Panama Canal Annual Report 2012

  • Upload
    dryanm

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 8/11/2019 Panama Canal Annual Report 2012

    1/112

  • 8/11/2019 Panama Canal Annual Report 2012

    2/112

  • 8/11/2019 Panama Canal Annual Report 2012

    3/112

  • 8/11/2019 Panama Canal Annual Report 2012

    4/112

    Chairman of the Board of Directors

    Roberto RoyChairman of the Board of Directors

  • 8/11/2019 Panama Canal Annual Report 2012

    5/112

    During this period, the Canal has tackled a new and signicant challenge, the designation of

    the team that will lead the organization towards the Canal expansion. The appointment of the

    Administrator and the Deputy Administrator dened the message of the Canal Authority to the

    Panamanian people, clients and stakeholders, of assuring that the management of the waterway

    will maintain its vision of offering quality and excellence in the services rendered to customers

    while providing economic well-being to the country and benets to the worlds economy, and

    ensuring best practices for environmental protection. The selection is representative of a certain

    institutional continuity that shows the Board of Directors commitment to achieving high standards

    for which this waterway has been recognized.

    In addition, we identied the need to align the organizational structure of the Panama CanaAuthority to suit our customers and clients evolving needs, prepare to manage an expanded

    Canal, and reect best business practices. As adaptability to change has always been a

    characteristic of the interoceanic waterway, we have intensied the efforts to diversify ou

    services,and simultaneously strengthen the core business of the organization.

    The execution of the Expansion Program, which is almost midway of its completion, is only one

    of the projects that are currently underway to continue providing better services every day

    The Panama Canal has also continued to implement an aggressive modernization program

    comprised of projects aimed at increasing the present Canal capacity, through the widening

    and dredging of the entrances. These works are currently in progress and will also contribute to the

    operation of the expanded Canal. This complementarity shows the Canals high professionalism

    standards in carrying out two parallel functions, the successful operation of the existing Canal, and

    the development of a agship mega-project in the engineering eld, as was clearly validated by

    the Panama Canal 2012 International Engineering and Infrastructure Congress.

    The nancial results for this period have been outstanding. Despite the global economic outlook

    the efforts of the Panama Canal Authority to improve the services our route offers resulted in

    greater throughput during this scal year, setting a new tonnage record for total revenues

    while maintaining high standards of service. These results reect the tireless efforts of a workforcecommitted to the development of the organization and the growth of our country.

    Message

  • 8/11/2019 Panama Canal Annual Report 2012

    6/112

  • 8/11/2019 Panama Canal Annual Report 2012

    7/112

    Rafael E. Brcenas P.Director

    Guillermo O. Chapman, Jr.Director

    Nicols CorcioneDirector

    Jos A. Sosa A.Director

    Ricardo De La Espriella T.Director

    Marco A, Ameglio S.Director

  • 8/11/2019 Panama Canal Annual Report 2012

    8/112

    Jorge L. QuijanoAdministrator of the Panama Canal

    Administrator of the Panama Canal

  • 8/11/2019 Panama Canal Annual Report 2012

    9/112

    Message

    I am proud to present the Annual Report of the Panama Canal Authority (ACP) for scal year 2012. As required by our

    practices of transparency and accountability, we have made every effort to accurately reect how the Panama Cana

    fullls its mission of contributing to the sustainable development of the country, while expanding its leading role in the

    worlds maritime trade.

    At the end of scal year 2012, for a second consecutive year, the Panama Canal has set a new tonnage record of 333.7

    million Panama Canal/Universal Measurement System (PC/UMS) tons. Beyond its historical signicance and the fact tha

    it represents an operational indicator, this record demonstrates the countrys sustained effort and reiterated commitmen

    to keep its most strategic resource, its geographical position, at a competitive edge and at the forefront of progress.

    It is important to emphasize these operating results are the outcome of the determination of 10,000 men and women

    who are aware of the responsibility that we embody, not only in managing and operating the Canal in an efcient, cos

    effective and safe manner, but also our responsibility with the environment, our social environment, our customers, our

    users and Panama.

    Together with the new tonnage record, other indicators show that the Panama Canal provides quality service and it

    is reected in the tonnage percentage and a reduction in Canal Waters Time. Direct contributions to the country also

    maintained a positive rate for a second year in a row exceeding B/. 1,000 million for a total of B/. 1,032.3, which surpassed

    by 8.6 percent the amount budgeted for scal year 2012.

    While the Panama Canal implements operational actions that result in the efcient administration of the Canal, our

    organization also prioritizes its environmental and social management. Specically this report, documents the many

    education, water quality, reforestation, sustainable development and other projects that aim to have an impact on the

    quality of life of the residents of the Panama Canal Watershed, as we work together to preserve it.

    Sustainability also has a signicant role in ACPs human capital management and labor relations, pursuing to maintain

    high equity and well-being standards for the Canals most valuable resource, its people. For instance, during this sca

    year over 8,000 employees were trained.

    Parallel to the effort to maximize the benets of our geographical position, we continue to reafrm our commitment

    to support the principles of the United Nations Global Compact through various activities and examples of our daily

    activities. Examples of this are contained in this document as are our responsibility towards each of our stakeholders, ou

    environmental commitment, the community relations programs, the visitors centers- and I want emphasize the opening

    of the new Center of Observation of the Canal Expansion on the Atlantic side as well as the communication strategies

    aimed at our shareholders.

    In the course of 2012, ve years of work in the Expansion Program have gone by and the progress and milestones are

    included in this annual report. In abidance of Law 28 of July 17, 2006, which approvest the proposal for the construction o

    a third set of locks in the Panama Canal, key steps have been taken to build a new bridge over the Canal on the Atlantic

    side and the construction will begin next year.

    As expected, the impact of the Panama Canal Expansion already transcends national boundaries. For Panama the

    results are tangible. There is still a way to go, and a lot of potential to consolidate the Panama Canal in the developmen

    of Panama.

    I would like to highlight the administration of three distinguished Panamanians who contributed to the Canals history

    and strengthened the pillars of this great Panamanian organization. They are Dr. Rmulo Roux, Engineer Alberto Alemn

    Zubieta and Engineer Jose Barrios Ng. Thanks to their work at the Panama Canal during great part of this scal year

    we managed to exceed the goals and achieve a transparent and seamless transition to a new administration. The

    organization and all its employees owe them our deepest gratitude.

    Along this path, I hereby commit to the promise of all Panama Canal workers to continue working in compliance with the

    highest standards of excellence, discipline and passion for our country.

  • 8/11/2019 Panama Canal Annual Report 2012

    10/112

    Administration

    Jorge L. QuijanoAdministrator

    Manuel BentezDeputy Administrator

    Luis AlfaroEngineering

    lvaro A. CabalGeneral Counsel

    Francisco Loaiza B.Human Resources

    Ilya MarottaEngineering and Program

    Management

  • 8/11/2019 Panama Canal Annual Report 2012

    11/112

    Esteban G. SenzOperations

    Francisco J. Miguez P.Administration and Finance

    Rodolfo SabongePlanning and

    Business Development

    Carlos VargasEnvironment, Water and Energy

    Manuel DomnguezCorporate Communications

    Ana Mara P. de ChiquilaniCorporate Affairs

  • 8/11/2019 Panama Canal Annual Report 2012

    12/112

    For ve centuries the route through Panama has been an important path for global

    trade and transportation. Currently, the railroad, airports, highways, the pipeline, optic

    ber communication cables, international techno parks, ports and the Panama Canal

    jointly comprise the key infrastructure that interdependently and complementarily,

    simultaneously exploit the unique geographical position of the Panamanian isthmus.

    On December 31, 1999, after 85 years of U.S. administration, the Republic of Panama

    assumed full administration, operation and maintenance of the Canal, in compliance

    with the 1977 Torrijos-Carter treaties.

    The waterway is now managed by the Panama Canal Authority (ACP), an autonomous

    government institution with a constitutional mandate that makes the Canal an efcient

    and cost effective entity that provides continuous and efcient services to world

    maritime trade.

    The more than 10,000 highly skilled employees that work in the Canal constitute the driving

    force behind the Canals excellence. The Panama Canal is an inalienable patrimony

    of the Panamanian nation and; therefore, it may not be sold, assigned, mortgaged

    or otherwise encumbered or transferred. By law, after covering operating, investment,

    modernization and expansion costs, surplus funds are awarded to the National Treasury.

    During the 13 years of Panamanian management, direct contributions have exceeded

    B/.7,609 million.

    The Canal is a shortcut water passage to reduce shipping distances, and save time and

    cost in the transportation of all types of goods. With about 80 kilometers in length, the

    waterway connects the Atlantic and Pacic oceans at one of the narrowest points of

    the American continent.

    The Panama Canal, a two-way canal, operates three sets of locks that work as water

    elevators that lift the ships to the level of Gatun Lake 26 meters above sea level to cross

    the Central Mountain Range, and later lower them again to sea level on the other side

    of the Isthmus of Panama.

    The Canals three sets of locks, have two lanes, operate as water lifts to elevate ships 26

    meters above sea level to the level of Gatun Lake, In their transit of the channel across

    the Continental Divide, and the lower them back on the opposite side of the Isthmus.

    Since its opening in 1914, more than one million vessels from around the world that reach

    more than 80 countries through 144 maritime routes, have transited the waterway.

    The Third Set of Locks, currently under construction as part of the Panama Canal

    Expansion Program, will be ready by the year 2014. This project will double the

    waterways capacity to meet the growing demand of world trade and to maintain the

    Canal as the route of choice for international trade.

