152

PARLIAMENT OF · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Embed Size (px)

Citation preview

Page 1: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 2: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 3: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

PARLIAMENT OF VICTORIA

NATURAL RESOURCES AND ENVIRONMENT COMMITTEE

No.95

REPORT UPON

ELECTRICITY SUPPLY AND DEMAND

BEYOND THE MID-1990'S

Ordered to be Printed

APRIL 1988

Page 4: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 5: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

NATURAL RESOURCES AND ENVIRONMENT COMMITTEE

MEMBERSHIP

The Honourable N.B. Reid, M.L.C. (Chairman)

The Honourable B.T. Pullen, M.L.C. (Deputy Chairman)

Mrs. J.M. Hill, M.P.

The Honourable R. Lawson, M.L.C.

The Honourable L.A. McArthur, M.L.C.

Mr. M.J. McDonald, M.P.

Mr. J.F. McGrath, M.P.

Mr. W.D. McGrath, M.P.

The Honourable B.W. Mier, M.L.C.

Mr. E.M.P. Tanner, M.P.

The Honourable C.F. V an Buren, M.L.C.

Dr. R.J.H. Wells, M.P.

Mr. M.R. Knight

Miss V. Velickovic

Mr. A.G. O'Neil

Ms E. Roadley

Mr. P. Garlick

Mr.B.NewelJ

Miss D. Kowalski

COMMITTEE STAFF

Director of Research

Secretary

Research Officer

Research Officer (to end of October 1987)

Consultant

Consultant (October, November 1987)

Word Processor Operator (to end February 1988)

*******

iii

Page 6: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 7: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

OVERALL TERMS OF REFERENCE

PARLIAMENTARY COMMITTEES ACT 1968

4C. The functions of the Natural Resources and Environment Committee shall be to inquire into, consider and report to the Parliament on -

(a) any proposal, matter or thing concerned with the natural resources of the State;

(b) how the natural resources of the State may be conserved;

(c) any proposal, matter or thing concerned with the environment;

(d) how the quality of the environment may be protected and improved; and

(e) any works or proposed works reasonably capable of having significant effect upon the resources of the State or the environment--

where the Committee is required or permitted so to do by or under this Act.

* * *

V

Page 8: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CONTENTS OF THE REPORT

CHAPTER Page

I. Introduction 1

1.1 Terms of Reference

1.2 Request for Additional Information 2

1.3 Amended Reporting Date 2

1.4 Public Consultation Prior to this Inquiry 3

1 • .5 The Inquiry Programme and Public Consultation 3

1.6 Use of Consultants 6

1.7 Format of the Report 6

1.8 Differences from the Preliminary Report and Draft Recommendations 7

2. Balancing Electricity Supply and Demand 9

2.1 Introduction 9

2.2 Demand Forecast 9

2.3 Existing Generating Capacity 13

2.4 Planned Availability and Retirement of Generating Capacity 13

2 • .5 Additional Supply Capacity Prior to the Mid-1990's 14

2.6 Plant Mix 1.5

2.7 Balancing Supply and Demand 1.5

3. Pricing, Demand Side Measures and Energy Conservation 19

3.1 Introduction 19

3.2 Pricing 19

3.3 Demand Side Measures and Energy Conservation 20

3.4 Assessment of Demand Side Measures and Energy Conservation 23

3 • .5 Integrated Planning 24

3.6 The Greenhouse Effect 24

3.7 Specific Recommendations 2.5

vi

Page 9: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER Page

•• The Performance of Existing Generating Plant and the Development of Improved Plant for the Future 27

4.1 Introduction 27

4.2 Plant Availability 27 4.3 Extending Plant Lifetimes 29 4.4 Research and Development into Electricity

Generation from Brown Coal 32

4.4.1 Boiler Plant 33 4.4.2 Coal Winning Techniques 36 4.4.3 Predpitators and Ash Handling Plant 36 4.4.4 New Coal Preparation or Combustion

Technologies 36 4.5 Specific Recommendations 38

,5. Large Scaie Supply Options 41

5.1 Introduction 41

5.2 Overview of Options 42

5.3 Location of Options 46

5.4 Status of Evidence on Options 46 5.5 Option Costs and Workforces 51 5.6 ReliabHity and Energy Efficiency Options 60 5.7 Environmental Impacts Common to Large Scale

Power Supply Options 61 5.8 Environmental Impacts of Individual Options 63 5.9 Preliminary Discussion of Options 67

5.10 Cost of Delivered Power from Selected Options 71

.5.11 Conclusions 71 5.12 Specific Recommendations 73

vii

Page 10: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER Page

6. Small Scale Supply Options 75 6.1 Introduction 75 6.2 Roles for Small Scale Supply Options 75

6.3 Small Scale Options and Technologies 76 6.4 Supply Planning and Small Scale Options 80 6.5 Specific Recommendations 81

7. Modelling and Analysis of Supply Sequence Impacts 83 7.1 Introduction 83 7.2 Scenario Modelling 83 7.3 Scenario Modelling Outputs and Analysis 86 7.4 Influence of Assumptions 89

7.5 Comparison of Results 90

7.6 SECV Debt Level 93

7.7 Discount Rates 95

7.8 Comments on Scenario Modelling 95

7.9 Conclusion 99

a. Loy Yang 8 Units 3 &.: 4 101

8.1 Introduction 101

8.2 Construction and Approval Lead Time 101

8.3 Earliest Required Service Date 102 8.4 Economics of Sequences with Loy Yang 8

Units 3 & 4 first 102

8.5 Capital and Operating Costs 103

8.6 Coal Supply for Loy Yang Power Stations 103

8.7 Latrobe Valley Interests 104

8.8 Other Socio-economic Effects 104

8.9 Overall Economic Uncertainty 105

8.10 Conclusions 105

8.ll Specific Recommendations 105

viii

Page 11: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER Page

9. Oaklands 107

9.1 Introduction 107

9.2 Costs and Benefits 108

9.3 Infrastructure 110

9.4 Potential for Arrangements with NSW 112

9.5 Specific Recommendations 113

10. Natural Gas 115

10.1 Gas Fired Options 115

10.1.1 Introduction 115

10.1.2 Potential Economic and Financial Benefits 116

1 0.1.3 Planning Flexibility Benefits 122

10.2 Natural Gas Resources 123

10.2.1 Introduction 123

10.2.2 Gippsland Basin Reserves 124

10.2.3 Impact of Additional Gas Fired Generating Capacity on Gippsland Basin Reserves 125

10.2.4 Allocating Natural Gas Resources 125

10.2.5 Deliverability of Natural Gas 128

10.2.6 Long Term Supply of and Demand for Natural Gas 129

10.3 Specific Recommendations .)(;

131

11. The Next Brown Coal Station to Follow Loy Yang B Units 3 &: 4 133

11.1 Options 133

11.1.1 Loy Yang "C" 133

11.1.2 Driffield 133

11.1.3 Morwell 134

11.1.4 Yallourn 134

11.1.5 The Briquette Factory 135

ix

Page 12: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER Page

11.2 Estimated Costs 136

11.3 Timing/Sequencing 136

11.4 Further Strategic Review and Planning and Environmental Approval Processes 138

11.5 Specific Recommendations 139

12. Interstate Electricity Transfers and Planning 141

12.1 Introduction 141 12.2 The Three-State South Eastern Electricity Grid 141

12.3 The Economics of Interstate Electricity Transfer -Zeidler Re-examined 145

12.4 Opportunities for Interstate Transfer of Electricity 149

12.4.1 Base/Intermediate Load Transfer 149

12.4.2 Peak Load Transfers 150

12.4.3 Interconnection with Tasmania 151

12.5 Mechanisms for Interstate Electricity Transfer and Planning 151

12.6 The Snowy Scheme 153 12.7 Specific Recommendations 157

13. Alternative Power Supply Sequences 159

13.1 Introduction 159

13.2 General Conclusions 159

13.3 Overall Evaluation of Sequences 161

13.4 Balancing Financial and Social Costs 162

13.5 Latrobe Valley Economy 164

13.6 Assumptions 166

13.7 Degree of Certainty in Relation to Major Supply Options 167

13.8 Conclusions Reached by the Committee 168

13.9 Specific Recommendations 171

X

Page 13: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER Page

14. Electricity Development Strategy Beyond the Mid-1990's 173

14.1 Introduction 17 3

14.2 An Electricity Development Strategy 173

14.3 Overall Objective 174

14.4 Strategic Principles 174

14.5 Key Elements 17 5

14.6 Relationship to Existing Strategies 176

14.7 Implementing the Electricity Development Strategy 178

14.8 Reviewing the Strategy and its Implementation 180

14.9 Principal Recommendations 181

* * *

xi

Page 14: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

LIST OF APPENDICES

APPENDIX NO.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

Key Reference Documents

Inquiry Programme

List of Witnesses

List of those who made Submissions to the Inquiry

Classification of Demand Side Measures and Summary of SECV Programme

SECV letter: System Value of Extending the Life of Hazelwood Power Station to 40 Years

Cost of Production Indices for Future Power Supply Options

Victorian Government Policy -The Use of Natural Gas for Power Generation

Natural Gas Resources

Description of Base Scenarios -Five Families of SECV Sequences

Basis for Comparison of Zeidler Inquiry and NREC Inquiry Generation Cost Estimates

Recommendations of the Commission of Inquiry into Electricity Generation Planning in NSW (McDoneU Inquiry) Concerning the Snowy Scheme

SECV letter: Brown/BlackCoal/Gas Scenario with Minimum Fluctuations in Latrobe Valley Construction Employment

Electricity Development Strategy and Implementation Review - Draft Format

Summary of Changes made in this Report from the Committee's Preliminary Report and Draft Recommendations of December 1987

Glossary of Terms

Energy and Power Units

List of Abbreviations

Extracts from the Proceedings

* * *

xii

Page

183

189

191

201

205

211

217

227 229

249

251

253

255

261

263

271

275

277

279

Page 15: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

FIGURE NO.

2.1

2.2

5.1

5.2

5.3

5.4

7.1

10.1

10.2

12.1

A9.1

A9.2

A9.3

A9.4

A9.5

LIST OF FIGURES

Total Electricity Generation Forecasts for the Victorian System 19&7-2002 (SECV)

Comparison of Demand Forecasts and Range of Supply Capability of Existing and Committed Plant (35 & 40 year life at Hazelwood Power Station)

Location of Power Supply Options in Victoria

Location of Power Supply Options in the Latrobe Valley

Location of Possible Sites for Power Stations based on Oaklands Coal

Cost of Power Delivered to Melbourne versus Capacity Factor for Representative Options

Simplified Diagram of Scenario Modelling Approach

Bass Strait Gas Delivered to Major Customers 1981/1982- 1986/1987

Long-run Marginal Costs for Gas Turbine/Brown Coal Sequences - SECV Results

Three-State Interconnected Electricity Supply System

Movements in Gas Reserve Estimates 1978-1987

Victorian Daily Gas Usage- 1981

GFCV Projection of Delivery Requirements

Australian Natural Gas Reserves - BHP

Natural Gas Pipelines in Australia - AMEC September 1986

* * *

xiii

Page

10

17

47

48

49

72

85

117

121

144

238

239

239

242

244

Page 16: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE NO.

7.1

9.1

10.1

10.2

10.3

12.1

13.1

A.5.1

A.5.2

A.5.3

A7.1

LIST OF TABLES

SECV Estimates of Conservation, Cogeneration and Off-peak Marketing included in the 1987 Forecast

SECV Planned or Expected Plant Installations and Retirements

Large Scale Supply Options - Cost Data

Large Scale Supply Options- Workforce Requirements

Reliability and Energy Efficiency of Different Types of Large Scale Supply Options

Comparison of Results for Selected Scenarios

Present Value of Potential Generation Cost Savings Due to Oak lands Option, 1986-2015

Present Value of Potential Generation Cost Savings for Gas Turbine Options, 1986-2015

Breakdown of Potential Generation Cost Savings for a 1000 MW Gas Turbine - Brown Coal Sequence, 1986-201.5

Gippsland Basin Gas Reserves, December 1987

Comparison of Zeidler Inquiry and Natural Resources and Environment Committee Inquiry Base Load Generation Cost Estimates

Ranking of Major Sequences on Evaluation Criteria (SECV Table 21.1)

Classification and Examples of Demand Side Measures

Expected Contribution of Current Demand Management Programmes - SECV December 1986

SECV Demand Side Measures under Investigation and Possible Future Programmes

Options and Direct Costs

xiv

Page

12

30

53

57

59

91

111

119

120

124

148

161

207

208

209

218

Page 17: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE NO.

A7.2

A7.3

A7.4

A7.5

A7.6

A9.1

A9.2

A9.3

A9.4

"Cost of Electricity Sent Out"- 4% Discount Rate

"Cost of Electricity Sent Out" - 8% Discount Rate

"Cost of Electricity Delivered" - 4% Discount Rate

"Cost of Electricity Delivered" - 8% Discount Rate

Offsets to Cost of Power Delivered from Oak1ands

Gipps1and Basin Natural Gas Reserves - Estimates at December 1987

Uncommitted Gipps1and Basin Natural Gas Reserves -Estimates at December 1987

Gippsland Basin Natural Gas Reserve Lifetimes based on Current Reserves and Usage Rates

North West Australian Gas Reserves- Identified Remaining Reserves at June 1987

* * *

XV

Page

221

222

223

224

225

231

232

233

247

Page 18: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TERMS OF REFERENCE

INQUIRY INTO ELECTRICITY SUPPLY AND DEMAND BEYOND THE MID-1990's

To inquire into, consider and report to the Parliament by 4 May 1988* on the most appropriate sequencing of future power supply options to foJJow Loy Yang B Units 1 & 2 in order to meet the forecast range of load growth for the decade beyond the mid-1990's, as part of the development of long-term strategies for balancing electricity supply and demand.

In particular, the Committee should:

J, Take into account:

(a) State Economic Strategy and Government Energy Policy, the SEC's statutory obligations and Corporate objectives, including social, employment, infrastructure, environmental and economic factors;

(b) current and proposed initiatives in demand planning and the potential impact of plant refurbishment programmes;

(c) consideration of the strategic role and economics of investment in conservation, cogeneration and load management and progress with development of renewable energy resources;

(d) the desirable mix of future fuels for generation in the Victorian electricity system (other than nuclear power, excluded under the Nuclear Activities (Prohibition) Act 1983), in the light of potential economic, business, and regional/State employment implications, and the location, nature and extent of potential fuel resources;

(e) the development of the three-State South East Australia interconnected power system and its potential for future extension/expansion; and

xvi

Page 19: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

(f) the extent to which the possible requirements for future steam supplies or other services to new industrial applications for coal, including the future requirements for briquetting, might impact on the sequencing of future Latrobe Valley power generation projects.

2. Include recommendations as to whether or not the SEC should pursue the feasibility of developing a black coal fired power station in northern Victoria, or the prospects for an arrangement with NSW and/or other partners for either investment in or purchase of power from a possible Oaklands, NSW power project.

3. Identify specific issues requiring detailed consideration during the subsequent environmental assessment/project approval processes for the future power generation projects recommended by the Committee.

* Amended by the Governor-in-Council 24 November 1987.

* * *

xvii

Page 20: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 21: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

SUMMARY OF FINDINGS

The Committee has concluded that a long-term electricity development

strategy should be implemented which has the objective of maximising the

benefits which can be obtained from the supply and utilisation of electricity by

minimising the economic, social and environmental costs.

This objective is consistent with the State Economic Strategy and SECV's

statutory obligations and corporate objectives.

It is anticipated that the bulk of the State's electricity supply will continue to

be based on the brown coal resources of the Latrobe VaJJey and the Committee

has concluded that Loy Yang B Units 3 & 4 should be the next base load units

committed for construction after Loy Yang B Units 1 & 2.

The development of black coal resources at Oaklands in NSW could provide

Victoria with an opportunity to gain access to an economic source of

intermediate load power supply and at the same time to benefit from the

strengthened interconnection between the two States. The Government should

pursue this opportunity with the Government of New South Wales. In certain·

circumstances, construction of the Oaklands plant could overlap with

construction of Loy Yang B Units .3 & 4.

An increased use of natural gas for power generation could have benefits for

Victoria. The Committee has inquired into the long-term availability of

natural gas to Victoria and the possibility that gas might need to be supplied to

Victoria from the North West Shelf some time after 2010. The Committee has

concluded that there is a case for inclusion of up to 500 MW of additional gas

fired capacity in the Victorian system.

xix

Page 22: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Committee commends the Unions, the Latrobe Regional Commission,

CRA Ltd., BHP and SECV for their submissions on the effects of a large range

of alternative future power supply sequences. This approach to long term

broadly based power supply planning is new in Victoria and has allowed the

Committee to propose a strategy for the development of the Victorian

electricity supply system.

Most of the submissions, lead to the conclusion that it is not in the best

interests of Victoria to define a sequence of power supply options for the

decade following the mid-1990's.

In principle, the evidence presented to the Inquiry shows that the least cost

Victorian electricity supply system should include a combination of

hydro-electric, brown coal, black coal and natural gas fired plant, and greater

energy interchange between Victoria and New South Wales. This in turn leads

to the conclusion that there will be an increasing need for co-ordination of the

development and use of all forms of energy both in Victoria and between

States.

The evidence indicates that the selection of the most appropriate future power

station sequence will be influenced by the future social and economic

environment as much as by the internal configuration of the sequence itself.

SECV has used sophisticated analytical techniques to forecast a range of

future electricity demands. Uncertainty still attaches to these forecasts.

Uncertain world economic conditions could result in an electrical load growth

which fluctuates and which may have a long term trend lying outside the

ranges projected by SECV.

This uncertainty about the economy and Victorian power requirements,

together with other uncertainties related to the performance and life of

existing plant, and the possibility of using a more diverse range of fuels

highlights the need to optimise capital and operating costs. The Committee

has concluded that it is in the best interests of Victoria to adopt a flexible

strategy rather than a definite sequence of future power supply options. Such

a strategy would also encourage competition between the available energy

resources and promote improved technology based on brown coal.

XX

Page 23: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The availability and expected life of existing generating plant is an important

factor in the need for and timing of new plant additions. Plant life extension

generally leads to greater economic benefits than new plant construction.

However, the economic life of a particular plant will only be established as a

result of regular reviews throughout its life. Predictions of plant lives and

performance therefore include an element of uncertainty.

On present estimates the installation of Loy Yang B Units 3 & 4 would cost

less than the installation of any of the other brown coal fired plant options in

the Latrobe Valley. The Committee believes that scope exists to further

reduce the capital and operating costs of this development. This should be

explored before the Government authorises commitment to contracts and

expenditure on the construction of Loy Yang B Units 3 & 4.

Further work needs to be undertaken by SECV before it is possible to

determine which should be the next Victorian brown coal power supply option

to follow Loy Yang B Units 3 & 4. The Committee has recommended that this

matter should be referred to it under new terms of reference.

A black coal fired power station based on the Oaklands coal deposit would be

significantly lower in capital cost than an equivalent brown coal fired station

and would be suitable for intermediate load duty on the Victorian system.

Estimates based on a range of probable coal prices indicate that the cost of

energy from such a station would be comparable to the cost of energy from

Loy Yang B Units 3 & 4 and significantly less than the cost of energy from

other brown coal fired options.

Joint development of the Oaklands project by NSW and Victoria would result

in a strengthening of the transmission link between the two States alJowing a

higher level of interchange and system reliability with overall economic

benefits to both States. There are also potential benefits for South Australia.

Development of the Oaklands project would provide the greatest economic

benefit to Victoria if it was timed to meet coincident needs in NSW and

Victoria. The economics do not favour sole Victorian participation in a two

unit development at Oaklands. Development of a two unit station at Telford,

xxi

Page 24: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

south of Yarrawonga is not considered to be economically or environmentally

desirable.

There is as yet no commitment by NSW to the development of Oaklands, it

remains one of a number of potential new power supply options which are

being evaluated by NSW. It is expected that the first draft Electricity

Development and Fuel Sourcing Plan for NSW will be available at the end of

June 1988.

It is essential that, should the Oaklands project proceed, an adequate

community infrastructure be provided in the region. Estimates of the cost of

providing this infrastructure show that this is unlikely to be comparable with

the potential benefits which could be derived from the project or with the

overall cost of the project itself.

In summary, there are potential benefits of joint participation with NSW in a

4 x 700 MW Oaklands power station project and the possibility of such an

arrangement should be pursued with the Government of New South Wales.

There are sufficient uncommitted Bass Strait gas reserves to allow the

installation of at least a further 500 MW of gas turbines. The additional gas

consumption, if this amount of new plant was installed, would shorten the

expected life of present known Bass Strait gas reserves by approximately one

and a half years in the period after 2010. At that time, unless further

significant reserves of gas are discovered in Bass Strait, it is probable that gas

wiH be supplied at competitive prices to the whole of south east Australia by a

pipeline from the North West Shelf.

There could be an economic argument for the inclusion of up to 1000 MW of

new gas turbines of a unit size in the order of 1 00 MW on the Victorian system

to supply peak and intermediate loads. The low capital cost of gas turbines,

together with their short construction lead time provides the potential for

financial savings if gas can be supplied at a suitable price. The cost of gas can

only be determined by negotiations with Esso-BHP for a firm contract to

supply defined quantities of gas, under certain conditions.

xxii

Page 25: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Committee has therefore concluded that Government policy should be

amended to allow for the further use of gas for power generation. The SECV

should attempt to negotiate a firm contract for the supply of sufficient gas to

fuel up to 500 MW of gas fired plant operating in a peak/intermediate load role

over a twenty year plant life.

During the Inquiry concern was expressed about the potential impacts of

various sequences of power supply options on the Latrobe Valley, particularly

with respect to employment levels and other socio-economic effects. The

Committee has concluded that, from an employment viewpoint, the Latrobe

Valley is one of the more fortunate areas of provincial Victoria in that three

of Victoria's largest and most stable industries are based in the region. These

are the power, oil and gas, and paper industries. However, because of the

generally high level of continuity of work in these industries, the regional

economy and the community as a whole has become unduly reliant on their

continuing growth. The investment required per employee in the power

industry is extremely high. It would benefit both the region and the State if

this reliance could be reduced through the introduction of other more diverse

industries. This is not something that will come about of its own accord. It is

most likely to be achieved as the result of initiatives developed either from

within the region, by Government or by individual industries.

Comments received as a result of the Committee publishing a Preliminary

Report and Draft Recommendations in December 1987 suggested that the

Committee had paid insufficient attention to the potential savings that could

be achieved through demand management and energy conservation. The

Committee has examined this aspect in more depth and has concluded that it

is necessary for SECV to develop improved analytical tools in order to present

demand and supply side measures on a common basis. The Committee has

recommended that demand side measures be further considered by it under

new terms of reference.

During the course of the Inquiry, the Committee made several requests for

further information on the briquette factory at Morwell. In March 1988,

limited information was made available; however, this information did not

cover all the issues associated with the future of this plant, and the

Committee has recommended that the briquette operation should also be

xxiii

Page 26: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

further considered by it under new terms of reference.

