    The Prominent Hill operation comprises

    both an open pit mine and a newly

    developed underground operation with a

    10Mtpa milling capacity. Prominent Hill

    produces some of the worlds highest

    grade copper concentrates. The site

    is a fly-in/fly-out operation employing

    approximately 1,200 employees and

    contractors.

    Simultaneous reline of SAG and ball mills completed

    with zero harm at Prominent Hill

    Organisation

    Oz Minerals

    Site

    Prominent Hill, South Australia

    Year

    2010

    Application

    Copper-Gold concentrate

    Challenge

    Prominent Hills first simultaneous reline Shutdown and relining concurrent with other

    major works on site

    Working within high foot traffic footprint

    Site had only one reline machine

    Solution

    Highly specialised Outotec team perform mill

    relining and maintenance works

    Result

    Reline completed on time and on budget

    Incident free (zero harm)

    Pneumatic torque unit being used to tighten bolts.

  • 8/12/2019 OTE OIA Prominent Hill Web Eng

    2/4

    Installing a new shell lifter on the SAG mill using the reline machine.

    Project overview

    Prominent Hills high grade ore production guidance

    for 2013 is between 90,000-95,000 tonnes copper and

    130,000-150,000 ounces gold. The newer Ankata

    underground mine produces ore with similar

    metallurgical characteristics as the original Malu open

    cut mine, allowing the two run-of-mine ores to be

    blended together.

    Prominent Hill engaged the specialised mill relining

    capabilities of the former TME Group, now part of Outotecs

    Services division, to perform the mills first dual shutdown

    since installed in August 2008. Both the SAG and Ball mill

    were scheduled for simultaneous relining to take place

    early in 2010, to replace the worn liners.

    Mill reline scope

    As the mill liners had originally been installed by

    the Outotec team (then TME), they were aware of

    the technical specifications. A subsequent site

    audit facilitated assessment of the worn linings,additional works required and any constraints in the

    working area. Originally the client anticipated the

    replacement of only the shell lifters, feed end lifters

    and plates and discharge grates on the 34 SAG mill.

    However, following inspection, the scope of works

    was extended to include replacement of all the shell

    plates, along with the discharge end outer grates.

    The 24 ball mill also required feed end outer and

    inner plates, as well as shell and discharge plates,

    to be replaced.

    Process

    A team of 56 specialised personnel took part in the

    reline works which involved the replacement and

    removal of over 1200 parts, with each mill taking less

    than 73 hours to complete. Skilled personnel and

    purpose designed equipment are critical in reducing

    reline time and ensuring safety.

    Many of the mill reline personnel have worked together

    for almost a decade and are all qualified specialists in

    their field with a reputation for expediency, innovation

    and safety. The reline team have worked on thecomplete range of mill types and lining configurations

    for gold, copper, lead, zinc, uranium, nickel, diamond

    and cement mills.

  • 8/12/2019 OTE OIA Prominent Hill Web Eng

    3/4

    The project managers worked closely with the client

    to manage the critical path. This continual focus on

    reducing reline incurred downtime ensured completion

    within the planned shutdown schedule. This was

    accomplished by expertise in planning, monitoring and

    evaluating the shutdown timetable as well as utilising

    Short Interval Control, a bespoke programme used

    to track the progress of reline tasks. The programme

    provided up-to-the minute information including parts

    moved, time lost, estimated time of completion and

    took all delays into account.

    Challenges

    To make optimal use of the shutdown period, Prominent

    Hill scheduled two major maintenance works by other

    teams to be carried out in addition to the relining project.

    During the works, the mill deck was therefore subject

    to high foot traffic and equipment congestion. As such,

    it was critical to ensure that strict safety standards

    were adhered to and a strong working relationship

    forged with mill staff and the other work forces on

    site. This had proven results in that the job was

    completed without incident or injury to the teams

    or equipment.

    As site had only one mill reline machine available,

    completion time would essentially have been doubled

    if works had to be performed consecutively. To combat

    this, the Outotec team worked around the clock to

    complete the SAG mill and used a boom crane to remove

    all of the dismantled lining from the ball mill until the

    reline machine became available. Utilising available

    resources in this way saved additional downtime and

    ensured the project was completed to deadline.

    Additional minor works were identified and completed

    as the job proceeded, including assisting with the

    isolations, set up on the mill and installation of the

    Davit crane. Also, the discharge end and trunnions gaps

    were filled with ceramic.

    Safety first

    Health and safety on-site is a primary objective for

    any project and during the mill reline the Outotec

    team ensured strict standards were adhered to. At thebeginning of each shift a pre-start and toolbox meeting

    was held, with site safety inspections conducted per

    shift. Prior to shutdown, safety performance was

    discussed in detail and the actual shutdown closely

    monitored, resulting in a safe procedure without

    incident.

    One area that existed within the former TME Group

    was a Safety and Training operation. Transfer of the

    licenses are due for completion in 2013, allowing the

    Registered Training Organisation (RTO) capability to

    be incorporated into Outotecs remit. This fast-track,

    industry-specific training ensures highly qualified

    personnel are always available and readily expedited

    to site.

    Results

    Through efficient planning and a strong working

    partnership with Oz Minerals and site, Prominent Hills

    first simultaneous shutdown of the SAG and Ball mill

    was executed on site with zero harm to personnel,

    equipment or the environment.

    Outotec was also on-site for the mill restart, completing

    the retorque of the bolts for both mills after the first day

    of operation.

    Feedback from site was very positive, with Graham Dearing,Process Superintendent saying,

    I would like to express my

    congratulations to the team and

    project manager on the completion

    of a dual reline to the SAG and

    Ball mills here at Prominent Hill

    without incident. It was made even

    more difficult by having to share

    the mill deck with two other large

    jobs taking place simultaneously.

    The whole crew had a very positive

    attitude throughout the day and

    night shifts. Please pass on to the

    guys and Supervisors my whole

    hearted thanks for a fantastic

    job. I look forward seeing them inaction again at Prominent Hill.

  • 8/12/2019 OTE OIA Prominent Hill Web Eng

    4/4

    Outotec provides leading technologies and services for the sustainable use of Earths natural resources. As the

    global leader in minerals and metals processing technology, Outotec has developed many breakthrough technologies

    over the decades. The company also provides innovative solutions for industrial water treatment, the utilization of

    alternative energy sources and the chemical industry. Outotec shares are listed on NASDAQ OMX Helsinki.

    Contact us at

    [email protected]

    www.outotec.com

    Despite the downtime incurred due to only one available

    relining machine, works were completed on schedule.

    The reline machine and liner removal tools on-site

    performed well with no issues, however, the Outotec

    team also identified site equipment improvements that

    would benefit future, long-term performance.

    Scheduled maintenance services

    Proactive maintenance ensures optimum grinding mill

    operation and Prominent Hill ensure this by scheduling

    maintenance shutdowns to be performed regularly

    at 14 week intervals. Outotec has been contracted

    to inspect and perform these future maintenance

    and repair works.

    Australia.

    November2013.