    Company Profle

  • 8/11/2019 Panama Canal Annual Report 2012

    13/112

    Honesty / Transparency / Competitivenes / Loyalty / Responsibility / Reliability

    l

    l

    Vision

    MissionProducir en forma sostenible el mximo benecio de nuestra posicin geogrca.

    OUR BUSINESS - This enterprise is charged with operating, maintaining and improving the Panama

    Canal so that it remains the route of choice for our customers.

    OUR COUNTRY - We bring wealth to Panama and contribute with our efforts to the nations welfare

    its development and its progress, and to an improved standard of living for all Panamanians.

    OUR CUSTOMERS - We build lasting relationships with our customers, understanding and anticipating

    their needs, adding value and offering quality service.

    OUR PEOPLE - We recognize that the Canal employee is the most important resource in achieving

    service excellence. We recruit and promote the very best.

    WORLD LEADER in services to the maritime industry and in sustainable development for the

    conservation of the Panama Canal watershed.

    CORNERSTONE of the global transportation system and driving force for the progress, developmen

    and growth of Panama.

    MODEL of excellence, integrity and transparency in our conduct; committed to the integra

    development of our human resource team.

    Corporate Values

    Objective 1 - To increase protability in a sustainable manner for the benet of the country.

    Objective 2 - To expand the range of services and products in order to exploit markeopportunities.

    Objective 3 - To implement business practices that enhance good corporate governance.

    Objective 4 - To efciently manage the volume and quality of the water resources of the PanamaCanal Watershed.

    Objective 5 - To increase productivity through excellence in performance and the wellbeing ohuman resources.

    Estrategic Objectives

    During scal year 2012, the Ofce of General Counsel has received 660 informationrequests.In the category of alimony, 178 were received, out of which 176 have been resolved andtwo are in process for revision.In the general requests category (which encloses unions, employees, governmenentities, and general public) 482 were received. Of these, 456 have been resolved and26 are in process, waiting for information to answer requesters.

    Inormation Request

  • 8/11/2019 Panama Canal Annual Report 2012

    14/112

    Operaciones

    Operations

  • 8/11/2019 Panama Canal Annual Report 2012

    15/112

    The Panama Canal reached a new PC/UMS (Panama Canal

    Universal Measurement System) tonnage record during scal year

    2012, when it reached 333.7 million PC/UMS tons. This historic

    milestone was the result of the determined effort of all Canal

    employees, the effective management of its operations, and the

    important role the route through Panama plays in international

    maritime global trade by always providing world-class services to

    its users.

    The year 2012 was characterized by a global economic slow

    down consequential of scal adjustments made by advanced

    economies, nancial systems instability and the economic

    uncertainty triggered by the crisis in Europe. At the same time, a

    reduction in the demand in the leading economies affected the

    emerging markets through a reduction in international trade.

    The economy of the United States, the main user of the Canal,

    showed signs of improvement, but at a less-than-optimal level.

    Retail and vehicle sales, as well as exports have improved

    signicantly; however, the 7.8 unemployment rate recorded in

    September keeps the economy increase from developing to

    desired levels.

    On the other hand, China, the second most important user of the

    Panama Canal and the worlds foremost exporter, is affected by

    Europe and the United States low demand for imports. From the

    beginning of 2012, economic indicators show a downward trend,

    Operating Results

    A N N U A L R E P O R T 2 0 1 2 13

    which culminated in a decline of the increase

    projections by the Chinese government, from

    8.5 per cent to 7.5 per cent.Regardless of the

    measures taken by the Chinese governmento stimulate its economy, such as more libera

    credit policies and the development of massive

    construction projects, their sustainability may be

    put to test if European and American economies

    do not improve. Nevertheless, China remained an

    important player in the maritime ow through the

    Canal during scal year 2012. If there is a recovery

    in world trade in 2013, it is expected that Chinas

    increase projections will be revitalized and the

    transportation of cargo through the Canal will rise

    The Panama Canal ended scal year 2012 with

    14,544 transits, a 0.95 per cent decrease from the

    previous year. Panamax vessel transits were 7,241

    56.3 per cent of oceangoing vessels The PC/UMS

    tonnage at the end of scal year 2012 was 333.7

    million, a 3.6 per cent increase compared to sca

    year 2011. The total cargo through the Cana

    registered at 218.1 million long tons, a slight 1.9 pe

    cent decrease compared to the previous yearToll revenues reached a record B/.1,852.4 million

    a 7.1 per cent increase, as a result of larger vesse

    transits.

  • 8/11/2019 Panama Canal Annual Report 2012

    16/112

    A N N U A L R E P O R T 2 0 1 2

    Full Container Vessel

    SegmentThe full container vessels segment performed well during scal year

    2012, showing an increase in trafc gures as compared for scal

    year 2011.A total of 3,331 container ships transited the Canal, with

    a volume of 119.9 million PC/UMS tons and 12.2 million TEU (twenty

    foot equivalent unit) invoiced. These gures reect a 2.9 percent

    increase in transits, a 5.4 percent increase in tons and a 5.6 percent

    increase in TEU volumes as compared to the previous year. Of

    the total transits, 74 percent are in the 100 feet or more in beam

    category; and vessels with over 900 feet overall length accounted

    for 47.3 percent.

    During scal year 2012, the full container vessels segment

    accounted for B/.960.1 million in toll revenues. From this total, 93.9

    percent correspond to TEU capacity and 6.1 percent to 7.4 million

    loaded TEUs which transited effectively. It is noteworthy that this

    segment comprised 51.8 percent of the total Canal toll revenues

    in scal year 2012.

    Containerized cargo imports at major ports on the East Coast of

    the United States, the main country of origin and/or destination

    of containerized cargo that transits through the Panama Canal,

    increased in scal year 2012 compared to the previous year,

    which contributed positively to increase cargo

    volumes transits. Likewise, the global demand for

    containerized cargo grew 3.4 percent in 2012.

    The number of liner services in the route through

    Panama remained fairly consistent, with 33

    services at the end of scal year 2012, a one

    service increase from the previous year. However,

    the average deployed vessel size increased from

    3,952 TEUs in 2011, to 4,078 TEUs in scal year 2012,

    leading to an increase in TEU capacity, and thus

    higher revenues.

    Reefer Vessels SegmentIn scal year 2012, the reefer vessel segment

    registered 1,116 transits, which represent 9.9

    million PC/UMS tons and B/.50.6 million in revenues

    from tolls. Transits, tonnage and tolls were down

    24.5 percent, 20.8 percent, and 12.9 percent,

    respectively, in comparison with scal year 2011.

    14

  • 8/11/2019 Panama Canal Annual Report 2012

    17/112

    A N N U A L R E P O R T 2 0 1 2

    The main driver for the downward trend is the transition of

    cargo transportation from conventional refrigerated cargo

    vessels to refrigerated containers on container vessels.

    During 2012, three liner container services were introducedfor the transportation of refrigerated cargo from the west

    coast of South America. These services are ECUMED

    service of Maersk Line, as well as MSCs Ecuador Express

    and Andean Feeder service, which compete directly for

    the transportation of bananas in conventional vessels.

    Low temperatures in countries like Ecuador and diseases

    such as black sigatoka affected the quality of some banana

    plantations during several months in scal year 2012. This

    curtailed the supply of exportable bananas, which allowed

    countries such as Colombia, Costa Rica and Panama to

    increase their share in consumer markets.

    Liquid Bulk SegmentFiscal year 2012 was an excellent year for the liquid bulk

    segment. This segment registered 2,478 transits, 51.6 million

    PC/UMS tons and B/.212.2 million in toll revenues, which

    amount to increases of 6.7 percent in transits, 5.4 percent

    in PC/UMS tonnage, and 8.1 percent in toll revenues over

    scal year 2011.

    These results are due to a 30.2 percent increase in transits

    by vessels of 80 to 90.99 feet or more in beam, which was

    reected in a 27.4 percent PC/UMS tonnage rise and

    30.9 percent increment in toll revenues. In addition, the

    volumes of cargo on board of these vessels also increased22.4 percent over the previous scal year.

    Diesel, gasoline and miscellaneous petrochemicals are

    among the main products that account for the increase in

    trafc gures for this segment during scal year 2012. Diese

    registered its biggest ows mainly in the routes from the Gul

    of Mexico to Chile and Ecuador, while gasoline was driven

    by exports from the Gulf of Mexico to Mexico, Guatemala

    Chile, Japan, and Ecuador.

    Chilean diesel imports, mainly from American reneries

    located in the Gulf of Mexico, continued their remarkable

    increase. This trade increased by 45.7 percent compared

    to scal year 2011, which was already a record yea

    for Chilean imports of this product. Chile continued to

    endure hydroelectric generation problems due to a

    lengthy drought, which along with the economic increase

    prompted the increase in diesel imports to supply for the

    rising electric generation demand.

    Regarding the supply of distillate products such as diese

    and gasoline, American reneries, mainly located in the

    15

  • 8/11/2019 Panama Canal Annual Report 2012

    18/112

    A N N U A L R E P O R T 2 0 1 2

    Gulf of Mexico, maintain large commercial inventories as a result

    of a decrease in the demand and prices of these products in that

    country. This situation allowed setting attractive export prices;

    countries such as Chile and Ecuador took advantage of this

    circumstance.

