Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
JUNE 2017
PANCHESHWAR DEVELOPMENT AUTHORITY (PDA)
Consultant:
76-C, Institutional Area, Sector – 18, Gurgaon – 122015, Haryana (INDIA)
Telephone: 0124-2342576, Fax: 0124-2349187 [email protected]
Website: http://www.wapcos.co.in
VOLUME-III : ENVIRONMENTAL MANAGEMENT PLAN REPORT
PANCHESHWAR MULTIPURPOSE PROJECT
GOVERNMENT OF INDIA Ministry of Water Resources,
River Development and Ganga Rejuvenation
GOVERNMENT OF NEPAL Ministry of Energy
CONTENTS
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
i
TABLE OF CONTENTS
Sub Heading Heading Page No.
CHAPTER 1: BIODIVERSITY CONSERVATION PLAN
1.1 INTRODUCTION 1
1.2 ACQUISTIION OF FOREST LAND 2
1.3 IMPACTS ON TERRESTRIAL ECOLOGY 4
1.4 COMPENSATORY AFFORESTATION 5
1.5 BIODIVERSITY CONSERVATION 6
1.6 BUDGET 12
CHAPTER 2: FISHERIES CONSERVATION PLAN
2.1 INTRODUCTION 1
2.2 RELEASE OF ENVIRONMENTAL FLOWS 3
2.3 SUSTENANCE OF MIGRATORY FISH SPECIES 6
CHAPTER 3: PUBLIC HEALTH DELIVERY SYSTEM
3.1 GENERAL 1
3.2 MOSQUITO CONTROL MEASURES 3
3.3 DEVELOPMENT OF MEDICAL FACILITIES 3
3.4 SURVEILLANCE 5
3.5 COST ESTIMATES 8
3.6 DISPOSAL OF BIO-MEDICAL WASTE 9
3.7 BUDGET FOR PUBLIC HEALTH DELIVERY SYSTEM 12
CHAPTER 4: ENVIRONMENTAL MANAGEMENT IN LABOUR CAMPS
4.1 INTRODUCTION 1
4.2 IMPACTS DUE TO CONGREGATION OF POPULATION 1
4.3 DEVELOPMENT OF LABOUR CAMPS 2
4.4 PROVISION OF HEATING 2
4.5 PROVISION OF WATER SUPPLY 2
4.6 SANITATION AND SEWAGE TREATMENT FACILITIES 3
4.7 SOLID WASTE MANAGEMENT 3
4.8 PROVISION OF FREE FUEL 7
CHAPTER 5: MUCK DISPOSAL PLAN
5.1 INTRODUCTION 1
5.2 MUCK GENERATION 1
5.3 ENGINEERING & BIOLOGICAL MEASURES FOR MUCK MANAGEMENT PLAN
2
5.4 BUDGET 4
CHAPTER 6: RESTORATION PLAN FOR QUARRIES
6.1 INTRODUCTION 1
6.2 CONSTRUCTION MATERIAL EQUIPMENT 1
6.3 IMAPCTS DUE TO QUARRYING 1
6.4 RESTORATION PLAN FOR QUARRIES 2
6.5 BUDGET FOR RESTORATION OF QUARRIES 4
6.6 LANDSCAPING AND RESTORATION PLAN 4
6.7 BUDGET 5
CHAPTER 7: ENVIRONMOENTAL MANAGEMENT IN ROAD CONSTRUCTION
7.1 INTRODUCTION 1
7.2 IMPACTS DUE TO CONSTRUCTION OF ROADS 1
7.3 MANAGEMENT MEASURES 1
7.4 BUDGET 4
CHAPTER 8: GREENBELT DEVELOPMENT PLAN
8.1 INTRODUCTION 1
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
ii
8.2 NEED FOR GREENBELT DEVELOPMENT PLAN 1
8.3 SCHEME FOR GREENBELT DEVELOPMENT 1
8.4 BUDGET 2
CHAPTER 9: CONTROL OF AIR POLLUTION
9.1 IMPACTS ON AIR QUALITY 1
9.2 MITIGATION MEASURES 2
9.3 BUDGET FOR AIR POLLUTION CONTROL 4
9.4 IMPLEMENTING AGENCY 4
CHAPTER 10: MEASURES FOR NOISE CONTROL
10.1 IMPACTS ON NOISE LEVELS 1
10.2 MITIGATION MEASURES 1
CHAPTER 11: WATER POLLUTION CONTROL
11.1 CONTROL OF WATER POLLUTION DURING CONSTRUCTION PHASE
1
11.2 CONTROL OF WATER POLLUTION DURING OPERATION PHASE
2
11.3 BUDGET 3
CHAPTER-12: ENERGY CONSERVATION MEASURES
12.1 GENERAL 1
12.2 PROVISION OF FREE FUEL 1
12.3 ENERGY CONSERVATION DURING CONSTRUCTION PHASE
2
12.4 ENERGY CONSERVATION DURING OPERATION PHASE
2
12.5 ENERGY EFFICIENT EQUIPMENT 2
12.6 BUDGET 3
CHAPTER-13: FIRE PROTECTION IN LABOUR CAMP AND STAFF COLONIES
13.1 INTRODUCTION 1
13.2 CONSTRUCTION OF CAMPS ETC. AND PLACEMENT OF FIRE PROTECTION EQUIPMENT
1
13.3 IMPLEMENTATION OF FIRE PROTECTION SYSTEM 2
13.4 RESPONSIBILITY 4
13.5 TRAINING AND AWARENESS 4
13.6 BUDGET 4
CHAPTER-14: CATCHMENT AREA TREATMENT PLAN
14.1 NEED FOR CATCHMENT AREA TREATMENT 1
14.2 APPROACH FOR THE STUDY 3
14.3 ESTIMATION OF SOIL LOSS USING SILT YIELD INDEX (SYI) METHOD
7
14.4 WATERSHED MANAGEMENT – AVAILABLE TECHNIQUES
9
14.5 CATCHMENT AREA TREATMENT MEASURES 10
14.6 COST ESTIMATE 19
CHAPTER-15: DISASTER MANAGEMENT PLAN
15.1 INTRODUCTION 1
15.2 DAM BREAK INUNDATION ANALYSIS 2
15.3 METHODOLOGY 2
15.4 DISASTER MANAGEMENT PLAN 7
15.5 COST ESTIMATE 13
CHAPTER-16: AGRICULTURE IMPROVEMENT PLAN
16.1 INTRODUCTION 1
16.2 IMPROVED AGRICULTURAL PRACTICES 1
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
iii
16.3 INTEGRATED PLANT AND NUTRIENT MANAGEMENT 1
16.4 BIOLOGICAL CONTROL OF PESTS AND DISEASES 2
16.5 USE OF AGRO-CHEMICALS 5
16.6 CONTROL OF WEEDS ON AGRICULTURE LANDS 5
16.7 TRAINING AND EXTENSION COURSES FOR FARMERS 6
CHAPTER-17: SAFETY PRACTICES DURING CONSTRUCTION PHASE
17.1 INTRODUCTION 1
17.2 PERSONAL SAFETY EQUIPMENT 1
17.3 RESCUE TEAM 2
17.4 ILLUMINATION AND EARTHING 3
17.5 MAINTENANCE OF TRAFFIC AND SAFETY ON PUBLIC ROADS
4
17.6 BLASTING 4
17.7 VENTILATION OF UNDERGROUND WORKS 5
17.8 CONTROL OF DUST, SILICA, AND NOXIOUS GASES IN UNDERGROUND WORKS
8
17.9 MANAGEMENT OF EXPLOSIVES 9
17.10 TRAFFIC MANAGEMENT DURING CONSTRUCTION PHASE
14
17.11 MEASURES TO BE TAKEN DURING EXCAVATION OF EARTH
14
17.12 IMPLEMENTATION OF SAFETY PLAN 15
CHAPTER 18: ECO-TOURISM
18.1 MEASURES FOR DEVELOPMENT OF ECO-TOURISM 1
18.2 BUDGET 1
CHAPTER 19: RELOCATION OF TEMPLES
19.1 INTRODUCTION 1
19.2 MANGEMENT MEASURES 1
CHAPTER-20: ENVIRONMENTAL MONITORING PROGRAMME
20.1 INTRODUCTION 1
20.2 AREAS OF CONCERN 1
20.3 WATER QUALITY 1
20.4 AMBIENT AIR QUALITY 2
20.5 NOISE 3
20.6 METEOROLOGICAL ASPECTS 3
20.7 EROSION AND SILTATION 3
20.8 ECOLOGY 4
20.9 FISHERIES 4
20.10 INCIDENCE OF WATER RELATED DISEASES 5
20.11 SUMMARY OF ENVIRONMENTAL MONITORING PROGRAMME
5
20.12 COST FOR IMPLEMENTING ENVIRONMENTAL MONITORING PROGRAMME
7
CHAPTER-21: COST ESTIMATES
21.1 COST FOR IMPLEMENTING ENVIRONMENTAL MANAGEMENT PLAN
1
CHAPTER-22: DISCLOSURE OF CONSULTANTS INVOLVED IN THE CEIA STUDY
1
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
iv
LIST OF TABLES
Table-1.1 Details of forest land acquisition 2
Table-1.2 Cost of habitat improvement for avi-fauna in the study area 8
Table-1.3 Cost for establishment of Botanical Gardens 9
Table-1.4 Measures for implementation of Wildlife Protection Plan 11
Table-1.5 Estimated cost of Biodiversity Conservation and
Management Plan implementation
12
Table-2.1 Inflows and outflows at Pancheshwar MPP (for 90%
Dependable Year)
4
Table-2.2 Summary of releases from Rupaligad dam in monsoon
season
5
Table-2.3 Summary of releases from Rupaligad dam in non-
monsoon non-lean season
6
Table-2.4 Summary of releases from Rupaligad dam in lean season 6
Table-2.5 Summary of releases from Rupaligad dam in various
seasons
6
Table-2.6 Component wise cost for development of fish seed farm 7
Table-3.1 Details of Para-medical staff for Dispensary 4
Table-3.2 Categories of bio-medical waste as per the Bio-Medical
Waste (Management and Handling) Rules 1998
9
Table-3.3 Categories of bio-medical waste to be generated in the
dispensary proposed to be developed as a part of the
project
10
Table-3.4 Colour coding and type of container for disposal of Bio-
medical waste
11
Table-3.5 Recommended treatment measures of various categories
of waste
11
Table-4.1 Cost Estimate for sanitary facilities for labour camps 3
Table-4.2 Cost required for solid waste management 6
Table-4.3 Cost estimate for LPG distribution 8
Table-5.1 Break-up of cost for stabilization of muck disposal sites 4
Table-6.1 Construction Material Requirement for Pancheshwar
Complex and Rupaligad Complex
1
Table-6.2 Cost estimate for restoration of quarry site and borrow
area
4
Table-6.3 Summary of costs for Restoration and Reclamation works 5
Table-7.1 Details of expenditure for implementation of measures for
management of Impacts due to construction of roads
4
Table-9.1 Emission limits for DG sets prescribed by CPCB 2
Table-9.2 Cost estimate for implementation of air pollution control
measures
4
Table-10.1 Maximum Exposure Periods specified by OSHA 3
Table-11.1 Budget earmarked for water pollution control measures 3
Table-13.1 Analysis of fire hazard in the construction of camps,
colonies and other facilities
1
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
v
Table-13.2 Responsibility for this EHS team in respect of Fire
protection system
2
Table-14.1 Landuse pattern of the catchment area 4
Table-14.2 Criteria for erosion intensity rate 8
Table-14.3 Basis for selection of catchment area treatment measures 9
Table-14.4 Erosion intensity categorization as per SYI classification 10
Table-14.5 Area under different erosion categories 13
Table-14.6 Treatment measures recommended for sub-watersheds
coming under high erosion category
13
Table-14.7 Cost estimate for Catchment Area Treatment of
Pancheswar Project- Biological Measures
15
Table-14.8 Cost estimate for implementation of Soil & Water
Conservation measures as a part of CAT Plan
15
Table-14.9 Cost earmarked for establishing Silt Observation points 16
Table-14.10 Cost summary for the Operational Support to Forest 17
Table-14.11 Cost summary for Forest Protection measures 17
Table-14.12 Cost earmarked for implementation of CAT plan 19
Table-15.1 Summary of wave profile in the event of Dam Break 7
Table-15.2 Status of Emergency 8
Table-15.3 Budget earmarked for implementation of Disaster
Management Plan
13
Table-16.1 Major Components of IPM 2
Table-18.1 Cost for development of Eco-tourism 2
Table-19.1 Abstract of Estimate for Construction of new temples 2
Table-20.1 Summary of Environmental Monitoring Programme during
Project Construction Phase
5
Table-20.2 Summary of Environmental Monitoring Programme during
Project Operation Phase
6
Table-20.3 Cost for Implementing Environmental Monitoringrogramme
during construction phase
7
Table-20.4 Cost for Implementing Environmental Monitoring
Programme during operation phase
7
Table-21.1 Cost for Implementing Environmental Management Plan 1
Table-22.1 List of Experts involved in the CEIA study 1
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
vi
LIST OF FIGURES
Figure-5.1 Typical cross section of retaining structure 3
Figure-7.1 Method of balanced cut and fill formation 2
Figure-7.2 Protection of slopes 3
Figure-14.1 Drainage Map for Pancheswar Catchment 2
Figure-14.2 Classified Imagery of Pancheswar catchment Area 5
Figure-14.3 Slope Map of Pancheswar catchment Area 6
Figure-14.4 Prioritisation of Sub Watersheds for Pancheswar Project 12
Figure-14.5 Catchment Area Treatment Measures for Pancheswar
Project
14
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
vii
ABBREVIATIONS AND ACRONYMS
AISLUS All India Soil and Land Use Survey
B/C Benefit Cost
BOD Biochemical Oxygen Demand
CAT Catchment Area Treatment
CGIAR Consultative Group on International Agricultural Research
CMO Chief Medical Officer
COD Chemical Oxygen Demand
CPCB Central Pollution Control Board
DEM Digital Elevation Model
DG Diesel Generator
DM District Magistrate
DO Dissolved Oxygen
DTM Digital Terrain Model
EAP Emergency Action Plan
EHS Environment Health & Safety
EMP Environmental Management Plan
ETL Economic Threshold Level
ETP Effluent Treatment Plant
GIS Geographic Information System
GPS Global Positioning System
HRT Head Race Tunnel
IARI Indian Agricultural Research Institute
IPNM Integrated Plant And Nutrient Management
Leq Equivalent noise level
LPG Liquefied Petroleum Gas
NEERI National Environmental Engineering Research Institute
NGO Non Governmental Organization
NO2 Nitrogen dioxide
NPK Nitrogen, Phosphorous, Potassium
NPV Net Present Value
ORS Oral Rehydration Solution
PAP Project Affected Population
PES Payments for Ecosystem Services
pH Potential of Hydrogen
PMP Pancheswar Multipurpose Project
PM10 Particulate Matter
POL Petroleum, Oils, and Lubricants
RET Rare Endangered Threatened
SO2 Sulphur dioxide
SP Superintendent of Police
SPM Suspended Particulate Matter
STP Sewage Treatment Plant
SYI Silt Yield Index
TDS Total Dissolved Solids
TSS Total Suspended Solids
VAM Vesicular Arbuscular Mycorrizae
CHAPTER-1 BIODIVERSITY CONSERVATION PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 1
CHAPTER-1
BIODIVERSITY CONSERVATION PLAN
1.1 INTRODUCTION
A detailed floral and faunal survey has been carried out in the study area for three
seasons to assess the presence of various floral and faunal species. The rare and
endangered species likely to be affected by the project were also assessed as a
part of the study.
During the field survey, a total of 193 plant species belonging to 131 genera and
61 families were recorded from the proposed project area. The findings of the
study revealed that herbaceous group of plant contributed highest number of
species with 63 species (32.64%) followed by trees with 46 species (23.83%),
shrubs with 38 species (19.69%), grasses with 29 species (15.03%), climbers with
11 species (5.70%), sedges with 5 (2.59%) and parasite with single species
(0.52%). The taxonomic group of species showed that angiosperms (monocot and
dicot) were the dominant component of the flora in the study area. The
composition of floristic elements of the study area consisted of 79.79% dicots,
19.69% monocots and 0.52% of gymnosperm.
The total forest land coming under reservoir submergence on Indian side due to
the project is 2031 ha. The project submergence does not contain any rare
endangered or unique species of the flora. The forest land in general is degraded
due to large scale human interferences in Mahakali river submergence. The
submergence of river Mahakali starts from the dam site at Pancheshwar and
extends upto village Kimkhola, which is at a distance of 6 km upstream of the
confluence of rivers Gauriganga and Mahakali at Jauljibi
There is no encroachment of any wildlife reserve. The nearest wildlife sanctuary is
the Askot wildlife sanctuary which is about 300 m from the tail end of the
submergence area. It is located about 50 km from project site, where main
construction activities are likely to take place. Considering the distance between
the major construction sites and the Askot Sanctuary, the adverse impacts likely to
accrue as a result of human interferences during construction and operation
phases of such projects are not expected.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 2
1.2 ACQUISTIION OF FOREST LAND The total forest land to be acquired is 2422.5 ha. The details are given in Table-1.1. Table-1.1: Details of forest land acquisition
S. No. Range Compartment Area (sqm)
A. Pancheshwar Project
1 Champawat Range 2b 159.367
2 Champawat Range 3b 5925.13
3 Champawat Range 23b 2692.23
4 Champawat Range 25a 4349.67
5 Champawat Range 22b 161.229
6 Champawat Range 20a 231.065
7 Champawat Range 12a 33017.2
8 Champawat Range 11a 4475.78
9 Champawat Range 11b 1031.82
10 Champawat Range 10a 15136.51
11 Champawat Range 9a 2619.43
12 Champawat Range Kali Kumaon Range 3308.73
13 Champawat Range Champawat Forest Area 4430373.52
14 Champawat Range NA 3675.37
15 Champawat Range 6b 103772.83
16 Champawat Range 1b 127323.23
17 Champawat Range 8b 1026193.59
18 Champawat Range 21c 100254.76
19 Champawat Range 20a 9090.88
20 Champawat Range 20b 87179.25
21 Champawat Range 18b 134708.27
22 Champawat Range 17b 222933.21
23 Champawat Range 16b 299500.54
24 Champawat Range 15b 33870.07
25 Champawat Range 15a 243996.43
26 Champawat Range 13b 57086.99
27 Champawat Range 12b 417137.38
28 Champawat Range 11b 126011.11
29 Champawat Range 10b 218702.06
30 Champawat Range West Chira 830004.58
31 Champawat Range 1b 111127.9
32 Champawat Range 2b 130375.88
33 Champawat Range 3b 17129.88
34 Champawat Range 4b 282601.15
35 Champawat Range 5b 150809.05
36 Champawat Range 23b 22728.59
37 Champawat Range 22b 78509.69
38 Champawat Range 20a 3669.58
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 3
S. No. Range Compartment Area (sqm)
39 Champawat Range 11b 142002.95
40 Champawat Range 9b 375590.34
41 Champawat Range 9a 10.768
42 Champawat Range Kali Kumaon Range 447.547
43 Champawat Range Kali Kumaon Range 6.36352
44 Champawat Range Kali Kumaon Range 145044.83
45 Champawat Range Kali Kumaon Range 2617433.91
46 Champawat Range Kali Kumaon Range 29.8438
47 Champawat Range Kali Kumaon Range 52.1417
48 Champawat Range Kali Kumaon Range 111.879
49 Champawat Range Kali Kumaon Range 2358326.79
50 Champawat Range Champawat Forest Area 232352.06
51 Champawat Range Champawat Forest Area 1961.39
52 Champawat Range Champawat Forest Area 7.7365
53 Champawat Range Champawat Forest Area 31.5506
54 Champawat Range Champawat Forest Area 1428.12
Sub-Total (A) 15216712.17 Say 1521.67 ha
1 Almora Range Kanarichina Range 897187.7495
2 Almora Range 27a 126709.7297
3 Almora Range 28a 347134.9588
4 Almora Range 29b 58888.5385
5 Almora Range 29a 268363.2137
6 Almora Range 30a 120227.2137
7 Almora Range 5a 92201.8233
8 Almora Range 6a 235680.4333
9 Almora Range
10b 362838.6702
10 Almora Range 12b 242648.9959
11 Almora Range 2 21820.9757
12 Almora Range 99 427045.1841
13 Almora Range 3 133084.6409
14 Almora Range 4a 45099.9734
15 Almora Range 4b 62874.2034
16 Almora Range 5b 299413.6902
17 Almora Range Jageshwar Range 1156834.417
18 Almora Range 2a 181901.5167
19 Almora Range 2b 68599.4555
20 Almora Range 3b 53973.4845
21 Almora Range 5b 98713.5672
22 Almora Range 5c 11938.7449
23 Almora Range 6a 49669.7185
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 4
S. No. Range Compartment Area (sqm)
24 Almora Range 7a 35274.6333
25 Almora Range 7b 217120.8889
26 Almora Range 9c 94874.705
27 Almora Range 11b 157565.1013
28 Almora Range 13b 65630.6858
29 Almora Range 14b 67546.6558
30 Almora Range 15b 223869.0516
31 Almora Range 15a 94710.0274
32 Almora Range Jageshwar Range 2076412.216
Sub-Total (B) 8395854.863 839.59 ha
B. Rupaligad Project
1 Champawat Range 2b 40851.897
2 Champawat Range 3b 181507.42
3 Champawat Range 4b 140864.4029
4 Champawat Range 5 126745.8326
5 Champawat Range Maurkot 80835.1052
6 Champawat Range East Dungrabanku 41570.8791
Sub-Total (C) 612375.5368
61.23 ha
Total (A+B+C) 24224942.57, say 2422.5 ha
Source: Forest Department
1.3 IMPACTS ON TERRESTRIAL ECOLOGY Key impacts envisaged on terrestrial ecology during project construction and
operation phases are given in the following sections.
1.3.1 Construction Phase
Impacts due to human interferences on flora and fauna
Habitat fragmentation
Clearance of forests
Impacts due to increased accessibility
Impacts due to dust
Imapcst due to noise
Impacts of mining/quarrying for construction materials
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 5
1.3.2 Operation Phase
Impacts on flora and fauna due to increased accessibility
Impacts on migratory route
Habitat fragmentation
Modification of animal behaviour
Impacts on avi-fauna due to construction activities
Impacts on avi-fauna due to formation of reservoir
Impact on Trans-boundary Avian Movement
The measures suggested for mitigation of adverse impacts on Indian Side are
described in following sections of this Chapter.
1.4 COMPENSATORY AFFORESTATION
On Indian side, the Forest Department of Uttarakhand is responsible for
conservation and Management of forests in the state. The objective of the
compensatory afforestation is to make up for the loss of forest land proposed to be
diverted for construction of Pancheshwar Multi-purpose project. The other
objectives are to combat soil erosion, afforestation and last but not least to
maintain and improve the ecological and environmental balance.
The total land required for the Pancheshwar and Rupaligad projects in India and
Nepal is 14100 ha. This includes 9100 ha in India and 5000 ha in Nepal. About
2422.5 ha of forest land is coming under reservoir submergence area of
Pancheshwar Main dam project and Rupaligad Project on the Indian Side. Orest
land shall not be acquired for other project appurtenences.
The dam construction, clearing of vegetation, movement of earth and rock,
widening of road, stocking of construction materials, erection of temporary labour
sheds and excavation disturb vegetation and forest area.The Indian Forest
Conservation Act (1980) stipulates:
- If non-forest land is not available, compensatory plantation is to be
established on degraded forest lands, which must be twice the forest area
affected or lost.
- If non- forest land is available, compensatory forest are to be raised over an
area equivalent to the forest area affected or lost.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 6
Considering the land to be acquired for Pancheshwar and Dams and other project
appurtenances, the total forest land to be acquired is 2422.5 ha. It is proposed to
afforest double the amount of entire land being acquired for the project including
private land. Thus, a total of 4,845 ha of land needs to be afforested. The
afforestation work is to be done by the Forest Department. Local species lieky to
be submerged in the reservoir or to be acquired shall be preferred for plantation
under compensatory afforestation.
The cost of afforestation on degraded forest land is Rs. 5,814 lakhs. In addition to
above the project proponent will compensate for NPV of the forest to be acquired,
which shall be estimated by the Forest Department at the time of Forestry
Clearance.
1.5 BIODIVERSITY CONSERVATION
As a part of Habitat Improvement Programme, the following measures are
proposed:
Afforestation
Soil stabilization measures & improving water regime,
Sustenance of Livelihoods
Establishment of botanical gardens for conservation and propagation of
RET species.
Anti-poaching measures
1.5.1 Habitat Improvement Programme
Habitat improvement programme is an integral part of biodiversity management.
This programme consists of bringing into useful association of those condition
needed by a species to reproduce and survive. The following activities have been
proposed for habitat improvement programme:
Afforestation: Area under forest and tree cover will be expanded through
systematic planning and implementation of afforestation and rehabilitation
programme in degraded and open forests and available non forest lands.
Regeneration of felled areas will be ensured in a time bound manner and
productivity of plantations will be increased through use of improved seeds and
planting stock. The indigenous fruit bearing plants, vital from wildlife point of view
are proposed to be planted so as to enrich the habitat & ensure the sufficient
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 7
availability of food. Monoculture will be discouraged and mixed plantations of
broad-leaved fodder, fuel wood and wild fruit species will be promoted. This
activity will increase forest cover and will provide habitat to the animals.
Afforestation programme in the degraded Forest Compartments is proposed to be
carried out with species suitable for the area and shall be finalized and executed
by the Forest Department. An amount of Rs.1000 lakh is proposed to be
earmarked for this purpose.
Avi-fauna: Forests are vital for the survival, foraging, breeding and nesting of
avifauna. Natural forests provide a variety of food materials to the birds not only in
the form of nectar of flowers, fruits, seeds etc. in the trees, shrubs, herbs and
grasses but they also contain a large number of insects eaten by birds. In the
forests, food is always available for the faunal component. Although most floral
species flower during spring through summer but fruit maturation and seed
ripening takes place in them throughout the year. Therefore, first strategy of
improvement of habitat for birds is avoiding nest predation or brood parasitism
through maintenance of large contiguous forest tract. These areas have the ability
to support the largest number of forest interior birds and will also be more likely to
provide habitat for area sensitive species. It is more practicable to protect the
existing forest area rather than creating new forest area.
Another measure for habitat improvement for avifauna is to be installation of
artificial nest boxes in the influence zone and catchment area of the project after
consultation with the forest department as well as local NGOs. These nest boxes
have been found to be quite beneficial for attracting hole nester birds. The size
and capacity of boxes vary from one species to another.
With the change in nature of landscape, its aquatic and terrestrial vegetation will
change the habits of the aquatic birds. The aquatic culture i.e. both floral and
faunal environments will change to the large extent e.g. in the initial years of the
reservoir water storage. The other measures recommended for improvement of
habitats are:
Fodder and wild fruit plantation for wild animals and for roosting, breeding
and hiding cover for migratory birds etc.
