Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Delivering on
Integrity
Safety
Value
Quality
Reliability
36 Harries Way
PINJARRA WA 6208
08 9530 4016
Company Experience
Experience
Quality Assured Contracting Pty. Ltd. ( QAContracting ) was established in Mandurah in 1995 by David Cameron,
primarily to provide contract services to the Water Corporation in the Mandurah - Murray, South West and Greater
Southern regions of Western Australia. Due to health reasons, David retired from QAContracting in April 2013
and the company was taken over by Wayne Elliott and Roy Nella. Although David was a significant factor in the
success of QAContracting and the works the company delivered, both Wayne and Roy brought a broad range of
experiences to the company which enabled the company to continue operating as it always has, providing a quality
multi discipline services to its clients.
Some of the works that QAContracting has successfully progressed over the previous years are shown following.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Discharge Pipe Repairs Brownell Crescent Kwinana Waste Water Pumping Station
Client Water Corporation
Client Representative Henry McKinlay
M&E Technical Services
Phone 08 9424 8587
Mobile 0403 584 112
Email [email protected]
Start 14th March 2016
Finish ( Scheduled ) 24th May 2016
QAContracting has been engaged to replace the corroded rising pipework flanges and discharge elbows at the
Brownell Crescent Kwinana waste water pumping station. QAContracting have developed a work methodology
whereby the pumping station can remain online whilst the pipework is replaced removing the need for station
downtime and costly bypass pumping systems.
Brownell Crescent Kwinana WWPS. Flange Replacement. Replacement Elbow.
Installation of an OdaTech Odour Control System to the Bibra Drive Bibra Lake Waste Water Pumping
Station
Client OdaTech Pty. Ltd.
Client Representative Ivan de Souza
Director
Phone 08 93495940
Mobile 0418947 971
Email [email protected]
Start 9th May 2016
Finish ( Scheduled ) 30th June 2016
QAContracting has been engaged to install a new OdaTech odour control system ( OCS ) to the Bibra Drive Bibra
Lake waste water pumping station. The system is an 11 tank assembly and is the largest OCS installed by OdaTech
to date with works scheduled for completion by the end of June 2016.
Bibra Drive Bibra Lake OCS Plan Bibra Drive Bibra Lake OCS Elevation
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Pump Upgrades Byford Waste Water Pumping Stations 1 and 2
Client DMCivil
Client Representative Martin Fisher
Contract Manager
Phone 08 9492 1800
Mobile 0419 000 458
Email [email protected]
Start 21st January 2015
Finish 29th July 2015
QAContracting was engaged to upgrade the pumps in the Byford waste water pumping stations numbers 1 and 2
as part of DMCivil's upgrade works to the local pressure main for the Water Corporation. QAContracting procured
and installed the pumps as well as fabricating and installing a new concrete cover to the number 2 pumping station
meeting the required schedule.
Concrete Cover Formwork. Byford WWPS Number 2. Newly Installed Concrete Cover.
Pump Upgrade Forrest Street Palmyra Waste Water Pumping Station
Client Water Corporation
Client Representative Sajan Samuel
Project Engineer Perth Regional Alliance
Phone 08 9424 8130
Mobile 0417 457 021
Email [email protected]
Start 16th July 2015
Finish 28th August 2015
QAContracting was engaged to upgrade the pumps at the Forrest Street Palmyra waste water pumping station. The
current pumps were overdue for replacement and could not meet the current required output. QAContracting laser
scanned the existing installation to ensure the premanufactured spools would match with the existing flange
orientation errors.
Forrest Street Pumps. Flange Alignment Laser Scanned Image. New Pumps Installed.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Pump Upgrade Mary Street Mandurah Waste Water Vacuum Pumping Station
Client Water Corporation
Client Representative Martin Cornelius
Trades Team Leader Mandurah Murray
Phone 08 9550 3428
Mobile 0407 478 470
Email [email protected]
Start 7th July 2014
Finish 7th September 2014
QAContracting was engaged to install new pumps to the Mary Street Mandurah waste water vacuum pumping
station as the old were badly eroded and not sized correctly for the current duty. The Water Corporation required
the new pumps to be Hidrostals which necessitated a total change to the existing pipework and because the well
could not be readily bypassed without significant risk, the installation was required to be performed as quickly as
possible. QAContracting premanufactured all of the pipework and installed the pumps simultaneously over a
period of three days, well within the five day schedule and with no installation or safety issues.