The overall thrust of this report is the same as that contained in the

Committee's Preliminary Report and Draft Recommendations published in

December 1987. Differences between the two reports are summarised in

Appendix 15.

xxiv

Page 27: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

RECOMMENDATIONS

PREAMBLE

The information provided in evidence to the Committee does not provide a

sufficient basis on which to nominate a specific power supply sequence to follow

Loy Yang B Units 1 & 2. The need to maintain flexibility to meet unpredicted

changes in electricity demand levels, to minimise the risk of commitment of

large State capital resources before it is necessary to do so and to have the

ability to incorporate improved technology and practices militates against

prescribing a single fixed sequence at this time.

Hence, the Committee considers that the future needs of Victoria will be best

served if the Government and SECV adopt a long term electricity development

strategy as described in the following recommendations.

Some aspects of the proposed electricity development strategy

endorse statutory requirements, policy and procedures already followed

or proposed by SECV. However, the recommendations are designed to ensure

that SECV becomes more accountable to the community.

AN ELECTRICITY DEVELOPMENT STRATEGY

Principal Recommendations

1. The Government and SECV should adopt an Electricity Development Strategy based on the Overall Objective, Strategic Principles and Key Elements described below, together with the Specific Recommendations which follow.

(S.14.9- P.181)

2. SECV should prepare and publish an annual Electricity Development Strategy and Implementation Review document for submission to the Parliament, in accordance with the format suggested in Appendix 14 of this report.

(S.14.9- P.181)

XXV

Page 28: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Overall Objective

3. The objective of the proposed Electricity Development Strategy should be:

"In the face of an uncertain future, to provide Victoria with the greatest opportunity to maximise the benefits that can be obtained from the supply and utilisation of electricity by minimising economic, social and environmental costs."

(S.14.3 - P.174)

Strategic Principles

4. The principles underlying the Electricity Development Strategy to meet this objective should be:

Conservation of the State's energy resources;

Effective and efficient use of the State's installed electricity supply system;

Regular evaluation of a full range of options for balancing electricity supply and demand over time based on assessment of the future economic, social, biophysical, political, technical, scientific and market environments in which Victoria's electricity supply system will evolve;

Consideration of the robustness and flexibility required to deal with a wide range of unpredicted changes without incurring unacceptable social or economic consequences;

Consideration of the level of diversity which should be provided in the supply system when selecting and locating new generation options and their associated fuels;

Introduction of new technology and techniques for supplying and more efficiently utilising electricity;

Incorporation of public accountability, participation and review where appropriate.

(S.14.4- P.174/5)

Key Elements

5. The strategy should include the following elements:

The development and implementation of economic conservation and demand side measures;

xxvi

Page 29: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The development of Research and Development programmes incorporating iMovative approaches to both electricity supply and demand. These should include the development of brown coal technology, energy conservation measures and renewable energy resources;

The extension of existing SECV programmes for improving the availability and life of existing plant:

The development of SECV's scenario approach to planning to ensure that the impacts of alternative measures for balancing supply and demand can be re-assessed as circumstances change;

An increased level of joint planning between the intercoMected States of NSW, SA and Victoria;

The establishment of a clear and open project approval process which encourages flexibility and rapid response to changed circumstances;

A reduction in the risks associated with the uncertain economic environment and the long lead time required for power supply projects, particularly coal fired plant. There is considerable scope for improvement in this area, and the following concepts outline some of the ways in which this could be achieved:

Where possible, plaMing and environmental approval being granted "in principle" for individual projects ahead of the time when they might be required. A shorter review should be held to consider remaining issues related to the timing of the project, just prior to the Government granting authority to proceed. However, projects with "in principle'' approval which do not proceed for several years should be examined at ten yearly intervals and the approval revoked if the basis for the original approval becomes invalid;

The use of short lead time options such as small gas fired units to buffer the longer lead time coal fired plant against unforeseen changes in electricity demand forecasts;

The avoidance of commitments to UMecessarily large packages of new plant consistent with optimising capital and operating costs;

The use of flexible purchase and installation contracts where this is economic and appropriate.

(8.14.5 - P.175/6)

xxvii

Page 30: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

SPECIFIC RECOMMENDATIONS

The following recommendations should form part of the electricity development

strategy:

Pricing, Demand Side Measures and Energy Conservation

6. SECV should continue to evaluate the relationship between the costs of proposed sequences of supply options and its pricing policies to establish the consequent implications for future levels of electricity demand.

(S.3. 7 - P .25)

7. SECV should give consideration to expanding its range of electricity supply tariffs to include more generally available tariffs for controllable or interruptable supplies.

(S.3. 7 - P .25)

8. SECV should continue its present programmes which are aimed at encouraging conservation and demand side measures. They should investigate the potential to expand these programmes and to develop new programmes. The effectiveness of these programmes and their potential for expansion should be reported in SECV's annual report.

(S.3. 7 - P.25)

9. The Government should amend the Victoria Building Regulations to require thermal insulation in new buildings and should continue to promote the design and construction of solar and energy efficient buildings.

(S.3.7- P.25)

10. Further terms of reference should be given to this Committee to allow for a more detailed examination of demand side and energy conservation measures and their potential to contribute to economically, socially and environmentally beneficial strategies for balancing electricity supply and demand. This examination should be based on:

The development of methodologies for quantifying the effects of and evaluating demand side and energy conservation programmes on a basis consistent with evaluation of supply side options;

The integration of demand side and supply side planning using a least cost approach to maximise overall benefits to Victoria;

The development, selection and implementation of practical demand side and energy conservation programmes for Victoria;

xxviii

Page 31: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The identification of research and information needs for effective demand side and energy conservation programmes.

(S.3. 7 - P.26)

11. The Commonwealth and Victorian Governments should support the gathering and analysis of information which would improve the current level of understanding of the Greenhouse Effect and its implications for Victoria, Australia and the world at large. In particular, SECV should assist by providing annual estimates of the total release of Carbon Dioxide and other contributing emissions from its operations. This information should be published each year in Victoria's "State of the Environment Report" together with estimates of contributions from other sources.

(8.3. 7 - p .26)

The Performance of Existing Generating Plant

12. Priority should be given to improving and maintaining the availability of existing plant and extending its life where this is economically viable.

(S.4.5 - P.38)

13. SECV should publish a yearly review of the performance and condition of its generating plant, including:

Details of available and actual capacity factors achieved, major planned and unplanned unit outages, repair times and other statistics;

Targets and projections for the performance of existing plant over future years, and explanations of any significant deviation of actual performance from earlier targets.

(8.4.5 - P.38)

14. SECV should carry out and publish regular assessments of the scope for improving the projected performance or expected lifetime of existing plant through refurbishment or preventive maintenance works, changed management or work practices, or technological enhancements.

(S.4.5 - P.38)

15. Prior to commitments to construct new generating plant, the interaction between existing plant performance and lifetime, and the introduction of new plant should be reviewed. This review should ensure that the fuel resources allocated to the existing plant allow the maximum scope for performance improvement and economic life extension. In particular, the planned retirement date of the Hazelwood Power Station should be subject to a detailed review prior to any commitments to construct new power stations for service after 1999.

(S.4.5 - P.39)

xxix

Page 32: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Research and Development Related to the Use of Brown Coal

16. A more active Research and Development programme should be initiated by SECV into improved techniques for the use of brown coal in power generation. This should include:

Development of efficient methods for the production and utilisation of pulverised dried brown coal;

Investigation of the potential for development of a "de watered" coal;

Development of improved milling, burner and precipitator designs;

Optimisation of boiler designs;

Optimisation of coal winning techniques, utilisation strategies, and equipment;

An on-going review of developments in the Circulating Fluidised Bed Combustion and Integrated Gasification Combined Cycle technologies;

A detailed review of the possibility that gas turbines could be developed to operate satisfactorily on brown coal.

(S.4.5 - P.39/40)

The Desirable Mix of Fuels

17. The Victorian electricity supply system should be developed to include hydro-electric, gas, black coal and brown coal fired plant, together with a strengthening as required of the interconnections between Victoria, NSW and SA.

(S.13.9- P.171)

18. The relative proportions of the different types of plant should be determined by regular reviews of resource availability and the economic social and environmental factors involved.

(S.13.9 - P.171)

19. SECV should carry out a further review of the possibility that pumped storage options could be developed in association with existing storages, in particular the Thomson and Dartmouth Reservoirs. If feasible sites are identified, the capital costs of their development should be estimated by expert feasibility studies and they should be subjected to economic and environmental evaluation. This evaluation should be carried out in a manner similar to the evaluations of other major supply options presented to this inquiry so that the value attributed to pumped storage in terms of system costs and reliability is demonstrably valid given the current and expected future plant mix and load profile.

(S.5.12- P.73)

XXX

Page 33: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Loy Yang B Units 3 &: 4

20. On the basis of the cost comparisons presently available to the Committee and the social and employment contributions to the Latrobe region and Victoria, Loy Yang B Units 3 &. 4 should be the next base load units committed for construction after Loy Yang B Units 1 &. 2.

(S.13.9 - P.172)

21. No final commitment to contracts and expenditure to construct Loy Yang B Units 3 &. 4 should be given until the latest time consistent with maintaining a reliable electricity supply system. Immediately prior to authorising expenditure on the major plant items, the Government should ensure that SECV reviews the capital and operating costs of both Loy Yang B Units 3 &. 4 and other viable power supply and demand side options. This should include a re-evaluation of the socio-economic effects of these alternatives in the light of updated load forecasts and other relevant information.

(S.B.ll - P.l 05)

Oaldands

22. Negotiations should be initiated and pursued by the Victorian Government with the Government of New South Wales to establish the prospects for an arrangement with NSW and/or other partners for either investment in or the purchase of power from a black coal fired power station at Oaklands in NSW.

(S.9.5 - P.113)

23. The introduction of the Oaklands plant should be primarily determined by a coincident need for additional sources of power supply in both Victoria and NSW and an agreement to proceed on a co-ordinated basis. The Oaklands plant would probably be constructed after Loy Yang B Units 3 &. 4, however, the possibility of the projects overlapping in certain circumstances, such as a rapid growth in the demand for electricity, should not be ruled out.

(S.9.5 - P.113)

24. Prior to the Oaklands project proceeding, a detailed evaluation of the electricity transmission systems interconnecting the three States and the Snowy Scheme should be carried out with a view to optimising the benefits which might flow from the reinforcement of this system as part of the Oaklands project. This should include a review of the appropriate voltage levels for the transmission system and the possible benefits that might arise from strengthening the transmission links in advance of the Oaklands development.

(S.9.5 - P.114)

xxxi

Page 34: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

25. The following issues should be considered before Victoria makes a final commitment to an Oaklands project:

The commercial relationships between the parties to the Oaklands project;

An independent detailed evaluation of the economics and long term viability of the Oaklands project including the proposals for the supply and disposal of water, and the proposed coal supply arrangements;

The requirements of the appropriate environmental and resource planning authorities including the Murray-Darling Basin Commission;

The provzswn and funding of community and project infrastructure both in NSW and Northern Victoria;

The arrangements for sharing the output both in respect of Victoria's needs and the passibility of minimising undesirable employment effects in the Latrobe Valley;

Transmission line routes from Oaklands to Melbourne. (S.9.5 - P.114)

Joint Interstate Planning

26. The Government should seek to achieve an increased level of co-ordination and joint electricity planning amongst the interconnected States of NSW, SA and Victoria. Consideration should be given to the sharing of new power projects, in addition to the opportunity offered by Oaklands, including gas fired peaking plant and coal fired intermediate and base load plant. The possibility of delaying capital expenditure on new plant by short term increases in the level of interstate energy transfers in the period immediately preceding the installation and commissioning of the new plant should always be considered. From time to time the possibility of a link with Tasmania should be reviewed.

(S.12.7- P.157)

27. The Government should initiate the formation of a South Eastern States Energy Planning Committee consisting of representatives of the Governments of Victoria, New South Wales, South Australia and Tasmania. This Committee should be responsible for the co-ordination and joint planning of energy supplies in South Eastern Australia, including an on-going review of:

Expanded electricity transfer between the States;

The development of a South Eastern States gas grid, including in the longer term a gas supply from North West Australia;

The development of management structures to formulate joint forward planning and efficient management of joint interconnected systems for the energy industry.

(S.12.7- P.157)

:r::r::r:ii

Page 35: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Snowy Scheme

28. Through its representation on the Snowy Mountains Council, Victoria should continue to ensure that the considerable benefits deriving from the Snowy Mountains Hydro-electric Scheme are maximised. A review of the potential for further pumped storage capacity should be carried out. Operational strategies, options for plant refurbishment and upgrading should be regularly reviewed and any changes assessed in relation to their overall impact on the Victorian and NSW electricity and water systems.

(S.12.7- P.158)

Natural Gas

29. The Government should review its present energy policy with respect to the use of natural gas for power generation, taking into account the Natural Resources and Environment Committee's conclusion that considerable benefits would result from the inclusion of up to 500 MW of additional gas fired plant in the Victorian system. This additional plant should be used for peak/intermediate load duties only.

(S.10.3- P.131)

30. If Government policy is changed to accommodate the conclusions reached by the Committee, then SECV should be authorised to negotiate a suitable gas supply contract. The Government should ensure that SECV and GFCV adopt a co-ordinated approach to negotiations with the producers so that adequate consideration of deliverability issues occurs, consistent with maintaining a minimum overall cost to Victoria.

(S.10.3 - P.132)

31. SECV should continue to develop proposals for both gas turbine and combined cycle plants, including the option of staged development of a combined cycle station.

(S.10.3 - P.132)

32. In determining the detailed programme for installing new gas fired plant, SECV should take into account the potential for improving the robustness and flexibility of the overall supply development programme.

. (S.10.3 - P.132)

33. The proposed study of Bass Strait natural gas reserves by the Department of Industry, Technology and Resources should be expedited and its findings should be made publicly available as soon as it is completed.

(S.10.3 - P.132)

34. If a gas supply contract is negotiated then planning and environmental approval procedures for an appropriate site or sites for locating gas fired generation facilities should be commenced as soon as the contract negotiations are completed. These procedures should be incorporated in

xxxiii

Page 36: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

an Inquiry conducted by the Natural Resources and Environment Committee under appropriate Terms of Reference proclaimed by the Governor-in-Council and should be co-ordinated with requirements under the Environment Effects Act 1978.

(8.10.3 - P.132)

Brown Coal Options after Loy Yang B Units 3 &: 4

35. Further terms of reference should be given to this Committee so that further consideration can be given as to which should be the next brown coal fired power station constructed after L.oy Yang B Units 3 & 4. The terms of reference should also require the Committee to address:

(a) the most appropriate form for the subsequent environmental assessment/project approval processes;

(b) the specific issues requiring detailed consideration during the subsequent environmental assessment/project approval processes.

(8.11.5- P.139)

High Voltage Transmission Lines

36. Prior to any new high voltage transmission lines being constructed, a further public evaluation of the long-term development of the Victorian high voltage transmission system should occur. This should be integrated with a review of the alternative demand and supply side options and sequences available at that time, together with consideration of environmental, health and safety issues.

(8.5.12- P.73)

The Briquette Factory

37. Further terms of reference should be given to this Committee to allow further consideration of the future of the Morwell Power Station and Briquette Factory. These terms of reference should require the Committee to address:

(a) The most appropriate auxiliary fuels for existing and future brown coal fired boilers;

(b) The future market for briquettes other than for use by SECV;

(c) The effects of any proposed changes on employment levels. (8.11.5 - P.139)

Small Scale Supply Options

38. SECV should consider stand alone power supply systems as an alternative to extending the electricity distribution system into remote areas.

(8.6.5 - P.81)

xxxiv

Page 37: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

39. The Government and SECV should review the effects of the cogeneration and renewable energy "incentives" package after a suitable period has elapsed and, if appropriate, further restructure SECV's standby and buy-back tariffs.

(S.6.5 - P.81)

40. SECV should investigate the possibility of making firm arrangements for the operation of private emergency and standby generators during periods of potential energy shortage on the interconnected generating system. These investigations should consider the possible cost advantages which might arise from such arrangements through reduction in SECV reserve plant requirements.

(8.6.5 - P.Bl)

41. SECV should significantly expand its involvement in research and demonstration projects related to renewable energy based electricity generating technologies.

(8.6.5 - P.81)

Latrobe Valley Employment Impacts

42. Local, Regional, State and Commonwealth Authorities should attempt to introduce a more diverse range of industry to the Latrobe Valley.

(8.13.9 - P.172)

43. When considering the detailed timing of future power supply options, consideration should be given to the possibility of minimising the employment impacts in the Latrobe Valley without incurring significant economic penalties.

(S.13.9 - P.172)

*

XXXV

Page 38: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 39: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Natural Resources and Environment Committee appointed pursuant to the

provisions of the Parliamentary Committees Act 1968 (No. 7727) has the honour to

report as follows:

INQUIRY INTO ELECTRICITY SUPPLY AND DEMAND

BEYOND THE MID-1990'S

CHAPTER ONE

INTRODUCTION

1.1 Terms of Reference

On 7 October 1986, the Committee was directed by His Excellency the

Governor-in-Council:

To inquire into, consider and report to the Parliament by 1 October 1987 on the most appropriate sequencing of future power supply options to follow Loy Yang B Units 1 & 2 in order to meet the forecast range of load growth for the decade beyond the mid-1990's, as part of the development of long-term strategies for balancing electricity supply and demand.

In particular, the Committee should:

1. Take into account:

(a) State Economic Strategy and Government Energy Policy, the SEC's statutory obligations and Corporate objectives, including social, employment, infrastructure, environmental and economic factors;

(b) current and proposed initiatives in demand planning and the potential impact of plant refurbiShment programmes;

(c) consideration of the strategic role and economics of investment in conservation, cogeneration and load management and progress with development of renewable energy resources;

1

Page 40: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

(d) the desirable mix of future fuels for generation in the Victorian electricity system (other than nuclear power, excluded under the Nuclear Activities (Prohibition) Act 1983), in the light of potential economic, business, and regional/State employment implications, and the location, nature and extent of potential fuel resources;

(e) the development of the three-State South East Australia interconnected power system and its potential for future extension/expansion; and

(f) the extent to which the possible requirements for future steam supplies or other services to new industrial applications for coal, including the future requirements for briquetttng, might impact on the sequencing of future Latrobe Valley power generation projects.

2. Include recommendations as to whether or not the SEC should pursue the feasibility of developing a black coal fired power station in northern Victoria, or the prospects for an arrangement with NSW and/or other partners for either investment in or purchase of power from a possible Oaklands, NSW power project.

3. Identify specific issues requiring detailed consideration during the . subsequent environmental assessment/project approval processes for the future power generation projects recommended by the Committee.

1.2 Request for Additional Information

In December 1986, the Committee requested the State Electricity

Commission of Victoria (SECV) to include in its evidence to the Inquiry

consideration of the possibility of an increased use of natural gas for power

generation. This request resulted in SECV having to considerably revise and

add to the information it was proposing to present as evidence to the

Committee. The time taken to prepare the revised evidence, together with

the extensive public consultation programme proposed by the Committee

resulted in a revision of the originally specified reporting date of

7 October 1987.

1.3 Amended Reporting Date

On 24 November 1987, the Governor-in-Council amended the reporting date

for the Inquiry to 4 May 1988.

2

Page 41: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

1.4 Public Consultation Prior to this Inquiry

Prior to a decision being made on the need for this Inquiry, SECV conducted a

public consultation process in order to review the most appropriate planning

and approval processes for the choice and sequencing of new power

generation options and their subsequent statutory approval.

During this public consultation process, three specific concepts were raised,

these were:

The need for any planning and approval process to create an

environment favourable to an informed public debate on the

significant issues. It was suggested that the adversarial nature of

earlier Parliamentary Inquiries, such as the Driffield Inquiry,

inhibited contributions from the public.

The need to provide funds to assist community groups and

individuals with the cost of preparing submissions to the approval

process.

The need to ensure that those involved in assessing the

submissions to the approval process had access to experts who

could assist in reviewing complex technical matters, where this

proved necessary.

This Inquiry was established on the understanding that the above concepts

would be incorporated in the Inquiry process in as far as might be practicable.

1.5 The Inquiry Programme and Public Consultation

The Inquiry has moved through the following broad stages:

October 1986

December 1986

Terms of Reference promulgated, Public Hearings- initial public briefing by SECY.

Public Hearings - SECV presented evidence on the need for new sources of power supply in the period 1995-2005.

3

Page 42: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

February 19&7 The Committee visited NSW, SA and the Snowy Mountains Hydro-electric Scheme.

March 19&7 The Committee visited Latrobe Valley, inspected existing power stations, reviewed plant improvement and plant life extension programmes.

March/ April 19&7 - Public Hearings - evidence presented on available energy resources and power supply options.

May 19&7 The Committee visited Latrobe Valley and Yarrawonga and inspected sites for possible future power supply options. The Committee also visited Richmond Control Centre and Newport Power Station.

July 19&7 Public Hearings - evidence presented on the effects of alternative sequences of the available power supply options.

August 19&7 Committee visited SECV's Latrobe Valley workshops. Informal public seminars held to allow more detailed discussion of the July evidence and its implications.

October 19&7 Public Hearings - formal evidence taken as to the most appropriate sequence of future power supply options.

December 19&7 The Committee issued its Preliminary Report and Draft Recommendations for public comment.

February 19&& Public Hearings - evidence taken in respect of comments on the Committee's Preliminary Report and Draft Recommendations.

April 19&& The Committee makes its report to the Parliament.

The public hearings in October and December 19&6 and July 19&7 were held in

Melbourne. The public hearings in March/ April 19&7, October 19&7 and

February 19&& and the seminars in August 19&7 were held in both MorweJl and

Yarrawonga.

Members of the public attending the public hearings have been provided with

the opportunity to raise questions through the chair to those giving evidence.

4

Page 43: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

A mailing list was established at the start of the Inquiry. This rapidly grew

to some 600 addresses. AH those on the mailing list received five

information booklets prepared by the Inquiry staff summarising evidence

given to the Committee, the Committee's Preliminary Report and Draft

Recommendations and four papers prepared by Consultants for the

Committee, and the Committee's report to the Parliament.

Some 200 of those on the mailing list requested and received copies of all

written evidence submitted to the Committee. A further 20 received copies

of the transcript of evidence given at the public hearings.

In total, over 1200 copies of the Committee's Preliminary Report and Draft

Recommendations and the Committee's Report to the Parliament have been

distributed.

All public hearings have been advertised in the local, regional and State

press. Press releases have been prepared and sent to all relevant newspapers,

radio and television stations on each occasion. Very good media coverage has

occurred in the Latrobe Valley and reasonable coverage occurred in the

Yarrawonga area. Very little comment, if any, has occurred in the Statewide

media.

The Department of Industry, Technology and Resources, on behalf of the'

Government, advertised and made available funds to assist individuals and

groups wishing to make submissions to the Inquiry. Approximately $15,000

was granted in total to the one individual and three organisations who took

advantage of this offer.

The Latrobe Valley Regional Commission organised the interested parties in

the Latrobe Valley to make a series of co-ordinated responses to the Inquiry.

In the Yarrawonga area, the Shires of Yarrawonga (Victoria), Corowa (N.S.W.)

and Urana (N.S. W .) combined to make a similar co-ordinated response.

