61

PARK Lighting Supply and Installation Specification

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 2

Contents

1. GENERAL ................................................................................................................................... 7

1.1 Description of Project ................................................................................................................ 7

1.2 Introduction ................................................................................................................................. 7

1.3 Preliminary ................................................................................................................................... 7

1.4 Preface ........................................................................................................................................ 7

1.5 Reference Documents .............................................................................................................. 8

1.6 Scope of Works ........................................................................................................................... 8

1.7 Programme ................................................................................................................................. 9

1.8 Information and Submissions required. ................................................................................... 9

1.9 Tender Submissions (Sub-contractors/Suppliers) .................................................................... 9

1.10 Post Tender Submissions .......................................................................................................... 10

1.10.1 Project initial submissions ....................................................................................................... 10

1.10.2 Project testing submissions .................................................................................................... 10

1.10.3 Project closeout submissions ................................................................................................. 11

1.10.4 Layout and System Drawings ............................................................................................... 11

1.10.5 Submission process ................................................................................................................. 11

1.11 Documents, information and communications .................................................................. 12

1.12 Submission and communication timeframes ....................................................................... 12

1.13 Work Plans and Co-ordination Meetings .............................................................................. 12

1.14 Commons Terms and Abbreviations ..................................................................................... 13

1.15 Codes and Standards for Compliance ................................................................................ 15

1.16 Contractor’s design responsibility .......................................................................................... 17

1.17 Preferred Suppliers ................................................................................................................... 18

1.18 Environmental and Noise Conditions .................................................................................... 18

1.18.1 Site Boundary Noise Limits ..................................................................................................... 18

1.18.2 Ambient Conditions ............................................................................................................... 18

1.18.3 Durability Requirements......................................................................................................... 19

1.19 Dissimilar Materials .................................................................................................................... 19

1.20 Surface treatments and Protective Coatings ...................................................................... 19

1.21 Painting and Durability ............................................................................................................ 21

1.21.1 Park Painting ........................................................................................................................... 22

1.22 Galvanising ............................................................................................................................... 22

1.23 Identification ............................................................................................................................. 22

1.23.1 General .................................................................................................................................... 22

1.23.2 Marking .................................................................................................................................... 22

1.23.3 Reticulated Services – General ............................................................................................ 23

1.24 Operating and Maintenance Manuals – General .............................................................. 23

1.24.1 General .................................................................................................................................... 23

1.24.2 Format ...................................................................................................................................... 24

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 3

1.24.3 Content .................................................................................................................................... 24

1.24.4 As Built Drawings ..................................................................................................................... 26

1.25 Construction Producer Statements and Certificates of Compliance .............................. 26

1.26 Seismic Performance ............................................................................................................... 26

1.26.1 Application .............................................................................................................................. 26

1.26.1.1 Park works ......................................................................................................................... 27

1.26.2 Design ...................................................................................................................................... 27

1.27 Alternate Designs ..................................................................................................................... 27

1.28 Site of the Works ....................................................................................................................... 28

1.29 Drawings .................................................................................................................................... 28

1.30 Approvals .................................................................................................................................. 28

2. SUPPLY OF EQUIPMENT AND MATERIALS ............................................................................... 29

2.1 Shipment .................................................................................................................................... 29

2.2 Materials .................................................................................................................................... 29

2.3 Packing Requirements ............................................................................................................. 30

2.4 Storage ...................................................................................................................................... 30

2.5 Identification and Documents ............................................................................................... 30

2.6 Spares ........................................................................................................................................ 30

2.7 Date Processing ........................................................................................................................ 31

2.8 Power Quality and Electromagnetic Interference .............................................................. 31

2.9 Construction Record Drawings – Equipment ....................................................................... 31

2.9.1 General .................................................................................................................................... 31

2.9.2 Submission ............................................................................................................................... 31

2.10 Training ....................................................................................................................................... 31

2.10.1 Training Plan ............................................................................................................................ 32

2.10.2 Training Equipment ................................................................................................................ 32

2.10.3 Training Manuals ..................................................................................................................... 32

3. ON SITE INSTALLATION ........................................................................................................... 33

3.1 Free Issued Equipment ............................................................................................................ 33

3.2 Contractor Supplied Documents ........................................................................................... 33

3.3 Material Substitution ................................................................................................................. 33

3.4 Coordination and Setting Out ................................................................................................ 33

3.5 Installation ................................................................................................................................. 34

3.6 Fire Stopping ............................................................................................................................. 34

3.7 Construction Record Drawings – On site Installations ......................................................... 35

3.7.1 General .................................................................................................................................... 35

4. INSPECTIONS, SNAGGING AND DEFECTS ............................................................................. 37

4.1 Inspection prior to closing up ................................................................................................. 37

4.2 Snagging ................................................................................................................................... 37

4.3 Defects....................................................................................................................................... 38

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 4

5. TECHNICAL ............................................................................................................................. 39

5.1 LV Power Distribution System .................................................................................................. 39

5.2 Design Parameters ................................................................................................................... 39

5.3 Permanent Lighting Design ..................................................................................................... 40

5.3.1 Maintenance Factors ............................................................................................................ 40

5.3.2 Lighting Control ...................................................................................................................... 40

5.3.3 Lamp Lumens .......................................................................................................................... 40

5.3.4 Quantities ................................................................................................................................ 40

5.4 Luminaire performance........................................................................................................... 40

5.4.1 Luminaire construction .......................................................................................................... 40

5.4.1.1 General ............................................................................................................................. 40

5.4.1.2 Temperature Rating ........................................................................................................ 41

5.4.1.3 Voltage Rating ................................................................................................................. 41

5.4.1.4 Ballasts ............................................................................................................................... 41

5.4.1.5 Igniters ............................................................................................................................... 41

5.4.1.6 Control Gear .................................................................................................................... 41

5.4.1.7 Lamp Protection .............................................................................................................. 42

5.4.1.8 Performance .................................................................................................................... 42

5.4.1.9 Independent Photometric testing ................................................................................ 42

5.4.1.10 CIDs ................................................................................................................................... 42

5.4.2 Luminaire performance ......................................................................................................... 42

5.5 Vibration .................................................................................................................................... 42

5.6 Cables and Wiring .................................................................................................................... 43

5.6.1 General .................................................................................................................................... 43

5.6.2 Cable Types ............................................................................................................................ 43

5.6.3 Termination of Conductors ................................................................................................... 44

5.6.3.1 Cable joints ...................................................................................................................... 44

5.6.3.2 Pole connection boxes................................................................................................... 44

5.6.4 Cable and Core Identification ............................................................................................. 44

5.6.5 Earth Bonding .......................................................................................................................... 45

5.6.6 Cable Penetrations ................................................................................................................ 45

5.6.7 Containment ........................................................................................................................... 45

5.6.7.1 General ............................................................................................................................. 45

5.6.7.2 Conduit ............................................................................................................................. 45

5.6.7.3 Segregation ...................................................................................................................... 46

5.6.7.4 Jointing.............................................................................................................................. 46

5.6.7.5 Glanding ........................................................................................................................... 46

5.7 Electrical Switchgear ............................................................................................................... 46

5.7.1 General .................................................................................................................................... 46

5.8 Works Included ......................................................................................................................... 46

5.9 Compliance with Electrical Codes and Standards ............................................................. 46

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 5

5.10 Particular Requirements .......................................................................................................... 47

5.10.1 Workmanship and Materials ................................................................................................. 47

5.10.2 Operational, Maintenance and Access Requirements ................................................... 47

5.10.3 Physical Construction ............................................................................................................. 48

5.10.4 Bus-Bars .................................................................................................................................... 48

5.10.5 Earth and Neutral Provisions ................................................................................................. 49

5.11 Wiring and Terminations .......................................................................................................... 49

5.12 Chart Holders & MCB Charts .................................................................................................. 49

5.13 Labelling and Mimics ............................................................................................................... 49

6. INSTALLATION ......................................................................................................................... 51

6.1 Appurtenances ........................................................................................................................ 51

6.2 Co-ordination ........................................................................................................................... 51

6.3 Instructions ................................................................................................................................. 51

6.4 Alignment .................................................................................................................................. 51

6.5 Wiring ......................................................................................................................................... 51

6.6 Clean-up: .................................................................................................................................. 51

6.7 Free Issued Equipment ............................................................................................................ 51

6.8 Contractor Supplied Documents ........................................................................................... 51

6.9 Pre- Manufacture Submissions – On Site Installation ........................................................... 52

6.9.1 Layout and System Drawings ............................................................................................... 52

6.9.2 Design Details .......................................................................................................................... 52

6.9.3 Procedure ................................................................................................................................ 52

6.10 Work Plans and Co-ordination Meetings .............................................................................. 52

6.11 Material Substitution ................................................................................................................. 53

6.12 Coordination and Setting Out ................................................................................................ 53

6.13 Installation ................................................................................................................................. 53

6.14 Construction Record Drawings – On site Installations ......................................................... 54

6.14.1 General .................................................................................................................................... 54

6.14.2 Submission ............................................................................................................................... 55

7. LIGHTING INSTALLATION TESTING .......................................................................................... 56

7.1 General ...................................................................................................................................... 56

7.2 Testing and Commissioning Manual ...................................................................................... 56

7.3 Pre-Testing Procedures ............................................................................................................ 56

7.4 Testing ........................................................................................................................................ 57

7.5 Witnessing .................................................................................................................................. 57

7.6 Grid Size ..................................................................................................................................... 57

APPENDIX A ................................................................................................................................... 58

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 6

Tables

Table 1 – Reference Drawings ........................................................................................................... 8

Table 2 – Reference Specifications ................................................................................................... 8

Table 3 – Post Tender Submission ..................................................................................................... 11

Table 4 – Common Terms ................................................................................................................. 13

Table 5 – Common Abbreviations ................................................................................................... 13

Table 6 – Current Standards ............................................................................................................. 15

Table 7 – Ambient Conditions .......................................................................................................... 18

Table 8 – Durability Requirements ................................................................................................... 19

Table 9 – O&M Format ...................................................................................................................... 24

Table 10 – O&M Content .................................................................................................................. 24

Table 11 - List of associated drawings ............................................................................................ 28

Table 12 – Maintenance Factor(s) .................................................................................................. 40

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 7

1. GENERAL

1.1 Description of Project

The Memorial Park Alliance (MPA) has been established between NZTA, and the Non-owner

Participants (NOPs) Joint-venture of Downer, HEB, Tonkin & Taylor and URS.

MPA, operating under an Alliance Agreement, is tasked with the National Memorial Park

Underpass and Basin Reserve Bridge, along with enhancements to the adjacent Inner City

Bypass.

The construction of these assets will enable the creation of the National Memorial Park and

significantly improve traffic flows in the Basin Reserve area.

This specification outlines the Park lighting design and should be read in conjunction with

the Urban Design documentation is ensure the full understanding of the design philosophy.

1.2 Introduction

Where required, all consents shall be obtained and local authority fees paid for the

completion of all systems. Necessary time and costs shall be allowed for to fully comply with

ALL relevant Local Authority Body regulations, all relevant AS/NZS documents, Codes of

Practice and other relevant Acts, Regulations, Standards and Codes.

All parties (inclusive of Subcontractors and suppliers) shall comply with all Statutory, Local

Authority Fire Service and New Zealand Insurance Council requirements.

This specification relates specifically to project works in relation to the establishment of MEC

services for the Park for the Memorial Park Alliance Project.

1.3 Preliminary

This document outlines requirements for the design, manufacture, factory testing, delivery

to site, unloading, movement and placement in location, installation, site testing,

commissioning, witnessing, warranty and maintenance. The works described in this

specification and associated drawings shall form the basis of a design, supply, install and

commissioning contract.

The specification(s) and drawings identify the system concepts and standards of

performance and quality required, but do not purport to identify all problem areas and

their solution(s), which shall be the responsibility of the sub-contractor/supplier.

1.4 Preface

Electrical Services for the Park will be fed from a DB within the UAB building located near

the western end of the Park. The building will house all of the necessary electrical switch

gear to operate the electrical and mechanical equipment that will be utilised within the

Park.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 8

1.5 Reference Documents

The following reference documents, drawings and specifications, shall be used for

coordination purposes.

Table 1 – Reference Drawings

Drawing Series Description

UND-13-000, 100 and

300 & 400 series

(excl. 13-070, 071 & 072)

Main Electrical Package

(includes Underpass Lighting, UAB security, plant communications and

controls as well as EEC/FCC cabinet security)

UND-13-500 series

ITS Field devices

(Includes field devices, racks & equipment at UAB, interconnecting

cabling)

Table 2 – Reference Specifications

Specification reference Description

MP-13-DES-SP-001 Main Electrical Supply and Installation Specification

MP-13-DES-SP-007 MEC General Technical Specification

1.6 Scope of Works

This specification is for the Park Lighting Supply and Installation. The contract includes the

supply, except where specifically stated otherwise, of all labour, materials, equipment,

tools, plant and scaffolding for the supply, delivery, installation, connection, testing,

commissioning, maintenance and guarantee of the complete installation which comprises

the following works (note, these works will be in conjunction with other works for the

Memorial Park Alliance):

The Park Lighting Contractor/Sub-contractor shall:

1. Supply and install all fittings and lamps to meet the requirements of the Park lighting

design specifications and drawings. (Refer to Appendix A - Schedule of fittings for details

of quantities and sizes of fittings.

2. Supply and installation of all poles for lighting purposes only.

3. Provide mounting brackets to mount all supplied fittings.

4. Comply with Environmental and Seismic design and installation.

5. Supply drawings and documentation for submission and installation

6. Deliver (including unloading) all supplied equipment to the designated lay down areas.

7. Provide spare parts.

8. Install the Park Lighting to the Principal’s and Park Lighting Sub-contractor’s

requirements.

9. Test and commission, providing test reports using calibrated equipment for the Park

Lighting to the Principal’s requirements in conjunction with the Park Lighting Sub-

contractor.

10. Provision of other such items to ensure a complete installation, this includes but is not

limited to lamps, luminaires, poles, cabling, control gear, fuse gear etc.

11. Liaise and coordinate with Wellington Electricity (Wellington City Council’s preferred

energy supplier and NZTA preferred energy supplier) to establish power supplies and

metering.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 9

12. Coordination of civil work including trenching and backfill, thrusting and ducting,

conduits, penetrations ,excavation and foundations for lighting columns and

switchboards.

13. Earthing to AS/NZS3000 and Network supplier requirements.

14. Installation of LV distribution networks starting from the main incoming terminals of the

distribution boards and all related cables to the lighting poles.

15. Compiance with WCC and NZTA requirements.

16. Electrical safety testing by an IQP (Independently Qualified Person) and an electrical

Certificate of Compliance.

