6
PROJECT STATUS SUMMARY

P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Embed Size (px)

Citation preview

Page 1: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

PROJECT STATUS SUMMARY

Page 2: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Insert Date Presentation Title Goes Here

Sample Project Status/Schedule Summaries

In addition to managing a project plan in Microsoft Project, you may also wish to depict the schedule or project status in a more summarized version for Steering Committee meetings, team meetings, project kickoffs, weekly status reports, etc. These can be tailored to a specific project’s needs:

• Sample 1: Executive View

• Sample 2: Basic Status Dashboard A

• Sample 3: Basic Status Dashboard B

• Sample 4: Excel (Week by Week View)

2

Page 3: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Insert Date Presentation Title Goes Here

Project Status Summary Sample 1

Green Yellow RedOn track; will complete as planned Planned delivery at risk Will miss planned deliveryOriginally planned or completed activityKey Milestone Legend:

1. Kickoff Project

2. Project Phase - TBD

3. Project Phase - TBD

Recent Accomplishments TBD TBD TBD

Upcoming Key Activities TBD TBD

Scope: TBD TBD TBD

Summary

Project Description: TBD

Actual/Estimated

Key Milestones

3

Nov 29

Planned

2

Oct 20

Sept 25

Sept 25

1

1

Sep 2011 Oct 2011 Nov 2011 Dec 2011 Jan 2012 Feb 2012 Mar 2012 Apr 2012

4. Project Phase - TBD

5. Project Phase - TBD

6. Deployment Date - TBD

Aug 2011

6

Mar30

4 5

Jan 29

Mar 15

6

May 1

3

Dec16

2

Nov 1

4 5

Mar30

Apr15

Key Risks and Issues TBD TBD

Required Decisions & Guidance TBD TBD

Gray

3

Page 4: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Insert Date Presentation Title Goes Here

Project Status Summary Sample 2

Summary of Recent Status: TBD

Activities Completed: TBD TBD TBD

Activities In Progress: TBD TBD TBD

Issues/Risks: TBD TBD TBD

Deliverable Owner/Signoff Status Planned/Revised Completion Date Comments

Key Deliverables/Milestones:

Project Name: Current Phase:Project Start: Planned/Revised End:Baseline Budget: % Budget Spent:

Overall Project Status As of <Insert Date>:

4

Page 5: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Insert Date Presentation Title Goes Here

Project Status Summary Sample 3

Planned Timeline / Major Milestones Activities completed since last report

1. Milestone 1

2. Milestone 2

3. Milestone 3

4. Milestone 4

5. Milestone 5

1. Activity 1

2. Activity 2

3. Activity 3

Headlines for next two weeks

1. Headline 1

2. Headline 2

3. Headline 3

Risks/Issues Key Decisions Required

Risks that impact critical Path

Status(R/Y/G)

Issue for R/Y/ MitigatingStrategy

Owner Risks that impact critical Path Owner Date Req’d

Overall Project Status As of xx/xx/xx

Feb 2013

321 4

Oct 2012 Nov 2012 Dec 2012 Jan 2013

Program Manager: _________________

Executive Sponsor: ___________________

5

Page 6: P ROJECT S TATUS S UMMARY. Insert Date Presentation Title Goes Here Sample Project Status/Schedule Summaries In addition to managing a project plan in

Insert Date Presentation Title Goes Here

Project Status Summary Sample 4

Activity by User Type Owner Notes Status

10/2

1

10/2

8

11/4

11/1

1

11/1

8

11/2

5

12/2

12/9

12/1

6

12/2

3

12/3

0

1/6

1/13

1/20

1/27

2/3

2/10

2/17

2/24

Complete UAT Tom In Progress

Confirm list of HR users Tom Confirm totals and types In Progress

Distribute 1st Comm Tom/Mary Not Started

Provide update at HRO meeting Tom Confirm date w/Alfredo Not Started 11/17

Produce & Finalize Training Tom Coordinate with? Not Started

Publish to iLearn Mary Coordinate with? Not Started

Update ITS Materials Tom Coordinate with? Not Started

Distribute 2nd Comm Tom Confirm distro list Not Started

Conduct ILT for Power Users? TBD TBD/confirm who? Not Started

Confirm Support Model Tom Not Started

Distribute Final Comm TBD Confirm distro list Not Started Final

Close-Out Deployment to HR Users TBD Track issues/next steps Not Started

Support Operational ITS Not Started

2011Project # 1 - Phase A

Human Resources Users

2012

6