Previous Installation. Workshop Preassembly.
New Installation
New Installation. New Installation
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Pump Upgrade Swanbourne Street Fremantle Water Booster Station
Client Water Corporation
Client Representative Mark Hadfield
Area Coordinator Mechanical Electrical Perth Regional Alliance
Phone 08 9423 7852
Mobile 0419 362 504
Email [email protected]
Start 21st January 2015
Finish 9th March 2015
QAContracting were given the works to install new pumps to the Swanbourne Street Fremantle water booster
station as the old pumps were not sized correctly for the current duty and were transferring vibration and noise
through the piping system resulting in customer complaints. The installation needed to be done as quickly as
possible with no interruption to fresh water supply services. To ensure there was no risk to the local water supply,
QAContracting premanufactured all of the pipework utilising jigs to remove problems due to flange misalignment
and installed the pumps on two separate days over a two week period with no installation or safety issues.
Previous Installation. Workshop Preassembly.
New Installation. New Installation.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Tank Floating Roof Demolition Kwinana Waste Water Treatment Plant
Client Water Corporation
Client Representative Ray Trinder
Plant Manager Kwinana Mandurah Operations
Phone 08 6330 6385
Mobile 0437510441
Email [email protected]
Start 10th May 2013
Finish 6th June 2013
QAContracting were awarded the works to demolish and dispose of the steel tank floating roof which was located
at the Kwinana Waste Water Treatment Plant ( WWTP ). The roof was systematically cut up using oxy acetylene
into manageable sizes and all steel delivered to the local scrap merchant for recycling. The roof was part of the
redundant equipment located at the treatment plant which QAContracting has proposed to demolish over a period
of three years, providing the Water Corporation with a milestone schedule and budget breakdown to assist with
their planning.
Redundant Tank Floating Roof. Wall Demolition.
Roof Demolition. Roof And Concrete Ring Demolition And Removal.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Installation of the OdaTech Odour Control System to the Busselton Waste Water Treatment Plant
Client OdaTech Pty. Ltd.
Client Representative Ivan de Souza
Director
Phone 08 93495940
Mobile 0418947 971
Email [email protected]
Start 28th May 2013
Finish 25th September 2013
QAContracting provided design, fabrication and installation services to OdaTech Pty. Ltd. who are a preferred
supplier of odour control systems to the Water Corporation. Liaising directly with Tenix and on behalf of OdaTech,
QAContracting installed an eight tank biomedia odour control system to the Busselton WWTP as part of the plant
upgrade. QAContracting were responsible for all installation activities ranging from the transport of components,
erection, installation of biomedia to the vessels and commissioning. QAContracting also designed and supplied
the pipe supports and the 8 meter self standing fibreglass reinforced plastic ( FRP ) stack.
Pipe Supports Specification Drawing. Fibre Reinforced Polymer Stack Construction.
Installation Of Centre Piping. Operational OdaTech Odour Control System.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Installation of Concrete Steps to the Caddadup Waste Water Treatment Plant
Client Water Corporation.
Client Representative George Kemshall
Operations Supervisor Waste Water Treatment Branch
Phone 08 9550 3426
Mobile 0417185585
Email [email protected]
Start 8th May 2013
Finish 8th August 2013
QAContracting were engaged to construct a set of concrete steps and associated pathways to the Caddadup WWTP.
QAContracting developed a specification and drawings based on Water Corporation standards which enable the
works to progress seamlessly with no issues.
Caddadup Stairs Location. Stairs And Handrail Specification Drawing.
Reinforcement Specification Drawing. Completed Stairs And Concrete.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Installation of the OdaTech Odour Control System to the Coodanup Waste Water Pumping Station
Client OdaTech Pty. Ltd.
Client Representative Ivan de Souza
Director
Phone 08 9349 5940
Mobile 0418947 971
Email [email protected]
Start 28th May 2013
Finish 25th September 2013
OdaTech Pty. Ltd. was engaged directly by the Water Corporation to install their proprietary odour control system
to the Wanjeep WWPS located in Coodanup. As OdaTechs' installer, QAContracting managed the complete works
liaising directly with local Water Corporation personnel to ensure all parties were aware of the works progress and
all approvals were in place. QAContracting installed the complete system whilst also supplying the concrete pad,
fencing, exhaust stack, sprays, drainage, ventilation, electrical components and connection plus coring of the well.
