Pacific Northwest National LaboratoryPrimavera P6 R8 Upgrade
Presented by:• Brian Fitzsimons
1
Date: 10/18/2011
Outline
P6 EnvironmentDriversUpgrade ProcessIssuesLessons Learned
2
Pre-Upgrade P6 EnvironmentVersion: 6.2Costing of resources
Uses PNNL finance web service to cost resourcesOver 170 possible rate options for each resource
3
Importing of actual cost from finance system
Project WBS elements are assigned financial elementsCosts are assigned as resources within the Project WBSCosts are imported monthly and weekly to show traceability
Pre-Upgrade P6 Environment
Update P6 enterprise resource library from HR systemRuns every nightAdds new resourcesMarks old resources as inactive
Industry standard reports
4
Drivers to Upgrade
5
Oracle Fusion Project Portfolio Management (PPM)Early AdoptersRequires R8
New FeaturesTrickle ETL process/Extended tables schemaTimescaled Logic DiagramsSchedule Comparison UtilityImproved Web InterfaceExcel import/export privilegesPlanned Value calculation corrections
Web Interface
6
Additional New Features PNNL not currently using
Team member status toolsEmail status updatesiPhone/iPad status applicationWeb portal status application
WorkflowStandalone version
Traveling with schedulesLimited/Classified access areasLimited network access
7
Terminology
P6/P6 EPPM (Enterprise Project Portfolio Management): Web Interface
P6 Professional/P6 PPM (Professional Project Management): Stand-alone Installation
P6 Optional Client/P6 Professional for EPPM: Windows Client
8
Upgrade Process
9
New WebLogic ServerJBoss no longer supported
Database Upgrade UtilityRe-implement modificationsTesting
IssuesAdministration only on the Web
UsersEPS
Optional Client interface confusionPerformance problem with Earned Value metrics
Fixed in recent service pack
Problem copying activity codes
10
Lessons Learned
More testingActivity code bug found after roll-out
Verify test system before upgrading
11