17. Preparation of construction and builders works drawings associated with the works

included in this specification including coordination with other Contractors.

18. Submission of required construction drawings and information on materials and

equipment for the designers review.

19. Preparation of detailed method statements and programmes for the execution of the

works, including testing and commissioning.

20. Protection coordination study and short circuit calculations for all electrical distribution

systems.

21. Provision of “as-built” manuals, including all necessary drawings and comprehensive

operation maintenance and parts manuals.

22. Maintenance and warranty of the equipment for 12 months maintenance contract to

commence once initial warranty period is complete.

The Park Lighting Contractor is invited to supply equipment as per this specification or such

that the supplied equipment will meet the design requirements of this specification.

Supply of alternative equipment will require the Park Lighting Contractor to provide design

modelling and calculations to verify that the alternatives offered meet the requirements of

the Park lighting design.

Acceptance of any alternative fittings will be subject to approval by the Engineer.

1.7 Programme

All elements of the MEC works shall be programmed within the Memorial Park Alliance.

1.8 Information and Submissions required.

Any and all alternatives offered as part of this submission.

1.9 Tender Submissions (Sub-contractors/Suppliers)

The following information shall be provided with any offer and/or submission:

1) Provide a preliminary method statement and works programme including the

manufacture, delivery, installation, commissioning and observation of the whole works.

2) Specific details and testimonials of previous experience of projects requiring the design,

installation and commissioning of the components used with any proposed system in the

MEC packages.

3) Details of proposed specialist suppliers and sub-suppliers.

4) List of recommended spares suitable for 10 years of operation.

5) Confirmation of Warranty.

6) Quality Assurance statement.

7) Statement on Safety

8) Manufacturer’s literature for equipment to be supplied.

9) List of items not complying with this specification.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 10

10) Detailed Cost Schedule.

1.10 Post Tender Submissions

The Contractor shall submit to the Principal’s Engineer two paper copies and one electronic

(pdf) copy of each submission.

The project MEC submissions shall include the following:

1.10.1 Project initial submissions

In addition to the specific reference specification requirements the following information

shall be provided within 2 to 4 weeks of appointment for approval by the Engineer:

1) Manufacturing detailed dimensioned drawings of OEM equipment at 1:20 or 1:50 scale,

including cables wiring and layout drawings with all elements sized.

2) Installation and construction detail dimensioned drawings to 1:20 , 1:50 or 1:100 scale,

including wiring and layout drawings, all complying with MPA CAD Procedures.

3) Equipment data sheets in English clearly identifying make and model of equipment

being supplied, including power consumption, durability, corrosivity and seismic

considerations, general documentation not clearly indicating make and model

applicable to this project will not be accepted. (This only applies if equipment differs

from those selected by suppliers)

4) Proposals for packaging and protection of equipment in transit.

5) Proposals for protection of works.

6) Inserts, anchors and supports, hangers and brackets, including materials and method

statements for installation and testing.

7) Surface coatings and painting including pre- and post-fabrication application materials

and method statements for off and on site applications.

8) Samples as listed in specific or general reference specification requirements.

9) Colour schemes of exposed and exterior work.

10) Identification and labelling schedule, including size, wording and materials.

11) Fire stopping.

12) Design and construction calculations forming part of the Works, including but not limited

to fixings, inserts, anchors, supports, hangers and brackets.

13) For areas of Contractor design responsibility, submit designers experience and

qualifications to indicate the designer has knowledge and skills required for the design

such that a Local Authority, or IPENZ, PS1 or equivalent can be provided.

14) Man-hours resourcing schedule for the contract works, coordinated and agreed with

MPA construction team.

15) Programme or schedule of contract works, coordinated and agreed with MPA

construction team.

16) Clause by clause confirmation of compliance with specification, and against Standards

if requested by Principal, for submission to Principal’s Engineer.

1.10.2 Project testing submissions

The following post tender submissions shall be provided no less than two working weeks prior

to testing or commissioning;

1) On-site testing such as site acceptance testing prior to equipment being made

available for commissioning.

2) Commissioning schedule and details.

3) Owner pre-handover operational witnessing.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 11

1.10.3 Project closeout submissions

The following post tender submissions shall be provided no less than four weeks prior to

handover of this Contract works, MPA complete contract works for the Underpass or

Owner’s beneficial use of the works whichever is the sooner:

1) Training Plan.

2) As built drawings.

3) Operations and Maintenance Manuals.

4) Test and commissioning results.

5) Asset schedule to NZTA requirements.

6) Maintenance schedule for planned preventative maintenance to provide the

environmental durability required by this and specific technical specifications.

7) Schedule of spares.

1.10.4 Layout and System Drawings

Submit layout Drawings of all areas as listed this Specification, including plans and

elevations. Submit layout and/or schematic system diagrams for those items where design

forms a part of the Works.

Submit details of any changes to the Works as shown in the Drawings arising from the

acceptance of a deviation from the Tender Documents, drawn at the same or larger scale

as the Drawings.

Should an accepted deviation include an alternative electrical distribution design, provide

a single line drawing giving manufacturers' reference numbers for each protection device,

plus technical data and calculations showing discrimination and the capability of the

devices to withstand expected fault levels.

1.10.5 Submission process

The Principal will review submission information and advice comments or amendment

requirements within 10 working days of receipt. The Contractor shall revise accordingly and

resubmit within 5 working days.

The Contractor shall retain corrected, unsoiled, clean copies of all submissions for future

inclusion in Operating and Maintenance Manuals.

Post Tender Submissions shall be reviewed by the Principal’s Engineer and returned marked

as status in table below, action required by the Contractor is indicated within the table,

either:

Table 3 – Post Tender Submission

Status Comment Contractor’s action Re-submission required

A No comment

The Contractor may continue with

manufacture and installation of the

equipment/works as submitted.

No

B Minor

comment

The Contractor may continue with the

manufacture and installation of the

equipment/works incorporating the

Engineer’s specific minor comments.

Yes. Resubmit

incorporating the

Engineer’s comments

until A status.

C Major

comment

The Contractor may not continue with the

manufacture and installation of the

Yes. Resubmit

incorporating the

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 12

Status Comment Contractor’s action Re-submission required

equipment/works. The Engineer’s specific

comments have a significant impact on

the equipment manufacture or works

installation.

Engineer’s comments

until A status.

D Rejected

The Contractor may not continue with the

manufacture and installation of the

equipment/works. The submission

indicates the Contractor does not have a

clear understanding of the equipment or

installation requirements

Yes. Resubmit

incorporating the

Engineer’s comments

until A status.

It is the Contractors responsibility to ensure the total time period to obtain Engineer’s

approval including re-submissions shall not exceed 4 working weeks.

Engineer’s comments or absence of comments on post tender submissions shall not detract

from the Contractor’s responsibility to comply with the Contract documents.

Comments by the Engineer do not imply a variation to the Contractor’s works.

The Engineer has allowed to review each post tender submission twice, should additional

reviews be required the Engineer shall charge the Contractor for the review time at the

Engineer’s standard time charge rate.

1.11 Documents, information and communications

The Contractor shall include for the use of the project electronic document transfer and

communication system, Orbit.

All documents and communications issued by the Contractor shall use the Orbit document

management system including but not limited to reports, test and commissioning results,

requests for information, responses to requests for information, post tender submissions, O&M

manuals and as built drawings.

The project specific requirements for Orbit are available for consultation from MPA and shall

be complied with.

1.12 Submission and communication timeframes

The Contractor shall submit all post tender submissions, documents, information and

communications to enable the Principal to meet the Works delivery programme.

The Contractor shall submit approvals and requests for information in a timely manner to

allow the Principal’s representative to respond. The Contractor should be aware that some

issues require more time to resolve and may require further information to be provided.

There shall be no delay to delivery of the works due to late or inadequate submissions or

requests for information resolution, the Contractor shall request clarification as soon as they

become aware of a need for clarification. The presence or absence of a request for

clarification does not absolve the Contractor of their obligation to comply with the

Contract Works.

1.13 Work Plans and Co-ordination Meetings

The Contractor shall ensure that all work activities on site are properly planned,

documented and communicated in advance. In addition to the Subcontractor’s

installation programme, comprehensive Work Plans shall be prepared for the guidance of

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 13

the workforce. The Work Plans are to be submitted to the Principal for approval in advance

of each significant construction operation being carried out.

The Contractor shall keep the Principal regularly informed about actual progress of the

Works and the cause of any delays.

The Contractor shall allow for weekly attendance of two (2) hours duration by one, or more,

staff at the Principal co-ordination meetings.

1.14 Commons Terms and Abbreviations

Table 4 – Common Terms

Term Definition

Contractor Engaged by MPA

Equipment Means the materials and labour to be supplied under this specification for the

Project

Owner NZTA

Principal Memorial Park Alliance

Project Means the National War Memorial Underpass

Project Works Means the works described in Section 2 and above

Sub-Contract Means the agreement between the Contractor and the subcontractor to

provide equipment nominated in this Specification

Subcontractor Means the organisation providing subcontract works defined in this

Specification.

Tenderer Means the entity that tenders the works to contract with the Principal to

become the Contractor

Table 5 – Common Abbreviations

Abbreviation Description

AA Alliance Agreement

ADN Alliance Defect Notice

AFFL Above final floor level

AM Alliance Manager

AMT Alliance Management Team

AS Australian Standards

AS/NZS Australian/New Zealand Standards

ATS Automatic Transfer Switch

AVID Automatic Incident Detection (this uses Traficon Video Image Processor

technology)

BAU Business as Usual

BS EN British Standards European Norm

CAD Computer Aided Design

CB Circuit Breaker

CC Cut and Cover

CCTV Closed Circuit Television

cd/sqm Candelas per square metre

CDST Construction design support team

CDU Critical Distribution Unit

Comms Communications

DB Distribution Board for non UPS supplies

EM Emergency

Engineer The WTA Lead Electrical Engineer

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 14

Abbreviation Description

EOC Estimated Out-turn Cost

EPMS Electrical Power Monitoring System

ESB Essential Switchboard

GST Goods and Services Tax

GUI Graphical User Interface

HDG Hot-dip galvanised

HLI High Level Interface

HMI Human Machine Interface

HPS High Pressure Sodium

HV High Voltage

ICB Inner City Bypass

ITP Inspection and test plan

L&P General Light & Power (non-critical)

LSZH Low Smoke Zero Halogen

LV Low Voltage

MCB Miniature Circuit Breaker

MCCB Moulded Case Circuit Breaker

MCR Main Communications Room

MDB Main Distribution Board ( Electrical, supporting multiple DBs & major plant–not UPS)

MDF Main Distribution Frame

MEC Mechanical, Electrical and Controls

MF Maintenance Factor

MPA Memorial Park Alliance

MSB Main Switchboard

MSSB Mechanical Services Switchboard

MTBF Mean Time Between Failure

MTS Manual Transfer Switch with intermediate OFF position

MTTR Mean Time to Repair

NOP Non-Owner Participant

NWMU National War Memorial Underpass

NZTA New Zealand Transport Agency

OEM Original equipment manufacturer

p.f. Power factor

PAB Project Alliance Board

PAT Performance Acceptance Testing

PFC Power Factor Correction

PHO Photometer

PLC Programmable Logic Controller

PTZ Pan / Tilt / Zoom

PUE Power Usage Effectiveness

PWR Power Supply

QA Quality Assurance

RCD Residual Current Device

RFI Radio Frequency Interference

SCADA Supervisory Control & Data Acquisition

SPG Standby Power Generator

SSD Safe Stopping Distance

STS Static Transfer Switch

THD Total Harmonic Distortion

TOC Traffic Operations Centre

WCC Wellington City Council

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 15

1.15 Codes and Standards for Compliance

Unless otherwise specified or approved, the equipment shall comply with the requirements

of the latest edition (including amendments) of the Standards and Codes relevant to the

provision of equipment, together with the requirements of competent Statutory Authorities

having jurisdiction over all or part of the manufacture, installation and operation of the

equipment.

Reference to any Standard shall include any amendments thereto, and any Standard in

substitution thereof, issued up to three months before the closing date for tenders.

All equipment and workmanship shall conform to the most recent requirements of the

relevant statutory Authorities and current applicable New Zealand Standards. Alternatively,

where no New Zealand Standard exists, work shall conform (in order of precedence) to the

most current Australian Standards, British Standards, United States Standards and other

international standards.

Where conflict exists between these and this Specification, the most stringent requirement

shall be satisfied.

The Supplier and Subcontractor shall not deviate from the provisions of the relevant

standard without first obtaining agreement in writing from the Contractor.

ISO units shall be used.

The codes of practice and Standards that shall be considered by the Contractor shall

include, but not be limited to the following:

Table 6 – Current Standards

Standard Description

AS 1110 ISO metric hexagon precision bolts and screws

AS 1111 ISO metric hexagon commercial bolts and screws

AS 1112 ISO metric hexagon nuts, including thin nuts, slotted nuts and castle nuts

AS 1214 Hot-dip galvanized coatings on threaded fasteners

AS 1345 Identification of the contents of piping, conduits and ducts

AS 1798 Lighting columns and bracket arms – Preferred dimensions

AS 1554.1 Structural Steel Welding

AS 1627 Code of Practice for Preparation and Pre-Treatment of metal surfaces prior to

Protective Coating

AS 1789 Electroplated Coatings: Zinc on Iron or steel

AS 1836 Tubes for pressure purposes – welded steel

AS 2184 Moulded case circuit-breakers for rated voltages up to and including 600V AC

and 25DV DC

AS 2700 Colour standards for general purpose

AS 4506 Metal finishing – Thermoset powder coatings’

AS 60529: 2004 Degrees of protection provided by enclosures (IP Code)

AS 60947 Low Voltage switchgear and control gear – General rules and other control

devices

AS/NZS 1158 Lighting for Roads and Public Spaces

AS/NZS 1170 Loadings Code

AS/NZS 1554.6 Structural steel welding – Welding stainless steels for structural

AS/NZS 1664.1 Aluminium Structures, Part 1 – Limit state design.

AS/NZS 1665 Welding of Aluminium Structures

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 16

Standard Description

AS/NZS 3000:2007 Wiring Rules

AS/NZS 3008 Electrical Installations- Selection of Cables

AS/NZS 3012 Electrical Installations- Construction & Demolition Sites

AS/NZS 3017 Electrical Installations- Testing & Inspection Guidelines

AS/NZS 3019 Electrical Installation-In-Service Testing

AS/NZS 3191 Electrical flexible cords

AS/NZS 3439 Switchgear - Specification for type tested and partially type tested Assembles

AS/NZS 3678 Hot-rolled structural steel plates, floor plates and slabs

AS/NZS 3947 Specification for Low Voltage Switchgear and Control gear

AS/NZS 4219 Specification for seismic resistance of engineering systems in buildings

AS/NZS

4251.1:1999

Electromagnetic Compatibility (EMC)

Generic emission standard; Part 1: Residential, commercial, and light industry

AS/NZS 4677 Steel utility services poles

AS/NZS 4680 Hot dip galvanised (zinc) coatings on fabricated ferrous articles.