QAContracting further assisted with commissioning and training to ensure the system operated as designed and
the handover to the Water Corporation progressed with no problems.
Coodanup Waste Water Pumping Station. Concrete Pad Directly Prior To Pour.
Biomedia Tanks Charged And In Place. Operational OdaTech Odour Control System.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Modifications to the Mandurah Garden Estate Pressure Reducing Valve Station
Client Water Corporation.
Client Representative David Podmore
Operations Coordinator Mandurah Murray
Phone 08 9550 3404
Mobile 0408 400 633
Email [email protected]
Start 7th June 2013
Finish 12th July 2013
During the winter months, the Mandurah Garden Estate pressure reducing valve ( PRV ) would become flooded
with ground water causing access issues for Water Corporation operations personnel. QAContracting elevate the
valve arrangement and relocated the existing walkway to make the installation accessible all year round. The
manifolds required to elevate the PRV were measured, drawn, then remeasured to confirm accuracy and to ensure
the PRV could be quickly elevated with minimal installation time and loss of water supplies to the local consumers.
The installation was progressed with no problems for a total isolation time of 45 minutes.
Mandurah Gardens Pressure Reducing Valve. New Pipe Risers Drawing.
Pipe Risers Installed. Pressure Reducing Valve Modifications Completed.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Installation of Falls Protection System to Rockford Street Waste Water Pumping Station
Client Water Corporation.
Client Representative Tony Addicoat
Project Manager Great Southern and Southwest Region
Phone 08 9791 0478
Mobile 0429 116 442
Email [email protected]
Start 1st March 2013
Finish 15th May 2013
QAContracting is a Water Corporation contract panel member for the Fabricate and Install of Prevention of Fall
Equipment. As a panel member, QAContracting has successfully installed prevention of falls equipment to over
20 pumping stations of which Rockford street is the most recent. Works included the supply and installation of
stainless steel grates, installation of receptacles to existing concrete plus installation of a davit base and new
concrete mass. QAContracting also replaced the existing galvanized pump rails with stainless steel whilst installing
the falls protection system.
Rochford Street Waste Water Pumping Station. Unguarded Pump Pit.
Prevention Of Falls Grates And Mounts Installed. Completed Waste Water Pumping Station.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Replace MSCL Piping at Bridgewater Waste Water Pumping Station
Client Water Corporation.
Client Representative Martin Cornelius
District Fitter Mandurah Murray
Phone 08 9550 3428
Mobile 0407 478 470
Email [email protected]
Start 23rd May 2012
Finish 28th June 2012
QAContracting was tasked with removing and replacing the badly corroded pumping system at the Bridgewater
WWPS. Works involved installing a bypass system to maintain flow then removing the existing pump set, valves
and discharge piping to be replaced with new. All works were progressed to Water Corporation standards and finish
to ensure the system operates trouble free and in excess of its intended life.
Corroded Valve. New Pressure Main.
Refurbished valve pit. Remediated Work Area.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Repair Water Tanks at Yarloop Water Treatment Plant
Client Water Corporation.
Client Representative Mick Adams
Project Manager South West Region
Phone 08 9791 0411
Mobile 0409080154
Email [email protected]
Start 30th August 2012
Finish 8th November 2012
During inspections of the water storage tanks at the Yarloop Water Treatment Plant ( WTP ) it was discovered that
a number of roof columns were corroded and in danger of collapsing. QAContracting was engaged to replace the
corroded columns and any damaged roof beams that were found plus clean the vessels. During the repairs,
additional problems were found which included corroded overflow pipes and corroded access ladders.
QAContracting subsequently replaced the overflow pipes with PVC pipe and replaced the existing steel ladders
for FRP units. Swing gates were also added to the roof access ladder to improve safety during access and egress.
Yarloop Water Treatment Plant Tank. Corroded Roof Support.
New Roof Support Columns. New Overflow Pipe.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Key Personnel
Wayne Elliott B.Eng. B.Com. MIEAust.