109 written submissions were made to the Inquiry by 79 individuals and

organisations. 128 people representing either themselves or their

organisations gave evidence to the Committee at the public hearings.

5

Page 44: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Full details of the Inquiry Programme and of those who made submissions and

gave evidence are contained in Appendices 2, 3 and 4.

1.6 Use of Consultants

The Committee received assistance from the following consultants:

G.J. McDonell

P.M. Garlick and Associates Pty. Ltd.

B.Newell

Professor G. McColl

A.S. Atkins, D.G. Evans A. Wain

P.J. Brain, B.S. Gray, J.K. Stanley

1.7 Format of the Report

Commissioner, Inquiry into Electricity Generation Planning in NSW.

Consultant in the energy field.

Consultant on brown coal.

School of Economics, University of NSW.

School of Environmental Planning, University of Melbourne.

National Institute of Economic and Industry Research

The report first sets out the basic evidence presented to the Inquiry dealing

with forecasts of future demand, the capability of existing generating plant,

predicted plant retirements and existing commitments to new plant. This

evidence indicates that it is probable that up to 4000 MW of additional power

supply capacity may be required during the decade after 1995.

Before examining the power supply options available, possible demand side

measures are reviewed, the performance of existing generating plant is

examined and the possibility of introducing new technology is discussed. This

occurs in Chapters 3 and 4.

The major potentially viable supply options available during the period

1995-2005 are identified in Chapter 5 and include completion of Loy Yang B

Units 3 & 4, the continued development of Victoria's brown coal reserves, a

6

Page 45: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

possible development based on black coal located at Oaklands in NSW and the

use of additional quantities of natural gas.

Chapter 6 discusses the role for small scale supply options in the Victorian

electricity supply system.

Chapter 7 describes the role of scenario modelling in the Inquiry and

summarises the results produced using this technique.

Each of the major power supply options is then reviewed in some detail in

Chapters 8, 9, 10 and 11. As part of this review, specific issues have been

identified which would require detailed consideration during any subsequent

project approval processes.

Chapter 12 examines the potential for an increased level of interstate

transfer of electricity and the need for an on-going review of the operation

of the Snowy Mountains Hydro-electric Scheme.

The review of the possible power supply options and increased interstate

trade in electricity leads, in Chapters 13 and 14, to consideration of the most

appropriate sequence of power supply options to follow Loy Yang B

Units 1 & 2 and in turn to a proposed electricity development strategy.

1.8 Differences from the Preliminary Report and Draft Recommendations

This report is based on the Preliminary Report and Draft Recommendations

published by the Committee for public comment in December 1987.

Comments received both as written submissions and at the public hearings in

February 1988 have been taken into account, and further background

information has been added. Appendix 15 summarises the differences

between this report and the Preliminary Report published in December 1987.

Copies of the comments received and transcript of the hearings can be

obtained from the Committee's offices.

7

Page 46: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 47: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER TWO

BALANCING ELECTRICITY SUPPLY AND DEMAND

2.1 Introduction

Economic operation of an electricity system requires that the system supply

capability remains in balance with the demands of electricity consumers.

Too much electricity generation capacity needlessly increases the cost of

electricity. Too little results in electricity rationing and blackouts with

resultant costs to the community.

The Committee has examined proposals for balancing electricity supply and

demand beyond the mid-1990's. This has involved projections of the future

which, by their very nature involve a degree of uncertainty.

Evidence from SECV has included forecasts of the future demand for

electricity, projections of the performance of the existing supply system and

detailed information on the options available to increase the capacity of the

system.

2.2 Demand Forecast

Each year, SECV updates its long-term forecasts of electricity generation

and sales. High, median and low growth projections give a range of

electricity demand which reflect SECV's estimates of the range of

uncertainties of future economic activity. SECV's June 1987 forecasts are

shown in Figure 2.1.

SECV forecasts use econometric techniques which relate electricity

consumption to economic factors, population and price levels. End use

analysis is also used to assess particular consumption sectors.

9

Page 48: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

et: ([

60000

ssooo

soooo

g:! 45000

c.. QJ a.

:I: 40000 3 (!)

asooo

aoooo

FIGURE 2.1

, '/-""

I

I

, ,

, , ,

HIGH

, , , , , , , MEDIAN , , , , , , LOW

/ /

/

Annual Growth Rate 1987-2002

I HIGH - 4. 9"1. MEDIAN ~ a. 5"1. LOW - 2. 9?.

1995 1990 1995 YEAR

2000 2005

TOTAL ELECTRICITY GENERATION FORECASTS FOR THE VICTORIAN SYSTEM 1987- 2002 (SECV)

10

Page 49: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Despite the use of sophisticated analytical methods, a high degree of

uncertainty must still be attached to any longer term forecast. Some of this

uncertainty is reflected in the range of the high, median and low forecasts

presented by SECV. However, these forecasts are based on fairly

conservative sets of alternative assumptions about the future which make no

allowance for the increasingly unstable world economic environment or for

significant changes in the longer term relationship between economic activity

and energy consumption. It is quite possible that future "catastrophic" events

such as the 1987 stock market crash or the 1973 oil price shock could lead to

quite different short or long term outcomes from those predicted by SECV.

It is worth recognising that, around the world, most forecasts of electricity

demand growth over the last decade have proven too high and have

consistently be:en revised downwards.

The demand for electricity can be modified deliberately by specific demand

side measures. Examples of these are the current Government policies

designed to promote cogeneration and conservation which should reduce the

future demand to be met by SECV. These measures are complementary to a

policy which aims to attract energy intensive industries to Victoria.

SECV has allowed for the effects of demand management by explicitly

adjusting the load forecasts in accordance with targets established for each

of the categories of demand management. The 1987 targets are shown in

Table 2.1 and SECV has indicated that these will be regularly reviewed as

further information becomes available.

SECV targets for demand management are not sufficiently substantive at this

stage. More work needs to be done to quantify the most appropriate targets

in order to maximise potential benefits and to integrate demand side

programmes with supply side developments. This is discussed further in

Chapter 3.

While it is recognised that demand management has the potential to improve

the efficiency of electricity utilisation, the Committee also acknowledges

that it is SECV's responsibility to maintain an adequate electricity supply

capability.

11

Page 50: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

..... N

TABLE 2.1

Year

1987 1988 1989 1990 1991 1992 1993 1994 199.5 1996 1997 1998 1999 2000 2001 2002

(1) NB.

SECV ESTIMATES OF CONSERVATION, COGENERATION AND

OFF-PEAK MARKETING INCLUDED IN THE 1987 FORECAST

MEDIAN SCENARIO

Impact on Retail Electricity Sales (GWh) Domestic Commercial Industrial Total Conservation Conservation Cogeneration Cogeneration Conservation Cogeneration and Cogeneration

- - - - - -2 1 1 29 66 99

47 42 7 .50 112 2.58 91 8.5 11 74 168 429

134 128 17 102 234 61.5 178 171 22 127 281 779 221 217 28 1.54 3.50 970 266 264 34 180 412 11.56 312 314 40 207 47.5 1348 360 366 47 237 .541 1.5.51 406 419 .54 26.5 609 1753 4.53 476 60 296 680 196.5 .500 .53.5 68 329 757 2189 .549 .597 76 364 838 2424 600 663 84 402 922 2671 6.53 732 93 440 1011 2927

----

Conservation and cogeneration reduce the forecast values, whereas off-peak marketing will increase sales.

DomesticW Off-Peak Marketing

28 .51 96

161 244 3.50 466 600 744 898 963

1028 1093 11.57 1223 1287

Page 51: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

2.3 Existing Generating Capacity

Victorian generating capability at 30 June 1988 will comprise 8003 MW of

plant made up of:

2750 MW of relatively new brown coal fired thermal plant of good

availability operating on base load duty. (Loy Yang A Units 1-4-

and YalJourn W Stage 2);

2710 MW of older brown coal fired thermal plant also on base load

duty but with lower availabilities and undergoing progressive

refurbishment (Yallourn W Stage 1, Hazelwood, Morwell and

Yallourn E);

500 MW of natural gas fired thermal plant on intermediate load

duty (Newport D).

465 MW of natural g.:~.s fired combustion turbines on peaking and

standby duty (Jeeralar:g);

1578 MW of hydro plant on intermediate and peaking duty

(includes 1084 MW of Snowy Mountains Hydro-electric Scheme

output).

2.4 Planned Availability and Retirement of Generating Capacity

It is currently estimated that Yallourn E (24-0 MW) will need to be retired in

1993 and that individual generating units at Hazelwood (8 x 200 MW) will be

progressively retired between 1999 and 2005.

The availability of a generating unit is a measure of the total possible annual

output from the unit allowing for maintenance shutdowns and partial

reductions in output caused by equipment failures. Until recently, Victorian

brown coal units have had relatively low availabilities and this has required

the establishment and maintenance of increased capacity margins.

13

Page 52: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Prediction of the future life and availability of existing plant is critical to

the assessment of the time that new plant might need to come into service.

SECV is currently proceeding with Production Improvement Programmes

(PIP) aimed at improving the availability of all power stations and Plant Life

Extension (PLE) programmes at Hazelwood and Yallourn W Stage 1 Power

Stations. The Hazelwood PLE programmes is intended to give these units a

life of 35 years. SECV has also submitted evidence that further life

extension at Hazelwood to 40 years would provide considerable savings (see

Appendix 6). Plant availability and lives have been dealt with in more detail

in Chapter 4.

2 • .5 Additional Supply Capacity Prior to the Mid-1990's

The Terms of Reference of this Inquiry imply that an additional two 500 MW

units (Loy Yang B Units 1 &: 2) will be installed prior to the mid-1990's on

the Loy Yang site. At the time of writing, the final date for completion of

these units had not been announced.

SECV is also in the process of investigating the possibility of a supply from

the Electricity Commission of New South Wales (ECNSW) on a block contract

basis over a period of up to two years during the early 1990's. This possibility

arises because ECNSW may have excess capacity available in its system

following completion of the Mt. Piper Power Station. Such a contract with

ECNSW may enable some capital expenditure by SECV to be delayed. SECV

also indicated that some additional delay may be possible if limited quantities

of energy are "banked" during the late 1980's when generating capacity is

expected to exceed the demand for electricity. This can be achieved in two

ways. The first is by allowing the water levels in the Snowy Mountains

Hydro-electric system to rise by reducing the call on the water for

generation. The second is to reduce power station natural gas consumption

and defer contractual minimum gas take requirements to later years.

14

Page 53: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

2.6 Plant Mix

It is normal for electricity systems to feature a mix of high capital cost, low

fuel cost base load plant; lower capital cost, higher fuel cost intermediate

and peaking plant; and high capital cost, zero fuel cost hydro-electric plant

with a range of duties dependent on water availability. Least cost electricity

supply requires a balanced mix of available plant types.

This principle has been followed to good effect in the development of the

Victorian electricity system. The high capital cost brown coal fired plants in

the Latrobe Valley provide base load energy. The lower capital cost natural

gas fired plants at Newport D and Jeeralang provide intermediate and

peaking energy. The hydro plants in Victoria and the Snowy Scheme also

provide peaking energy but the total energy available from this source varies

from year to year with rainfall and irrigation demands. Natural gas provides

a flexible energy source which balances the base load brown coal energy and

the peaking energy from the hydro-electric schemes.

The Victorian electricity system is connected with the NSW electricity

system through the Snowy Scheme and is also to connect with the South

Australian system in early 1990. Interconnection improves system reliabiJity

because interstate support is usually available if one State's electricity supply

position becomes short for any reason. "Opportunity" transfers also give

overall fuel cost savings which are shared between the States. Interstate

trade in electricity is discussed in more detail in Chapter 12.

2.7 Balancing Supply and Demand

The need for new plant additions to the generating system depends on load

growth, the capacity and availability of the existing plant, plant retirements,

the level of interstate support available and the desired level of system

reliability. SECV evidence has stated that the desirable level of reliability

should be achieved with an Energy Reserve Margin of 5%. This is equivalent

to 25-30% of spare plant capacity above the system's maximum load.

15

Page 54: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Figure 2.2 is based on the various predictions by SECV of future loads and

plant capad ties.

The three broken lines represent the 1987 high, medium and low electricity

demand forecasts.

The heavy black lines represent alternative SECV views as to the most likely

capability of the existing and committed plant. This capability rises in the

period 1988-1993 because of the commissioning and working up of

Loy Yang A Power Station and the refurbishment of Hazelwood and

Yallourn W Power Stations. This is offset by the retirement of Yallourn E

Power Station in the period just prior to 1993. Flexible arrangments for the

commissioning of Loy Yang B Units 1 & 2 result in a range of possible plant

capabilities in the period 1992-1999. After 1999, the plant capabilities tail

off as Hazelwood units are progressively retired. This process could be

delayed by at least five years and is shown by the 35 year and 40 year life

alternatives.

The shaded area indicates the range of possible deviation from the most

likely plant capability if plant availability can be up-graded beyond or,

alternatively, falls below targetted levels.

Figure 2.2 is indicative of the large range of uncertainty involved in

predicting what supply and demand side measures will be required to balance

supply and demand in the decade beyond the mid-1990's.

It can be concluded from this diagram that it is probable that some additional

sources of supply will be required in the period 1995-2005.

16

Page 55: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

> 0 a: w z w ...1

50000

45000

40000

~ 35000 z z c(

30000

25000

POSSIBLE RANGE OF CAPABILITY PROVIDED BY FLEXIBLE INSTALLATlON PROGRAM FOR LOY YANG B UNITS~ & 2

I I

I I

I

I I

1HIGH

I

/

/MEDIAN

/

POSSIBLE RANGE OF CAPABILITY DEPENDENT ON PLANT PERFORMANCE AND HAZELWOOD PLANT LIFE

1985 1990 1995 2000

YEAR ENDING 30th JUNE

1987 DEMAND FORECASTS

40 YR UFE. HAZEL WOOD

2005

FIGURE 2.2 COMPARISON OF DEMAND FORECASTS AND RANGE OF SUPPLY CAP ASD..ITY OF EXISTING AND COMMITTED PLANT (J' &: lfO YEAR LIFE AT HAZELWOODPOWERSTATION)

17

Page 56: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 57: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER THREE

PRICING, DEMAND SIDE MEASURES AND

ENERGY CONSERVATION

3.1 Introduction

Pricing, demand side measures and energy conservation should not be

overlooked in the formulation of a long-term strategy for balancing supply

and demand. Such measures have received comparatively little attention in

the evidence presented to this Inquiry. The SECV approach to demand

management is outlined in the 1986 report, "SEC Outlook for Demand

Management to the Mid-1990's". This document establishes targets for a

number of demand management and energy conservation measures but fails

to establish clear economic criteria by which these can be compared and

integrated with supply side strategies. The Committee has concluded that a

further more detailed evaluation of the potential for demand management

and energy conservation measures to economicaJly contribute to a long-term

strategy is warranted. This chapter briefly discusses the reasons for this

conclusion and comments on the evidence presented to the Inquiry on demand

side measures and energy conservation.

3.2 Pricing

Pricing policy plays a large role in determining the relative economic

attractiveness of supply side and demand side measures.

A frequent recommendation concerning electricity prices is that they should

reflect the marginal costs of supply, that is, the costs of supplying additional

units of demand. Under marginal cost pricing it is argl'ed that both

consumers and supply authorities wiU receive the most appropriate signals

about consumption, conservation and investment decisions. Demand side

measures, which rely on modifications to consumer investment or

consumption decisions to achieve an overall economic benefit, will only occur

if the pricing signals encourage these modifications.

19

Page 58: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

It is not proposed here to enter what continues to be an active field of

research and debate into public monopoly pricing, nor to analyse SECV's

present pricing levels and structure, but it is stressed that the relationship

between the price of electricity and the cost of supplying it must receive

early consideration in assessing all options for balancing supply and demand

over the longer term.

This will require a re-examination of SECV's intended pricing policies over

the next five to ten years in conjunction with the supply options chosen as a

result of this Inquiry. Evidence to the Inquiry has shown that different

combinations of supply options can have quite widely varying long run

marginal costs. The short run marginal costs of production would also vary

considerably between different plant sequences. This will probably have

implications for the level and structure of electricity prices, for the

consequent levels of electricity demand, and for the role of demand side

options. SECV has acknowledged that existing cross-subsidies between

consumers and consumer classes further complicate the consideration of

demand side measures.

SECV previously intended to issue a Pricing Development Plan in 1987 for

public consideration and comment. It is understood that an early draft of

this plan was discussed with the Commission's Consultative Committee on

Pricing, however, no final document has been released. The finalisation of

such a plan should be a matter of priority, although it is recognised that

reduction of cross-subsidies and moves to marginal cost pricing may require a

lengthy phase-in period. SECV should therefore continue to refine their

marginal cost analyses and to pursue the adoption of more consistent tariff

structures.

3.3 Demand Side Measures and Energy Conservation

Demand side measures are programmes aimed at reducing, or changing the

pattern of, electricity demand. Energy conservation measures form a

specific class of demand side measures. Typical examples of conservation

programmes would be financial assistance for thermal insulation in houses or

factories, and the promotion of energy efficient appliances. Other demand

side measures not necessarily leading to conservation of energy would include

20

Page 59: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

initiatives like time-of-use prtcmg to encourage consumers to shift

electricity consumption to off-peak periods. It may be more cost effective

to change the future demand for electricity rather than to install additional

generating capacity in order to supply the "natural" level and pattern of

demand. Demand side measures can be thought of as alternatives, or

complements, to "conventional" supply measures. By comparing the costs and

other effects of different combinations of supply side and demand side

measures the most suitable combination can be selected.

Compared to thermal power stations, some demand side measures have the

advantage of requiring a short lead time. In addition, they can require only

small outlays of capital, particularly by the supply authority. This would be

of great advantage to SECV given its relatively high level of capital assets

and debt. Another advantage of many demand side measures, particularly

conservation, is their lack of, or low level of, environmental impact in

comparison with the impact of energy production technologies. Factors such

as the Greenhouse Effect, when more fully evaluated, may significantly

affect the emphasis placed on demand side measures by the community at

large.

On the other hand, there is less certainty about the overall level of effect of

demand side programmes. Only by implementing a programme can the rate

of penetration and ultimate effect be finally assessed.

More attention should be paid to conservation and demand side measures as a

means of improving the efficiency of Victorian energy use, reducing the

heavy demands for capital from the energy supply sector, and maintaining or

enhancing environmental quality. SECV should demonstrate that a

proportion of potential future load growth can or cannot be "supplied" more

economically through investment in demand side measures than through

investment in conventional supply options.

It is important that all options for balancing supply and demand in the longer

term are fully considered at the strategic planning stage, because the

relative attractiveness of demand side measures and energy conservation

changes markedly once irrevocable supply side investment decisions are

made. For example, SECV is committed contractually to the construction

21

Page 60: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

of Loy Yang B Units 1 &: 2, and so has Jimited financial incentive to invest

heavily in the short to medium term in conservation or other demand side

measures which might reduce projected demand to the point where

over-capacity would result from installation of these units.

System reliability considerations are also important in balancing supply and

demand. Traditionally, electricity systems have invested in a certain

proportion of reserve plant to cover the probability that plant outages might

occur when system demand is high. Demand side measures are also available

which can contribute to system reliability. Specifically, arrangements can

be made by means of financial incentives for particular consumers to reduce

demand when supply capacity is short. Such interruptible or controllable

loads are common overseas. In Victoria, arrangements have been made for

the large aluminium smelting loads to be interrupted for short periods when

emergency situations occur. Arrangements could also be made for

privately-owned emergency or standby generators to come into service

during periods of potential energy shortage in SECV generating system.

These demand side measures should receive more detailed consideration by

SECV.

The earlier comments on electricity pricing should also be noted here. SECV

has argued that opportunities for significant investment in demand side

measures will be limited by the intention of SECV and government to adjust

prices over time to reflect long-run marginal costs. However, evidence

before this Inquiry has shown how widely marginal costs can vary with the

inclusion of different supply options and with the discount rate used to

calculate marginal cost, making it difficult to reconcile this intention with

the concurrent aim of maintaining stability in electricity prices. It can be

expected that there will continue to be areas in which substantial investment

in demand management can be justified.

22

Page 61: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

3.4 Assessment of Demand Side Measures and Energy Conservation

Appendix 5 categorises demand side measures according to their nature and

purpose, and presents a summary of SECV's current demand side programmes.

The SECV approach to demand management has identified nineteen demand

management programmes and these provide the basis for the targets in

Table 2.1. However, no evidence has been presented as to how the

economics of each programme compares with supply side options, or how the

quantitative targets set by SECV were determined.

SECV should develop economic screening methods for demand side measures

so that each programme's priority can be set in relation to conventional

supply side options. The Committee understands that such methods have

been the subject of much development work in the U.S.A. over recent years

and that evaluation techniques are now available in that country.

In addition, the contribution of each demand side measure should be

quantified in relation to the duration of each programme and the programme

participants. Because the effects of demand side programmes can be

uncertain, SECV should develop methodologies aimed at quantifying and

reducing the uncertainty.

On the financial assessment of demand side programmes, SECV have proposed

that each programme should be required to pass the "non-participant's test".

This test would require that each programme should have no adverse financial

impact on any section of the community.

In practice, application of this test can serve to prevent the implementation

of demand side programmes with very sound economic features and benefit to

cost ratios. Application of the test to individual programmes is not

necessarily sound as it is the aggregate effect of all programmes which is

important. Consumers who are slightly worse off under one programme can

benefit from other programmes. In addition, there has never been a

requirement that supply side strategies should meet a non-participant's test.

For these reasons, the non-participant's test has fallen out of favour in the

USA and the most favoured approach is to develop least cost energy

23

Page 62: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

strategies. The least cost strategy seeks to minimise the overall cost of

both supply and demand side developments.

SECV should pursue a least cost strategy as this will result in the maximum

long-term benefit to the Victorian community.

3.5 Integrated Planning

SECV have developed targets for their proposed demand management

programmes and then adjusted the load forecasts in accordance with these

targets. Supply side scenarios are then developed against the modified load

forecasts. This approach fails to properly integrate supply side options with

demand side programmes.

After developing priorities for demand management, SECV should seek an

integrated approach where the timing of both supply side and demand side

options are co-ordinated in individual scenario studies. Under such an

approach, more flexible and responsive strategies can be developed.

3.6 The Greenhouse Effect

It has been demonstrated that the levels of carbon dioxide in the atmosphere

have increased significantly over the last century. lt is currently thought

that two of the major underlying causes for this increase are dramatic

increases occurring in the world population combined with increased per

capita usage of fossil fuels. It is predicted that the levels of carbon dioxide

will continue to increase.

The term "greenhouse effect" arises because carbon dioxide acts like the

glass in a greenhouse. Visible radiation from the sun passes through glass or

carbon dioxide; on hitting the ground the sunlight is converted into heat and

the ground emits infra-red radiation. Infra-red radiation is blocked or

absorbed by the glass or carbon dioxide and this causes the overall ambient

temperatures of the air, the earth's surface and the sea to rise.

It has been predicted that changes in the ambient temperature will cause sea

levels to rise and major changes in global weather patterns to occur.