AS/NZS 4792 Hot-dip galvanised (zinc) coatings on ferrous hollow sections, applied by a

continuous or a specialised process

AS/NZS 4836 Safe Work on LV Electrical Installations

AS/NZS 61000.3 Electromagnetic compatibility (EMC) – Part 3 -*: Limits (* parts as they relate to

the provision of this equipment)

AS/NZS

61000.6.2:2006

Electromagnetic Compatibility (EMC) General standards – Immunity for

industrial environments.

AS/NZS 6401 Specification for PVC insulated cables for electric power and lighting

AS/NZS2312 Guide to the protection of structural steel against exterior atmospheric

corrosion by use of protective coatings

BS 5467 Specification for cables with thermosetting insulation.

BS 5486 Pt11 Particular requirements of Fuseboards.

BS 5486 Pt12 Particular requirements for miniature circuit breaker boards.

BS336 Specification for fire hose couplings and ancillary equipment

BS EN 40-7 Part 7: Requirements for fibre reinforced polymer composite lighting columns

BS EN 12767 Passive safety of support structures for road equipment – Requirements,

classification and test methods

BS EN 60947

Specification for Low Voltage Switchgear and Control gear/Circuit

breakers/Switches and disconnectors / contactors and motor starters / control

circuit devices

ECP 34 Electrical Safety Distances

ECP 35 Power Systems Earthing

ECP 36 Harmonics Levels

Electricity

Regulations

Compilation

EN 61000-4 Electromagnetic Compatibility (EMC)

HSE Act Health and safety and employment act.

IEC 60364-4 Low Voltage Electrical Installations

IEC 60445

Basic and safety principles for man-machine interface, marking and

identification – Identification of equipment terminals, conductor terminations

and conductors’

IEC 60529 Degrees of protection provided by enclosures’

IEC 60947 Low-voltage switchgear and control gear

IEC 848 (Grafcet)

standard Preparation of function charts for control systems

IEEE 519 Standard practices and requirements for harmonic control in electrical power

systems

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 17

Standard Description

ISO 9223 Corrosion of metals and alloys – Corrosivity of atmospheres – Classification

New Zealand

Building Code

NS/NZS 1677 Refrigeration systems.

NZ Electricity

(Safety)

Regulations (2010)

NZ Electricity Act 1997

NZ Electricity Act

and

Amendments.

NZBC New Zealand Building Code and New Zealand Building Act 1991.

NZECP34:2001 Electrical Safe Distances from Overhead HV Lines.

NZECP36:1993 New Zealand Electrical Code of Practice for Harmonic Levels

NZS 1170.5 Seismic Loads (2004).

NZS 3101 Concrete structures standard, Part 1 – The design of concrete structures

NZS 3109 Concrete construction

NZS 3404 Steel structures standard

NZS 4203 General structural design and design loadings for buildings.

NZS 4219 Seismic Resistance, Engineering Systems.

NZS 4296 Cable trunking system

NZS 5807 Code of practice for industrial identification by Colour, Wording or other

coding.

NZS 6401 PVC Insulated Cables for Electric Power and lighting’

NZS 6701 Code of practice for road lighting

NZS 7643 Code or practice for the installation of unplastercized PVC pipe.

NZS 7702 Specification for colours for identification, coding and special purposes

1.16 Contractor’s design responsibility

The Contractor shall be responsible for the design and submit design details of the following

elements of the MEC and ITS services to comply with Standards, this specification and the

specific technical specification:

1) Original equipment manufacturer (OEM).

2) Inserts, anchors, fixings, supports and hangers.

3) Seismic calculations, details and certification of seismic restraint details.

4) Compliance with project durability requirements.

5) Final selection of equipment to comply with design.

6) Colour schemes of exposed and exterior work (in conjunction with Designers if change

from specified requirements is needed).

7) Identification and labelling schedule, including size, wording and materials.

8) Fire stopping.

9) Trade specific design detail.

10) Co-ordination with all other trades and also with other parts of the installation.

11) Builders work requirements.

12) Detailed system drawings including

• Detailed schematics and wiring diagrams

• Termination details

• Cable schedules

• Configuration

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 18

1.17 Preferred Suppliers

The design has been based upon equipment or works (preferred suppliers) mentioned in this

Specification. The tender shall be based upon the design preferred suppliers.

The Contractor shall confirm at tender the suppliers they propose to use for the Contract

Works.

Should the Contractor desire to offer alternative suppliers the Contractor shall:

1) Provide a compliant tender using the design preferred supplier with a compliance

statement.

2) Provide a non-compliant tender using the alternative supplier clearly confirming:

• Detail with make and model of alternative supplier with a compliance statement.

• The complete impact upon all interfacing or other Contract works

• The advantage to the Principal of proceeding with the alternative supplier

• The programme implications of accepting the alternative supplier

For alternative supplier any commercial implications shall take into consideration additional

cost due, these costs shall be borne by the Main Electrical Contractor, including but not

limited to:

• Additional submission and approval costs

• Re-design costs for the systems and interfacing Contract works

The Principal or Principal’s Engineer shall in no way accept any additional costs associated

with alternative suppliers or effected related or interfacing contract works.

1.18 Environmental and Noise Conditions

1.18.1 Site Boundary Noise Limits

1.18.2 Ambient Conditions

The following ambient conditions apply for the Memorial Park Project.

Table 7 – Ambient Conditions

Conditions Value Unit

Mean maximum temperature 25.7 °C (Dry Bulb)

21.6 °C (Wet Bulb)

Highest temperature 28.4 °C (Dry Bulb)

Mean minimum temperature 1.7 °C (Dry Bulb)

Lowest temperature -1.6 °C (Dry Bulb)

Ambient relative humidity 40-60 % RH

Ambient air pressure 101.23 mbar

Altitude not exceeding 126 m

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 19

1.18.3 Durability Requirements

Table 8 – Durability Requirements

Area Design

Life

Environmental

Factors

AS/NZS 2312

Corrosivity

Category

IP Ratings Material

Surface/ Surface Road

Lighting and

equipment

support poles

40

Rain

Wind

UV

C: Medium

carbon steel HDG600

Support brackets 40 carbon steel HDG601

LV and ELV cables 20

XLPE, underground cables

shall be PVC Neutral

Screen with heavy grade

3.2 mm PVC sheath

Photometers 10 IP66 Manufacturer's standard

HPS or LED lighting 18 IP65 Manufacturer's standard

Buried Services

LV and ELV cables 20

Moisture

Periodic

immersion in

water

D: High

XLPE or fire rated

Ducts/conduit for

cables 100

PVC

Access pits for

cables 100

Pre-cast or cast-in-situ

Access pit covers 100

Carbon steel infilled with

concrete

Electrical earthing

rods/mats 100

Copper

1.19 Dissimilar Materials

To prevent bimetallic corrosion, dissimilar metals shall not be used. Where fasteners/screws

are used, these shall be of a similar durability to the columns.

Isolate dissimilar metals that are prone to galvanic action. Examples of isolation materials

include rubber, Teflon or bitumen tape. Non-conductive materials such as elastomeric

spacers shall be used to keep aluminium alloy parts from direct contact with steel or other

dissimilar metals in the presence of moisture to avoid galvanic corrosion. Avoid metal

components coming in direct contact with cement surfaces when corrosion could occur;

for example copper & cement.

1.20 Surface treatments and Protective Coatings

The column materials must comply with the relevant design standards for durability and

shall have a life expectancy greater than the specified intended life.

Where applicable, corrosion protection shall be carried out in accordance with the

appropriate standards, for the following lighting column materials:

• Steel

All lighting columns and outreach arms shall be hot dipped galvanized in accordance

with AS/NZS 4680. The average coating mass shall not be less than 390 g/m², (equivalent

to a nominal coating thickness of 55 microns).

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 20

Fasteners shall be galvanized as specified in AS 1214.

All galvanizing vent holes/drainage holes shall be sealed where they could allow ingress

of rainwater.

Within the salt spray zone (ISO 9223 Category C4), the AS/NZS 2312 galvanizing

designation of HDG390 will not provide sufficient protection. For these columns, the lives

to first major maintenance must be extended by application of suitable organic barrier

coatings as recommended in Tables 5.2 and 5.3 of AS/NZS 2312.

The underside of flanged bases bolted to concrete foundations also require additional

protection against crevice corrosion and the galvanizing should also be epoxy coated

to a minimum thickness of 150µm.

The outer surfaces of galvanized ground planted lighting columns and stub bases shall

be further protected to 100 mm above finished surface level (ground or concrete) and

to the base of the column, with a continuous self-priming non-conductive barrier

coating (epoxy-mastic or similar) at least 350µm thick.

Proprietary 100% volume solids polyurethane and polyurea coatings for ground planted

columns and stub bases are available that will extend the life even further, and an NZTA

approved system should be applied where the specified service life is greater than 25

years.

Repairs to any damaged surface protection of the steelwork shall be carried out in

accordance with Section 8 of AS/NZS4680 for damaged galvanizing, except that the

maximum permitted damaged or uncoated area shall not exceed 40mm2. Repairs to

damaged organic barrier coatings shall be by reinstatement of the system.

Application and repair of all organic barrier coatings shall be in accordance with the

written instructions to be provided by the manufacturer of the coating(s). Surface

preparation prior to coating shall be by sweep blasting as specified in Appendix I of

AS/NZS4680, unless not required by the coating manufacturer (e.g. when using an etch

primer over degreased new galvanizing).

• Aluminium

Aluminium lighting columns require no specific corrosion protection other than the

application for ground planted columns of a non-porous, electrically insulating bitumen-

containing coating with a minimum layer of 250µm, or the required thickness of any

other material (e.g. helically wound polymer or petrolatum tape) that provides the same

degree of protection. The coating should only be applied after degreasing and an

appropriate treatment to ensure adhesion.

This coating should be applied to external surfaces of the embedded column section

extending to a level 100mm to 150mm above finished ground level. Internal surfaces

below ground level may be filled with clean free draining material e.g. river sand.

Aluminium in contact with concrete shall be similarly protected where moisture is

present and corrodents may be trapped between the surfaces.

Non-conductive materials such as elastomeric spacers shall be used to keep aluminium

alloy parts from direct contact with steel or other dissimilar metals in the presence of

moisture to avoid galvanic corrosion.

All parts of the enclosures shall be surface treated during manufacture to ensure protection

from the effects of moisture during transportation, prolonged storage, installation and

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 21

service. All materials shall be selected to minimise the potential for corrosion under their

service conditions.

Application and repair of all organic barrier coatings shall be in accordance with the

written instructions to be provided by the manufacturer of the coating(s). Surface

preparation prior to coating shall be by sweep blasting as specified in Appendix I of AS/NZS

4680, unless not required by the coating manufacturer (e.g. when using an etch primer over

degreased new galvanizing).

Full details of all paint systems offered shall be provided with the tender and shall be

approved by MPA.

1.21 Painting and Durability

Protection provided by both the column materials and the coating systems, may be shorter

than the specified intended life of the lighting column, and due consideration should be

given to the maintenance programme or renewal requirements at the planning and design

stage.

Durability is expressed in terms of the material or coating life to the first major maintenance.

The specified intended life is dependent on both the atmospheric and foundation soil

corrosivity classification for the local micro environment.

The durability of a lighting standard in its environmental exposure shall be such that it

remains fit for purpose during the design working life given the appropriate level of

maintenance.

Surfaces shall be prepared and paints or coatings applied in accordance with vendor

recommendations or coatings specialist recommendations. Paint all mild steel, proprietary

equipment, components exposed to the view of occupants and components likely to

corrode.

The contractor shall allow for the painting with a good quality paint specification of all

equipment, e.g. fans, and other plant items, mounting brackets, supports, etc., (whether of

wood or metal) particularly where corrosion or rotting is possible.

This shall include the following:

• All steel supports.

• All steel equipment and panels.

• Immediately inside all inlet and exhaust louvers.

Immediately before any equipment is delivered to the site, assembled or erected, all

surfaces which require painting and which will be inaccessible after assembly or erection

shall be thoroughly cleaned and painted.

Immediately after the installation of equipment, the sub-contractor shall check the paint

and touch up all damaged spots. If signs of rusting are apparent, rusted areas shall be

cleaned, primer painted and touched with finish paint.

After the primer coating has been approved by the Engineer the contractor shall paint the

steel pipework with a white top coat. No insulation shall be installed on the pipework until

the top coat has been inspected and approved by the Engineer.

Mitestingscellaneous steel supplied by the subcontractor shall be painted to the Engineer's

approval and finish coated such that it blends with the existing plant.

Welds made by the contractor shall be properly cleaned down before being painted.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 22

Exterior painting shall not be done in rainy, damp, or dusty weather. All surfaces shall be

completely dry at the time of painting.

Where possible all shop painting shall be by spraying. Where shop applied paint surfaces

are damaged they shall be made good to "as new" condition at the completion of the

Contract.

1.21.1 Park Painting

To accommodate any painting by another Contractor for the Principal. The MEC

Contractor shall undertake their works:

• To accommodate the physical paint application without detrimental performance of

the equipment or system.

• In a sequence that allows the services to be painted, to be agreed with the Principal,

e.g. post first fix painting prior to second fix installation of equipment.

All MEC equipment and materials requiring masking shall be masked by the MEC

Contractor prior to painting, overspray that hinders the performance of the equipment or

systems shall be cleaned according to the equipment manufacturers and paint system

manufacturers’ recommended cleaning procedure

1.22 Galvanising

Galvanising shall be by hot dipped process for all components, with a thickness of zinc

coating as specified in the relevant standards. The zinc coating shall be smooth, clean,

uniform thickness and free from all defects. The preparation for galvanising and the

process of galvanising itself shall not in any way adversely affect the mechanical properties

of any coated materials. Fabricate all items with this in mind. Inadequate consideration of

the thermal stresses during galvanising will lead to distortion and subsequent rejection by

the Engineer.

Where practical, all damaged areas, e.g. all drilling, punching, cutting and bending of

parts shall be completed and all burrs removed before the galvanising process is applied.

Where this is not possible a cold galvanising system shall be used to make good the

damaged area.

1.23 Identification

1.23.1 General

Identify the Works as required by the relevant standards or regulations or as otherwise

indicated herein.

