Upload
korom-chand
View
185
Download
0
Embed Size (px)
DESCRIPTION
A chronology of The Padma Bridge.
Citation preview
Padma Bridge
From Wikipedia, the free encyclopedia
Padma Bridge
Padma Bridge
CarriesMotor vehicles,Railway
CrossesPadma River
LocaleLouhajong,MunshiganjtoShariatpurandMadaripurBangladesh
Maintained byBangladesh Bridge Aurhority
DesignerAECOM
DesignTruss bridge
MaterialSteel
Total length6,150m (20,180 ft)
Width21.10m (69.2ft)
Construction beginexpected in 2011
Construction endexpected in 2013 (-2015)
Coordinates232521N901835ECoordinates:232521N901835E
ThePadma Bridgeis a multipurposeroad-rail bridgeacross thePadma Riverto be constructed inBangladesh. When completed it will be the largest bridge in Bangladesh and the first fixed river crossing for road traffic. It will connectLouhajong,MunshigonjtoShariatpurandMadaripur, linking the southwest of the country, to northern and eastern regions. The Project covers three districts namely, Munshiganj (Mawa Point/North bank),ShariatpurandMadaripur((Janjira/South bank). The civil work components of the project requiring acquisition and requisition of land are presented in Table 1. The total area of land to be acquired and required for various components is 918 ha. The requisition of land for the construction yard will be for six years on a rental basis. As per the new design, an additional 144.04 ha has been identified for acquisition, bringing the total to 1062.14 ha. This additional land is required because project site lost significant land due to erosion, for transition structures and also due change in railway alignment.
The two-level steeltruss bridgewill carry a four-lane highway on the upper level and a single track railway on a lower level. The project will include 6.15km long and 21.10 m wide bridge[1], 15.1 km of approach roads, toll plazas and service areas.[2]Project cost is estimated to beUS$3.00 billion. Funding for the project is provided by the Asian Development Bank (ADB) (US$615 m[2]), theWorld Bank($1.5 billion[3]), Japan International Cooperation Agency ($415 m), Islamic Development Bank[4]($140 m). The government also signed another $ 14.84 million agreement with the IDB for the implementation of the water-supply and sanitation project in cyclone-prone coastal areas, and Abu Dhabi Development Group ($30 m).[5]Of the total amount, the government will provide Tk 50 million while the rest will come in the form of project aid.
The Bangladesh Bridge Authority invited the pre-qualification tender for the project in April 2010.[1]Construction of the bridge is expected to commence by early 2011[5]and be ready for major completetion in 2013[1](and complete all sections by late 2015[4]). The proposed Padma Multipurpose Bridge Project will provide direct connectivity between the central and southwestern part of the country through a fixed link on the Padma River at Mawa-Janjira points. The bridge will contribute significantly towards facilitating the social, economic and industrial development of this relatively underdeveloped region with a total population of over 30 million. The area of influence of the direct benefit of the project is about 44,000 sq km or 29% of the total area of Bangladesh. Therefore, the project is viewed as a very important infrastructure towards improving the transportation network and regional economic development of the country. The bridge has provisions for rail, gas, electric line and fibre optic cable for future expansion. The project will be co-financed by the Government of Bangladesh (GOB), the World Bank (WB), the Asian Development Bank (ADB), the Japan International Cooperation Agency (JICA) and the Islamic Development Bank (IDB). Bangladesh Bridge Authority (BBA) is the executing agency (EA) of the Project.
Padma Bridge
Construction phase:2015Status:project phase
Location:BetweenMawa,BangladeshandJanjira,BangladeshCrosses:Padma River
Click on the image to enlarge it.
Structural Type:Truss bridgedouble deck
Function / usage:Railroad (railway) bridgeRoad bridge
Persons involved with this structure
Legend:Phase of worksRole
Name
Part of structure
Consulting engineerKatsufumi Matsuzawa
Takeshi Yoshida
Firms, offices, etc. involved with this structure
Legend:Phase of worksRole
Name
Part of structure
DesignConstruction Project Consultants, Inc.