Annual bird count of migratory birds by involving locals and bird experts.
Removal of weeds and rehabilitation with local fruit bearing species in gaps.
Anti-grazing drive in draw down area to protect the bird breeding areas in
proximity to reservoir during breeding season.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 8
Construction of watch towers
An amount of Rs. 604.72 lakh has been earmarked for habitat improvement of avi-
fauna in the study area. The details are given in Table-1.2.
Table-1.2: Cost of habitat improvement for avi-fauna in the study area
S. No. Particulars Amount
(Rs. lakh)
A Non-recurring Cost
1. Cost of nests of different sizes (10”x10” to
20”x20”; average cost Rs. 1500 per wooden
box) and installation in the area along the
green belt (10000 Nos)
150.00
2. Repair and maintenance of the nests 45.00
3. Fodder and wild fruit plantation for wild
animals and for roosting, breeding and hiding
cover for migratory birds etc.
60.00
4. Annual bird count of migratory birds by
involving locals and bird experts.
30.00
5. Removal of weeds and rehabilitation with local
fruit bearing species in gaps.
50.00
6. Construction of watch towers 100.00
Sub-Total (A) 435.00
B Recurring Cost (for 8 years)
1. Salary for two qualified person @ Rs. 40,000
per month for implementation and data
collection including 10% escalation
109.72
2. Contingencies (including avifaunal biodiversity
awareness programme for the local
inhabitants)
60.00
Sub-Total (B) 169.72
Total (A+B) 604.72
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 9
Other Measures
The Proponent will instruct the project officials, labor force, consultants and other
stakeholder not to indulge in such activities and abide by the Forest Acts and its
regulation. Special consideration should be given to the migratory bird species in
order to protect their natural habitat. Limiting forest areas to be cleared during
construction period and planting a suitable broadleaves and indigenous trees and
plants for breeding birds to increased the forest areas as well as prohibition of
hunting, fishing, trapping, poisoning, killing of birds is prohibited and effective
application of pollution control measures. However, enforcement of strict regulation
for controlling the hunting, trapping, poaching, poisoning, fishing and pollution will
improve trans-boundary movement of avi fauna.
1.5.2 Establishment of Botanical Gardens
For conservation & propagation of local species, development of Botanical and
Herbal garden shall be done at suitable place in consultation with State Forest
Department. These gardens would function as repositories and would catalyze the
biodiversity conservation, scientific research, education and environmental
awareness in the area.
It is proposed to develop nursery at appropriate location preferably in the Gram
Panchayat. Self help groups formed by women shall be involved for the promotion
of herbal drugs from the kitchen stock and rare medicinal plants.
An amount of Rs. 727.01 lakh has been earmarked for the botanical gardens
including development of nurseries, collection of seeds and plant species, small
laboratory and staff for seven years. The details are given in Table-1.3.
Table-1.3: Cost for establishment of Botanical Gardens
S. No. Particulars Amount
(Rs. lakh)
A Non-recurring Cost
1 Nursery Development 215.00
2 Garden Development 275.00
3 Water Supply & other equipments 100.00
B Recurring Cost (For 8 years)
1 Salary for one Research Scientist person @ Rs. 45.86
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 10
S. No. Particulars Amount
(Rs. lakh)
40,000 per month for implementation and data
collection including 10% escalation
2 Salary for three Gardener person @ Rs. 10,000
per month for implementation and data collection
including 10% escalation
41.15
3 Seeds & Plant species 50.00
Total 727.01
1.5.3 Anti-poaching Measures
For the improvement of vigilance and measures to check poaching, number of
measures described below would be undertaken.
During construction phase in and around the main construction areas, i.e. the dam
site, powerhouse site, etc. where construction workers congregate, some
disturbance to the wildlife population may occur. The terrain is hilly & difficult,
therefore, the wildlife protection force adequately equipped with watch towers,
wildlife personnel and other necessary equipment be deployed to prevent
poaching in the area. The measures proposed for wildlife protection are outlined in
the following paragraphs.
Purchase of anti-poaching kits: To capture and translocate wild animals out of
human habitations or agricultural lands, various trapping equipments pertaining to
anti-poaching activities are needed. For this an amount of Rs. 200.0 lakh has been
earmarked. The anti-poaching kits will include equipments for self defense of the
staff as well.
Infrastructure Development: This includes anti-poaching huts, rock shelters
development and residential quarters for forest guards. For effective monitoring,
one watch tower is also proposed to be established at an identified place having
high pressure of biotic interference. The basic amenities for the field staff shall be
provided to enable them to do effective patrolling in the areas. For watch tower
and accommodation an amount of Rs. 300.0 lakh has been earmarked.
Purchase of Survey equipment and Vehicles: In order to improve network and
vigilance it is required to procure communication equipment like walkie talkie, IT
infrastructure to document and develop a database, altimeters, G.P.S., binoculars,
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 11
video as well as digital still cameras are essential. Purchase of field vehicle will
help in increased vigilance. For better communication and purchase of survey
equipment, an amount of Rs. 300.0 lakh has been earmarked.
Construction of Check posts: To improve vigilance for anti-poaching, better
protection, enforcement for control grazing practices, control-grazing-cum-anti
poaching check posts are proposed to be constructed. An amount of Rs. 145.0
lakh has been earmarked for this purpose.
Wildlife Protection Force
A team of forest personnel and guards shall be deployed for works under forest &
wildlife protection plan and an amount of Rs. 384.05 lakh has been earmarked for
this purpose.
The details are given as below:
Salary
Guards (24 nos.) @ Rs.8000 per month Rs. 28.80 lakh
One range officer @ Rs.40000 per month Rs. 4.80 lakh
Total cost for one year Rs. 33.60 lakh
Cost for 8 years Rs. 384.05 Lakhs
(Assuming 10% increase per year)
An amount of Rs. 1369.05 lakh has been earmarked for implementation of various
measures as a part of Wildlife Protection Plan. The details are given in Table-1.4.
Table-1.4: Measures for implementation of Wildlife Protection Plan
S. No. Particulars Amount (Rs. lakh)
Non-recurring
1 Anti Poaching Kits 200.0
2 Infrastructure 300.0
3 Survey equipment & vehicle 300.0
4 Check posts 185.0
5 Salary for wildlife protection force 384.05
Total 1369.05
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 1: Biodiversity Conservation Plan Page 12
1.5.4 Awareness Programme
Publication of conservation guides and manuals for local biodiversity (flora and
fauna including lower animals, insects and molluscs), posters, pamphlets on the
threatened species will enhance conservation practices and generate awareness
among the locals. The responsible agency for the publication will be PMP Locals
will be provided with awareness and introductory programmes on alien and
invasive species of both flora and fauna. Introductory posters and documents and
brochures on alien and invasive plants and animals will be prepared and
distributed during awareness and introductory training programmes. An amount of
Rs. 100 lakh has been earmarked for this purpose.
1.6 BUDGET
A total provision of Rs. 3801 lakh has been earmarked for biodiversity
conservation. The details are given in Table-1.5.
Table-1.5: Estimated cost of Biodiversity Conservation and Management Plan
implementation
S. No. Particulars Cost
(Rs. Lakhs)
1 Afforestation 1000.00
2 Habitat improvement for avi-fauna 604.72
3 Establishment of Botanical & Herbal
Gardens
727.01
4 Wildlife protection 1369.05
5 Awareness Programme 100.00
Total 3800.78
say Rs. 3801 lakh
CHAPTER-2 FISHERIES CONSERVATION PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 1
CHAPTER-2
FISHERIES CONSERVATION PLAN
2.1 INTRODUCTION
A river valley project may have adverse or beneficial effects on the fish fauna,
depending upon the particular situation and the fish fauna inhabiting the
concerned river. Similarly it has various impacts on the people, the livelihood of
whom depends on the fish. The construction of the dam leads to the fragmentation
of habitat, modification in hydrologic regime and may have adverse effects on
indigenous and migratory fish. On the other hand pondage provides a large
volume of water, which is beneficial with respect to fish culture and can play an
important role in the upliftment of economic growth.
2.1.1 Fisheries Status
A total of 30 species of fishes were recorded in Mahakali and Sarju rivers from all
sources in all seasons. All species belong to 5 families. Cyprinidae is largest family
comprising of 18 species (60% of total species). Tor putitora and Schizothorax
richardsonii are abundant species of Sarju and Mahakali rivers while Labeo dero,
Barilius bendelisis, Puntius ticto, Acanthocobitis botia and Schisturainglisi are
common species of this region (Joshi, 1999).
Out of 30 species, 25 species are included under IUCN’s list, of which 18 species
are categorized as ‘Least Concerned’. Tor putitora (Golden Mahseer) is an
‘endangered’ species while Schizothorax richardsonii (Snow trout) and Schistura
inglisi (Loach) are categorised as ‘vulnerable’ species. The game fishing is
common in Mahakali river, which comprises Tor putitora, Tor tor, Schizothorax
richardsonii and Bagarius bagarius. Game fishing is found in the form of ‘catch-
and-release’, thus no major threats are foreseen on the threatened species.
Schizothorax richardsonii descends in low temperature and use tributaries in
relatively lower reaches for spawning. The main purpose of migration is to cope
with low temperature. Tor putitora and Tor tor are long migratory species and
ascend in pre-monsoon season. In this river system Sarju river and its tributaries
like Eastern Ramganga are probable spawning grounds of Mahseer.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 2
2.1.2 Impacts on Fisheries
Impacts on migratory fish species
The construction of the dams would hinder migration of species especially
Schizothorax sp., Tor torand Tor putitora. These fish species undertakes annual
migration for feeding and breeding. Under this situation poaching activities may
increase in the area. Most of the species will shift to the section of the river where
they find favourable environment for breeding since the dam is 315 m high and
construction of fish ladders is not feasible in the proposed dam. However, it is
proposed that the artificial seed production in hatchery may be adopted which can
be stocked in the river stretches downstream and upstream of the proposed dam.
Impacts on fish fauna due to damming and reservoir formation
There are two types of effect that could be caused on the aquatic flora and fauna
of the water body (Mahakali River) due to damming and reservoir creation. One
could be considered as the negative impact and the second could be a positive
impact. The negative impact is caused by the submersion of the present fish
habitat and the obstruction of migration upstream and down stream movement of
the fishes due to the construction of the dam. Positive impact could be expected
as the damming will create deeper and wider water body which could provide
suitable habitat for both the coldwater as well as warm water fish species and
wider niches for the aquatic biomass that could help aquatic bio-diversity as well
as could provide more opportunities for improving the economy of the local
community and improve the social environment of the locality.
Obstruction in fish migration
The habitat of fishes like Asla and Mahaseer could exist up stream of the main
river Mahakali and its major tributaries. Asla (Schizothorax sp.) may be limited
around the confluence areas of its tributaries and along the periphery of the
reservoir/s at shallow water regions because, Asla feed on the plankton and
macro-organisms attached to the substrates like pebbles and boulders of the river
bottom at shallower area.
It has been reported that large fishes like Gaunch (Bagarius spp.) and Sahar (Tor
sp.) are vanishing from upstream of the dam of Kali Gandaki Hydro Project after
the implementation of the project (Kantipur National Daily, 2006). The breeding
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 3
habitat of Gaunch (Bagarius spp.) are likely to be observed downstream of the
dam. The migration of these fishes will be obstructed by the dam. However, they
are expected to remain in the Mahakali River up and down stream of Pacheswar
area as they were not found to be affected by Sarada Barrage and Tanakpur
Barrage so far and these fishes were found upstream of Pancheshwar dam area in
summer and winter).
However, for warm water fishes like Labeo sp., Barilius sp., Bagarius sp. etc. it
may possibly be affected by the barrier effect of the dam as the water temperature
does not go above 18ocelsius upstream of the high dam during winter. These
fishes were rarely found during winter upstream area of Pancheshwar dam site.
They could have migrated upstream during summer time when the water
temperature reached to or over 20o celsius in summer.
Impacts due to change in Water Quality
The water temperature of the reservoir, created by the high dam at Pancheshwar,
should increase by the absorption of more solar heat by its increased water
surface area which should help providing suitable habitat for warm water fish
species, residing down stream of the dam. The expansion of water surface area
and rise in water temperature is not only expected to improve in the fish bio-
diversity by accommodating more fish species up stream of the dam but also
should help increase fish production to many folds due to increase in water surface
area as well as increase its productivity due to the accumulation of organic
nutrients drained into the reservoir from its watershed area.
The mitigation measures for amelioration of adverse impacts are given in the
following sections.
2.2 RELEASE OF ENVIRONMENTAL FLOWS
The month-wise average inflows at Pancheshwar Main Dam and Rupaligad
Reregulating Dam for 90% dependable year (1998-99) are given in Table-2.1.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 4
Table-2.1: Inflows and outflows at Pancheshwar MPP (for 90% Dependable Year)
Month Pancheshwar Dam Rupaligad Dam
Inflows
(cumec)
Average
Outflows
(cumec)
Peak
Outflows
for hours
in Col (5)
(cumec)
Hours of
Peak
Outflow
Free CA
Inflows
(cumec)
Continuous
Outflows
over 24 Hrs
(cumec)
(1) (2) (3) (4) (5) (6) (7)
July 909 978 1876 12.51 65 1043
August 1045 385 2039 4.54 56 441
September 1487 447 2174 4.93 91 538
October 396 334 2092 3.84 25 360
November 185 335 2098 3.84 0 335
December 161 340 2130 3.84 0 340
January 131 347 2171 3.84 16 363
February 115 355 2222 3.84 7 362
March 108 365 2215 3.95 5 369
April 115 376 2113 4.28 19 396
May 295 387 2029 4.57 37 424
June 622 382 2065 4.44 55 437
Source: DPR
The Pancheshwar multipurpose project envisages re-regulating pond of Rupaligad
dam as an integral part of the Project. Hence, the concept of Environmental Flows
is applicable only at the Rupaligad site. River Mahakali would always carry
discharge downstream of Rupaligad site round the clock and throughout the year.
This aspect is clearly highlighted in the “Mahakali Treaty”, which was signed on
February 12, 1996 between His Majesty’s Government of Nepal and the
Government of India. Various principles are enshrined in the Treaty, on which
the Pancheshwar Multipurpose Project is to be designed and implemented,. The
key principle concerning the Integrated Developmnet is given as under:
“The P roject shall be implemented as an integrated project
including power stations of equal capacity on each side of the
Mahakali River and the total energy generated shall be shared
equally between the Parties”
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 5
This issue was considered in detail in the Expert Appraisal Committee (EAC) for
River Valley and hydroelectric projects of Ministry of Environment, Forest and
Climate Change (MOEFCC) in their 83rd and 93rd meetings held on 23.04.2015 to
24.04.2015 and 02.05.2016 respectively. The EAC agreed to the fact that
Rupaligad dam is an integral part of the Pancheshwar Project In the minutes of
the above referred EAC meetings it is clearly mentioned that:
“A reregulating dam at Rupaligad 25 km downstream is proposed to even out
powerhouse releases into continuous river flows an irrigation demands
downstream”.
The recommended Environmental Flows to be released are as follows:
Monsoon Season- May to September - 30% of the average flows during
90 % dependable year.
Non-monsoon Non lean Season- October & April - 25% of the average
flows during 90% dependable year.
Lean Season- November to March - 20% of the average flows during 90%
dependable year.
The summary of releases from Rupaligad dam in monsoon season, non-monsoon
non-lean and lean seasons is given in Table-2.2 to 2.4 respectively and
summarized in Table-2.5.
Table-2.2: Summary of releases from Rupaligad dam in monsoon season
Month Rupaligad Dam Percentage of flow
as Environmental
Release (%)
Recommended
Environmental
Release (%)
Inflows Releases
June 677 437 64.5 30
July 974 1043 107.1 30
August 1101 441 40.1 30
September 1578 538 34.1 30
Average 1217.7 674 55.4 30
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 6
Table-2.3: Summary of releases from Rupaligad dam in non-monsoon non-lean
season
Month Rupaligad Dam Percentage of flow
as Environmental
Release (%)
Recommended
Environmental
Release (%)
Inflows Releases
October 421 360 85.5 25
May 332 424 127.7 25
Average 376.5 392 106.6 25
Table-2.4: Summary of releases from Rupaligad dam in lean season
Month Rupaligad Dam Percentage of flow
as Environmental
Release (%)
Recommended
Environmental
Release (%)
Inflows Releases
November 185 335 181.1 20
December 161 340 211.2 20
January 147 363 246.9 20
February 122 362 296.7 20
March 113 369 326.5 20
April 134 396 295.5 20
Average 143.7 360.8 251.2 20
Table-2.5: Summary of releases from Rupaligad dam in various seasons
Month Rupaligad Dam Percentage of flow
as Environmental
Release (%)
Recommended
Environmental
Release (%)
Inflows Releases
Monsoon season 1217.7 674 55.4 30
Non-monsoon
non-lean season 376.5 392 106.6 25
Lean season 143.7 360.8 251.2 20
2.3 SUSTENANCE OF MIGRATORY FISH SPECIES
Since, migratory fish species are observed in the project area, scientific
management of the existing stock needs be adopted. It is proposed to implement
reservoir and supplementary stocking programmes for the project. It is proposed to
stock the following:
Reservoir of Pancheswar Main Dam
10 km upstream of reservoir periphery of river Mahakali and its tributaries
River Mahakali, 10 km downstream of Rupaligad Dam
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 7
The rate of stocking is proposed as 100 fingerlings of about 30 mm size per km.
For reservoir area, stocking shall be 1000 fingerlings/ha of 30 mm size. The
migratory fish species namely, Mahaseer and snow trout can be stocked. The
stocking can be done annually by the Fisheries Department, State Government of
Uttarakhand. To achieve this objective, facilities to produce seeds of Mahaseer
and snow trout would be created at suitable sites. The site would be identified in
consultation with Fisheries Department, State Government of Uttarakhand. The
reservoir and river stocking shall cover both Indian and Nepal side.
The total cost for development of one fish seed farm is Rs. 650 lakh. The details
are given in Table-2.6. Since, separate farms are to be developed for mahaseer,
snow trout and Indian Major Carps, an amount Rs.1950 lakh are proposed to be
earmarked.
Table-2.6: Component wise cost for development of fish seed farm
S. No. Particulars Quantity Rate (Rs.) Amount (Rs. lakh)
A. Capital cost (Non-recurring expenditure)
1. Hatchery (20 troughs and 80 trays) 1 Lump sum 80.00
2. Nursery ponds (3.0mx0.75mx0.5m)
9 30,000 2.70
3. Rearing ponds (10mx1.50mx0.5m)
9 1,50,000 13.50
4. Stocking ponds (30m x 6.0m x 1.5m)
2 1,500,000 30.00
5. Office, store, hut with infrastructure 4 2,50,000 10.00
6. Laboratory 1 2,00,000 2.00
7. Water supply (lump sum) - - 5.00
8. Other project cost (Drag nets, wide mouth earthen pots, miniature hapa, buckets, bamboo poles etc.) (lump sum)
- - 2.00
Total (A) 145.20
B. Working Capital /year (Recurring expenditure)
1. Salaries
i) Farm Manager (one) @ 25000/month
6.0
ii) Farm Assistants (one) @ Rs. 15000/ month
3.60
iii) Farm Attendants (one) @ Rs.10000/ month
2.40
iv) Chowkidars (one) @ Rs. 10000/ 1.20
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 2: Fisheries Conservation Plan Page 8
S. No. Particulars Quantity Rate (Rs.) Amount (Rs. lakh)
month
2. Fish food (rice bran, oil cake, etc.) Lumpsum
2.0
3. Brooders 200 kg 150 0.60
4. Ponds manuring
i) Cow dung 20 tons 200/tons 0.04
ii) Urea 100 kg 10/kg 0.01
iii) Potash, phosphate 100 kg 100/kg 0.01
5. Lime 300 kg 10/kg 0.03
6. Training and Research Lump sum 15.00
7. Chemical Lump sum 5.00
8. Maintenance Lump sum 5.00
9. Travel Lump sum 5.00
10 Miscellaneous Lump sum 12.00
TOTAL (B) Total recurring expenditure for eight years including 10% escalation (B)
504.32
Grand Total (A+B) 649.52, say Rs. 650 lakh
CHAPTER-3 PUBLIC HEALTH DELIVERY SYSTEM
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 1
CHAPTER-3
PUBLIC HEALTH DELIVERY SYSTEM
3.1 GENERAL
The creation of a huge and an artificial water body will certainly change the micro-
climate of the surrounding area, particularly raising the humidity levels. These
changes are likely to reflect in creating conditions for human diseases directly and
indirectly. Direct causes include water-borne diseases, while indirect causes
include breeding grounds for carriers and vectors.
About 8500 labourers and technical staff with a total increase in population by
22,500 will aggregate in the project area during construction phase. The labourers
would live in dormitories provided by the Contractor where proper sanitary facilities
are to be provided as per contract agreement. However, some of the labourers
coming from outside the project area could be carrier of certain diseases therefore
proper screening of labour population will be done by the contractor.
Inadequate facilities in labour camps
Labour camps without adequate facilities for potable water supply and sewage
treatment could lead to outbreak of epidemics of water-borne diseases. Adequate
measures for supply of potable water and sewage treatment need to be
implemented.
Water pollution and water borne diseases
Poor and unhygienic drinking water supply condition could be the cause for
incidence of water borne diseases particularly in camp sites and in adjoining
areas. Communities located in direct impact zone as well as indirect impact zone
could be severely affected from such epidemics. Similarly, other infections such as
cold cough, pneumonia, skin diseases and infections could occur due to the water
pollution during the construction phase. Chapter-4 of EMP Volume outlines
measures to control water pollution due to labour camps.
Air pollution
Dusts, particulate matters and smoke generated during the time of construction in
project construction sites could increases chances of respiratory diseases and
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 2
dust allergies. Project staffs and labor workers could be affected from the air
pollution during the construction of high dam and other relevant engineering
structures during the time of construction period. Dust particles ranging from 1-10
microns could spread air borne infections. Diseases related to dusts and smoke
such as asthma, bronchitis, eye irritation, throat and nose irritations etc. could
prevail into the communities situated at the direct impact zones during the time of
construction. Chapter- 9 of this report outlines measures to control air pollution
during various construction activities.
Noise Pollution
Moving of heavy vehicles from one part to other around project site, use of
excavator/ crane work force and blasting activities will create a noisy environment
for the total community resides in the project site. These activities will produce not
only the annoyance but also will cause ill health. The noise of blasting and
crouching will create a long lasting effect. The effect of noise exposure will have
either Auditory or Non-Auditory or both. In the Auditory effect there will be auditory
fatigue, deafness and will cause hearing loss. In the Non-Auditory effect there will
be interference with speech, annoyance reduction in the efficiency of work and
other psychological, physiological changes occur. In addition to this rise in blood
pressure and increase of breathing and sweating will occur. Chapter-10 outlines
measures to mitigate noise emanating from main project construction related
activities.
Solid Waste Management
Solid waste could be the major impacts upon the community and human resources
at the project construction and facility sites. In appropriate and unsustainable
disposal and direct disposal as well as open defecation by the project staffs and
labor workers at the project site could enhances the possibilities of emergence of
various diseases. Open defecation of human excreta both feces and urine at the
project site could enhances the possibility of emergence of water borne diseases
as well. Diseases such as diarrhea, cholera, dysentery, typhoid etc. could have
substantial affect upon human health of the project staffs as well as upon the
population at the community level.Chapter-4 outlines measures for solid waste
management in labour camps
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 3
3.2 MOSQUITO CONTROL MEASURES
3.2.1 Reservoir Operation
The Reservoir basin should be cleared and prepared prior to filling for removing
unwanted materials in the reservoir, which may lead to unhealthy condition giving
rise to breeding ground to mosquito. It involves removal of trees, undergrowth, etc.
and clearance of shoreline subjected to erosion to the extent to which the wave
action is anticipated. It also involves clearance of mats of logs and other floating
debris, so that it does not provide mosquito-breeding sites.
3.2.2 Residential Colonies for the Workers
The site selected for habitation of workers should be properly planned and should not
be in the path of natural drainage. Adequate drainage system to dispose storm water
drainage and sewage water from labour colonies shall be provided.
Strict procedures will be followed in importing labour force from outside the state.
Quarantine measures will be adopted and any possibility of importing any
communicable diseases would be eliminated by keeping close vigil on the potential
carriers. A thorough medical screening of the labour population migrating in the
area will be conducted.
3.2.3 Other Measures
The project authorities would ensure that all preventive measures and norms are
strictly enforced to avoid outbreak of any such eventuality. Surface sprays on the
reservoir waters to eliminate breeding of disease bearing insects, like mosquitoes,
etc. will be made from time to time. These sprays will be intensified particularly
during monsoon season.
- Adequate vaccination and immunization facilities shall be provided for
workers at the construction site.
- Labour camps and resettlement sites shall be at least 2 to 3 km away from
a main water body or quarry areas.
3.3 DEVELOPMENT OF MEDICAL FACILITIES
Labour colonies will be developed for the construction work. It is estimated that a
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 4
population of about 22,600 is likely to congregate during construction phase. The
labour population will be concentrated at two or three sites. It is proposed to
establish one Dispensary shall be developed at a site, which is easily accessible
from the three labour colonies.
The details of manpower, infrastructure requirement for this dispensary are given
as below:
3.3.1 Manpower
3 Doctors of having M.B.B.S./M.D qualification can be employed in the dispensary
and it is advisable that the doctors reside in the staff quarters adjacent to the
dispensary. The Para-medical staff required for assistance to these doctors is
given in Table-3.1.
Table-3.1: Details of Para-medical staff for Dispensary
Para medical staff Numbers
Auxiliary Nurses 6
Male Multipurpose Health workers 3
Attendants 3
Driver 3
Total 15
In addition to above, one dresser and health assistant shall also be posted at each
first-aid post.
3.3.2 Proposed Health Facilities at Construction sites and labour camp
It is possible that during the construction work, the technical staff operating
different equipment is not only exposed to the physical strain of work but also to
the physical effects of the environment in which they are working. The workers and
other technical staff may come up with common manifestations such as insect
bites, fever, diarrhoea, work exhaustion and other diseases, which they are
suffering. In addition they may invariably come up with injuries caused by
accidents at work site. Under all circumstances, workers need immediate medical
care.
At least three first-aid posts are to be provided at each of the major construction
sites, so that workers are immediately attended to in case of an injury or accident.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 5
The first-aid post will have at least the following facilities:
- First aid box with essential medicines including ORS packets
- First aid appliances-splints and dressing materials
- Stretcher, wheel chair, etc.
The first aid post can be housed in temporarily erected structure and should be
managed by one Health Assistant and assisted by one dresser/first aid attendant.
Doctors from the dispensary can attend First Aid post regularly every day at a fixed
time. Communication to establish link between the dispensary and then first-aid
post, so as to enable doctors from dispensary to reach the work site in case of an
emergency shall be developed. The first-aid post shall have facilities such as
firefighting equipment; telephone connection, one vehicle or ambulance van for
effective functioning.