Ensure colours, letters, arrows and labels are plainly visible at the angle from which the

Works are most likely to be viewed. Use English.

1.23.2 Marking

All lighting columns and outreach arms shall be clearly and durably marked with the

following information:

• Name, identifying mark or symbol of the manufacturer

• Year of manufacture (or at least the last two digits of the year in which the marking was

affixed)

• Manufacturers model number or identification reference

• Impact classification and performance class (F if passively safe/frangible, blank

otherwise).

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 23

The form of marking may be either with a plate setting out in full the information above; a

plate with a decipherable single key provided by the manufacturer; a securely fixed label;

or a bar code formed either in the material or by painting or by hard stamping. The

identification plate, label or marking shall be of the same durability as the intended life of

the lighting column. The identification marking and accompanying information shall be

placed on the product itself (not on base compartment door) and be recorded in the

accompanying documentation.

Where segmented columns are used, each segment shall be appropriately marked to

enable replacement parts to be identified and ordered if damaged.

Uniquely identify such items using a numbering system conforming to that shown on the

Drawings for major equipment items. Uniquely list such items in the Operating and

Maintenance Manual.

Attach levels by instant adhesive or rivets. Do not mount labels on removable covers.

Where required by individual Specifications, proposed labels shall be submitted to the

Contractor for Review prior to production of the labels.

1.23.3 Reticulated Services – General

Identify pipework, ductwork, trunking, cable tray, conduits, etc with letter and colour

coding as listed under the individual specifications. Apply identification lettering and

banding:

• For buried and concealed runs (including in floors and walls) – the points where the

service disappears/reappears.

• For concealed runs in ceiling spaces – every 5m but at least once at point of entry to/

exit from ceiling space(s).

• For exposed runs – every 20m but at least once within each space.

The identification lettering shall be 25mm high, or half the height of the service that it

identifies, whichever is smaller.

Where services are required to be painted, extend the identification band colour

throughout the length of the service, except where otherwise directed for services that are

exposed to view.

1.24 Operating and Maintenance Manuals – General

1.24.1 General

Where there is requirement to provide an Operating and Maintenance Manual. Use authors

and compilers that are experienced in the maintenance and operation of equipment and

systems installed, and in editorial ability. Include all necessary information to enable the

Contractor to efficiently operate and cost effectively maintain the systems.

Provide three hard copies and an electronic (PDF and Excel) copy of the manual.

Electronic copies shall follow the same structure as the hard copy complete with hyperlinks

from the contents page and each section to allow speed of navigation. The electronic

copies may be provided by wither USB drive and/or CD.

All design documentation shall be as-built and submitted to the MPA for comment and

acceptance.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 24

In addition, the Contractor shall submit a Test Result document that includes copies of all

tests completed throughout the Contract.

The MPA Engineer will review the as-built Test Result documents. Any comments will be

acted upon by the Contractor and a final set issued before Practical Completion is

achieved and a certificate to this affect issued by the MPA Engineer. The Contractor shall

also update any affected NZTA records or systems in accordance with current practice.

1.24.2 Format

The format of the O&M Manuals shall comply with the following:

Table 9 – O&M Format

Format Requirement

Binding A4 size, D type, 3 ring binders with black plastic or vinyl faced hard covers.

Cover Title

“MEMORIAL PARK INNER CITY BYPASS” for MEMORIAL PARK ALLIANCE 30 point

Operating and Maintenance Manual 24 point

(Name of service) Services 24 point

Spine

“MEMORIAL PARK UNDERPASS” 24 point

Operating and Maintenance Manual 16 point

(Name of service) Services 16 point

Volume (number) 16 point

Lettering Gold HELVETICA X/BOLD CONDENSED 20 UPPER CASE. Silk screen or hot foil blocking

printing process.

Paper 80 gsm copy paper. Xerox or other long-lasting copying process.

Dividers Use durable index tab dividers between each element, with the section number

typed on the tab and section name typed on the divider.

Contents List Provide at front of each volume, listing contents of all volumes. Provide at front of

each section, listing contents of each section.

1.24.3 Content

Table 10 – O&M Content

Section Sub-section To contain

1. Introduction 1.1 Sub-contractors/

Suppliers/ Specialist

Trades/ Contractor

to this contract.

— Names

— Addresses

— Phone

— Facsimile

— Email

1.2 Termination of

defects liability.

Information in table format of different equipment

supplied and expiry dates for defects liability

1.3 Brief description

of Purposed of

Manual.

Include an explanation of the purpose of the manual

and a brief description of each section included in the

manual. Describe that in general, Section 3 (Operating

Instructions) details instruction for the building owner and

Section 4 (Routine Maintenance) is intended for

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 25

Section Sub-section To contain

engineering personnel.

1.4 Brief description

of overall system.

Provide a description of the overall installation covered

by the manual.

1.5 External parts

and components.

Where parts of the installation are supplied under the

other contracts or by the owner, related information shall

be included in the manual or expressly excluded.

1.6 Table of

contents.

Table of contents for manual

2. Description of

the Systems

2.1 Description of the

system installed

This section is to have a technical description of each

individual system, including function, normal operating

characteristics, limiting conditions, and interfaces with

other installations. Describe type and location of major

equipment.

2.2 External parts

and components.

Where parts of the installation are supplied under other

contracts or by the owner, or were existing, describe how

the Works relate to those parts.

3. Operating Instructions Including but not limited to

— Procedures necessary to operate the plant under

normal operating conditions.

— Other operations which may be carried out by

unqualified personnel under abnormal or emergency

conditions.

— Operating procedures under seasonal changeovers.

— Full operational instructions and warnings.

— Operational set points.

— Fault finding procedures.

— Day-to-day routine operations.

— Explanation of alarm conditions and record of alarm

set points.

4. Routine Maintenance Routine maintenance descriptions on every element of

the system installed. This shall include

— Detailed maintenance and servicing instructions.

— Recommended spares list.

— Recommended periodic maintenance.

— Recommended torque settings.

5. Manufacturers Details A table detailing the New Zealand agents for all of the

components supplied.

6. Equipment Details Including but not limited to

— Part numbers of all equipment modules.

— Complete internal wiring and component drawings

including individual assemblies and cards.

— Component data sheets for all of the components

supplied.

7. Testing and Commissioning Results Including but not limited to

— Record all physical details and cable sizes.

— Have a Set-Up Sheet documenting all

optional/adjustable settings.

— Contain a completed copy of the factory

commissioning "Check-Sheet".

— Contain a complete copy of the site commissioning

‘Check Sheet’.

8. Certificates and Warranties Including but not limited to

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 26

Section Sub-section To contain

— Copy of the Certificate of Compliance (COC).

9. Post Completion Modifications and

Adjustments

List of all post completion modifications that have been

carried out on system.

10. As-built drawings Drawings in A3 format. Hard copy manual to include a

set of Construction Record Drawings legibly reproduced

on A3. Fold to A4 size such that Drawings can be

unfolded without removal from ring binder.

1.24.4 As Built Drawings

As built drawings shall be submitted by the Contractor for Approval by the Engineer.

The as built drawings shall comply with MPA drawing protocols, standards, procedures and

processes, a copy of these are available from MPA.

The as built drawings shall be at a scale agreed with the engineer, they shall not be less

than:

• 1:20 or 1:50 scale for details

• 1:50 or 1:100 scale for sections and elevations

1.25 Construction Producer Statements and Certificates of Compliance

In addition to the general requirements for Practical Completion as defined in the

Conditions of Contract, the following specific requirements shall apply for the MEC sections

of the Works:

1) Construction Producer Statements: Required for each relevant section of the Building

code, in a form acceptable to the relevant Building Consent Authority.

2) Electrical Certificates as required by the Electrical Act and Electricity Regulations.

a) Declarations of Conformity (DoC) for electrical systems/equipment for which the

Subcontractor is responsible for design and/or selection as specified in respective

trade sections of this Specification.

b) Electrical Certificates of Compliance

3) Seismic Certificates of Compliance – Construction: Provide inspection and certification

of all seismic restraints.

4) Fire Rated Equipment and systems.

5) Any 3rd (third) party certifications as and when required.

6) Contractors Certificate if Compliance: Required to certify that the work undertaken has

been carried out in accordance with the contract documents.

1.26 Seismic Performance

1.26.1 Application

This section applies to the design, support and fixing of all MEC systems and equipment,

including floor, roof, ceiling or wall mounted, suspended, and vibration and non-vibration

isolated systems.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 27

1.26.1.1 Park works

The seismic design and installation compliance criteria for the Park MEC works shall include

but not be limited to:

1) The greater of:

a) Design for seismic actions (forces and displacements) in accordance with NZS 4219

(2009) and this Specification, or

b) Design for seismic peak ground acceleration of 0.74g and this Specification

2) Where the requirements of this Specification are in addition to the requirements of NZS

4219, the requirements of this Specification shall apply. (Additional requirements

extracted from ASHRAE, Tauby et al “Practical Guide to Seismic Restraint”, with the

objective of reducing the need for specific seismic design in accordance with NZS4219

Section 4.)

3) Supports and fixings include structural members, braces, skirts, legs, saddles, pedestals,

cables, guys, stays, snubbers, tethers and elements forged or cast as part of the

component.

4) Accumulated loads: The accumulated load of multiple systems/equipment to any given

support (with or without seismic restraint) shall be limited so as not to exceed the load

limitations of the support assembly or those structural load limitations established by the

Engineer.

Certificates as required by Standards, this Specification or the specific technical

specification.

1.26.2 Design

General

Any designs by the Contractor shall include

1) Design for seismic actions (forces and displacements) in accordance with NZS 4219

(2009) and this Specification. Where the requirements of this Specification are in addition

to the requirements of NZS 4219, the requirements of this Specification shall apply.

(Additional requirements extracted from ASHRAE, Tauby et al “Practical Guide to

Seismic Restraint”, with the objective of reducing the need for specific seismic design in

accordance with NZS4219 Section 4.)

2) Supports and fixings include structural members, braces, skirts, legs, saddles, pedestals,

cables, guys, stays, snubbers, tethers and elements forged or cast as part of the

component.

3) Accumulated loads: The accumulated load of multiple systems/equipment to any given

support (with or without seismic restraint) shall be limited so as not to exceed the load

limitations of the support assembly or those structural load limitations established by the

Engineer.

1.27 Alternate Designs

Designs alternate to the lighting design presented on the Drawings may be provided to the

designer for consideration. Design alteration shall only be in the form of luminaires (NZTA

approved), all other elements of design that require co-ordination with the civil works shall

remain. Alternate designs must meet the following requirements:

• Utilize the same power supply and control architecture as shown in the drawings;

• Be compatible with the documented system operation and provisions; and

• Meet the requirements of this specification and the Project Documents.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 28

This section outlines the Design Criteria to which the lighting installation must adopt and

must comply. It is noted that, should an alternate design be adopted, the Design

Documentation requirements of the Project Documents may apply depending on the level

of deviation from the current presented design. It is further noted that design calculations

will be required and submitted to URS for review.

1.28 Site of the Works

The site of the works is as described in the specification.

Access times for delivery shall be co-ordinated with the Principal.

Ensure that the appropriate licences and approvals are obtained for work in those

particular areas.

1.29 Drawings

The following drawings are associated with and should be read in conjunction with this

document. Where a conflict exists between the drawings and this Specification, the

Engineer shall be consulted for a determination.

Table 11 - List of associated drawings

Drawing Number Drawing Title

MP-10-100 COVER SHEET & KEY PLAN

MP-10-101 DRAWING LIST & LEGEND

MP-10-111 SITE POWER LAYOUT (GRID 01-19)

MP-10-112 SITE POWER LAYOUT (GRID 18-34)

MP-10-113 SITE LIGHTING LAYOUT (GRID 01-19)

MP-10-114 SITE LIGHTING LAYOUT (GRID 18-34)

MP-10-115 PARK DB SITE PLAN

MP-10-116 PARK DB GENERAL ARANGEMENT

MP-10-117 DB-P1, DB-P1 EV, DP-P1 AWM & DB-P2 SCHEMATIC

MP-10-118 DB-P1 LIGHTING CONTROL SCHEMATIC

MP-10-119 DB-P2 LIGHTING CONTROL SCHEMATIC

MP-10-120 LIGHTING DETAILS 1

MP-10-121 LIGHTING DETAILS 2

1.30 Approvals

Details of fully compliant designs including calculations confirming compliance with the

design criteria and drawings shall be submitted for approval by the Engineer before

commencing manufacture of the order.

Alternatives shall only be considered if submitted and confirmed as fully compliant, the

onus shall be on the Park Lighting Sub-contractor to proof full compliance with the design

and specification criteria.

The Park Lighting Contractor shall submit a sample of each type of light fitting and its

associated bracket system for approval by the Engineer prior to commencing manufacture

of the order.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 29

2. SUPPLY OF EQUIPMENT AND MATERIALS

2.1 Shipment

Equipment shall be packed to prevent damage in transit. Packages shall be clearly

labelled with:

1) Order number.

2) Equipment number.

3) Package number and total number of packages.

4) Gross weight.

All equipment shall be packaged in a manner suitable for handling during transport and

storage to avoid damage components or any painted surfaces.

The Contractor shall submit their proposals to the Principal for protection of equipment

during transit. The responsibility for safe and damage free delivery remains with the

Contractor.

Heavy and bulky equipment shall be provided with adequate lifting fixtures to facilitate

ready handling during transit and on arrival at site. All equipment shall be shipped below

decks.

2.2 Materials

Materials include all building elements, plant, equipment, machinery, components, fluids,

consumables and the like, that form part of the Contract Works.

Materials shall be:

• New unless specified otherwise.

• To the latest and most appropriate technology.

• Suitable for the intended use.

• Proven in service.

• Compatible with surrounding and joining materials.

• Suitable for installation in the intended space with allowance for long term

maintenance access.

• Supported by locally available spares and service.

• Consistent in brand, type and size for each material item.

• Supported by appropriate servicing facilities and locally available spare parts.

Deliver materials to site with the maker's label intact and protect all materials. Where

practible materials should be delivered “just in time” for the required works, with minimal

storage durations. Protection shall include safe storage and preventing ingress of foreign

material, or damage to internal and external parts. Replace or make good any damaged

materials.

Where any material is mentioned by a trade name or by any other specific reference, it is

for the purposes of indicating suitable standards of quality (including but not limited to

finish, durability and serviceability), space requirements and structural loading for the

purpose intended, and for no other reason. Material characteristics other than those

specifically covered by the Drawings and Specifications, shall be at least equivalent to

those of any mentioned trade name, or if no trade name is mentioned, typical of the

respective material kind.

