59
Other Considerations Proposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal Aid Project No. 0755 095 1 April 18, 2011

Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Embed Size (px)

Citation preview

Page 2: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

IntroductionAwareness/Approach to Project Proposed StaffingOther ConsiderationsQuestions & Answers

Agenda

Awareness/Approach to Project

Page 3: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Introduction

Awareness/Approach to Project

IntroductionProviding CEI service for 26 yearsPrimary service is CEI – “It’s What We Do”Serve as extension of District 1 – eyes & ears“Pro-Active” approach – manage changeServe as a catalyst to the construction processExercise independent professional judgmentPartnering – formal or informalAlways listening & learning

Page 4: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to projectUnderstanding of scope of projectIdentification of unique project issuesInnovative concepts

Awareness/Approach to Project

Awareness/Approach to Project

Page 5: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Adding Lanes to the inside• Bridge Widening

Tucker’s Grade Alligator Creek

• Weigh-in-Motion Stations• RTMC Coordination• Drainage Design• Environmental Concerns

Awareness/Approach to Project

Awareness/Approach to Project

Page 6: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project • Adding Lanes (Inside) / Milling and

Resurfacing• Cross Slope Correction – Control Point• Emergency Median Opening

Issues/Solutions

Awareness/Approach to Project

Awareness/Approach to Project

Page 7: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project • Overbuild Details (TCP Plan Sheet 179)

Issues/Solutions• Asphalt Quantities

Awareness/Approach to Project

Awareness/Approach to Project

Page 8: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Bridges at Tucker’s Grade

Issues/Solutions• Pier Construction• Bolted Field splices• Coating/Painting (BCI)• Erection Plan• Grades/Elevation• Details

Awareness/Approach to Project

Awareness/Approach to Project

Page 9: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Bridge at Tucker’s Grade

Bats

Issues/Solutions

Awareness/Approach to Project

Awareness/Approach to Project

Page 10: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Bridge over Alligator Creek

Issues/Solutions

Awareness/Approach to Project

Awareness/Approach to Project

Page 11: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Alligator Creek is a Class I Waterway

Issues/Solutions• Permits• Turbidity

Awareness/Approach to Project

Awareness/Approach to Project

Page 12: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Weigh-in-Motion Stations (WIM)

Issues/Solutions• Locate Conduits / Flag Pull Boxes• Straightedge between new pavement and

concrete• Minimize disruptions• Time Lines

Awareness/Approach to Project

Awareness/Approach to Project

Page 13: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• RTMC Coordination (SWIFT)• High Mast Lighting

Issues/Solutions• Locate Conduits / Flag Pull Boxes

Awareness/Approach to Project

Awareness/Approach to Project

Page 14: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Drainage Design

Issues/Solutions• Retention Pond (1) at Tucker’s Grade• Attenuation (7) and Treatment (16)• 10 Outfalls to Alligator Creek• 18” Jack & Bore

Awareness/Approach to Project

Awareness/Approach to Project

Page 15: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Ditch Blocks (9) and weir structures

Issues/Solutions

Awareness/Approach to Project

Awareness/Approach to Project

Page 16: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of ProjectEnvironmental (Brian Monkelbaan – FDOT)• Protected Species (FWC)

Issues/Solutions Bats Bald Eagle Eastern Indigo Snake Gopher Tortoise Sand Hill Crane American Alligator Burrowing Owl Florida Scrub Jay

Awareness/Approach to Project

Awareness/Approach to Project

Page 17: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of ProjectEnvironmental (Brian Monkelbaan – FDOT)• Permits (general and specific conditions)

Issues/Solutions• Stormwater Pollution Prevention Plan• DEP• NPDES

Notice of Intent Contractor/subcontractor certification forms Inspection reports

Awareness/Approach to Project

Awareness/Approach to Project

Page 18: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Earthwork

Issues/Solutions• 27,000 CY Regular Excavation• 49,000 CY Embankment• Access to Median Plan

Awareness/Approach to Project

Awareness/Approach to Project

Page 19: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Guardrail and Cable Barrier

Issues/Solutions• Guardrail - 1,194 LF Remove, 2,076 LF

Replace• Cable Barrier – 14,950 Remove, 17,586

Replace

Awareness/Approach to Project

Awareness/Approach to Project

Page 20: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Asphalt

Issues/Solutions• 6,700 tons of overbuild• 6,400 tons on existing lanes• 24,000 tons on new lanes• Superpave Traffic Level E• Friction course FC-5

Awareness/Approach to Project

Awareness/Approach to Project

Page 21: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Utility Relocation/Coordination

