5.OOOE+03 5.OOOE+03 1.OOOE+03 5.000E+03 5.OOOE+03 5.OOOE+03

f

9,808E-01 5.167E-03 0.OOOE+00 5.291 E-05 5.105E-05 0.000E+00 2.339E-05 3.744E-05 4.734E-03 2.178E-04 4.363E-05 0.OOOE+00 0.OOOE+00 0.OOOE+00 2.274E-05 6.528E-03 2,144E-03 5.91 OE-05

9,999E-01

SPGL 1.516E+03

F

5.106E-05

2,339E-05 3.744E-05 4.734E-03 2.178E-04 4.363E-05

0.000E+00

2.274E-05 6.529E-03

5.91 OE-05

1 .172E-02

f/G L

4.904E-06 2.584E-08 0.000E+00 1.058E-08 1.021E-08 0.OOOE+00 4.678E-09 7.488E-09 9.468E-07 4.356E-08 8.725E-09 0.000E+00 0.OOOE+00 0.000E+00 2.274E-08 1.306E-06 4.288E-07 1 .182E-08

7.731 E-06

Page 191: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(

SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-2 (TOTAL ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cm^2

SAMPLE GEL-2 (CONCRETE SAMPLE) COLLECTED IN MEDICAL DOOR TO PIT ON 1/12/00

NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N

H-3 1.390E+02 1.228E+01 N 2.OOOE+05 1.382E-01 6.909E-07 Fe-55 4.680E+02 2,700E+00 N 2.000E+05 4.652E-01 2,326E-06

Pu-239/240 < 2.413E+04 N 1.000E+02 0.000E+00 0,OOOE+00 U-233/234 9.520E-01 1.592E+05 N 5.OOOE+03 9.463E-04 1.893E-07

U-238 6.850E-01 4.460E+09 Y 5.OOOE+03 6.809E-04 6.809E-04 1.362E-07 Ni-59 < 7.500E+04 N 5.OOOE+03 0.OOOE+00 0.OOOE+00

Cs-134 < 2.062E+00 Y 5.000E+03 0.OOOE+00 0.OOOE+00 0.000E+00 Cs-137 2.460E+00 3.017E+01 Y 5,000E+03 2.445E-03 2.445E-03 4.891E-07 Co-60 2.340E+02 5.271E+00 Y 5.OOOE+03 2.326E-01 2.326E-01 4,652E-05 Eu-152 1.460E+00 1.360E+01 Y 5.000E+03 1.451 E-03 1,451 E-03 2,903E-07 Eu-154 < 8.800E+00 Y 5.OOOE+03 0.000E+00 0.OOOE+00 0.OOOE+00 Mn-54 < 8.600E-01 N 5.OOOE+03 0.000E+00 0.000E+00

Ag-110m < 6.800E-01 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 O.OOOE+00 Zn-65 < 6.700E-01 N 5.OOOE+03 0.000E+00 0,OOOE+00 Sr-90 < 2.860E+01 Y 1.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00 C-14 7.740E+01 5.730E+03 Y 5.OOOE+03 7.694E-02 7.694E-02 1.539E-05 Ni-63 8.200E+01 1.001 E+02 N 5,OOOE+03 8,151 E-02 1.630E-05 Tc-99 < 2.130E+05 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00

1.006E+03 1.OOOE+00 3.141 E-01 8,233E-05

SPGL 3.815E+03

l,

Page 192: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

(

SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-3 (TOTAL ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cmA2

SAMPLE GEL-3 (RESIN SAMPLE) FROM PRIMARY COOLANT SYSTEM COLLECTED 1/12/00

NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N

H-3 4.880E+07 1.228E+01 N 2.000E+05 9.827E-01 4.913E-06 Fe-55 2.020E+03 2.700E+00 N 2.OOE+05 4.068E-05 2.034E-10

Pu-239/240 9.460E-01 2.413E+04 N 1.OOOE+02 1.905E-08 1.905E- 10 U-233/234 6.860E-01 1.592E+05 N 5,OOOE+03 1.381 E-08 2.763E-1 2

U-238 < 4.460E+09 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00 Ni-59 2.690E+01 7.500E+04 N 5.OOOE+03 5.417E-07 1,083E- 10