24

Page 63: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The overall process is extremely complicated and not well understood;

considerable co-ordinated international research is required over the next

decade or more before the implications can be fully evaluated. Until this

work has been done, it will not be possible to come to definite conclusions

about what precise action, if any, should or could be taken with regard to the

use of fossil fuels for the generation of electricity.

There is an urgent need for both the Commonwealth and Victoria to actively

support the gathering and analysis of the necessary information.

3.7 Specific Recommendations

SECV should continue to evaluate the relationship between the

costs of proposed sequences of supply options and its pricing

policies to establish the consequent implications for future levels

of electricity demand. (Recommendation 6)

SECV should give consideration to expanding its range of

electricity supply tariffs to include more generally available

tariffs for controllable or interruptable supplies.

{Recommendation 7)

SECV should continue its present programmes which are aimed at

encouraging conservation and demand side measures. They

should investigate the potential to expand these programmes and

to develop new programmes. The effectiveness of these

programmes and their potential for expansion should be reported

in SECV's annual report. {Recommendation 8)

The Government should amend the Victoria Building Regulations

to require thermal insulation in new buildings and should continue

to promote the design and construction of solar and energy

efficient buildings. (Recommendation 9)

25

Page 64: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Further terms of reference should be given to this Committee to

allow for a more detailed examination of demand side and energy

conservation measures and their potential to contribute to

economically, socially and environmentally beneficial strategies

for balancing electricity supply and demand. This examination

should be based on:

The development of methodologies for quantifying the

effects of and evaluating demand side and energy

conservation programmes on a basis consistent with

evaluation of supply side options;

The integration of demand side and supply side planning

using a least cost approach to maximise overall benefits to

Victoria;

The development, selection and implementation of

practical demand side and energy conservation programmes

in Victoria;

The identification of research and information needs for

effective demand side and energy conservation

programmes;

(Recommendation 10)

The Commonwealth and Victorian Governments should support the

gathering and analysis of information which would improve the

current level of understanding of the Greenhouse Effect and its

implications for Victoria, Australia and the world at large. In

particular, SECV should assist by providing annual estimates of

the total release of Carbon Dioxide and other contributing

emissions from its operations. This information should be

published each year in Victoria's "State of the Environment

Report" together with estimates of contributions from other

sources.

(Recommendation 11)

26

Page 65: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER FOUR

THE PERFORMANCE OF EXISTING GENERATING

PLANT AND THE DEVELOPMENT OF IMPROVED PLANT

FOR THE FUTURE

4.1 Introduction

The generating capability of SECV's existing plant is a major determinant of

the short-term reliability of, and cost of operating, the electricity system,

and of the longer term requirements for the addition of supply capacity.

Poor performance from existing plants can increase the risk of electricity

restrictions and blackouts, and if prolonged, advance the time at which new

plant must be constructed and brought into service. Conversely, good

performance ensures reliability of supply, and if sustained, reduces future

requirements for new plant.

Over the last four years, SECV has identified the performance of its existing

brown coal fired power stations as an area of significant concern. Under the

Production Improvement Programme (PIP), it has obtained approval to spend

nearly five hundred million dollars on refurbishment and other works to

increase the projected energy contribution from these stations by either

improving reliability and capability or extending plant lifetimes. SECV

evaluations indicate that expenditures of this magnitude are more cost

effective than the alternative of earlier construction of new generating

plant.

Many of those giving evidence stressed the need for an increased level of

Research and Development if brown coal is to continue to compete with

other fuels in the long term.

4.2 Plant Availability

Plant availability can be broadly defined as the extent to which a power

station (or its individual units) is able to supply its rated capacity to the

system if called on.

27

Page 66: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Committee commissioned P.M. Garlick &:: Associates to produce a paper

on power plant availability issues, with particular reference to experience

overseas and in other Australian states. Amongst the issues identified were:

Improving or stable trends in overseas plant availability, at levels

generally higher than Australian averages;

Significantly lower availabilities for thermal power stations in

NSW and Victoria than in Queensland, SA, or overseas;

Recent declines in availability in Victoria's older brown coal

stations;

The importance of technology, management procedures, work

practices and industrial relations in improving availabilities.

The paper reinforces the conclusion that availability is an extremely

important issue for SECV over the remainder of this century, and can

potentially have major impacts on the requirements for new generating

capacity over this period. PIP represents a significant commitment by SECV

to the objective of improving availability.

It is therefore important that the progress of this programme and the scope

for additional improvements in plant availability and performance are

regularly and publicly reviewed, in the same way as other aspects of SECV

operations, such as cost control on the Loy Yang project since 1982. Failure

to maximise the performance of existing generating plant by pursuing all

opportunities for improvement could lead to large and unnecessary additional

costs being imposed on all electricity consumers.

As part of this public review, SECV could produce a regular yearly report on

the performance of its installed generating plant, including details of

available and actual capacity factors achieved, planned and unplanned unit

outages, repair times and other statistics. In addition, target performance

levels for future years could be published and any significant deviations of

actual performance from earlier targets explained. Such a report would

enhance accountability and complement the detailed financial statements

presently required of SECV.

28

Page 67: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Any future commitments to new generating plant construction must be made

with adequate regard to existing plant performance. The incentive to

maximise plant performance can be severely reduced once fixed

commitments to expenditure and service dates for new plant are made.

Therefore, developing a strategy for new plant commitments that retains

incentives to maximise availability in existing power plants is an important

consideration.

4.3 Extending Plant Lifetimes

The assumptions used to estimate the financial, economic and regional

effects of future supply option sequences presented in this Inquiry, required

SECV to nominate retirement dates for its older power stations. SECV

indicated that a significant proportion of the present installed capacity,

particularly the base load brown coal fired capacity, would reach the end of

its operational life in the period following the mid-1990's. The retirement

dates nominated by SECV are shown in Table lf.l.

This means that the magnitude and timing of new plant installation over this

period is significantly driven by the requirement to replace retiring plant, in

addition to meeting projected demand increases. Consideration of the high

capital cost of new generating plant suggests that, if the lifetime of older

stations such as Hazelwood and YaHourn W Stage 1 can be prolonged by even

five or ten years, then very substantial cost savings may be available as the

need to construct a corresponding amount of new base load capac,ity would be

deferred.

Recognising the potential importance of this issue, the Committee requested

SECV to examine the economic value of extending the life of Hazelwood

Power Station from the assumed 35 years used in previous scenario studies to

lj.Q years. SECV's response to this request, reproduced as Appendix 6,

indicates that very significant benefits could accrue if such an extension

were feasible.

In fact, Hazelwood Power Station is currently undergoing a major

refurbishment and life extension programme, at a cost of around $300 m

(June 19&6), following a plant life study in 19&1f that indicated that

29

Page 68: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE 4.1

SECV PLANNED OR EXPECTED PLANT INSTALLATIONS

AND RETIREMENTS

YEAR INSTALLATION RETIREMENT

1988 Loy Yang A4 (500 MW)

1992-940) Loy Yang Bl (500 MW)

1993-960) Loy Yang B2 (500 MW)

1993 Yallourn E (240 MW)

1999 Hazelwood I &: 2 (400 MW)

2001 Hazel wood 3 &: 4 ( 400 MW)

2003 Hazelwood 5 &: 6 (400 MW)

2005 Hazelwood 7 &: 8 (400 MW)

2006 Jeeralang A (225 MW)

2008 Jeeralang B (240 MW)

2011 Newport D (500 MW)

2013 Yallourn W l &: 2 (700 MW)

(I) Loy Yang B Units 1 &: 2 are currently programmed for installation on a flexible timetable dependent on load growth and plant performance.

30

Page 69: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

complete closure of the station by as early as 1990, a twenty-five year life,

could have occurred without such works. This early closure would have had

severe consequences, necessitating reformulation of the present strategy for

Loy Yang B Units 1 & 2, with employment and other implications for the

Latrobe Valley.

It is of some concern to the Committee that the condition of the Hazelwood

plant had evidently deteriorated to the point where quite drastic measures,

such as complete replacement of the boiler waterwalls on the older units, had

become necessary to avert possibly imminent closure of the station. It is

somewhat fortuitous that the excess capacity now existing on the generating

system (a result of the inability to re-schedule Loy Yang A construction

despite lower than expected load growth) allows the extended outages needed

at Hazelwood to undertake this work, without prejudicing the reliability of

electricity supply. Such a situation cannot be relied on to occur in the

future.

It remains to be seen whether the present work on Hazelwood does result in

the extension of the plant's life to the thirty-five years hoped for. To date,

two units have undergone life extension works. Several years of operation

and continued monitoring of the condition of each unit will be required before

any definite indications will be available. The fact that two units underwent

costly "reconstructions" between 1981 and 1983, only to require further major

works five years later indicates that life extension is not a certain business.

Despite these uncertainties, it is obvious that SECV must continue to devote

considerable attention and resources to maximising the economic lifetimes of

its existing plants. Over the next three years, major works under PIP will

occur at all Latrobe Valley brown coal stations. Following these, the

Committee believes that a process of continuous review of plant condition

and remaining lifetime should be maintained, in order to detect deterioration

early, avert unexpected major failures where possible, arrange fuel supplies

for replacement plant and ultimately allow orderly planning of plant

retirement. The present notional retirement of the Hazelwood Power Station

at the turn of the century is clearly an issue that should be the subject of an

early, detailed economic and engineering review following the present life

extension works.

31

Page 70: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

4.4 Research and Development into Electricity Generation from Brown Coal

Generation of electricity from Victorian brown coals presently involves

technology based on German experience modified to deal with the unique

properties of Latrobe Valley coals.

Brown coal in the Latrobe Valley has a very high moisture content

(over 6096). Considerable effort has gone into the development of plant

which can handle and burn this fuel in a reliable and efficient way.

Some of the particular utilisation characteristics of this fuel include:

Spontaneous combustion of stockpiled coal;

Auxiliary fuels (distillate or briquettes) are required for start-up

and to maintain flame stability at low load;

Coal needs to be partially dried by furnace gases prior to

combustion;

Coal needs to be finely crushed in milling plant and thoroughly

mixed with hot air to obtain efficient combustion;

Fouling of boiler tubes by ash deposits can be a major problem

with some Latrobe Valley coals;

Very large volumes of water vapour have to be removed with the

combustion products from the furnace;

Boiler furnace size is relatively very large;

Flue gas temperatures at the boiler outlet have to be kept high in

order to avoid condensation of the water vapour and consequent

corrosion problems;

A very low density fly ash must be removed from flue gases.

32

Page 71: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Plant design features have largely accommodated these utilisation

characteristics particularly in the later plant such as Loy Yang A; however,

it has resulted in the development of highly capital intensive plant. Evidence

to this Inquiry has revealed that the current level of capital intensity of

brown coal fired generation plant appears to significantly offset the

advantages of the abundance of, and relative ease of mining the raw fuel.

Electricity generation from other fuels, particularly black coal, may now

have significant overall cost advantages (see Chapter 12). If the capital

intensity of technologies for generating electricity from brown coal is not

reduced, Victoria may lose its apparent comparative advantage in electricity

generation, despite its very large primary energy reserves.

The scope for significantly reducing this capital intensity using the

technology currently employed is limited. Some of the concepts put forward

during the Inquiry for marginally improving the capital intensity were:

4.4.1 Boiler Plant

The use of pulverised dried brown coal (PDBC) as an auxiliary

fuel.

The briquettes currently used for auxiliary fuel have to be ground

up prior to use in the boiler system. Pulverised dried brown coal

would not require pre-grinding and thus eliminate the cost of the

mills currently used for this purpose.

Proven technology is available in Germany where PDBC is

produced in conventional briquette factory dryers. An

alternative means of production has been proposed which uses a

stand alone mill drying system similar to those used in Latrobe

Valley boilers. Production and use of PDBC using this system is

to be tried out by SECV during 1990.

The need to evaluate alternative auxiliary fuels to possibly

replace briquettes is becoming a presssing issue and is further

addressed in Section 11.1.5. This work should be given a high

priority.

33

Page 72: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The development of improved milling systems

SECV have calculated that application of their present knowledge

to the redesign of the current mill system will save 15-2096 of the

current capitalised life cycle costs of the mills which are about

$3.3 million per mill. Specific proposals include:

Improving the fan efficiency;

Pre-milling the coal prior to injecting into the

furnace gas offtake.

This is a proposal which will have the effect of immediate cost

reductions if applied to the next stage of Loy Yang.

proposals should be implemented.

The development of improved burners

These

Swirl burners have been investigated by SECV and are a

technically viable option. Major laboratory and prototype studies

were done in the 1970's and swirl burners were offered for

Loy Yang boilers by one tenderer following tests in Yallourn

Power Station. Further work on swirl burners is currently being

done in a burner test rig.

The recessed burners of the type used for Yallourn W2 and

Loy Yang have unique mixing characteristics which have been

examined in some depth. Their influence on overall furnace

flow/combustion/fouling is being investigated both in a physical

model in the Herman Research Laboratory and through a

collaborative research programme with Swinburne Institute of

Technology.

This work will improve SECV's ability to design burners for

specific coals and to determine if separation of the hot coal/air

stream by particle size is required. In conjunction with other

research work, this could lead to lower capital costs and increased

34

Page 73: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

availability of future brown coal plants. This is an area where

SECV should place considerable emphasis.

Optimisation of boiler design

Currently, brown coal combustion chambers are some 2.5 times

the volume of equivalent black coal chambers. Significant cost

savings could be achieved if furnace height and volume were

reduced. This would raise furnace exit temperature and could

increase superheater fouling. Key elements of a current SECV

research project are aimed at:

Establishing the sensitivity of ash fouling to gas

temperature;

Investigation of combustion modification and use of

additives as a means of fouling control;

Investigation of the possible use of water blowers in

superheaters - their effectiveness and influence on

superheater tube integrity.

There is potential for reduction in furnace cross-section if the

combustion system can be optimised so as to minimise furnace

wall fouling and slagging. Investigations of the effects of

changes to furnace aspect ratio, burner positioning, degree of

separation firing and means of keeping burner jets and hence ash

from impinging on the furnace waHs are to be conducted by SECV

using simulation modelling techniques being developed in

conjunction with Swinburne Institute of Technology. Considerable

emphasis should be placed on this work as it is fundamental to

improving the design of brown coal fired boilers.

35

Page 74: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

4.4.2 Coal Winning Techniques

The Union submission suggested that the amount of coal extracted from a

particular open cut could be maximised if much more cost effective and

flexible coal-winning techniques were used, including the possible

interconnection by coal transfer systems of selected open cuts. It was

suggested that this would allow maximum use of existing infrastructure. This

possibility should be further reviewed.

4.4.3 Precipitators and Ash Handling Plant

The Union submission suggested that further work was required to optimise

the design of precipitators in order to reduce corrosion and to improve the

operation of precipitator ash handling plant. This should be further

investigated.

4.4.4 New Coal Preparation or Combustion Technologies

New technologies which could have a significant impact on the capital

intensity of brown coal fired electricity generation in the longer term are:

Thermal dewatering of coal

Conventional pre-drying of brown coal for combustion processes

increases boiler combustion temperatures and aggravates fouling

problems. However, thermal dewatering (heating slurried coal

under presssure to approximately 300°C) removes most of the

inorganic materials from the coal. These materials are the cause

of fouling problems. The resulting dewatered coal could be used

in the form of a concentrated slurry suitable for injection into a

gas turbine or as an auxiliary fuel or main fuel for a conventional

boiler. Use of this fuel as the main fuel in a conventional boiler

would considerably reduce the size of the boiler for a similar

output and hence reduce its capital cost. This technique should

be further investigated.

36

Page 75: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Circulating Fluidised Bed Combustion (CFBC)

Preliminary studies indicate CFBC boilers are competitive with

conventional boilers with flue gas desulphurisation plant but not

when desulphurisation is not required. Desulphurisation is not

required for brown coal. However, the studies referred to were

carried out by overseas authorities and do not relate directly to

brown coal. Other benefits may occur when using brown coal.

The Electricity Trust of S.A. (ETSA) are having tests conducted

on Bowmans and Lochiel coal in a Lurgi 1.5 MW CFBC pilot plant

in Germany. These are to be followed by a Boiler Feasibility

Study.

Consideration should be given to conducting similar tests on

Latrobe Valley coals if the tests on SA coal indicate potential

benefits from using this technology.

Gasification

Integrated gasification combined cycle (IGCC) plants are

considered to be competitive with conventional plant based on a

German proposal for a 600 MW plant for brown coal. A 100 MW

demonstration plant at Cool Water, USA, has operated

successfully but not on brown coal. A German consortium is

investigating a possible 2 x 300 MW IGCC plant for Bow mans coal

in SA. This investigation includes gasification tests in the HT

Winkler pilot plant in Germany. The SA work should be kept

under review by SECV and a more detailed assessment of the

economics conducted. If these assessments are favourable, the

research required to evaluate Latrobe Valley coals should be

undertaken.

Coal Fired Gas Turbine

Investigations by the Commonwealth Aircraft Research

Laboratories in 1948-1971 showed that the main limitation to

37

Page 76: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

using dri~d brown coal to fuel a "gas" turbine was the fouling and

erosion of the turbine's blades. With the advances in materials

technology and blade design to combat erosion and transpiration

cooling of blades to reduce fouling, a review of this technology is

warranted.

The possibility that gas turbines could be developed to operate

satisfactorily on brown coal should be further investigated. This

investigation should include the possibility of using coal that has

not been pre-dried, coal pre-dried using turbine exhaust heat and

thermally dewatered coal.

4..5 Specific Recommendations

The Committee recommends that:

Priority should be given to improving and maintaining the

availability of existing plant and extending its life where this is

economically viable. (Recommendation 12)

SECV should publish a yearly review of the performance and

condition of its generating plant, including:

Details of avallable and actual capacity factors

achieved, major planned and unplanned unit outages,

repair times and other statistics;

Targets and projections for the performance of existing

plant over future years, and explanations of any

significant deviation of actual performance from earlier

targets. (Recommendation 13)

3&

Page 77: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

SECV should carry out and publish regular assessments of the

scope for improving the projected performance or expected

lifetime of existing plant through refurbishment or preventive

maintenance works, changed management or work practices, or

technological enhancements. (Recommendation 14)

Prior to commitments to the construction of new generating

plant, the interaction between existing plant performance and

lifetime, and the introduction of new plant should be reviewed.

This review should ensure that the fuel resources allocated to the

existing plant allow the maximum scope for performance

improvement and economic life extension. In particular, the

planned retirement date of the Hazelwood Power Station should

be subject to a detailed review prior to any commitments to

construct new power stations for service after 1999.

(Recommendation 15)

A more active Research and Development programme should be

initiated by SECV into improved techniques for the use of brown

coal in power generation. This should include:

Development of efficient methods for the production

and utilisation of pulverised dried brown coal;

Investigation of the potential for development of a

"dewatered" coal;

Development of improved milling, burner and

predpitator designs;

Optimisation of boiler designs;

Optimisation of coal winning techniques, utilisation

strategies, and equipment;

39

Page 78: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

An on-going review of developments in the Circulating

Fluidised Bed Combustion and Integrated Gasification

Combined Cycle technologies;

A detailed review of the possibility that gas turbines

could be developed to operate satisfactorily on brown

coal.

(Recommendation 1 6)

40

Page 79: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER FIVE

LARGE SCALE SUPPLY OPTIONS

5.1 Introduction

This chapter summarises evidence presented to the Inquiry on possible large

scale power supply options for Victoria beyond the mid-1990's, in terms of

their locations, technology, environmental impacts and costs. Key individual

large scale power supply options and considerations on their sequencing are

discussed in detail in later chapters of the report.

Small scale power supply options, typically of less than 10 MW capacity, are

discussed in Chapter 6. These small scale options may currently be

attractive because of factors such as geography (e.g. remote area power

supplies), energy efficiency (e.g. cogeneration), or environmental

considerations (e.g. wind, small hydro, and solar). It is unlikely that their

implementation in the decade covered by this Inquiry will have major impacts

on the choice or sequencing of the large scale supply options, although they

may well affect the timing of such options.

The Committee also considered the possibility that future large scale power

supply options could be based on technologies other than those currently in

use in Victoria. A wide range of new technologies is being developed

throughout the world and many of these are approaching the stage where

large scale implementation may become economically viable and hence

provide additional competitive options by the turn of the century. These

options are discussed, together with the need for research and development in

other chapters of this report. At this time, none has reached a stage of

development where a positive recommendation to include a particular option

based on a new technology in a future power supply sequence for Victoria

could be substantiated.

41

Page 80: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Therefore, the Committee has reached its primary recommendations on the

sequencing of supply options to follow Loy Yang B Units 1 & 2 in the decade

following the mid-1990's on the basis of large scale options using currently

proven technologies. The possibility that new power generation technologies

may become viable in the future has been taken into account in the

Committee's recommendations covering research and development, and

recommendations on processes that would enable early advantage to be taken

of future technological change.

5.2 Overview of Options

The following large scale power supply options were presented in evidence to

the Inquiry, classified here according to their primary energy source and

technology:

Latrobe Valley Brown Coal

These options were presented in SECV evidence and are based on

conventional pulverised fuel boiler technology. They would be similar in most

respects to recent Latrobe Valley power stations.

Loy Yang open cut

Morwell open cut

Yallourn open cut

Driffield area

42

2 x 500 MW option at Loy Yang B (Loy Yang B Units 3 & 4}

2 x 350 MW, 2 x 500 MW or 4 x 500 MW options at Hazelwood South

2 x 350 MW or 2 x 500 MW options at Morwell Siding

2 x 375 MW, 2 x 500 MW or 4 x 500 MW options at Yallourn F

220 MW or 320 MW redevelopments of (retired) Yallourn C/D station

4 x 500 MW or 8 x 500 MW options based on a new open cut.

Page 81: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

These options represent the lowest potential cost brown coal options

available and would, in total, provide adequate additional power supply

capacity until well after 2010. Consequently, other "greenfield" brown coal

options described in earlier SECV reports have not been considered by this

Inquiry.

Oaklands Black Coal

CRA Ltd. (on behalf of the CRA/Mitsubishi Oaklands Joint Venture) and

SECV presented evidence on three black coal fired options based on Oaklands

coal. These options would be based on conventional pulverised black coal

boiler technology and would be of a similar design to recent NSW power

stations.

Oaklands power station -

Yarrawonga power station

Natural Gas

2 x 700 MW or 4 x 700 MW options located adjacent to the proposed open cut mine

2 x 700 MW option located near T elford, coal supplied by rail from Oaklands

SECV and BHP Ltd. presented information on gas fired generating options.

These would be supplied with natural gas from the Bass Strait fields, although

other sources of gas supply are possible in future years.

No firm locations for gas fired options were specified in evidence as it was

proposed that the precise location would be resolved by a more detailed

inquiry dealing with the specific environmental effects arising at the

alternative sites. Fuel, land, water, infrastructure and environmental

requirements for such options can be satisfied at a wider range of sites than

is the case for coal fired power stations. Sites would tend to be chosen for

either gas supply or electricity transmission advantages, provided that all

environmental requirements could be met.