The Contractor shall:

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 30

• Provide consistent type, brand, size, quality and appearance for the whole quantity of

each material or equipment item.

• Deliver materials and equipment to the Site with the Manufacturer’s label intact and

with the Manufacturer’s written installation procedures.

• Store and protect all materials and equipment furnished in connection with the Works.

Protection shall include preventing moisture and foreign substances from entering the

working parts or damaging the structure or finish of materials and equipment. Make

good or replace, at the Engineers discretion, any damaged materials or equipment

from whatever cause, at no extra cost to the Principal.

2.3 Packing Requirements

All equipment shall be carefully packed and secured for transport to ensure that the

equipment is protected from all dust and climatic conditions during loading, transport,

unloading and subsequent storage in the open. Equipment shall be suitably packed and

protected against vibration, movement and shock that may occur during loading and

transport. Particular care in packing shall be taken when the equipment is transported by

road.

Instruments and other fragile items shall be packed separately. All items that include

delicate equipment shall be sealed in polythene sheeting. Silica gel desiccant or vapour

corrosion preventive shall be inserted within the polythene packing.

All packaging shall comply with the New Zealand government customs and quarantine

requirements.

2.4 Storage

All equipment, whether fabricated or not, shall be stored above ground on pallets, skids or

other supports and adequately protected from the weather and corrosion. Items that are

damaged will be subject to rejection.

2.5 Identification and Documents

All equipment supplied under this Contract shall be clearly identified on the outside of any

case with the type and number of items contained therein and the gross weight. Large

crates are to be marked on three sides, and smaller crates which can be easily

manhandled are to be marked on at least two sides.

The names of haulage firms, shipping companies, shipping agents, customs authorities and

any special handling firms shall be advised to the Principal before the equipment is

despatched. One copy of each applicable shipping specification, packing list, mass note,

packing note and the relevant control numbers of consignment notes, waybills, bills of

loading, customs clearance certificates, tranship notes and the like shall be forwarded to

the Principal as each paper required is raised, together with expected dates of departures

and arrivals en route.

2.6 Spares

Spares necessary to support normal operation and maintenance requirements for a period

of 12 months shall be provided under the Contract.

Spares shall be:-

1) Re-stocked to the recommended inventory levels on completion of the warranty period

2) Suitably packed for long term storage.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 31

3) Indelibly labelled on the outside of the packaging so that the part and its purpose can

be accurately identified without unpacking.

2.7 Date Processing

Hardware, software and firmware products and systems provided under this Contract,

including proprietary equipment incorporating date aware electronic controls or

embedded microchips, shall accurately process date data (including, but not limited to,

calculating, comparing and sequencing) from, into and between centuries, including leap

year calculations and day light savings times, when used in accordance with the product

documentation provided by the Supplier.

2.8 Power Quality and Electromagnetic Interference

The Supplier’s attention is drawn to supply voltage variations at the Site. These may be

expected to occur beyond the normal limits referred to in the Electricity Regulations. These

variations may include harmonics, surges, sags and impulses (spikes) and may be

generated either outside or within the installation.

Provide appropriate devices such as power conditioners, voltage stabilisers, harmonic filters

or surge diverters as necessary to protect all equipment supplied under the Contract which

may be sensitive to supply voltage variations. The Supplier shall be responsible for the

adequate selection and provision of all necessary protective measures.

The Supplier’s attention is also drawn to the high electromagnetic environments caused by

radio transmitters used by Police, Fire Brigade, and Security. Mobile Phone Companies and

other services, which may cause premature failure of or interference with electronic

equipment. Provide all necessary earthing, screening, protection etc, so that the system will

operate satisfactorily and without degradation in this environment.

Where cable routes are not designated on the Drawings, route cables so as to minimise the

effects of electric and magnetic fields on other equipment. Run single core cables in trefoil

with the neutral conductor adjacent the phase conductors. Route cables clear of

computer or VDU suites and the like. Route communication, control and instrumentation

cables using twisted screened cables as a minimum.

2.9 Construction Record Drawings – Equipment

2.9.1 General

Provide Construction Record (As-Built) Drawings recording the specific design details for all

equipment items as listed under the individual Specifications.

2.9.2 Submission

Submit the information to the Principal for review four weeks prior to the date of

completion.

2.10 Training

The Contractor shall submit for review by the Principal the Training Plan. It shall include as a

minimum a range of staff for which training is recommended and a training plan shall be

submitted by the Contractor to the Principal at least three (3) months prior to the issue of

the Taking-Over Certificate for the Works.

The Contractor shall provide input relating to the Works to the Training Plan in accordance

with the overall philosophy for training.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 32

The Training Plan shall be prepared based on, but not limited to, the System Operations Plan

and the System Maintenance Plan.

2.10.1 Training Plan

Where required by the individual Specifications, the Contractor shall include the cost of the

services of qualified instructor(s) to instruct the Principal and Owner’s operating and

maintenance personnel in the operation, adjustment, care and maintenance of all

equipment required for fully functioning equipment or systems.

Instruction shall be performed at a time approved by the Principal after all equipment and

systems are installed, completed, adjusted and operating to specific requirements.

The Contractor shall notify the Principal when instructions will be given.

Qualifications of instructor(s) shall be subject to the approval of the Principal.

2.10.2 Training Equipment

With the prior agreement of the Principal, the Contractor may use the Permanent Works

being erected, tested or commissioned for the training of the Principal’s staff. In general the

Contractor shall not use spare parts for this purpose.

The Contractor’s Training Plan shall be supplemented by hands on experience, alongside

the Owner’s personnel, during the testing and commissioning of the Works.

Training course notes shall be entirely compatible, and, where appropriate, cross-

referenced to the manuals supplied by the Supplier as part of the Operation and

Maintenance documentation.

The Contractor shall provide such written or printed matter, functional equipment, samples,

models, cutaway equipment, slides, films and other instructional material as may be

necessary for training. Such equipment and material shall remain the property of the

Principal and shall be sufficient both for the persons trained by the Contractor and for those

to be subsequently trained by the Principal’s instructors.

The Contractor shall provide a trainer’s guide for each training course. The guide shall

include the course agenda, objectives, list of resources and facilities required, detailed

lesson plans, presentation notes, discussion guides, training aids and job aids, test papers,

criteria and methodology for testing and assessment, and all other things that will enable

the Principal’s own trainers to carry out repeat or refresher courses in the future.

2.10.3 Training Manuals

All project specific training documentation shall be written in concise and simple English

making maximum practicable use of diagrams, drawings, photographs and screen dumps.

The Training material shall be prepared on the basis that the actual operating and

maintenance manuals will be the foundation of the training courses.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 33

3. ON SITE INSTALLATION

3.1 Free Issued Equipment

The Contractor shall inspect any equipment or material supplied by the Principal or any

other party prior to any work commencing. Any such items that are noted to be damaged

or otherwise non-compliant with the specifications provided shall be brought to the

attention of the Principal at the earliest opportunity.

In the event that any equipment is damaged during the Works by the Contractor, the

Contractor shall repair the damage at their cost to the satisfaction of the Principal.

3.2 Contractor Supplied Documents

Any anomalies between documents must be referred to the Principal for resolution as soon

as practicable and prior to construction.

3.3 Material Substitution

A substitution of materials or equipment specified under the contract may be proposed by

the Contractor if:

• Specified products are not available.

• Indicated lead times may cause delay to the Works.

• Substitute products are considered to be equivalent or superior to those specified.

The Contractor shall provide all information necessary for the Principal to be able to

adjudge suitability of the substitution.

The Principal shall not be obliged to accept any substitutions unless a specified product is

not available and a substitute has been assessed to be suitable.

No substitution of materials or equipment shall be made without prior written approval by

the Principal.

3.4 Coordination and Setting Out

The Contractor shall install the Works according to the “Issue for Construction” Drawings.

However, the Contractor shall be responsible for the detailed setting out of his section of

the Works so as to:

• Co-ordinate with other Trades, particularly with respect to other building services,

including area by area discussions with all appropriate Trades, having all up to date

Drawings with them at these discussions. If the Principal is not present at any of these

area by area discussions, then brief notes of the conclusions reached at that discussion

are to be prepared by each Trade and submitted to the Principal to enable it to check

that this process of setting out discussions, is working properly.

• Locate the Works in the spaces allocated for the purpose with suitable access and

clearances for normal and long term operation and maintenance requirements.

The Contractor shall confirm all dimensions on site prior to fabrication.

Where a discrepancy exists which prevents successful setting out and co-ordination, obtain

clarification instructions. Should the Contractor consider that it is not possible to coordinate

the setting out of their work in the space available, they shall advise the Principal who shall

designate which Trade shall sketch a proposed solution and submit it to the Principal for

consideration and for the Principal to issue an instruction on how to proceed.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 34

The Contractor shall discuss upcoming site work on a daily basis with the Principal to ensure

that their works do not adversely impact on other subcontractors or separate contractors

working on the Project

No account will be taken of any abortive manufacture, fabrication or installation work

which has been due to the failure of the Contractor to carry out proper setting out and co-

ordination.

3.5 Installation

Workmanship shall be:

• In accordance with best modern trade practice.

• Carried out by appropriately qualified and experienced tradesmen and supervised

apprentices.

• Carried out under the supervision of a competent foreman.

• To a high standard of construction and leave an efficient, robust, tidy and fully

operational installation.

Install materials and equipment in accordance with the manufacturer's written instructions.

Provide labour and materials required to clean, treat, shim, grout, adjust, alter, support or

do any other work on materials and equipment which the manufacturer, or his agent, may

consider necessary to achieve a satisfactory installation.

Provide proper connections and interfacing between relevant materials and equipment,

such as to avoid such interfacing causing damage to or adversely affecting the

performance or durability of the Works.

If materials are required to comply with product certification schemes, use them in

accordance with the certification requirements.

Where material samples are required, incorporate in the works only those materials which

match the approved samples.

Arrange reticulated services to run parallel with adjacent services, building elements, and

grid lines where possible and practical.

Ensure access to services is not impeded.

Provide for movement in both structure and services.

3.6 Fire Stopping

The Contractor shall provide fire stopping around and within the Works passing though fire

rated compartment walls, ceilings or roofs. Only fire stopping materials certified and

approved by the Contractor shall be used.

The Contractor shall maintain the continuity and effectiveness of fire separations around

penetrations, and in gaps between or within fire rated building elements, by the use of

approved fire stops. Fire stops shall have certified fire resistance ratings (FRR) no less than

that required for the separation in which they are installed.

Fire stop certification shall be based on tests carried out by an independent laboratory in

accordance with internationally recognised fire resistance rating test procedures.

Select fire stop materials that are appropriate for the type and size of the gap or

penetration, and for the type of material and construction used in the fire separation.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 35

Materials and methods of installation used on site shall be identical to those of the

prototype used in their FRR tests.

Fire stop materials shall generally include:

• Plastic pipes, including plastic water pipes: Fire rated intumescent collars (closures).

• Metal pipes: Fire seal gaps between pipes and fire separation with a material capable

of maintaining the fire rating.

• Electric cables: Fire seal gaps between cables and fire separation with a material

capable of maintaining the fire rating.

Fire stops for penetrations in hollow construction shall protect the penetration over the full

depth of the fire separation.

Fire stops shall be fixed and supported such as to:

• Be restrained from moving or parting from the surfaces of both the penetration and the

fire separation during a fire.

• Allow for normal expansion and contraction of the services that run through the

penetration.

Specific requirements for penetrations in fire rated dry wall and floor construction (in

addition to the above requirements) shall include:

• Through penetrations: Provide trimmers around penetration to support the fire rated

lining material.

Partial penetrations (e.g. for light fittings, socket outlets, switches and the like): To be in

accordance with the specific detail of the dry wall/floor system manufacturer.

3.7 Construction Record Drawings – On site Installations

3.7.1 General

Provide As-Built (Construction Record) Drawings recording the Works as installed by the

Contractor. Show the as installed locations and details of building elements, plant,

equipment, cables, piping, ductwork and the like. Include schematic drawings of each

system.

Where identified by the individual Specifications, update existing Construction Record

Drawings recording the Works as installed by the Contractor. Do not create new Drawings if

it is practicable to record the work by updating existing Drawings.

Retain one “Mark Up” set of the construction Drawings at the Site. Neatly mark up all

changes to the installed work from the Drawings, including all amendments under site

instructions or contract instructions, as they occur. These prints shall be available for

inspection on request.

All CAD files are to comply with MPA CAD processes, procedures and formatting.

All drawings shall have the appropriate external reference files (Xrefs and Images)

referenced into the drawings (e.g. “Xref …. overlayed”). External reference files shall be

overlayed to Modelspace with the insertion point being 0,0. Do not alter any external

reference file names. Do not include a path name to any attached file in the drawing.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 36

.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 37

4. INSPECTIONS, SNAGGING AND DEFECTS

The Contractor’s works shall be subject to review by the Engineer to assess if the Works

comply with the Contract.

4.1 Inspection prior to closing up

The Contractor shall via the Principal advise the Engineer that works are to be closed up

such that MEC or ITS services will no longer be visible for snagging.

10 working days’ notice shall be provided to the Engineer.

No works shall be closed up with the Engineer’s approval.

The Engineer shall attend and advise if the works can be closed up, if the works do not

meet the Contract requirements the Contractor shall remedy the works and invite the

Engineer to inspect the works again, the process shall be repeated until the Engineer is

satisfied.

Agreement to closing up by the Engineer does not alleviate the Contractor of their

responsibilities.

Should works be closed up without the Engineer’s agreement the Contractor shall arrange

for the Principal to open up the works for inspection and make good following agreement.

The cost of opening up and making good shall be at the Contractor’s expense and not

passed onto the Principal.

4.2 Snagging

The Engineer shall be advised by the Contractor via the Principal that the works or a sub-

section of the works are available for inspection and snagging, 10 working days’ notice

shall be provided.

At the time the Contractor advises the works are available for snagging the Contractor shall

provide their own snag clearance schedule demonstrating that they have inspected their

own works and cleared known snags.

The Engineer will attend site and review the works, passing a list of snags to the Contractor

while on site.

The Contractor shall be responsible for maintain a list of snags and logging the clearance of

the snags against a master schedule. Snags shall not be cleared unless agreed by the

Engineer.

Following rectification of the snag the Contractor shall invite the Engineer to re-review the

works, demonstrating the snag is cleared. This process shall be repeated until the snag is

agreed as cleared by the Engineer.

All snags shall be agreed as cleared by the Engineer prior to the Contract works being

offered or accepted as complete, and in any case prior to witnessing or testing.