Cs-134 1.700E+01 2.062E+00 Y 5.OOOE+03 3.423E-07 3.423E-07 6.847E- 11 Cs-137 4.220E+03 3.017E+01 Y 5.OOOE+03 8,498E-05 8.498E-05 1,700E-08 Co-60 1.220E+04 5.271E+00 Y 5.OOOE+03 2.457E-04 2.457E-04 4.913E-08 Eu-152 1.310E+01 1.360E+01 Y 5.OOOE+03 2.638E-07 2.638E-07 5.276E-11 Eu-1 54 < 8.800E+00 Y 5.OOOE+03 0.OOOE+00 O.OOOE+00 0.OOOE+00 Mn-54 5.330E+01 8.600E-01 N 5.OOOE+03 1.073E-06 2.147E-10

Ag-110m 1.220E+02 6.800E-01 Y 5.OOOE+03 2.457E-06 2.457E-06 4.913E-10 Zn-65 1.500E+02 6.700E-01 N 5.OOOE+03 3.021 E-06 6.041 E-10 Sr-90 6.570E+03 2.860E+01 Y 1.OOOE+03 1.323E-04 1.323E-04 1,323E-07 C-14 8.320E+05 5.730E+03 Y 5.OOOE+03 1.675E-02 1.675E-02 3.351E-06 Ni-63 •4.800E+03 1.001 E+02 N 5.OOOE+03 9.666E-05 1.933E-08 Tc-99 1.140E+02 2.130E+05 Y 5.OOOE+03 2.296E-06 2.296E-06 4.591E-10

4.966E+07 1.OOOE+00 1.722E-02 8.484E-06

SPGL 2.030E+03

Page 193: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

"( (/

SI I E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-I (REMOVABLE ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2

SAMPLE GEL-1 COLLECTED UNDER VESSEL ON 1/12/00

NUCLIDE Act HALF-LIFE Detectable GL f F f/GL

pCi/g years Y/N

H-3 3.170E+04 1.228E+01 N 1.000E+04 9.808E-01 9.808E-05

Fe-55 1.670E+02 2.700E+00 N 1.000E+04 5.167E-03 5.167E-07

Pu-239/240 < 2.413E+04 N 2.000E+01 0.000E+00 0.000E+00

U-233/234 1.710E+00 1.592E+05 N 1.OOOE+03 5.291 E-05 5.291 E-08

U-238 1.650E+00 4.460E+09 Y 1.OOOE+03 5.105E-05 5.105E-05 5.105E-08

Ni-59 < 7.500E+04 N 1.OOOE+03 0.OOOE+00 0.OOOE+00

Cs-134 7.560E-01 2.062E+00 Y 1.OOOE+03 2.339E-05 2.339E-05 2.339E-08

Cs-137 1.210E+00 3.017E+01 Y 1.OOOE+03 3.744E-05 3.744E-05 3.744E-08

Co-60 1.530E+02 5.271 E+00 Y 1.000E+03 4.734E-03 4.734E-03 4.734E-06

Eu-152 7.040E+00 1.360E+01 Y 1.000E+03 2.178E-04 2.178E-04 2.178E-07

Eu-1 54 1.41 OE+00 8.800E+00 Y 1.000E+03 4.363E-05 4.363E-05 4.363E-08

Mn-54 < 8.600E-01 N 1.000E+03 0.OOOE+00 0.000E+00

Ag-110m < 6.800E-01 Y 1.000E+03 0.000E+00 0.OOOE+00 0.000E+00

Zn-65 < 6.700E-01 N 1.000E+03 0.000E+00 0.000E+00

Sr-90 7.350E-01 2.860E+01 Y 2.OOOE+02 2.274E-05 2.274E-05 1.137E-07

C-14 2.11OE+02 5.730E+03 Y 1.OOOE+03 6.528E-03 6.528E-03 6.528E-06

Ni-63 6.930E+01 1.001 E+02 N 1.000E+03 2.144E-03 2.144E-06

Tc-99 1.910E+00 2.130E+05 Y 1.000E+03 5.910E-05 5.910E-05 5.910E-08

3.232E+04 9.999E-01 1.172E-02 1.126E-04

SPGL 1.041 E+02

Page 194: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

b, E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-2 (REMOVABVLr- ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2