43

Page 82: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Notional sites used by SECV for comparative purposes were:

Longford

Latrobe Valley

South-east of Melbourne (e.g. Tyabb or Carrum)

North-west of Melbourne (e.g. Donnybrook or Sydenham)

North-west of Geelong (e.g. Moorabool)

Siting of individual gas turbine units at existing SECV facilities

(e.g. transmission terminal stations)

Possible technologies and station capacities were:

Gas turbines

Combined cycle

Steam cycle (gas fired boiler)

Hydro-electricity

500-2000 MW in 500 MW "blocks" distributed siting of 100 MW units

500-2000 MW in 500 MW blocks

500-1000 MW in 500 MW units

SECV has identified larger hydro-electric options on the following river

systems:

Kiewa - options for extension of existing scheme providing additional 120 MW (150 GWh/yr) or 200 MW (330 GWh/yr)

McAJister 40 MW (60 GWh/yr) option

Mitchell 55 MW (80 GWh/yr) option

Mitta Mitta 20 MW (40 GWh/yr) or 40 MW (80 GWh/yr) options

Rub icon options for redevelopment of existing 13 MW, 80 GWh/yr run of river scheme to provide an additional 12-16 GWh/yr (no extra capacity) or additional 31 MW, 12-16 GWh/yr and storage (peak load) capability.

44

Page 83: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

During an inspection of the Snowy Mountains Hydro-electric Scheme by the

Committee, officers of the Snowy Mountains Hydro-electric Authority

informed the Committee that no cost effective and environmentally

acceptable developments appeared feasible in that system in the period under

consideration, with the possible exception of the Yarrangobilly pumped

storage scheme (see below).

Pumped Storage

Previous SECV studies of pumped storage developments included a 500 MW,

30-40 hour storage scheme at Trawool (near Seymour). The Snowy Mountains

Hydro-electric Authority has undertaken preliminary desk studies of a

1000 MW 10 day storage scheme, Yarrangobilly, utilising the existing

Tantangara and Talbingo reservoirs. Pumped storage schemes are net

consumers of energy whose value lies in the ability to store lower cost off

peak electricity and generate at times when high fuel cost sources would

otherwise be required.

Interstate Contract Supply

Victoria's electricity system is connected with that of NSW as a result of

shared access to the Snowy Mountains Hydro-electric Scheme. An extension

to provide interconnection with South Australia is planned for 1990. An

interconnection between the mainland States and Tasmania is technically

feasible. The main uses of the existing Victoria/NSW interconnection (other

than for carrying each State's Snowy energy entitlement) and the justification

for its planned extension to South Australia are short term, non-contractual,

"opportunity" energy interchange which minimises the hourly operating costs

of the combined State systems, and the sharing of reserve generating plant

which increases supply reliabHity. However, large scale interstate contract

supplies would be feasible with appropriate transmission reinforcements.

Supply to Victoria from an Oaklands Power Station could represent one

example of such an arrangement.

Interstate transfers and contract supplies are discussed separately from other

supply options in Chapter 12 of this report.

45

Page 84: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

~.3 Location of Options

Figures 5.1, 5.2 and 5.3 illustrate the location of the options listed above.

Definite sites for a Yarrawonga Power Station and for gas fired options were

not specified in the evidence given to the Inquiry.

~.4 Status of Evidence on Options

Evidence before the Inquiry on the impacts of future supply options,

particularly the effects of alternative sequences of these options, has been

complex and voluminous. The consistency and usefulness of this evidence in

describing the effects of the alternative sequences is dependent, in the first

instance, on the basic information presented on individual supply options. It

is important that information on the costs, workforce requirements,

reliability, efficiency and environmental impacts of each option is provided

on a comparable basis and as a result of appropriately detailed studies. In

view of the Inquiry's strategic nature and medium to long term focus, it was

recognised that the level of detail to which each option has been investigated

and described need not be as high as would be required if immediate

investment decisions were necessary, and that some changes in the data

presented are inevitable over time.

Taking as one example the information provided on the capital costs of each

option, the Committee accepts that in most cases cost data have been based

on preliminary or conceptual designs rather than a detailed estimate. This

level of accuracy is quite adequate for establishing the cost relativities of

options. However, some changes from the costs presented would be expected

when more detailed designs, the effects of foreign exchange variations,

tender market conditions and site investigations were fully taken into

account. The preparation of detailed cost estimates would certainly be

required prior to the government giving approval to proceed with any option.

During the early part of the Inquiry, it became apparent that estimates of the

cost of the possible Oaklands developments provided by SECV and CRA were

significantly different.

46

Page 85: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

::!l ~~nHm

C)

~ j Mildura

1'11 i ~ .... i

i i I

t""

~ I

g z

..j::>o ~ .......,

~ ~ I

" VI I

~ I

t"" I -< 0

I

8 I

z VI

z < .... Q ~ >

~ LEGEND

• THERMAL POWER STATION

C HYDRO POWER STATION

t1 TERMINAL STATION

TRANSMISSION LINES

• SITE OF POWER STATION OPTIONS

..... , \.SNOWY \sCHEME

' I "- I

e MlTTA MlTTA RIVER

.... ..... .,

• MACALISTER R~lVER ·,,

MITCHELL RIVER • 0

./Lakes Entrance ~Traralgon / '-------'\""\ _ ~.LO.._ . • LONGFORD

Page 86: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

~ ~~ YAllOUIIN NORTH

YAUOUMrsf G) YAI.lDIIIIII w ,. I

~ ~ \11 N

.;:. .... t"' (X)

~g

IWIIWOOOrs

ffi~ ~

t"'Q 2iZ ~~

® D''tl I'TIQ <~

® F=, t"'CII ~"~'~c -<., .,

t"' -< 0 g z VI

~)

~ ~r~ ~~i ~ 'j\\1>

IOYU"G A OPI"CUI~

IOY U"G. PS ~

IOY Ylll1!11 I II(J ®

LEGEND

(£) YAllOURN F

I I f J 4 '''" ® MORW!ll SIDING IICAII ® HAZEl WOOD SOUTH

@ lOY YANG 8 UNITS 3 6:.

® DRIFFIELD

Page 87: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

FIGURE 5.3

------~r---------1~~

8£RRIGAN

I I

8£NALLA

l -1 i --j

I i L -]

I I I

LOCATION OF POSSIBLE SITES FOR POWER STATIONS BASED ON OAKLANDS COAL

49

Page 88: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CRA estimates were derived from two sources. In the first instance, CRA

had appointed consultants to prepare a feasibility study for an Oaklands coal

mine and power station which included cost estimates for the power station

based on the consultants' "reference design" (of which there are many

operating examples, mostly in the USA). In addition, CRA appointed the

Electricity Commission of New South Wales (ECNSW) as consultants to

prepare cost estimates for the 11power station island" section of the project

based on appropriate adjustments to the design of its recently completed

4 x 660 MW Bayswater Power Station.

SECV had access to ECNSW's cost data on the Bayswater station and used

these as the basis for preparing a "check estimate11 of the Oaklands costs.

The Oaklands cost estimates prepared by CRA and SECV initially differed by

19%. Discussions between SECV and CRA, with the participation of the

Committee's staff, resolved a number of differences on elements of the cost

estimates. However, the resulting revised estimates were still at variance by

some 9%. In an attempt to avoid unnecessary confusion during the later

stages of the Inquiry, the Committee requested that evidence describing the

effects of alternative sequences of these options, should be based on a

"compromise" set of estimates defined by the Committee. These estimates

were intermediate in value to the two revised estimates. The use of the

estimates defined by the Committee did not affect the broad cost relativities

between Oaklands and other supply options. It was also apparent that the

relatively very small differences between the overall estimates for the cost

of energy supplied from either Loy Yang B Units 3 &: 4 or a half share in an

Oaklands project were almost entirely related to the different assumptions

made by the various parties. The potential for variation in more detailed

future estimates of the capital and operating costs of Oaklands (and of all

other options) has been recognised in the Committee's recommendations.

Natural gas and Oaklands black coal would be supplied to power stations

under commercial contracts not yet negotiated. For the purposes of the

Inquiry, participants used a range of fuel prices within which the negotiated

prices would probably fall. Again, the Committee recognises the potential

for actual negotiated prices to lie outside the notional ranges adopted, or for

50

Page 89: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

negotiations to fail completely, and has made recommendations allowing for

these possibilities.

During the course of the Inquiry, SECV made the point that the costs for

Loy Yang B Units 3 & 4 were based on the costs for Loy Yang A.

Considerable cost overruns occurred during the early stages of this project

which resulted in a review of these costs being initiated by the Government

and a greatly improved management and cost control structure being

implemented. SECV claim that their estimates for Loy Yang B Units 3 & 4

based on this experience are now very accurate and that costs will be

contained during the course of construction.

SECV indicated that as a result of the July 1987 annual review, the original

capital cost estimates for Loy Yang B Units 3 & 4 could be reduced by

$113 million from those originally given to the Committee in Aprill987. The

SECV also indicated that a review of expected operating and maintenance

costs was being conducted jointly with the Unions.

5.5 Option Costs and Workforces

Tables 5.1 and 5.2 show the basic costs and workforce requirements

associated with the large scale supply options described in this chapter. The

following items are shown:

Capital cost - Cost associated with the construction of each

option and its supporting infrastructure, including direct costs,

overheads and contingency sums. Interest during construction is

not included. For brown coal fired options only, fuel supply (i.e.

coal mine) capital costs are included.

Operating and maintenance cost - Direct and overhead costs of

annual operation and maintenance. For brown coal fired options

the incremental coal mine operating costs associated with each

option are included. For black coal and gas fired options the cost

of purchased fuel is not included.

51

Page 90: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Fuel cost - The cost per unit of energy of purchased fuel (black

coal or gas).

Transmission cost The capital cost of transmission works

required to connect each option to the main transmission system.

Unit capital cost The capital cost and transmission cost of

each option divided by its generating capacity.

Unit operating and maintenance cost - The annual operating and

maintenance cost divided by the generating capacity of each

option.

Construction worker-years - The total number of worker-years

required for construction of the option (on-site employment only).

Peak construction workforce - The highest number of on-site

jobs over the construction period of the option.

Operations workforce The eventual size of the workforce

required to operate the option, including maintenance workers

and, for brown coal fired options only, additional workers required

in the open cut coal mine.

52

Page 91: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE .5.1

Capital Option Capacity Cost

(MW) ($M)

LA TROBE VALLEY BROWN COAL FIRED OPTIONS

Loy Y ang open cut

- Loy Yang B Units 3 & '+ 1000 1236

0'1

w Morwell open cut

- Hazelwood South 700 1.511 1000 1742 2000 3.536

- Morwell Siding 700 1.524 1000 17.5'+

Yalloum open cut

- Yal1ourn F 7.50 1.513 1000 1697 2000 3464

- Yallourn C/D 220 639 (re-development) 320 72.5

Driffield 2000 3661 4000 7247

LARGE SCALE SUPPLY OPTIONS

COST DATA

Operating and

Maintenance Fuel Cost Cost

($M/yr) ($/GJ)

(Note 1) (Note 2)

'+0 0

.57 0 68 0

119 0

.57 0 67 0

62 0 67 0 94 0

29 0 30 0

136 0 200 0

Unit Unit Transmission Capital Operating

Cost Cost Cost ($M) ($/kW) ($/kW /yr)

(Note 3)

0 1236 '+0

.5 2166 81

.5 1747 68 8 1772 60

16 2200 81 16 1770 67

24 2049 83 24 1721 67 42 17.53 47

n/s. 290.5 132 n/s. 2267 94

19 1840 68 n/s. 1812 .50

Page 92: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE 5.1 (Cont'd)

Operating and Unit Unit

Capital Maintenance Fuel Transmission Capital Operating Option Capacity Cost Cost Cost Cost Cost Cost

(MW) ($M) ($M/yr) ($/GJ) ($M) ($/kW) ($/kW/yr)

OAKLANDS BLACK COAL FIRED OPTIONS (Note 4) (Note 5) (Note 6)

Oak1ands 1400 1277 33 0.8-1.0 ) 187-249 1046-1090 24 2800 2300 57 0.8-1.0 ) 888- 910 20

<.n (1400 MW to ~ Victoria)

Yarrawonga 1400 1430 34 1.1-1.3 219 1178 24

NATURAL GAS FIRED OPTIONS (Note 7) (Note 8)

Gas Turbine 500 274 5 2-3 5 558 10 1000 497 10 2-3 7 504 10 2000 (No separate estimate)

Combined Cycle 500 (No separate estimate) 1000 889 8 2-3 7 896 8 2000 (No separate estimate)

Steam Cycle 500 (No separate estimate) 1000 1034 13 2-3 8 1042 13

Page 93: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE .5.1 (Cont'd.)

Operating and Unit Unit

Capital Maintenance Fuel Transmission Capital Operating Option Capacity Cost Cost Cost Cost Cost Cost

(MW) ($M) ($M/yr) ($/GJ) ($M) ($/kW) ($/kW/yr)

HYDRO-ELECTRIC OPTIONS

Kiewa (extension) 120(150 GWh) 228 0.1 0 n/s. 1900 0.8 200 (330 G Wh) 542 0.4 0 n/s. 2710 2

U'1 McAlister 40( 60 GWh) (Not estimated - total costs similar to 120 MW Kiewa Scheme) U'1

Mitchell 55( 80 GWh) (Not estimated - total costs similar to 120 MW Kiewa Scheme)

Mitta Mitta 20( 40 GWh) (Not estimated - total costs similar to 120 MW Kiewa Scheme) 40( 80 GWh) (Not estimated - total costs similar to 120 MW Kiewa Scheme)

Rub icon 0(12-16 GWh) > 100 n/s. 0 n/s. n/a. n/a. (re-development} 31 (12-16 GWh) c. 250 n/s. 0 n/s. c. 8000 n/a.

PUMPED STORAGE OPTIONS

Victorian 500MW n/s. n/s. n/a. n/s. > 1000 n/a. (e.g. Trawool} (30- 40 hours)

Yarrangobilly lOOOMW ( 10 days)

n/s. n/s. n/a. n/s. c. 1500 n/a.

Page 94: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

(J'l

0"1

TABLE .5.1 (Cont'd)

NOTES: n/s. = not stated; n/a. = not applicable.

1. Operating and maintenance costs for brown coal options include the cost of auxiliary fuel and an effective 'fuel cost' component for open cut operations. These costs would vary depending on the utilisation of the station. Operating costs would also vary depending on the status of other power stations supplied from the same open cut. Figures shown are for base load operation and are lifetime averages assuming eventual retirement of existing stations sharing open cuts.

2. Fuel costs for brown coal fired options are not available as separate items. The open cut operating and capital costs are included in the individual power stations costs.

3. Spare Latrobe Valley-Melbourne transmission capacity exists to accommodate a further 1000 MW of generation after Loy Yang B Units 1 &: 2. Transmission increments costing $.50M-80M would probably be required to accommodate a subsequent Latrobe Valley option. However, this cannot be attributed to a particular option independently of its sequencing. The costs shown are for connection of each brown coal option to the Latrobe Valley end of transmission system.

11.

.5.

6.

7.

&.

9.

to.

Black coal option operating costs do not include transmission maintenance costs, coal costs, or the cost of auxiliary fuel.

Black coal fuel price ranges include auxiliary fuel (e.g. oil or gas) costs. The ranges shown are equivalent to $111/t-$17/t and S20/t-$23/t coal prices at Oaklands and Yarrawonga respectively.

Transmission from Oaklands or Yarrawonga for a Victorian supply of 1400 MW could be at 330 kV or .500 kV. The range of Oaklands transmission costs is for both voltages while the Yarrawonga figure is for .500 kV transmission.

Gas turbine and combined cycle operating and maintenance costs would vary considerably with load factor. Figures shown are for moderate utilisation.

Transmission costs for gas options assume that sites would be adjacent to existing main transmission facilities.

All costs are expressed at June 1986 price levels.

Source: SECV and CRA submissions and supporting documents.

Page 95: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE .5.2

Option

LARGE SCALE SUPPLY OPTIONS

WORKFORCE REQUIREMENTS

Construe- Construe- Peak tion tion Construction

Capacity Period Worker Employment (MW) (years) Years

(Note l)

LA TROBE VALLEY BROWN COAL FIRED OPTIONS

(Note 2) Loy Y ang open cut

- Loy Yang B Units 3 & 4 1000 5+3 5015 1100

Morwell open cut

- Haze1wood Sth. 700 7+3 4490 950 1000 7+3 5385 1200 2000 (Not estimated)

- Morwell Siding 700 7+3 4490 950 1000 7+3 5385 1200

Y allourn open cut

- Yallourn F 750 7+3 4450 950 1000 7+3 5435 1200 2000 (Not estimated)

- Yallourn C/D re-development 220 n/s. n/s. 500

320 n/s. n/s. 600

Driffield 2000 (Not estimated) 4000 9+7 22450 2800

OAKLANDS BLACK COAL FIRED OPTIONS

Oaldands 1400 (Not estimated) 2800 5+5 9460 1840

(1400 to Victoria)

Yarrawonga 1400 7+2 6000 1600

57

Operations Workforce

(Note 2)

624

800-ll60 800-1220

800-1160 800-1220

800-1230 800-1300

600-900 600-900

3050

665

350

Page 96: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE .5.2 (Cont'd.)

Construe- Construe- Peak tion tion Construction Operations

Option Capacity Period Worker Employment Workforce (MW) (years) Years

NATURAL GAS FIRED OPTIONS (Note 3)

Gas Turbines .500 1. .5+ • .5 n/s. 400 18 1000 1..5+ n/s. 400-600 26 2000 (Not estimated)

Combined Cycle .500 (Not estimated) 1000 3+ n/s. 600-900 47 2000 (Not estimated)

Steam Cycle .500 (Not estimated) 1000 .5+ n/s. n/s. 200

(n/s. = not stated)

Notes:

1. Construction period expressed as years before first operation of first unit + years after first operation of first unit.

2. Construction and operations workforces for brown coal fired options include additional workforce numbers in existing open cuts, and would vary with the status of existing power stations fed from shared open cuts. Construction and operations workforces for black coal fired options do not include mine personnel.

3. Data not available for length of construction period after first operation of first unit for gas fired options.

4. Source: SECV and CRA submissions and supporting documents. (Driffield data from 1981 EES.)

.58

Page 97: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE 5.3

RELIABILITY AND ENERGY EFFICIENCY OF DIFFERENT TYPES

OF LARGE SCALE SUPPLY OPTIONS

Reliability (Available Energy Used in

Types of Capacity Efficiency Station Option Factor) (Thermal) Losses

% % %

Latrobe Valley

Brown Coal Fired 75 32-34 8

Oaklands

Black Coal Fired 80 36 6

Gas Fired

- Gas Turbines 85 30 0.5

- Combined Cycle 85 42 1.5

- Steam Cycle 85 39 5

Hydro-electric 95-99 n/a. 0

Pumped Storage 90 (Note 1) 0

Notes: 1. Overall efficiency of pumping and hydro-generation cycle is about 60-70%.

2. Source: SECV and CRA submissions and supporting documents.

59

Page 98: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

.5.6 Reliability and Energy Efficiency of Options

The various types of large scale supply option considered by the Inquiry have

inherent differences in reliability and energy efficiency. Table 5.3 shows the

expected reliability and efficiency of each type of option, according to the

following definitions:

Reliability

This has been expressed as the available capacity factor

achievable by each type of option. The available capacity factor

is the ratio of the maximum energy that could be generated in a

given period by a particular option, allowing for scheduled

maintenance and unscheduled breakdowns, to the total energy

that would be generated in the same period if the option operated

continuously at its rated capacity with no breakdowns and no

stoppages for maintenance. It should be noted that energy

production from hydro-electric plant is not limited by reliability,

but by the availability of water. This is not taken into account in

the calculation of available capacity factor.

Energy Efficiency

This is the ratio of the electrical energy generated to the heating

energy input as fuel (for coal fired and gas fired stations).

Used in Station Losses

This is the proportion of rated electrical output lost in operating

power station auxiliary equipment. Both available capacity factor

and energy efficiency for each type of option are given in terms

of the total electrical energy generated, but the actual energy

available to the system is reduced by power station losses.

60

Page 99: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

5.7 Environmental Impacts Common to Large Scale

Power Supply Options

All large scale electricity generation options have significant environmental

impacts. The major impacts of the options presented to this Inquiry are first

discussed in terms of features common to each type of option, then specific

issues raised by individual options are examined.

Coal Fired Options

Brown coal and black coal fired power stations are essentially similar in

terms of their environmental impacts. Combustion of coal in power station

boilers produces large quantities of exhaust gases including particulates (ash

and dust) and acid-forming gases such as oxides of sulphur and nitrogen.

Australian environmental protection authorities generally apply strict limits

to these particulate and oxide emissions and require the installation of such

equipment as is necessary to reduce emissions to the limits imposed. The

costs of emission control measures are reflected in the capital and operating

cost estimates for the coal fired options presented to the Inquiry. Australian

coals are considerably lower in sulphur content than overseas coals and "acid

rain" has not been a problem associated with coal fired power generation in

this country. Nevertheless, the possibility of its occurrence should be

reviewed during environmental impact assessment of future coal fired

stations.

Coal combustion also generates large quantities of carbon dioxide which is

recognised as a major contributor to the "greenhouse effect". However,

there are no controls world-wide on carbon dioxide emissions and, as

discussed in Chapter 3, scientific debate continues on the implications of the

greenhouse effect. If it becomes necessary or desirable to limit such

emissions in future, it seems probable that energy conservation and

renewable energy sources will increase in value.

Steam cycle power stations must reject large quantities of low grade heat to

the environment and generally depend on a cooling water system to do so.

Where large quantities of water are readily ayailable (e.g. at coastal sites) a

"once through" cooling circuit is used, but where water supply is more limited

61

Page 100: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

and expensive, a recirculating system and evaporative cooling towers are

used. Where water supplies are even more limited (South Africa is an

example} higher cost "dry cooling" is an option, but one which so far has not

been used in Australia. Again, the capital and operating costs of water

supply and the cooling system are incorporated in the estimates for the

options presented to the Inquiry. Nevertheless, cooling systems for different

options will have differing effects on the environment, both through

consumption of water from stream or groundwater systems and through

disposal of cooling "purge" water.

Open cut coal mines occupy large areas of land and require the storage of

correspondingly large quantities of overburden, particularly during their early

years of development. Their land use and visual impacts are significant on a

regional basis. Water management in open cut mining is essential to avoid

far reaching environmental effects. On this basis, there is some presumption

in favour of maximising the use of existing open cut mines before developing

new mines as fuel sources.

Disposal of ash from coal combustion can present environmental problems if

not properly handled. However, there are not expected to be difficulties with

the options before this Inquiry.

The visual impacts of large coal fired power stations are unavoidable but the

extent of the impact is a function of each site's relationship to the

surrounding landscape and communities. None of the options presented to

this Inquiry is considered inappropriate on this basis. Similar considerations

apply to noise impacts.