3.4 SURVEILLANCE
In water resources schemes it is imperative to develop a proper surveillance
system. If facilities for diagnosis and treatment of parasitic diseases are available,
then the data obtained should be reported systematically and reviewed at higher
levels, where operational decisions on specific interventions can be made. The
systematic surveillance may be followed as per the following:
3.4.1 Malaria control activities
One of the doctors may be designated as “Medical Officer for Malaria” and will be
permanently posted at the dispensary. It is suggested that the anti-malarial
campaign be carried out under his immediate personal supervision. A systematic
campaign should be conducted amongst the labour population in the months of
March and September, which are the breeding months of mosquito. Surveillance
for malaria is very important as during construction phase, stagnant pools for
water, wastewater, etc. are created which can lead to greater incidence of malaria.
One male multi-purpose health worker along with one attendant will visit the labour
camps and surrounding areas once a fortnight and will inquire:
- Whether there is a case of fever in the house
- Whether there was a case of fever in the house between his previous visit
and the present visit.
If the answer to either of these two questions is 'yes' then the health worker will
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 6
collect a blood sample and give a single dose of chloroquine (600 mg for adults
and proportionate dose for others) as a presumptive treatment. The blood sample
is then sent to laboratory at the dispensary for testing. If the test is positive then
infected person is administered a course of Radical Treatment.
There shall be regular fumigation and sprays of insecticides in the areas where
water is likely to be stagnant, to prevent the growth of malarial larvae. Expert
opinion may be sought by project authority before selecting the appropriate
insecticide for malaria control. The frequency of monitoring could be decided once
the insecticide is selected. For this purpose a special van may be arranged.
3.4.2 Vaccination and Health Check-up Camps
Regular health check-up will be held at the construction sites for the labourers in
order to assess general health conditions and any other communicable diseases.
Vaccination camps also will be held for the labourers as well as their family
members in the labour colonies. A provision for adequate quantity of medicine
distribution also will be kept for the requirement of the labourers. Sufficient stock of
medicines also will be ensured for meeting the requirement in case of epidemic
situation.
3.4.3 Health Extension Activities
The health care activities proposed in the plan shall also be extended to the PAPs
and the locals residing in project area. It is important to inculcate hygienic habits of
environmental sanitation especially with respect to water pollution by domestic
wastes. There would be possibility of the transmission of communicable diseases
due to migration of labour population from other areas at the construction site.
The doctors from dispensary will make regular visits to these villages and organize
health promotional activities with the active participation of the local village
leaders, NGOs and available local health functionaries. The health functionaries
would undertake the following tasks as a part of health promotional activities:
- Collect water samples to ascertain the potability of water from different
sources so as to monitor regular disinfections of drinking water sources.
- Surveillance of incidence of communicable diseases in these villages.
- Maintain close liaison with the community leaders and health functionaries
of different departments, so that they can be mobilized in case of an
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 7
emergency.
3.4.4 Control of Vector-borne diseases
The following actions need to be taken:
- All the private doctors in the area to be provided chloroquin tablets and
arrangements for collection of blood samples.
- Few of the Primary Heath Centres to have Static Malaria Laboratory.
- Regular check up, surveillance and immunization of mobile populations.
Reduce exposure to mosquitoes
Encourage prevention of mosquito-borne disease by helping people by reducing
their exposure to mosquitoes during the day and at night. Work with the malaria
control programme in the project area to:
popularize the use of bed net programme
conduct community education on the proper use of bed nets and how to
avoid dawn-to dusk mosquito bites.
regular spray of insecticides.
implementation of various management measures for vector control
(drainage, filling, of breeding, sites) as outlined in the earlier section.
Vector control is still one of the major measures to control malaria in endemic
area. The following measures are recommended:
Residual spraying with insecticides.
Space application of insecticides in the form of a fog or mist. The method
has proved economical due to ultra-low volume dispersion of pesticides in
air.
Prevention of man-vector contact by use of repellents, protective clothing,
bed nets, etc.
Use of larvicides at regular intervals.
Reduction of mosquitoes breeding sites by drainage or filling, deepening or
flushing, management of water level, intermittent irrigation, etc.
Introduction of fish species in permanent water bodies which feed on
mosquito larvae.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 8
3.5 COST ESTIMATES
Cost Estimates
The costs estimated as below are tentative in nature and indicate the order of
expenditure likely to accrue.
A. Expenditure on salaries
Dispensary
-------------------------------------------------------------------------------------------------------------- Post Number Monthly emoluments (Rs.) Annual expenditure (Rs.) --------------------------------------------------------------------------------------------------------------Doctors 3 120,000 43,20,000 Nurse 6 40,000 8,80,000
Male Multipurpose 3 40,000 14,40,000
Health workers
Attendants 6 20,000 14,40,000
Dressers
Drivers 3 20,000 720,000
Total 1,08,00,000
B. Expenditure on Material and Supplies (Non-Recurring)
First-Aid Posts
3 Vehicles (Closed Jeep)@ Rs 20 lakh/vehicle Rs. 60,00,000
Furniture, etc. Rs. 20,00,000 Equipment in Dispensary Rs.10,00,00,000 --------------------------------------------------------------------------------------------------------------Total Rs. 10,80,00,000
Recurring Malaria control-dosage of chloroquine, spray for mosquito Rs. 60,00,000 control, blood testing, contingencies etc.@ Rs.500,000/month --------------------------------------------------------------------------------------------------------------Total Rs. 60,00,000/yr --------------------------------------------------------------------------------------------------------------
Infrastructure
An amount of Rs. 3 crore has been earmarked for development of dispensary. An
amount of Rs.15.0 lakh is also proposed to be earmarked for construction of first
aid at major construction sites.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 9
The total expenditure for implementation of various public health measures shall
be about Rs 26.29 crore. The details are given as below:
A. Recurring Expenditure
Expenditure on salaries : Rs. 1,08,00,000/yr
* Expenditure on materials & supplies : Rs. 60,00,000/yr
--------------------------------------------------------------------------------------------------------------
Total Rs. 168,00,000/yr
--------------------------------------------------------------------------------------------------------------
Total Expenditure for 8 years : Rs.1234.4 lakh
(construction period ) Sub-Total (A)
B. Non-Recurring Expenditure
* Construction of Dispensary : Rs. 300.0 lakh
* Construction of First aid posts : Rs. 15.0 lakh
* Expenditure on materials & supplies : Rs. 80.0 lakh
* Expenditure on Equipment & Dispensary : Rs. 1000 lakh
--------------------------------------------------------------------------------------------------------------
Sub-Total (B) Rs. 1395.0 lakh
--------------------------------------------------------------------------------------------------------------
TOTAL (A+B) Rs. 2629.4 lakh
--------------------------------------------------------------------------------------------------------------
3.6 DISPOSAL OF BIO-MEDICAL WASTE
Dispensaries use a variety of drugs including antibiotics, cytotoxics, corrosive
chemicals etc. a part of which is generated as a solid waste. With greater
emphasis on disposables, the quantum of solid waste generated in a hospital is
quite high. As per the Bio-Medical Waste (Management and Handling) Rules 1998,
the bio-medical waste has been classified into various categories which are
outlined in Table-3.2.
Table-3.2: Categories of bio-medical waste as per the Bio-Medical Waste
(Management and Handling) Rules 1998
Waste Category No. Waste category type
Category No. 1 Human Anatonical Waste Human tissues, organs, body parts
Category No. 2 Animal Waste
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 10
Waste Category No. Waste category type
Animal tissues, organs, body parts, carcasses, bleeding parts, fluid, blood and experimental animals used in research, waste generated by veterinary hospitals, colleges, discharge from hospitals, animal houses
Category No. 3 Micro-biology and Biotechnology wastes Wastes from laboratory cultures, stocks or specimens of micro-organisms, live or attenuated vaccines, human and animal cell culture used in research and infections agents from research and industrial laboratories, wastes from production of biologicals, toxins, dishes and devices used for transfer of cultures
Category No. 4 Waste sharps Needles syringes, scalpels, blades, glass, etc. that may cause punctures and cuts, including both used and unused drugs
Category No. 5 Discarded medicines and cytotoxic drugs Wastes comprising of outdated, contaminated and discarded medicines
Category No. 6 Soil Waste Items contaminated with blood and body fluids including cotton, dressings, soiled plaster casts, lines bleedings other material contaminated with blood.
Category No. 7 Solid Waste Wastes generated from disposable items other than the waste sharps, such as tubings, catheters, intravenous sets, etc.
Category No. 8 Liquid waste Waste generated from laboratory and washing, cleaning, house keeping and disinfecting activities
Category No. 9 Incineration Ash Ash from incineration of any bio-medical waste
Category No. 10 Chemical Waste Chemicals used in production of biologicals, chemicals used in disinfection, as insecticides, etc.
Out of the categories listed in Table-3.2, the bio-medical waste categories to be to
be generated in the dispensary proposed to be developed as a part of the project
are given in Table-3.3.
Table-3.3: Categories of bio-medical waste to be generated in the dispensary
proposed to be developed as a part of the project
Waste Category No. Waste category type
Category No. 1 Human Anatonical Waste Human tissues, organs, body parts
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 11
Waste Category No. Waste category type
Category No. 4 Waste sharps Needles syringes, scalpels, blades, glass, etc. that may cause punctures and cuts, including both used and unused drugs
Category No. 5 Discarded medicines and cytotoxic drugs Wastes comprising of outdated, contaminated and discarded medicines
Category No. 7 Solid Waste Wastes generated from disposable items other than the waste sharps, such as tubings, catheters, intravenous sets, etc.
Category No. 8 Liquid waste Waste generated from laboratory and washing, cleaning, house keeping and disinfecting activities
Category No. 10 Chemical Waste Chemicals used in production of biologicals, chemicals used in disinfection, as insecticides, etc.
The bio-medical waste must be segregated in accordance to the guidelines laid
under Schedule-I of Bio-medical Waste (Management and Handling) rules notified
by Ministry of Environment and Forests. The proposed colour coding and container
for disposal are given in Table-3.4.
Table-3.4: Colour coding and type of container for disposal of Bio-medical waste
Colour coding Type of container Waste category
Yellow Plastic bag Category 1and category 6
Red Disinfected container/
plastic bag
Category 6 and category 7
Blue/white
transparent
Plastic bag/ puncture
proof container
Category 4 and category 7
Black Plastic bag Category 5, category 9 and
category 10 (solid)
The treatment measures recommended for various categories of waste is outlined
in Table-3.5.
Table-3.5: Recommended treatment measures of various categories of waste
Waste type Recommended treatment
Category No. 1 – Human Anatomical wastes
Incineration
Category No. 4 – Waste sharps Secured landfill
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 3: Public Health Delivery System Page 12
Waste type Recommended treatment
Category No. 5 – Discarded medicines and lytotoxic drugs
Secured landfill
Category No. 7 Solid Waste Incineration
Category No. 8 – Liquid waste Treatment through an Effluent Treatment Plant (ETP)
Category No. 10 – Chemical waste Secured land fill
It is proposed to treat the effluent generated from the dispensary in an Effluent
Treatment Plant (ETP) prior to its disposal. The ETP shall comprise of the
following units:
Screen
Grit chamber
Equalization tank
Neutralization tank
Clari-floculator
Activated carbon filter.
Ozonator
Guard pond
An amount of Rs.300.0 lakh has been earmarked for commissioning of the
following:
Incineration
Secured landfill
Effluent Treatment Plant (ETP)
3.7 BUDGET FOR PUBLIC HEATH DELIVERY SYSTEM
The total budget earmarked for Public Health delivery system shall be Rs.29.29
crore. The details are given as below:
Public Health Delivery System : Rs. 2629.4 lakh
Disposal of Bio-medical waste : Rs. 300.0 lakh
Total : Rs. 2929.4 lakh or Rs. 29.29 crore
CHAPTER-4 ENVIRONMENTAL MANAGEMENT IN
LABOUR CAMPS
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 1
CHAPTER-4
ENVIRONMENTAL MANAGEMENT IN LABOUR CAMPS
4.1 INTRODUCTION
The aggregation of large number of workers in the project area during the
construction phase is likely to put considerable stress on the prevailing biotic and
abiotic environment of the area. The aim of the EMP is to minimize these stresses.
The construction activities are likely to be concentrated at various locations along
the canal alignment.
4.2 IMPACTS DUE TO CONGREGATION OF POPULATION
The total construction time will be 8 years. The expected maximum personnel
requirement for the employer and the contractor has been estimated in the order of
500 and 8,000 respectively. However, with the advent of mechanised construction,
the number of maximum personnel requirement for the employer and contractor
has been estimated to be of the order of 500 and 8,000 respectively. Thus, the
peak aggregation of labour and technical staff will be 8500. The immigration of
such a large population will also induce secondary migration in the area to cater to
the various requirements of the project construction staff. These will include
persons to manage shops of various types, transportation, etc.
Assuming that 80% of the total labour force (8,500) are married and in 80% cases
of the married families both husband and wife will work, the total persons expected
to emigrate into the area are around 22,600. This sudden increase of such a large
population will definitely lead to adverse impacts on the ecosystem of the area.
The domestic water requirement of the immigrant population will be of the order of
1.58 mld of which about 1.26 mld will be generated as sewage. The BOD load will
be of the order of 1017 kg/day. It is recommended to treat the sewage from labour
camps prior to disposal.
The labour colony will be located at Dam site, powerhouse and adit sites. During
construction phase, about 800 labour and 500 technical staff is likely to
congregate. The increase in population is expected to be of the order of 22,500.
The solid waste likely to be generated from labour camps shall be of the order of
4.73 tonnes/day.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 2
Various measures to control pollution due to labour camps are delineated in the
following sections. The measures recommended for labour camps on Indian side
shall be implemented for labour camps on Nepalese side as well.
4.3 DEVELOPMENT OF LABOUR CAMPS
The aggregation of large number of workers in the project area during the
construction phase is likely to put considerable stress on the prevailing biotic and
abiotic environment of the area. The aim of the EMP is to minimize these stresses.
The construction activities are likely to be concentrated at various locations along
the canal alignment.
It has been observed during construction phase of many of the earlier water
resources projects, that workers generally live in slum type conditions, with
inadequate facilities for potable water and sanitation. Such conditions, coupled
with lack of hygiene make the labour population prone to increased incidence of
various water-borne and vector-borne diseases. It is proposed that it should be
made mandatory for the contractor involved in the construction activities to provide
adequate facilities for water supply and sanitation. It is recommended that the
contractor provides living units of 30-40 m2 to each of the labour family involved in
the construction activities. The unit should have proper ventilation. An amount of
Rs. 3120 lakh has been earmarked for purchase of land for construction of labour
camps.
4.4 PROVISION OF HEATING
The contractor can make a block of two large rooms in which about 30-40 workers
can stay. Community toilets for each block can be constructed close by.
4.5 PROVISION OF WATER SUPPLY
The water for drinking purpose is collected from the rivers or streams flowing
upstream of the labour camps. The water is stored in tanks and supplied for use.
The water quality in general is good and does not require any elaborate treatment.
However, it is proposed to disinfect the water prior to distribution. The settlements/
labour camps shall be located at a distance from the drinking water sources, so
that the sewage generated from these labour camps, does not affect the water
quality.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 3
4.6 SANITATION AND SEWAGE TREATMENT FACILITIES
One community toilet can be provided per 20 persons. The sewage from the
community latrines can be treated in a sewage treatment plant (STP) comprising
of aerated lagoon and secondary settling tank. Each labour camp can be provided
with a STP. The treated effluent shall be disposed off in nearest water body.
However, efforts shall be made to ensure, that treated effluent is disposed only in
these water bodies, which are not used for meeting domestic water requirements.
The total construction time for the project is about 8 years. At peak construction
phase, there will be an increase in population up to 22500. To ensure that the
sewage from the labour camps do not pollute the river water, it has been estimated
that about 560 community latrines and a sewage treatment plant shall be
constructed for treatment. The total cost required will be Rs. 2060 lakhs (refer Table-
4/1).
Table- 4.1: Cost Estimate for sanitary facilities for labour camps
S. No. Unit Rate (Rs./unit) Number Cost
(Rs. lakh)
1. Community toilets 100,000 1120 1120.0
2. Sewage Treatment Plant - 940.0
Total 2060.0
4.7 SOLID WASTE MANAGEMENT
The labour colony will be located at Dam site, powerhouse and adit sites. During
construction phase, about 800 labour and 500 technical staff is likely to
congregate. The increase in population is expected to be of the order of 22,500.
The solid waste likely to be generated from labour camps shall be of the order of
4.73 tonnes/ day.
Adequate facilities for collection, conveyance and disposal of solid waste will be
developed. The solid waste will be disposed at the designated landfill sites.
The landfill shall have impervious clay at the bottom most layer. The second layer
shall be impervious liner (Geo-membrane), third layer will be of sand, after that
well compacted solid waste is to be put over the sand, then again a layer of clay,
finally a layer of soil. Vegetation shall be grown on the top most layers. It will give a
good aesthetic view of landfill.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 4
Various aspects of solid waste management include:
Reuse/Recycling
Refuse storage
Collection and Transportation
Disposal
Reuse/Recycling
In order to reduce quantum of waste generated, project will reuse significant
quantity of Muck (generated due to excavations) for backfilling, form work (in civil
work) wherever possible and will also reuse the packing materials received with
packages etc.
Project proponent will explore opportunity to recycle the waste generated at the
project site. In this context project will identify authorized vendors and send used
batteries, used oil, and used oil filters for recycling.
Bio- degradable waste will be disposed by composting and the manure generated
will be given to local community for cultivating vegetables and flowers.
Refuse storage
In the proposed project, labour camps are proposed to be located near Hawai. The
labour colony shall have provisions to separately store the degradable and non-
degradable solid waste.
Two different coloured bins shall be supplied to each labour family, who will
segregate the waste generated by their family. Green and Biodegradable waste is
to be deposited in one container and non-biodegradable waste in another
container. In case of canteens, kitchens also, two different coloured dust-bins
suitable to deposit the Biodegradable and non-biodegradable waste generated in
their unit shall be provided. A sustained awareness programme will be conducted
to educate workers about the segregation of degradable and bio-degradable
wastes.
Collection of house-hold Waste
Every day the trolleys will collect the waste at the door of each unit of labour camp
and colonies. The trolleys will be provided with two compartments for depositing
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 5
segregated waste separately. Each worker will be allotted at a fixed area. The
collection will be on regular pre-informed timings and the arrival will be informed
through blowing a whistle/horn. The solid waste so collected shall be disposed at
a common storage point. Two trucks will be commissioned to collect the solid
waste and dispose the same at sites designated for disposal of solid waste.
Segregation of waste
The awareness programmes shall be organized for waste segregation. Residents
of labour camps shall be apprised of the benefits of waste segregation. Regular
meeting shall be conducted with representative of residents of colonies where
good upkeep shall be recognized & rewarded.
Disposal
Degradable component
The degradable portion of the solid waste would be disposed off by composting.
The degradable portion is taken as about 38.9%. Thus, (0.389*4.73) about 1.84
t/day of degradable portion of solid waste will be generated. In composting the
process takes around 60 days to mature. Keeping, a margin of 30 days total
capacity of pits has been provided as (3.1x90 = 279 m3). Thus the total capacity of
pits required would be 280 cu m.
A pit of 2m x 1.5m x 1.3m deep (0.3 m freeboard) size can take 3.0 cu m of
compostable waste. Thus the no. of pits required shall be about 95. The total area
will be almost three times the pit area as some area in between pits will be
required for transportation and stacking of waste. Hence, total area required will be
855 m2. The pits will be covered with GI sheets. Additional 300 sq.m shall be kept
for storage for compost plus screening and other activities.
The pits to be constructed will have around 25 cm of bottom lining consisting of
about 5 cm thick stone grit over which 15 cm thick coarse sand followed by 15 cm
thick earth lining will be done. The refuse along with animal dung will have to be
laid in layers of 5 to 10 cm thickness. The pit will be then watered on alternate
days. Thereafter waste is laid in 5 to 10 cm thick layers twice in a week till the
whole pit is filled up. Every week the waste will need to be turned up and water will
have to be sprinkled every day to keep adequate moisture. The process will take
around 60 days where after the composted waste from the pit is taken out and
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 6
after drying it is screened with screens having 2 mm dia holes. The screened
compost would be filled in plastic bags and used as good manure especially for
cultivation of vegetables and flowers.
Non-Degradable component
The non- degradable portion (about 0.384 t/day) such as plastic bottles, cans, etc.
shall be segregated and disposed off at separate sites identified by the district
administration.
The details of landfill site are given as below:
Waste Generation 2.89 tonnes per day
Design Life 8 years (construction phase)
Total Waste Generation in 8 Years 8440 tonnes
Length 70 m
Width 40m
Depth of fill 5 m
A provision of 15% of the total area, for accommodating infrastructure facilities
will be included while working out requirement of space. The liner system will
comprise of the following layers below the waste:
0.30 m thick drainage layer comprising of coarse sand or gravel
(stone dust with no fines)
0.2m thick protective layer of sandy silt
1.50mm thick HDPE geo-membrane
1.0 m thick clay layer/amended soil layer, amended soil layer
comprising of local soil + bentonite is to be provided).
The total cost required for solid waste management is estimated as Rs.1258.64
lakh. The details are given in Table-4.2.
Table-4.2: Cost required for solid waste management
S. No. Item Cost (Rs. lakh)
1. Cost of land 100.0
2 Reclamation and stabilization cost of 500.0
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 7
S. No. Item Cost (Rs. lakh)
landfill and composting sites
3 Four covered trucks for conveyance of
solid waste to landfill site @ Rs. 4 0 lakh
per truck
160.0
4. Manpower cost for 40 persons @ Rs.
10000/ month for 8 years including 10%
escalation/year
548.64
5. Awareness programme 20.0
6. Water facility and Toilet facility 25.0
7. Tools and Implements 26.0
8. Yard lighting maintenance store room
lighting, Monitoring station
20.0
9. Periodical Training and Medical Checkup
of labour involved solid waste
management
30.0
Total 1369.64, say Rs.
1370 lakh
4.8 PROVISION OF FREE FUEL
As a part of EMP, following measures are proposed:
- Make a clause mandatory in the contract of every contractor involved in
project construction to provide supply of fuel to their labourers, so that trees
are not cut for meeting their fuel demands.
- Establish LPG godown within the project area for providing LPG cylinder to
run community kitchens.
-
The project proponents in association with the state government shall make
necessary arrangements for distribution of LPG.
The total increase in labour population shall be 22,500. For every 5 persons, 1
LPG Cylinder shall be taken per month. Considering the cost of each LPG Cylinder
as Rs. 1500 and taking 10% escalation in cost every year, the total cost for
provision of fuel works out to Rs. 8208.48 lakh. The details are given in Table-4.3.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 4: Environmental Management in Labour Camps Page 8
Table-4.3: Cost estimate for LPG distribution
Year Population
to be
served
Annual requirement
@1cylinder per 5
persons per month
(No. of cylinders)
Total Cost
@Rs.1000
/cylinder
(Rs. lakh)
Cost after
escalation @
10%/ year (Rs.
lakh)
I 15000 36000 540.0 540.0
II 20000 48000 720.0 720.0
III 22500 54000 810.0 980.1
Iv 22500 54000 810.0 1078.11
V 22500 54000 810.0 1185.92
VI 22500 54000 810.0 1304.52
VII 20000 48000 720.0 1275.52
VIII 15000 36000 540.0 1052.31
Total 336.0 8208.48
CHAPTER-5 MUCK DISPOSAL PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 5: Muck Disposal Plan Page 1
CHAPTER-5
MUCK DISPOSAL PLAN
5.1 INTRODUCTION
Muck Management plan envisages that the disposal of muck is done with
engineering measures in such a manner that the fill is stable and does not flow,
terraces developed after the completion of the excavation are utilized for project
infrastructure, storage etc. This also optimizes the land use and improves the
aesthetics of the area. The muck disposed in disposal areas is devoid of nutrients
and soil contents that support vegetation. The biological measures are envisaged
on the surface of muck disposal areas in order to have administered growth of
forest canopy. This rehabilitates the muck disposal areas and prevents
contamination of any land or water resource due to muck disposal in post
construction stage.
5.2 MUCK GENERATION
The total quantum of muck to be generated as a result of various project related
activities, construction of dam, HRT and Powerhouse is 53.98 Mm3 and 2.91 Mm3
for Pancheshwar and Rupaligad projects respectively.
For Pancheshwar Dam Complex, about 85% of the muck (0.85*53.98x1.4) 64.26
Mm3 generated shall be used and about 11.33 Mm3 of muck shall be disposed for
which an area of 67 ha has been earmarked. On Indian side, the area earmarked
for muck disposal is 50 ha and 17 ha has been earmarked on Indian and
Nepalese side respectivelly. The capacity of the muck disposal sites is 11.6 Mm3.
For Rupaligad Dam Complex, about 25% of the muck (0.25*2.91 x 1.4) 1.02 Mm3
of muck generated shall be used and about 3.05 Mm3, (considering swelling factor
of 40%) of muck shall be disposed for which an area of 25 ha (20 ha on Indian
side and 5 ha on Nepal side) has been earmarked. The capacity of the muck
disposal site is 3.05 Mm3.
The total area under muck disposal site is 92 ha which includes 67 ha of
Pancheshwar project and 25 ha for Rupaligad project.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 5: Muck Disposal Plan Page 2
5.3 ENGINEERING & BIOLOGICAL MEASURES FOR MUCK MANAGEMENT
PLAN
Muck is envisaged to be disposed in pre identified area during the planning stage.
Trees, if any, are felled before muck disposal. Muck then generated is required to
be disposed in a planned, efficient and optimal manner so that the adverse
impacts are minimized.
Muck Management plan envisages that the disposal of muck is done with
engineering measures in such a manner that the fill is stable and does not flow,
terraces developed after the completion of the excavation are utilized for project
infrastructure, storage etc. This also optimizes the land use and improves the
aesthetics of the area. The muck disposed in disposal areas is devoid of nutrients
and soil contents that support vegetation. The biological measures are envisaged
on the surface of muck disposal areas in order to have administered growth of
forest canopy. This rehabilitates the muck disposal areas and prevents
contamination of any land or water resource due to muck disposal in post
construction stage.
5.3.1 Engineering Measures
Various engineering measures to be implemented at muck disposal sites are given
as below:
• Construction of toe walls, wire crate wall, boulder crate wall, Retaining
walls.
• Construction of catch water Drains
The dumping of muck will be done with engineering measures in the scientific
manner by providing appropriate retaining walls with adequate foundations so that
muck is well restrained and does not flow / gets washed away into the river.
Masonry work, crate work and check dam will also be provided wherever
necessary in order to avoid the chances of soil erosion and to ensure flow of silt
free water. The check dams / retaining walls shall have weep holes for proper
drainage during rainy season. The weep holes would be provided with filters on
the rear side facing the dumped materials. Besides these engineering measures,
proper plantation will be done at the dumping sites for reclamation of the dumping
areas.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 5: Muck Disposal Plan Page 3
The typical cross section of the retaining structure is shown in Figure-5.1.
