Construction
Update
Schedule Update• 92% Complete
• Substantially Complete - 1 Story classroom
• 6/07/19 - 2 Story classroom pod
• 6/28/19 - Commons / Kitchen
• 8/2/19 – Site Complete (Weather delayed)
Bidding Update• 100% Complete
Walden Middle School
Photo 1
• Gymnasium - Area D
Photo 2
• Vocal Music - Area D
Photo 3
• FACS Cooking - Area D
Photo 4
• Collaborative Learning - Area B
Photo 5
• Science Lab - Area B
Schedule Update• 81% Complete
• 3/26/19 - Roofs Complete
• 7/15/19 - 2 Story classroom pod
• 7/20/19 - 1 Story classroom pod
• 7/29/19 - Commons / Kitchen
Bidding Update• 100% Complete
Hopewell Elementary
Photo 1-2
• East Side Bus Drop Off
• North Side Main Entrance – Admin Office Front
Photo 3-4
• South Side – Patio and Area A Brick & Glazing
Photo 5
• Main Entry Corridor to Main Terrazzo Stair Section
Photo 6
• Area A Upper Level Flex Space
Photo 7-8
• Area B Lower Level
Photo 9-10
• Area C Classrooms
• Area A Lower Level Restrooms
Service Center / Transportation
Bidding Update• 95% Complete
• Final IT/AV, Access Controls, and ServeillanceCamera FFE package remaining
Schedule Update – SSC• Total Project – 29%
• SSC - 17% Complete
• 6/18/19 – Slab on Grade
• 09/16/19 – Roofing
• 12/01/19 – Priority “Tech Sections”
• 12/20/19 – Administration
• 1/08/20 – Warehouse
Photo 1
Service Center – North View
Photo 2
• Service Center –Warehouse East Side View
Service Center / Transportation
Bidding Update• 95% Complete
• Final IT/AV, Access Controls, and ServeillanceCamera FFE package remaining
Schedule Update – Transportation Hub• Total Project – 29%
• TH - 6% Complete
• 06/18/19 – Slab on Grade
• 08/20/19 – Roofing
• 09/20/19 – Fuel Island, South Bus Lot and Access
• 12/18/19 – “Service Areas”
• 1/14/20 – Administration*
Photo 3
• Building Pad –Transportation Building East Side UnderslabUtilities
Photo 4
• South Parking Lot and Underground Utilities
LEAD Innovation Center
Bidding Update• 90% Complete
• IT/AV, Access Controls, Surveillance Cameras
• Coventry Roadway Intersection & Improvements
• Line Creek Storm Sewer Lines
Schedule Update• 5% Complete
• 07/01/19 - Slab On Grade
• 12/16/19 - Roofing
• 04/09/19 - 1st Floor
• 04/20/20 - 2nd Floor
• 05/20/20 - 3rd Floor
• 6/20/20 – Site Improvements
Photo 1
• Front Entrance Drive to Building
Photo 2
• Building Pad Fill
Photo 3
• Roadway and Parking Lot Areas
Photo 4
• Pathway for Line Creek Parkway Connection towards Hopewell
questions?thoughts?
youthank