    On the other hand, gas carrier ships, despite being a small sub

    segment, registered good trafc indicators-41 additional transits-

    22.0 percent over scal year 2011. In addition, this segment

    was above the previous scal year in PC/UMS tonnage and toll

    revenues, recording increases of 16.3 percent and 19.0 percent,

    respectively.

    Over the last scal year, the increment in trafc gures for the

    gas carrier ships was driven by a 62.9 per cent increase in the

    transit of vessels of 80 to 90.99 feet of beam, which replicated in

    a 56.8 percent PC/UMS tonnage increase and 62.4 percent in tolls

    revenues. These vessels carried mostly LPG (Liqueed petroleum

    gas) and miscellaneous petrochemicals.

    The amount of cargo transported by gas carrier ships through the

    Canal during scal year 2012 was very similar to the levels of the

    previous scal year. The 36.8 percent and 32.2 percent increase

    in cargo for vessels of less than 80 feet and from 80 to 90.99 feet in

    beam, respectively, helped offset the 14.3 percent cargo decrease

    transported by vessels with 100 feet or more in beam.

    The products which increased over the previous scal year were

    the ammonium compounds (ammonia) originating in Venezuela

    and Trinidad and Tobago with destination to Chile; and LPG from

    Trinidad and Tobago bound for El Salvador, transported primarily

    on ships with less than 80 feet and from 90 to 90.99 feet in beam.

    Drybulk Carrier SegmentDuring scal year 2012, the drybulk carriers

    segment recorded 83.4 million PC/UMS tons, the

    highest level in vessel capacity tonnage since

    scal year 1996. PC/UMS tonnage increased 4.2

    per cent compared to 80.0 million tons of scal

    year 2011. For the third consecutive year, dry bulk

    carriers recorded the highest number of transits

    of all vessel types transiting the waterway, with a

    total of 3,339 transits.

    Total toll revenues were B/.337.7 million, an 8.2

    percent increase compared to scal year 2011,

    mainly as a result of the transiting vessels increased

    PC/UMS tonnage.

    Cargo tonnage totaled 98.6 million long tons

    without greater variations. On the other hand,

    tonnage of in ballast vessel capacity increased 12

    percent, which contributed to PC/UMS tonnage

    increase for the period. Vessel transits with beams

    over 100 feet accounted for 69 percent of total

    dry bulk transits. In general, the average vessel

    size increased 3 percent.

    Grains remained as the top commodity

    transported in bulk carriers, with 36.0 million long

    tons; however, the cargo level was 8.1 percent

    below the 39.1 million long tons recorded in scal

    2010 2011 2012

    Dry-Bulk Carriers

    Full ContainershipTanker

    Miscellaneous

    Refrigerated Cargo

    General Cargo

    Vehicle Carrier

    Container/Break-Bulk Vessel

    Liquid-Gas Carrier

    Fishing Vessel

    Passenger Ship

    Roll-on/Roll-off

    0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0

    Transit by Vessel Types(in thousands of transits)

    16

  • 8/11/2019 Panama Canal Annual Report 2012

    19/112

    A N N U A L R E P O R T 2 0 1 2

    year 2011. Exports from Brazil and Argentina increased

    their participation in the Asian market in the period, with a

    negative impact on U.S. exports, the main source of grain

    moving through the Panama Canal.

    Coal shipments remained stable at 13.9 long tons. The

    main coal routes were from: Colombia to Chile and from

    the U.S. Gulf of Mexico to Mexico, Chile, and Asia. Iron ore

    from Brazil and Venezuela to China also remained at with

    about 4 million long tons, while the route from the U.S. Gulf

    of Mexico to China doubled to 1 million long tons. Strong

    shipments of coke were also reported from the U.S. Gulf of

    Mexico to Asia, as well as iron metal on the same route in

    the opposite direction.

    Vehicle Carriers SegmentThe main trafc indicators exceeded last scal years

    gures. Vehicle carrier transits totaled 669 at the closing of

    scal year 2012, 5.7 percent over scal year 2011. PC/UMS

    tonnage registered 37.7 million, an 8.6 percent increase

    from the previous year. Consequently, toll revenues

    totaled B/.153.9 million, a 12.8 percent increase over scal

    year 2011 for this segment.

    The demand for maritime vehicle transportation rose

    during the rst half of scal year 2012, due to the increase

    in global car production and the restoration of vehicle

    inventories in Asia. In addition, vehicle sales in the United

    States and inventory restocking of Japanese and Korean

    brands, which had slipped signicantly since the Japanese

    earthquake, combined to spur the vehicle car carrier

    demand.

    For the second half of the scal year, the high demand

    for maritime vehicle transportation, alongside intense

    competition between South Korea and Japan for world

    leadership of vehicle production and sales, were important

    elements towards global recovery. These optimistic

    projections were based on a stronger than expected

    recovery in vehicle demand in the United States. As aresult, segment trafc remained dynamic, along with the

    rise of vehicle ows in the main maritime trade routes.

    Passenger Vessels SegmentAt the end of the 2011-2012 season, passenger vessel trafc

    experienced a downward trend. The decline of this trafc

    through the Panama Canal was mainly due to a strategic

    decision by one of the major cruise lines to redeploy some

    ships to Europe and Asia, in response to demand in these

    destinations.

    Passenger vessel transits were 211 at the end of scal yea

    2012, a 6.2 percent decrease from the previous year

    Furthermore, the vessels passenger capacity decreased

    to 248,674. In contrast, vessel tonnage was 1.5 million, a

    0.3 percent increase over the 2010-2011 cruise season

    as a result of an increase in transits of vessels with beams

    under 80 feet.

    17

  • 8/11/2019 Panama Canal Annual Report 2012

    20/112

    A N N U A L R E P O R T 2 0 1 2

    Toll revenues totaled B/.39.8 million, a 13.7 percent decline from the

    B/.46.1 million in scal year 2011. The revenues for billed passenger

    capacity represented 83.7 percent of the amount collected during

    scal year 2012.

    Throughout this season, ships of the major worldwide cruise lines

    fullled their navigational itineraries through the Panama Canal. In

    turn, smaller vessels also contributed to the Canal trafc statistics;

    in general terms, the itineraries of these ships are of short duration

    between the Caribbean islands and the east and west coasts of

    Central America. It is worth mentioning that as in previous seasons,

    the Canal destination maintained its tourist appeal, attracting

    vessels with itineraries that included passage through Panama on

    their maiden voyages.

    Transit Operations PerformanceIt has been mentioned that the Panama Canal registered 333.7

    million PC/UMS tons in scal year 2012, 11.6 million tons more than

    for scal year 2011. This was accomplished at an operating cost

    of B/.1.22 per ton, less than the established goal of B/.1.29. This is

    the result of the improved quality service rendered to our clients

    in terms of Canal waters time, the appropriate management of

    resources, and the effort and dedication of the more than 10,000

    Panama Canal employees.

    Tolls Revenues and OtherMaritime ServicesTolls and other maritime services totaled B/.2,248.9

    million, 5.5 percent higher than the revenues

    recorded for scal year 2011, which were

    B/.2,130.6 million.

    Revenues for other maritime services (OMS)

    amounted to B/. 395.4 million, 1.3 percent less

    than scal year 2011 (B/.400.72 million), as a result

    of less utilization of the transit reservation system.

    322.1333.7

    300.8350325300275250225200

    1751501251007550250

    Vessel Tonage(in millions of PC/UMS)

    2010

    2011

    2012

    18

  • 8/11/2019 Panama Canal Annual Report 2012

    21/112

    A N N U A L R E P O R T 2 0 1 2

    Transit of Oceangoing VesselsA total of 12,862 oceangoing transits were registered (not including

    small vessels), a reduction of 126 vessels or 1 percent compared

    to scal year 2011 (12,988 transits). From this amount, 8,479 transits

    were super-size vessels with a beam equal to or more than 91

    feet, 315 more than the previous scal year (3.9 percent). Similarly,

    4,383 were regular-size vessels with a beam of less than 91 feet,

    a reduction of 441 transits (9.1 percent) compared to scal year

    2011. Small vessels had a slight drop of 14 transits (from 1,696 to

    1,682 transits) or 0.8 percent less compared to scal year 2011.

    Transits of Panamax VesselsIn scal year 2012, a total of 7,241 transits of Panamax vessels were

    recorded (beam equal to or more than 100 feet), an increase of

    323 transits (4.7 percent) compared to scal year 2011 (6,918).This

    increase is mainly perceived in the container ships (+147), dry bulk

    (+88), and tankers (+56) segments. Panamax vessels represented

    56.3 percent of oceangoing transits, compared to

    53.3 percent in scal year 2011. Similarly, Panamax

    vessels with overall length equal or more than 900

    feet totaled 1,658, an increase of 114 (7.4 percent

    when compared to scal year 2011 (1,544). These

    vessels represent 12.9 percent of oceangoing

    transits, compared to 11.9 percentof the previous

    scal year. Panamax vessels, especially those with

    overall length more than 900 feet, require more

    time and resources. Despite the increase in the

    complexity of the operations this represents, there

    was an improvement in the service level provided

    to our customers.

    9,000

    8,000

    7,000

    6,000

    5,000

    4,000

    3,000

    2,000

    1,000

    0

    Panamax Vessel Transits

    6,918 7,2416,231

    2010

    2011

    2012

    Oceangoing Transits

    12,989 12,86212,591

    16,000

    14,000

    12,000

    10,000

    8,000

    6,000

    4,000

    2,000

    0 2

    010

    2011

    2012

    19

  • 8/11/2019 Panama Canal Annual Report 2012

    22/112

    A N N U A L R E P O R T 2 0 1 2

    Service Rendering PerformanceThe service level rendered, measured based on PC/UMS

    tons that transited within the time expectations for Canal

    Waters Time (CWT), was 86.28 percent, higher than the

    results for scal year 2011 (85.2 percent). This reduction is

    mainly due to improved processes and, in a lesser extent,

    to a reduction in the average arrival of vessels and a

    reduced backlog, which allowed accomplishing transits in

    less time than programmed.