Figure-5.1: Typical cross section of retaining structure
5.3.2 Biological Measures
Various Biological treatment measures to be implemented at muck disposal sites
are given as below:
• Plantation of suitable tree species and soil binding species
• Plantation of ornamental plants
• Barbed wire fencing
Muck generally lacks nutrients and therefore, are difficult to re-vegetate and in
absence of vegetation in the slopes, the muck could slide lower down during rain
and may eventually wash off the check dams also. Since, top soils are not
available in large quantities in Himalayas, it may not be possible to apply a thin
layer of soil over the muck for all the areas. Bio-fertilizer technique developed by
National Environmental Engineering Research Institute (NEERI) can be adopted in
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 5: Muck Disposal Plan Page 4
the proposed project. This technique has been successfully used in Uri
hydroelectric project. Similar approach can be utilized in the proposed project as
well. In this process, the unused excavated material is piled and stacked with
proper slopes at the designated muck disposal sites. The slopes are broken up by
creating benches across them. This is done to provide stability to the slopes and
also to provide ample space for planting of trees that would further help in holding
and consolidating biotechnological approach. The traditional methods of
afforestation of these areas would be supplemented with the use of fungus, i.e.
Vesicular Arbuscular Mycorrizae (VAM) and nitrogen fixing bacteria that form
partnership with plant roots. These grow on plant roots and provide water and
nutrition especially phosphorus to plants at faster rate. The seeding of plants
would be inoculated with VAM and nitrogen fixing bacteria before planting. It has
been found that plants inoculated with bio-fertilizers grow at faster rate especially
in the medium where the soil/rock is devoid of nutrients.
5.4 BUDGET
The total expenditure required for stabilization of muck disposal sites has been
estimated to be of the order of Rs.7924.6 lakh or Rs. 80 crore. The details are
given in Table-5.1.
Table-5.1: Break-up of cost for stabilization of muck disposal sites
S. No. Items Cost (Rs. lakh)
1 Construction of Retaining walls (concrete / masonry)
along river banks – for 18000 m Concrete base wall
@4.5 Sqm. per m.- Rs.0.225 lakhs per m Gabions @
6 Sqm. per m – Rs. 0.15 lakhs per m
6750.00
2 Preparation of muck disposal site@ Rs. 2.0 lakhs /ha
for 92 ha
184.00
3 Provision of 15 cm soil layer over an area of 92 ha @
Rs. 5 lakh/ha
460.00
4 Development of vegetation over an area of 92 ha@
Rs. 2.4 lakh/ha
220.80
5. Watch & Ward (4 persons @ Rs. 20,000/month/for 8
years considering 10% escalation per year
109.80
6 Development of nursery 200.00
Total 7924.60
say Rs. 80.0 crore
CHAPTER-6 RESTORATION PLAN FOR QUARRIES
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 6: Restoration Plan for Quarries Page 1
CHAPTER-6
RESTORATION PLAN FOR QUARRIES
6.1 INTRODUCTION
Opening of the quarries will cause visual impacts because they remove a
significant part of the hills. Other impacts will be the noise generated during
aggregate acquisition through explosive and crushing, which could affect wildlife in
the area, dust produced during the crushing operation to get the aggregates to the
appropriate size and transport of the aggregates, and transport of materials.
6.2 CONSTRUCTION MATERIAL REQUIREMENT
The construction material requirement for Pancheshwar Complex and Rupaligad
Complex are given in Table-6.1.
Table-6.1: Construction Material Requirement for Pancheshwar Complex and Rupaligad Complex
S. No. Type of Material Quantity Required (Mm3)
Source of Material
A. Pancheshwar Complex
1. Impervious Core 13.18 Harkhera area (Indian side)
2. Filter Material 4.69 Common Excavation
3. Shell Materials 120.00 River bed material
4. Concrete- coarse and fine aggregates
2.88 Leopard Quarry Tiger & Little Elephant Quarry Rock excavation - 47.862 Mm3
B. Rupaligad Complex
1. Concrete- coarse and fine aggregates
1.8 Birmola
U/s of dam axis
D/s of Dam axis
Source: DPR
6.3 IMPACTS DUE TO QUARRYING The quarrying operations are semi-mechanized in nature. Normally, in a hilly
terrain, quarrying is normally done by cutting a face of the hill. A permanent scar
is likely to be left, once quarrying activities are over. With the passage of time, the
rock from the exposed face of the quarry under the action of wind and other
erosion forces, get slowly weathered and after some time, they become a potential
source of landslide. Thus it is necessary to implement appropriate slope
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 6: Restoration Plan for Quarries Page 2
stabilization measures to prevent the possibility of soil erosion and landslides in
the quarry sites.
The measures suggested for landscaping of these quarry sites comprise of
construction of garland drains around quarry site , construction of concrete guards
check the soil erosion of the area, filling of depressions / pit formed after
excavation with small rocks, sand, laying top soil cover, barbed wire fencing and
re-vegetation by through ‘Integrated Biological and Biotechnological Approach’.
6.4 RESTORATION PLAN FOR QUARRIES
i) Measures to be adopted before quarrying
The top 6-12” of soil will be removed before starting the quarrying activity or any
other surface disturbance. This top soil will be kept separate and stock piled so
that it can be reused after quarrying is over for rehabilitation of sites.
ii) Measures to be adopted after quarrying
Diversion of run off
Effective drainage system will be provided to avoid the infiltration of run-off and
surface waters into the ground of quarry sites. Garland drains around quarry site
shall be constructed to capture the runoff and divert the same to the nearest
natural drain.
Filling of depressions
Removal of rocks from quarry sites for different construction works will result in the
formation of depression and/or craters. These will be filled by the dumping
materials consisting of boulders, rock, gravel and soil from nearby plant/working
sites.
Construction of retaining walls
Retaining walls will be constructed at the filled up depressions of quarry sites to
provide necessary support particularly where there are moderately steep slopes. In
addition concrete guards, shall be constructed to check the soil erosion of the
area.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 6: Restoration Plan for Quarries Page 3
Rocks for landscaping
After the quarrying activities are over, these sites will be splattered with the
leftovers of rocks and boulders. These boulders and rocks can support the growth
of mosses and lichens, which will act as ecological pioneers and initiate the
process of succession and colonization. The boulders of moderate size will be
used to line the boundary of a path.
Laying of the top soil
The depressions/craters filled up with rock aggregates will be covered with top soil.
Fungal spores naturally present in top soil will aid plant growth and natural plant
succession. The top soil will be further enriched by organic manure and Vesicular-
arbuscularmycorrhizal (VAM) fungi. This will help in the process of soil reclamation
and the early establishment of juvenile seedlings.
Barbed wire fencing the area of rock quarry site will be fenced to prevent entry of
animals in the quarry area and to protect the plantation from grazing and to
enhance natural regeneration.
Re-vegetation
The work plan formulated for re-vegetation of the dumping sites through
‘Integrated Biological and Biotechnological Approach’ would be based upon the
following parameters:
i) Evaluation of rock material for their physical and chemical properties to
assess the nutrient status to support vegetation.
ii) Formulation of appropriate blends of organic waste and soil to enhance
the nutrient status of rhizosphere.
iii) Isolation and screening of specialized strains of mycorrhizal fungi,
rhizobium, azotobacter and phosphate solubilizers (bio-fertilizers
inoculums) suitable for the mined out sites.
iv) Mass culture of plant specific biofertilizer and mycorrhizal fungi to be
procured from different institutions/organisations which are engaged in
the phyto-remediation activity of degraded areas.
v) Plantation at quarry sites/areas using identified blend and
biofertilizerinoculums.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 6: Restoration Plan for Quarries Page 4
6.5 BUDGET FOR RESTORATION OF QUARRIES
An amount of Rs. 3000 lakh has been earmarked for implementation of restoration
plan for quarries. The details are given in Table-6.2.
Table-6.2: Cost estimate for restoration of quarry site and borrow area
S. No. Activities/purpose Cost(Rs. lakh)
1. Filling up the land with soil 650.0
2. Cost of green manure 200.0
3. Cost of sapling (10,000 saplings/ha) 250.0
4. Cost of fertilizers and pesticides 300.0
5. Fencing with RCC pillars and barbed wire 600.0
6. Maintenance activities including cleaning of
weeds @ Rs.10,00,000 for 5 years
50.0
7. Digging of pits 50.0
8. Construction of garland drains 900.0
Total 3000.0
6.6 LANDSCAPING AND RESTORATION PLAN
Area for landscaping
The working area of dam site, power house complex colony area have been
selected for beautification of the project area after construction is over. The
reservoir created due to the construction of dam may be a local point of tourist
attraction. This could be used for sport fishing, so there is a need to construct
benches for sitting, development of resting sheds and footpath. The beautification
would be carried out by developing flowering beds for plantation ornamental plant
and flower garden.
There would be sufficient open space in power house complex and colony area.
Forested area in the power house complex would provide aesthetic view and add
to natural seismic beauty. The beautification in the colony area would be carried
out by development of flowering beds for plantation of ornamental plant, creepers,
flower garden and a small park, construction of benches for sitting, resting sheds,
walk way and fountain.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 6: Restoration Plan for Quarries Page 5
A provision of Rs. 290 lakh has been earmarked for landscaping and beautification
of the area.
6.7 BUDGET
A total provision of Rs. 3290.0 lakh has been earmarked for Restoration of quarry
sites, reclamation of construction sites landscaping and beautification (Refer
Table-6.3).
Table-6.3: Summary of costs for Restoration and Reclamation works
S.No. Activity Cost (Rs. lakh)
1. Restoration of quarry sites 3000.0
2. Reclamation of construction sites 290.0
Total 3290.0
CHAPTER-7
ENVIRONMENTAL MANAGEMENT IN ROAD CONSTRUCTION
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 7: Environmental Management in Road Construction Page 1
CHAPTER-7
ENVIRONMENTAL MANAGEMENT IN ROAD CONSTRUCTION
7.1 INTRODUCTION
The approach roads will have to be constructed as a part of providing access to
the construction site. In a hilly environment, construction of roads sometime
disturbs the scenic beauty of the area. In addition, landslides are often triggered
due to road construction because of the loosening of rocks by water trickling from
various streams.
7.2 IMPACTS DUE TO CONSTRUCTION OF ROADS
The construction of roads can lead to the following impacts:
The topography of the project area has steep slope, which descends rapidly
into narrow valleys. The conditions can give rise to erosion hazards due to
net downhill movement of soil aggregates.
Removal of trees on slopes and re-working of the slopes in the immediate
vicinity of roads can encourage landslides, erosion gullies, etc. With the
removal of vegetal cover, erosive action of water gets pronounced and
accelerates the process of soil erosion and formation of deep gullies.
Consequently, the hill faces are bared of soil vegetative cover and
enormous quantities of soil and rock can move down the rivers, and in
some cases, the road itself may get washed out.
Construction of new roads increases the accessibility of a hitherto
undisturbed areas resulting in greater human interferences and subsequent
adverse impacts on the ecosystem.
Increased air pollution during construction phase.
7.3 MANAGEMENT MEASURES
The various aspects to be considered while making the project roads are briefly
described in the following figures and paragraphs.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 7: Environmental Management in Road Construction Page 2
Construction
Area for clearing shall be kept minimum subject to the technical requirements
of the road. The clearing area shall be properly demarcated to save desirable
trees and shrubs and to keep tree cutting to the minimum.
Where erosion is likely to be a problem, clearing operations shall be so
scheduled and performed that grading operations and permanent erosion
control of features can follow immediately thereafter, if the project conditions
permit; otherwise temporary erosion control measures shall be provided
between successive construction stages. Under no circumstances, however,
should very large surface area of erodible earth material be exposed at any
one time by clearing.
The method of balanced cut and fill formation shall be adopted to avoid large
difference in cut and fill quantities. (Refer Figure-7.1).
Figure-7.1: Method of balanced cut and fill formation
The cut slopes shall be suitably protected by breast walls, provision of flat
stable slopes, construction of catch water and intercepting drains, treatment of
slopes and unstable areas above and underneath the road, etc. (Refer Figure-
7.2).
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 7: Environmental Management in Road Construction Page 3
Figure-7.2: Protection of slopes
Landslide prone areas shall be treated with location specific engineering
protection measures.
Where rock blasting is involved, controlled blasting techniques shall be adopted
to avoid over-shattering of hill faces.
Excavated material should not be thrown haphazardly but dumped duly
dressed up in a suitable form at appropriate places where it cannot get easily
washed away by rain, and such spoil deposits may be duly trapped or provided
with some vegetative cover.
Drainage
Drainage of the water from hill slopes and road surface is very important. All
artificial drains shall be linked with the existing natural drainage system.
Surface drains shall have gentle slopes. Where falls in levels are to be
negotiated, check dams with silting basins shall be constructed and that soil is
not eroded and carried away by high velocity flows.
Location and alignment of culverts should also be so chosen as to avoid severe
erosion at outlets and siltation at inlets.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 7: Environmental Management in Road Construction Page 4
Grassing and Planting
Tree felling for road construction/works should be kept bare minimum and strict
control must be exercised in consultation with the Forest Department.
Equivalent amount of new trees should be planted as integral part of the project
within the available land and if necessary, separate additional land may be
acquired for this purpose.
Depending on the availability of land and other resources, afforestation of
roadside land should be carried out to a sufficient distance on either side of the
road.
7.4 BUDGET
An amount of Rs. 4472 lakh has been earmarked for implementation of various
measures for Environmental Management in road construction.The details are
given in Table-7.1.
Table-7.1: Details of expenditure for implementation of measures for management
of Impacts due to construction of roads
S.No. Item Cost (Rs. lakh)
1. Clearing @ Rs.2.5 lakh per km for 172 km 430.0
2. Provision of breast walls, construction of catch
water and interceptor drains @Rs.10.5 lakh per
km for 172 km
1806.0
3. Provision of drainage system along roads
@Rs.10 lakh per km for 172 km
1720.0
4. Roadside plantation, Jute matting etc. @ Rs.3
lakh per km for 172 km
516.0
Total 4472.0
CHAPTER-8
GREENEBELT DEVELOPMENT PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 8: Greenbelt Development Plan Page 1
CHAPTER-8
GREENBELT DEVELOPMENT PLAN
8.1 INTRODUCTION
The greenbelt development plan aims to overall improvement in the environmental
conditions of the region. The plan with a five-fold objective addresses issues such
as prevention of land degradation due to activities during construction phase;
enhancing the forest cover for increasing the biodiversity of the region; providing
aesthetic value to the project area and consequently inviting a proportionate tourist
flux; enhancing the ecological equilibrium of the area; and to a large proportion in
combating soil erosion. Although the forest loss due to reservoir submergence and
other project appurtenances have been compensated as a part of compensatory
afforestation. It is proposed to develop greenbelt around the periphery of various
project appurtenances, selected stretches along reservoir periphery.
8.2 NEED FOR GREENBELT DEVELOPMENT PLAN
The green belt on either side of the reservoir will reduce the sedimentation and
ensure protection of the reservoir area from any other human activity that could
result in the reservoir catchment damage. On moderately steep slopes tree
species will be planted for the creation of green belt which are indigenous,
economically important, soil binding in nature and an thrive well under high
humidity and flood conditions.
8.3 SCHEME FOR GREENBELT DEVELOPMENT
The scheme of plantation around the reservoir is given as follows:
i) The green belt will start from the immediate vicinity of the reservoir rim
on both the banks, up to the tail of the reservoir moderately steep slopes
are available for plantation.
ii) The width of the green belt will be around 50 m or as physiographic and
land features allow. There would be at least 2-3 layers of plantation.
iii) The green belt will be put under a protective regulatory framework to
ensure that it is not degraded or disturbed. No ecologically disruptive
activity will be allowed in this zone.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 8: Greenbelt Development Plan Page 2
8.4 BUDGET
The plantations would be carried out on an approximate area of 36 ha. This work
would be completed in three years at an estimated cost of Rs.43.2 lakh at the rate
of Rs. 1.2 lakh/ha which includes the cost of nursery creation, advance works,
actual plantations and maintenance. The plantation for this purpose will be carried
out by Forest Department, state government of Uttarakhand.
CHAPTER-9
CONTROL OF AIR POLLTION
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 9: Control of Air Pollution Page 1
CHAPTER-9
CONTROL OF AIR POLLUTION
9.1 IMPACTS ON AIR QUALITY
In a water resources project, air pollution occurs mainly during project
construction phase. The major sources of air pollution during construction phase
are:
Fuel combustion in various construction equipment, e.g. crushers, drillers,
rock bolters, diesel generating vehicles, etc.
Fugitive emissions from crusher
Impacts due to vehicular movement
a) Pollution due to fuel combustion in various equipment
The operation of various construction equipment requires combustion of fuel.
Normally, diesel is used in such equipment. The major pollutant, which gets
emitted as a result of diesel combustion, is SO2. The SPM emissions are
minimal. Based on past experience in similar projects, SPM and SO2 are not
expected to increase significantly. Thus, in the proposed project, no significant
impact on ambient air quality is expected as a result of operation of various
construction equipment.
b) Emissions from crusher
The operation of the crusher during the construction phase is likely to generate
fugitive emissions, which can move even up to 1 km in predominant wind
direction. During construction phase, crushers of total capacity of 750 TPH are
likely to be commissioned. During crushing operations, fugitive emissions
comprising of the suspended particulate will be generated. There could be
marginal impacts to settlements close to the sites at which crusher is
commissioned. However, based on past experience, adverse impacts on this
account are not anticipated. However, during finalizing the project layout, it should
be ensured that the labour camps, colonies, etc. are located on the leeward side
and outside the impact zone (about 1.5 to 2 km) of the crushers.
c) Impacts due to vehicular movement
During construction phase, there will be increased vehicular movement for
transportation of various construction materials to the project site. Large
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 9: Control of Air Pollution Page 2
quantity of dust is likely to be entrained due to the movement of trucks and
other heavy vehicles. However, such ground level emissions do not travel for
long distances. Thus, no major adverse impacts are anticipated on this
account.
9.2 MITIGATION MEASURES
a) Control of Emissions
Minor air quality impacts will be caused by emissions from construction
vehicles, equipment and DG sets, and emissions from transportation traffic.
Frequent truck trips will be required during the construction period for removal
of excavated material and delivery of select concrete and other equipment and
materials. The following measures are recommended to control air pollution:
The contractor will be responsible for maintaining properly functioning
construction equipment to minimize exhaust.
Construction equipment and vehicles will be turned off when not used for
extended periods of time.
Unnecessary idling of construction vehicles to be prohibited.
Effective traffic management to be undertaken to avoid significant delays
in and around the project area.
Road damage caused by sub-project activities will be promptly attended
to with proper road repair and maintenance work.
b) Air Pollution control due to DG sets
The Central Pollution Control Board (CPCB) has issued emission limits for
generators upto 800 KW. The same are outlined in Table-9.1, and are
recommended to be followed.
Table-9.1: Emission limits for DG sets prescribed by CPCB
Parameter Emission limits (gm/kwhr)
NOx 9.2
HC 1.3
CO 2.5
PM 0.3
Smoke limit* 0.7
Note : * Light absorption coefficient at full load (m-1)
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 9: Control of Air Pollution Page 3
The above standards need to be followed by the contractor operating the DG
sets.
The other measures are recommended as below:
Location of DG sets and other emission generating equipment should be
decided keeping in view the predominant wind direction so that emissions
do not effect nearby residential areas.
Stack height of DG sets to be kept in accordance with CPCB norms, which
prescribes the minimum height of stack to be provided with each generator
set to be calculated using the following formula:
H = h+0.2x √KVA
H = Total height of stack in metre
h = Height of the building in metres where the generator set is installed
KVA = Total generator capacity of the set in KVA
c) Dust Control
The project authorities will work closely with representatives from the
community living in the vicinity of project area to identify areas of concern and
to mitigate dust-related impacts effectively (e.g., through direct meetings,
utilization of construction management and inspection program, and/or through
the complaint response program). To minimize issues related to the generation
of dust during the construction phase of the project, the following measures
have been identified:
Identification of construction limits (minimal area required for
construction activities).
When practical, excavated spoils will be removed as the contractor
proceeds along the length of the activity.
When necessary, stockpiling of excavated material will be covered or
stacked at offsite location with muck being delivered as needed during
the course of construction.
Excessive soil on paved areas will be sprayed (wet) and/or swept and
unpaved areas will be sprayed and/or mulched.
Contractors will be required to cover stockpiled soils and trucks hauling
soil, sand, and other loose materials
Contractor shall ensure that there is effective traffic management at site.
Dust Suppression – The roads, construction area and vicinity (access
roads, and working areas) shall be sprinkled with water on daily basis to
suppress dust.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 9: Control of Air Pollution Page 4
9.3 BUDGET FOR AIR POLLUTION CONTROL
An amount of Rs. 900.0 lakh is earmarked for air pollution control. The details
are given in Table-9.2.
Table-9.2: Cost estimate for implementation of air pollution control measures
S. No. Activity Cost (Rs. Lakh)
1. Dust Suppression – Water sprinkling on roads
during construction phase
625.00
2. 5 Traffic managers @ Rs.25,000 per month for 8
years including 10% escalation per year
171.60
3. 5 Sweepers @ Rs.15,000 per month for 8 years
including 10% escalation per year
102.96
Total 899.56, say Rs.
900 lakh
9.4 IMPLEMENTING AGENCY
Various management measures needs to be implemented for control of air
pollution control need to be included in the Tender Document for the Contractor
involved in construction activities. The same shall be monitored on a regular
basis by the project proponents.
CHAPTER-10
MEASURES FOR NOISE CONTROL
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 10: Measures for Noise Control Page 1
CHAPTER-10
MEASURES FOR NOISE CONTROL
10.1 IMPACTS ON NOISE LEVELS
In a water resource projects, the impacts on ambient noise levels are expected
only during the project construction phase, due to earth moving machinery, etc.
Likewise, noise due to quarrying, blasting, vehicular movement will have some
adverse impacts on the ambient noise levels in the area.
10.2 MITIGATION MEASURES
The contractors will be required to maintain properly functioning equipment and
comply with occupational safety and health standards. The construction
equipment will be required to use available noise suppression devices and
properly maintained mufflers.
Vehicles to be equipped with mufflers recommended by the vehicle
manufacturer.
Staging of construction equipment and unnecessary idling of
equipment within noise sensitive areas to be avoided whenever
possible.
Notification will be given to residents within 100 m of major noise
generating activities. The notification will describe the noise
abatement measures that will be implemented.
Monitoring of noise levels will be conducted during the construction
phase of the project. In case of exceeding of pre-determined
acceptable noise levels by the machinery will require the
contractor(s) to stop work and remedy the situation prior to
continuing construction.
The following Noise Standards for DG sets are recommended for the running of
DG sets during the construction:
The maximum permissible sound pressure level for new diesel generator
sets with rated capacity upto 1000 KVA shall be 75 dB(A) at 1 m from the
enclosure surface.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 10: Measures for Noise Control Page 2
Noise from the DG set should be controlled by providing an acoustic
enclosure or by treating the enclosure acoustically.
The Acoustic Enclosure shall be made of CRCA sheets of appropriate
thickness and structural/ sheet metal base. The walls of the enclosure shall
be insulated with fire retardant foam so as to comply with the 75 dB(A) at 1
m sound levels specified by CPCB, Ministry of Environment & Forests.
The acoustic enclosure/acoustic treatment of the room shallbe designed for
minimum 25 dB(A) Insertion Loss or for meeting the ambient noise
standards, whichever is on the higher side.
The DG set shallalso be provided with proper exhaust muffler.
Proper efforts shall be made to bring down the noise levels due to the DG
set, outside its premises, within the ambient noise requirements by proper
siting and control measures.
A proper routine and preventive maintenance procedure for the DG set
shallbe set and followed in consultation with the DG set manufacturer which
would help prevent noise levels of the DG set from deteriorating with use.
Noise due to crushers
Based on literature review, noise generated by a crusher is in the range of 79-80
dB(A) at a distance of 250 ft or about 75 m from the crusher. Thus, noise level at a
distance of 2 m from the crusher shall be of the order of 110 dB(A). The exposure
to labour operating in such high noise areas shall be restricted upto 30 minutes on
a daily basis. Alternatively, the workers need to be provided with ear muffs or
plugs, so as to attenuate the noise level near the crusher by atleast 15 dB(A). The
exposure to noise level in such a scenario to be limited upto 4 hours per day.
It is known that continuous exposure to noise levels above 90 dB(A) affects the
hearing of the workers/operators and hence has to be avoided. Other
physiological and psychological effects have also been reported in literature, but
the effect on hearing acuity has been specially stressed. To prevent these effects,
it has been recommended by international specialist organizations that the
exposure period of affected persons be limited as specified in Table-10.1.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 10: Measures for Noise Control Page 3
Table-10.1: Maximum Exposure Periods specified by OSHA
Maximum equivalent continuous
noise level dB(A)
Unprotected exposure period per
day for 8 hrs/day and 5 days/week
90 8
95 4
100 2
105 1
110 ½
115 ¼
120 No exposure permitted at or above this
level
Measures to control noise due to blasting
Various measures outlined for control of noise due to blasting is given as below:
Use of backfill cover has the potential to reduce air overpressure levels by
10 dB (A).
Air overpressure levels may also be reduced by deck loading. In a blast with
a significant vertical free face, this reduction may in some circumstances be
obtained by deck loading the front row holes fired on the initial delays only,
without needing to deck load all the front row holes.
Rock excavation by blasting shall be done for all solid rock in place which
can not be removed until loosened by blasting, barring or wedging, removal
of all big boulders or detached pieces of massive rock.
Rock excavation close to the final excavated surfaces shall be performed
using controlled blasting methods such as "pre-splitting", "cushion blasting"
or “smooth blasting". Line-drilling shall be used to limit the overbreak and
damage of surround rock.
All excavations shall be performed using methods and techniques that will
produce smooth and sound rock surfaces with minimum overbreak and
fracturing beyond the lines and grades or limits of excavation. Drilling and
blasting shall be done in such a manner as to ensure that the rock will break
along the desired lines and grades. Rock faces and slopes shall be scaled
or cleaned of loose or overhanging rock immediately after excavation.
Blast holes shall be drilled not exceeding two-third of the depth of rock to be
excavated from the elevation at which the hole is started. The holes shall
not be larger than necessary to permit easy passage of whole sticks of
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 10: Measures for Noise Control Page 4
explosives to the bottom of the holes. As the excavation approaches its final
limits, the depth of holes for blasting and the amount of charges for the
holes shall be reduced progressively.
Blasting shall be carried out with non-electric detonators only except for the
cord/fuse initiation by electric detonators. A separate circuit, independent of
power and light circuits, shall be used for blasting.
Charging, tamping and firing of drilled holes shall be done by an approved
licensed person under his personal direction. Proper signals by siren shall
be given before each operation of blasting.