Nippon Koei Co. Ltd.
Technical information
Description
Value
Construction materials used
trusssteel
Dimensions
main spans
150 m
piers number
41
The Daily Star; Tuesday, September 13, 2011The construction of Padma Bridge will face a long delay if the World Bank does not accept the government's proposal to start the work soon without involving the firms accused of corruption.
The proposal was made when WB Vice-President Isabel M Guerrero met Prime Minister Sheikh Hasina on Sunday.
Finance Minister AMA Muhith, who was present at the meeting, said this at a press briefing at his secretariat office yesterday.
The WB official came to Dhaka on a day's trip to inform the government about the lending agency's position on corruption allegations concerning the Padma Bridge project.
Muhith told journalists, We cannot wait for an indefinite period. We have told them [World Bank] to officially communicate to us the names of the companies accused of corruption. The government will drop those from the short-list and start the construction.
At Sunday's meeting, Guerrero said the bank will take its decision after discussing the matter at its headquarters in Washington.
The government has short-listed five firms for appointment as consultants including Canadian company SNC-Lavalin Group Inc. The names of those short-listed have been sent to the World Bank for its approval.
The Canadian authorities are investigating the SNC-Lavalin Group Inc for corruption following a WB referral.
Guerrero told the government that the bank cannot approve the appointment of consulting firms until the Canadian authorities dispose of the allegations against SNC-Lavalin.
The minister told her that the probe against the accused firms may take two to three years to be completed, and the government cannot wait that long to begin the construction.
The WB official said they have received some other allegations as well.
Muhith said, The prime minister and I have emphatically told the World Bank vice-president to inform the government about the companies against whom they have allegations. The government will begin construction of the bridge without those companies.
Besides the proposal for appointing consulting firms, tender documents for the construction work and river training have been sent to the WB for approval. But none of those has been approved yet.
The minister said both he and the PM will go to the US separately this month. They will have talks with the WB officials there on the issues regarding Padma Bridge.
If the matter is settled by this month and the bank accepts the government proposal, preparatory work for construction of the bridge will start next month.
It, however, might take till January to begin the construction, which was earlier expected to get underway by October.
Asked about speculations that the WB will not fund the bridge as long as Syed Abul Hossain stays communications minister, Muhith said, I don't know of anything like that. Maybe it all is being spread.
THE FEASIBILITY STUDY OF PADMA BRIDGE
Study team : Japan International Cooperation Agency (JICA)Start : May 2003, END : March 2005
Timing of SubmissionMain Contents
Inception ReportJune 2003-Scope, methodology and implementation plan of the Study
Progress Report 1September 2003Selection of the bridge location alternatives, Traffic demand projection
Interim ReportMarch 2004-Results of Preliminary Engineering Studies- Results of IEE and SIA- Decision of the Bridge Location
Progress Report 2September 2004-Design criteria and design standards-Comparative analysis, preliminary design and construction plan
Draft Final ReportJanuary 2005-All Study results
Final ReportMarch 2005- All study results, reflecting comments by the Bangladeshi Government
Findings of Progress report - 1
Four alternative bridge sites were identified as alternative locations in the following areas:
Site-1:Paturia-GoalundoSite-2:Dohar-CharbhadrasanSite-3:Mawa-JanjiraSite-4:Chandpur-Bhedarganj
-Four alternative locations were examined from the view points of existing transport of the project area, traffic demand forecast, preliminary river study and technical consideration in highway planning, preliminary bridge planning, environmental & social consideration.
-JICA study team considers site-1 and site-3 to be most advantageous for a new fixed crossing and recommends these sites for further study until Interim report.