Cosmetic snags that do not affect the operation or performance of the equipment or

systems shall be able to be cleared during testing, commissioning or witnessing so long as

the Contractor can demonstrate the clearance will not affect the equipment or system

performance.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 38

4.3 Defects

Defects in the Contractor’s works shall be advised by the Contractor or Engineer to the

Principal as soon as they arise. Corrective action shall be agreed with the Engineer prior to

installation.

Defects occurring before the Contract works are agreed complete shall be cleared prior to

the Engineers Witness testing or operational testing if the defect arises during the witness

testing.

Defects according flowing Contract works completion shall be cleared according to the

Contract.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 39

5. TECHNICAL

5.1 LV Power Distribution System

The system objective is to provide a safe and efficient LV power distribution system, which is

designed and installed in accordance with the specified standards and regulations. The LV

power distribution system is deemed to include the entire electrical distribution cabling,

cable joints, connection boxes and all switchboards.

The objective is to include all equipment, wiring, switching devices and other accessories

from the source of supply to the relevant distribution boards and to the end-use equipment.

All cables, switchgear and devices shall be dimensioned in accordance with NZS 3000 and

the current supply authority regulations. In particular all cables and switchgear shall be

suitably rated for the maximum load and the electromagnetic stresses arising from

prospective short circuit currents and earth fault currents under the particular installation

conditions.

Ensure the earthing and bonding of equipment and the earth leakage devices comply with

the requirements of AS/NZS 3000 and the current supply authority regulations to ensure

there is no danger to persons under fault conditions.

Obtain all necessary approvals and agreements from the supply authority and any other

relevant authorities.

Protective devices shall be suitable for protection against overload, short circuit and earth

fault current.

Effective disconnection devices shall be provided for easy and rapid operation in case of

danger and, suitable for disconnection during maintenance, testing, fault detection and

repair.

The arrangement of the installation shall be so as to precent mutual detrimental;

interference between different electrical installations and non-electrical installations, which

take into account electromagnetic interference.

5.2 Design Parameters

Footing design for the lighting columns shall be submitted by the column supplier for

approval by the designer.

All poles fitted with 17° up-cast light masts shall be fitted with a tilt adaptor, allowing a 10

degree luminaire up-cast to be achieved as required.

Lighting columns to local roads shall be co-ordinated with local councils. Contractors to

allow for any tie-ins that may be required during the construction process and/or temporary

works.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 40

5.3 Permanent Lighting Design

5.3.1 Maintenance Factors

Following the procedures outlined in ASNZ1158 (series) the maintenance factors (MF) for

lighting are:

Table 12 – Maintenance Factor(s)

HPS Fluoro (T8) LED

Lamp Lumen Depreciation Factor 0.91 0.91 0.95

Luminaire Dirt Depreciation Factor 0.88 0.88 0.89

Room Surface Dirt Depreciation 0.87 0.87 0.87

Maintenance Factor 0.70 0.686 0.74

AS/NZS Recommendation 0.80 0.80 0.80

5.3.2 Lighting Control

Park’s associated lighting to shall be controlled via a timer in series with photometer(s)

located on the roof of UAB building with manual override switch.

State Highway associated lighting control is via ripple control by Wellington Electricity.

5.3.3 Lamp Lumens

The lighting design LED luminance used for street lighting:

The lighting design has used the following LED Lumen outputs (where required to show

compliance with the annotated standards.

5.3.4 Quantities

Provide a price for the provision of Park Luminaires meeting the specification requirements.

Quantities shall be initially based on the drawings and the price offered shall not vary per

unit for quantity changes of ± 50. Cost shall include preliminary samples for approval; full

witnessed photometric testing at an independent testing laboratory, with electronic format

test results and full shop drawing submittal.

Price should reflect installation of body, site protection and installation of louvres, and clean

to achieve practical completion.

5.4 Luminaire performance

5.4.1 Luminaire construction

5.4.1.1 General

All materials, accessories and other related fitting parts shall be new and free from defects

which in any manner may impair their character, appearance, strength, durability and

function, and effectively protected from any damage from the time of fabrication to the

time of delivery and until final acceptance of the work.

The luminaire enclosures shall be fabricated special section. Enclosures may be constructed

of other metals, provided they are equivalent in mechanical strength and acceptable for

the purpose.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 41

All metal work shall be free from tool marks and dents and shall have accurate angles bent

as sharp as compatible with the gauges of the required metal. All intersections and joints

shall be formed true of adequate strength and structural rigidity to prevent any distortion

after assembly.

Housings shall be so constructed that all electrical components are easily accessible and

replaceable without removing fittings from their mountings, or disassembly of adjacent

constructions.

The copper content of all die cast aluminium luminaires shall be a maximum of 0.1%.

Minimal cut-off optic luminaires with an internal seal safe IP66 lamp chamber for optimum

light output to be used.

All castings shall be exact replicas of the approved patterns and shall be free of sandpits,

blemishes, scales and rust, and shall be smoothly finished. Tolerance shall be provided for

any shrinkage of the metal castings in order that the finished castings will accurately fit in

their designated locations.

All lamp sockets in luminaires shall be suitable for the indicated lamps and shall be set so

that lamps are positioned in optically correct relation to all lighting fitting components.

All luminaires shall be completely wired at the factory.

Yokes, brackets and supplementary supporting members needed to mount luminaires to

carrier channels or other suitable ceiling members shall be furnished and installed by this

Specialist Supplier.

For stainless steel fittings, all fastenings shall be stainless steel.

5.4.1.2 Temperature Rating

All luminaires and ballasts must operate within the temperature limits of their design and as

specified by British Standards Institute in the applications and mounting conditions herein

specified.

5.4.1.3 Voltage Rating

All luminaires (including all internal components) must be nominally rated 230V, single

phase, 50Hz. Luminaires must be capable of continuous operation anywhere in the range

of 230VAC +10% to -6% at the rated ambient temperature as described in Section 6.4. For

the avoidance of doubt this means up to a constant supply voltage of 253VAC.

5.4.1.4 Ballasts

Ballasts shall comply with AS/NZS 61347.2 and AS/NZSCISPR 15 and have an insulation rating

not inferior to Class H, in accordance with IEC 60085.

5.4.1.5 Igniters

Igniters shall comply with AS/NZS 61347.1, AS/NZS 61347.2.1 and AS/NZS 60927 and shall be

of the solid state type.

5.4.1.6 Control Gear

Control gear shall be high frequency, mounted in luminaire body, sized and arranged to

give maximum circuit watts per lamp at unity ballast lumen factor and no less than 0.95

lagging power factor. All control gear and lamp connectors to be interconnected using

high temperature, LSF cable. High frequency control equipment to have the performance

specification as follows:

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 42

5.4.1.7 Lamp Protection

Lamp protection shall be provided to prevent any failed tube from repeat starting

attempts.

Each ballast to be provided with over-voltage protection for short duration voltage pulses

as defined by DIN/VDE 0160.

Each high frequency ballast shall comply with the requirements of the standards listed in the

General MEC Specification, including but limited to BS800, BS5394, CISPR15, VDE 0107 and

VDE 0875(B) for mains conducted and airborne radio frequency interference.

5.4.1.8 Performance

Luminaires as described in this specification shall be installed at spacing as indicated on the

drawings. Luminaire output to design performance requirements shall be demonstrated by

the Park Lighting Contractor.

5.4.1.9 Independent Photometric testing

The Park Lighting Contractor shall include for and have each luminaire type tested by an

independent testing authority with calculations to support the test results.

The independent laboratory testing results shall be made available for the Principal’s

Engineer’s approval and submitted such that approval is obtained prior to manufacture

and delivery of the luminaires.

The independent testing laboratory shall be a certified laboratory and the report shall be

provided with paper and electronic copy of the results, including IES file format for lighting

modelling.

Independent means independent of the Park Lighting Contractor, Wholesaler, Supplier or

Manufacturer, or an associated company.

Certified means certified by an internationally recognised certification body for

photometric performance, ingress protection, vandal resistance.

Tests shall include photometric performance over the environmental condition and

temperature expected.

5.4.1.10 CIDs

Each luminaire shall be complete with horizontally arranged which shall be as approved

suitable for operating from specified control gear.

Lamps shall be equally spread in back box to maximise lumen output.

Lamp type shall operate within the optimum lamp output range

5.4.2 Luminaire performance

The luminaires shall meet or exceed the required lighting technical parameters (LTPs)

required by AS/NZS 1158. The drawings indicate a design/luminaire layout, based on

currently available in the market place, Park luminaires that are compliant with this

standard. Detail calculations are required to be submitted to show the proposed luminaire

will likewise comply with the LTPs.

5.5 Vibration

The lighting columns and the associated luminaires and lamps mounted on the columns

shall be designed, as a system, to withstand the vibration that is typically induced by wind,

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 43

and adjacent traffic, as well as seismic requirements in accordance with the TNZBM, and

AS/NZS 1170.

5.6 Cables and Wiring

5.6.1 General

The installation of cables and wires unless otherwise specified, shall be in accordance with

the requirements of the New Zealand Wiring Regulations and manufacturers requirements.

Jointing of cables shall not be permitted, without notifying the designer.

Any cabling passing through concrete (e.g. column foundations) shall be run in conduit

with large sweep radius bends. Cables shall generally be run in conduits unless otherwise

specified.

The contractor shall be deemed to have visited the site and made allowances for

coordination of all trenching, thrusting, re-instatement work etc.

All underground cabling shall be buried to a minimum of 600mm cover. Supply and install

cable pits as shown in drawings and/or where considered necessary to complete the

works. All cable pits in sealed areas shall be ACO “Polyconcrete” with lock down

“Rhinocast” lid or approved equivalent. All other cable pits shall be ACO plastic pit with a

“Polyconcrete” lid and shall be positioned in areas unlikely to be driven over.

The Contractor shall be responsible for the protection of cables during storage and

installation. Any repairs to damaged cables shall be authorised by the Designer prior to any

remedial works to repair cables.

During handling and installation care shall be taken to ensure that the cables are not bent

to an extent which may cause undue stress on the insulation or sheathing but in any case

not less than the minimum internal radius specified by the manufacturer. Cables shall not

be drawn through their minimum radius during installation.

All cable ends shall be kept sealed until the cable is required and any cables delivered

unsealed shall be tested and checked for suitability prior to resealing and accepting the

cable for use. Reseal after cutting and before re-use should more than one day lapse after

running out cables.

Damaged cables shall not be installed and the Contractor shall replace any cables which

have been damaged during installation. Replacement shall be carried out in accordance

with the requirements of this specification and procedures approved by the designer.

Segregation of functions shall be maintained throughout and cables shall be de-rated for

the installation conditions in accordance with AS/NZS 3008.

The Contractor shall immediately report to the Designer any visible/external damage to

cables and carry out an Insulation Resistance test on the cable in the designers’ presence.

Approved cable glands and terminations shall be of the correct type and size to suit the

cables.

Holes for mounting glands in plates shall be matched to the threaded portion of the gland

to allow ease of installation without excessive side clearance.

The neutral screen and/or steel wire armour of power cabling shall be bonded to the

earthing system at both ends of the cable run.

5.6.2 Cable Types

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 44

Unless otherwise specified power cables shall be in accordance with NZS-3008 and shall be

XLPE insulated with multi-stranded copper conductors. All underground cables shall be PVC

Neutral Screen with heavy grade 3.2mm PVC sheath.

Wiring within columns from the fuse-gear to the luminaires shall be 2c+E PVC insulated TPS

cables.

5.6.3 Termination of Conductors

The conductors in electrical cables shall be terminated in the relevant equipment terminals

in accordance with the appropriate connection schedule or connection diagram.

5.6.3.1 Cable joints

Cable branch joints in cable draw-pits shall be made with “Raychem”, “Raygel” type joints

with mechanical connectors, the appropriate joint type being selected to suit the size of

the cables used. The joints shall be made strictly in accordance with the manufacturer’s

instructions.

5.6.3.2 Pole connection boxes

Purpose made pole connection boxes shall be purpose made units of the “EKM” range

manufactured by “Raychem”, complying with IEC-60439. These comprise of impact

resistant thermoplastic, minimum ingress protection of IP43, with loop terminals for incoming

and outgoing cables, fuses and cable connections for the lighting pole circuits. The

appropriate size unit shall be selected to suit the cable sizes used.

Conductors terminated on stud type terminals shall be made with approved compression

type crimp lugs. After crimping the lugs shall be fitted with heat shrink sleeving and/or

preformed insulation boots, which shall extend over the whole termination so there is no

exposed metal.

Control wires shall be terminated using spade, blade or ring type crimp lugs, crimped with

the manufacturer's recommended ratchet type tool which does not release until the lug

has been properly crimped and which crimps on both the core and the insulation except

where Grafoplast 'Spark' pin markers are used. Crimp lugs, which do not cover the

insulation, shall not be acceptable.

All neutral screens shall be fitted with heat shrink insulation before the crimp lug is applied.

Refer Appendix A for specification sheets for the proposed connection boxes. The

specification sheets provided are extracts from the supplier (Transnet) catalogue, and

installer shall verify product specification currency prior to install.

5.6.4 Cable and Core Identification

Identification markers shall be held captive on the cores and shall be used to identify cores

in accordance with the drawings. "C" type ferrules will not be acceptable. The carrier

ferrules shall be of the appropriate size for the cable and shall be tight fitting over the

insulation. Wrap-round write-on, or adhesive ferrules will not be acceptable.

All wires identified by means of wire numbers shall be applied at each termination by

means of full circle plastic cable markers, Critchley Z or approved equivalent.

Equipment terminals shall be identified with matching terminal numbers shown on the

termination diagrams. Terminal numbers do not necessarily have to be identical with wire

numbers.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 45

A single unified core and cabling marking system shall be used in order to mark and identify

all cores, cables, terminals, switchgear and contactors. The system may be either manual or

computer generated with full inter-changeability. All characters must be etched not

printed and shall have the ability to be altered without withdrawal of the core or cable.

5.6.5 Earth Bonding

Earth continuity and connections shall be provided for all circuit cables in accordance with

the AS/NZS 3000 and the Electricity Regulations.

Provide earth bonding of extraneous metalwork as described in accordance with AS/NZS

3000.

Where wires are enclosed in non-metallic conduit or trunking, each circuit shall be provided

with a separate fully insulated protective earth conductor.

The metalwork of all luminaires shall be earthed through a separate earth terminal in the

fitting.

The results of tests shall be documented and submitted to the designer for comment prior to

the completion of the works.

The testing of the earth bonding shall be in accordance with AS/NZS 3000.

5.6.6 Cable Penetrations

The contractor shall be responsible for preparation of drawings for all builders work

penetrations, and shall provide coordination with other trades to avoid the risk of damage

to other services including cabling and pipework.