Blasting shall be permitted only when proper precautions are taken for the
protection of persons, work and property. Any damage done to the work or
property by blasting shall be repaired immediately.
A trained professional shall be hired to monitor the technical specifics of the
blast, such as size and depth of drilled holes, and the type and amount of
explosive used.
CHAPTER-11
WATER POLLUTION CONTROL
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 11: Water Pollution Control Page 1
CHAPTER-11
WATER POLLUTION CONTROL
11.1 CONTROL OF WATER POLLUTION DURING CONSTRUCTION PHASE
During project construction phase, sufficient measures need to be implemented to
ameliorate the problem of water pollution from various sources. The sewage
generated from various labour camps should be treated in septic tanks and
disposed by discharging into nearest water body. However, efforts shall be made
to discharge the treated effluent only in these water bodies, which are not used for
meeting domestic water requirements.
i) Effluent from tunneling work
During tunneling work the ground water flows into the tunnel along with
construction water, which is used for various works like drilling, shotcreting, etc.
The effluent thus generated in the tunnel contains high suspended solids.
Normally, water is collected in the side drains and drained off into the nearest
water body without treatment. It is recommended to construct a settling tank of
adequate size to settle the suspended impurities. 7 no adits and 10 portals shall be
required for the underground work. Thus, effluents are expected to be generated
from these locations. The sludge from the various settling tanks can be collected
once in 15 days and disposed at the site designed for disposal of municipal solid
wastes. The sludge after drying could also be used as cover material for landfill
disposal site. An amount of Rs. 180.0 lakh has been earmarked for construction of
various settling tanks.
ii) Effluent from crushers
During construction phase, crushers will be installed at various locations in the
project area. While operating a crusher, water is required to wash the boulders and
to lower the temperature of the crushing edge. About 0.1 m3 of water is required
per tonne of material crushed. The effluent from the crusher would contain high
suspended solids, i.e. 3,000 to 4,000 mg/l. The effluent from crusher, if disposed
without settling in settling tanks can lead to increase in the turbidity levels in the
receiving water bodies.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 11: Water Pollution Control Page 2
Five crushing units have been proposed for the project at different project
locations. If the effluent is discharged into the receiving water body at different
locations there shall be marginal increase in turbidity of the river water. Thus, no
adverse impacts, are anticipated due to small quantity of effluent and large volume
of water available in river Mahakali for dilution. However, it is proposed to treat the
effluent in settling tanks before disposal into receiving water body. An amount of
Rs. 200.0 lakh has been earmarked for construction of various settling tanks
iii) Effluent from Batching Plants
During construction phase, batching plants will be commissioned for production of
concrete. Effluent containing high suspended solids shall be generated during
operation and cleaning of batching plants. However, no major adverse impacts,
are anticipated due to small quantity of effluent and large volume water available
for dilution in river Mahakali. It is proposed to treat the effluent before disposal to
ameliorate even the marginal impacts likely to accrue on this account. An amount
of Rs. 100.0 lakh has been earmarked for construction of settling tanks to treat
effluent generated from Batching Plants.
iv) Effluent from Fabrication Units and Workshops
The fabrication units and workshops which shall be functional during construction
phase will generate effluents with high suspended solids and oil and grease level.
It is proposed to treat the effluent from fabrication units and workshops in a oil and
grease separate unit prior to disposal. An amount of Rs.200.0 lakh has been
earmarked for construction of settling tanks to treat effluent generated from
Fabrication Units and Workshops.
11.2 CONTROL OF WATER POLLUTION DURING OPERATION PHASE
In the project operation phase, a plant colony with 50 quarters and nonresidential
buildings is likely to be set up. It is recommended to provide a suitable Sewage
Treatment Plant (STP) to treat the sewage generated from the colony. The cost
required for construction of sewage STP in the project colony has already been
covered in the budget earmarked for construction of the project colony. Hence, the
cost for the same has not been included in the cost for implementing EMP.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 11: Water Pollution Control Page 3
11.3 BUDGET
The total budget earmarked for water pollution control measures is Rs. 680.0 lakh .
The details are given in Table-11.1.
Table-11.1: Budget earmarked for water pollution control measures
S. No. Source of effluent Cost (Rs. lakh)
1 Effluent from tunneling work 180.00
2 Effluent from crushers 200.00
3 Effluent from batching plants 100.00
4 Effluent from Fabrication Units and Workshops 200.00
Total 680.00
CHAPTER-12
ENERGY CONSERVATION MEASURES
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 12: Energy Conservation Measures Page 1
CHAPTER-12
ENERGY CONSERVATION MEASURES
12.1 GENERAL
Energy conservation measures would be implemented to ensure that the use of
non-renewable resources is minimised. A key component of achieving energy
conservation would be the development of an Energy Management Action Plan.
This plan would be included as part of the Construction and Operational EMPs.
The Energy Management Action Plan would be consistent with the energy
conservation measures during both construction and operation phases.
12.2 PROVISION OF FREE FUEL
As a part of EMP, following measures are proposed:
- Make a clause mandatory in the contract of every contractor involved in
project construction to provide supply of fuel to their labourers, so that trees
are not cut for meeting their fuel demands.
- Establish LPG godown within the project area for providing LPG cylinder to
run community kitchens.
-
The project proponents in association with the state government should make
necessary arrangements for distribution of LPG.
The total increase in labour population shall be 22,500. For every 8 persons, 1
LPG Cylinder shall be taken per month. Thus, every month about 2850 LPG
Cylinder will be ensured, which works out to about 34,200 cylinder per year.
Considering the cost of each LPG Cylinder as Rs. 2000 and taking 10% escalation
in cost every year, the total cost for provision of fuel works out to Rs. 7840
lakh.This cost is already considered in the EMP cost earmarked for
implementation of Environmental Management Measures in labour camps.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 12: Energy Conservation Measures Page 2
12.3 ENERGY CONSERVATION DURING CONSTRUCTION PHASE
The following mitigation measures would be undertaken during construction works.
Efficient work scheduling and methods that minimise equipment idle time and
double handling of material
Throttling down and switching off construction equipment when not in use
Switching off truck engines while they are waiting to access the site and while
they are waiting to be loaded and unloaded
Switching off site office equipment and lights and using optimum lighting
intensity for security and safety purposes
Careful design of temporary roads to reduce transportation distances
Regular maintenance of equipment to ensure optimum operations and fuel
efficiency.
12.4 ENERGY CONSERVATION DURING OPERATION PHASE
The mitigation measures would be implemented during site operations as follows:
Design of buildings and layout would aim to achieve energy efficiencies by
employing renewable energy sources such as day lighting and passive solar
heating
Designing roads on the site to reduce transportation distances.
12.5 ENERGY EFFICIENT EQUIPMENT
Large energy savings could be achieved in using energy efficient equipment. The
following measures are recommended for energy conservation:
Using energy efficient electrical appliances
Installing lighting control devices where appropriate and linking to photo-electric
dimming
Providing sufficient energy metering and switching for energy management.
Energy would also be conserved through efficiency in work schedules and
practices such as:
Use of modern container yard management systems for the efficient stacking
and retrieval of containers and to minimise vehicles waiting times
Switching off truck engines while they are waiting to access the site and while
these are waiting to be loaded and unloaded
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 12: Energy Conservation Measures Page 3
Throttling down and switching off idle equipment
Regular maintenance of all powered equipment to ensure appropriate fuel
consumption rates
Communication and education of energy conservation measures to employees.
12.6 BUDGET
An amount of Rs. 450.0 lakh has been earmarked for implementation of various
energy conservation measures.
CHAPTER-13
FIRE PROTECTION IN LABOUR CAMPS AND STAFF COLONIES
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 13: Fire Protection Measures Page 1
CHAPTER-13
FIRE PROTECTION IN LABOUR CAMP AND STAFF COLONIES
13.1 INTRODUCTION
It has been envisaged that the fire protection planning in labour camps and staff
colonies shall be taken up. The details are given in following sections of this
chapter.
13.2 CONSTRUCTION OF CAMPS ETC. AND PLACEMENT OF FIRE
PROTECTION EQUIPMENT
It has been planned that all facilities to be constructed shall be fully equipped with
the fire protection equipments as per IS standards. The analysis of fire hazard in
the construction of these camps, colonies and other facilities is given in Table-
13.1.
Table-13.1: Analysis of fire hazard in the construction of camps, colonies and other
facilities
S. No Stage Potential hazard Remedial Measures
1. Construction
of labour
camps and
staff colonies
Fire prevention
and firefighting
not considered in
design
Inadequate fire
protection
measures during
construction
phase
BY PROJECT PROPONENT
While construction of Field
hostels, Guest House/office and
other facilities owned by project
proponent shall provide the fire
protection system as per IS
Standards for Fire code.
Proper housekeeping will also
be ensured and maintained
during these facilities to protect
them from any fire related
incidents.
It will be ensured that the
firefighting equipments are
placed at common place also
including work place preferably
within 15 meters of work place.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 13: Fire Protection Measures Page 2
S. No Stage Potential hazard Remedial Measures
BY CONTRACTORS
Clear term of reference will be
given to contractor at tendering
stage for incorporating fire code
as per IS Standard.
Firefighting equipments will be
placed at all common places
(within 15 meters of work place)
13.3 IMPLEMENTATION OF FIRE PROTECTION SYSTEM
During construction, it has been envisaged to set up full-fledged Environment
Health & Safety (EHS) department reporting directly to Head of Project. This
department shall also take care of the adequacy of Fire Safety measures set up in
all facilities created either owned by project proponent or any of its Contractors.
The analysis of responsibility for this EHS team in respect of Fire protection
system is given in Table-13.2
Table-13.2: Responsibility for this EHS team in respect of Fire protection system
S. No. Stage Potential hazard Remedial Measures
1. During
Occupation
Fire incident due to
electrical short
circuit/LPG Leakage/
Improper handling of
flammable liquids/lack
of precaution
Improper access to
and from the location
In adequate fire
fighting arrangements
Lack of knowledge
Lack communication
Lack of Knowledge on
fighting fire and
handling fire
equipment
Inadequate emergency
response
Residential complex will be
constructed as per the
approved design and will
be checked for
completeness on fire
aspect before allotment to
residents
Each Block Colony/ camp
will be provided with rated
estimated trip off circuit
breaker will be installed on
each block.
All residents are made
aware of fire hazard by
training, regular campaigns
and by placing posters and
signs
LPG Cylinders/Flammable
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 13: Fire Protection Measures Page 3
S. No. Stage Potential hazard Remedial Measures
liquids will stored at
designated storage area.
The storage will be well
protected, ventilated with
adequate provision of fire
equipment.
Each block of the colony
will be provided with 10 kg
DCP fire extinguishers.
Additionally fire point
containing fire buckets,
CO2 extinguishers, DCP
Extinguisher will be
provided at the common
place covering four
residential blocks in labour
camp.
Placement of written
posters of preventive
measures in each
accommodation block
Regular EHS inspection of
the camp site
Placement of placard of
emergency numbers to be
contacted in case of
Emergency
Dedicated phone line will
be provided in labour
camps for effective
communication.
Ensure proper access is
maintained around and to
the residential blocks
Identification of emergency
Muster points at safe
distance
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 13: Fire Protection Measures Page 4
13.4 RESPONSIBILITY
Project In charge is responsible for implementation of plan through his authorized
representative on site. Site EHS Team shall monitor the implementation of plan
and report noncompliance to site management.
13.5 TRAINING AND AWARENESS
Training of employees on fire prevention and firefighting is important to prevent
occurrence of fire incident in project area. All employees will be given brief
overview of fire prevention, firefighting procedure and response process at the
time EHS Induction training. Project proponent will also carry out regular
campaigns on fire prevention around the site. EHS Department is responsible for
providing required training.
13.6 BUDGET
The firefighting system in the project area will be suitably built in the contract
document which would be executed by specialized vendors, cost for which will be
included in the project cost.
CHAPTER-14
CATCHMENT AREA TREATMENT PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 1
CHAPTER-14
CATCHMENT AREA TREATMENT PLAN
14.1 NEED FOR CATCHMENT AREA TREATMENT
It is a well-established fact that reservoirs formed by dams on rivers are subjected to
sedimentation. The process of sedimentation embodies the sequential processes of
erosion, entrainment, transportation, deposition and compaction of sediment. The
study of erosion and sediment yield from catchments is of utmost importance as the
deposition of sediment in reservoir reduces its capacity, and thus affect the water
availability for the designated use. The eroded sediment from catchment when
deposited on streambeds and banks causes braiding of river reach. The removal of
top fertile soil from catchment adversely affects the agricultural production. Thus, a
well-designed Catchment Area Treatment (CAT) Plan is essential to ameliorate the
above-mentioned adverse process of soil erosion.
Soil erosion may be defined as the detachment and transportation of soil. Water is the
major agent responsible for this erosion. In many locations, winds, glaciers, etc. also
cause soil erosion. In a hilly catchment area as in the present case, erosion due to
water is a common phenomenon and the same has been studied as a part of the
Catchment Area Treatment (CAT) Plan.
The CAT plan highlights the management techniques to control erosion in the
catchment area. Life span of a reservoir in case of a seasonal storage dams is greatly
reduced due to erosion in the catchment area. The catchment area considered for
treatment of Pancheswar Project is 14147sq.km. The sub-watersheds in the
catchment area considered for the present study are given in Figure-14.1.
In the present study `Silt Yield Index’ (SYI), method has been used. In this method,
the terrain is subdivided into various watersheds and the erodibility is determined on
relative basis. SYI provides a comparative erodibility criteria of catchment (low,
moderate, high, etc.) and do not provide the absolute silt yield. SYI method is widely
used mainly because of the fact that it is easy to use and has lesser data requirement.
Moreover, it can be applied to larger areas like sub-watersheds, etc.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 2
Figure-14.1 : Drainage Map for Pancheswar Catchment
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 3
14.2 APPROACH FOR THE STUDY
Various thematic maps have been used in preparation of the CAT plan. Due to the
spatial variability of site parameters such as soils, topography, land use and rainfall,
not all areas contribute equally to the erosion problem. Several techniques like manual
overlay of spatially index-mapped data have been used to estimate soil erosion in
complex landscapes.
Geographic Information System (GIS) is a computerized resource data base system,
which is referenced to some geographic coordinate system. In the present study, real
coordinate system has been used. The GIS is a tool to store, analyze and display
various spatial data. In addition, GIS because of its special hardware and software
characteristics, has a capacity to perform numerous functions and operations on the
various spatial data layers residing in the database. GIS provides the capability to
analyze large amounts of data in relation to a set of established criteria.
In order to ensure that latest and accurate data is used for the analysis, satellite data
has been used for deriving land use data and ground truth studies too have been
conducted.
The various steps covered in the study are as follows:
Data acquisition
Data preparation
Output presentation
The above mentioned steps are briefly described in the following paragraphs.
14.2.1 Data Acquisition
The requirement of the study was first defined and the outputs expected were noted.
The various data layers of the catchment area used for the study are as follows:
Soil Map
Land use Classification Map
Current Management Practices
Catchment Area Map.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 4
14.2.2 Data Preparation
The data available from various sources was collected. The ground maps, contour
information, etc. were scanned, digitized and registered as per the requirement. Data
was prepared depending on the level of accuracy required and any corrections
required were made. All the layers were geo-referenced and brought to a common
scale (real coordinates), so that overlay could be performed. A computer programme
was used to estimate the soil loss. The formats of outputs from each layer were firmed
up to match the formats of inputs in the program. The grid size used was also decided
to match the level of accuracy required, the data availability and the software and time
limitations. The format of output was finalized. Ground truthing and data collection was
also included in the procedure.
For the present study 5 Resourcesat-,LISS-III imageries are used. The details are
given as below:
RSAT, LISS-III Path 098, Row 049 dated 14.12.2016
RSAT, LISS-III Path 098, Row 050 dated 20.11.2016
RSAT, LISS-III Path 099, Row 050 dated 19.12.2016
RSAT, LISS-III Path 099, Row 051 dated 19.12.2016
RSAT, LISS-III Path 099, Row 049 dated 25.11.2016
The digital satellite data was used for interpretation & classification. The classified
land use map of the catchment area is shown in Figure-14.2. The land use pattern of
the catchment area is summarized in Table-14.1.
Table-14.1: Landuse pattern of the catchment area
Category Area (ha) Percentage
River/ Water body 41679 2.95
Dense Vegetation 534633 37.79
Open Vegetation 562027 39.73
Barren area 151007 10.67
Terrace farming 102329 7.23
Snow 18790 1.33
Builtup area/Settlements 4234 0.30
Total 1414700 100.00
Digitized contours from toposheets were used for preparation of Digital Elevation
Model (DEM) of the catchment area and to prepare a slope map. The first step in
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 5
generation of slope map is to create surface using the elevation values stored in the
form of contours or points. After marking the catchment area, all the contours on the
toposheet were digitized (100 m interval). The output of the digitization procedure was
the contours as well as points contours in form of x, y & z points. (x, y location and
their elevation). All this information was in real world coordinates (latitude, longitude
and height in meters above sea level).
A Digital Terrain Model (DTM) of the area was then prepared, which was used to
derive a slope map. The slope map is enclosed as Figure-14.3
Various layers thus prepared were used for Modeling. Software was prepared to
calculate the soil loss using input from all the layers.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 5
Figure-14.2 Classified Imagery of Pancheswar catchment Area
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 6
Figure-14.3 Slope Map of Pancheswar catchment Area
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 7
14.2.3 Output Presentation
The result of the modeling was interpreted in pictorial form to identify the areas with
high soil erosion rates. The primary and secondary data collected as a part of the field
studies were used as an input for the model.
14.3 ESTIMATION OF SOIL LOSS USING SILT YIELD INDEX (SYI) METHOD
The Silt Yield Index Model (SYI), considering sedimentation as product of erosivity,
erodibility and arial extent was conceptualized in the All India Soil and Land Use
Survey (AISLUS) as early as 1969 and has been in operational use since then to meet
the requirements of prioritization of smaller hydrologic units.
The erosivity determinants are the climatic factors and soil and land attributes that
have direct or reciprocal bearing on the unit of the detached soil material. The
relationship can be expressed as:
Soil erosivity = f (Climate, physiography, slope, soil parameters, land use/land cover,
soil management)
Silt Yield Index
The Silt Yield Index (SYI) is defined as the Yield per unit area and SYI value for
hydrologic unit is obtained by taking the weighted arithmetic mean over the entire area
of the hydrologic unit by using suitable empirical equation.
Prioritization of Watersheds/Sub-watersheds:
The prioritization of smaller hydrologic units within the vast catchments are based on
the Silt Yield Indices (SYI) of the smaller units. The boundary values or range of SYI
values for different priority categories are arrived at by studying the frequency
distribution of SYI values and locating the suitable breaking points. The watersheds/
sub-watersheds are subsequently rated into various categories corresponding to their
respective SYI values.
The application of SYI model for prioritization of sub watersheds in the catchment
areas involves the evaluation of:
a) Climatic factors comprising total precipitation, its frequency and intensity,
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 8
b) Geomorphic factors comprising land forms, physiography, slope and drainage
characteristics,
c) Surface cover factors governing the flow hydraulics and
d) Management factors.
The data on climatic factors can be obtained for different locations in the catchment
area from the meteorological stations whereas the field investigations are required for
estimating the other attributes.
The various steps involved in the application of model are:
- Preparation of a framework of sub-watersheds through systematic delineation
- Rapid reconnaissance surveys on 1:50,000 scale leading to the generation of a
map indicating erosion-intensity mapping units.
- Assignment of weightage values to various mapping units based on relative silt-
yield potential.
- Computing Silt Yield Index for individual watersheds/sub watersheds.
- Grading of watersheds/sub watersheds into very high, high medium, low and
very low priority categories.
The area of each of the mapping units is computed and silt yield indices of individual
sub watersheds are calculated using the following equations:
a. Silt Yield Index
SYI = (Ai x Wi ) x 100 ; where i = 1 to n
Aw
Where
Ai = Area of ith unit (EIMU)
Wi = Weightage value of ith mapping unit
n = No. of mapping units
Aw = Total area of sub-watershed.
The SYI values for classification of various categories of erosion intensity rates are
given in Table-14.2.
Table-14.2: Criteria for erosion intensity rate
Priority categories SYI Values
Very high > 1300
High 1200-1299
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 9
Priority categories SYI Values
Medium 1100-1199
Low 1000-1099
Very Low <1000
14.4 WATERSHED MANAGEMENT – AVAILABLE TECHNIQUES
Watershed management is the optimal use of soil and water resources within a given
geographical area so as to enable sustainable production. It implies changes in land
use, vegetative cover, and other structural and non-structural action that are taken in a
watershed to achieve specific watershed management objectives. The overall
objectives of watershed management programme are to:
- increase infiltration into soil;
- control excessive runoff;
- Manage & utilize runoff for useful purpose.
Following Engineering and Biological measures have been suggested for the
catchment area treatment.
1. Engineering measures
- Nallah Bunding
- Contour Bunding
- Angle iron barbed wire fencing
2. Biological measures
- Development of nurseries
- Plantation/afforestation
- Pasture development
- Social forestry
The basis of site selection for different biological and engineering treatment measures
under CAT are given in Table-14.3.
Table-14.3: Basis for selection of catchment area treatment measures
Treatment measure Basis for selection
Social forestry, fuel wood and
fodder grass development
Near settlements to control tree felling
Contour Bunding Control of soil erosion from agricultural fields.
Pasture Development Open canopy, barren land, degraded surface
Afforestation Open canopy, degraded surface, high soil erosion, gentle
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 10
Treatment measure Basis for selection
to moderate slope
Barbed wire fencing In the vicinity of afforestation work to protect it from
grazing etc.
Nallah Bunding Nala bunding work consists of constructing bunds of
suitable dimensions across the nala or gullies to hold the
maximum runoff water to create flooding of the upstream
area temporarily for some days or weeks, with surplusing
arrangements at suitable intervals to drain the water.
Nursery Centrally located points for better supervision of proposed
afforestation, minimize cost of transportation of seedling
and ensure better survival.
14.5 CATCHMENT AREA TREATMENT MEASURES
The erosion category of sub-watersheds in the catchment area as per a SYI index is
given in Table-14.4. The details are shown in Figure-14.4. The area under different
erosion categories are given in Table-14.5. The Treatment measures under each sub-
watershed are given in Table-14.6
Table-14.4: Erosion intensity categorization as per SYI classification
Watershed number Area SYI values Category
W1 19287 1060 Low
W2 9630 1080 Low
W3 5196 1170 Medium
W4 25519 1160 Medium
W5 24917 1210 High
W6 34057 1080 Low
W7 20336 1130 Medium
W8 25208 1160 Medium
W9 34867 1170 Medium
W10 29996 1240 High
W11 39966 1255 High
W12 25000 1230 High
W13 13066 1150 Medium
W14 14281 1210 High
W15 7379 1120 Medium
W16 22902 1220 High
W17 33610 1224 High
W18 21053 1270 High
W19 24345 1140 Medium
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 11
Watershed number Area SYI values Category
W20 6268 1220 High
W21 12630 1210 High
W22 27399 1230 High
W23 23972 1180 Medium
W24 50093 1248 High
W25 33537 1240 High
W26 25291 1230 High
W27 29320 1120 Medium
W28 54642 1170 Medium
W29 33101 1250 High
W30 42179 1226 High
W31 27814 1240 High
W32 54549 1250 High
W33 51890 1260 High
W34 38658 1240 High
W35 57010 1170 Medium
W36 60936 1180 Medium
W37 33122 1070 Low
W38 55681 1080 Low
W39 38834 1120 Medium
W40 55909 1060 Low
W41 29466 1140 Medium
W42 21011 1130 Medium
W43 40777 1150 Medium
W44 38211 1160 Medium
W45 22081 1090 Low
W46 15268 1080 Low
W47 4435 1210 High
Total 1414700
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 12
Figure-14.4: Prioritisation of Sub Watersheds for Pancheswar Project
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 13
Table-14.5: Area under different erosion categories
Category Area (ha) Percentage
Low 245035 17.32
Medium 550097 38.88
High 619568 43.80
Total 1414700 100.00
Table14.6: Treatment measures recommended for sub-watersheds coming under high
erosion category
Sub-watershed Contour Bunding
(ha)
Gap Plantation
(ha)
Pasture Development
(ha)
W5 283 376 252
W10 474 340 265
W11 411 594 247
W12 196 423 163
W14 135 367 318
W15 40 426 257
W16 256 0
W17 295 951 301
W18 356 351 274
W20 146 138 167
W21 66 221 515
W22 559 595
W24 401 234 1032
W25 844 414
W26 460 458
W29 341 518 426
W30 945 386
W31 385 251
W32 281 885 432
W33 359 539 310
W34 422 609 391
W47 78 144
Total 4540 10309 7454
The objective of the SYI method is to prioritize sub-watershed in a catchment area for
treatment. The total area under high erosion category in various dams is to be treated
as a part of the project cost. The various measures suggested for catchment area
treatment are depicted in Figure-14.5.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 14
Figure-14.5: Catchment Area Treatment Measures for Pancheswar Project
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 15
14.5.1 Biological Treatment
An amount of Rs. 9864.22 lakh has been earmarked for various afforestation measures.
The details are given in Table-14.7.
Table-14.7: Cost estimate for Catchment Area Treatment of Pancheswar Project-
Biological Measures
S.
No.
Item Unit Rate
(Rs.)
Unit Target
Physical Financial
(Rs. lakh)
1. Gap Plantation 60,000/ha ha 10309 6185.4
2. Pasture development 33,000/ha ha 7454 2459.82
3. Nursery development 11,00,000/no. no. 15 165
4. Vegetative fencing 70,000/km km 150 105
5. Watch and ward for 7
years @ 50 persons
12,000/man-
month
Man-
months 4200 504
6. Rim Plantation Lumpsum 300.0
7. Social Forestry Lumpsum 145.0
Total 9864.22
14.5.2 Soil & Water Conservation Works
An amount of Rs. 4938.44 lakh has been earmarked for various Soil & Water
Conservation measures. The details are given in Table-14.8.
Table-14.8: Cost estimate for implementation of Soil & Water Conservation measures as
a part of CAT Plan
S.
No.
Item Unit Rate
(Rs.)