Findings of the Interim reportBasic Policy of the Feasible Study:
Main Function of Padma Bridge
Location of Padma Bridge
Socio-Economic Impacts of Padma Bridge
Associated Road Development Project
Associated Road Development Project
Impact of Macro Balance of the Country
Private Sector Participation
Study Items completed by Progress Report (1)
Collection & Review of Existing Data, Information and Reports related to the Study
Identification of Conceivable Bridge Crossing Sites
Traffic Survey & Traffic Demand Forecast
Preliminary River Study
Preliminary Technical Consideration of Highway & Bridge Planning
Preliminary Environment & Social Condition
Screening of Alternatives
The Study Items completed by Interim Report
Engineering Survey
Preliminary River Facility Design
Preparatory Preliminary Study for Bridge & Highway
IEE
SIA & Resettlement Issue
Economic Effect & Preliminary Feasibility
Findings from Geotechnical Investigation
Difference of Subsoil Conditions between 2 Sites
N-values of SPT at Mawa-Janjira site are higher than those at Paturia-Goalundo site.
Horizontal Ground Reaction
As the coefficients of horizontal ground reaction in the bored holes showed relatively smaller values, such characteristics would have to be considered in the preliminary design of foundations.
Liquefaction
Paturia-Goalundo site has high potential risks of liquefaction when sever earthquake takes place. On the other hand, Mawa - Janjira site has lesser potential risks of the same.
Finding (1 )
N -values of SPT at Mawa-Janjira site are higher than those at Paturia-Goalundo. Main reason of this result might come from the subsoil composition at Paturia - Goalund that consists of relatively singular particle size distribution of fine sand.
Finding (2)
Below maximum scour levels El -40m PWD, N-values of SPT at Mawa-Janjira are higher than those at Paturia-Goalundo.
Finding (3)
From the pressure - meter tests in situ bored holes, the following relation was obtained:
Em=4.52N
Where, N:N-value of SPT
Em: Coefficient of horizontal ground reaction
Ref.: Em+7N.....Design specification of Highway Bridges adopted by JRA.
Em=7n
Finding (4)
As a result of liquefaction analysis, there is no potential risk of liquefaction at Mawa-Janjira site.
On the other hand , there is some protential risks of liquefaction at Paturia-Goalundo site in some depts either before or after scour.
Preparatory Study for Preliminary Design on Bridge
Bridge Length, which was decided by the river study
Paturia-Goalundo= 6.5 kmMawa-Janjira =6.2 km
Applicable Bridge Types over 100m Span Length
Concrete Bridge: PC Continuous Box, Extradosed, Cable-stayed
Steel Bridge: Steel Continuous Box, Cable-stayed
Foundation Types
Steel Tubular Driven Piles, Cast-in-situ RC Piles, RC Caissons
Cost-Span Relation
Minimum cost would be at approx. 200m span length.
Favorable Bridge Types and Span Length
PC extradosed girder bridge or PC cable-stayed girder bridge would be the most favorable bridge type from the view points of construction cost, maintenance cost, etc. Favorable span lengths will be further examined in a rage of 150m to 250m.