Natural Gas Fired Options

Natural gas is generally regarded as the cleanest-burning fossil fuel and gas

fired power stations present fewer environmental difficulties than other

forms of thermal power generation. As with all fossil fuels, large quantities

of carbon dioxide are produced. However, the quantities of carbon dioxide

are considerably less than those produced by burning an equivalent amount of

brown coal. Some emissions, in particular oxides of nitrogen, may need to be

limited by control measures such as water or steam injection.

62

Page 101: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Combined cycle and steam cycle plants would require significant quantities

of cooling water and the disposal of saline cooling tower purge and boiler

water. The associated environmental impacts would be similar in nature to,

but smaller in magnitude than those of coal fired stations. Visual impacts

would be greatly reduced in the case of gas turbine and combined cycle plants

due to smaller size and height but similar to coal fired stations in the case of

steam cycle plant. Noise impacts would also be reduced relative to coal fired

stations.

Hydro-electric and Pumped Storage Options

The major environmental impacts of hydro-electric and pumped storage

options are due to the size of the water storages required and the disruption

to river systems caused by their construction and operation. Where options

could be located at existing water storages, these impacts would be greatly

reduced. As net consumers of energy, pumped storage schemes would also

result indirectly in the consumption of additional fossil fuels •

.5.8 Environmental Impacts of Individual Options

In thi$ section, specific environmental impacts of individual power supply

options are considered, where these are likely to require special control

measures or raise issues bearing on project selection.

Latrobe Valley Brown Coal Fired Options

The environmental impacts of Loy Yang B Units 3 & I+ have already been the

subject of formal public review prior to the entire Loy Yang project being

approved by Parliament in 1976. However, the Committee notes that there

have been some environmental problems with the Loy Yang project to date;

in particular surface water discharges have affected Traralgon Creek. More

attention to controlling these problems would enable Loy Yang B Units 3 & 4

to be constructed and operated within the approved discharge limits.

The Y allourn F options would require the opening of the Maryvale open cut

north of Morwell. Even in the absence of further development at Yallourn,

63

Page 102: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

the Maryvale field may be opened after about 2005 to provide coal for the

extension of the life of the existing Yallourn W station beyond 30 years.

Other coal supply options might be feasible (but probably more costly) for

this life extension. As noted above, the environmental impacts of open cut

coal mines are considerable. Attention would also have to be given to the

noise and visual impacts of a Yallourn F station due to the proximity of

Yallourn North township, to discharge of effluents (including cooling tower

purge water) to the Latrobe River, and to buffer zones separating the

Maryvale mine from the Morwell township and Australian Paper

Manufacturers' Maryvale Mill.

Options based on Morwell open cut would not require the immediate

development of further open cut coal mines, but could be limited to 1000 MW

by the exhaustion of economically winnable coal in the Morwell open cut,

particularly if the life of Hazelwood Power Station is extended.

Alternatively, a 2000 MW development at Hazelwood South would probably

require coal supply from a new open cut mine in the later part of its lifetime.

A Driffield Power Station would involve the development of a new open cut

mine west of the Morwell River, as well as extensive flood control works on

surrounding streams. A 4000 MW development at Driffield would eventually

require a major diversion of the Morwell River. (See the 1981 Driffield

Environmental Effects Statement and the 1983 NREC Report on the Morwell

River Diversion.)

As a final point the first 1000 MW of new plant constructed in the Latrobe

Valley after Loy Yang B Units 1 &: 2 can be accommodated without any

augmentation of the high voltage transmission system between the Valley and

Melbourne. Increases in the Latrobe Valley generating capacity beyond this

initial 1000 MW will require augmentation of this system, and this in turn will

require transmission works within the outer Melbourne metropolitan region,

possibly including the construction of new 500,000 volt overhead transmission

lines. These transmission lines would have visual and land use impacts and

significant community concern might be expected. Prior to any new high

voltage transmission lines being constructed between the Latrobe Valley and

Melbourne, a further public evaluation of the long term development of the

total high voltage transmission system should occur.

64

Page 103: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Oaklands and Yarrawonga

Oaklands would involve establishment of a large scale open cut coal mine and

power station in a rural area. Careful research and evaluation will be

required to ensure that acceptable environmental impacts are achieved. A

particular area of concern is that of water supply and disposal. CRA's

feasibility study proposes a relatively novel method of water management

with the supply being groundwater from mine dewatering and a dedicated

borefield, and disposal of excess mine water and cooling tower purge water

via re-injection to a saline aquifer. Studies of this proposed scheme by CRA

consultants and the NSW Department of Water Resources are continuing.

Water supply and disposal would also be a major environmental factor at

Yarrawonga. Coal supply to Yarrawonga by rail from Oaklands would involve

transportation of approximately 2,500,000 tonnes of coal per year on the

Oaklands-Yarrawonga rail line. Currently the line carries around

200,000 tonnes of grain annually. An increase in rail traffic of this

magnitude would have significant impacts, particularly as the railway line

passes through built up areas of Mulwala and Yarrawonga.

Oaklands or Yarrawonga Power Stations would transmit electricity to the

Victorian grid via new 330,000 volt or 500,000 volt power lines. No definite

routes have been proposed in evidence, but the new lines would probably

terminate at one of the SECV terminal stations north or west of Melbourne

and could cause alterations to the present outer metropolitan transmission

network. Transmission line routes and consequential environmental impacts

would have to be considered in a decision to take supply from Oaklands or

proceed with a Yarrawonga project. However, the deferment of Latrobe

Valley to Melbourne transmission works allowed by supply from Oaklands or

Yarrawonga would have environmental advantages.

65

Page 104: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Natural Gas Fired Options

The environmental impacts of gas fired power stations would be site specific.

Of the notional locations used by SECV, those near the Melbourne

metropolitan area would require more stringent environmental controls on

exhaust and noise emission and visual impacts due to the higher population

densities. Steam cycle and combined cycle options would be more difficult to

locate than gas turbines due to their cooling water requirements.

It is possible that the alternatives of siting a gas fired power station in the

Latrobe Valley, close to Melbourne or in the Geelong region could have

significantly different effects on the future need for additional high voltage

transmission lines, both between the Latrobe Valley and Melbourne and

through the outer suburbs of Melbourne. This will need to be considered when

selecting the most appropriate site for gas fired options.

Hydro-electric and Pumped Storage Options

The larger hydro-electric options identified by SECV would all require new

dams and storages and have significant environmental impacts as a

consequence. Schemes involving extension or redevelopment of existing

works might be considered to have slightly less serious impacts since

infrastructure such as transmission and construction access is generally in

place and the environment is already affected by existing hydro-electric

generation.

A new Victorian pumped storage scheme (e.g. Trawool) would involve

construction of large storages and have associated environmental impacts.

The Yarrangobilly scheme would use existing storages but require extensive

tunnelling with requirements for construction access and waste disposal.

Pumped storage schemes would cause high rates of water level change in

associated reservoirs which could have important physical and biological

impacts.

66

Page 105: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

5.9 Preliminary Discussion of Options

As pointed out in Chapter 2, economic electricity generation requires an

appropriate mix of plant types, and the impacts of supply options and the

sequencing of their development should be considered from a wider

perspective than that of the supply system alone. For these reasons, it is not

appropriate to draw firm conclusions on supply strategies simply by

comparison of individual options. Nevertheless, some limited conclusions can

be drawn at this level.

Brown Coal Fired Options

It is evident that Loy Yang B Units 3 & 4 is the most attractive of these

options on cost grounds, as shown by its unit capital and operating costs

which are less than three quarters of any other brown coal fired option. This

option also has a shorter lead time and probably fewer environmental impacts

than any other brown coal fired option. These advantages are reflections of

the fact that Loy Yang was originally conceived as an eight unit development

and SECV has already constructed substantial project infrastructure to

support eight units.

Economies of scale in unit size lead to 2 x 500 MW options at existing open

cuts having unit capital costs over 20% lower than 2 x 350 MW and

2 x 375 MW developments or redevelopment of Yallourn C/D stations.

Operating costs would be similarly reduced. 4 x 500 MW options offer no

further capital savings per MW when compared with the 2 x 500 MW options,

but operating cost economies would occur, particularly at Yallourn F.

Arguments in favour of brown coal unit sizes smaller than 500 MW have been

raised in the past on the grounds of lower risk of over-capacity or

under-capacity and a more stable construction employment situation due to

closer timing of smaller units. Loy Yang A can be pointed to as a project

where an initially high rate of development has now given way to a decline in

construction employment, and resulted in current excess supply capacity.

However, the evidence presented shows that in addition to substantialJy

higher costs, smaller units have construction lead times no shorter than those

67

Page 106: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

of large units and so would be subject to similar risks of over- or

under-capacity, given that the same total capacity would be committed for

construction in a given period. A better way to reduce risks is to commit to

smaller projects (e.g. 2 x 500 MW or 4 x 500 MW rather than 8 x 500 MW) and

programme construction flexibly.

From an environmental point of view, neither Loy Yang B Units 3 & 4 nor

Morwell options would require opening of a new open cut, whereas Yallourn F

and Driffield options would require immediate opening of new open cuts.

However, this aspect cannot be fully considered by comparing individual

options because open cut developments will also be affected by the

retirement or life extension of existing stations.

Oaklands Black Coal Fired Options

A 2800 MW (4 x 700 MW) power station at Oaklands would have significant

capital and operating cost advantages over 1400 MW options at either

Oaklands or Yarrawonga. The Yarrawonga option would be further penalised

by higher fuel costs due to the cost of transporting coal by rail. However,

the involvement or non-involvement of New South Wales in an Oaklands

project would be an important factor in determining which of these options

might be available to Victoria.

The unit capital and operating costs of black coal fired options are

significantly lower than those of brown coal fired stations. This is partially

a reflection of the lower moisture and higher energy content of black coal,

which reduces the size and complexity of the boilers and associated

equipment required for a given power output. However, fuel costs must also

be taken into account in comparing the costs of brown coal based and black

coal based generation.

Natural Gas Fired Options

Gas turbines have the lowest capital cost per unit of electrical output for any

of the options presented to the Inquiry. Combined cycle plant has a higher

unit capital cost, but operates more efficiently by converting heat from

68

Page 107: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

gas turbine exhaust gases to electrical energy. Steam cycle plant is more

costly than combined cycle plant, less flexible in operation and construction

timing, and less fuel efficient. Further consideration of gas fired generation

should therefore be limited to gas turbine or combined cycle plant.

The short construction lead time of gas fired options, as well as their

flexibility of location and operation are also strategic advantages. However,

natural gas is usually a more expensive fuel than brown or black coal.

Hydro-electric Options

SECV's investigations of larger hydro-electric schemes were only

preliminary, but on the evidence presented to the Inquiry, none of the

identified schemes appears attractive on either economic or environmental

grounds. The high capital costs of dams, tunnels and aqueducts result in

effective energy costs many times higher for these schemes than for

generation from natural gas or coal. Each scheme (except redevelopment of

Rubicon) would involve extensive civil works within or adjacent to National

or State parks or proposed park extensions. With access to over 1500 MW of

existing hydro-electric capacity, the Victorian system would gain little

additional operational flexibility from installation of further hydro

generation.

The lower capacity extension of the existing Kiewa scheme, which would

involve a new water storage on the Pretty Valley branch of the East Kiewa

River, below the McKay Creek Power Station, new tunnels, and a new power

station upstream of Lake Guy, appears to be the most cost effective of the

identified options, but still quite uncompetitive in comparison with low

capacity factor operation of gas turbines. The other schemes identified

would produce more costly energy and would probably have less acceptable

environmental effects.

These larger hydro-electric options should not be further considered for

implementation in the decade beyond the mid-1990's, unless it can be

demonstrated that they would have significant economic advantages not

69

Page 108: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

evident in the information provided to this Inquiry, and that their

environmental impacts would be acceptable given the size of any such

advantages.

Pumped Storage Options

Evidence provided by SECV on the possible role of large pumped storage

developments argued that the relatively high capital cost of this technology,

long construction lead times and its dependence on the availability of

significant quantities of low fuel cost generation during off-peak periods

made any potential financial benefit smaJI and uncertain. The financial

attractiveness of pumped storage schemes depends on substantial differences

between average peak and off-peak loads and on the relative costs of base

load and peak load generation. The Victorian system has relatively small

variations in the ratio of peak to off-peak load (i.e. a relatively high system

load factor) compared to, say, NSW, and SECV is undertaking tariff and

demand management measures aimed at improving or maintaining this

situation. Natural gas generation is a relatively inexpensive form of peak

electricity generation in comparison with the options available in systems

which do not have access to substantial gas reserves.

Several submissions to the Inquiry criticised SECV's arguments on the grounds

that SECV had not thoroughly investigated possibilities for lower cost pumped

storage developments (possibly using existing large reservoirs for lower

storage, or as part of multi-purpose water resource developments), that

SECV had not conducted up-to-date system simulation studies to evaluate

the impact of additional pumped storage on system costs and reliability, and

that the relatively low cost of gas fired peak generation is a temporary

situation.

Further information is required before pumped storage can be categorically

ruled out as a medium term supply option. In particular, it should be

established that there are no feasible, environmentaJly acceptable, lower cost

pumped storage options based on existing storages, and that the basis used by

SECV to assess the value of pumped storage in terms of system costs and

reliability is valid given the current and expected future plant/load mix.

70

Page 109: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

.5.10 Cost of Delivered Power from Selected Options

On the basis of the cost estimates summarised in this chapter, the

Committee's research staff has derived a "Cost of Power Delivered to

Melbourne" index for a representative set of options. This index takes into

account the level and distribution in time of capital, transmission, and

operating costs, fuel prices and transmission losses, and is presented over a

range of capacity factors for four options in Figure 5.4. Supporting data is

provided in Appendix 7.

The results indicate that gas turbine options would have cost advantages at

lower capacity factor (peak/intermediate load) operation. Oaklands (half

share of 2800 MW) and Loy Yang B Units 3 & 4 exhibit similar costs over a

range of load factors and appear more economic than other options at high

capacity factor (base load) operation. Brown coal fired options other than

Loy Yang B Units 3 & 4, represented by Hazelwood South (2 x 500 MW) are

signficantly more costly than either Oaklands or Loy Yang B Units 3 & 4 •

.5.11 Conclusions

On the basis of initial economic comparison, there could be a role in the

future development of the Victorian electricity system for large scale supply

options based on brown coal, black coal and natural gas. A more detailed

analysis than that provided in this chapter is required to resolve decisively

the possible roles for and appropriate sequencing of these options. Additional

large hydro-electric developments and pumped storage schemes appear

unlikely to be economically attractive in the decade beyond the mid- I 990's,

particularly when environmental impacts are considered. However, some

limited further review of pumped storage options is seen to be warranted.

Interstate contract supplies, particularly from NSW, could have a role which

has not been addressed here, but is discussed in Chapter 12.

71

Page 110: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

c w ~ w > ::J w c ~.c w~ ~X O' a..O u. 0 1-(/)

0 0

FIGURE 5.4 COST OF POWER DELIVERED TO MELBOURNE VERSUS CAPACITY FACTOR FOR REPRESENTATIVE OPTIONS

8

7

6

5

4

3

LOT YaneB Units:J & 4

I /

HIJJ!JSJwood Sorztb.

CIIJs t:arbines

Disootmt rate 8%

20 30 40 50 60 CAPACITY FACTOR (%)

72

70 80

Fual cost

$3/SJ

$2/SJ

$17/t

$14/t

Page 111: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

It is apparent from comparisons of the kind in Figure 5.4 that future brown

coal fired options after Loy Yang B Units 3 & 4 suffer significant cost

disadvantages in comparison with black coal fired generation. This is a

matter of some strategic importance to Victoria, given its large reserves of

brown coal and paucity of black coal, and should be considered in light of the

State's economic strategy.

It is also apparent from the discussion in Section 5.8 that the eventual need

for, and location of, additional high voltage transmission lines will be

considerably affected by the mix and sequence of future power supply

options. Future review processes will need to consider these implications in

more detail •

.5.12 Specific Recommendations

Prior to any new high voltage transmission lines being constructed, a

further public evaluation of the long-term development of the

Victorian high voltage transmission system should occur. This

should be integrated with a review of the alternative demand and

supply side options and sequences available at that time, together

with consideration of environmental, health and safety issues.

(Recommendation 36)

SECV should carry out a further review of the possibility that

pumped storage options could be developed in association with

existing storages, in particular the Thomson and Dartmouth

Reservoirs. If feasible sites are identified, the capital costs of

their development should be estimated by expert feasibility studies

and they should be subjected to economic and environmental

evaluation. This evaluation should be carried out in a manner

similar to the evaluations of other major supply options presented to

this inquiry so that the value attributed to pumped storage in terms

of system costs and reliability is demonstrably valid given the

current and expected future plant mix and load profile.

(Recommendation 19)

73

Page 112: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 113: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER SIX

SMALL SCALE SUPPLY OPTIONS

6.1 Introduction

This chapter discusses possible roles for small scale supply options in the

Victorian electricity system, outlines some of the relevant technologies and

opportunities for their implementation, and considers the place of small scale

options in supply planning strategies.

The supply options and technologies discussed in this chapter are classified as

small scale for either economic or technical reasons. Opportunities for

implementation of some options, such as smal.l hydro-electric generators, are

limited by the availability of sites and primary energy sources. Other forms

of generation, such as wind or solar power, could be developed on a large

scale either as central generating facilities or at many distributed sites (e.g.

households), but only at costs which are currently substantially higher than

those of the large scale options described in the previous chapter. This is not

to say that the relative costs of gene,rating technologies will necessarily

remain fixed and that the present economic distinction between large scale

and small scale options will be appropriate for all time.

6.2 Roles for Small Scale Supply Options

Despite being uneconomic for bulk power supply purposes in the short term,

small scale supply options can currently be considered for certain specialised

roles in the electricity supply system. These roles are discussed below under

the general headings of the efficient use of energy and capital resources, and

remote/isolated supplies.

Efficient Use of Energy and Capital Resources

There is a potentially large number of opportunities for generating electricity

on a limited scale as part of another productive process, or at sites where a

75

Page 114: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

particularly favourable combination of resources exists. Generation of

electricity in these circumstances for supply to the grid (or to replace energy

that would otherwise be consumed from the grid) may enable an overall

improvement in society's use of energy or capital resources, in comparison

with a situation where all electricity is generated at large scale facilities

dedicated to this single purpose.

Cogeneration, the joint production of heat and electricity where both are

required for some commercial or industrial activity, is a well known example

of such an opportunity. Others would include small scale hydro-electric

generation at existing water supply storages, or the installation of a wind

generator at a particularly windy site.

Remote or Isolated Supplies

There are roles for small scale supply options in areas where connection to

the statewide grid is impractical or highly expensive. Diesel generators are

widely used in such situation, but renewable energy technologies, particularly

solar and wind generation, are becoming more attractive for such supplies as

the technologies develop and their costs decrease.

Some evidence given to the Inquiry indicated that where SECV provides new

connections to remote consumers from its supply system, the overall costs

may be greater than the direct connection costs recovered from the

particular consumer because of additional costs incurred in the overall

distribution network over a period of time. Further subsidisation may also

arise because the higher electricity losses incurred in supplying such

connections are not reflected in SECV tariffs, which are uniform across the

State (in accordance with government policy). In these circumstances, it

could be appropriate for SECV to promote stand alone systems as alternatives

to grid connection in remote areas.

6.3 Small Scale Options and Technologies

In this section, a range of possible small scale supply sources and technologies

are discussed. The range is not intended to be complete, nor the discussion

exhaustive.

76

Page 115: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Cogeneration

There is currently about 300 MW of installed, operating cogeneration

capacity in Victoria (this figure includes 170 MW at the Morwell Power

Station and associated briquette factory). The government and SECV

recently announced an "incentive" scheme to attract up to 150 MW of

additional cogeneration and renewable energy based private electricity

generation into the system under agreements to be signed before June 1988.

Key features of the scheme are revised standby and buy-back tariff

arrangements for generators of up to 10 MW. SECV electricity demand

forecasts allow for additional cogeneration of around 500 G Wh per year by

1995 and around 1000 GWh per year by 2001. There has been considerable

interest in the "incentives'' package and this may indicate that an increased

level of cogeneration may now be economically feasible. The potential for

such an increase should be assessed, following a review of the effects of the

"incentives" scheme and, if appropriate, further restructuring of SECV's

standby and buy-back tariffs should take place.

Emergency and Standby Generators

Modern high rise buildings, telephone exchanges, computer centres and other

facilities. requiring very high levels of eiectricity supply security often have

emergency generating facilities installed to maintain electricity supply in the

event of restrictions or blackouts. In principle, these generators could play a

larger role in electricity supply if they were more readily available for

operation during periods when the electricity generating system was being

stretched to capacity. Such periods can be expected to arise in any

generating system which is not over-capitalised. SECV planning, like that of

all generating authorities, is based on accepting some risk of supply shortage

due to combinations of high demand and plant failures. The basic criterion

for installing new plant on any generating system is to balance this risk

against the cost of providing spare or reserve generating capacity.

If firm arrangements could be made for the operation of emergency

generators during periods of potential energy shortage on the SECV

generating system, then SECV could possibly avoid or defer the installation of

some of its own central generating plant, while still achieving its chosen level

77

Page 116: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

of reliability. At present, no such arrangements exist. The total installed

emergency generating capacity in Victoria is not known, but is probably of

the order of several hundred megawatts. Incorporation of even half of this as

a resource available to the generating system could represent an effective

additional use of capital. that has already been spent and avoid some further

expenditure of SECV capital.

Small Hydro-electric Generators

Recent studies by SECV and the National Energy Research Development and

Demonstration Council (NERDDC) have identified potentially economic,

small hydro-electric generation opportunities (less than 20 MW) at a number

of existing water storages in Victoria. One of these, a 5.6 MW scheme at the

Thomson Dam, is currently being constructed by the Melbourne and

Metropolitan Board of Works. It is understood that other previously

identified schemes have been proposed under the SECV /government

cogeneration "incentive" package described above.

Such schemes would have minimal environmental effects and can be more

cost effective than the large hydro schemes described in the previous

chapter, as there is no need to construct new water storages. Schemes

assessed by SECV as more favourable could produce up to 150 GWh per year

if aU proceeded.

The Alternative Technology Association drew attention to the fact that none

of the studies by SECV or sponsored by NERDDC has examined the possibility

that a large number of relatively small potential hydro projects with output

capacities as low as 50 kW could be developed and be economicaUy viable.

However, the Committee notes that the economic viability of such schemes

is very site specific and normally reqires that the generator site be close to

the electrical load because of the high cost of small scale electricity

transmission.

78

Page 117: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Wind Generation

As noted earlier, wind generation can have a role in remote power supply

applications. Grid-connected wind generation in Victoria has been under

investigation through a joint SECV /V SEC coastal wind monitoring

programme, and a demonstration 60 kW aerogenerator installed at Breamlea,

south of Geelong. While large scale wind generation in Victoria does not

appear to be economic given current costs, development of wind generation

technology is continuing throughout the world particularly where wind based

energy can substitute for energy produced from fuel oils. SECV estimates

that by 1995 wind generation may be contributing up to 3 GWh to the grid. In

the medium to longer term, grid connected wind generation could be one of

Victoria's more promising renewable energy options.