Where cables pass through penetrations in concrete structures they shall be perpendicular

to the surface and protective sleeves shall be installed through the penetration, with

adequate clearance to prevent damage due to abrasion.

Approval of the designer shall be obtained prior to cutting or drilling of any structural

elements.

The size of penetrations shall be kept to the minimum necessary.

5.6.7 Containment

5.6.7.1 General

All cables below ground shall be installed in buried conduits unless otherwise specified.

5.6.7.2 Conduit

Unless otherwise specified, conduit shall be rigid high impact PVC complying with NZS 2053.

Conduit fixings shall be selected to suit the surface to which they are fixed and the details

of fixings shall be submitted for the designer’s review prior to use. Conduit systems shall be

oil and watertight. Allowance shall be made for thermal expansion where it is required due

to site conditions.

Conduit runs shall be parallel to or at right angles to carriageways.

Conduit embedded in concrete shall have a minimum cover of 75mm tied to reinforcing

steel and installed in vertical, straight and uniform lines with easy sets or bends.

Conduits installed in the external areas shall be totally sealed to prevent ingress of water

including the connections to equipment and distribution boards.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 46

5.6.7.3 Segregation

Minimum cable spacing from other underground services shall be as follows:

• HV 300 mm.

• MV or LV 150 mm.

• Water/sewerage or Gas 200 mm.

• Telecommunications 200 mm.

Spacing from overhead power lines shall be in accordance with NZECP 34.

5.6.7.4 Jointing

Jointing of cables is not allowed without the approval of the designer.

5.6.7.5 Glanding

Glands shall be provided and installed for the termination of all cables. For unarmoured

cables compression type nylon glands shall be used, for armoured cables the cone grip

armour type brass glands shall be used.

All outdoor cabling shall be terminated with weatherproof glands at the bottom of

enclosures; all glands shall be of weatherproof brass type and fitted with appropriate

shrouds.

5.7 Electrical Switchgear

5.7.1 General

All switchboards shall be supplied by a single switchboard fabricator, who has been

regularly engaged in the manufacture of similar boards for at least 10 years. Switchboards

shall comply with the standards referenced in this specification and NZ Electricity Legislation

& Regulations.

5.8 Works Included

This specification applies to all switchboards installed on this project, which shall be

manufactured using the same enclosure system, busbars and switchgear types as far as

practically possible.

The switchboard supplier shall provide fully detailed drawings including general

arrangement, sections, single line diagrams and control diagrams. These drawings shall be

incorporated into the As-Built manuals after commissioning.

The Contractor shall provide a detailed short circuit analysis and protection co-ordination

study covering the whole distribution system including any downstream systems by other

contractors.

Provide a schedule of spare parts, which shall be handed over at commissioning.

5.9 Compliance with Electrical Codes and Standards

The switchboards offered shall be fully compliant with the specification and drawings and

any deviations from the specification shall be clearly identified and justified.

Switchboards shall comply with the standards and current NZ Electricity Regulations and

Codes of Practice and Local Authority requirements.

All distribution boards shall be protected to a minimum of IP65, Form 1, 18kA for 0.1second,

Service Conditions – Normal.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 47

The MPA “For Construction” issue drawings provided show typical dimensions; it shall be the

responsibility of the Contractor to verify the dimensions are fit for purpose and coordinate

with other contractors to ensure that the boards and panels fit into the allocated spaces.

All works and materials shall comply with the current issue [at date of contract award] of

the following codes and standards, which are referred to in the Specification.

In the absence of a specific standard reference, the work and materials shall comply with

the latest issue of relevant New Zealand Standards, British Standards and International

Electro-technical Commission standards with New Zealand / Australian Standards taking

precedence.

5.10 Particular Requirements

5.10.1 Workmanship and Materials

• Fully experienced personnel shall be employed who are competent to carry out work

on switchboards.

• Workmanship shall always comply with the best trade practices. All work shall be neatly

executed. Sharp edges, off plumb placement and untidy cable work will not be

accepted.

• All bolts used within the bus system shall be tightened with a torque wrench set to the

bus system manufacturers recommended setting.

• Provide a suitably sized, enclosed type cabinet, rated to IP 65, fitted with side-hinged

doors and quick acting latches.

• The cabinet shall be fabricated from folded stainless steel sheet, of 2 mm minimum

thickness. All materials and construction shall be appropriate for the local environment.

• The cabinet shall have a suitable vandal resistant polycarbonate meter viewing

window.

• Provide a three phase main incoming isolator and outgoing circuit breaker for each

circuit.

• Provide space for the energy provider’s meter.

• Contactors & controls as required.

• Auto-off-manual bypass for controlled circuits.

• A lockable IP56 series switched socket outlet on the outside (normally isolated at the

circuit breaker), complete with 30mA earth leakage protection.

• Busbars and connected circuits shall be capable of carrying continuously a total load

equal to the rated capacity of the incoming isolator without the temperature rise of any

component mounted with, or on, a chassis exceeding 20°C above ambient

temperature.

• Ensure that adequate terminal space is provided on neutral bars and that adequate

wiring space is provided.

• All metalwork shall be bonded to the earth bar and starred washers shall be used to

provide earth continuity between adjacent steel surfaces.

• All mechanisms susceptible to rust shall be cadmium plated or otherwise rust proofed.

• The new box shall be mounted on a raised smooth-finish concrete plinth to the

manufacturer's recommendations, with the top of the plinth finished 75mm above

adjacent ground level, with a 100mm wide mowing collar in grassed areas.

• Circuit breaker chassis shall comprise of proprietary 3 phase assemblies.

5.10.2 Operational, Maintenance and Access Requirements

The boards shall be designed and constructed to allow:

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 48

• Lockable cabinet with escutcheon & raised concrete plinth foundation with mowing

strip.

• Termination and removal of cables safely, without the need to isolate the whole board.

This means all cable terminations in wire-ways shall be totally shrouded to prevent

accidental contact with live terminations.

• Safe access to all control terminations with the board in operation.

• Safe access to all control and indicator fuses with the board in operation.

• Cubicle doors shall be open able without switching off the MCCB’s.

• Inspection of all components with the board in service. Note: to meet this requirement

fuse switch cubicles need to have their interlocks which can be defeated by means of

tools.

• All switchboards shall be built up from modular system assemblies, be dead front,

cubicle type, metal clad. The bus bar assemblies shall be an integral part of the modular

system, which shall be type-tested.

5.10.3 Physical Construction

• Seals on doors, covers and around any equipment inserted in doors/covers shall be

continuous extrusions, which provide the required degree of protection.

• Generous aluminium gland plates shall be provided for all switchboard cable entries

and exits. Their shape and thickness shall ensure rigid and secure glanding of incoming

and outgoing cables without any deformation of the gland plates.

• Welded and/or system prefabricated stainless steel plinths with a thickness of not less

than 3mm shall be provided.

• The board fixings shall be in accordance with the seismic requirements.

• All cubicles and cable doors shall be fitted with hinged doors. Removable covers are

not acceptable.

• Non-locking latches shall secure doors. Where required for safety “coin” turn latches

shall be provided to limit access. Provide complete shrouding to all accessible

terminations, to prevent accidental contact.

• All doors shall have adequate earth bonding.

• All terminals and components that are door mounted, shall be adequately shrouded

and insulated to prevent accidental contact.

• All physical shrouds, escutcheons and masking panels shall be constructed of clear fire

resistant material that is fit for purpose. This allows viewing of all terminations without

removal of the covers.

• Where wiring passes through one cubicle to another, there shall be a separate enclosed

wire-way to accommodate the cables.

• Control fuses and terminals may be located within the wire-ways provided they have

mechanical protection barriers and the switchboard type approvals are not

compromised.

5.10.4 Bus-Bars

• Provide high conductivity electro tinned copper bus bars mounted on insulated

supports of high-impact, non-tracking, high quality insulation material and adequate to

withstand the maximum prospective fault currents as specified. Type tests certificates

shall be provided as verification of the design in accordance with AS-3439-1.

Temperature rise shall be limited to 65 ºC. Tin plated aluminium switchgear connection

tags are not acceptable.

• Short circuit rating of busbars shall be the minimum required to withstand the maximum

prospective short circuit current plus 20% safety margin.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 49

• Bus temperature rise shall conform to AS3439.1 clause 7.3 (table 3). Bus temperatures

shall not exceed 110ºC at the maximum bus current ratings and an ambient 40ºC

temperature. Bus temperatures shall not exceed 90ºC at the 65% of the maximum bus

current ratings and an ambient 40ºC temperature.

5.10.5 Earth and Neutral Provisions

Neutral and Earth bar link to be arranged as shown in the drawings.

New distribution boards to be provided with a separate compartment to facilitate neutral &

earth terminations.

Neutral bars shall be of the same sectional area as the phase bars and earth neutral bars

shall be sized for the maximum short circuit currents, earth and neutral bars shall be

provided with separate terminals for each outgoing circuit and 10% spares.

5.11 Wiring and Terminations

The boards shall be complete with all internal connections.

• All control wiring shall be flexible multi-stranded insulated copper of minimum size

1.5 mm2.

• All control wiring shall have correctly fitted bootlace ferrule terminations.

• All wiring shall be neatly loomed and wiring to door mounted equipment and shall be

adequately "goose necked" using nylon cable ties.

• Mains and ELV wiring and terminals shall be physically segregated.

• All ELV wiring to have a minimum 600-volt rated insulation.

• All control wiring shall be identified with full circle type ferrule wire numbers. All

terminations shall be re checked two weeks after initial installation.

• Crimp terminations are to have correct size lugs terminated with crimp tools in good

condition and fitted with the correct dies. The use of scissors type crimp tools or pliers for

crimping is not acceptable.

• Flexible (welding) type cables shall only be terminated with one of the following:

o Correctly sized and fitted bootlace ferrule.

o Correctly sized and fitted hex or “half hex” crimp lugs (indent crimping is not

acceptable).

5.12 Chart Holders & MCB Charts

• A clear plastic rigid chart holder shall be permanently mounted on the rear of the

distribution cubicle.

• A circuit schedule chart shall be provided within the chart holder. The layout of the

chart shall be the same as the physical layout of the HRC fuses.

5.13 Labelling and Mimics

• All terminals shall be numbered with clip-in machine lettered plastic numbers.

• All control and contactor wiring within the panel terminals shall be identified with full

circle type ferrule wire numbers

• Each board and individual equipment such as contactors, relays, etc shall be identified

by means of laminated plastic name plates engraved with black letters on a white

background. This shall include the switchboard drawing numbers.

• Nameplates shall be screwed to the panels with metal thread or self-tapping screws.

Glued fixings will not be accepted.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 50

• All switches are to be labelled with the name of the function or service (as indicated on

the switchboard drawing) together with the switch rating and the fuse values.

• Labels shall be provided on each door that indicates what control fuses and sensors are

located behind the door.

• A label shall be provided at the Switchboard with the following text “WARNING; FAULT

CURRENT EXCEEDS 10KA”.

A label schedule for the switchboard shall be provided to the Designer for approval. This

shall include details of the size, wording, colour and material.

• Lettering size shall meet the following minimum requirements:

o 20 mm Switchboards, control panels, danger labels.

o 10 mm Power switches, selector switches, major switch positions, etc.

o 5 mm Minor switch positions, miniature circuit-breakers, fuses, relays,

contactors, connection boxes.

Note: where space is available no abbreviation or code shall be used - e.g. SWITCHBOARD

A, not SB-A.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 51

6. INSTALLATION

Drawings shall not be scaled for exact location of the luminaires. In general, the plans

indicate the proper locations of all luminaires.

6.1 Appurtenances

Install each luminaire properly and safely. Furnish and erect hangers, rods, mounting

brackets, supports, frames and all other equipment required. Hanger system for luminaires

must be compatible with support system.

6.2 Co-ordination

Furnish luminaires complete with appurtenances required for the proper, safe and

distortion-free installation in the various surfaces in which they appear. Determine surface

types from the drawings.

6.3 Instructions

Each luminaire shall be packaged with complete instructions and illustrations showing how

to install. Install luminaires in strict conformance with manufacturer’s recommendations and

instructions.

Replace blemished, damaged or unsatisfactory luminaires as directed by the Contractor.

6.4 Alignment

Rigidly horizontally and vertically align luminaires for true in-line appearance. The luminaires

shall be installed level and aligned along the true Park axis, taking into regard any support

or containment for the luminaire.

6.5 Wiring

All wire utilised for connections to or between individual lamp sockets and lamp auxiliaries

(i.e. wires which do not constitute “through circuit” wiring) shall be suitable for temperature,

current, and voltage conditions to which it is subjected.

6.6 Clean-up:

At the time of final acceptance by the Principal all luminaires shall have been thoroughly

cleaned with materials and methods recommended by the manufacturers, all broken parts

shall have been replaced and all lamps shall be operative.

6.7 Free Issued Equipment

The Contractor shall inspect any equipment or material supplied by the Principal or any

other party prior to any work commencing. Any such items that are noted to be damaged

or otherwise non-compliant with the specifications provided shall be brought to the

attention of the Principal at the earliest opportunity.

In the event that any equipment is damaged during the Works, the Contractor shall repair

the damage at their cost to the satisfaction of the Principal.

6.8 Contractor Supplied Documents

Any anomalies between documents must be referred to the Principal for resolution as soon

as practicable and prior to construction.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 52

6.9 Pre- Manufacture Submissions – On Site Installation

6.9.1 Layout and System Drawings

Submit layout Drawings of all areas as listed by individual Specifications, including plans and

elevations. Submit layout and/or schematic system diagrams for those items where design

forms a part of the Works.

Submit details of any changes to the Works as shown in the Drawings arising from the

acceptance of a deviation from the Tender Documents, drawn at the same or larger scale

as the Drawings.

Should an accepted deviation include an alternative electrical distribution design, provide

a single line drawing giving manufacturers' reference numbers for each protection device,

plus technical data and calculations showing discrimination and the capability of the

devices to withstand expected fault levels.

6.9.2 Design Details

Submit design details for all installations as follows:

• Colour schemes of exposed and exterior work.

• Identification and labelling schedule, including size, wording and materials.

• Seismic calculations, details and certification of seismic restraint details in accordance

with Section 1.26 Seismic Performance.

• Fire stopping details. Refer to Section 3.6 Fire Stopping.

• Trade specific design details as listed in the individual Specifications

6.9.3 Procedure

Submit two (2) copies of submission information to the Principal. Principal will review

information and advise comments or amendment requirements within 10 working days of

receipt. Contractor to revise accordingly and resubmit within 5 working days. Where

amendments/comments are of a minor nature which do not affect the technical or safety

integrity of the Works, the Contractor may proceed with the Works execution after due

consultation and agreement with the Principal.