    Canal Waters Time and InTransit TimeCanal Waters Time (CWT), the time elapsed since a vessel

    arrives at Canal waters, averaged 25.66 hours, a reduction

    of 4.0 percent compared to scal year 2011 (26.74 hours).

    This is the result of an improvement in our transit processes,

    which allowed us to reduce both waiting and transit times.

    The average CWT for booked vessels was 14.97 hours,

    while for non-booked vessels this average was 34.49 hours.

    In scal year 2011 these results were 15.20 and 39.02 hours,

    respectively.

    The average In Transit Time (ITT), the time elapsed since the

    ship arrives to the rst lock until its departure from the last

    lock, recorded 10.70 hours by the end of scal year 2012, a

    26.81

    Canal Water Time (CWT)Monthly Average and CumulativeAverage

    36.0

    30.0

    24.0

    18.0

    12.0

    CWT Monthly 2012

    Oct. Nov. Dic. Jan . Feb. Mar. Apr. May. Jun. Jul. Ago. Sep.CWT Cumulative2012

    Hours

    23.72

    27.0928.48 28.0627.32

    28.26

    25.6625.9326.20

    25.63 25.98

    26.7426.7927.2728.88

    29.7729.1330.21

    32.00

    33.87

    26.41

    26.7027.40

    CWT Monthly 2011 CWT Cumulative2011Percentaje of CP/SUAB Tonswith Good Service Level95%

    90%

    85%

    80%

    75%

    70%Oct. Nov. Dic. Jan. Feb. Mar. Apr. May. Jun. Jul. Ago. Sep.

    Percentage

    79.08%

    80.60%81.39% 82.19%

    83.50%

    84.85%85.73% 85.68%

    85.20%84.85%85.10%84.38%83.91%

    84.47%

    80.78%83.51%

    82.70%

    85.56%

    Accumulated 2012Accumulated 2011

    81.09%

    81.36%

    82.30%

    82.74%

    86.28%

    89.78%

    20

  • 8/11/2019 Panama Canal Annual Report 2012

    23/112

    A N N U A L R E P O R T 2 0 1 2

    1.33 percent increase over scal year 2011 results of 10.56

    hours.

    This cumulative average was slightly affected by theincreased number of larger ships (Super and Panamax),

    especially those with overall length of more than 900 feet,

    in addition to the programmed maintenance performed

    at the locks, which required closing lanes in Gatun and

    Miraores locks.

    Customer SatisfactionAt the end of this scal year, the customer satisfaction

    index was registered at 97.82 percent, 1.22 percent above

    last scal year results (96.6 percent). Several efforts were

    made to improve customer service and promote a change

    in our organizational culture in customer satisfaction

    matters.

    We are conducting a survey among the Ship Masters

    after each transit to gather their impressions on the service

    received as well as their suggestions for improvement. We

    have also improved the process for handling complaints

    resulting in a more expedited response.

    Maintenance ManagementPerformanceAs part of the Expansion Program, 98 deliverables (section

    inside the navigational channel) were completed in the

    Culebra Cut. This represents an execution of 140 percent

    compared to the programmed goal. This success was

    the result of a combined strategy of working concurren

    In Transit Time (ITT) MonthlyAverage and Cumulative Average

    12.0

    11.5

    11.0

    10.5

    10.0

    9.5

    9.0

    8.5Oct. Nov. Dic. Ene. Feb. Mar. Abr. May. Jun. Jul. Ago. Sep.

    Hours

    10.71

    11.49

    11.05 10.95

    10.7810.72 10.68 10.71

    10.5610.5610.5210.5810.61

    10.68

    11.23

    11.25

    11.41

    10.69 10.69

    ITT Cumulative 2012ITT Monthly 2011ITT Monthly 2012ITT Cumulative 2011

    10.8310.90

    10.71

    11.13

    10.70

    Oct-10 Nov-10 Dic-10 Ene-11 Feb-11 Mar-11 Abr-11 May-11 Jun-11 Jul-11 Agt.11 Sept.11

    Dredging Operations ProgressReport (Expansion Works) FY2012

    108.6%

    127.1%

    150%

    140%

    130%

    120%

    110%

    100%

    90%

    80%

    70%

    60%

    50%

    40%

    30%

    20%

    10%

    0%

    18.6%

    8.6%

    22.9%

    38.6%

    42.9%

    54.3%

    124.6%

    64.3%

    77.1%

    %

    o f P r o g r e s s t o D a t e a n d A n n u a l

    100.0%

    118.2%

    84.2%

    100.0% 100.0%

    111.8%

    104.7% 105.9%

    114.3%

    Goal FY2012Percentage of Progress Annual Percentage of Progress to Date

    91.4%

    140.0%

    134.8%140.0%

    Deliverables

    18

    16

    14

    12

    10

    8

    6

    4

    2

    0

    21

  • 8/11/2019 Panama Canal Annual Report 2012

    24/112

    A N N U A L R E P O R T 2 0 1 2

    drilling and blasting and dredging activities, followed by shoal

    removal (small areas above design level) to nish the deliverables.

    The inclusion of dredge Quibin I and the utilization of chartered

    dredge Cornelius in the removal of shoals helped to achieve these

    results.

    The Dredging Division excavated 1.189 million cubic meters, of an

    estimated total of one million cubic meters 118.9 percent of the

    expected results, as part of the works under the Modernization

    Program.

    This outcome was due to the high production of chartered dredge

    Cornelius, and the work of dredge Rialto M. Christensen, which

    was working at the limits of the Expansion Program and was able

    to remove material for both projects.

    In September 2012 the new backhoe dredge was baptized with

    the name of Alberto Alemn Zubieta. This ceremony was held at

    NMC in Niew Lekkerland Shipyard, Holland, and it is estimated that

    it will be arriving at the port of Cristobal in Panama on January

    2013. Initial tests will begin in February to formally put it into service

    in late March 2013.

    Preparation for the Operation of theExpanded CanalSeventy three pilots (104.3 percent) and 28 tug captains (127.3

    percent), which together represent 109.78 percent out of

    the established goal of 92 employees, have been trained in

    maneuvering Post-panamax vessels at the SIDMAR Simulation

    Center. As part of the preparation for this training, negotiation

    was undertaken with the Pilots Union and a variety of tests were

    placed in the simulator with the different types of vessels, which

    were validated for the pilot and tug captain training.

    Specic Tasks ProgramA high level committee was created to identify

    and follow up on specic tasks required to operate

    the expanded canal.

    Some of the tasks completed by the end of scal

    year 2012 include establishing restrictions and

    requirements for vessels to transit through the

    new set of locks, based on the results of lockage

    tests without locomotives and comments from

    pilot unions and tug ofcers. The risk analysis for

    the operation of the expanded canal was also

    completed and presented to the Advisory Board,

    and we continue following up on the identied

    mitigation measures.

    A contract is being prepared for the extraction of

    submerged logs from Gatun Lake to expand the

    anchorage area, which will be reduced by the

    crossing of the navigational channel to the new

    Atlantic locks.

    Human resources needs and structures

    requirements (docks, workers waiting areas,

    landings, equipment, and power plants) are

    being analyzed to handle the operations for the

    expanded canal and to meet maintenance and

    fuel supply requirements for oating equipment.

    22

  • 8/11/2019 Panama Canal Annual Report 2012

    25/112

    A N N U A L R E P O R T 2 0 1 2

    On the other hand, we are analyzing the infrastructure required

    for the Maritime Trafc Control Center as well as transit processes

    in order to improve the maritime services management, based on

    a Service Oriented Architecture (SOA). We are also evaluating the

    implementation of new transit support technologies.

    With regards to dredging, we are developing a plan for the

    day to day maintenance and improvement of the navigational

    channels, and to tackle the sedimentation accumulated during

    the expansion program.

    Regarding safety, we are assessing the capacity required to respond

    to emergencies, considering the new hydrocarbons that will transit

    through the Panama Canal and the requirements to be ready for

    a Tier-2 in the new facilities. We are also analyzing the safety tariffs

    for the new Post-Panamax vessels, based on the increasing spill risk

    factor, and a new tariff required for hazard materials. We are also

    working in the changes required to provide re protection remen

    response for facilities, equipment and systems, and as identifying

    the resources needed to respond to new hazardous materials

    (LNG).

    Capacity Model for the Expanded

    CanalWe continue developing a capacity model for the presentand the expanded Canal through a contract with Paragon

    Consultora Ltda., from Brazil. Phase I of the model was completed

    and it included the development of a scenario manager and a

    scheduling model for the operation and vessel scheduling based

    on information from the demand model for the

    current, as well as for the expanded Canal.

    This model will allow analyzing the Canals

    operational capacity in different demand

    scenarios, the infrastructure conguration and

    navigation rules for both the present, as well as fo

    the expanded Canal.

    Beginning September, 2012, we proceeded with

    Phase II of the project, which will include thesimulation of tugs, launches, line handlers, lane

    outages, and full convoy scheduling mode (a

    ships going in one direction and in the opposite

    direction the following day).

