The Prominent Hill operation comprises
both an open pit mine and a newly
developed underground operation with a
10Mtpa milling capacity. Prominent Hill
produces some of the worlds highest
grade copper concentrates. The site
is a fly-in/fly-out operation employing
approximately 1,200 employees and
contractors.
Simultaneous reline of SAG and ball mills completed
with zero harm at Prominent Hill
Organisation
Oz Minerals
Site
Prominent Hill, South Australia
Year
2010
Application
Copper-Gold concentrate
Challenge
Prominent Hills first simultaneous reline Shutdown and relining concurrent with other
major works on site
Working within high foot traffic footprint
Site had only one reline machine
Solution
Highly specialised Outotec team perform mill
relining and maintenance works
Result
Reline completed on time and on budget
Incident free (zero harm)
Pneumatic torque unit being used to tighten bolts.
8/12/2019 OTE OIA Prominent Hill Web Eng
2/4
Installing a new shell lifter on the SAG mill using the reline machine.
Project overview
Prominent Hills high grade ore production guidance
for 2013 is between 90,000-95,000 tonnes copper and
130,000-150,000 ounces gold. The newer Ankata
underground mine produces ore with similar
metallurgical characteristics as the original Malu open
cut mine, allowing the two run-of-mine ores to be
blended together.
Prominent Hill engaged the specialised mill relining
capabilities of the former TME Group, now part of Outotecs
Services division, to perform the mills first dual shutdown
since installed in August 2008. Both the SAG and Ball mill
were scheduled for simultaneous relining to take place
early in 2010, to replace the worn liners.
Mill reline scope
As the mill liners had originally been installed by
the Outotec team (then TME), they were aware of
the technical specifications. A subsequent site
audit facilitated assessment of the worn linings,additional works required and any constraints in the
working area. Originally the client anticipated the
replacement of only the shell lifters, feed end lifters
and plates and discharge grates on the 34 SAG mill.
However, following inspection, the scope of works
was extended to include replacement of all the shell
plates, along with the discharge end outer grates.
The 24 ball mill also required feed end outer and
inner plates, as well as shell and discharge plates,
to be replaced.
Process
A team of 56 specialised personnel took part in the
reline works which involved the replacement and
removal of over 1200 parts, with each mill taking less
than 73 hours to complete. Skilled personnel and
purpose designed equipment are critical in reducing
reline time and ensuring safety.
Many of the mill reline personnel have worked together
for almost a decade and are all qualified specialists in
their field with a reputation for expediency, innovation
and safety. The reline team have worked on thecomplete range of mill types and lining configurations
for gold, copper, lead, zinc, uranium, nickel, diamond
and cement mills.
8/12/2019 OTE OIA Prominent Hill Web Eng
3/4
The project managers worked closely with the client
to manage the critical path. This continual focus on
reducing reline incurred downtime ensured completion
within the planned shutdown schedule. This was
accomplished by expertise in planning, monitoring and
evaluating the shutdown timetable as well as utilising
Short Interval Control, a bespoke programme used
to track the progress of reline tasks. The programme
provided up-to-the minute information including parts
moved, time lost, estimated time of completion and
took all delays into account.
Challenges
To make optimal use of the shutdown period, Prominent
Hill scheduled two major maintenance works by other
teams to be carried out in addition to the relining project.
During the works, the mill deck was therefore subject
to high foot traffic and equipment congestion. As such,
it was critical to ensure that strict safety standards
were adhered to and a strong working relationship
forged with mill staff and the other work forces on
site. This had proven results in that the job was
completed without incident or injury to the teams
or equipment.
As site had only one mill reline machine available,
completion time would essentially have been doubled
if works had to be performed consecutively. To combat
this, the Outotec team worked around the clock to
complete the SAG mill and used a boom crane to remove
all of the dismantled lining from the ball mill until the
reline machine became available. Utilising available
resources in this way saved additional downtime and
ensured the project was completed to deadline.
Additional minor works were identified and completed
as the job proceeded, including assisting with the
isolations, set up on the mill and installation of the
Davit crane. Also, the discharge end and trunnions gaps
were filled with ceramic.
Safety first
Health and safety on-site is a primary objective for
any project and during the mill reline the Outotec
team ensured strict standards were adhered to. At thebeginning of each shift a pre-start and toolbox meeting
was held, with site safety inspections conducted per
shift. Prior to shutdown, safety performance was
discussed in detail and the actual shutdown closely
monitored, resulting in a safe procedure without
incident.
One area that existed within the former TME Group
was a Safety and Training operation. Transfer of the
licenses are due for completion in 2013, allowing the
Registered Training Organisation (RTO) capability to
be incorporated into Outotecs remit. This fast-track,
industry-specific training ensures highly qualified
personnel are always available and readily expedited
to site.
Results
Through efficient planning and a strong working
partnership with Oz Minerals and site, Prominent Hills
first simultaneous shutdown of the SAG and Ball mill
was executed on site with zero harm to personnel,
equipment or the environment.
Outotec was also on-site for the mill restart, completing
the retorque of the bolts for both mills after the first day
of operation.
Feedback from site was very positive, with Graham Dearing,Process Superintendent saying,
I would like to express my
congratulations to the team and
project manager on the completion
of a dual reline to the SAG and
Ball mills here at Prominent Hill
without incident. It was made even
more difficult by having to share
the mill deck with two other large
jobs taking place simultaneously.
The whole crew had a very positive
attitude throughout the day and
night shifts. Please pass on to the
guys and Supervisors my whole
hearted thanks for a fantastic
job. I look forward seeing them inaction again at Prominent Hill.
8/12/2019 OTE OIA Prominent Hill Web Eng
4/4
Outotec provides leading technologies and services for the sustainable use of Earths natural resources. As the
global leader in minerals and metals processing technology, Outotec has developed many breakthrough technologies
over the decades. The company also provides innovative solutions for industrial water treatment, the utilization of
alternative energy sources and the chemical industry. Outotec shares are listed on NASDAQ OMX Helsinki.
Contact us at
www.outotec.com
Despite the downtime incurred due to only one available
relining machine, works were completed on schedule.
The reline machine and liner removal tools on-site
performed well with no issues, however, the Outotec
team also identified site equipment improvements that
would benefit future, long-term performance.
Scheduled maintenance services
Proactive maintenance ensures optimum grinding mill
operation and Prominent Hill ensure this by scheduling
maintenance shutdowns to be performed regularly
at 14 week intervals. Outotec has been contracted
to inspect and perform these future maintenance
and repair works.
Australia.
November2013.