Wayne Elliott is a professional Mechanical Engineer who also holds a
further degree in Commerce ( Finance ) and a trade qualification as a
Mechanical Fitter. He has extensive experience across a broad range of
fields including asset management and maintenance, engineering design
and drafting, contract services, project engineering and project
management. Wayne is a Director and the General Manager of
QAContracting whilst also providing project and engineering management
support to QAContracting's operations. A member of the Institute of
Engineers Australia ( IEAust. ), Wayne is equally at home applying
engineer theory to design a piece of equipment or operating a skid steer
loader assisting the execution team to deliver their works to budget and
schedule.
Wayne Elliott
Director / General Manager
Some of the works Wayne has managed prior to taking over QAContracting include the following.
2012Transfield Alcoa Pinjarra – Project Engineer
Number 7 Secondary Thickener Tank Repairs.
Replace Corroded Roof Truss.
2011 Transfield Alcoa Pinjarra – Project Engineer
30A3 Spent Liquor Tank Reconstruction.
Tank Demolition and Reconstruction.
2011 Fluor Alcoa Pinjarra – Project Engineer
125L Diesel Tank Flat Bottom Tank Inspection.
Design And Install 1 Kilometre Diesel Transfer
Piping.
2009 Terex – Reliability Engineer
MT6300 Reliability Issues.
Investigate Recurring Component Failures.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Matthew Bee MPE. GradIEAust.
Matthew Bee
Project Engineer / Mechanical Engineer
Matthew Bee is a graduate Mechanical Engineer with a Master’s
Degrees from the University of Western Australia. He is a member of
the Institute of Engineers Australia (IEAust) and has experience in
several fields from Mining Operations and Alumina Refining to
domestic construction work. Matthew has a thorough understanding
of mechanical engineering principles and good administrative practices,
along with significant hands-on labouring experience.
Some of the works Matthew has been involved with prior to taking on his position with QAContracting include
the following:
2016 Alcoa WAO – Engineering Vacation Student.
Calciner Alliance Team for all WA refineries.
ESP Inspection and troubleshooting.
2016 UWA Final Year Thesis project.
Finite Element Modelling of Chopped Aramid fibre
adhesive joint toughening in Carbon Fibre composites.
2015 Alcoa Huntley – Engineering Vacation Student.
Payload Management System/Lifting Jig design.
Improve payload data & system utilisation.
2011-2016 Port Form Construction – Labourer.
Commercial & Industrial Construction around Perth.
Formwork, Concreting & Tilt-Up Panel Construction.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Frank Wheel B.Eng. CPEng. MIEAust.
Frank Wheel is a qualified Mechanical Engineer who has attained the
title of Chartered Professional Engineer ( CPEng. ) as recognized by the
Institute of Engineers Australia ( IEAust. ). Frank has many years'
experience in the field of Mechanical Engineering with a particular
emphasis on project management and concrete structures. Frank is
QAContracting's Office Manager, overseeing all aspects of the companies'
administration including company processes and procedures. In addition to
his Office Managers role, Frank is also the primary lead for
QAContracting's quality assurance system and ISO 9001 accreditation.
Frank Wheel
Office Manager
Some of the works Frank has managed prior to taking on his position with QAContracting include the following.
2011 Fluor Alcoa Pinjarra – Project Manager.
35C Condensate Storage Tank.
Flat Bottom Tank Inspection and Repairs.
2011 Fluor Alcoa Pinjarra – Project Manager.
6C2 Caustic Storage Tank.
Flat Bottom Tank Inspection and Repairs.
2010 Fluor Alcoa Pinjarra – Project Manager
Ball Mill Cooling System.
Replace Cooling Towers.
2009 Rapley Wilkinson – Concrete Manager.
Seashells Resort Mandurah.
Apartment Building Construction.
Quality Assured Contracting Pty. Ltd. ACN 071 696 743 ABN 41 071 696 743
Referees
Ivan de Souza Ray Trinder
Director Plant Manager
OdaTech Pty. Ltd. Water Corporation Kwinana Mandurah Operations
Phone 08 9349 5940 Phone 08 6330 6385
Mobile 0409 841 510 Mobile 0437510441
Email [email protected] Email [email protected]
Gary Adlam
Operations Manager
Water Corporation Mandurah Murray
Phone 08 9550 3408
Mobile 0417 944 309
Email [email protected]