26
F~ebruary 1, 1982 Proposed No.: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 ORDINANCE NO. 5878 AN ORDINANCE relating to Forward Thrust Park Resolution No. 34571; finding certain projects to be completed; duly providing for the comple tion of’ certain projects; finding certain pro jects to be impractical to complete and therefore deleting said projects; adding additional projects; and repealing Ordinances No. 3977, 4350, 4696, 5131 and 5258. King County Resolution No. 34571 (hereinafter “Resolution”), was adopted by the Board of County Commissioners (now the King County Council and the King County Executive) on December 18, 1967 and, is commonly referred to as the Forward Thrust Park Bond Resolution. This Resolution was approved by the voters of King County on the 13th day of February, 1968. The voters authorized the issuance of general obligation bonds for the purpose of development and improvement of public park and recreation facilities all within King County by the various cities, towns and King County. Public park and recreation facilities as contemplated by the Resolution and defined therein mean any land, interest in land and, facilities thereon within the County set aside for public park, recreational, green belt, arboretum, historic, scenic, viewpoint, aesthetic, ornamental or natural resource preservation purposes Pro~ts described in Section 3 of the Resolution (hereinafter “Pro~’ects”) assigned to the County were based in whole or in part upon , input from citizens, civic organizations, public officials and the thirty cities and towns in King County. ‘The Resolution authorized King County to develop and improve 166 park and recreational facilities in the County. To date, 156 of those Projects have been completed, are in progress, or —1— 4. Introduced by: SCOTT BLAIR 81— 745 4,

Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

F~ebruary 1, 1982

Proposed No.:

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

ORDINANCE NO. 5878

AN ORDINANCE relating to Forward Thrust ParkResolution No. 34571; finding certain projectsto be completed; duly providing for the completion of’ certain projects; finding certain projects to be impractical to complete and thereforedeleting said projects; adding additional projects;and repealing Ordinances No. 3977, 4350, 4696, 5131and 5258.

King County Resolution No. 34571 (hereinafter “Resolution”),

was adopted by the Board of County Commissioners (now the King

County Council and the King County Executive) on December 18,

1967 and, is commonly referred to as the Forward Thrust Park Bond

Resolution.

This Resolution was approved by the voters of King County on

the 13th day of February, 1968. The voters authorized the

issuance of general obligation bonds for the purpose of

development and improvement of public park and recreation

facilities all within King County by the various cities, towns

and King County.

Public park and recreation facilities as contemplated by the

Resolution and defined therein mean any land, interest in land

and, facilities thereon within the County set aside for public

park, recreational, green belt, arboretum, historic, scenic,

viewpoint, aesthetic, ornamental or natural resource

preservation purposes Pro~ts described in Section 3 of the

Resolution (hereinafter “Pro~’ects”) assigned to the County were

based in whole or in part upon , input from citizens, civic

organizations, public officials and the thirty cities and towns

in King County.

‘The Resolution authorized King County to develop and improve

166 park and recreational facilities in the County. To date,

156 of those Projects have been completed, are in progress, or

—1—

4.

Introduced by: SCOTT BLAIR

81— 745

4,

Page 2: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 their completion duly provided for.

2 King County will have sufficient funds from the Resolution

3 bond proceeds, interest earned on such bond proceeds, or

4 supplemental matching funds, to duly provide for the completion

5 of all park Projects to be developed or improved by King County

6 and which the King County legislative authority (as intended by

7 the Resolution) finds to be practical of accomplishment within

8 the contemplation of the Resolution.

9 Section 5 of the Resolution provides in part that if the

10 King County legislative authority (hereinafter “Legislative

11 Authority”) shall determine that conditions occurred which make

12 it impractical to substantially accomplish any of the Projects

13 by reason of prior incompatible development, cost substantially

14 in excess of the amount of bond proceeds estimated to be applied

15 thereto, prior acquisition by a superior governmental authority

16 or other changed conditions, King County shall not be required

17 to accomplish such Project and may apply such funds as provided

18 in Section 6 of the Resolution. The Legislative Authority

19 desires to specify those Projects which are impractical to

20 complete as contemplated by the Resolution.

21 ((c~)) Sixteen Projects have become impractical of

22 completion by reason of’ prior incompatible development, cost in

23 excess of the amount of bond proceeds estimated to be applied

24 thereto or opposition by other governmental authorities.

25 Topographical conditions and the requirements of’ the State

26 Environmental Policy Act (hereinafter “SEPA”) resulted in

27 changed conditions after the passage of the Resolution which

28 required review of certain Projects.

29 Bond proceeds, in addition to those required for the

30 Construction of those Projects which were deemed practical of

31 accomplishment, have been available for additional park and

32 recreational improvements contemplated by the Resolution. The

33 egislative Authority now desires to specify, ratify and approve

i a

Page 3: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 the additional projects eligible to be funded from such bond

2 proceeds.

3 The organization, classification and numbering of the

4 Projects listed in Sections 1, 2, 3, and 4 hereof are those of

5 the Resolution.