    23

  • 8/11/2019 Panama Canal Annual Report 2012

    26/112

    A N N U A L R E P O R T 2 0 1 2

    Expansion

  • 8/11/2019 Panama Canal Annual Report 2012

    27/112

    A N N U A L R E P O R T 2 0 1 2

    Five Years LaterSkills, knowledge, challenges, commitment, and achievements are

    just some of the many day-to-day factors that make the Panama

    Canal Expansion Program possible. The teamwork betweencontractors and ACP workers is a key element that together

    with the design, construction, excavation, dredging, quality

    assurance, good environmental management, documentation,

    and occupational safety have made it possible to get to this point

    meeting with world-class quality standards in all of the Programs

    work fronts.

    In its fth year, the Expansion Program, with over 12,000 active

    employees working day and night shifts, reached a 47

    percent progress rate at the end of scal year 2012. Signicantaccomplishments that were achieved during this year include

    awarding 96 percent of the contracts; removing 42 of the 49

    million cubic meters through dry excavation for the Pacic Access

    Channel; and dredging 46 out of 53 million cubic meters from the

    navigational channels. With regards to the combined excavated

    and dredged total volume of 33 million cubic meters of the

    projected 47.5 in the Pacic and Atlantic sides for the construction

    of the new set of locks; structural concrete placements added

    up to 1.2 of the 4.2 million cubic meters; and 115 tons out of the

    foreseen 197 tons of rebar have been received.

    Post-Panamax LocksThis component comprises the construction of two locks complexes,

    one on the Pacic and another on the Atlantic side; each with

    three levels and three water saving basins. This

    project has a 33 percent progress rate. Grupo

    Unidos por el Canal S.A. (GUPCSA), the consortium

    in charge of this activity, has focused its efforts on

    fabricating electromechanical components such

    as valves and gates; conducting excavation and

    dredging activities in the areas where the locks

    are built; and, just as important, developing and

    obtaining approval for concrete mix designs and

    placement. During this period, the contracto

    met all design requirements for the locks

    gates, and valves, and obtained the necessary

    certications to start fabrication. This enabled

    GUPCSAs subcontractors Hyundai Samho

    Heavy Industries Company Ltd. in South Korea

    and Cimolai S.p.A. in Italy to proceed with the

    fabrication of lock valves and gates, respectively

    Hyundai for instance, has manufactured 47 valve

    bodies and conducted factory acceptance

    tests on 34 culvert valves; while Cimolai makes

    progress welding and assembling blocks fo

    the 16 gates now in process. These fabrication

    activities are monitored by GUPCSAs resident

    inspection services subcontractor SGS S.A. and

    by ACPs Program Administration consultant

    CH2M Hill Panam S. de R.L., which carries out this

    25

  • 8/11/2019 Panama Canal Annual Report 2012

    28/112

    A N N U A L R E P O R T 2 0 1 2

    task through its subcontractor, NDE Associates Inc. Meanwhile,

    Hyundai subcontracted Bosch-Rexroth AG to fabricate hydraulic

    cylinders for the valves.

    Another major effort by GUPCSA is the excavation and dredging

    activity. On the Pacic sector, the contractor reported the

    removal of a cumulative volume of approximately 15.9 million

    cubic meters from the area for the three lock chambers; lock

    heads 1, 3, and 4; the middle and lower water saving basins;

    the north wing walls and approach channel; and the dams.

    The cumulative volume removed from the main excavation on

    the Atlantic sector is about 14.8 million cubic meters and the

    cumulative volume reported for the Atlantic entrance channel

    is nearly 2.3 million. These activities are conducted at the locks

    footprint where they are about to conclude- the lower and

    middle water saving basins and at the Atlantic entrance channel.

    No doubt one of the contractors main tasks has been pouring

    structural concrete, with a total of 580,000 cubic meters poured

    on the Pacic site. By the end of the scal year GUPCSA had

    submitted and ACP approved two new structural marine concrete

    mixes. For the Atlantic sector, this activity reported a cumulative

    volume of about 652,000 cubic meters. The placement of lean

    concrete as foundation treatment on the Atlantic site is nearly

    complete, with only small sections remaining.

    As part of the measures to improve its performance,

    GUPCSA hired the Consorcio Borinquen S.A.to

    build three dams and excavate the north Pacic

    approach channel. This consortium completed

    the excavation for the rst dam to the west as well

    as the mapping; and cleaning of its foundation.

    It also started the treatment of the exposed

    foundation and applied dental concrete and

    backll, based on its geological features. On

    the second dam to the east, the consortium is

    conducting dewatering activities and remove

    overburden material to reach the design

    excavation level for the foundation.

    Another important task is the transportation of

    aggregates from the Pacic to supply the Atlantic

    site, where it is processed to obtain the ne

    aggregates required to prepare concrete. By the

    end of the scal year, the contractor has mobilized

    a cumulative volume of 2.8 million cubic meters.

    Likewise, the reinforcing steel supplier contracted

    by GUPCSA, Mexican company ArcelorMittal,

    has delivered a total of approximately 67,000 tons

    to the Pacic site and about 48,000 to the Atlantic

    site.

    The quality assurance, environmental

    management, and occupational safety efforts

    Design and Construction of theThird Set of LocksDredging and Excavation Volumes

    Actual vs Programmed through September 2012

    Programmed Accumulated

    50

    45

    40

    35

    30

    25

    20

    15

    10

    5

    0

    AccumulatedVolume(Mm3)

    Jan.

    10

    Mar.10

    May.10

    Jul.10

    Sep.

    10

    Nov.10

    Jan.

    11

    Mar.11

    May.11

    Jul.11

    Sep.

    11

    Nov.11

    Jan.

    12

    Mar.12

    May.12

    Jul.12

    Sep.

    12

    Nov.12

    Jan.

    13

    Mar.13

    May.13

    Jul.13

    Sep.

    13

    Nov.13

    Jan.1

    4

    Mar.14

    May.14

    Jul.14

    33 Mm3

    Actual Accumulated

    26

  • 8/11/2019 Panama Canal Annual Report 2012

    29/112

    A N N U A L R E P O R T 2 0 1 2

    have continued without interruptions by means of

    audits, inspections, regular meetings, and a constant

    presence on both the Pacic and Atlantic construction

    sites. In order to keep Expansion Programs historical

    documentation at the forefront of technology, this year

    a remote control axial recording system was used while

    ying over construction worksites to record progress on

    high-denition video as if viewed from the helicopter

    pilots viewpoint. This recording system was fabricated

    by Canal specialists, who put their resourcefulness

    and determination to test in order to manufacture the

    device. The Panama Canal has held high level meetings

    with senior management of the companies form the

    consortium responsible for this project to follow up on

    its performance, always stressing the importance of

    complying with contract requirements and encouraging

    the contractor to take any and all appropriate corrective

    actions. GUPCSA submitted a schedule that estimates

    the contract completion date in April 2015 (six months

    after the contractual completion date), and they are

    working to reduce delays.

    Pacic Access ChannelA dry excavation is underway to connect the Pacic Locks

    with the Culebra Cut through a new 6.1 km-long access

    channel. Three of the four phases to accomplish this

    work have been completed successfully; and the fourth

    phase reected a 67 percent progress rate at the end o

    scal year 2012. As part of this last phase, several majo

    structures have been built, including a 1.8 km-long cellula

    cofferdam and two cut-off walls, which consist of a 500

    meter-long cement-bentonite structure and a 144 meter

    long jet grouting wall, to reduce potential see page from

    Gatun and Miraores Lakes, respectively. The purpose o

    these structures is to allow dry excavation works for the

    channel and the construction of a dam.

    During this scal year, the contractor responsible fo

    these works, the consortium ICA-FCC-Meco, comprised

    27

    Pacifc Access Channel (CAP4)Excavation Volumes Actual vs Programmed throughSeptember 2012

    28

    26

    24

    22

    20

    18

    16

    14

    12

    10

    8

    6

    4

    2

    0

    AccumulatedVolume(Mm3)

    A

    pr.10

    May.

    10

    Ju

    n.

    10

    J

    ul.10

    Ago.

    10

    Sep.

    10

    O

    ct.10

    Nov.

    10

    D

    ic.

    10

    Jan.

    11

    Feb.

    11

    M

    ar.11

    A

    pr.11

    May.

    11

    Ju

    n.

    11

    J

    ul.11

    Ago.

    11

    Sep.

    11

    O

    ct.11

    N

    ov.11

    D

    ic.

    11

    Jan.

    12

    Feb.

    12

    M

    ar.12

    A

    pr.12

    May.

    12

    Ju

    n.

    12

    J

    ul.12

    A

    go.1

    2

    Sep.

    12

    O

    ct.12

    Nov.

    12

    D

    ic.

    12

    Jan.

    13

    Feb.

    13

    M

    ar.13

    A

    pr.13

    May.

    13

    Programmed Accumulated Actual Accumulated

    19.3 Mm3

  • 8/11/2019 Panama Canal Annual Report 2012

    30/112

    A N N U A L R E P O R T 2 0 1 2

    of Ingenieros Civiles Asociados S.A. de C.V. (ICA), Fomentos de

    Construcciones y Contratas S.A. (FCC), and Constructora Meco

    S.A., removed a total of 7.8 million cubic meters of unclassied

    material, for a cumulative volume of 19.3 million from the start of

    the project. This volume represents a 74 percent progress rate.

    The material was excavated from the access channel and the

    footprint of the rst dam to the east.

