Mbulelo Kibido General Manager - Transmission ESKOM South Africa

Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

• Mbulelo Kibido

• General Manager - Transmission

• ESKOM

• South Africa

Page 2: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Overview of the presentation

• Investment Allocation Decisions in Transmission

• Grid Expansion Plans (TDP Period 2015 to 2024)

• Cost-Drivers in Grid Expansion

• Summary of the DoE RE Programs 1, 2 and 3

• Constraints to Grid Access post REBIDs 1,2,3

• Strategies to Accommodate Future IPP Projects

• Required Investments to Unlock Connection Capacity

• Conclusion

• Questions ???

Page 3: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Investment Allocation Decisions in Transmission

Page 4: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Transmission Capital Plan for the

TPD period (2015-2024)

Categories FY15-24 (Rm)

Capacity Expansion 145,968

Refurbishment 7,680

Capital spares 2,397

EIA and servitudes 5,150

Strategic 1,066

Production Equipment 519

Total 162,779

Page 5: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Cost-Drivers in Grid Expansion • Load Growth:

o Connection of new and anticipated customer loads

o Resolution of Quality of Supply excursions

• Legal and Regulatory Compliance: o N-1 Reliability Investments

• Power Corridors

• Transformation Capacity

o Mitigation of Fault-level Exceedances (existing and anticipated)

• Integration of New Generation: o Eskom generation new build

o New and anticipated IPP generation

• Land Development: o Securing of Lands Rights and Environmental Authorisations

Page 6: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Summary: DoE REBIDS 1, 2 & 3

Page 7: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Eskom Investment to Enable

REBID 1, 2, & 3 (RM)

Page 8: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Constraints to Grid Access • Servitude Acquisition and EIAs (can take up 24 Months to resolve)

o IPP developments tend to be in close proximity of Eskom substations. This sometimes restricts access to other RE IPP participants due to limited powerline corridors through IPP properties

• Long Lead Times for New Infrastructure (can take up to 7 years):

o Post REBIDs 1, 2, & 3; there is very limited spare capacity on the existing Distribution and Transmission networks. Hence, necessity for deep strengthening.

• High Cost of the Shared Infrastructure (due to requirement for deep strengthening)

o Due to uncertainty of allocation of Preferred IPP Bidders, quotations are issued on an individual basis i.e. no other application is considered in the quotation. This potentially raises the cost of connection per quotation

• CELs issued to IPPs are non-binding but are utilised in the BID price, which is a binding, to the DOE IPP

Page 9: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Required Investment to Unlock

Capacity for Future IPP projects

Page 10: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Strategies to Optimise Infrastructure Requirements for Future IPP Projects

• Develop Renewable Energy Zones”

• Encourage the installation of smaller blocks of PV (e.g. < 50MW) closer to Load Centres

• Avoid Large Projects in Grid-remote areas

• Encourage Projects in Areas with Grid Capacity (Align Projects to GCCA doc)

Page 11: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

23 October 2012 11

Strategic Projects to Unlock REDZ

Page 12: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Wayforward

• Eliminate misalignment in the planning of the IPP programmes

(i.e. continue working with key stakeholders).”

• Special measures and resources

(to accelerate the Transmission infrastructure required for the IPP

programmes; e.g. strategic EIA’s; special funding mechanisms, etc.)

Page 13: Overview of the presentation - ESI Africa...Overview of the presentation • Investment Allocation Decisions in Transmission • Grid Expansion Plans (TDP Period 2015 to 2024) •

Questions ????