Initial Environmental Examinations (IEE)
Initial Environmental Examination (IEE) was conducted for the two preferred sites to identify the significant environmental impacts
A tailor made project specific 6 step template was developed exclusively for this project and applied for two sites
For the two sites, most of the impacts are found to be similar
There is no significant advantage of one site over other
SIA and Resettlement Issues
SIA was conducted for two alternative sites to ascertain the likely impacts of :
1.Land acquisition
2.Local response to the project
3.Resettlement needs of the potentially affected persons
Survey Results
Estimated amount of land to be acquired is almost same (about 1,250 ha ) in both cases
The number of affected households / structure varies due to differences in population density
Current estimate suggests:-
Mawa - Janjira70,000 to 80,000
Paturia - Goalundo40,000 to 45,000
Estimated LA and resettlement cost for M-J site is $39 million, and G-P is $24 million
The Study Team found strong support to the project at both locations
Traffic Study and Economic Analysis (Main Work Items)
1)Traffic Surveys (Traffic counts, OD Survey)
2)Establishment of Future Socioeconomic Framework (Population, GDP, GRDP)
3)Traffic Demand Forecast (Target year 2025)
4)Confirmation of Economic Feasibility
5)Economic Impacts of the Padma Bridge
1)Improvement of Accessibility
2)Regional Economic Development
3)Formation of International Road Network
Summary of Comparisons of Two Sites from traffic and Economic Point of View
Evaluation CriteriaPaturia-GoalundoMawa-JanjiraTraffic Demand (2025)19,850 vehicles/day41,550 vehicles/dayEconomic FeasibilityEIRR=9.6%EIRR=16.9%Financial Project Cost (Million US$)1,2601,074Improvement ofAccessibility(Travel time)Dhaka - MonglaDhaka - Benapole
(Beneficiary Population)Within 3 hours from DhakaWithin 4 hours from Dhaka
4.5 hours4.6 hours
2,791,000 (9%)12,738,000 (42%)3.6 hours3.6 hours
10,417,000 (35%)22,247,000 (74%)Density of Feeder RoadsNo big differenceFormation of International Road Network
Asian Highway A-1. Short distance to Benapole Land Port and Mongla Sea PortRegional Economic DevelopmentGDP of Southwest region will increase by 18% (1.2% /year)GDP of Southwest region will increase by 35% (2.3% /year)Growth centers around the bridge sitesNo big difference
Indicative Cost
Paturia - GoalundoMawa - JanjiraUS$ 1,260 millionUS$ 1,074 million
Evaluation of P-G & M-J sites
Evaluation CriteriaPaturia - GoalundoMawa - JanjiraEconomicFeasibilityEIRR9.6%16.9%B/C Ratio0.711.81NPV (Mil.Taka)-9,85723,140RegionalDevelopmentIncrease of GRDP of Southwest Region18% up(1.2% per year)35% up(2.3% per year)EnvironmentalImpactResult of IEENo big differenceSocial impact and Resettlement IssuesHouseholds requiring relocation1,8422,635Community structures affected1860Total population affected (both direct and indirect)40,000-45,00070,000-80,000Preliminary RAP cost23.7 mil. US$38.79 mil. US$
RIVER TRAINING WORKS (RTW)
Types of RTW:Guide Bund works (GBW),abutment protection works (APW) and bank protection works (BPW).
GBW:To guide river flow to the bridge opening and to protect bridge abutment and approach road from erosion.
APW:To protect bridge abutment from erosion.
BPW:To ensure the functions of the GBW and APW by maintaining present flow conditions around the bridge sites.
ALTERNATIVES SCHEMES
For RTW on Left Bank:Two alternative measures(1) GBW facing to Padma river, or(2) APW behind the less erodible riverbank (1km apart considering possible erosion during 100 years in future)
For RTW on Right Bank:GBW facing to Padma River were proposed, since no reliable stable bank for abutment could not be found on the right bank according to the erodibility study.
Alternative Schemes:In combination with the left and right RTW mentioned above, two alternative schemes with same functions were established each for PG-site and MJ-site.
BPW:The BPW were also planned for each site considering respective site conditions.
SELECTION OF OPTIMUM SITE
RTWin combination of GBW(R), APW(L) and BPW are proposed for both PG- and MJ- sites.
Construction Cost:According to the preliminary cost estimate, MJ-site requires less construction cost than PJ-site.
0ptimum Site:The optimum site will be finally proposed afterward considering economic, social and environmental aspects as well as the engineering aspect.