    The contractors most demanding task has been the construction

    of the previously mentioned dam. The contractor is focused

    on dewatering the area and the underground water level was

    lowered in several areas of the dam footprint preparing the

    foundation; placing rock ll in the inboard dam shell; placing

    backll concrete in areas requiring leveling; and the stockpiling

    and processing of rock from the projects excavations to produce

    lters, chimney drains, and blanket lters for the dam, among

    others. Further dam-related tasks included the construction of a 3

    meter-deep concrete cut-off wall at the dams axis, of which 1,100

    square meters have been completed, and grout-jetting works to

    create a curtain below the dam to prevent seepage.

    On the other hand, construction works have concluded for the

    support operations building located west of Pedro Miguel Locks,

    as well as the construction of additional drainage systems and the

    paving of the existing ones west of the access channel. These

    contracts lie on the main excavations footprint, making their

    execution relevant to the project.

    Navigational ChannelImprovementsWith the purpose of providing Post-Panamax

    vessels the necessary draft to transit safely, another

    component was included in the Expansion

    Program, which encompasses the widening and

    deepening of the existing navigational channels

    in Gatun Lake and in the Pacic and Atlantic

    entrances, as well as the deepening of CulebraCut. The work in Gatun Lake and Culebra Cut

    includes dredging operations to remove 26.5

    cubic meters of material and 8.7 million from

    the Pacic entrance; whereas about 17.9 million

    cubic meters must be dredged and excavated

    for the Atlantic entrance.

    Gatun Lake and Culebra CutThese works have been assigned to the Panama

    Canals Dredging Division and contractors, who

    have joined in the effort to reach the design depth

    required to meet the Programs objectives. The

    ACP has removed nearly 12.5 million cubic meters

    from the beginning of the project with cutter-

    suction dredges Mindi and Quibian I, dipper

    dredge Rialto M. Christensen, and the chartered

    backhoe dredge Cornelius. These works have

    28

  • 8/11/2019 Panama Canal Annual Report 2012

    31/112

    A N N U A L R E P O R T 2 0 1 2

    resulted in the completion of the Culebra and Chagres

    Crossing reaches, both located in the Culebra Cut. On

    the other hand, in March 2012, Dredging International de

    Panam S.A. concluded its contract to dredge Gatun

    Lakes northern reaches according to schedule.

    This work included dredging the Bohio, Buena Vista,

    Gatun, Pea Blanca and Balsa reaches, where a

    cumulative volume of 4.0 million cubic meters were

    removed with cutter-suction dredge DArtagnan.

    In the meantime, Jan De Nul n.v.continues with the

    dredging operations under its contract at the northern

    entrance of the Pacic access channel, where abou

    3.2 million cubic meters of material have been removed

    In this way, the Panama Canals and its contractor

    combined production reached a cumulative volume o

    20.2 million cumulative cubic metersof removed materia

    volume, a 78 per cent progress rate by the end of sca

    year 2012.

    Pacic Entrance

    Close to 300,000 cubic meters are left to be dredged a

    the sea entrance on the Pacic side. Dredging operation

    Gatun Lake Deepeningand Widening and Culebra CutDeepeningDredging and Dry Excavation Volumes Actual vs Programmed through September 2012

    VolumeAccumula(Mm3)

    Fe

    b.

    07

    May.07

    Ago.

    07

    Nov.07

    Fe

    b.

    08

    May.08

    Ago.

    08

    Nov.08

    Fe

    b.

    09

    May.09

    Ago.

    09

    Nov.09

    Fe

    b.1

    0

    May.10

    Ago.

    10

    Nov.10

    Fe

    b.

    11

    May.11

    Ago.

    11

    Nov.11

    Fe

    b.

    12

    May.12

    Ago.

    12

    Nov.12

    Fe

    b.

    13

    May.13

    Ago.

    13

    Nov.13

    Programmed Accumulated Actual Accumulated

    20.2 Mm3

    28

    26

    24

    22

    20

    18

    16

    14

    12

    10

    8

    6

    4

    2

    0

    Pacifc Entrance Deepeningand WideningDredging Volume - Actual vs Programmed throughSeptember 2012

    8.4 Mm3

    AccumulatedVolume(Mm3)

    Ago.

    08

    Oct.08

    Dic.

    08

    Feb.

    09

    Apr.09

    Jun.

    09

    Ago.

    09

    Oct.09

    Dic.

    09

    Feb.

    10

    Apr.10

    Jun.

    10

    Ago.

    10

    Oct.10

    Dic.

    10

    Feb.

    11

    Apr.11

    Jun.

    11

    Ago.

    11

    Oct.11

    Dic.

    11

    Feb.

    12

    Abr.12

    Jun.

    12

    Ago.

    12

    Oct.12

    Dic.

    12

    10

    9

    8

    7

    6

    5

    4

    3

    2

    1

    0

    Actual AccumulatedProgrammed Accumulated

    29

  • 8/11/2019 Panama Canal Annual Report 2012

    32/112

    A N N U A L R E P O R T 2 0 1 2

    by Dredging International de Panam S.A., covered around 11

    km of the navigational channels;1.8 km north of the Bridge of

    the Americas; and the rst kilometer of the new access channel

    to the third set of locks. All dredging works were performed with

    dredge DArtagnan, upon completion of its assignment in Gatun

    Lakes northern reaches. The project has reached a 95 percent

    progress rate with the conclusion of the widening and deepening

    of control sector 7, that of sector 2A at design depth, plus the

    extensive completion of sector 6, and the beginning of dredging

    activities in sector 4.

    Atlantic EntranceJan De Nul n.v., a Belgian company in charge of dredgingoperations at the sea entrance on the Atlantic side, ended

    operations in control sectors 3A, 4A, 2B, 3B, and 5B with support

    from the Filippo Brunelleschi, Charles Darwin and Al Idrisi hopper

    dredges. All sectors were delivered prior to established contract

    date on the projects schedule. Signicant progress has also

    been made in the removal of the remaining volume in sector 3C.

    This project registered a cumulative volume of nearly 17.4 million

    cubic meters of removed material, for a 98 percent progress rate.

    Raising Gatun LakesMaximum Operational LevelWith a view to guarantee an adequate water

    supply for human consumption, as well as for the

    expanded waterway, this Program component

    consists in raising Gatun Lakes maximum

    operational level 45 centimeters. The works

    required to accomplish this goal continued

    during this period and increased the projects

    progress rate to 9 percent.

    Atlantic Entrance Deepeningand WideningDredging and Dry Excavation Volumes -

    Actual vs Programmed through September 2012

    Fe

    b.

    10

    Abr.10

    Jun.

    10

    Ago.1

    0

    Oct.10

    Dic.

    10

    Fe

    b.1

    1

    Abr.11

    Jun.

    11

    Ago.

    11

    Oct.11

    Dic.

    11

    Fe

    b.

    12

    Abr.12

    Jun.

    12

    Ago.

    12

    Oct.12

    Dic.

    12

    Fe

    b.

    13

    Abr.13

    20

    18

    16

    14

    12

    10

    8

    6

    4

    2

    0

    AccumulatedVolume(m3)

    Actual Accumulated

    17.4 Mm3

    Programmed Accumulated

    30

  • 8/11/2019 Panama Canal Annual Report 2012

    33/112

    A N N U A L R E P O R T 2 0 1 2

    One of the most signicant activities under this project, which

    is performed by the Panama Canal,focused on extending the

    Gatun spillway gates, completing 13 of the 14 gates. Review

    and nal adjustment works were also completed on two new

    gates fabricated by the ACP with the required dimensions. The

    spillway has 14 gates, but the project includes a total of 16 so

    as to have 2 additional gates available for maintenance and

    emergency purposes. Additionally, raising Gatun Lakes level

    requires other modications to structures in Pedro Miguel Locks

    as well as Gatuns upper chambers. For this reason, proposals

    for the acquisition of 32 submersible hydraulic cylinders are

    being evaluated; designs have been made to modify other

    components such as the conductor-slot drainage system, miter

    gates, and yoke seal, among others; and specications for new

    water level sensors are being prepared.

    Administration and FinancingThe program management effort continued as planned with the

    support of international experts in various areas. For instance,

    CH2M Hill Panama R. de S.L., the program management services

    consultant, worked jointly with the ACP on all construction aspects

    for the new locks. Additionally, they continued providing supervision

    and inspection services in South Korea and Italy

    during the fabrication of the lock valves and

    gates, respectively. With regard to legal advisory

    services for international contracts, Mayer Brown

    LLP provided guidance on several topics related

    to the locks contract. Other contractors, such as

    Shearman & Sterling, Willis Limited, Consorcio Post

    Panamax, and URS Holding Inc., also provided

    the respective project management support on

    nancial legal issues; risk management; technica

    consultancy on geotechnical aspects, dams

    and concrete mixes; as well as dam construction

    The ve credit facility lenders that provide

    part of the funds required to execute the

    Expansion Program continued receiving nancial

    operational, environmental, and progress reports

    as established in the common terms agreement

    Meanwhile, the ACP complied with its paymen

    commitments and debt service fees in Novembe

    2011 and May 2012, respectively. Pursuan

    to the agreement, in February 2012 a visit to

    Expansion Program sites by credit facility lenders

    31

  • 8/11/2019 Panama Canal Annual Report 2012

    34/112

    A N N U A L R E P O R T 2 0 1 2

    representatives was prepared and coordinated. In June

    2012, the ACP requested a B/.100 million disbursement

    from the Interamerican Development Bank.

