32
© Crown copyright Page 1 Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June 2005

Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

Embed Size (px)

Citation preview

Page 1: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 1

Operational Use of ECMWF products at the Met Office: Current practice,

Verification and Ideas for the future

Tim Hewson 17th June 2005

Page 2: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 2

Contents

Describe use of ECMWF output, in the Operations Centre at the Met Office (which provides guidance to the outfield), in 3 forecast categories:

1. ‘Short range’ (up to 36 hours)

2. ‘Medium range’ (36 hours to 6 days)

3. ‘Trend period’ (6 to 10 days)

4. Some verification ideas (severe weather)

Page 3: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 3

1. Short Range

Relatively recent changes in ECMWF operational suite (2 operational runs per day, much reduced delay in forecast arrival time, etc) render ECMWF operational runs much more useful for short range forecasting than hitherto

Data time (DT) difference c.f. Met Office operational runs now averages 9 hours (previously it was 21 hours)

9 hours is comparable to the short period lead time gain of ECMWF over Met Office (10 hours), implying high potential for adding value to deterministic forecasts using the consensus (“poor man’s ensemble”) approach

Though not necessarily part of the ‘ECMWF remit’ if ECMWF model output can potentially improve our short range forecasts we will use it

Some use also made of ensemble data (though much less than in the medium range – due to reduced reliability of severe weather probabilities)

Page 4: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 4

Operational Model Errors

1 5 days 10

RANK Best - EC UK FR..

NH rms MSLP errorvs Lead Time

Lead time gain = 10 hours

short range | medium range | trend period |

Page 5: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 5

RAWMODOBS

Short Range Forecast Example

RAW

Cloud coverPpn ratePpn typeMslp

Page 6: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 6

“What was it, specifically, about the good forecast that made it better?”

Helps highlight common model errors

Verification of Modifications

Page 7: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 7

Scope for Improvement

Forecasters are usually able to improve upon raw (Met Office) model output, using different models, knowledge of systematic errors, comparison with current trends

Degree of improvement could potentially be increased by making more use of the high quality ECMWF operational run, which at present is under-utilised

WISH LIST! –

3 hourly data, T+0 to T+48

Instantaneous total ppn rates, plus cloud cover and mslp (same format?!)

Separate plots showing dynamic /convective rain and snow components

10m mean wind and likely gust strength

Sub areas – parts of Europe ?

Timely appearance on ECMWF web site is crucial (probably the most expedient route for making this data available)

Page 8: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 8

Severe Weather

Table records ‘Significant Errors’, from perspective of hazardous weather, in Raw (Red) and Modified (Blue) forecasts (2.5 years of data)

A key forecasting target is a reduction in the number of blue boxes

This verification has highlighted warm air summer convection as one area where the forecaster is able to add little value, and where there can be major errors in the model

Potentially ECMWF oper runs could assist in this area, via the wish list data? (convective characteristics?)

Cold air convection is also a problem area, though one that the forecaster often addresses reasonably successfully. FGEW verification has highlighted this as a significant weakness in ECMWF output (snow in NE’lies, Feb/Mar 2005)

Low pressure centres and surface wind gusts in strong gradient regions are another sig problem

Page 9: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 9

2. Medium Range

Use of ECMWF data - operational and ensemble runs - is more common in the medium range

Timeliness is a key issue for practical applications; recently the ECMWF web site has been used more often, because of timely updating

Issued forecast guidance has both deterministic and probabilistic components

Page 10: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 10

Deterministic Component

Underlying Strategy: First ascertain the key meteorological feature(s),

Then incorporate different model and ensemble solutions accordingly, weighting as appropriate (on screen or on paper) to arrive at a consensus solution

Page 11: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 11

Operational Model Errors

1 5 days 10

NH rms MSLP errorvs Lead Time

short range | medium range | trend period |

Page 12: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 12

•Cold front is themain feature

•Consensus wouldmove GM front south,possibly hinting atwave development,as GM underdoeswaves, and as NCEPshows one.

Simple Example to Illustrate

Page 13: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 13

Modifying a Selected Model Run

Use Field Modification tool (devised by Eddy Carroll) AFTER a model run has finished

Allows quick, interactive, dynamically consistent changes to be made to a set of 3-d fields from one model run, eg:

Move low or front Deepen/fill low Introduce low or wave…

Relies on modification vectors applied to PV distribution, followed by PV inversion with changed boundary conditions

Equivalent translation vectors applied to ppn and RH; simple boundary layer model used for surface winds

Temporal consistency achieved via time-linking (with ‘decay’ parameter)

Precipitation rate & type, winds etc can also be adjusted directly and time-linked

Page 14: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 14

Field Modification Example – moving a low with slight deepening

Page 15: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 15

Resulting fields (takes ~2 seconds)

Page 16: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 16

Initial Fields

Page 17: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 17

500mb ht and 100-500mb Thickness - before

Page 18: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 18

500mb ht and 100-500mb Thickness - after

Page 19: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 19

Objective Verification

Page 20: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 20

Subjective Verification

Met Office Global model, ECMWF Oper and issued Modified forecasts are compared, primarily for mslp, but also for fronts and thickness, over NW Europe, using 12Z data times, for T+48,72, 96 and 120h

The overall ranking is (best first): Modified >> ECMWF >> UKMO

This is despite the objectively calculated lead time gain of ECMWF over UKMO (10-16 hours) being generally greater than it is for Modified over UKMO (0-12 hours)

Objective schemes can penalise good forecasts of cyclogenesis (especially rms errors)

A new ‘more discriminating’ subjective verification scheme will be introduced this year

Page 21: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 21

Forecaster Impact

Modification Time

Page 22: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 22

Probabilistic component

Consists of a headline summary of probabilities of severe weather, in a number of categories (introduced relatively recently)

Minima and maxima for sites are issued with upper and lower bounds. Probabilities are given for rainfall total exceedance. Starting point is calibrated ECMWF ensemble output.