Steps of Environmental Study
Initial Environmental Assessment for Padma River eco-system particularly for four alternative sites
Initial Environmental Examination (IEE) for two preferred sites (reporting in Interim Report)
Environmental Impact Assessment (EIA) for the selected site
Environmental Management Plan (EMP)
Objectives of IEE
To identify the significant environmental impacts
Prepare Scope of EIA
Prepare a preliminary EMP with cost estimates
Features of the IEE Study
Impact area is considered as 10,000 km2
ROW is considered as 60m and Bridge landing site requirement is assumed as 6 km2
Secondary data was collected on related parameters
Primary data was collected by questionnaire survey, reconnaissance, and discussion with local people.
Assessment Procedure
A tailor project specific 6 step template was developed and applied
Environmental parameters are identified with rational
Numerical weightage values are decided with justification
Project specific mitigation guidelines are prepared
Impact analysis template is used
An impact rating template is employed (screening)
A Leopold graded impact matrix is applied
Impact Assessment
40 parameters used for screening
There are 8 positive impacts
No impacts for 8 parameters
There are 24 negative impacts (befort mitigation)
There are 14 negative impacts after mitigation (however, impact will be reduced much)
Impact Comparison
For two sites, most of the impacts are similar
More erosion/siltation at Paturia site
More water bodies loss at Paturia site
More fisheries loss at Paturia site
More homestead loss at Mawa site
More Income loss at Mawa site
More split of communities at Mawa site
There is no significant advantage of one site over other
Scoping of EIA
(as Identified in IEE)
Erosion and siltation (including regional hydrology and drainage congestion)
Agricultural / vegetation loss (including plant cutting)
Fisheries (including water bodies)
Wildlife
Land acquisition (including split of communities)
Resettlement (including Income loss)
Navigation
Road accident
Air, noise and vibration pollution
Preliminary EMP
A rough cost estimates show that the EMP requirement will be between 2 and 3 million US$ (the EMP cost for the Jamuna Bridge was about 3 million US$)
However the cost requirement variation between the two sites is insignificant
SIA & Resettlement Issues
Objectives of the SIA
SIA was conducted for two alternative sites -(I) Mawa / janjira and (II) Paturia / Goalundo
Planned and carried out to ascertain the likely impacts of
-Land acquisition-Local response to the project-Resettlement needs of the potential APs
Primary objectives were to
-Develop comparative SIA of the two alternatives-Preliminary Cost estimates- Develop social/ resettlement criteria for site selection
SIA was not designed for a full scale resettlement study
SIA Methodology
Conducted over two months (Nov / Dec 2003)
Similar ecological and socioeconomic features
Methodology adopted include
--Participatory Rapid Appraisal (PRA)Focus Group Discussion (FGD)
-Meetings with local govt. officials/community leaders
-Sample survey using structured questionnaire
200 heads of households were interviewed
SIA Survey Results
Impacts of Land Acquisition
Estimated amount of LA is same in both sites
Mawa / janjira1272 ha
Paturia / Daulatdia1239 ha
impact on households/ population varies
-M/J2,635 hhs (13,204 APs)
-P/G1,842 hhs (8,732 APs)
These numbers limited to affected hhs requiring relocation
Those affected by loss of land are not Included
Jamuna experience - three times higher than those requiring relocation
SIA Survey Results
Loss of residential /commercial structureMawa /Janjira - 2635 unitsPaturia / Goalundo - 1842 units
Close to 80% of the units are made of
straw / bamboo, Cl sheet/tile roof - can easily be dismantled and moved
Community structures /facilities will also be affected - (I) M/J - 60, and (ii) P/G - 18
SIA Observations
Total population affected (directly and indirectly) may run into:
Mawa - 70,000-80,000Paturia - 40,000-45,000
Impacts surely will begreater than currently understood
More accurate assessment will be possible only after the site is selected and preliminary design available
Awareness and Response to the Project