Unit Target
Physical Financial
(Rs. lakh)
1. Check Dams 3,50,000 Nos. 45 157.5
2. Contour Bunding 55,000 4540 2497
3. Landslide Control
Measures
1000.0
4. Drainage line treatment 400.0
5. Silt Observation Points
(Refer Table-14.8)
883.94
Total 4938.44
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 16
14.5.3 Silt Observation points
Four silt observation locations for regular monitoring of silt load coming in tributaries of
sub-watersheds falling under high and very high categories are proposed. This would
ensure monitoring efficacy of implementation of various treatment measures proposed
in CAT plan. Monitoring would be undertaken for a period of 10 years including 5 years
for CAT plan implementation period. An amount of Rs. 883.94 lakh has been earmarked
for this purpose. The details are given in Table-14.9
Table-14.9: Cost earmarked for establishing Silt Observation points
S. No. Parameter Cost (Rs. lakh)
1 Cost of ten laboratories – Rs 5,00,000/- for silt analysis per
laboratory
50.0
2 One observation hut at each site (@ Rs 5.0 lakh/site) 50.0
3 Cost for hiring services of 10 person (Average salary- Rs
10,000/- for 10 years) considering 10% escalation per year
191.2
4 Cost for hiring services of supervisor 10 persons (Average
salary Rs. 20,000/- for 10 years) considering 10%
escalation per year
444.74
5 Consumables for the measurement Rs. 8.0 lacs per year
for next 10 years, considering 10% escalation per year
148.0
Total 883.94
14.5.4 PES & Eco tourism
Under this an amount of Rs. 10000.0 lakh has been earmarked for conducting
catchment specific study to identify proposals and activities to be undertaken under
PES and its implementation then keep implemented. Eco-tourism activity shall feature
under this component and suitable eco-tourism promotion activities shall be identified
and promoted under this category. Local community involvement to promote nature
based local products are proposed to be encouraged
14.5.5 Research Training and Capacity Building
An amount of Rs. 15000 lakh has been earmarked for Training & Capacity building of
forest staff as well as local community through State Forest Training Institutes and
reputed non-governmental organizations.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 17
14.5.6 Infrastructure Development
The total budget kept for infrastructure development for Forest department during the
implementation of CAT Plan is Rs. 2550 lakh. The details are given in Table-14.10.
Table-14.10: Cost summary for the Operational Support to Forest
S. No. Component/Item No. Unit Rate (Rs. lakh) Total Cost (Rs. lakh)
1 Vehicle Including
operation and
maintenance
50 No. 10.0 500.0
2 Office Expenditure - Lumpsum 550.0
3 Office Equipment
Dual Core computer with
UPS & Laser Jet Printer,
50 No. 1.0 50.0
Photocopier machine 50 No. 3.0 150.0
Office Furniture - Lumpsum 50.0
4 GPS 50 No. 3.0 150.0
5. Maintenance of
Departmental buildings
500.0
6. Maintenance of Forest
roads/inspection paths
600.0
Total 2550
14.5.7 Forest Protection
An amount of Rs. 1200 lakh has been earmarked for implementation of various Forest
Protection measures. The details are given in Table-14.11.
Table-14.11: Cost summary for Forest Protection measures
S. No. Component/Item No. Unit Rate
(Rs. lakh)
Total Cost
(Rs. lakh)
1 Fire protection measures 550.0
2 Distribution of Non-conventional
Energy and Fuel Saving
Devices in catchment area
on a cost-sharing basis, such
as, LPG, Tandoors, Pressure
cookers and Solar devices
- Lumpsum 650.0
Total 1200
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 18
14.5.8 Wildlife Management
It is proposed to fund various components of wildlife management plan through CAT
Plans that have a direct bearing on the reduction of silt load. The activities proposed for
wildlife related interventions will be restricted to the project catchment area only. An
amount of Rs. 8000.0 lakh has been earmarked for implementation of various wildlife
management measures.
14.5.9 Monitoring and Evaluation
Monitoring and evaluation is very essential for the various types of activities in CAT plan
on daily, monthly and annual basis for proper execution of planned works. This will also
include the recording of silt data at 2 gauge and discharge stations proposed in
Catchment Area.
M & E studies including impact evaluation studies should be scheduled for the later
years of the CAT Plan implementation calendar. Indicators for Monitoring impact of CAT
Plan would include:
Change in silt load.
Survival of plantations
Changes in land-use [private holdings]
Changes in man-animal conflicts.
Trend of fire incidences in vulnerable areas.
A provision of 6% of the total CAT Plan cost has been earmarked for Monitoring and
Evaluation. Thus an amount of Rs. 4200.0 lakh has been earmarked for Monitoring and
Evaluation.
14.5.10 Site Specific Working Plan
Site specific micro-plans shall be prepared to address specific natural resource base
livelihood activities of the local communities. The emphasis will be laid on strengthening
the natural resource base of the area by promoting indigenous flora. Micro-level disaster
mitigating measures will be identified and promoted under this activity. A provision of
3% of the total CAT Plan cost amounting to Rs. 2100.0 lakh has been earmarked for
this activity.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 14: Catchment Area Treatment Plan Page 19
14.5.11 CONTINGENCIES
An amount of Rs. 1348 lakh has been earmarked for meeting any unforeseen
expenditure.
14.6 COST ESTIMATE
The cost required for implementation of various measures is Rs. 70000 lakh or 700.0
crore. The details are given in Table 14.12.
Table-14.12: Cost earmarked for implementation of CAT plan
S. No. Activity Amount
(Rs. lakh)
1 Afforestation 9864
2 Soil & Water Conservation Works 4938
3 PES And Eco-Tourism 10000
4 Research Training and Capacity Building 15000
5 Infrastructure Development 2550
6 Forest Protection 12000
7 Wildlife Management 8000
8 Monitoring and Evaluation 4200
9 Site Specific Working plan 2100
10 Contingencies 1348
Total 70000
CHAPTER-15
DISASTER MANAGEMENT PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 1
CHAPTER-15
DISASTER MANAGEMENT PLAN 15.1 INTRODUCTION
Any Dam project if not designed on the sound principles of design after detail
investigations in respect of hydrology, geology, seismicity etc., could spell a
large scale calamity. Thus these are inherent risk to the project like improper
investigation, planning, designing and construction which ultimately lead to
human catastrophy. Though through detailed field investigations it has been
ensured that the dam is founded on firm foundation, designed for suitable
seismic design parameters, yet in view of that uncertain element of “Force
Mejure” the eventuality of a disaster cannot be ignored but a rescue plan has to
be devised for confronting such an exigency without being caught in the vast
realm of unpreparedness.
A disaster is an unwarranted, untoward and emergent situation that culminates
into heavy toll of life and property and is a calamity sometimes caused by “force
mejure” and also by human error. The identification of all types of disaster in
any proposed project scenario involves the critical review of the project vis-à-vis
the study of historical past incidents/disasters in the similar situations. The
evolution of disaster management plan dwells on various aspects such as
provision of evacuation paths, setting up of alarms and warning systems,
establishing communicating system besides delineating an Emergency
Response Organization with an Effective Response System. Keeping in view
the grievous affects a disaster can cause on human or animal population, loss
of property and environment in and around the areas of impact. Therefore it is
essential to assess the possibility of such failures in context to the present
project and formulate a contingent plan.
The proposed Pancheshwar Dam Project comprises of constructing a 311 m
high dam near Pancheshwar Temple with FRL of EL 680.00 masl having
following main structures
Main Rockfill 311 m high dam across the Mahakali river, forming
an a submergence area of around 116 Km2 (at EL 680 m) with a
gross storage volume of about 11355 Mm3;
Spilway on the left bank, designed to safely discharge the
estimated Probable Maximum Flood (PMF= 23,500 cumec);
Two underground power houses, one on reach bank;
A re-regulating dam downstream to re-regulate the power
releases from Pancheshwar dam.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 2
15.2 DAM BREAK INUNDATION ANALYSIS
The outflow flood hydrograph from a dam failure is dependent upon many
factors such as physical characteristics of the dam, volume of reservoir and the
mode of failure. The parameters which control the magnitude of the peak
discharge and the shape of outflow hydrograph include: the breach dimensions,
the manner and length of time for the breach to develop, the depth and volume
of water stored in the reservoir, and the inflow to the reservoir at the time of
failure. The shape and size of the breach and the elapsed time of development
of the breach are in turn dependent upon the geometry of the dam, construction
materials and the causal agent for failure.
For reasons of simplicity, generally, wide applicability and the uncertainty in the
actual mechanism, the HEC-RAS model has been used. The model uses
failure time interval, terminal size and shape of the breach as the inputs. The
possible shapes of the breach that can be accomplished by the model are
rectangular, triangular and trapezoidal. The model is capable of adopting either
storage routing or dynamic routing methods for routing floods through
reservoirs depending on the nature of flood wave movement in reservoirs at the
time failure.
The dynamic routing method based on the complete equations of unsteady flow
is the appropriate technique to route the flood hydrograph through the
downstream valley. The method is derived from the original equations
developed by St. Venant. The model uses St. Venant’s equations for routing
dam break floods in channels.
15.3 METHODOLOGY
HEC-RAS 4.1 system contains two one dimensional hydraulic components for:
i) steady flow surface profile computations; ii) unsteady flow simulation. The
steady/unsteady flow computations are capable of modeling subcritical,
supercritical, and mixed flow regime water surface profiles. The basic
computational procedure is based on the solution of one dimensional energy
equation. Energy losses are evaluated by friction (manning’s equation) and
contraction/expansion (coefficient multiplied by the velocity head). The
momentum equation is utilized in situations where the water surface profile is
rapidly varied. The graphics include X-Y plots of the river system schematic,
cross-sections, profiles, rating curves, hydrographs and many other hydraulic
variables.
Model Stability during unsteady flow simulation
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 3
HEC-RAS model uses an implicit finite difference scheme. The common
problem of stability in the case of unsteady flow simulation can be overcome by
suitable selection of following;
Computational time step
Theta weighing factor for numerical solution
Cross section spacing along the river reach
Solution iterations
Solution tolerance
Weir and spillway factor for numerical solution
Computational time step Stability and accuracy can be achieved by selecting a computational time step
that satisfies the courant condition;
Cr = Vw (Δt/Δx)≤1.0
Therefore: Δt ≤ (Δx/ Vw)
Where:
Vw= Flood wave speed
V = Average velocity of flow
Δx = Distance between the cross sections
Δt = Computational time step
For most of the rivers the flood wave speed can be calculated as:
Vw = dQ /dA
Factors for various channel shapes are shown in the table below.
Channel shape Ratio (Vw/V)
Wide rectangular 1.67
Wide parabolic 1.44
Triangular 1.33
Natural channel 1.50
Theta weighing factor for numerical solution
Theta is a weighing factor applied to the finite difference approximations when
solving the unsteady flow equations. Theoretically theta can vary from 0.5 to
1.0. Theta of 1.0 provides the most stability, while theta of 0.6 provides the
most accuracy.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 4
15.3.1 Reservoir Routing
The storage routing is based on the law of conservation given as:
I –Q = dS/dt …………………….….. (1)
In which, I is reservoir inflow. Q is the total reservoir outflow which includes the
flow spillway, breach, overtopping flow and head independent discharge, and
rate of change of reservoir storage volume. Equation (1) can be expressed in
finite difference form as :
(1 + I’ ) 2 - (Q + Q’ )/2 = ∆ S/∆t -.-----(2)
In which the prime (‘ ) superscript denotes the values at the time t - ∆t and the
notation approximates the differential. The term ∆S may be expressed as:
∆S = (As +A’s) (h-h’)/2 ………………(3)
In which, As is the reservoir surface area coincidental with the elevation (h) and
is a function of h. The discharge Q which is to be evaluated from equation (2) is
a function of h and this known h is evaluated using Newton–Raphson iteration
technique and thus the estimation of discharge corresponding to h.
15.3.2 Dynamic Routing
The hydrologic storage routing technique, expressed by equation (2) implies
that the water surface elevation within the reservoir is horizontal. This
assumption is quite adequate for gradually occurring breaches with no
substantial reservoir inflow hydrographs. However, when the breach is
specified to form almost instantaneously so as to produce a negative wave
within the reservoir, and/or the reservoir inflow hydrograph is significant enough
to produce a positive wave progressing through the reservoir, a routing option
which simulates the negative and /or positive wave occurring within the
reservoir may be used in DAMBRK model. Such a technique is referred to as
dynamic routing. The routing principle is same as dynamic routing in river
reaches and it is performed using St. Venant’s equation. The movement of the
dam break flood wave through the downstream river channel is simulated using
the complete unsteady flow equations for one dimensional open channel flow,
alternatively known as St. Venant’s equations. These equations consist of the
continuity equation
∂Q ∂(A +A0)
___+ _______ = q …………………………………(4)
∂t ∂t
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 5
and the conservation of momentum equation :
∂Q ∂(A2/ +A) ∂h ___+ _______ + g A ( ---- + Sf +S e) + Lc = 0 ……(5) ∂t ∂t ∂t
where,
A = active cross – sectional flow area
A0 = inactive (off-channel storage) cross – sectional area
X = distance the channel
q = lateral inflow or outflow per unit distance along the channel
g = acceleration due to gravity
Q = discharge
H = water surface elevation
Ss = friction slope
Se = expansion – contraction loss slope
Lc = lateral inflow/outflow momentum effect due to assumed flow path of inflow
being perpendicular to the main flow.
The friction slope and expansion – contraction loss slope are evaluated by the
following equation
n3 Q2
Sf = --------------- ……………………….…….(6)
2.21 A2 R¾
and,
K∆(Q/A)2
Se = -------------------- ……………………………….…….(7)
2g ∆ X
where,
n = Manning’s roughness coefficient
R = A/B where B is the top width of the active portion of the channel
K = Expansion – contraction coefficient varying from 0.1 to 0.3 for
contraction and 0.5 to – 1.0 expansion
∆(Q/A)2 = Difference in (Q/A)2 for cross sections at their end of a reach
The non-linear partial differential equations (4) and (5) are represented by a
corresponding set of non-linear finite difference algebraic equations and they
are solved by the Newton-Raphson method using weighted four point implicit
scheme to evaluate Q and h. The initial conditions are given by known steady
discharge at the dam, for which steady state non-uniform boundary flow
equation are used. The outflow hydrograph from the reservoir is the upstream
boundary condition for the channel routing and the model is capable of dealing
with fully supercritical flow or fully supercritical flow in the reach or the upstream
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 6
reach having supercritical flow and downstream reach having subs critical flow.
There is a choice of downstream boundary conditions such as internally
calculated loop rating curve, user provided single valued rating curve, user
provided time dependent water surface elevation, critical depth and dam which
may pass flow via spillways, overtopping and/or breaching.
15.3.3 Statement of the problem
The computation of flood wave resulting from a dam breach basically involves
two scenarios which can be considered jointly or separately: (1) the outflow
hydrograph from the pond (2) the routing of the flood wave downstream from
the breached dam along the river valley and the flood plain. If breach outflow is
independent of downstream conditions, or if their effect can be neglected, the
reservoir outflow hydrograph is referred to as the free outflow hydrograph. In
this case, the computation of the flood characteristics is divided into two distinct
phases: (a) the determination of outflow hydrograph with or without the routing
of the negative wave the reservoir, and (b) the routing of flood wave
downstream from the breached dam. In this study the problem of simulating the
failure of “Dam” and computing the free outflow hydrograph from the breached
section using storage routing technique’ with the aim of reproducing the
maximum water level marks reached during the passage of flood wave is
considered. The information regarding inflow hydrograph into the pond due to
the storm at the time of failure, the structural and the hydraulic characteristics
details of the dam, the time of failure, the channel cross sections details, the
maximum water level marks reached in the reservoir at the time of failure and
those observed in the downstream reach of the dam to the passage of flood
wave etc. are available for the study.
15.3.4 Availability of Data
The input data required can be categorized into two groups. The first data
group pertains to the dam and inflow hydrograph into the reservoir and the
second group pertains to the routing of the outflow hydrograph through the
downstream valley. These are described in the following paragraphs.
First Data Group
With reference to the data group pertaining to the dam, the information on
reservoir elevation-volume relationship, spillway details, elevation of bottom and
top of dam, elevation of water surface in the pond at the beginning of analysis and
at the time of failure, breach description data are required.
Second Data Group
The second group of data pertaining to the routing of the outflow hydrograph
through the downstream valley consists of a description of cross-sections,
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 7
hydraulic resistance coefficients of the reach, steady state flow in the river at the
beginning of the simulation and downstream boundary condition. The cross
section is specified by location mileage, and tables of top width and
corresponding elevation.
15.3.5 Results
A rectangular breach at an El 691 masl with side slope 1:0 and breach formation
time as 1 hr. have been considered in the study for dam break analysis of
Pancheshwar Dam Project. After the breach, immediately below the dam, the
maximum flow will occur immediately after the start of breach. The magnitude of
the simulated outflow hydrograph will be 27,660 cumec corresponding to
maximum stage elevation 666 masl at Km. 2.50 is attenuated to 26,400 cumecs
corresponding to maximum stage elevation of 456 masl at km. 24.00. and further
increase at km. 25 to 27650 cumecs and further reduced to 26178 at km. 38. The
maximum flow and flood wave arrival time at various distances d/s of the dam is
given in Table-15.1.
Table-15.1: Summary of wave profile in the event of Dam Break
Distance from Dam (km)
Max Elevation, (masl)
Maximum Flow (cumec)
Time to Maximum Stage, (Minutes)
Maximum velocity m/s
2.50 666.24 27660 4.41 12.54
4.50 646.11 27675 6.57 10.39
7.61 624.23 27444 14.36 7.81
12.80 588.61 27711 24.51 10.30
16.00 582.24 27540 31.22 8.11
18.59 578.12 27112 35.66 8.25
24.00 559.24 26400 40.11 9.68
25.40 558.31 27650 48.22 8.22
28.34 527.24 27411 56.62 8.04
35.05 371.72 26432 68.11 8.62
38.24 364.41 26178 70.22 9.37
15.4 DISASTER MANAGEMENT PLAN
The emergency planning for dam break scenario is devised on the basis of
results of dam break analysis mainly the travel time of flood wave to various
locations in the downstream stretch of the river. It is inferred from the analysis
that in case of main dam failure the flood peak discharge as it prorogates
through valley shall inundate downstream stretch of 2.50 km within 4.41 minute
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 8
and the flood wave peak will reach at 38.24 km d/s in 70.22 minutes, implying
that a little reaction time for executing any rescue plan. The plan is, therefore,
based on such measures, which are purely preventive in nature.
The degree of alertness has to enhance during high stage of river manifested
with sharp increase in discharge. Though there cannot be very sharp edge
demarcation between different levels of emergency yet the following flood
conditions have been contemplated and the preventive measures suggested
against each as given in Table-15.2.
Table-15.2: Status of Emergency
S. No.
Status of emergency
Water Level Preventive measures
1. Normal Flood
Below FRL i.e. EL 680 masl and flood discharge below 27666 cumecs
Utmost vigil observed in regulation of spillway gates
2. Level –1 Emergency
Rises above EL 680 masl but flood discharge below 27666cumecs
(1) All gates fully operational (2) All the official should attend dam site. Local officials informed and warning system be kept on alert.
3. Level –2 Emergency
Above FRL i.e. EL 680 masl but below top of dam and the discharge continues rising above 27666 cumecs
Communication & public announcement system should be put into operation and flood warning issued to people.
4. Level –3 Emergency
Top of dam (1) All staff from dam site, power house & TRC outlets alerted to move to safer places (2) Possibility of dam failure should be flashed to District Administration.
5. Disaster Rising above top of dam and the breach appears in any form
District Administration and Project authorities be intimated and only life saving measures should be resorted too
15.4.1 Dam Safety and Maintenance Manual
Based on standard recommended guidelines for the safety inspection of dams
a manual should be prepared by the project proponents in respect of dam
safety surveillance and monitoring aspects. This should be updated with the
availability of instrumentation data and observation data with periodical review.
The need for greater vigil has to be emphasized during first reservoir
impoundment and first few years of operation. The manual should also delve on
the routine maintenance schedule of all hydro-mechanical and electrical
instruments. It should be eloquent in respect of quantum of specific
construction material needed for emergency repair along with delineation of the
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 9
suitable locations for its stocking and also identify the much needed machinery
and equipment for executing emergency repair work and for accomplishing the
evacuation plan.
15.4.2 Emergency Action Plan (EAP)
Dam safety programme as indicated above includes the formation of an
Emergency Action Plan for the dam. An emergency is defined as a condition of
serious nature which develops unexpectedly and endangers downstream
property and human life and required immediate attention. Emergency Action
Plan should include all potential indicators of likely failure of the dam, since the
primary concern is for timely and reliable identification and evaluation of
existing of potential emergency.
This EAP presents warning and notification procedures to follow during the
monsoon season in case of failure or potential failure of the dam. The objective
is to provide timely warning to nearby residents and alert key personnel
responsible for taking action in case of emergency.
15.4.3 Administration and Procedural Aspects
The administrative and procedural aspects of the Emergency Action Plan
consist of flow chart depicting the names and addresses of the responsible
personnel of project proponent and the Dist. Administration. In order of
hierarchy, the following system will usually be appropriate. In the event that the
failure is imminent or the failure has occurred or a potential emergency
conditions is developing, the observer at the site is required to report it to the
Junior Engineer who will report to the Executive Engineer / Superintending
Engineer for their reporting to the Chief Engineer through a wireless system or
by any available fastest communication system. The Engineer-in-Charge is
usually responsible for making cognizant with the developing situation to the
Civil Administration. Each personnel are to acknowledge his/her responsibilities
under the EAP in an appropriate format at a priority.
The technical aspects of the EAP consist of preventive action to be taken with
regards to the structural safety of the dam. The EAP is drawn at a priority for
the regular inspection of the dam. For this purpose, providing an adequate and
easy access to the dam site is a necessity. The dam, its sluices, overflows and
non-overflow sections should be properly illuminated for effective operations
during night time. Whenever sinkholes, boils, increased leakages, movement of
masonry rock, gate failure, rapid rise or fall of the level in the reservoir, rise in
the level of reservoir beyond the maximum working level, or wave overrun of
the dam crest are observed, the personnel on patrol is required to inform
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 10
immediately to the Junior Engineer (JE) / Assistant Engineer (AE) for initiation
of the execution of EAP. They are required to inform the Engineer-in-Charge
and the local administrative authorities. It is desirable if the downstream
inhabitants are warned using siren, if available, so as to make them aware the
likely imminent danger.
The other preventive measures may include availability of sufficient number of
sandbags at several selected downstream locations and logs (for holding
sandbags) and at the dam site, one tractor, two motor boats, gas lanterns,
Manila ropes and life jackets. Areas from where the labour can be mobilized
should be chalked out at a priority. In addition to these, public participation in
the process of execution of the EAP may further help in amelioration of the
adverse impacts of the likely disaster. For this, it is necessary that the public
should be made aware of its responsibilities.
15.4.4 Preventive Action
Once the likelihood of an emergency situation is suspected, action has to be
initiated to prevent a failure. The point at which each situation reaches an
emergency status shall be specified and at that stage the vigilance and
surveillance shall be upgraded both in respect of time and level. At this stage a
thorough inspection of the dam should be carried out to locate any visible
sign(s) of distress.
Engineers responsible for preventive action should identify sources of
equipment needed for repair, materials, labour and expertise for use during an
emergency. The amount and type of material required for emergency repairs
should be determined for dam, depending upon its characteristics, design,
construction history and past behavior. It is desirable to stockpile suitable
construction materials at appropriate sites. The anticipated need of equipment
should be evaluated and if these are not available at the dam site, the exact
location and availability of these equipments should be determined and
specified. The sources/agencies must have necessary instructions for
assistance during emergency. Due to the inherent uncertainties about their
effectiveness, preventive actions should usually be carried out simultaneously
with the appropriate notification on alert situation or a warning situation.
15.4.5 Communication System
An effective communication system and a downstream warning system are
absolutely essential for the success of an emergency preparedness plan. The
difference between a high flood and dam-break situation must be made clear to
the downstream population.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 11
15.4.6 Evacuations Plans
Emergency Action Plan includes evacuation plans and procedures for
implementation based on local needs. These could be:
- Demarcation / prioritization of areas to be evacuated.
- Notification procedures and evacuation instructions.
- Safe routes, transport and traffic control.
- Safe areas/shelters.
- Functions and responsibilities of members of evacuation team.
Any precarious situation during floods will be communicated either by an alert
situation or by an alert situation followed by a warning situation. An alert
situation would indicate that although failure of flooding is not imminent, a more
serious situation could occur unless conditions improve. A warning situation
would indicate that flooding is imminent as a result of an impending failure of
the dam. It would normally include an order for evacuation of delineated
inundation areas.
15.4.7 Evacuation Team
It will comprise of following official / Representative:
District Magistrate (D. M.)/ His Nominated officer (To peacefully
relocate the people to places at higher elevation with state
administration).
Engineer in charge of the project (Team Leader)
Superintendent of Police (S. P.) / Nominated Police Officer (To
maintain law and order)
Chief Medical Officer (C. M. O.), (To tackle morbidity of affected
people)
Head of affected village to execute the resettlement operation with
the aid of state machinery and project proponents.
Sub committees at village level
The Engineer-in-Charge will be responsible for the entire operation including
prompt determination of the flood situation time to time. Once the red alert is
declared the whole state machinery will come into swing and will start
evacuating people in the inundation areas delineated in the inundation maps.
For successful execution, annually demo exercise will be done. The D.M. is to
monitor the entire operation.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 12
15.4.8 Public Awareness for Disaster Mitigation
In addition, guidelines that have to be followed by the inhabitants of flood prone
areas, in the event of flood resulting from dam failure, which form part of public
awareness for disaster mitigation may also include following:
Listen to the radio for advance information and advice.
Disconnect all electrical appliances and move all valuable personal
and household goods beyond the reach of floodwater, if one is
warned or if one suspects that flood waters may enter the house.
Move vehicles, farm animals and movables goods to the higher
place nearby.
Keep sources of water pollution i.e. insecticides out of the reach of
water.
Turn off electricity and LPG gas before one has to leave the house.
Lock all outside doors and windows if one has to leave the house.
Do not enter floodwaters.
Never wander around a flood area.
15.4.9 Notifications
Notification procedures are an integral part of any emergency action plan.
Separate procedures should be established for slowly and rapidly developing
situations and failure. Notifications would include communication of either an
alert situation or an alert situation followed by a warning situation. An alert
situation would indicate that although failure or flooding is not imminent, a more
serious situation could occur unless conditions improve. A warning situation
would indicate that flooding is imminent as a result of an impending failure of
the dam. It would normally include an order for evacuation of delineated
inundation areas.
15.4.10 Notification Procedures
Copies of the EAP that also include the above described inundation map are
displayed at prominent locations, in the rooms and locations of the personnel
named in the notification chart. For a regular watch on the flood level situation,
it is necessary that the flood cells be manned by two or more people so that an
alternative person is always available for notification round the clock. For
speedy and unhindered communication, a wireless system is a preferable
mode of communication. Telephones may be kept for back up, wherever
available. It is also preferred that the entire flood cells, if more that one, are
tuned in the same wireless channel. It will ensure communication from the dam
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 15: Disaster Management Plan Page 13
site to the control rooms. The communication can be established by messenger
service in the absence of such modes of communication.
15.4.11 Management after receding of Flood Water
It is to be accepted that in the even of dam break, even with maximum efforts,
the loss of human lives, livestock and property would be inevitable. Under such
a scenario, a massive effort would be used by various government agencies to
provide various relief measures to the evacuees. Formulation of a plan
delineating such measures is beyond the scope of work of this document.
However, some of the measures which need to be implemented are listed as
below:
Provision of various food items and shelter to the evacuees.