SAMPLE GEL-2 COLLECTED AT DOOR TO PIT ON 1/12/00

NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N

H-3 1.390E+02 1.228E+01 N 1.000E+04 1.382E-01 1.382E-05 Fe-55 4.680E+02 2.700E+00 N 1.OOOE+04 4.652E-01 4.652E-05

Pu-239/240 < 2.413E+04 N 2.OOOE+01 0.000E+00 O.000E+00 U-233/234 9.520E-01 1.592E+05 N 1.000E+03 9.463E-04 9.463E-07

U-238 6.850E-01 4.460E+09 Y 1.000E+03 6.809E-04 6.809E-04 6.809E-07 Ni-59 < 7.500E+04 N 1.000E+03 0.000E+00 0.OOOE+00

Cs-1 34 < 2.062E+00 Y 1.000E+03 0.OOOE+00 O.OOOE+00 0.000E+00 Cs-1 37 2.460E+00 3.017E+01 Y 1.000E+03 2.445E-03 2.445E-03 2.445E-06 Co-60 2.340E+02 5.271 E+00 Y 1.000E+03 2.326E-01 2.326E-01 2.326E-04 Eu-152 1.460E+00 1.360E+01 Y 1.000E+03 1.451 E-03 1.451 E-03 1.451 E-06 Eu-1 54 < 8.800E+00 Y 1.000E+03 0.OOOE+00 0.000E+00 0.000E+00 Mn-54 < 8.600E-01 N 1.000E+03 0.OOOE+00 0.OOOE+00

Ag-110m < 6.800E-01 Y 1.OOOE+03 0.OOOE+00 0.000E+00 0.OOOE+00 Zn-65 < 6.700E-01 N 1.000E+03 0.OOOE+00 0.OOOE+00 Sr-90 < 2.860E+01 Y 2.OOOE+02 0.OOOE+00 0.000E+00 0.000E+00 C-14 7.740E+01 5.730E+03 Y 1.000E+03 7.694E-02 7.694E-02 7.694E-05 Ni-63 8.200E+01 1.001 E+02 N 1.000E+03 8.151 E-02 8.151 E-05 Tc-99 < 2.130E+05 Y 1.000E+03 0.000E+00 0.OOOE+00 0.OOOE+00

1.006E+03 1.OOOE+00 3.141 E-01 4.569E-04

SPGL 6.875E+02

Page 195: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

/(

E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-3 (REMOVABLt ACTIVITY)

RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2

SAMPLE GEL-3 RESIN SAMPLE COLLECTED 1/12/00

NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N

H-3 4.880E+07 1.228E+01 N 1.000E+04 9.827E-01 9.827E-05 Fe-55 2.020E+03 2.700E+00 N 1.000E+04 4.068E-05 4.068E-09

Pu-239/240 9.460E-01 2.413E+04 N 2.OOOE+01 1.905E-08 9.525E-10 U-233/234 6.860E-01 1.592E+05 N 1.OOOE+03 1.381 E-08 1.381 E-1 1

U-238 < 4.460E+09 Y 1.000E+03 0.000E+00 0.OOOE+00 0.OOOE+00 Ni-59 2.690E+01 7.500E+04 N 1.000E+03 5.417E-07 5.417E-10

Cs-134 1.700E+01 2.062E+00 Y 1.OOOE+03 3.423E-07 3.423E-07 3.423E-10 Cs-137 4.220E+03 3.017E+01 Y 1.OOOE+03 8.498E-05 8.498E-05 8.498E-08 Co-60 1.220E+04 5.271 E+00 Y 1.OOOE+03 2.457E-04 2.457E-04 2.457E-07 Eu-152 1.310E+01 1.360E+01 Y 1.OOOE+03 2.638E-07 2.638E-07 2.638E-10 Eu-154 < 8.800E+00 Y 11.000E+03 0.OOOE+00 0.000E+00 0.OOOE+00 Mn-54 5.330E+01 8.600E-01 N 1.000E+03 1.073E-06 1.073E-09

Ag-1I0m 1.220E+02 6.800E-01 Y 1.OOOE+03 2.457E-06 2.457E-06 2.457E-09 Zn-65 1.500E+02 6.700E-01 N 1.OOOE+03 3.021E-06 3.021 E-09 Sr-90 6.570E+03 2.860E+01 Y 2.OOOE+02 1.323E-04 1.323E-04 6.615E-07 C-14 8.320E+05 5.730E+03 Y 1.000E+03 1.675E-02 1.675E-02 1.675E-05 Ni-63 4.800E+03 1.001 E+02 N 1.OOOE+03 9.666E-05 9.666E-08 Tc-99 1.140E+02 2.130E+05 Y 1.000E+03 2.296E-06 2.296E-06 2.296E-09

1.000E+03 4.966E+07 1.OOOE+00 1.722E-02 1.161 E-04

SPGL 1.483E+02

ATTACHMENT A, Page 2

Page 196: Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the Georgia Institute of Technology Research Reactor Facility NRC License Number R-97 GSFIC

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT

Attachment B

Final Survey Packages 1 through 22

REVISION 0

GA TECH RESEARCH REACTOR FINAL SURVEY REPORT