Local people are fairly aware of the impacts of LA & Resettlement Impacts
Also Informed about donor policies due to the Jamuna and Southwest Road Projects
Association and lobby groups have been established at both crossings for selection of their favored sites
Strong support to the project
- Improved transportation- Business and new income opportunities- Control of riverbank erosion- Opportunities for regional industrial development
Resettlement and Preferred Options
Survey included questions with regard to choices and preferred options
(i) Mawa / Janjira - 75% of those Interviewed preferrelocation on their own (self -relocation)(ii) Paturia / Goalundo - 96% indicated their preferences for self-relocationOver all, there will be limited demand for resettlement site development
Cost estimate - too early for an accurate cost estimate: M-j $39 million; P-G $24 million
Review and analysis of the Findings
SIA data should be treated as indicative of the potential impacts
The data is generally in line with the pre-feasibility study
A more extensive survey to be carried out for the selected site
The detailed information would be crucial for preparing the RAP
Criteria for Final Site Selection
Preliminary results shows greater impacts In Mawa-Janjira overPaturia site
Site selection should be more on technical - engineering grounds-future safety of the bridge infrastructure
Major Impacts of the project - Irrespective of sites
Selection of Final site Is critical to set the next agenda preparation of RAP
Task would be to minimize Impact, develop Improved policy for mitigation of adverse Impacts, management and capacity building for resettlement management
Experience of the Jamuna and other donor-funded projects will be used In the planning and Implementation of RAP for Padma
Traffic Demand Forecast ofthe Padma Bridge
Traffic Volumes across Padma River(both ways 2003: From Traffic Survey)
Paturia-GoalundoMawa-CharjanjatCross-PadmaTotalLight Vehicle572128700Bus687227914Truck1,217781,295Total2,4764332,909Launch Passenger15,5599,12624,685
Present Traffic Movement Pattern
At present, traffic at Mawa is lower than Paturia due to the following reasons:
1) Road condition of NH 8 is now very poor.
2) A narrow approach road to the Mawa ghat.
3) Quality of ferry services at Mawa is lower than Paturia in general.
4) No sufficient parking space for trucks.
5) Two hour river crossing time at Mawa is significantly longer than 35 minutes of Paturia.
Future Traffic Movement Pattern
Future traffic movement pattern will be drastically changed if the Padma Bridge is constructed at Mawa with following reasons:
1) Improvement of NH 8 (Dhaka - Khulna Road Project by ADB) will be completed by the end of 2004.
2) Direct road link from Dhaka for the largest traffic demands to Khulna and Jcssore.
3) Elimination of two hour crossing time.
Quantification of Benefits
1) Vehicle Operating Cost (VOC) Savings
2) Travel Time Cost (TTC) Savings
3) Freight Value Deterioration Savings
4) Ferry Operation Cost Savings
5) Traffic Accident Savings
6) Air Pollution (C02,NOx) Reduction
7) Benefits from Utility Facilities
8) Land Enhancement Benefits
Preliminary Economic Evaluation
- Evaluation period : 30 years
- Opportunity Cost of Capital : 12 %
Tentative results: 1) EIRR: Paturia = 9.6%
Mawa = 16.9%
Relationship Between GRDP and Travel Time to / from Dhaka
[Model]
Ln (G)=3.0453-0.5482 Ln (T)+Q.4926 Ln (F)
where: (R=0.902)G=Gross Regional Domestic Product/kM2T=Time to Dhaka from districts in Southwest region (hours)F=Density of feeder roads (km/kM2)
Estimated Impact on Economic GrowthinSouthwest Region (Growth of GRDP)
PaturiaMawaSW region18% up(1.2%/year)35% up(2.3%/year)Bangladesh4% up7% up
Conclusion
From the result of the engineering studies, the economic feasibility including costs for social and resettlement issues and future effect on GRDP growth in Southwest Region, the best bridge site is concluded at Maws - Janjira .
Findings of Progress report - 2
This report mainly deals with
-Natural condition survey such as topographic survey, geotechnical investigation, riverMorphology & mathematical modeling
-Preliminary design of Padma Bridge, approach roads, toll plaza, service area, minor Bridges, underpass, riverbank protection works public utilities etc.