Provision of fuel for various evacuees.
Provision of adequate fodder supply.
Arrangements for potable water supply.
Commissioning of low cost sewage treatment and sanitation
facilities, and disposal of treatment sewage.
Expeditious disposal of dead bodies human and livestock.
Immunization programmes for prevention of outbreak of epidemics
of various water related diseases.
Adequate stocks of medicines of various diseases, especially
water-related diseases.
15.5 COST ESTIMATES
The budget for different activities required to be carried out for mitigation and
prevention of dam break hazard exclusively from the dam is Rs 1230.00 lakh as
per details given in Table-15.3.
Table-15.3: Budget earmarked for implementation of Disaster Management Plan
S. No. Particular Cost (Rs. lakh)
1. Installation of alert system in control room 100.0
2 Setting up of communication between various projects on river Mahakali/Sharda
200.0
3 Setting up of communication system between dam and d/s settlements
300.0
4 Public information system 200.0
5 Setting up of a seismic observatory at dam site
400.0
6 Training and miscellaneous expenses 30.0
Total 1230.0
CHAPTER-16
AGRICULTURE IMPROVEMENT PLAN
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 1
CHAPTER-16
AGRICULTURE IMPROVEMENT PLAN
16.1 INTRODUCTION
As a part of the EMP, various measures have been suggested to improve
agricultural practices in the area. These include:
Improved agricultural practices
Integrated plant and nutrient management
Biological control of pests and diseases
Use of agro-chemicals
Control of weeds on agricultural lands
Training & Extension courses for farmers
16.2 IMPROVED AGRICULTURAL PRACTICES
Normally introduction of irrigation, in command area of any irrigation project
leads to a genetic erosion and a large number of traditional strains of crops give
way to identical high yielding varieties. Such phenomenon makes the crops
prone to attack by fewer strains of virus, fungus etc. and provides little chance
to develop newer varieties of crop to fight future adverse environmental
conditions.
To develop a suitable EMP, to negate the above adverse impact may not be an
easy task, as the concept is yet to take roof in India. Quite a few institutions in
the country are doing significant research in the area, and their help can be
taken i.e. Indian Agricultural Research Institute (IARI). Likewise, the services of
Consultative Group on International Agricultural Research (CGIAR) which has a
Centre at Hyderabad can also be used.
16.3 INTEGRATED PLANT AND NUTRIENT MANAGEMENT
Under the best farming practices, only 40-50% of the applied fertilizers are
used by the crop and the balance find their way into the aquatic environment
through drainage runoff. Besides eutrophication of neighboring water bodies
through washing down of fertilizers and organic matter rich in nutrients from the
surrounding agricultural fields, the soil productivity is also threatened due to
continuous overdosing of fertilizers. IPNM approach would be useful for
building soil productivity and improving crop yields. IPNM is an approach for
maintenance or adjustment of soil fertility in relation to plant nutrient supply at
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 2
an optimum level for sustaining desired crop productivity. This is done through
optimization of the benefits from all possible sources of plant nutrients in an
integrated manner. Some benefits of the IPNM are listed as below:
Helps achieve highest production per unit of investment by way of reducing
unavoidable losses due to leaching and volatilization.
Helps reduce toxicity, which happens due to excessive use of single
nutrients.
Helps in quality production besides enhancement of Benefit Cost (B/C) ratio.
Provides natural safeguard against biotic and abiotic stresses.
Soils using only chemical fertilizer exhibit declining productivity per unit of
plant nutrient used.
Using only major nutrients (NPK) results in deficiencies of micro and
secondary nutrients.
Helps maintain soil health through organic matter and results in better
fertilizer use efficiency.
Organic manures and plant residues are available locally and thus if
managed properly are cost effective.
Maintenance of soil health with maximum use of organic manure and recycling
of organic waste along with chemical fertilizers and bio-fertilizers in an
integrated manner is environmentally sound and cost effective alternative.
16.4 BIOLOGICAL CONTROL OF PESTS AND DISEASES
16.4.1 Components of IPM
The major components of IPM in increasing order of complexity are given in
Table-16.1.
Table-16.1: Major Components of IPM
IPM Component Notified Component Practices
Cultural practices Preparation of nurseries or main fields free from pest
infestation by removing plant debris, trimming of bunds,
treating of soil and deep summer ploughing which kills
various stages of pests. Proper drainage system in field
be adopted.
Testing of soil for nutrients deficiencies on the basis of
which fertilizers should be applied.
Selection of certified seeds and treating seeds with
fungicide or bio-pesticides before sowing for seed borne
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 3
IPM Component Notified Component Practices
disease control.
Selection of seeds of relatively pest resistant/tolerant
varieties which play a significant role in pest suppression.
Adjustment of time of sowing and harvesting to escape
peak season of pest attack.
Rotation of crops with non-host crops. It helps in
reduction of incidence of soil borne diseases.
Proper plant spacing which makes plants more healthy
and less susceptible to pests.
Optimum use of fertilizer. Use of FYM and bio-fertilizers
should be encouraged.
Proper water management (alternate wetting and drying
to avoid water stagnation) as the high moisture in soil for
prolonged period is conducive for development of pests
especially soil borne diseases.
Proper weed management. It is well known fact that most
of weeds besides competing with crop for micronutrients
also harbour many pests.
Root dip or seedling treatment in pest infested area.
Inter-cropping or multiple cropping wherever possible. All
the crops are not preferred by each pest species and
certain crops act as repellents, thus keeping the pest
species away from preferred crops resulting in reduction
of pest incidence.
Harvesting as close as to ground level. This is because
certain developmental stages of insect pests/diseases
remain on the plant parts which act as primary inoculum
for the next crop season. Hence, harvesting crops at
ground level will lessen the incidence of pests in next
season.
Before planting, nursery plants be sprayed/dipped in
copper fungicide/bio-pesticide solutions to protect the
plants from soil borne diseases.
Keeping bee hives or placing flower bouquets of pollinizer
cultivars facilitate better pollination and subsequent fruit
set.
Mechanical
practices
Removal and destruction of egg masses, larvae, pupae
and adults of insect pests and diseased parts of plants
wherever possible.
Installation of bamboo cage cum bird perchers in the field
and placing parasitized egg masses inside them for
conservation of natural enemies and withholding of pest
species wherever possible.
Use of light traps and destruction of trapped insects.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 4
IPM Component Notified Component Practices
Installation of bird scarer in the field where required.
Installation of bird perchers in the field for allowing birds
to sit and feed on insects and their immature stages viz.,
eggs, larvae and pupae.
Use of pheromone traps for monitoring and suppression
of pest population.
Genetical practices Selection of high yielding varieties for different crops
Selection of comparatively pest resistant/tolerant varieties
Biological practices Bio-control is use of living organisms to control unwanted
living organisms (pests). It involves deliberate use of
parasitoids, predators and pathogens to maintain pest
population at level blow those causing economic loss
either by introducing a new bio-agent into the
environment of pest or by increasing effectiveness of
those already preset in the field.
Parasitoids: These are the organisms which lay eggs in
or on the bodies of their hosts and complete their life
cycles on host bodies as a result of which hosts die. A
parasitoid may be of different type depending on the host
developmental stage in or on which it completes its life
cycle. These include different species of Trichogramma,
Apanteles, Bracon, Chelonus, Brachemeria,
Pseudogonotopus etc.
Predators: These are free living organisms which prey
upon other organisms for their food. These include
species of spiders, dragon flies, damsel flies, lady bird
beetles, Chrysopa species, birds etc.
Pathogens: These are micro-organisims which infest and
cause diseases in their hosts as a result of which hosts
are killed. Major groups of pathogens are fungi, viruses
and bacteria. Some nematodes also cause diseases in
some insect pests. Important examples of fungi are
different species of Hirsutella, Beauveria, Nomurae and
Metarhizium which have been reported to infest and kill
large number of insects (upto 90%) in the fields. Among
viruses, most important examples are of nuclear
polyhedrosis virus (NPV) and granulosis viruses.
Outbreak of viruses in armyworms, cut worms, leaf
folders, hairy caterpillars and plant hoppers have been
reported many times. Among bacteria, Bacillus
thuringiensis (B.t.) and B. popillae are very common
examples.
Chemical practices Use of chemical pesticides is the last resort when all other
methods fail to keep the pest population below economic
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 5
IPM Component Notified Component Practices
loss. Although there is a great advancement in pest
management research, yet pesticides would continue to
play an important role in crop protection in view of
complexity of pest problems. Therefore, use of pesticides
should be need based, judicious, based on pest
surveillance and economic threshold level (ETL) to
minimise not only the cost involved, but also to reduce
associated problems, following aspects need to be
considered:
ETL and pest defender ratio must be observed
Relatively safer pesticides should be selected e.g. neem
based and biopesticides.
If pest is present in strips or isolated patches, whole field
should net be sprayed.
16.5 USE OF AGRO-CHEMICALS
A great deal of attention has been focused on agro-chemicals especially on
pesticides as these are supposed to be carcinogenic, mutagenic, teratogenic
and allergenic. The following measures are recommended to prevent pollution
and associated adverse impacts due to over-use of agro-chemicals:
Soil should be tested to analyse the nutrients before each cropping
season and the fertilizer dose shall be fixed considering the
concentration of soil nutrients and the type of crops to be grown.
Organic manures should be used in place of chemicals fertilizers,
Agronomic practices such as crop rotation and green cover mulching
which reduce the dependence on chemical fertilizers should be
incorporated in the cropping pattern itself.
Land conservation measures suggested as a part of watershed
management are effective in controlling erosion by surface runoff. The
agro-chemicals clinging to the eroded soil material is prevented from
reaching the surface waters.
16.6 CONTROL OF WEEDS ON AGRICULTURE LANDS
Measures against weeds comprise mechanical (cultivation and mowing),
cultural or cropping, biological and chemical means.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 6
Mechanical Methods
Hand weeding is the most efficient method, but it is back-breaking, time-
consuming and costly. Further, high wages paid to the hired labour narrow
down the profits of the cultivator.
Cultural or cropping methods
The farming practices are capable of changing the condition in such a way as
to enable the crop plants to compete with weeds successfully or to reduce their
interference to the minimum and thus preventing them from acting as
impediments to increased crop production. Seeds with good germination will
give the crop a vigorous and close stand and thus enable it to steal a march on
the weeds.
Chemical methods
The controlling of weeds in the growing crops with weedicides increases their
yields and ensures the efficient use of irrigation, fertilizers and plant protection
measures.
16.7 TRAINING AND EXTENSION COURSES FOR FARMERS
The change from rainfed to irrigated cropping requires extension, training and
demonstration programmes for farmers. Considering these aspects it is proposed
that the project authorities need to provide adequate training to farmers.
The training must include the following aspects of environmental protection:
Prevention of spread of water related diseases;
Safe use of agro-chemicals, and
Environmental conservation programmes.
Measures under prevention of spread of water related diseases must deal with:
Hygeine and personal health care;
Control of water spills, pudding etc.;
Prevention and prophylactic measures for control of vectors;
Disposal of human waste, and
Disposal of drainage water.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 16: Agriculture Improvement Plan Page 7
The aspects due to be covered under safe use of agro-chemicals are:
Control of weeds in channels
Methods of cleaning and disposal of weeds;
Detrimental environmental effects of agro-chemicals; and
Information on biological weed control.
Pest control
Specific uses of pesticides and its optimization;
Residual degradability;
Effect on untargeted species;
Safety procedures during application;
Rate and frequency of application;
Disposal of packing material and surpluses;
Storage of chemicals;
Information on cropping measures such as weeding, rotational
cropping, cleaning of bunds, etc.
Fertilizer use
Type, dosage, application techniques, timing and frequency of
application and its relationship with type of soils;
Disposal or storage of packing materials and surpluses.
Topics to be covered under Environmental conservation programmes are:
Protection of forest or trees;
Control of tree felling of fuel wood and timber;
Advice on establishment of village woodlot; and
Soil conservation measures.
Such training courses can be organized by Agriculture Department, state
government of Uttar Pradesh.
CHAPTER-17
SAFETY PRACTICES DURING CONSTRUCTION PHASE
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 1
CHAPTER-17
SAFETY PRACTICES DURING CONSTRUCTION PHASE
17.1 INTRODUCTION
The information on following aspects pertaining to safety have been presented in
this chapter:
Personal Safety Equipment
Rescue Team
Illumination and Earthing
Maintenance of Traffic and Safety on Public Roads
Blasting
Ventilation of Underground Works
Control of Dust, Silica and Noxious Gases in Underground Works
Management of Explosives
Traffic management during construction phase
Measures to be taken during excavation of earth
Safety practices during construction phase
Fire protection in labour camp and staff colonies
17.2 PERSONAL SAFETY EQUIPMENT
All the personnel as well as the site representatives and visitors shall be
equipped with appropriate personal safety equipment. 'I he use of such
equipment shall be compulsory.
Every person entering the working area in open air or in underground shall
wear a protective helmet. Every person entering into underground works
shall have an battery operated electric lamp.
The safety-loc footwear with steel caps shall be worn by all employees
engaged in work having an inherent danger to the feel. Light footwear such
as sandals, canvas or tennis shoes shall not be permitted for construction
work.
During the drilling works and in the areas where the employees are exposed
to harmful noise levels, car protectors shall be made available and required
to wear.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 2
Employees engaged in work having an inherent danger of eye or face injury1
shall be furnished and required to wear protection glasses, goggles or masks
Where irritant or toxic substances may come in contact with the skin or
clothing, employees shall be wearing the protective clothing or shall be
required to apply a protective ointment by a competent physician.
Employees working on sleep slopes or otherwise subject to possible falls
from levels not protected by fixed guardrails or safety nets, shall be secured
by safety bells and lifelines.
Requirements for Underground Works
Emergency material shall be provided at each underground excavation heading.
This equipment shall consist of the following, as a minimum:
a) 3 stretchers
b) 3 woollen blankets
c) 2 appliances for artificial breathing
d) I oxygen flask
e) 3 explosion-pcooflamps
f) wound dressing and disinfecting material
g) pain-killing injections
h) gas masks
At least two members of the Rescue Team as described hereinafter, properly
instructed and trained in the rescue procedures, shall be in each crew
working
underground
17.3 RESCUE TEAM
Prior to the commencement of construction, a Rescue Team shall be formed.
This Rescue Team shall be capable to render help after accidents caused by
fire, gas explosion, avalanche, etc.
The Rescue Team shall be organized in such a way that sufficient number of
members will be ready for action at any time until the Completion of Works.
The Rescue Team members shall be instructed and trained for their task by a
qualified and experienced person. If required, an outside specialist shall be
hired to perform such training. A refresher training for all members of the
Rescue Team shall be conducted at least every six months.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 3
Each Rescue Team member shall be skilled in giving the first aid, dealing
with the appliances for artificial respiration, and lire fighting equipment and
shall possess a good local knowledge. Adequate equipment for reaching
even the remotest working area shall be at their disposal.
17.4 ILLUMINATION AND EARTHING
17.4.1 General
All working sites in the open, transit areas, excavation sites, access to
tunnels, etc., shall be adequately illuminated during night work by electrical
lights as specified in the Section "Site Installations and Services".
Illumination of Underground Works
Each working face shall be brightly illuminated.
The vaults along the entire length of the tunnel adits and shaft shall be
illuminated with electrical light throughout the duration of construction works.
The lamps shall be located as follows;
a) Every 25 m in unlined stretches,
b) Every 50 m in lined stretches.
The lamps shall be installed in a particular area immediately after the rock
supporting measures have been completed.
Electrical cables shall be well insulated, protected and firmly fixed to tunnel
walls by means of adequate insulators, Lamps shall be well protected against
damage.
Lighting by flame is expressly forbidden in the underground.
17.4.2 Earthling, Wet Work Areas, Control of Electric Discharges
All equipment and appliances, which are exposed to lightning, shall be
earthed electrically, and the effectiveness of such earthling shall be
periodically checked by the specialized personnel.
No equipment electrically powered by more than 24 Volts shall be operated
by personnel standing in water.
Only air, battery-powered or hydraulic tools shall be permitted in the wet
areas.
Where electrical blasting will be used, equipment shall be installed to control
possible electric discharges in the ground due to storms, electrical motors,
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 4
etc. As soon as such discharges arc noted, electrical blasting operations
shall be suspended, or the detonator type changed.
17.5 MAINTENANCE OF TRAFFIC AND SAFETY ON PUBLIC ROADS
All necessary precautions for the protection of the work and the safety of the
public on the roads affected by his activities shall be taken. Where the work
will be carried out at the site of, or close to an existing road, the vehicular and
pedestrian traffic shall be maintained safe at all times. If any operations can
cause traffic hazards, the repair or fence or any such other measures shall
be taken for ensuring safety.
Roads subject to interference by the work shall be kept open or suitable
detours shall be provided and maintained, and all necessary barricades,
suitable and sufficient flashlights, flagmen, danger signals, and signs be
provided.
Roads, which will be closed to traffic, shall be protected by effective
barricades on which acceptable warning and detour signs shall be placed. All
barricades shall be kept illuminated and all lights shall be kept on from sunset
to sunrise.
The temporary passes and bridges shall be provided lo give an access to the
existing villages, houses, etc., to the satisfaction of the authorities concerned
whenever he disturbs such existing way during the execution of the Works.
17.6 BLASTING
17.6.1 General
All blasting shall be carried out in a workmanlike and safe manner by a
competent, licensed and experienced blasting engineer or foreman. No
blasting shall be done without his approval.
Blasting will be permitted only after adequate provisions have been made for
the protection of persons, the Works, and public or private property.
Responsibility for the safety of persons and property shall be ensured. All
claims resulting from personal injury and damage to property and equipment
that may resulting from its blasting operations shall be taken care of. Any
damage done to the Works or property by blasting shall be repaired.
Blasting in the open air shall be carried out only at certain hours of (he day in
accordance with a schedule. Barriers shall be erected and warning shall be
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 5
given to the workers at the Site and to the public immediately before blasting,
so that no person will enter the danger zone until blasting is finished.
Upon completion of blasting, an "all clear" signal shall be given by the
responsible blasting engineer after he has satisfied himself that all charges
loaded have detonated and that no delay-explosions or misfiring arc to be
expected.
Such methods of blasting shall be employed that shock and vibration are
minimized.
No blasts involving charges larger than 200 kg shall be carried without at
least one hour prior to the blast.
No blasting shall be permitted within 25 m of any concrete placed within the
previous 7 days, except backfill concrete behind steel ribs. After 7 days.
Blasting will not be permitted within 10 m of structures or installations
vulnerable to damage by blasting.
No charging and firing will be permitted during thunderstorms and other
electrical disturbances.
Mats or rubber tires tied together with rope shall be used as protection from
flying debris to cover the charges where blasting may expose persons or
properly to injury or damage.
17.6.2 Underwater Blasting
Only water resistant blasting caps and detonating cord shall be used in
underwater blasting operations.
Loading tubes and casings of dissimilar metals shall not be permitted
because of possible electrical transient current from galvanic action.
When more than one charge is placed underwater, a float device shall be
attached to an element of each charge in such manner that it will be released
by the firing.
No drilling, digging or excavating shall be permitted until all misfires have
detonated or the explosives are removed from the missed holes.
17.7 VENTILATION OF UNDERGROUND WORKS
17.7.1 General
Installation and operation of ventilating systems for underground construction
sites, shall be done. Calculations of fresh air supply volume, type of
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 6
ventilation scheme, duct diameters, materials and equipment and position of
ventilators and dust arrestors shall be performed. Description of the working
cycle including number of persons employed, number and capacity of diesel-
powered equipment working at one time at each tunnelling face shall also be
included.
All parts of the Works shall be maintained in a slate which will not be injurious
to the health of the personnel. The air in underground shall contain no less
than 20% oxygen and shall not contain a concentration of gases, vapours or
dust greater than is safe for the health of workmen.
If requited, the ventilating system shall be kept in operation also after break-
through in tunnels, galleries and shafts in order to maintain the fresh air
volume requirements staled hereafter
Intermediate fans attached to the main duct line shall be provided as required
to ensure satisfactory removal of contaminated air. All ventilation ducts shall
be maintained in an airtight condition.
Ventilation ducts shall be firmly fixed to the vault in such position that a
minimum clearance of 200 mm remains between the duct and the extremities
of train or vehicular traffic employed in the underground.
Should the volume of fresh air at the heading face not reach the required
amount and quality, the whole duct system shall be pressure-and-volume
tested in portions not exceeding a few hundred meters. Measuring stations
shall be located not closer than 10 times the duct diameter from any fan or
other flow disturbance within the duct.
17.7.2 Ventilating System
The ventilating system shall be of such efficiency that the average air velocity
in the largest excavated profile is not less than 0.3 m/s. In case the presence
of methane gas is detected or suspected this value shall be increased to 0.5
m/s.
Furthermore, the main ventilating system shall ensure that both of the
following minimum fresh air volume requirements are satisfied at all times:
3.0 m3/min for each person employed underground at one time
6.0 m3/min for each metric horse power (PS) of diesel-powered equipment at
work underground at one lime. This value may be reduced to 3.0 m3/min
providing the equipment is using diesel oil low in sulphur content (max. 0.2%
of sulphur by volume).
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 7
These fresh air volumes shall be cumulative and the design calculations for
the maximum number of persons and diesel-powered equipment working in
the underground at any one time. Any estimated losses, e.g. due to the leaks
in the ducts, shall be added to the figures stated above.
The ventilating system in the underground excavation performed by drilling
and blasting shall consist of two parts:
a) Main ventilating system,
b) Secondary ventilating system.
The main ventilating system shall be designed to allow the flow to be
reversed and shall be operated as follows:
a) Prior to the blasting, the system will be put in the exhaust mode of
operation. Blasting fumes shall be extracted as close as possible to the
excavation face. Exhaust air and blasting fumes shall be discharged in
such a way that they can neither escape in any other working place nor
be re-circulated in the fresh air supply system.
b) Prior to the commencement of mucking and removal of material the
system will be put in the forced mode of operation which will continue till
termination of mucking.
The secondary ventilating equipment of the forced type shall be installed to
provide adequate ventilation of the area between the heading face and the
air intake/outlet of the main system. This system shall be switched on prior to
the blasting and shall be operating until the main system has been put into
forced mode of operation. The air intake shall be located at a sufficient
distance from the heading face to ensure that blasting fumes do not
permeate into this area and cause a recycling of blasting fumes. The outlet of
this duct shall be located so close to the heading face that the driving of the
blasting fumes and dust away from the face into main system is ensured. The
minimum capacity shall be at least 70% of the main system capacity. The
end diameter of the duct shall be such that the air discharge velocity is not
less than 20 m/s.
Re-entry to the heading face and resuming of the work may not occur earlier
than IS minutes following each blast.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 8
17.8 CONTROL OF DUST, SILICA, AND NOXIOUS GASES IN
UNDERGROUND WORKS
17.8.1 Dust and Silica
To reduce the amount of dust, only wet drilling will be allowed and during
mucking, muck tips shall be kept constantly damp by sprinkling with water.
The use of high-pressure water jets for this purpose will not be permitted.
The concentration of fine dust shall be measured and content of silicon
dioxide (SiO2) in all dust-producing underground operations by an approved
method.
Air samples shall be taken within 10 days of commencing underground
excavation, and at 90-day intervals thereafter. Samples shall be taken from
actual working areas. The sampling and testing shall be performed by a
qualified person or laboratory.
Should the concentration of fine dust exceed the limits, such necessary
measures shall be undertaken and install such additional equipment which
will ensure that the dust concentrations are within the specified safe hygienic
limits.
17.8.2 Noxious Gases
Use of internal combustion engines, other than approved mobile diesel-
powered equipment will not be permitted in underground construction sites.
Concentrations of other flammable gases shall not exceed 40% of the lower
explosive limit at the heading face and 20% of the lower explosive limit in the
general tunnel or shaft atmosphere.
If concentrations of noxious gases or other flammable gases exceed the
permissible limits set forth above, all operations shall be interrupted
immediately and personnel shall be removed to a safe area. AH sources of
ignition shall be extinguished or removed. All equipment, with the exception
of ventilation equipment, shall be shut down.
In case of need, an independent consultant experienced in gaseous
tunneling shall be engaged. Re-entry and resuming of the work shall be
prohibited until such measures are taken.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 9
17.9 MANAGEMENT OF EXPLOSIVES
17.9.1 General requirements of responsible persons
All persons charged with, responsible for or involved in the storage,
transportation and handling of explosives are to have received appropriate
training, are to be suitably qualified and experienced and are to be familiar
with the details and guidelines of this chapter.
Persons responsible in whatever capacity for the storage, transportation
and/or handling explosives are to be in good health.
Persons not qualified to store, transport or handle explosives may carry, load
and unload dangerous material into vehicles or storage under supervision of
a qualified person, provided they are verbally briefed on safety measures
prior to handling explosives.
All transportation and storage of explosives, temporarily or permanent must
be recorded in a log book showing the amount of explosives transported or
stored and the amount of explosives being used.
17.9.2 Environmental Requirements
The environmental requirements (temperature, humidity and vibration) of explosives
vary, and are dependent on their intended storage conditions (including shelf life),
transportation, handling and use. The performance of explosives will be
unpredictable and the safety will be reduced if the manufacturers' environmental
conditions are not met. In general, explosives should be:
Kept dry and well ventilated.
Kept as cool as possible and free from excessive or frequent changes of
temperature.
Protected from direct sunlight
Kept free from excessive and constant vibration.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 10
17.9.3 STORAGE REQUIREMENTS
The key aspects to be considered while considering the storage site are:
All storage facilities require adequate ventilation to prevent dampening and
heating of stored explosives. Climatic conditions, size of magazine and
location will determine the amount of ventilation required.
Permanent and/or main storage facilities shall be fire-resistant, theft resistant,
weather resistant and ventilated.
Portable storage facilities, such as a skid-mounted container, trailer or semi-
trailer shall be theft-resistant, fire-resistant and weather-resistant. The
magazine should be constructed of steel with an interior lining of timber.
Magazines of less than one cubic meter in size should be fixed to the ground
to prevent theft of the entire magazine.
A day box is used for the on-site storage of explosives required for daily
operation and shall be:
Weather resistant and able to be locked.
Wherever possible or practical it should be of steel construction
but can be wooden boxes or other appropriate containers.
They shall contain no more than 10 kg of explosives and or (including)
appropriate quantity of initiating means to fire the given quantity of
explosives.
Detonators and/or other means of initiation are to be stored and carried in a
separate box from explosives.
Vehicles are not to be left loaded with explosives at any time unless they are
under continuous security guard and are not to be used as overnight storage
facilities.
The following are the minimum general rules and guidelines for the storage of
explosives:
Permanent and/or main storage facilities are to have ventilation, installed in
such a way that it cannot be closed, blocked or allow water to penetrate.
Permanent and/or main storage facilities are to be fitted with lightning
conductors.
Permanent and/or main storage facilities are to have separate rooms or a
substantial barrier for separating explosives and detonators/blasting caps.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 11
In all circumstances, where possible explosives shall be stored in their
original packaging.