Embarq Florida Power & Light FDOT Statistics Office, ITS (SWIFT), and

Motor Carrier Compliance Charlotte County Public Works City of Punta Gorda - Utilities

Awareness/Approach to Project

Awareness/Approach to Project

Page 22: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Issues/Solutions

FP&L Relocation at Tucker’s Grade High Mast Lighting conflict at Pond

Awareness/Approach to Project

Awareness/Approach to Project

Page 23: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• Landscaping

Issues/Solutions• Cocoplums• Wildflowers• Wax Myrtles• Live Oaks• Sabal Palms• Bald Cypress Trees

Awareness/Approach to Project

Awareness/Approach to Project

Page 24: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of ProjectKey elements of the project• Maintenance of Traffic (MOT)

Issues/Solutions• Three (3) Phases

Phase I: Signs, mill resurface outside shoulders, bridge foundations and Piers

Phase II: Signs, shift traffic, drainage, inside widening, bridge work and guard rail

Phase III: Shoulder gutter, mill & resurface, place friction, final pavement markings

• ADT = 52,600• Lane Closure Restrictions 6PM – 6AM• Traffic on milled surface is NOT allowed

Awareness/Approach to Project

Awareness/Approach to Project

Page 25: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

Key elements of the project• FHWA

Issues/Solutions• Coding SA’s and Work Orders• Process and Procedure

Awareness/Approach to Project

Awareness/Approach to Project

Page 26: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

CEI Scope of work• Preconstruction

Constructability review Bid-ability review Bid tabulations Preconstruction conference Schedule pre-services meeting Schedule Final Estimates meeting Schedule District Compliance meeting Schedule meeting with materials office Schedule Environmental meeting

Awareness/Approach to Project

Awareness/Approach to Project

Page 27: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

CEI scope of work• Preconstruction (cont.)

Prepare and submit computer access requests

Attend Site Manager/ EDMS information meeting

Partnering meeting / DRB Videotape pre-construction conditions Pre-construction survey Office set-up Review contractor’s CPM schedule Review contractor’s QC plan Set up field books, office files, and

documentation

Awareness/Approach to Project

Awareness/Approach to Project

Page 28: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

CEI scope of work• During construction

MOT review Inspection of contractor’s work Materials sampling Density testing Environmental monitoring Measurement of pay item quantities Contract administration

Awareness/Approach to Project

Awareness/Approach to Project

Page 29: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

CEI scope of work• During construction (cont.)

CPM reviews Contractor quality control (CQC) Pre-Activity Meetings Critical Time lines Project photographs and video Emphasis on INSPECTION!

“You get what you INSPECT not what you EXPECT”

Awareness/Approach to Project

Awareness/Approach to Project

Page 30: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Understanding of Scope of Project

CEI scope of work• Post Construction

Final Estimate Materials Certification Permit Closeout As-builts Outstanding Issues and Claims

Awareness/Approach to Project

Awareness/Approach to Project

Page 32: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Identification of Unique Project Issues

Ramp Detours (Plan Sheet 184)• Southbound Off Ramp at Tucker’s Grade• Coordination with Charlotte County

Chuck Koons Barry Cohen

• Railroad Crossing Harry Neaves

Awareness/Approach to Project

Awareness/Approach to Project

Page 33: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Identification of Unique Project Issues

Airport Golf CourseSpeed

Awareness/Approach to Project

Awareness/Approach to Project

Live TrafficSpeed: 78mph

Page 34: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Identification of Unique Project Issues

Charlotte County Airport

Awareness/Approach to Project

Awareness/Approach to Project

Page 35: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Identification of Unique Project Issues

Blue Heron Pines Golf Club• Noise abatement and dust control

Awareness/Approach to Project

Awareness/Approach to Project

Page 36: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project

CPM schedule goes here

Awareness/Approach to Project

Page 37: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Plans Review

Awareness/Approach to Project

Awareness/Approach to Project

Issue Solution ResultThe Phase IV plans contain the requirements for 100% EDC Monitoring Devices.

We suggest that the direction given in Design Bulletin C11-03 be implemented prior to completing the Contract Plans. Because this project is anticipated to let in June of 2011, the first option (SDG 3.5.10.F) in C11-03 is recommended, which includes the listing of ONE EDC in the pay item list and coordination with the Specifications office to include SP4550512 in the Specifications Package

Potential Cost Savings of approximately $2,500 per each of the 64 piles resulting in a possible savings of $160,000

For the Tucker's Grade bridges, test pile lengths are not intended to reach the lime rock layer near elevation -120-ft, but it is intended to reach the sand layer near elevation -70. The existing bridge piles were driven to much shorter lengths of approximately 75-ft to the first sand layer near elevation -45, due to the lighter pile loads and smaller pile size (18”). Some hard driving will be required to reach tip past this first hard layer of sand.