Failure to make these submissions or any amended submissions on time shall not relieve the

Contractor of any of their obligations under the terms of the Contract.

Retain corrected, unsoiled, clean copies of all submissions for future inclusion in Operating

and Maintenance Manuals.

6.10 Work Plans and Co-ordination Meetings

The Contractor shall ensure that all work activities on site are properly planned,

documented and communicated in advance. In addition to the Subcontractor’s

installation programme, comprehensive Work Plans shall be prepared for the guidance of

the workforce. The Work Plans are to be submitted to the Principal for approval in advance

of each significant construction operation being carried out.

The Contractor shall keep the Principal regularly informed about actual progress of the

Works and the cause of any delays.

The Contractor shall allow for weekly attendance of two (2) hours duration by one, or more,

staff at the Principal co-ordination meetings.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 53

6.11 Material Substitution

A substitution of materials or equipment specified under the contract may be proposed by

the Contractor if:

• Specified products are not available

• Indicated lead times may cause delay to the Works

• Substitute products are considered to be equivalent or superior to those specified

The Contractor shall provide all information necessary for the Principal to be able to

adjudge suitability of the substitution.

The Principal shall not be obliged to accept any substitutions unless a specified product is

not available and a substitute has been assessed to be suitable.

No substitution of materials or equipment shall be made without prior written approval by

the Principal.

6.12 Coordination and Setting Out

The Contractor shall install the Works according to the “Issue for Construction” Drawings.

However, the Contractor shall be responsible for the detailed setting out of his section of

the Works so as to:

• Co-ordinate with other Trades, particularly with respect to other building services and to

the set-out of ceilings, including area by area discussions with all appropriate Trades,

having all up to date Drawings with them at these discussions. If the Principal is not

present at any of these area by area discussions, then brief notes of the conclusions

reached at that discussion are to be prepared by each Trade and submitted to the

Principal to enable it to check that this process of setting out discussions, is working

properly.

• Locate the Works in the spaces allocated for the purpose with suitable access and

clearances for normal and long term operation and maintenance requirements.

The Contractor shall confirm all dimensions on site prior to fabrication.

Where a discrepancy exists which prevents successful setting out and co-ordination, obtain

clarification instructions. Should the Contractor consider that it is not possible to coordinate

the setting out of their work in the space available, they shall advise the Principal who shall

designate which Trade shall sketch a proposed solution and submit it to the Principal for

consideration and for the Principal to issue an instruction on how to proceed.

The Contractor shall discuss upcoming site work on a daily basis with the Principal to ensure

that their works do not adversely impact on other subcontractors or separate contractors

working on the Project

No account will be taken of any abortive manufacture, fabrication or installation work

which has been due to the failure of the Contractor to carry out proper setting out and co-

ordination.

6.13 Installation

Workmanship shall be:

• in accordance with best modern trade practice,

• carried out by appropriately qualified and experienced tradesmen and supervised

apprentices,

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 54

• carried out under the supervision of a competent foreman,

• to a high standard of construction and leave an efficient, robust, tidy and fully

operational installation.

Install materials and equipment in accordance with the manufacturer's written instructions.

Provide labour and materials required to clean, treat, shim, grout, adjust, alter, support or

do any other work on materials and equipment which the manufacturer, or his agent, may

consider necessary to achieve a satisfactory installation.

Provide proper connections and interfacing between relevant materials and equipment,

such as to avoid such interfacing causing damage to or adversely affecting the

performance or durability of the Works.

If materials are required to comply with product certification schemes, use them in

accordance with the certification requirements.

Where material samples are required, incorporate in the works only those materials which

match the approved samples.

Arrange reticulated services to run parallel with adjacent services, building elements, and

grid lines where possible and practical.

Ensure access to services is not impeded.

Provide for movement in both structure and services.

6.14 Construction Record Drawings – On site Installations

6.14.1 General

Provide Construction Record (As-Built) Drawings recording the Works as installed by the

Subcontractor. Show the as installed locations and details of building elements, plant,

equipment, cables, piping, ductwork and the like. Include schematic Drawings of each

system.

Obtain electronic copies of the relevant "Issue for Construction" Drawings from the

Contractor. Where identified by the individual Specifications, update existing Construction

Record Drawings recording the Works as installed by the Subcontractor. Do not create new

Drawings if it is practicable to record the work by updating existing Drawings.

Retain one “Mark Up” set of the for construction Drawings at the Site. Neatly mark up all

changes to the installed work from the Drawings, including all amendments under site

instructions or contract instructions, as they occur. These prints shall be available for

inspection on request.

All CAD files are to be in AutoCAD Release 2010/LT compatible format or Inventor/STEP/SAT

files.

All drawings shall have the appropriate external reference files (Xrefs and Images)

referenced into the drawings (e.g. “Xref …. overlayed”). External reference files shall be

overlayed to Modelspace with the insertion point being 0,0. Do not alter any external

reference file names. Do not include a path name to any attached file in the drawing.

All CAD files (excluding Xrefs) are to have a single title block. The variable part of the title

block is to be an "Attributed Block", named “[Insert Client name] TITLE”.

The title block and Supplier/Subcontractor logo shall be placed in Paperspace and only

one “Paperspace Layout” should be used. Insert the block on the same layer across the

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 55

company’s series of CAD files. The layers used in the attribute block are to be consistent. All

other work shall be undertaken in the Model Space environment.

Only fonts supplied with standard AutoCAD are to be used in the composition of Drawings.

All objects in the drawing shall be drawn “Colour by Layer”. All objects should be separated

into consistent, logical and logically named layers. CAD pen assignments will be made

available as and when required.

6.14.2 Submission

Prepare first draft Construction Record Drawings based on the “Mark Up” set, and submit

A3 hardcopies prior to the subcontract date of completion for review.

Provide final Construction Record Drawings, checked and certified correct by the

Subcontractor, in the form of:

• A signed off hard copy A3 in the Operating and Maintenance Manual;

• An electronic PDF copy;

An AutoCAD copy of all electronic files. Include all external reference files (Xrefs and

Images).

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 56

7. LIGHTING INSTALLATION TESTING

7.1 General

Where required by the individual Specifications, carry out testing and commissioning to

clearly demonstrate and record that the Works efficiently meet the specified performances

and have been successfully commissioned as a complete, integrated and efficiently

operating installation.

Supply all necessary testing equipment, measuring instruments and the appropriately skilled

labour required for conducting the tests. Arrange for the specialist Subcontractors / Trades

and their Subcontractors / Suppliers to be in attendance.

Should any test reveal a fault, correct and re-test the fault, all stages of the process shall be

documented.

For major one-off tests and a sample of repetitive tests, give the Principal 10 working days

prior notice to enable him to attend.

Submit to the Principal examples of test record sheets 10 working days prior to conducting

tests. Record testing and commissioning results on test sheets, sign and date the sheets, and

submit for review. Testing and commissioning results shall demonstrate performance within

the acceptance criteria specified. The Principal reserves the right at their discretion to

accept results which may be outside the specified acceptance criteria but which are not,

in their opinion, detrimental to the overall performance of the Works.

At completion of the Contractor’s testing and commissioning, including recording of results,

the Principal reserves the right to instruct the Contractor to carry out random sample

confirmatory tests in the presence of the Principal.

7.2 Testing and Commissioning Manual

Where required by the individual Specifications, provide a Testing and Commissioning

Manual containing:

• descriptions of testing and commissioning procedures to be used for each equipment

item or system as appropriate

• requirements and constraints to perform the testing

• check list of all equipment and systems requiring testing and commissioning

• pro-forma Test Sheets for each equipment item or system as appropriate

• commissioning programme

• space for inclusion of completed testing and commissioning results.

7.3 Pre-Testing Procedures

Prior to starting tests, ensure that:

• the installation is strictly in accordance with the Specification and Drawings

• inspection and test records are complete

• equipment is in proper working order

• any automatic controls that might invalidate the test have been relaxed

• instruments to be used for testing are suitable for the purpose and have been calibrated

• the commissioning personnel are competent in the relevant fields

• the Testing and Commissioning Manual is available to the commissioning personnel.

• the testing area is safe and restrictions are in place where required

• all parties are aware of the process.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 57

7.4 Testing

The final installation shall be tested to show compliance with AS/NZS 1158 and WCC Design

Guide. The procedures and methodology for field measurements are generally described

in AS/NZS 3827.1 Lighting System performance-Accuracies and tolerances, Section 7

Verification.

Since the lighting design calculations are based on maintained values and the measured

values are initial values, both luminance and equivalent illuminance requirements need to

have the maintenance factor of .75 removed to compare calculated and measured

values for initial conditions.

7.5 Witnessing

The Park Lighting Contractor shall offer to the Principal’s Engineer a complete lighting

installation test that has been pre-tested and is compliant with this specification.

The witness testing plan shall be submitted for approval by the Principal’s Engineer 10

working days prior to the witness testing.

Independently certified and calibrated test equipment shall be used and advised within he

test method statement.

The Park Lighting Contractor shall record the witness testing results in paper and electronic

copy for record purposes, included in the Operations and Maintenance Manuals.

7.6 Grid Size

Measuring grid size is determined by reference to AS/NZS 1158.

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 58

APPENDIX A

MPA-Park Luminaires Schedule Date: 2014/01/10 Revision: R01

Type Quantity Image

Proposed

Manufacture

/Product code

Description Location /

Mounting

Supplier’s

details

A 43

Mark Herring

Lighting

WE-EF 108-0823

PFL 72W-LED

Mark Herring WE-EF PFL 72W S70 –

108-0823 Street optics LED luminaire

marine grade die cast aluminium

alloy body IP66 pole mounted

comes complete with LED

controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Road

Carriageway

and Park pole

mounted

Mark Herring

Lighting

Ph: 09 5510 500

B 35

Mark Herring

Lighting

WE-EF 108-0824

PFL 48W-LED

Mark Herring WE-EF PFL 48W S70 –

108-0824 Street optics LED luminaire

marine grade die cast aluminium

alloy body IP66 pole mounted

comes complete with LED

controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Park Lighting

pole mounted

Mark Herring

Lighting

Ph: 09 5510 500

C 1

Mark Herring

Lighting

WE-EF 108-0949

PFL 48W-LED

Mark Herring WE-EF PFL 48W S60 –

108-0949 Street optics LED luminaire

marine grade die cast aluminium

alloy body IP66 pole mounted

comes complete with LED

controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Park Lighting

pole mounted

Mark Herring

Lighting

Ph: 09 5510 500

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 59

MPA-Park Luminaires Schedule Date: 2014/01/10 Revision: R01

Type Quantity Image

Proposed

Manufacture

/Product code

Description Location /

Mounting

Supplier’s

details

E 4

Mark Herring

Lighting

WE-EF 108-0822

PFL 96W-LED

Mark Herring WE-EF PFL 96W S70 –

108-0822 Street optics LED luminaire

marine grade die cast aluminium

alloy body IP66 pole mounted

comes complete with LED

controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Park Lighting

pole mounted

Mark Herring

Lighting

Ph: 09 5510 500

F 6

Mark Herring

Lighting

WE-EF 108-0954

PFL 144W-LED

Mark Herring WE-EF PFL 144W S60 –

108-0954 Street optics LED luminaire

marine grade die cast aluminium

alloy body IP66 pole mounted

comes complete with LED

controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Park Lighting

pole mounted

Mark Herring

Lighting

Ph: 09 5510 500

G 2

Mark Herring

Lighting

WE-EF 108-0963

PFL 96W-LED

Mark Herring WE-EF PFL 96W A60 –

108-0963 forward throw LED

luminaire marine grade die cast

aluminium alloy body IP66 pole

mounted comes complete with

LED controller and 12m 1.5mm2 3C

PVC/PVC flexible cable.

Park Lighting

pole mounted

Mark Herring

Lighting

Ph: 09 5510 500

H 92

Mark Herring Kilk

systems LED

Mark Herring Kilk systems LED pod

for Stairs handrail asymmetric throw

IP65 spotlight with dedicated 24V

DC driver per handrail with remote

mounted at the switchboard.

Stairs Handrails

recessed

Mark Herring

Lighting

Ph: 09 5510 500

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 60

MPA-Park Luminaires Schedule Date: 2014/01/10 Revision: R01

Type Quantity Image

Proposed

Manufacture

/Product code

Description Location /

Mounting

Supplier’s

details

J 22

Lighting Pacific

Collingwood

GL090

Lighting Pacific Collingwood GL090

for Walkway lighting marine grade

stainless steel IP68 7W flood optics

cool white with remote driver

mounted at the switchboard.

Walkway

recessed into

precast

concrete

Lighting Pacific

Ph: 0800 707

272

K 24

Mark Herring

Lighting

Osirion LED

Megabay OS5

Mark Herring Lighting

Osirion LED Megabay OS5 5W spot

optics IP68 for Pavilion columns

uplighting 3x per column with

remote driver mounted at the

switchboard.

Pavilion

columns

recessed

Mark Herring

Lighting

Ph: 09 5510 500

L 3

Mark Herring

Lighting

ACDC Linear LED

Mark Herring Lighting

ACDC Linear LED Blade 53W IP68

lengths to match windows micro

louvre.

Building

windows

mounted

Mark Herring

Lighting

Ph: 09 5510 500

R1 1

Lightstudio

Hawko LED

LED strip Light concealed mounted

under capping lid 3x10 meter long

sections. Light studio Hawko LED

HLE white colour 50mm LED

spacing IP68 LED driver mounted

beside lighting.

West Tunnel lid

balustrade

Light studio

Ph: 04 567 8830

R2 1

Lightstudio

Hawko LED

LED strip Light concealed mounted

under capping lid 16 meter and 5

meter long sections. Light studio

Hawko LED HLE white colour 50mm

LED spacing IP68 LED driver

mounted beside lighting.

East Tunnel lid

balustrade

Light studio

Ph: 04 567 8830

PARK Lighting Supply and Installation Specification

MP-13-PRC-SP-001 61

MPA-Park Luminaires Schedule Date: 2014/01/10 Revision: R01

Type Quantity Image

Proposed

Manufacture

/Product code

Description Location /

Mounting

Supplier’s

details

CL TBC TBC TBC Cloake

Lighting TBC

TBC

T 14

ECC Iguzzini

Woody LED

ECC Iguzzini Woody LED 12x1W

white 4200k flood beam dark grey

colour and adjustable base

Surface

mounted

feature lighting

Walls before

and after

underpass

ECC

Ph: 4 473 3456.

Notes:

1. This luminaires schedule shall be read in conjunction with the drawings and specification.

2. All lamps colour temperatures shall be cool white (4000k) unless noted otherwise.

3. Allow for Architect’s finish colour selection.