    Projects Occupational SafetyWith the responsibility shouldered from the beginning,

    for occupational safety management sets the norm to

    keep work areas free of accidents, injuries, and diseases.

    Monitoring contractor activities in the implementation of

    safety and hygiene measures at work sitessuch as the

    use of personal protection equipment; fall protection;

    unhealthy (noise, dust) work conditions control; and

    ergonomic risk evaluations, among others, is the constant

    of these efforts. This task also includes reviewing safe

    work procedures and plans, as well as specic audits.

    To support this commitment, and as a corporate initiative,

    the Program management consultant launched the

    Dont Walk By campaign to raise workers awareness

    regarding the need not to ignore or walk by an evident

    risk without correcting or reporting it. On the other

    hand, in an effort to draw attention to the importance

    of occupational safety among ACP and contractor

    employees, the second annual seminar under the slogan

    Excellency in Safety Management at the Executive

    Level was carried out. Another effort of the occupational

    safety projects team was a workshop to promote

    accident-prevention innovations. As a result from this

    event, new initiatives were taken such as the visible

    participation of senior management in health and safety

    activities, and regular workshops for ACP employees

    and contractors to promote benchmarking between

    ACP and contractor personnel on the subject. The ACP

    continues to permanently stress the consideration that

    should be given to this component in order to preserve

    the health and life of each and every worker playing a

    part in the Programsexecution.

    The Panama Canal Expansion Program received Spains

    Consejo General de Relaciones Industriales y Licenciados

    en Ciencias del Trabajo Prever 2011 Award under their

    international category; an award that highlights labor

    risk-prevention initiatives.

    Environmental ManagementRelentlesswould be the appropriate term to describe

    the effort that goes into environmental management.

    Follow-up on the mitigation measures included in the

    environmental impact study and the resolution issued

    32

  • 8/11/2019 Panama Canal Annual Report 2012

    35/112

    A N N U A L R E P O R T 2 0 1 2

    by the National Environmental Authority (ANAM for its

    acronym in Spanish) which approved it, entails several

    components, such as monitoring water and air quality,

    and noise; managing solid wastes and hazardous

    materials in work areas; working conditions; erosion

    control; siltation migration; secondary containments for

    fuel and lubricant storage; wildlife care and protection;

    and ecological compensation, among others.

    The reforestation program is executed in coordination

    with ANAM and the Authority for Aquatic Resources

    (ARAP for its acronym in Spanish) in the provinces of

    Colon, Panama, Cocle, Herrera,and Chiriqui. At the end

    of this scal year, the mangrove of the Chiriqui Viejo River

    was included in the reforested areas, which amounted

    to 565 planted hectares, 515 hectares of forest and 50

    hectares of mangrove. All Expansion Program plantations

    have been established and are in their maintenance

    phase, which requires a 4 year period and includes yearly

    cleanups, re protection, and replanting; among many

    other activities. A new contract was awarded in February

    2012 for the reforestation of 61 hectares of land within

    the Tapagra hydrological protection zone, in Chepo,

    Panama, with a reported 45 percent progress by the end

    of the period. As it is generally known, the environmental

    effort also involves rescuing and relocating wild life from

    areas where the vegetation has been removed during

    the waterways expansion works.

    The independent consultant for this component

    Environmental Resources Management Panam S.A.

    made two scheduled semi-annual visits to project sites

    and reforestation areas; and prepared the respective

    reports on the verication of the implementation, and the

    effectiveness of mitigation and social and environmenta

    follow-up measures. These reports render account to the

    credit facility lenders and ANAM.

    Paleontological andArchaeological StudiesAs a result of the required excavation and dredging

    activities during the Programs execution, some areas and

    part shave become exposed that would not be visibleotherwise. This allows for performing paleontologica

    rescues, and evaluating artifacts and other identied

    cultural remains.

    The required paleontological evaluations are a service

    provided by personnel from the Smithsonian Institute fo

    Tropical Research, who inspected throughout the yea

    33

  • 8/11/2019 Panama Canal Annual Report 2012

    36/112

    A N N U A L R E P O R T 2 0 1 2

    a number of areas on the Atlantic and Pacic sectors, and in

    the Culebra Cut.For example, they observed the stratigraphy

    of sediments in the exposed rock and found a sh and mollusk

    deposit where excavations for the locks are underway on the

    Atlantic sector. Additionally, marine fossils have been recovered

    at different locations, and a Culebra formation rock layer full

    of organic matter found in a particular area in the excavations

    for the construction of the Pacic locks. This area also had crab

    remains and fossilized leaves, a rare nding that requires specic

    research. A layer of freshwater mollusks and bivalve fossils

    was found at Culebra Cut, in a Cucaracha formation. This is a

    major scientic discovery, as it will help reconstruct the isthmus

    environmental conditions during the Middle Miocene Era. Other

    discoveries in the Cut included mammal and reptile fossils found

    in the area of Lirio; teeth and bones of mammals were recovered

    at Hodges; and turtle shells and crocodile teeth were found in the

    area of the Centennial Bridge. In addition to recovering remains,

    scientists also analyze, evaluate, categorize, and document

    each nding for their preservation.

    Archaeological inspections were also conducted in different

    Program areas, albeit less than before, given that at most

    work fronts dredging and excavation design levels have

    been reached. A metallic remains deposit with railroad track

    fragments, iron wheels with varying diameters, and an iron chain

    were found in the construction site for the rst dam to the east

    of the Borinquen dam, among others. Other

    ndings took place in one of the Pacic locks

    projects disposal sites, where there were four

    World War II concrete bunkers; a number of mid-

    twentieth century bottles; a 1912-1913 stone-lined

    trench; an aluminum helmet; an iron ashtray; 12

    glass bottles; 2 caskets; and an iron pick. An

    archaeological evaluation performed at Dock

    45 on the Atlantic sector reported nding a 5

    feet-long Decauville wagon wheel axis with its

    gear box, from the time of the French Canal. An

    inspection conducted in the old Emperador Town

    resulted in the recovery of several archaeological

    cultural remains belonging to town residents,

    such as industrial implements, ceramic, glass

    bottles, and metallic artifacts; as well as in the

    identication of 13 iron crosses in the cemetery

    area, which date back to the French Canal Era

    (1880-1903).

    Public Relations,Communication, andHistorical DocumentationIf the eld work doesnt relent, communication

    and historic documentation of Expansion

    Program progress dont stop either. The task

    34

  • 8/11/2019 Panama Canal Annual Report 2012

    37/112

    A N N U A L R E P O R T 2 0 1 2

    of informing about the development of this major Program

    has become the permanent trend of those who generate all

    sorts of communication instruments, such as brochures, iers,

    leaets, writings, reports, presentations, photos, videos, and

    recordings, among others. The preservation of documents for

    future generations is another tremendous effort, one that requires

    technical know-how and long-term vision to gure out how the

    images and documents prepared today will be interpreted, so as

    to ensure that they stand the test of time.

    During an assessment of the communication activity from the

    beginning of the Expansion, over 37,000 persons have received

    assistance, including visits to the new locks construction sites and

    to dredging and excavation areas on the Pacic and Atlantic

    sectors; speeches and presentations to different international

    and national audiences on the progress of the Program; fullling

    requests from foreign and local media; responding the toll free

    customer care line, 800-0714; and replying to emails received at

    [email protected].

    Art goes hand-in-hand with the Canal Expansion as it advances.

    Various engineering activities have been depicted in oil and

    watercolor paintings featuring the movement of heavy equipment

    and Expansion workers, by the hands of local artists such as

    George Scribner, Carlos Gonzalez Palomino, Jose Inocente

    Duarte, Amalia Tapia, and Roberto Vergara.

    Honoring the commitment to document the

    evolution of this remarkable initiative, the ACP

    published a second volume of the book titled

    The Panama Canal Expansion: Portraits o

    a Historic Undertaking 2010-2011. This book

    compiles photos of the work sites, contracto

    activities and equipment, and the Panamanian

    workforce who contribute with their daily effor

    to meet the goal and turn over this project, which

    will render tangible benets and place Panama

    in a leading international maritime trade position

    35

  • 8/11/2019 Panama Canal Annual Report 2012

    38/112

    Environment

  • 8/11/2019 Panama Canal Annual Report 2012

    39/112

    A N N U A L R E P O R T 2 0 1 2 37

    Environmental ManagementEnvironmental management refers to how we interact with nature

    through instruments keen to making our actions sustainable. In this

    respect, thinking of sustainability is thinking of life. This represents,

    managing responsibly with balance between human activities,

    social equality and environmental protection at different levels.

    The Constitution of the Republic of Panama gives the Panama

    Canal Authority (ACP) a mandate to shift from concept to action,

    mainly to protect Panama Canal Watershed resources through an

    integrated management approach. Water is a critical resource for

    the sustainability of the business of the Panama Canal; therefore

    the effort of the Panamanian society as a whole is required topreserve its quality and quantity. The Interinstitutional Commission

    for the Panama Canal Watershed (CICH for its acronym in Spanish),

    created in the year 2000, is responsible through close coordination

    with State entities to integrate efforts, initiatives and resources for

    the Watersheds conservation and management and to promote

    its sustainable development. Strategic alliances are made through

    the CICH and a community participative framework is established

    for the water governance, building a sustainability culture.

    The Panama Canals water governance approach is based

    on a community structure of 6 Regional Advisory Councils and

    30 Local Committees in 23 sub basins is organized under hydric

    planning criteria. The year 2012 consolidated the

    participatory process in the management of the

    Watershed, for the eastern and western sectors o

    Gatun Lake, which facilitated the strengtheningof local and organizational capabilities, resulting

    in the development of annual action plans.