‘Alternative scenarios’ can be issued to highlight uncertainties

Probabilistic components appear to be used far less by customers than the deterministic component. Somewhat disappointing – education required, but may take a long time.

Page 23: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 23

3. Trend Forecast

Consists of an issued worded forecast, with expected temperature anomalies, and considerable discussion of uncertainties, highlighting possible severe weather

Based primarily on ECMWF data, but with some input from other models and ensembles, notably from NCEP

Customer base for this forecast has been dwindling (perhaps they watch Swedish TV)

Page 24: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 24

Trend Period – Subjective Verification

ECMWF - OPERATIONAL vs ENSEMBLE - DAYS 6 TO 10 (2004)

0102030405060708090

100

Operational Days 6 and7

Ensemble Days 6 and 7 Operational Days 8 to 10 Ensemble Days 8 to 10

A = good/useful forecasts. B = indeterminate. C = poor or misleading forecasts

A

B

C

Based primarily on mslp, over NW Europe, ECMWF only Ensemble mean rated a little more useful than Oper run, but not by much Only 1 in 5 forecasts for days 6 and 7 were considered useful, and 1 in 10 forecasts for days 8, 9 and10 Scores have not changed a great deal over the years

Page 25: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 25

Extras for ‘Wish List’

Meteograms to include overlapping 24-hour rainfall totals (but still in 6 hour blocks)

Total cloud cover – is this ‘altitude weighted’, or is 8 oktas cirrus considered ‘cloudy’? Weighting would be preferable

Postage stamps showing estimated surface gusts, with colour-shading for high values

Cluster ensemble means for mslp, thickness, annotated with percentages of members

Page 26: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 26

4. Verification – some ideas

Conceptually there should be a ‘deterministic limit’ for predicting a pre-defined meteorological event

Simply defined this could be the point in lead time beyond which forecasts concerning that event are more likely, on average, to be wrong than right

Defined in this way, this provides some guidance on when to shift the emphasis, in forecasts for particular events, towards the probabilistic

For rare events at least, correct null forecasts – ie the majority - can be ignored as not relevant

Page 27: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 27

Verification ideas (contd)

The ‘deterministic limit’ for the event in question is then simply the lead time at which, over a suitably large forecast sample, hits equals the sum of misses and false alarms (or CSI = 0.5)

misses + false alarms

hits

number

‘deterministic limit’

lead time

dc

baFc

Ob

a/(b+c) = 1

Page 28: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 28

Event Examples (numbers are very crude estimates)

Tornado within 2km radius (deterministic limit ~ 5 mins)

Snow falling at a point (~5 hours)Rain falling at a point (~18 hours)Gale force gusts at a point (~6 hours)Gale force gusts within a UK county (~24 hours)Rainfall >15mm in 3 hours somewhere in a UK county

(2 hours)Cyclonic surface pressure pattern at a point (~120

hours)Atmospheric front within 200km of a point (~60 hours)Day with maximum above 30C in London (~96 hours)

Page 29: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 29

Benefits

Potential to provide a meaningful measure of what to expect from, and therefore what to put into, a forecast. Too many forecast elements are deterministic.

It is something that the public, other customers (and auditors!) could potentially relate to

The equivalent, from an idealised, reliable ensemble prediction system, would be the lead time at which the average probability, for hindcasts of observed past events, fell to 50% (?)

As always extreme events would be more difficult to represent (though hindcasts from re-analyses are becoming increasingly tractable)

Facility also to measure forecast improvements, compare systems, assess forecaster performance

Page 30: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 30

Summary

The Met Office makes extensive use of ECMWF products for forecasts from T+48 to T+240, and is increasingly using the operational run as an input to short range forecasts

Verification indicates that the forecaster is adding value in many areas, in part using the poor man’s ensemble approach, though some weaknesses remain

Various enhancements to ECMWF web-based output have been suggested

Disappointingly, the customer base for probabilistic forecasts is currently limited

More guidance on what we can and cannot forecast deterministically is required

A new measure of ‘deterministic limit’ has been tentatively proposed

Page 31: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 31

References

• Carroll, Meteorological Applications, 1997, for field modification description

• Carroll and Hewson, Weather and Forecasting, 2005 (out shortly) for ops centre practice and verification

Page 32: Page 1© Crown copyright Operational Use of ECMWF products at the Met Office: Current practice, Verification and Ideas for the future Tim Hewson 17 th June

© Crown copyright Page 32

Accreditation

WAFCWorld Area Forecast Centre