Solar Power

As with wind generation, solar electricity systems have current application in

remote power supplies. Grid connected solar generation is presently further

from being economic than wind power, although extensive development work

around the world is reducing costs. SECV has been involved in a number of

solar research and demonstration projects. Consultants are examining the

feasibility of a 50 kW grid connected solar photovoltaic generating facility

for installation in northern Victoria.

Other Renewable Energy Sources

These include tidal, wave, geothermal, and biomass generating technologies.

In the longer term, limited opportunities may be available for generating

small quantities of electricity economically from wave energy and through

the disposal of solid waste,

The opportunity to exploit either tidal or geothermal energy appear to be

limited by the relative availability of these forms of energy in Victoria.

79

Page 118: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

6.• Supply Planning and Small Scale Options

Individual small scale supply options cannot be meaningfully incorporated in

strategic electricity supply planning. However, it is important that the

collective impacts of possible small scale supplies are adequately assessed,

since these may have some effect on the timing of future large scale plant

additions. For example, an additional 1000 GWh per year of cogenerated

electricity is equivalent to several months' output from a 500 MW base load

unit. Making firm arrangements for the occasional operation of private

emergency generators could lower (on a once-off basis) the amount of new

SECV plant needing to be installed in a given period to maintain a given level

of supply reliability.

With large scale supply options having long lead times, and considerable

uncertainty inherent in future forecasts of electricity demand, it is important

to retain flexibility in supply development programmes to enable adjustments

for the impacts of small scale supply options.

There is a potential dilemma in pursuing both large scale and small scale

options caused by the very different lead times of typical developments.

Once commitment to a large scale option is made, there is some risk that

development of 11too many11 small scale options could lead to expensive

over-capacity when construction of the large scale option is completed. On

the other hand, there are risks that opportunities for potentially economic

small scale options (or for whole classes of options) could be lost if these are

discouraged by the supply authority on relatively short-term considerations.

The governmment and SECV should take a long-term view on this sort of

problem, just as a long-term view is taken on electricity pricing.

For the purposes of this Inquiry, SECV planning has adequately addressed the

current potential of these small scale supply options, except in the area of

access to private emergency generation. However, the opportunities to

utilise cogeneration and private renewable energy based electricity

generation may increase, and the future potential contribution from these

supply sources will have to be carefully reviewed over the next few years.

Maximum economic flexibility in implementation of large scale options will

80

Page 119: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

be important if the less predictable implementation of the smaller scale

options by bodies other than the SECV is to be accommodated.

Organisations and individuals with interests in developing these small-scale

options will, in general, be better placed than SECV to identify, implement

and operate specific opportunities, provided that sufficient information on

SECV buy-back and standby tariffs and connection requirements is available.

However, SECV should continue to encourage the development of these

opportunities through its direct involvement in research and demonstration

projects as well as maintaining a watching brief on overseas developments.

6 • .5 Specific Recommendations

SECV should consider stand alone power supply systems as an

alternative to extending the electricity distribution system into remote

areas. (Recommendation 38)

The Government and SECV should review the effects of the

cogeneration and renewable energy "incentives" package after a

suitable period has elapsed and, if appropriate, further restructure

SECV's standby and buy-back tariffs. (Recommendation 39)

SECV should investigate the possibility of making firm arrangements

for the operation of private emergency and standby generators during

periods of potential energy shortage on the interconnected generating

system. These investigations should consider the possible cost

advantages which might arise from such arrangements through

reduction in SECV reserve plant requirements. (Recommendation lj.Q)

SECV should significantly expand its involvement in research and

demonstration projects related to renewable energy based electricity

generating technologies. (Recommendation lj.l)

81

Page 120: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 121: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

7.1 Introduction

CHAPTER SEVEN

MODELLING AND ANALYSIS OF SUPPLY

SEQUENCE IMPACTS

This Inquiry has been concerned with the assessment of supply options and

sequences for balancing supply and demand following completion of

Loy Yang B Units I &: 2. In reaching a judgement on the overall advantages

and disadvantages of those options or sequences, the Committee has

examined economic, social, financial, environmental and other impacts.

This chapter discusses how participants in the Inquiry have evaluated the

economic, social and financial impacts and brings together the Committee's

observations and conclusions in this area.

7.2 Scenario Modelling

A substantial part of the evidence to this Inquiry concerned itself with future

electricity supply and demand "scenarios". Scenario planning can be

characterised as the evaluation of numerous alternative plans or strategies

under a range of future sets of conditions (e.g. different economic outlooks}

by considering their overall effects during the time period in question. An

alternative to this approach is the traditional "single project" style of

analysis (of which the Driffield Environment Effects Statement is a typical

example in Victorian electricity planning}.

Two significant advantages of the scenario planning approach are:

Its capacity to evaluate strategies or sequences of decisions and

projects through the use of detailed modelling tools; and

Its flexibiJity in assessing a wide range of possible strategies and

assumptions about the future, allowing a better understanding of

factors such as risk and uncertainty.

83

Page 122: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

For example scenario planning has provided the present Inquiry with the

ability to simultaneously consider the role for both new base load and new

peak load plant (e.g. Loy Yang B Units 3 & 4 and gas turbines). While "stand

alone" analysis, which provided the comparative electricity costs illustrated

in Figure 2.2, shows that each of these options is competitive in its

respective role, scenario analysis is able to provide information on the

appropriate mix of base load and peak load capacity and the implications of

different construction sequences and timing.

Scenario planning can be used in a very broad fashion, for example to

consider the implications of very different futures which might range from

high economic and energy demand growth to major recessions or

environmental bans on the construction of new fossil fuel burning power

stations. Some overseas energy organisations currently use scenario planning

this way.

Participants in this Inquiry used a much narrower form of scenario planning,

and concentrated on detailed modelling of the impacts of different sequences

of large scale power supply options under a restricted range of assumptions

about future electricity demand, the economic environment and technological

factors. A list of representative scenarios studied is contained in Appendix 10

and the alternative electricity demand forecasts appear in Figure 2.1.

Figure 7.1 represents in a simplified fashion the common modelling approach

used by SECV, CRA and BHP to support their evidence to the Inquiry on

future supply and demand scenarios. The functions of each of the models

shown are, briefly:

System model - Simulates the development of the electricity

generation system with a forecast demand growth to determine

system reliability, and the expansion plan - the required

magnitude and timing of new supply options and associated works

(e.g. transmission);

84

Page 123: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

plant performanoe

load foreoasts

00 I (J1

sequenoe of regional

~~ly op ions impact 1-- employment. population projeotions

model I I I

I system model

L---- ____j '-Ions run marginal oost

~ generation option costs C 0 S t

FIGURE 7.1

fuel costs I model

eoonomia environment finanoial policies ----;

sales ------;

financial model

SIMPLIFIED DIAGRAM OF SCENARIO MODELLING APPROACH

tariff's

debt

rate of re tarn

Page 124: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Generation cost model - Uses the output of the system model,

and detailed cost data relating to the new supply options and the

existing generating system, to simulate the operation of the

electricity supply system and to determine the total financial or

economic costs involved in expanding and operating the

electricity generation and transmission system under the given

expansion plan;

Regional impact model - (SECV only) Uses the expansion plan,

together with workforce and expenditure data to indicate the

employment-related impacts of power station construction and

operation within regions;

Financial model - Takes the expenditure pattern for generation

and transmission and flows this through a model of the SECV

business and financial structure to estimate the ultimate impacts

on financial indicators including ·electricity tariffs, debt levels

and rate of return on assets.

7.3 Scenario Modelling Outputs and Analysis

The models illustrated in Figure 7.1 and described above produce a

substantial body of data - year by year data on energy produced, fuels

used, workforce employed, capital costs, operating costs, debt levels and

so on. These can be aggregated in meaningful ways to produce indicators

that allow decision makers to comprehend the relative impacts of

alternative scenarios. There is no single indicator that can completely

incorporate all of the data produced and be used to choose a "best"

scenario, because there is no objective definition of "best" - this depends

on the weight given by decision makers to each of the economic, social,

financial, environmental and other factors.

Nevertheless, there are certain more or less standardised analytical

techniques for evaluating economic, financial and social impacts in order

to focus more clearly on the trade-offs between scenarios. A number of

these have been used or recommended by participants in the Inquiry and

are discussed briefly below:

86

Page 125: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Cost Effectiveness Analysis

This concentrates on the direct economic costs, on a discounted cash flow

basis, of meeting a projected electricity demand growth forecast. These

costs include capital, operating and fuel costs for proposed supply options and

changes to the operating and fuel costs of existing plants. The benefits of

meeting the given load forecast are assumed to be equal irrespective of how

the forecast is met, as the best scenario is the one resulting in the minimum

cost on a present worth basis. SECV produced a "long-run marginal cost"

indicator for different scenarios on this basis by dividing the discounted sum

of a11 such additional costs above a base level by the discounted sum of a11

additional energy produced. Such an indicator provides no information on the

different patterns or proportions of capital and operating expenditures

incurred under different scenarios over time. More importantly the overaU

financial position of the SECV itself cannot be assessed. This does not

necessarily invalidate the use of this indicator, but iUustrates the need to

consider such issues in addition to a simple economic indicator like long-run

marginal cost.

Financial Analysis

This seeks to estimate the impacts of a given scenario on the enterprise

implementing it (in this case SFCV) in terms of commonly used financial

indicators, such as electricity prices, debt levels, internal funding ratios and

rates of return. This approach concentrates on the cashf1ows required to

implement the scenario and their interaction with the overaU financial

position of the enterprise. CRA's evidence concentrated heavily on this

form of analysis. Financial analysis provides a more detailed and potentia11y

more realistic interpretation of the business implications of scenarios than

does long-run marginal cost analysis, but does not provide a single

unambiguous indicator of overa11 economic cost. The output of the analysis is

also subject to external assumptions. For example, the analyses presented to

the Inquiry by SECV assumed that electricity prices would fo11ow current

Government policy and that the effects of the different scenarios would be

seen in SECV debt levels. It would have been just as valid to have assumed

that electricity prices should be a11owed to float in order to produce a

particular level of debt, rate of return or internal funding for capital works.

87

Page 126: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Cost Benefit Analysis

Many submissions to the Inquiry pointed out that to concentrate solely on the

costs of implementing scenarios to the electricity supply system, or SECV,

would ignore other important economic and social effects of large scale

power station construction and operation. For example, associated with

different options would be socio-economic costs not necessarily borne by

SECV such as health and education facilities for construction workers, or the

less tangible but real costs of unemployment or relocation. Another

frequently-mentioned possibility was that of "multiplier effects" whereby

power station construction and operation would stimulate economic activity

that would not have otherwise occurred leading to benefits beyond the

production of extra electricity.

Cost benefit analysis is a generic term for evaluation methods that attempt

to incorporate estimates of such costs and benefits into an overall measure of

economic value (e.g. a cost/benefit ratio). Such methods frequently rely on

sophisticated econometric techniques such as shadow pricing in order to

represent external, secondary, or intangible costs and benefits as monetary

values.

The only evidence before the Inquiry to take a step in the direction of

performing (rather than suggesting) this form of analysis was that of the

National Institute of Economic and Industry Research (NIEIR) as consultants

to SECV. NIEIR's analysis used a macro-economic model to estimate the

likely magnitude of multiplier effects, but concluded that it was probable

that these would be negligible from a national perspective. While there

would be multiplier effects at a local level, these would be at the expense of

economic activity elsewhere leading to no net gains in an economic sense.

Thus, potential multiplier effects would not change conclusions drawn on the

basis of cost effectiveness analysis.

This leaves the issue of external and intangible costs and benefits which are

not automatically quantified in economic terms. In the current Inquiry,

examples of such costs would be those associated with changes in regional

employment levels, and possibly some advancement of the depletion of Bass

Strait gas reserves which have alternative uses to power generation. The

88

Page 127: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Committee has preferred to consider such issues directly rather than seek to

integrate them into a technical cost benefit analysis, since there is no

generally accepted and uncontroversial method of doing the latter.

Nevertheless, the Committee strongly supports the identification of all such

costs and benefits as an input to decision making.

Regional Employment and Population Analysis

Scenario modelling by SECV produced estimates of power industry

employment levels in regional areas, particularly the Latrobe Region and the

Oaklands- Yarrawonga area. In conjunction with projections of non-power

industry employment, this allowed some estimation of overall employment

and population trends and the effect on these of alternative scenarios. Large

or rapid fluctuations in employment levels would tend to be associated with

social costs such as regional unemployment or dislocations to social networks

and regional housing land and rental markets. These issues are discussed in

Chapter lJ and in a discussion paper prepared for the Committee by the

Melbourne University School of Environmental Planning.

7.4 Influence of Assumptions

Figure 7.1 did not depict the very large number of individual assumptions and

inputs to each model, nor all the possible linkages between models (for

example, load forecasts would vary according to the economic environment

projected, and would also be affected by tariffs).

Summaries of the major assumptions used are to be found in SECV's "Scenario

Study Results - July 1987", CRA's "Third Evidence - July 1987" and BHP's

"Third Public Submission - October 1987".

Because of the many assumptions required to operate a set of models like

that shown in Figure 7.1, the Committee does not believe that it is desirable

to regard their outputs as definite, or even probable, predictions of the

absolute future position of SECV and of the regions concerned. The value of

the results is for comparison of alternative strategies. Provided that all

assumptions are held constant, the differences between results obtained for

89

Page 128: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

different supply/demand strategies will be valid indicators of the relative

impacts of these strategies.

7.5 Comparison of Results

Table 7.1 provides an indication of the economic and financial results

obtained by SECV and CRA for a representative range of scenarios.

Approximately 150 scenario studies were carried out, some of these are

reported in later chapters of this report and a complete listing is available

from the Committee's offices.

While using the common framework of Figure 7.1 for conducting scenario

studies, SECV, CRA and BHP used different individual models and presented

results in differing terms. Certain basic data were agreed and used by all

three parties including:

Load forecasts (SECV's 1987 forecasts were used);

Capital and operating costs of supply options;

Performance levels and lifetimes of existing plant.

The detailed nature of each of the models used by those making submissions

and their differing information requirements meant that many other

assumptions were not standardised for the scenario studies. Therefore SECV,

CRA and BHP did not present directly comparable results. Furthermore,

SECV's evidence was the only source of quantitative data on the regional

employment effects of alternative sequences, as CRA and BHP evidence on

scenario studies was confined to financial issues.

Despite this, there was agreement on important aspects of the sequences of

supply options studied by the three organisations:

An all brown coal development sequence would lead to the highest

cost of generation and transmission for a wide range of load

growth and interest/discount rates;

90

Page 129: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

<.0 ......

TABLE 7.1 - COMPARISON OF RESULTS FOR SELECTED SCENARIOS

SECV INDICATORS CRA INDICATORS

SCENARIO Long Run Reduction in Present Value Reduction in

Marginal Cost 1999/2000 debt of Total Expenditure 1999/2000 debt level (from -saving on level (from

All Brown Coal) All Brown Coal All Brown Coal) c/kWh $m (19&6) $m (19&6) $m (19&6)

All Brown Coal SECV - 10 5.44 0 0 0 CRA - A2

Oaklands/Loy Yang B3,4 SECV - 30 4.60 1500 1964 1700 CRA - B2

Loy Yang B3,4/0aklands SECV - 31 4.55 1500 1431 1450 CRA - H2

Gas/Brown Coal SECV - 70 4.79 1900 1519 1700 CRA - C2

Gas/Oaklands/Loy Yang B3,4 SECV - 92 4.33 2100 2190 2200 CRA - G2

------ -·-·---~ ----

Page 130: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Sequences including black coal fired and/or gas fired options could

offer significantly lower generation and transmission costs,

particularly through reductions in capital expenditure

requirements. These sequences would offer SECV opportunities to

moderate increases in tariffs and/or debt accumulation and/or to

increase rates of return on assets;

The magnitude of the total cost reductions available over the

period to the year 2000 (as measured by comparative levels of

SECV debt estimated in that year) was in the vicinity of

$1,000-$2,000 million (1986 dollars) for mixed fuel sequences.

This is equivalent to a saving of $300-700 million (1986 dollars) in

1986, using a real discount rate of 896.

There were also some important areas of disagreement, including the

following:

SECV absolute financial position - SECV results indicated that

under the most expensive development sequence (all brown coal),

electricity tariffs could, nevertheless, be reduced in real terms

while debt would not increase in real terms. CRA and BHP

results indicated large real increases in both tariffs and debt

levels for an all brown coal sequence.

The major apparent reason for this difference related to each

party's estimate of future SECV operating costs (exclusive of

finance charges). SECV results were based on continuing real

reductions in this area, while CRA and BHP studies assumed

increasing real operating costs in future years. This is one

example of different modelling assumptions leading to

substantially different results.

Nevertheless, there was broad agreement about the relative

impact of different supply development sequences on SECV's

financial position, as described above.

Page 131: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Sequencing of options - While agreeing on the potential for black

coal and gas fired options to reduce generation and transmission

costs, SECV, CRA and BHP did not agree on the optimum

sequencing of these options. One contentious example was the

relative sequencing of Loy Yang B Units 3 & 4 and Oaklands.

SECV evidence stated that no clear distinction could be drawn on

economic grounds between sequences where these options

appeared in reverse orders, while CRA results indicated a distinct

financial advantage in the case where Oaklands was constructed

first.

The Committee's research staff investigated this matter in

considerable depth and concluded that differences between the

models and assumptions used by CRA and SECV were more than

sufficient to explain the different results. This does not mean

that the order of construction of these two options would have no

economic and financial implications. However, there are still

significant uncertainties about basic data including the capital

and operating costs of both Loy Yang B Units 3 & 4 and Oaklands,

as well as non-financial factors to be taken into account. In these

~ircumstances, the Committee did not consider it worthwhile

attempting to fully reconcile the SECV and CRA models, as it is

probable that no clear conclusion on this issue can be drawn until

the broader uncertainties referred to are resolved.

7.6 SECV Debt Level

A further issue to be considered is that of different interpretations of, or

emphases placed on, similar results by the parties undertaking scenario

modelling. An important example. is the question of relative SECV debt

levels. By any yardstick, SECV is currently experiencing a high level of

debt. This means that the differing capital expenditures involved in different

sequences of generating options, and the implications for SECV borrowing

requirements are important, since a high level of debt exposes an

organisation like SECV to financial risk in the event of increases in interest

rates or downturns in sales (which are likely to occur in tandem).

93

Page 132: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

SECV's long-run marginal cost indicator abstracts from the question of the

relative levels of capital and operating expenditure required to implement

different sequences of generating options. High capital cost, low operating

cost sequences may show the same long-run marginal cost as lower capital

cost, higher operating cost sequences. However, there are important

differences between such expenditure patterns, since a higher capital cost

sequence would involve earlier commitment of funds, higher initial debt

levels, and greater exposure to financial risks if economic circumstances

deteriorate after investment decisions are made. Lower capital cost

sequences may provide greater opportunity to reduce operating costs in an

adverse financial and business climate. A further consideration is the

tendency of Commonwealth governments to restrict access by State public

authorities to capital markets during times of economic restraint.

SECV's evidence concentrated on the long-run marginal cost of scenarios as

the major economic criterion for choice. This was illustrated in the

following quotation from its Part Ill Evidence document:

.... debt is not regarded as a primary issue separable from either the SEC's cost reduction or the longer-term macro-economic cost to the whole economy Wlder the balance of payments constraint.

However, where long run marginal costs are not significantly different between alternative sequences, debt considerations including State and national co,1Straints on borrowing may be the determining factor.

{emphasis added)

On the other hand, CRA emphasised the issue of SECV debt throughout the

Inquiry and argued that the lower unit capital cost of the Oaklands project

{relative to other coal-fired options) had advantages beyond those revealed

by a long-run cost analysis.

The level of SECV debt is not inseparable from long-run marginal cost, given

the SECV's current stock of debt and the financial risks associated with high

debt levels in an uncertain economic environment. Consideration of

predicted debt levels in the various scenarios reinforces the attractiveness of

mixed fuel supply development sequences.

94

Page 133: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

7.7 Discount Rates

A number of submissions raised the issue of the discount rate used in

economic and financial analysis of scenarios. A discount rate is used in

comparing costs and benefits which wiU accrue at different times in the

future, by reducing future costs or benefits to present day equivalents. The

further into the future a cost or benefit is expected to occur, the smaUer wiU

be its discounted present day equivalent. High discount rates assign lower

values to future costs or benefits than do low discount rates, and make low

capital cost options more attractive than high capital cost options. The

discount rate is not in general identical with the "real interest rate" used to

calculate the interest charges on borrowed funds in business modeHing

studies.

Professor McCoU's discussion paper "The Economic Framework for

Considering Options for Electricity Supply in Uncertain Environments"

canvasses some of the arguments related to choice of discount rate, which

remain unresolved even at a theoretical level. The Committee has concluded

that a range of discount rates should be used to assess the sensitivity of

results to this factor, and notes that the broad conclusions drawn in

Chapte~ 13 from the evidence to this Inquiry are not affected by the use of

discount rates as low as 496 or ashigh as 1296.

7.8 Comments on Scenario Modelling

The Committee considers that the scenario modelling undertaken for this

Inquiry has served a number of useful purposes, not the least of which has

been to ensure that a wider range of issues has been considered, if not

resolved, within an analytical framework. This process has been assisted by

several of those giving evidence using scenario modelling to illustrate their

arguments. The Committee hopes that this approach to planning will

continue to be developed and offers the folJowing comments on scenario

modeHing as suggestions for that development:

Demand Side Measures and Integrated Planning - In Chapter 3,

the Committee has drawn attention to the importance of further

development of demand side measures and energy conservation,

95

Page 134: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

and has recommended an extension of the Inquiry to consider this

area in more detail. A major improvement to SECV's scenario

modelling approach would be the ability to consider demand side

and supply side options on a consistent basis. This would assist in

the development of integrated demand side and supply side plans

using the least cost criterion favoured by the Committee.

Broadening of assumptions While the scenarios studied

incorporated a range of electricity demand forecasts and the

presence or absence of demand side targets, a broader range of

forecasts should be considered. Zero growth or high growth

scenarios could occur and their study would shed light on the

contingency measures available to SECV, while more detailed

study of scenarios with non-uniform rates of growth would probe

the flexibility and robustness of supply/demand strategies and

aHow better appreciation of risk.

The retirement dates and performance of existing generating

plants are major influences on supply capability and the

implications of variations in this area should be further explored.

Modelling perspective Analysis of projects (or sequences of

projects) from the viewpoint of a proponent organisation, in terms

of its financial position alone, may not provide the same result as

analysis from the point of view of society as a whole. The

presence of taxes and other transfer payments, costs or benefits

accruing to others for which the organisation pays or receives no

financial compensation, and possible distortions in relevant areas

of the rest of the economy can cause such a divergence. The

perspective of the organisation undertaking the analysis can also

lead to the analysis being mis-specified.

For example, SECV treats coal mining costs for brown coal

developments quite differently from those for a black coal

development at Oaklands. For the former, mine capital and

operating costs are included as part of the relevant power project.