    Part of the process and with the participation o

    all interested stakeholders, a 25 year vision maste

    plan was approved in the year 2007. It facilitates

    a set of organized and concerted actions called

    Sustainable Development Plan and Integrated

    Management of the Water Resources in the

    Panama Canal Watershed (DSGIRH Plan for its

    acronym in Spanish).

    The results of the plans implementation have

    been satisfactory from its formulation. For sca

    year 2012, it has facilitated the execution of

    54 projects with an active participation of the

    community and different government and

    non-governmental institutions. The greates

    investment has been concentrated in community

    infrastructure projects that improve the quality o

    life of the Watershed population.

  • 8/11/2019 Panama Canal Annual Report 2012

    40/112

    A N N U A L R E P O R T 2 0 1 2

    Education for Sustainable DevelopmentThe Environmental Conservation and Work Training Program

    is carried out under a strategic partnership with the National

    Institute for Human Development (INADEH), and the Ministry of

    Education (MEDUCA). This program facilitates the insertion of the

    Watershed population in the national labor market, and at the

    same time it develops modules for good environmental practices

    and community awareness. In the 2012 period, this program

    was implemented in 65 educational and community centers in

    training areas such as functional English, electricity, masonry, and

    information technology. During six years of execution more than

    5,300 youngsters have graduated and 10,368 certicates have

    been issued.

    It also notes the development of the annual missions and

    environmental projects in programs such as Our Canal and its

    Watershed (NUCA), Adequate Management of Solid Waste, and

    Water Quality Assessment focused on 4th, 5th, and 6th graders,

    respectively, in which more than 35,000 students and 1200

    teachers actively participated. The capacity building approach

    has reinforced the education of children and adults this year 2012.

    This is the best guarantee of a sustainable future.

    During the Environmental Workdays, which is an annual program

    for the participation and interaction of students and teachers,

    there were environmental contests, regional and interregional

    encounters, as well as camps, and activities.

    More than 10,000 students and 900 teachers from

    110 schools participated in the activities. We may

    conclude that during the 2012 period we hadthe participation of more than 50,000 students,

    2,500 teachers for elementary, premiddle, and

    middle levels, from 153 schools located within the

    Panama Canal Watershed.

    Panama Canal WatershedConservationFor consideration purposes, we have divided

    the 339 thousand hectares of the Panama

    Canal Watershed territory into eight work regions

    established under hydric criteria. The Panama

    Canal Watershed is one of the most important

    areas for the Republic of Panama. It consists

    of 42 corregimientos located in 7 districts of the

    provinces of Panama and Colon. The Watershed

    is an area dened by its sub basins that drain their

    water to the Alhajuela, Gatun and Miraores lakes.

    Six protected areas occupy 38.5 percent of

    the Panama Canal Watershed territory onnatural elements, vegetable cover and the rich

    ecosystems which make up the Watershed.

    The Panama Canal in close collaboration with

    38

  • 8/11/2019 Panama Canal Annual Report 2012

    41/112

    A N N U A L R E P O R T 2 0 1 2

    competent authorities focuses its conservation and

    environmental restoration programs.

    Watershed Vegetable Cover andSoil Use ProgramIn general terms, the forest cover of the Panama Canal

    Watershed has shown a favorable tendency during

    the 2008-2012 period, and despitethe extreme natural

    climatic phenomena that contributed to the covers

    reduction, there is natural regeneration and a positive

    impact as a result of reforestation activities performed by

    the Panama Canal in association with the communities

    and local authorities. This joint participative and

    integrated management approach with stakeholders

    has played an important role in the conservation of the

    environment and in the protection of water sources.

    During the year 2012, the mature and secondary forest

    cover was mainly reduced in the Chagres Nationa

    Park, at the margins of the interoceanic route and the

    headwaters of the Ciri Grande and Trinidad rivers

    This was mainly due to the high precipitation during

    Vegetable Cover and Soil Use in the Watershed, 2008 and 2012Cover Surface (ha) 2012 2012% Surface (ha) 2008 2008%

    Mature Forest 84,082.2 24.3 85,609.2 24.80

    Secondary Forest 82,217.9 23.8 82,941.9 24.00

    Bushes and Stubble 31,279.2 9.1 31,213.6 9.00

    Reforestation 8,212.8 2.4 6,330.5 1.80

    White grassland 6,474.8 1.9 6,946.8 2.00

    Crops 3,218.4 0.9 1,996.4 0.60

    Grassland 75,823.7 22.0 77,874.7 22.60

    Bare soil 1,461.2 0.4 406.6 0.10

    Population 10,397.2 3.0 10,218.7 3.00

    Mining 859.3 0.2 488.3 0.10

    Water 41,292.6 12.0 41,292.6 12.00

    TOTAL 345,319.3 100.0 345,319.3 100.0

    39

  • 8/11/2019 Panama Canal Annual Report 2012

    42/112

    A N N U A L R E P O R T 2 0 1 2

    the climatic phenomenon La Purisima in the year 2010 and

    the strong rains in the year 2011, as well as the construction of

    infrastructure in the Transisthmian Corridor during the last ve

    years. The 2009-2012 period showed a deforestation rate of -0.27

    in comparison with the 2003-2008 period.

    Water Quality and QuantityThe Panama Canal, as the water resources administrator for

    the Panama Canal Watershed, is responsible for ensuring the

    quality and availability of water for human consumption as well

    as for the operation of the Panama Canal by means of complex

    forecasting systems, together with water quality monitoring and

    ood control and prevention programs.

    Water QualityThe Water Quality Surveillance and Monitoring Program in the

    Panama Canal Watershed comprises natural water at stations

    located on tributary rivers and reservoirs in Gatun, Miraores and

    Alhajuela. This generates the water resources physico chemical

    and biological conditions data for better decision-making

    regarding policies, programs, and projects that contribute to

    sustainable use and efcient water management. With regards to

    the monitoring of drinking water quality, samples were analyzed

    for daily, monthly and quarterly assessments of processes with

    products of the three water treatment plants managed by the

    Panama Canal, Miraores, Mendoza and Monte Esperanza. These

    included, among others, testing for metals, organic compounds,

    pesticides, cyanobacteria, protozoa and other

    biological indicators. In addition, wastewater

    quality was followed up on by participating in

    the characterization and monitoring of different

    sewage discharges generated in the operations

    of the Canal.

    Production of Drinking WaterThe water resources of the Panama Canal

    Watershed are the source for the water used by

    the treatment plants managed by the Canal,

    beneting approximately more than half a million

    people in the cities of Arraijan, Colon, La Chorrera

    and surrounding areas; as well as Panama City,

    the district of San Miguelito and the Transisthmian

    Corridor towns. The Mendoza Treatment Plant,

    with a production capacity of 40 million gallons

    per day, produces 31 million gallons supplying

    water to 125,000 recipients who have lived for

    more than 15 years without continuous access to

    safe drinking water.

    Climate ChangeRecently the Republic of Panama has experienced

    some extreme climate events related to the

    climate change that our planet lives today.An

    40

  • 8/11/2019 Panama Canal Annual Report 2012

    43/112

    A N N U A L R E P O R T 2 0 1 2

    example of this was the climatic event that took place

    in December 2010, La Purisima, caused by the 2010-

    2011La Nia phenomenon, which brought heavy rainfall

    for more than 21 days, causing harm to human and natural

    systems, related to the loss of human lives, millionaire losses

    in agricultural production, infrastructure, and a reduction

    in drinking water production for the provinces of Panama

    and Colon.

    The Panama Canal has started looking for alternatives

    to face the challenges and opportunities of climate

    change through an integrating vision regarding social,

    economic and environmental matters, including nancial

    mechanisms to implement actions that facilitate the

    application of mid to long term adaptation measures

    based on a sustainability culture oriented towards risk

    prevention.

    Under this approach, the Canal is bound to reduce the

    Watersheds social and natural systems vulnerability, the

    adverse impact of climate change and other risks related

    to global warming, in order to increase the populations

    adaptation capacity to those events. The Green Route

    Program includes concrete actions implemented by the

    Panama Canal in the adaptation and mitigation of the

    effects of global climate change.

    The Green Route: The Routethrough PanamaIn a green economy framework, we are implementing a

    comprehensive carbon management plan that includes

    the development of a greenhouse gases baseline (GHG

    for our operations and the establishment of a strategy fo

    the reduction and compensation of these emissions. We

    are trying to mitigate the impact of our activities and to

    reduce its carbon footprint in a proactive way, through

    the execution of reforestation projects and recovering

    degraded areas.

    The route through Panama is considered the green

    maritime route of the world, because of its contribution

    to fuel use reduction per transported cargo unit by the

    vessels that transit through the Canal in comparison with

    other immediate alternative routes, reducing in this way

    the CO2emissions of the world maritime sector. With the

    Panama Canal Expansion, we expect to have twice the

    cargo that transits today avoiding the emission of more

    than 160 million tons of CO2during the rst 10 years of the

    new set of locks, between the years 2015 and 2025. The

    Panama Canal offers the maritime industry a valuable

    alternative for the transportation of great volumes o

    cargo through an all water route, with safety, low costs

    41

  • 8/11/2019 Panama Canal Annual Report 2012

    44/112

    A N N U A L R E P O R T 2 0 1 2

    and effective Canal waters time, in addition to reducing CO2

    emissions and contributing with the international efforts to reduce