Recommend coordination with Geotechnical Services to minimize potential of damaging piles during the hard driving.

Prevents potential time overruns.

The Alligator Creek Bridge reveals that the 120-ft test pile length is short of the rock layer near elevation -105 for that bridge. Bridge widening will be constructed on Pile Bents (not multi-pile footings) and the pile loads are 25% greater for the Alligator Creek Bridge than the Tuckers Grade Bridge.

Recommend that the test pile lengths be set in order to reach the lime rock layer.

Prevents significant overruns of pile quantities during construction

Page 38: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Plans Review

Awareness/Approach to Project

Awareness/Approach to Project

Note 5 on Sheet B-4 indicates that the Contract has a choice of welding the shear studs in the shop if 100% fall protection is provided. This used to be an option, but DCE Memo 03-10 clarified that OSHA no longer allows this practice.

Recommend this note be deleted and the Specifications Package includes the proper requirements, per DCE Memo 03-10.

Ensures compliance with the Specifications

The footings for the Tuckers Grade Bridge are large enough in every dimension to just qualify for the Mass Concrete designation. The EOR has smartly specified Class II (3,400 psi) concrete for the footing, which would reduce core temperatures and reduce the need for Mass Concrete measures, and thus has not specified the Mass Concrete Pay Item.

We recommend that a note be added to warn the Contractor that if another class of concrete is proposed, say to achieve high early strength, that a mass concrete plan will be required to be submitted by the Contractor and approved by the State Materials Office.

Will save potential time lost to approve mass concrete plan.

In the plans for the Alligator Creek Bridge, that the existing deck is only 7 ½” thick. For this reason, the plans prohibit the use of SIP forms between the new and existing girders. Use of SIP forms there would reduce the Load Rating for the existing Girders. Related to this issue is the plan requirement for 4” horizontal build-up shown on Sheet B2-20. Examination of the existing bridge plans reveals that this 4” horizontal build-up was waived during the original construction; and it is likely the Contractor will request that waiver on this project to make wood forms more compatible with standard wood form hangers.

We do not specifically recommend removal of the note, but recognize that our TEAM will coordinate this issue with District Structures Design and we will ensure that the side of the girder top flange is properly painted before the deck pour.

Ensures compliance with the Specifications

An existing high mast light pole is in conflict with the new pond construction.

Recommend that the EOR address this issue prior to bid and either include a means of relocating the light pole or revising the pond construction to avoid it.

Prevents delays associated with the pond construction.

ITS conduits are in possible conflict with the ditch construction.

Recommend locating all facilities so that conflicts can be addressed prior to construction.

Prevents delays associated with ditch excavation.

Page 39: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

LeadershipDecision MakingTwo Professional EngineersTake Ownership of the ProjectCohesive TeamPartnering

Page 40: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Public InvolvementPublic contact logTracker lettersFDOT Public Information officeProject website

Page 41: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Timely CompletionBudget

Value engineeringElimination of unnecessary workManagement of CEI contractTroubleshootingProblem-solving ability

Page 42: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Documentation• Daily reports of

construction• Controlling items of

work• MOT reports• Summary of daily

reports• EDMS / Hummingbird• Issues and RFI logs• Meeting Minutes

• Field books• Density log books• Pile logs• Jobsite photographs• Site Manager• LIMS• CPPR (CIM

Reporting)

Page 43: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Change Orders, Claims and Unforeseen Work

Proactive claims avoidanceSupplemental agreementsEngineer’s estimate / entitlement analysis

Page 44: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Quality Review ScheduleAt project start up• Quality Assurance Plan submitted to FDOT

within 30 days after Notice to Proceed.• Initial QA Review within first 60 days

Six-month QA reviewsWritten report to FDOT PM, Nikesh Patel, P. E. within 14 days after review.

InspectorSenior

Inspector

Project Administra

tor

Senior Project

Engineer

Corporate Quality

Assurance Manager

Contract Support

Specialist

Page 45: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Innovative ConceptsProject Operation Plan• Developed prior to project start• FDOT job guide schedule• FDOT guidelists

Critical Time Lines

Page 46: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Innovative Concepts (10 Points)