All boxes are to be placed at least 100mm above the floor, e.g. on wooden
pallets.
When boxes are stacked the height will not exceed 1.5 metres. The space
between the top of the boxes and the ceiling will not be less than 600mm.
When stacked on shelves boxes are to be at least 100mm away from the
upper shelf, and 500mm away from the walls of the room.
When stacking boxes the width of the base is to be bigger than the height of
stacked boxes.
Blasting caps and electric detonators may be stacked only if packed in boxes
and on wooden shelves maximum two layers on a shelf. Total height of
stacked boxes will not exceed 1.4 meters.
If portable lanterns or pocket torches of any description are required they will
be switched on before entering the store. The person holding the torch will
not handle explosives or detonators or blasting caps.
Materials used for packaging explosives are to be destroyed and not
discarded after use.
Fire extinguishers shall be available in storage facility.
17.9.4 Additional Safety Measures for Storing and Handling of Explosives
These following shall be implemented and adhered to by the contractor/ project
proponent:
A trained and qualified person is to be responsible for managing the receipt,
storage, guarding and issuing explosives at all levels
Only authorized persons are to enter any storage facility and where
appropriate and relevant to be escorted at all times.
All smoking materials, including cigarettes, matches, lighters etc. and any
object or item that might cause fire are prohibited from the storage facility. At
the entrance to the facility there is to be a warning sign stating ‘NO
SMOKING OR SMOKING MATERIALS ALLOWED BEYOND THIS POINT’.
Clothing and shoes of all workers are to be in accordance with rules on
storage of explosives. Shoes are to be manufactured in such a manner as
not to cause sparks.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 12
The storage facility is not to be used for anything other than storing
explosives. It should be kept free from any other tools, equipment of items
and should at all times be kept as clean and tidy as is practicable.
The facility is to be secured at all times except when it is being ventilated
when it should be guarded.
Facilities are to be constructed in such a way as to provide protection from
static electricity.
If thunderstorms are predicted all work in and around the facility is to stop
and personnel are to go to a safe place.
In the event that the facility repair, all explosives and explosive accessories
are to be removed before repairs are started.
17.9.5 Requirements when preparing to Transport Explosives
Persons responsible for the transportation of explosives are to ensure:
That suitable communications systems are available that will allow for
communication from the vehicle to the project throughout the complete
journey.
That an appropriate communication plan (covering as a minimum a radio
check prior to leaving the start location and informing on arrival at
destination) is in place for the journey.
That a route card is prepared covering the complete journey. That the driver
and drivers assistant are aware of all actions to be taken covering all possible
eventualities during the journey i.e. breakdown, accident, robbery, etc.
Explosives will not be transported unless securely packed in appropriate
boxes. Boxes or individual packages are to have specific identification marks
on them.
Each box is to be marked with the applicable hazardous classification code.
Boxes are to be closed and made waterproof in order to prevent any loss or
spilling and moisture ingress during transport. If the vehicle is not a covered
vehicle, boxes are to be covered with a waterproof cover.
Detonators are to be securely packed in a separate metal box from
explosives. Boxes containing detonators are to be carried in a separate
compartment of the vehicle from boxes containing explosives. UNDER NO
CIRCUMSTANCES ARE DETONATORS TO BE CARRIED IN THE SAME
BOX AS EXPLOSIVES.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 13
Detonators and explosives are to be loaded on to the vehicle in such a way
that they do not move about during transportation.
Boxes, pallets and other packaging for transport of explosives are to be
evenly distributed over the whole deck area, and can be loaded up to the
height of the sides of the truck. All individual packaging and boxes with
explosives are to be loaded and fixed to prevent spillage from boxes and
turning over or impact inside boxes.
17.9.6 Requirements of vehicles used for the Transport of Explosives
Vehicles employed to transport explosives are to be roadworthy, well maintained,
and in good working order. Persons in charge of the transport of explosives will
check the following prior to any movement of vehicles carrying explosives.
The vehicle is marked appropriately.
The driver and driver’s assistant are briefed about the type of explosives to
be transported as well as their destination and the route they are to take. The
type and quantity of explosives and conditions of roads to be travelled on are
to be considered when deciding the type of vehicle to be used.
If vehicles carrying explosives are travelling in convoy, then the distance
between vehicles is to be a minimum of 100 meters.
All vehicles that are employed for the transport of explosives should also carry the
following equipment:
At least two appropriate fire extinguishers, one for the vehicle engine and one
for the load, extinguishers are to be charged with a content that will efficiently
extinguish an explosives fire.
Two hand-torches, Two warning triangles for marking the vehicle when
stationary on the road.
Vehicles transporting explosives shall be fitted with an earthing-strap to take
away static electricity from the vehicle to the ground.
No passengers are to be carried in vehicles transporting explosives.
Vehicle crews are to consist only of a driver and a driver’s assistant.
No material that may cause a fire may be carried in vehicles transporting
explosives.
No repairs that might cause fire by sparking due to impact or violent contact
may be carried out.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 14
No smoking is allowed in the driver’s cabin or any other part of the vehicle.
The vehicle is not to be left unattended.
The driver will drive with care and at an appropriate speed for the roads and
conditions which in all cases shall never exceed 70 KPH or 80% of the
highest speed determined for the road whichever is less.
If the explosives are stolen, the project, contractor or persons transporting
the explosives are to take measures to find it and to report the incident to the
person in charge of the transport and also inform the local authorities.
Explosives and the means to initiate explosives may be transported
together only when the quantity of explosives does not exceed 50 kg, and
100 detonators. This will only be allowed provided that the detonators are in
their originally packed boxes, and that the explosives is packed and loaded
separately from the detonators.
17.10 TRAFFIC MANAGEMENT DURING CONSTRUCTION PHASE
Temporary diversions will be constructed with the approval of the Engineer. Detailed
Traffic Control Plans will be prepared and submitted to the Engineer for approval, at
least 5 days prior to commencement of works on any section of road. The traffic
control plans shall contain details of temporary diversions, details of arrangements
for construction under traffic, details of traffic arrangement after cessation of work
each day, safety measures for transport of hazardous material and arrangement of
flagmen.
The Contractor will ensure that the diversion/detour is always maintained in running
condition, particularly during the monsoon to avoid disruption to traffic flow. He shall
inform local community of changes to traffic routes, conditions and pedestrian
access arrangements. The temporary traffic detours will be kept free of dust by
frequent application of water.
17.11 MEASURES TO BE TAKEN DURING EXCAVATION OF EARTH
While planning or executing excavation the contractor shall take all adequate
precautions against soil erosion, water pollution etc and take appropriate drainage
measures to keep the site free of water, through use of mulches, grasses, slope
drains and other devices. The contractor shall take adequate protective measures to
see that excavation operations do not affect or damage adjoining structures and
water bodies. The recommended measures are listed as below:
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 17: Safety Plan Page 15
Ensure unobstructed natural drainage through proper drainage channels/
structures.
Dispose surplus excavated earth at identified sites. Ensure minimum
hindrance to locals.
All excavations will be done in such a manner that the suitable materials
available from excavation are satisfactorily utilized as decided upon
beforehand. The excavations shall conform to the lines, grades, side slopes
and levels shown in the drawings or as directed by the engineer.
17.12 IMPLEMENTATION OF SAFETY PLAN
The implementation of this plan will be mandatory for all contractors involved in the
projects. The requirements of this plan will be part of contract agreement; therefore
no cost has been kept under this plan in the EMP.
CHAPTER-18 ECO-TOURISM
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 18: Eco-tourism Page 1
CHAPTER-18
ECO-TOURISM
18.1 MEASURES FOR DEVELOPMENT OF ECO-TOURISM
The reservoir will have great tourism potential and it can create many income
generating resources to the local people in many ways viz ; boating , angling
competition , guide, creation of the paying guest houses, travelers’ tour packages
to the nearby sight-seeing places, development of camping sites, birds watching
etc. This must be linked with the ecology environment of the reservoir. For the
development of the tourism, brochures, pamphlets, signage, models, opening of
the tourism information centers, Telescopes, Binoculars, computerized data,
trekking routes and their stay arrangements etc shall be required.
The following activities are proposed for the development of the eco-tourism zone:
Create interest for birds by Bird watching.
Develop infrastructure for perform various water sports activities
such as Boating etc.
Infrastructure for stay of tourists
Provision of house boats, paddle boats
Distribution of plants for plantation on community and private lands.
Distribution of fruit trees for planting on private lands.
Training to locals, viz. Bird Watching, Boating, Catering, Tourist
guides, etc.
.
18.2 BUDGET
An amount of Rs. 13250.0 lakh has been earmarked for development of
infrastructure for Eco-tourism. The details are given in Table-18.1.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 18: Eco-tourism Page 2
Table-18.1: Cost for development of Eco-tourism
S. No. Items of Expenditure Amount
(Rs. lakh)
1. Development of hotels, resorts, restaurants, etc. 10000.0
2. Construction of helipads 500.0
3. Construction of connecting roads 1000.0
4. Purchase of House Boat, Battery Operated boat and
Motor boat, computers, GPS ,etc .etc.
100.0
5 POL for vehicles , boats, generators etc. including
hiring of vehicle in apprehending of poaching cases
100.0
6 Training to locals, viz. Bird Watching, Boating, Catering,
Tourist guides, etc. etc.
50.0
7 Miscellaneous Expenses 1500.0
Total 13250
A Committee for implementation of Eco-tourism can be set up by the State
Government of Uttarakhand. The Committee shall have the following members:
Representative of State Tourism Department
Representative of State Irrigation Department
Superintending Engineer of the Project
Representatives of nearby Gram Panchayat
Representatives of women of the nearby villages.
Representatives of Local NGOs
MLA/MP of the Area
The Committee shall review and oversee the conservation work to be undertaken.
CHAPTER 19 RELOCATION OF TEMPLES
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 19: Relocation of Temples Page 1
CHAPTER-19
RELOCATION OF TEMPLES
19.1 INTRODUCTION
The reservoir so constructed as a result of construction of the dam will not
submerge any monument notified by Archaeological Survey of India (ASI).
However, about 89 temples are likely to be submerged. Among these temples,
three temples located at Pancheshwar, Rameshwar and Taleshwar are the
major temples which are revered not only by the locals but also by the people in
the surrounding areas. The main deity in these three temples is Lord Shiva.
The temple at Pancheshwar is located about 2.5 km upstream of dam site at the
confluence of rivers Sarju and Mahakali. The Reduced Level of the temple is
about 450 m. Thus, the depth of the reservoir water above this temple will be 230
m.
The temple at Rameshwar is situated at the confluence of rivers Sarju and
Ramganga. The R.L. at this site is 550 m. The depth of the water above the
temple will be about 130 m.
The temple at Taleshwar is located along the banks of river Mahakali, about 10
km upstream of Jhoolaghat. The depth of water above this temple would be about
120 m. The reservoir depth over the above mentioned temples sites is too high
(120 m to 250 m) to be protected by engineering structures. Thus, these temples
will be submerged as a result of the projects.
19.2 MANGEMENT MEASURES
In the submergence area, few temples are coming under submergence. It is
proposed to relocate these temples to sites as per sites identified in consultation
with local population. An amount of Rs. 20.0 crore has been earmarked for this
purpose. The details are given in Table-19.1.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 19: Relocation of Temples Page 2
Table-19.1: Abstract of Estimate for Construction of new temples
S. No.
Description of Item Area / Quantity
Unit Rate Rs.
Amount Rs.
1 Built Up Area
Flooring 900 sqm 3963 3566938
Barricading 900 sqm 1467 1320300
Railing 150 m 12380 1857000
Signage’s 20 no. 73685 1473705
Re-handling Charges for Material 2449 tonne
331 810734
Sub - Total 9028677
2 Covered Area approx. 200 sqm 200 sqm 29951 5990200
3 Trash bins 10 no. - 2 wheeler of 120 ltr. Capacity
10 no. 4553 45530
4 Electrification of entire area 1307328
5 Solar Street Poles 20 no. 20 no. 24467 489340
6 Bio-Digester Toilet (Male & Female) with Water Storage Tank RCC + Reed bed (2 no.)
2 no. 1062087 2124174
7 Chatri Octagonal (2 no.) 2 no. 138822 277644
8 Toe Wall 300 mm around approach path and temple structures
1150 m 10591 12179650
9 Water Spout ( 3 no. of 2.5 m) 3 no. 408008 1224023
10 Planter Bed (25 % area i.e. 225 sqm) 225 sqm 301 67725
11 SS benches 20 no. of 3 seats each 20 no. 37621 752420
12 Murals 144 sqm 35000 5040000
13 Idols @ 50 lakh per idol 5 no. 500000 2500000
14 Access path 500 m 9650 4824775
15 Sheds / Shaded Area 10 no. 82627 826270
16 Type-III Retaining Wall 120 m 24720 2966400
Sub - Total 40615479
17 Topo-graphical Survey 1000000
18 Geotechnical & Soil Investigation 1000000
Sub - Total 42615479
19 Contingency @ 20% 8523096
Sub - Total 51138574
20 Cost Index for Pithoragarh @ 20.9% 10687962
GrandTotal 61826536
Cost for Construction of 1 Temple Rs. 618.30 lakh
Cost for Construction of 3 Temples Rs. 1854.90 lakh, say Rs. 20 crore
CHAPTER-20
ENVIRONMENTAL MONITORING PROGRAMME
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 1
CHAPTER-20
ENVIRONMENTAL MONITORING PROGRAMME
20.1 INTRODUCTION
Environmental Monitoring is an essential tool in relation to environmental
management as it provides the basis for rational management decisions regarding
impact control. Environmental monitoring shall be performed during construction,
commissioning, and operation phases to ensure that the adverse impacts have
been mitigated efficiently and to verify the impact predictions. The monitoring
program will indicate where changes to procedures or operations are required, in
order to reduce impacts on the environment or local population. The monitoring
program for the Pancheshwar Multipurpose Project will be undertaken to meet the
following objectives:
To monitor the environmental conditions of reservoirs areas, power
houses and command areas as impacted by the project;
To check on whether mitigation and benefit enhancement measures
have actually been adopted, and are proving effective in practice;
To provide information on the actual nature and extent of key
impacts and the
Effectiveness of mitigation and benefit enhancement measures
which, through a feedback mechanism, can improve the planning
and execution of future, similar projects.
20.2 AREAS OF CONCERN
From the monitoring point of view, the important parameters are water quality, air
quality, noise, erosion and siltation, afforestation, fishery, etc. An attempt will be
made to establish early warning of indicators of stress on the environment.
Suggested environmental monitoring plans are described in the following sections.
20.3 WATER QUALITY
Construction Phase
It is proposed to monitor the waste water before and after treatment from sewage
treatment plants. The frequency of sampling and analysis could be once per
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 2
month. The sampling sites shall be labour camps area, power house site,
reservoirs sites; the parameters to be monitored include pH, Biochemical Oxygen
Demand (BOD), Chemical Oxygen Demand Total Suspended Solids (TSS) and Oil
& Grease. A total of 240 samples shall be analysed for which a provision of Rs.
7.2 lakh/year has been earmarked.
Operation phase
The surface water quality of the proposed reservoirs can be monitored during pre
and post-monsoon seasons. The proposed parameters to be monitored include;
pH, turbidity, total dissolved solids, calcium, magnesium, total hardness, chlorides,
sulphates, nitrates, DO, COD, BOD, etc.
During project operation phase, a Sewage Treatment Plants (STP) is proposed to
be set up to treat the sewage from the power houses. It is envisaged to analyze a
sample each before and after treatment from the STP, once every month. The
parameters to be analyzed include pH, Biochemical Oxygen Demand (BOD),
Chemical Oxygen Demand (COD), Total Suspended Solids (TSS) and Oil &
Grease. It is proposed to analyse 24 samples in a year which a provision of Rs.
0.72 lakh/year has been earmarked.
20.4 AMBIENT AIR QUALITY
Construction Phase
The ambient air quality monitoring during construction phase will be carried out by
the external agency, approved by Uttarakhand Pollution Control Board. Every year
monitoring is to be done for the following three seasons:
Winter Season
Summer Season
Monsoon Season
The number of sites to be covered as a part of Environmental Monitoring
Programme shall be around 6. The frequency of monitoring could be twice a week
for four consecutive weeks at each station for each season. The parameters to be
monitored are Particulate Matter (PM2.5) and Particulate Matter (PM10), Sulphur
dioxide (SO2) and Nitrogen dioxide (NO2). The number of days of monitoring shall
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 3
be 144 days in a year for which a provision of Rs. 7.20 lakh/year has been
earmarked.
20.5 NOISE
Construction Phase
Noise levels from vehicular movement and operation of various construction
equipment will be measured during construction phase at major construction sites.
The frequency of monitoring could be once every month at various construction
sites. For monitoring of noise levels at construction sites an Integrating Sound
Level Meter will be purchased. An amount of Rs. 1.5 lakh has been earmarked for
this purpose.
20.6 METEOROLOGICAL ASPECTS
It is suggested that a meteorological laboratory be set up to monitor various
meteorological parameters. Automatic instruments for continuous recording of
following meteorological parameters will be installed:
Temperature
Rainfall
Humidity
Cloud cover
Wind speed
Wind direction
Evaporation Rate
Solar Intensity
Cloud Cover
An amount of Rs. 15 lakh has been earmarked for this purpose.
20.7 EROSION AND SILTATION
Operation Phase
Soil erosion rates, slope stability of embankments of reservoirs, efficacy of soil
conservation measures, need to be closely monitored ones a month. The study
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 4
should be undertaken throughout the life of the project so as to design the soil
erosion prevention measures and also for the rehabilitation of the project. The
various parameters to be monitored include soil erosion rates, stability of bank
embankment, etc. An amount of Rs. 10 lakh has been earmarked for this purpose.
20.8 ECOLOGY
Project Construction Phase
A detailed ecological survey covering forestry, fisheries, wildlife is recommended
during entire construction phase. The survey can be conducted three seasons every
year for the entire construction period. The various aspects to be covered include:
- Qualitative and Quantitative assessment of flora and fauna.
- Monitoring of restoration of muck disposal area.
An amount of Rs. 30 lakh/year has been earmarked for this purpose.
Project Operation Phase
Status of afforestation programmes, changes in migration patterns of the aquatic
and terrestrial fauna species should be studied. The study could be undertaken
with a frequency of three seasons per year for the entire design life of the dam. An
amount of Rs. 30 lakh/year has been earmarked for this purpose.
20.9 FISHERIES
Operation Phase
Monitoring of fisheries in the reservoirs will be essential to achieve sustainable
yield of fish. Some of the parameters to be monitored are phytoplanktons,
zooplanktons, benthic life and fish composition, etc. Based on human resources
and facilities available, monthly observations in time and space need to be made.
An amount of Rs. 30 lakh/year has been earmarked for this purpose.
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 5
20.10 INCIDENCE OF WATER-RELATED DISEASES
Project Construction Phase
Identification of water-related diseases, adequacy of local vector control and
curative measures, status of public health are some of the parameters which
should be closely monitored three times a year with the help of data maintained in
the local dispensaries/hospitals. An amount of Rs. 20 lakh/year has been
earmarked for this purpose.
Project Operation Phase
Identification of water-related diseases, sites, adequacy of local vector control and
curative measures, status of public health are some of the parameters which should
be closely monitored four times a year with the help of data maintained in the local
dispensaries/hospitals. An amount of Rs. 20 lakh/year has been earmarked for this
purpose.
20.11 SUMMARY OF ENVIRONMENTAL MONITORING PROGRAMME
The Environmental monitoring programme for implementation during construction
and operation phases is given in Tables-20.1 and 20.2 respectively.
Table-20.1: Summary of Environmental Monitoring Programme during Project
Construction Phase
S. No. Item Parameters Frequency Location
1. Effluent from STPs
pH, BOD, COD, TSS, TDS
Once every month
Before and after treatment from Sewage Treatment plant
2. Water-related diseases
Identification of water related diseases, adequacy of local vector control and curative measure, etc.
Three times a year
Labour camps and colonies
3.
Noise Equivalent noise level (Leq)
Once in three months
At major construction sites.
4. Air quality PM10 SO2 and NO2 Once every season
At major construction sites
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 6
Table-20.2: Summary of Environmental Monitoring Programme during Project
Operation Phase
S. No. Items Parameters Frequency Location
1. Water pH, Temperature, EC,
Turbidity, Total Dissolved
Solids, Calcium,
Magnesium, Total
Hardness, Chlorides,
Sulphates, Nitrates, DO.
COD, BOD, Iron, Zinc,
Manganese
Thrice a
year
1 km upstream of
dam site
Reservoir area
1, 5 and 10 km
downstream of Tail
Race discharge
2. Effluent from
Sewage
Treatment
Plant (STP)
pH, BOD, COD, TSS,
TDS
Once every
week
Before and after
treatment from
Sewage Treatment
Plant (STP)
3. Erosion &
Siltation
Soil erosion rates,
stability of bank
embankment, etc.
Twice a year -
4. Ecology Status of afforestation
programmes of green
belt development
Once in 2
years
-
5. Water-
related
diseases
Identification of water-
related diseases, sites,
adequacy of local vector
control measures, etc.
Three times
a year
Villages adjacent to
project sites
6. Aquatic
ecology
Phytoplanktons,
zooplanktons, benthic
life, fish composition
Once a year 1 km upstream of
dam site
Reservoir area
1, 5 and 10 km
downstream of Tail
Race discharge
7.
Land use Land use pattern using
satellite data
Once in a
year
Catchment area
8. Soil pH, EC, texture, organic
matter
Once in a
year
Catchment area
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 20: Environmental Monitoring Programme Page 7
20.12 COST FOR IMPLEMENTING ENVIRONMENTAL MONITORING
PROGRAMME
The cost required for implementation of the Environmental Monitoring Programme
is of the order of Rs.736.74 lakh @ Rs.64.4 lakh/ year. A 10% annual price
increase may be considered for every year. The construction period for estimation
of cost for implementation of Environmental Monitoring programme during
construction phase has been taken as 8 years. The details are given in Table-20.3.
The cost required for implementation of the Environmental Monitoring Programme
in operation phase is of the order of Rs.81.0 lakh/year. The details are given in
Table-20.4.
Table-20.3: Cost for Implementing Environmental Monitoring Programme during
construction phase
S. No Item Cost
(Rs. lakh/year)
Total cost for construction period
of 8 years with 10% escalation
per year (Rs. lakh)
1 Water quality 7.20 82.37
2 Ambient Air quality 7.20 82.37
3 Ecology 30.0 343.20
4 Incidence of water
related diseases
30.0 228.40
Total 64.4 736.74
Table-20.4: Cost for Implementing Environmental Monitoring Programme during
operation phase
S. No Item Cost (Rs. lakh/year)
1 Water quality 0.72
2 Ecology 30.00
3 Fisheries 30.00
4 Incidence of water related diseases 20.00
Total 80.72,
say Rs. 81.0 lakh/year
CHAPTER-21
COST ESTIMATES
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 21: Cost Estimates Page 1
CHAPTER-21
COST ESTIMATES
21.1 COST FOR IMPLEMENTING ENVIRONMENTAL MANAGEMENT PLAN
The total amount to be spent for implementation of Environmental Management
Plan (EMP) is Rs. 1089650 lakh or Rs. 10896.50 crore. The details are given in
Table-21.1.
Table-21.1: Cost for Implementing Environmental Management Plan
S. No. Item Cost (Rs. million)
Cost (Rs. lakh)
1. Compensatory Afforestation 581.40 5814.0
2 Biodiversity Conservation 380.10 3801.0
3. Fisheries Management 195.0 1950.0
4. Public health delivery system 292.94 2929.4
5. Construction of labour camps including land cost 312.00 3120.0
6. Sanitation facilities in labour camps 206.00 2060.00
7. Solid Waste Management in labour camps 137.00 1370.0
8. Fuel in labour camps 820.85 8208.48
9. Muck management 800.00 8000.0
10. Restoration of quarries 300.00 3000.0
11. Landscaping of construction sites 29.00 290.0
12. Environmental Management in Road construction
447.20 4472.0
13. Greenbelt Development around reservoir 4.32 43.2
14. Air pollution control 90.00 900.0
15. Water pollution control 68.00 680.0
16. Energy Conservation Measures 45.00 450.0
17. Catchment Area Treatment 7000.00 70000.0
18. Disaster Management Plan 123.00 1230.0
19. Resettlement and Rehabilitation Plan 77339.88 773398.8
20. Livelihood Plan 2261.82 22618.16
21. Fund for Local Area Development Activities @ 0.5% of project cost
1683.35 16833.5
22. Monitoring and Evaluation Aspects 25.00 250.00
23. Tourism Development 1325.00 13250.0
24. Relocation of temples 200.0 2000.0
25. Environmental Monitoring during construction phase
73.67 736.74
26. Micro-meteorological instruments 1.50 15.0
27. Noise meter 0.15 1.5
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 21: Cost Estimates Page 2
S. No. Item Cost (Rs. million)
Cost (Rs. lakh)
28. Environmental Audit 10.00 100.0
Sub-Total (A) 94752.18 947521.78
Contingency (15%) of Sub-total (B) 14212.827 142128
Total (A+B) 108965.01 1089650
CHAPTER-22 DISCLOSURE OF CONSULTANTS
INVOLVED IN THE CEIA STUDY
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 22: Disclosure of Consultants Involved in CEIA Study Page 1
CHAPTER-22
DISCLOSURE OF CONSULTANTS INVOLVED IN THE CEIA STUDY
The EIA study has been conducted by WAPCOS Ltd., a Government of India
Undertaking under Ministry of Water Resources, River Development & Ganga
Rejuvenation. WAPCOS Ltd. has a full-fledged Centre for Environment who has
conducted the CEIA study. The list of the Experts involved in the EIA study is
given in Table-22.1.
Table-22.1: List of Experts involved in the CEIA study
S. No.
Name Expertise Signature
1. Dr. Aman Sharma
EIA Coordinator
Air Pollution Expert
Water Pollution Expert
Solid Waste Management Expert
Hydrologist & Ground Water Expert
2. Dr. A. K. Sharma Ecology and Bio-diversity Expert
3. Mr. R.V. Ramana Noise Expert
4. Dr. K.K. Gaur Social Expert
5. Mr. S.M. Dixit Air Quality Expert
6. Mrs. Moumita Mondal Ghosh
Landuse Expert
PANCHESHWAR MULTIPURPOSE PROJECT EMP Report
Chapter 22: Disclosure of Consultants Involved in CEIA Study Page 2
S. No.
Name Expertise Signature
7. Mr. Sanjeev Sharma
Noise & Vibration Expert
8. Dr. H S Rumana Ecology and Bio-diversity Expert
9. Mr. B M Sinha Geologist
10. Dr. Santosh K Sati
Geologist
Consultant:
76-C, Institutional Area, Sector – 18, Gurgaon – 122015, Haryana (INDIA)
Telephone: 0124-2342576, Fax: 0124-2349187 [email protected]
Website: http://www.wapcos.co.in JUNE 2017