Client : PT. Krakatau Steel (Persero) Revision 1Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of BFW, Daerator & Condensate Approved Doc No. : Date 28/03/2011

BILL OF MATERIAL

N0 DESCRIPTION SIZE SPECIFICATION UNIT Q'TY

86 ORIFICE FLANGE 4" 300#, Sch.Std, WN-RF, FS, A-105 Pcs 487 ORIFICE FLANGE 3" 300#, WN-RF, SCH.40, Forged Steel, A105 Pcs 2

Page 2: Orrifice Flange R.5

Page 2 of 11

Client : PT. Krakatau Steel (Persero) Revision 2

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By

Package : Mechanical And Piping Checked

Doc.title. : Bill Of Material Modification of Dummy Quench & charge System (Stage 1, Material Tambahan) Approved

Doc No. : Date 23/05/2011

BILL OF MATERIAL

NO DESCRIPTION SIZE SPECIFICATION UNIT QT'Y

Page 3: Orrifice Flange R.5

Page 3 of 11Client : PT. Krakatau Steel (Persero) Revision 6

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of ECW Cooling Tower Approved Doc No. : Date 24/05/2011

BILL OF MATERIAL

NO DESCRIPTION SIZE SPECIFICATION UNIT QT'Y

93 ORIFICE FLANGE 6" A105, 300#, WN-RF, FS, ANSI B16.36 Pcs 294 ORIFICE FLANGE 28" A105, 300#, WN-RF, FS, SCH.40, ANSI B16.36 Pcs 2

Page 4: Orrifice Flange R.5

Page 4 of 11

Client : PT. Krakatau Steel (Persero) Revision 1Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of Heat Recuperator & Outlet Duct Approved Doc No. : Date 27/04/2011

BILL OF MATERIAL

NO DESCRIPTION SIZE SPECIFICATION UNIT Q'TY

Page 5: Orrifice Flange R.5

Page 5 of 11

Client : PT. Krakatau Steel (Persero) Revision 3

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By

Package : Mechanical And Piping Checked

Doc.title. : Bill Of Material Modification of Medium Pressure System Approved

Doc No. : Date 21/04/2011

BILL OF MATERIAL

No Description Size (inc) Remarks Unit Quantity

Page 6: Orrifice Flange R.5

Page 6 of 11

Client : PT. Krakatau Steel (Persero) Revision 1

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By

Package : Mechanical And Piping Checked

Doc.title. : Bill Of Material Modification of Medium Pressure System (Tambahan) Approved

Doc No. : Date 11/05/2011

BILL OF MATERIAL

No Description Size (inc) Remarks Unit Quantity

Page 7: Orrifice Flange R.5

Page 7 of 11

Client : PT. Krakatau Steel (Persero) Revision 2

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By

Package : Mechanical And Piping Checked

Doc.title. : Bill Of Material Modification of N2 Skid & Discharge Solid Cut off Valve / Sealing Approved

Doc No. : Date 11/05/2011

BILL OF MATERIAL

No Description Size (inch) Specification Unit QT'Y

Page 8: Orrifice Flange R.5

Page 8 of 11

Client : PT. Krakatau Steel (Persero) Revision 2Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of Quench Gas Reduction Approved Doc No. : Date 31/03/2011

BILL OF MATERIAL

No Description Size (inc) Remarks Unit Quantity

Page 9: Orrifice Flange R.5

Page 9 of 11

Client : PT. Krakatau Steel (Persero) Revision 1Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of Recycle Gas Approved Doc No. : Date 28/03/2011

BILL OF MATERIAL

N0 DESCRIPTION SIZE SPECIFICATION UNIT Q'TY

32 ORIFICE FLANGE 24" 300#, WN-RF, FS, A105, ANSI B16.36 Pcs 4

Page 10: Orrifice Flange R.5

Page 10 of 11

Client : PT. Krakatau Steel (Persero) Revision 1

Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By

Package : Mechanical And Piping Checked

Doc.title. : Bill Of Material Modification Of Steam Drum 221 F1 & F2 Approved

Doc No. : Date 02/05/2011

BILL OF MATERIAL

No Description Size (inc) Remarks Unit Quantity

Page 11: Orrifice Flange R.5

Page 11 of 11

Client : PT. Krakatau Steel (Persero) Revision 1Project Title : Zero Reformer Project For 5800 TPD DR1 HYL III DR Plant Prep. By Package : Mechanical And Piping Checked Doc.title. : Bill Of Material Modification of BFW, Daerator & Condensate Approved Doc No. : Date 28/03/2011

BILL OF MATERIAL

N0 DESCRIPTION SIZE SPECIFICATION UNIT Q'TY

87 ORIFICE FLANGE 3" 300#, WN-RF, SCH.40, Forged Steel, A105 Pcs 286 ORIFICE FLANGE 4" 300#, Sch.Std, WN-RF, FS, A-105 Pcs 493 ORIFICE FLANGE 6" A105, 300#, WN-RF, FS, ANSI B16.36 Pcs 232 ORIFICE FLANGE 24" 300#, WN-RF, FS, A105, ANSI B16.36 Pcs 494 ORIFICE FLANGE 28" A105, 300#, WN-RF, FS, SCH.40, ANSI B16.36 Pcs 2