96

Page 135: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

In the case of Oaklands, an externally set coal price is used with

no breakdown into capital and operating components. This

different treatment reflects the nature of the ownership and

contractual arrangements expected to prevail, but it is not

relevant for economic analysis from the viewpoint of society as a

whole. It could lead to distortion of comparisons between

Oaklands and brown coal options, particularly when sensitivity to

discount rates is examined. Oaklands could be unduly favoured at

high discount rates and unduly penalised at low rates by SECV's

treatment.

Turning to another area, SECV and CRA have excluded from their

primary analyses some of the costs of "community infrastructure11

for which they would (or might) not be liable to pay. However,

from society's viewpoint, infrastructure in any way associated

with a project represents a real economic cost if it would not

have to be provided (possibly in a different location) if the project

did not proceed. Its cost should then be identified irrespective of

who pays for it. This is done in Chapter 9, where it is shown that

such costs are small relative to the savings in generation costs

arising from the inclusion of the Oaklands plant.

This does not mean that all community infrastructure costs are

relevant to economic evaluation of projects. For example,

although an Oaklands project would require the expenditure of

some tens of millions of dollars on house construction in the

Oaklands region, it would not be appropriate to recognise this as a

cost for evaluation purposes because, if Oaklands did not proceed,

a similar amount would be spent on constructing houses elsewhere

in Australia (e.g. in the Latrobe Valley). Nor is it implied that

project proponents should necessarily be liable for all community

infrastructure costs - the issue of who should pay is separate from

the identification of economic costs for evaluation purposes.

97

Page 136: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Committee believes that SECV should refine its scenario

modelling approach to explicitly identify possible divergences

between analysis from SECV's viewpoint and that from the

viewpoint of society as a whole.

Interstate modelling - In Chapter 12, the Committee discusses

the broader issues related to interstate electricity trade and

planning. It is essential that the scenario modelling approach be

developed to cover the South Eastern States' interconnected

electricity systems on an integrated basis.

Modelling for future Inquiries - It is understood that some recent

overseas Inquiries have specified both the assumptions and the

specific detailed models to be used in analyses submitted as

evidence. This has the benefit that evidence produced by

different parties is directly comparable.

An alternative to this approach is for an Inquiry to call for the

primary data and to carry out all evaluations using expert

independent consultants employing a defined modelling technique.

Consultants having sufficient expertise and not already aligned to

any of the parties involved are not readily available in Australia.

Both options discussed above, whilst apparently simplifying the

Inquiry process, may not challenge all the assumptions.

This Inquiry has been fortunate in that at least two independent

and technically different systems have been used by competing

organisations to model some of the major alternative scenarios.

This has highlighted differences in the results obtained and has led

to productive detailed questioning of the assumptions being made.

It has also placed the value of the conclusions reached as a result

of the modelling exercises into a more realistic perspective than

might otherwise have been the case. This is a technique which

should be promoted in any future Inquiries of this nature.

98

Page 137: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

7.9 Conclusion

Any future Inquiry of this nature should ensure, if possible, that the

major assumptions, techniques and form of output to be used as evidence

are agreed and clearly defined at a very early stage in the Inquiry. It

should also ensure that the more detailed assumptions are chaiJenged

during the Inquiry by analysts using independent and different techniques

to the principal proponent.

99

Page 138: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 139: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER EIGHT

LOY YANG B UNITS 3 &. 4

8.1 Introduction

Many of the submissions made to the Inquiry expressed the opm1on that

immediate approval of Loy Yang B Units 3 & 4 should result from the Inquiry

process. This chapter discusses the issues related to the early approval of

this supply option.

8.2 Construction and Approval Lead Time

Loy Yang B Units 3 & 4 are the final two units of an 8 x 500 MW project

which has already received statutory and environmental approval. The first

four units which form the 'A' Station have been installed, three are

operational and the fourth is currently being commissioned. The final timing

of the fifth and sixth units (Bl and B2) has still to be determined. The site

for the 'B' station has been levelled and basic drainage works are currently

being installed in preparation for the first two units. The open-cut and coal

handling plant, the water and waste water services and most of the other

necessary operational infrastructure have been installed and currently supply

the Loy Yang A Station; these services have the capacity, and were intended,

to supply both the A and B Stations. Therefore, the lead time from contract

and investment approval to operation of the first unit for Loy Yang B

Units 3 & 4 could be limited to five years if the orders placed for boiler

equipment for Loy Yang B Units 1 & 2 were duplicated. However SECV has

indicated that some potential benefit could be gained from calling for further

tenders for the boilers. This could extend the lead time to eight years. The

work required in the first three years would include one year for tender

preparation, evaluation and acceptance, followed by a further two years of

detailed design work to incorporate the latest experience and technological

developments. The point of final investment approval which initiates site

works and boiler manufacture would still be five years ahead of

commissioning Loy Yang B Unit 3.

101

Page 140: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

8 • .3 Earliest Required Service Date

SECV's projections of demand growth and system capability indicated that a

brown coal fired supply option to follow Loy Yang B Unit 2 would be required

for service in May 1996 (under median demand growth) or November 1994 (for

high growth) assuming that no gas or black coal generated supply was

introduced. Therefore, if Loy Yang B Units 3 & 4 were to be the next supply

option after Loy Yang B Units 1 & 2 a decision might be needed in late 1989

to proceed with its construction, should a high demand growth pattern

emerge. Under median growth, commitment to construct would be required

by May 1991. Should the Plant Improvement Programme be totally

successful, both dates could be postponed because the equivalent plant

capacity that can be achieved from the overall programme is of the order of

several hundred megawatts.

8.4 Economics of Sequences with Loy Yang B Units .3 & 4 First

There is no doubt that the substantial investment already in place at the Loy

Yang site makes Loy Yang B Units 3 & 4 the least expensive and most

practicable brown coal option, so it would precede any other brown coal

options if costs are to be minimised.

SECV and other evidence has shown that sequences of power supply options

based on the use of gas, black and brown coal and commencing with either

Loy Yang B Units 3 & 4, gas turbines, or supply from Oaklands, can produce

the lowest long run marginal cost, depending on the precise capital and

operating costs of these options and the negotiated fuel prices. Although

SECV evidence tended to show that it was preferable to proceed with

Loy Yang B Units 3 & 4 before Oaklands, SECV stated that because of the

assumptions built into the economic evaluations it was not possible to

differentiate on financial grounds alone between sequences in which the order

of Oaklands and Loy Yang B Units 3 & 4 was reversed. CRA's evidence tended

to show that it would be more economic to install Oaklands ahead of

Loy Yang B Units 3 & 4. It should be noted that the costs of all these options

(including Loy Yang B Units 3 & 4 capital and operating costs) have changed

at various stages during the Inquiry. It should also be noted that no black

coal or gas price negotiations have occurred and that considerable variation

is possible in these prices.

102

Page 141: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

A sequence with some gas fired capacity programmed for installation before

the next black or brown coal fired capacity could increase flexibility to

handle sudden changes in load growth, reduce SECV debt accumulation in the

short term, and possibly have the lowest long run marginal cost (depending on

the cost of gas).

8.5 Capital and Operating Costs

In October 1987, the Unions and SECV jointly indicated to the Committee

that they intended to reach a further agreement on ways to reduce operating

costs and improve plant availability and that they would present this

agreement to the Committee by the end of 1987. In the February 1988

hearings, the Unions and SECV indicated that initial discussions had been held

but that it would be at least a further six months before any detailed

agreement was finalised. The Committee understands the need for very

thorough discussions on these complex issues. Nevertheless, the Committee

stresses the importance of reaching agreement on these matters before any

final commitment is made to Loy Yang B Units 3 & 4. It is also essential that

an ongoing review of potential capital cost savings be maintained.

8.6 Coal Supply for Loy Yang Power Stations

In the light of comments contained in Chapter 4 of this report, the

Committee is of the opinion that there is a strong possibility that it could

prove economic to extend the lives of the Loy Yang power stations to forty

or even fifty years.

The Government has allocated about 150 million tonnes (Mt) of the good

quality coal from the Loy Yang open cut for the "Coal for Industry

Programme". This was done on the basis that the two Loy Yang power

stations would only have thirty year lives.

In evidence, SECV indicated that, if the lives of the power stations were

extended to forty years and the allocation of coal for industry was taken up,

then coal with a high sodium content would start to be used towards the end

of the power station lives. This might lead to reduced plant availability at

that time as the high sodium coal could cause increased boiler fouling.

103

Page 142: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Consequently, in its Preliminary Report and Draft Recommendations the

Committee indicated that it believed that the Government should review the

long term allocation of coal from the Loy Yang Open Cut.

Evidence given to the February 1988 hearings indicated that current

proposals for use of Loy Yang coal by industry will not significantly affect

the coal supply for Loy Yang power stations. It was also suggested that it

was inappropriate to review the Loy Yang coal situation at this time as this

would introduce a further element of uncertainty into current attempts to

develop brown coal based industries.

The Committee has therefore decided not to make any recommendations on

this matter at this time.

8.7 Latrobe Valley Interests

Evidence from organisations with interests in the Latrobe Valley generally

argued that immediate approval of Loy Yang B Units 3 & 4 is required to

maintain confidence and mitigate damaging effects of uncertainty in the

region.

8.8 Other Socio-economic Effects

The major socio-economic effects of building Loy Yang B Units 3 & 4 will

primarily arise because of the increased workforce required to construct the

power station and the subsequent reduction in the workforce on completion of

the power station. The magnitude of the socio-economic impact will depend

on the overlap with or gap between preceding and following power supply

projects in the Latrobe Valley. It will also depend on the overall level of the

workforce employed on other construction projects in the Valley at that time.

The number of people directly affected by this project will be lower than was

the case in the earlier phases of the Loy Yang project because much of the

project infrastructure now exists. The effects of the influx of construction

workers and their families are also likely to be more manageable because the

community infrastructure was developed to cope with more than this scale of

development during the construction of Loy Yang A.

104

Page 143: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

8.9 Overall Economic Uncertainty

The current economic climate is very uncertain and this may significantly

affect the predicted rate of load growth. In this situation, the Committee

believes that a final commitment to construct Loy Yang B Units 3 & 4 should

be made at the latest possible time thus providing the maximum scope to

adapt to any changes which may occur.

8.10 Conclusions

At this stage, there is no clear economic difference between completion of

the Loy Yang B Units 3 & 4 and proceeding with the Oaklands project.

However, as will be discussed later in this report, Oaklands is best proceeded

with when a coincident need with NSW exists. The Oaklands project has still

to be approved by the NSW Government and joint negotiations between the

two States will be necessary. Loy Yang B Units 3 & 4 is an approved project

and could proceed immediately, although it would appear that there is scope

for further cost reductions.

The Committee has concluded that Loy Yang B Units 3 & 4 should be the next

base load units committed for construction after Loy Yang B Units 1 & 2.

This is further discussed in Chapter 13 and should not be taken to exclude the

possibility that in certain circumstances the construction of Oaklands might

overlap with the construction of Loy Yang B Units 3 & 4.

8.ll Specific Recommendations

The Committee recommends that:

No final commitment to contracts and expenditure to construct

Loy Yang B Units 3 & 4 should be given until the latest time consistent

with maintaining a reliable electricity supply system. Immediately

prior to authorising expenditure on the major plant items, the

Government should ensure that SECV reviews the capital and operating

costs of both Loy Yang B Units 3 & 4 and other viable power supply and

demand side options. This should include a re-evaluation of the

socio-economic effects of these alternatives in the light of updated

load forecasts and other relevant information. (Recommendation 21)

105

Page 144: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page
Page 145: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

CHAPTER NINE

OAKLANDS

9.1 Introduction

The Oaklands power project is based on a large deposit of sub-bituminous coal

located near the town of Oaklands in New South Wales approximately 100 km

north-west of Albury-Wodonga. A Joint Venture of CRA Ltd. (6096) and

Mitsubishi Development Pty. Ltd. (4096) has been carrying out exploration of

the coalfield under an authorisation from the NSW Department of Mineral

Resources, with CRA acting as managers for the project.

To date a coal resource of some 3000 million tonnes (Mt) has been identified

with up to 1500 Mt capable of economic mining. The coal is located in a thick

seam and should be suitable for large scale open cut mining at a low unit

cost. The coal is not a prospect for export because of its location and

relatively low specific energy (for black coal).

The Joint Venture has been investigating the prospect of a large scale power

station (2800 MW) to be supplied from a new mine located on this coalfield.

Other uses for the coal are not considered prospective at this time.

A feasibility study was initiated by the Joint Venture in June 1985 and

consultants were engaged to carry out the study. Lead consultants were

GHD/Black and Veatch supported by Coffey and Partners on groundwater and

geotechnical studies, and Coleman and Associates on mine planning. Black

and Veatch are power consultants based in Kansas City. Power Technologies

Inc. of the USA have also conducted electrical transmission studies.

The feasibility study was completed in October 1986 and has provided the

basis for CRNs evidence to the Inquiry on the Oaklands project.

107

Page 146: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The study has examined:

A power station of initially two and ultimately four 700 MW

boiler/turbine units, conceptually based on the design of existing

4 X 660 MW power stations in NSW;

An associated open cut coal mine of initial capacity of 5.6 million

tonnes per annum (Mtpa) and later expansion to 11.2 Mtpa;

Infrastructure necessary to service such a development including

water supply, waste water treatment, electrical supply,

transmission line access and local community services.

Coal exploration and mine planning are still in progress. Water supply is

envisaged at this stage to be derived from a mixture of water obtained by

dewatering the mine site and from boreholes. Excess mine water and cooling

tower blowdown would be re-injected into another more saline deep aquifer

24 km from the mine. The water and environmental studies related to these

aspects of the project are still in progress and are to be reviewed by NSW

authorities.

9.2 Costs and Benefits

SECV has also presented evidence on the various Oaklands options. The

capital cost of plant based on Oaklands coal would be lower than that of an

equivalent plant based on Victorian brown coal because of the higher specific

energy and lower water content of the Oaklands coal. However, because the

coal would have to be purchased on contract from CRA, Oaklands coal will

probably cost more on an energy basis than the Victorian brown coal. SECV

has indicated that it would use an Oaklands based plant to supply Victoria as

an intermediate duty plant being scheduled after brown coal fired plants but

ahead of gas fired plant.

Installation of intermediate and peaking duty plant preserves the base load

operational status of existing brown coal fired plant. The economics of the

plant life extension programmes would therefore be enhanced by an extended

base load role for plants such as Hazel wood and Yallourn W.

108

Page 147: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The construction of Oaklands would lead to a strengthening of the

transmission system between Victoria and NSW and would enable a higher

level of interchange of electrical energy to occur with resultant fuel cost

savings to both States. System reliability would also be increased because of

the higher level of interstate support provided. This in turn results in savings

in the long term capital investment programmes of both States.

Oaklands also has the potential to enhance the use of the Snowy Scheme

through the use of surplus off-peak energy for pumped storage and the

availability of a higher level of short-term transmission capacity.

In evidence to the Inquiry, CRA and SECV disagreed over the transmission

voltage and configuration appropriate to deliver Oaklands output to Victoria.

This issue cannot be fuJJy resolved until the precise nature of any Victorian

participation in Oaklands has been agreed.

Possible power station options examined by SECV to serve Victoria's needs

have been:

A 2 x 700 MW unit development with all output exported to

Victoria. i.e. No NSW participation and no strengthening of

transmission links from Oaklands into NSW;

A 2 x 700 MW unit development near TeJford, 10 km south of

Yarrawonga in Victoria with coal supplied by rail from Oaklands.

This development presupposed that NSW opened up the coal field

in order to build a 4 x 700 MW unit development for its own

purposes at Oaklands;

Participation in a 4 x 700 MW unit development at Oaklands on

the basis that a share of the station's output would supply

Victoria's needs. Victoria could be an "equity" partner or could

take a long-term contract supply from the station.

The economics do not favour a development located at Telford nor a two unit

development at Oaklands. Evidence presented by CRA and SECV indicates

that the cost of electricity from a 4 x 700 MW development at Oaklands

109

Page 148: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

could be competitive with the cost of energy from Loy Yang B Units 3 & 4

and lower than the cost of energy from other future brown coal options. A

four unit development would require joint Victorian and NSW participation in

the project. As yet there is no commitment to Oaklands by NSW, but the

project promises to be cost competitive with other future NSW power station

options.

The scenario studies presented to the Inquiry by SECV and CRA show a

significant economic and financial benefit to Victoria through participation in

the Oaklands project. The cost savings estimated by SECV, which would

accrue to Victoria's electricity consumers over a thirty year plant life, are

shown in Table 9.1. The savings are shown as a range, dependent on coal

price, discount rate, and position in the development sequence.

9.3 Infrastructure

Employment in the Oaklands region is based on agriculture with the nearest

large centre of industry being Albury- Wodonga. There is 1i ttle infrastructure

or industrial development and no experienced power industry workforce in the

area immediately surrounding the proposed Oaklands site. The construction

and operation of an Oaklands coal mine and power station would require more

expenditure on infrastructure and services than a similar project in an area

like the Latrobe Valley. Infrastructure costs are estimated to be in the order

of $50M to $80M. The influx of workers employed on the project would have

impacts on the cities and towns in the region.

It has been argued that the lack and likely cost of infrastructure for the

Oaklands project are such as to rule out this option. However, despite

disagreement about this aspect, it can be seen that the cost of infrastructure,

even if doubled, is small relative to the potential benefits of the project to

Victoria.

The Committee has concluded that infrastructure costs are not decisive in

the question of whether or not Oaklands should be included as a future supply

option for Victoria. However, in proceeding with an Oaklands development,

infrastructure planning and financing arrangements are an important aspect

which should be addressed in some detail at the project approval stage.

110

Page 149: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

TABLE 9.1

PRESENT VALUE OF POTENTIAL GENERATION COST SAVINGS

DUE TO OAKLANDS OPTION; 1986-20U

SECV RESULTS ($M 1986)

Oaklands Coal@ $14/t Coal@ $20/t Position in Discount Rate Discount Rate Sequence 496 896 496 896

$M $M $M $M

First 536 468 382 391

Second 601 497 492 446

Third 537 415 459 381

Notes

1. Results are differences between the present value in mid-1986 of SECV future generation costs (operation and maintenance costs of all existing and future plant, and annualised real capital charges for new plant after Loy Yang B Units 1 &: 2) for an all brown coal sequence and those for brown coal/black coal sequences including a half (1400 MW) share of an Oaklands project.

2. Based on median load growth.

3. Source: Compiled by NREC from SECV data.

111

Page 150: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Oaklands would have regional employment and economic benefits for North

Eastern Victoria. Furthermore, a proportion of the project staff could be

expected to be domiciled in Victorian towns along the Murray River. A

proportion of the equipment for the mine and power station would be

manufactured in Victoria and other indirect activities would be supported by

services located in Victoria. It is expected that the construction of the

proposed Oaklands development would lead to overall benefits for Victoria.

9.4 Potential for Arrangements with NSW

Under its Terms of Reference the Committee is required to "include

recommendations as to whether or not the SEC should pursue the feasibility

of developing a black coal fired power station in northern Victoria, or the

prospects for an arrangement with NSW and/or other partners for either

investment in or purchase of power from a possible Oaklands, NSW power

project".

There has been a long history of interstate negotiations between Victoria and

NSW in respect of the current interchange agreement. Under this agreement

negotiations have recently been examining the prospects for deferral of

expenditure on Loy Yang B Units l & 2 by contract purchase of energy from

the NSW 2 x 660 MW Mt Piper Power Station due for commissioning in

1992-1993.

Negotiations in respect of Oaklands could be an extension of past practice

although ownership arrangements for Oaklands would need to be addressed.

CRA have proposed that the Oaklands mine would be privately owned and

operated to supply coal to the power station under a long-term contract.

This would be in accordance with existing practice in NSW and Queensland.

However, ownership and development of the power station could involve both

public and private participation.

Under recently amended legislation, ECNSW is currently preparing a Draft 30

year Electricity Development and Fuel Sourcing Plan. The Draft Plan is to

be presented in mid-1988 and will then be subject to public review by the

NSW Department of Energy. A Final Plan is to be tabled by mid-1989.

112

Page 151: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

The Draft Plan will examine timing for new power stations and the ranking of

Oaklands relative to other NSW power supply options. A Coal Enquiry

Document has been issued by ECNSW to enable all sources of coal to be

assessed for new power supply options. CRA has responded to this document

on behalf of Oaklands. Final selection of power station options to follow

Mt Piper Units 1 &: 2 could require formal coal supply tenders. Such tenders

are not called for in the preparation of the Draft Plan but may be before the

Final Plan is submitted.

In a letter to the Committee, the then NSW Minister for Energy, the

Honourable Peter Cox, MP, indicated his support for joint Victorian/NSW

studies of the Oaklands development. In addition, Mr. Cox mentioned the

wider issues of joint planning and interstate energy trade including possible

NSW access to Bass Strait gas. Following publication of the Committee's

Preliminary Report and Draft Recommendations, Mr. Cox's successor, the

Honourable Ken Gabb, M.P., wrote to the Committee reaffirming these

positions and that -

The NSW Government is basically supportive of the possible development of the Oaklands coal resource to provide benefits to both Victoria and NSW.

Recently, there has been a change of government in NSW. The situation is

therefore not clear; however it may become clearer, particularly with

respect to Oaklands, during late 1988.

9.5 Specific Recommendations

Negotiations should be initiated and pursued by the Victorian

Government with the Government of New South Wales to establish the

prospects for an arrangement with NSW and/or other partners for

either investment in or the purchase of power from a black coal fired

power station at Oaklands in NSW. (Recommendation 22)

The introduction of the Oaklands plant should be primarily determined

by a coincident need for additional sources of power supply in both

Victoria and NSW and an agreement to proceed on a co-ordinated

basis. The Oaklands plant would probably be constructed after

113

Page 152: PARLIAMENT OF  · PDF file2.3 Existing Generating Capacity 13 ... 4.4.3 Predpitators and Ash Handling Plant 36 ... 11.1.5 The Briquette Factory 135 ix . CHAPTER Page

Loy Yang B Units 3 &: 4, however, the possibility of the projects

overlapping in certain circumstances, such as a rapid growth in the

demand for electricity, should not be ruled out.

(Recommendation 23)

Prior to the Oaklands project proceeding, a detailed evaluation of the

electricity transmission systems interconnecting the three States and

the Snowy Scheme should be carried out with a view to optimising the

benefits which might flow from the reinforcement of this system as

part of the Oaklands project. This should include a review of the

appropriate voltage levels for the transmission system and the possible

benefits that might arise from strengthening the transmission links in

advance of the Oaklands development. (Recommendation 24)

The following issues should be considered before Victoria makes a final

commitment to an Oaklands project:

The commercial relationships between the parties to the

Oaklands project;

An independent detailed evaluation of the economics

and long-term viability of the Oaklands project

including the proposals for the supply and disposal of

water, and the proposed coal supply arrangements;

The requirements of the appropriate environmental and

resource planning authorities including the

Murray-Darling Basin Commission;

The provision and funding of community and project

infrastructure both in NSW and Northern Victoria;

The arrangements for sharing output both in respect of

Victoria's needs and the possibility of minimising

undesirable employment effects in the Latrobe Valley;

Transmission line routes from Oaklands to Melbourne.

(Recommendation 25)

114