-Operation & Maintenance plan of Padma Bridge
-Construction plan & procedure of preliminary cost estimate
-Environmental study & social impact & resettlement study
Design Criteria & standards
The preliminary design in the study would be conducted on the basis of Asian Highway (AH) standards and Roads & Highways Department (RHD) standards. RHD standards are similar to AASHTO standards. Standards adopted by Japan Road Association (JRA), BSI and Indian Road Congress (IRC) would be used as supplementary ones.
Parameters related to River Engineering
Water levels:
Design High Water Level( 100 year return period):DHWL=+7.35m PWDStandard High Water Level:SHWL=+5.81m PWDMean Water Level:MWL=+3.02m PWDStandard Low Water Level:SLWL=+1.43m PWD
Water Discharge and velocity:
Design Discharge( 100 year return period):Qd=134,400m3/secDesign Water velocity( 100 year return period):Vd=4.6m/sec
Scour Levels:
Adjacent to Riverbank ( 100 year return period)300m from riverbank:Zs=-37.56m PWDIn middle of river( 100 year return period):Zs=-23.63m PWD
Reasons for review on bridge types, span-cost relation of Interim
-Bridge width was changed from 17.2m in the interim report to 21.5m in this report
-In the interim report foundation stability was examined based on the ship collision force 23.3 MN, which is slightly refined 23.7 MN in this report.
-In the interim report current market prices in Japan were used for estimating the indicative cost of steel girder bridge (US$5,000/ton including materials, fabrication, transport, erection). It would have to be re-estimating taking into consideration the possible case of internationally prevailing market prices (US$3,800/ton including materials, fabrication, transport, erection).
Girder Depths and Bridge lengths
Bridge TypeGirder Depth at mid spanAprox. Bridge length
PC Box Girder(Span 160m)4.8m5,680m
PC Extradosed(Span 180m)3.3m5,580m
PC Cable Stayed(Span 200m)1.85,480m
Indicative cost by Bridge type without Railway
Bridge TypeUnit cost/mBridge lengthIndicative costPC Box Girder(Span 160m)US$99,0105,680m562 million US$
PC Extradoses(Span 180m)US$91,6205,580m511 million US$
PC Cable Stayed(Span 200m)US$109,6405,480m601 million US$
Reduced river widths by bridge type
Bridge TypeNumber of Piers in the riverPier width per eachReduced river width% Reduced river widthPC Box Girder(Span 160m)3415.0m510m9.6%PC Extradoses(Span 180m)3115.0m465m8.8%PC Cable Stayed(Span 200m)2816.20m454m8.6%
Present river width in 2004=approx. 5,300m
Total Bridge length
Padma main bridge: 5,400m
Left(North) bank Viaduct: 60m
Right(South) bank Viaduct: 120m
Total tength: 5,580m
Specific bridge type and alternatives for preliminary design
PC extradosed girder Type Bridge has been selected for the main bridge structure of the Padma Bridge from the view points of less construction cost, aesthetics and river aspect. In addition Bangladesh side requested the study team to include alternative options that has cable stayed girder at the center portion of approximately 800m in length. As a result the following five alternatives will be examined in the preliminary design of the study:
Alternative-1(Base case):PC extradosed girder bridge without railway provisionAlternative-2:PC extradosed girder bridge with cable stayed girder at bridge center portion without railway provisionAlternative-3:PC extradosed girder bridge with railway provisionAlternative-4:PC extradosed girder bridge with cable stayed girder at bridge center portion with railway provisionAlternative-5:PC extradosed girder bridge with minimum investment case
Approach & service Roads
-12,163 m long approach roads on the both river banks (213 m at left & 11,950 m at right banks)
- 6 m width service road on both sides along the approach road & 2m lower than that of the approach road
-No of minor bridges on approach roads-6nos (total length=1000m)
-No of culverts (for underpasses for crossing RHD/LGED road) on approach roads-13nos
- 16 -