Dailies summary spreadsheet“Contractor-Caused Delay” File

Activities

Date Cont

ract

Day

Wea

ther

No

Wor

k - H

olid

ay

No

Wor

k - O

ther

Tim

e Ex

tens

ion

Road

Tim

e Ex

tens

ion

Brid

ge

Description of Activities Prim

e Co

ntra

ctor

Subc

ontr

acto

r 1

Subc

ontr

acto

r 2

Subc

ontr

acto

r 3

Utility Comments Comments/Delays/ Issues9/29/2003 1 Prime began mobilizing equipment.9/30/2003 2 1 No work10/1/2003 3 Construction warning signs placed.10/2/2003 4 1 No work10/3/2003 5 1 No work10/4/2003 6 1 No work10/5/2003 7 1 No work10/6/2003 8 Prime began mobilizing materials 410/7/2003 9 Began Clear & Grubbing, and staked silt fence installation. 810/8/2003 10 Continued clear& grub and staked silt fence inst. ,barricades delivered. 910/9/2003 11 Continued clear & grub and staked silt fence inst. , relocating Rdwy signs. 9

10/10/2003 12 Continued clear & grub 910/11/2003 13 1 No work10/12/2003 14 1 No work

10/13/2003 15Installing Stabilized Subgrade for Phase 1 temp. detour, conti. Silt fence install, (Night) Attempted to place HMA for temp. detour. 17 8 Locating FM&WM

Prime stopped paving operation due to yielding subgrade.

10/14/2003 16Brdg. Crew preparing for temp. barrier wall placement(Imp.rv.brdg.) . Rd. crew inst. Temp. base for detour 1, and conti. Silt fence inst. 13

Repairing washouts (Lt. sta. 1280+00~130+00)

Prime hauled in base rock to correct problem with yielding

10/15/2003 17Conti. Inst. Of temp. base inst for detour, clear & grub, and silt fence inst. (Night) - Conti temp base inst , and resumed HMA inst for detour. 18 8

Cont washout repair. Locate FM & WM (RT STA

WorkersContract Time Comments

Page 47: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Awareness/Approach to Project

Awareness/Approach to Project

Innovative ConceptsCPM Snapshot

Page 48: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project Proposed Staffing

Proposed Staffing

Proposed StaffingQuantity Proposed Qualifications/Certifications/Availability of Staff Quality/Experience on Similar Projects Team’s Past Performance on Similar Projects

Page 49: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project Proposed Staffing

Proposed Staffing

Page 51: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project Proposed Staffing

Proposed Staffing

Qualifications/Certifications/Availability of Staff

Page 52: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project Proposed Staffing

Proposed Staffing

Quality/Experience on Similar ProjectsiRox, District 1 I-75 at Alico Rd Interchange. District 1I-75 at Golden Gate Parkway, District 1I-75 Grouping, Broward County, District 4SR 9 / I-95 Grouping, Broward County, District 4I-95 Design Build, Broward County, District 4I-95 / I-295 Interchange, Duval County, District 2I-95 Widening Heckscher Dr. to SR 9A (I-295), District 2I-595 Milling / Resurfacing, Broward County, District 4I-95 HOV lanes, Palm Beach County, District 4I-295 / I-10 Interchange, Duval County, District 2I-75 Widening and Weigh-in-Motion Station, District 2

Page 53: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed StaffingAwareness/Approach to Project Proposed Staffing

Proposed Staffing

Past Performance of TeamThe proposed Team is currently working together on the Jolley Bridge project as currently holds a grade of 3.4

Four phases of Team Development

Forming Storming Norming Performing

Page 54: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Other ConsiderationsCommunication AbilitiesCommitment to Satisfy FDOT Needs

Other Considerations

Agenda Other ConsiderationsAwareness/Approach to Project

Page 55: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Communication AbilitiesCell phones with email capabilityCentralized Computer NetworkEmail – Laptops, air cards – mobile officeProject website Dailies summaryCPM snapshot – brings the job to youCommunication with all project stakeholders

Other Considerations

Agenda Other ConsiderationsAwareness/Approach to Project

Page 56: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Commitment to Satisfy Department Needs

Local Office Locations on Taylor Road

Other Considerations

Agenda Other ConsiderationsAwareness/Approach to Project

Page 57: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Commitment to Satisfy Department Needs

History of success• Superior LOCAL Staff that is currently

working together

Efficient Project DeliveryCustomer satisfaction• Timeliness and Accuracy

ValueCommitment to meet Interstate Resident Office Goals

Other Considerations

Agenda Other ConsiderationsAwareness/Approach to Project

Page 58: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Why Eisman & Russo ?

Committed to District 1

Responsive to Departments Needs

Provide Experience at all levels

Take ownership of projects

“CEI is what we do”

Page 59: Other ConsiderationsProposed Staffing Oral Technical Presentation CEI Services for I-75 from Tucker’s Grade to North Jones Loop FM No. 413042-3-62-01 Federal

Other ConsiderationsProposed Staffing

Questions