6 BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:

SECTION 1. Based on a recommendation from the Executive the

8 King County Council hereby finds the following Projects to be

9 completed as contemplated by the Resolution. (Amounts listed

10 were authorized by the Resolution):

11 A. Regional Parks

12 (2) Coal Creek $1,100,000

13 Acquisition of approximately 300 acres inCoal Creek Valley, east of Highway 405,

14 south of Somerset and southeast of Cougar

15 Mountain. (King County)

16 (3) North Soos Creek $1,100,000Acquisition of approximately 350 acres

17 north of Soos Creek Gorge and east of

18 Kent and Auburn. (King County)

19 (4) Sammamish Valley $3,000,000Acquisition of approximately 450 acres,

20 including river bank easements, in theSammamish River Valley between Marymoor

21 Park and Bothell. (King County)

22 (5) Cedar River $ 825,000

23 Acquisition of approximately 250 acres inthe Cedar River Valley as several separate

24 park sites between Renton and Maple Valleywith river bank access and river bank

25 easements. (King County)

26B. Major Urban Parks:

27(1) Weona Beach $ 385,000

28Acquisition of approximately 80 acres

29 immediately east of Lake Hills community

30 overlooking Lake Sammamish. (King County)

31 (2) Steel Lake $ 196,000Acquisition of approximately 48 acres in

32 the vicinity of the existing county parkat Steel Lake. (King County)

33 —3—

11 ii

Page 4: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1

2 (4) Big Finn Hill $ 249,000Acquisition of’ approximately 60 acres on

3 the east side of Lake Washington nearDenny Park. (King County)

4 (5) Earlington $ 374,000

Acquisition of approximately 90 acres ofeither sloping lands south of Empire Way

6 overlooking the Green River Valley and/orriverfront in the vicinity of the FosterGolf Course. (King County)

8 (9) North Green River $ 553,000

Acquisition of approximately 100 acresalong Green River north of Issac Evans

10 County Park. (King County)

11 (10) Des Moines $ 550,000

12 Acquisition of approximately 135 acres inthe valley from the south end of Seattle—

13 Tacoma Airport, in a south—westerly direction

14 to the vicinity of Des Moines. (King County)

15 C. New Community Parks:

16 (2) Redondo Community Park $ 165,000

17 Acquisition and preliminary development ofapproximately 18 acres now owned by the

18 County Engineering Department near propertynow held by Federal Way School District for

19 a junior high school site. (King County)

20 (4) East Norway Hill

21 Acquisition of approximately 24 acres of $ 88,000

22 state—owned land. (King County)

23 (8) Lake Boren $ 77,000Acquisition of approximately 20 acres near

24 the lake. (King County)

25 (9) Lake Sammamish Bulge Park $ 77,000

26 Acquisition of approximately 20 acres in

27 ravine near Redmond. (King County)

28 (11) Maplewood Heights $ 113,000Acquisition of approximately 20 acres on

29 plateau east of Renton and south of 128th

30 Avenue SE. (King County)

31 (13) Lea Hill $ 165,000Acquisition of approximately 20 acres on

32 plateau east of Auburn and north of Green

33 River Community College. (King County)—4—

I

Page 5: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

*

(1)(2)(3)

(4)(6)(7)(8)(9)

(T~T(11)(12)(13)(14)

(15)(16)(18)(19)(20)(21)(22)(24)(25)(26)

Boulevard Lane ParkDes Moines ParkDockton ParkEastgate ParkEnumclaw ParkFive Mile Lake ParkHamlin ParkJuanita ParkKenmore ParkLake Hills Park

Lakewood ParkLake WildernessMoshier ParkPine Lake ParkRichmond Beach ParkSeahurst ParkSi View ParkSunsetValley Ridge ParkWhite Center Park

HighlineShorelineBellevueRentonKentFederal WayI ssaquahNorthshoreLower SnoqualmieVashon IslandLake WashingtonTahoma

$ 62,500$ 45,600$ 61,000

$ 78,500$ 98,500$ 92,000$ 57,000$157,500$717 ,000$107 ,000$296,500$ 71,000$ 98,500

$133 , 500$232,150$ 39,400$ 38,000$ 95,200$272,700$ 43,500$ 44,000$ 64,000$ 65,000.

((i))(C;))((i))((2))((2))((2))

1((i))

1112

(14) Lake Forest Community Park

Partial acquisition and development of’ an8 acre park site (former Nike site). (Cityof Lake Forest Park)

0. Improvements to Existing County Parks:

(All King County)

1

2

3

4

5

6

7

8

9

10

11

12

Agren ParkAngle Lake ParkBellevue Highlands Parks

5878

$ 45,000

$2, 906 , 000

(Transferred toCity of Bellevue)

(Transferred toCity of Bellevue)

Park14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

NOTE: See Section 2 hereof for duly provided for Projects.

E. Local and Neighborhood Parks in Presently $5,655,000Unincorporated Areas:

(4) Acquisition and development of approximately 80neighborhood park sites averaging 7 acres each,distributed within school district boundary areasapproximately as follows: (King County) See Section 2hereof for duly provided for Projects.

Approx. No.Area of Sites

1087445

2

33 TOTAL ((2~)) ~ =

*

(($~T6467~86))$3,515,270

Page 6: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 F. Puget Sound Waterfront Parks and Beaches:

2 (6) Seahurst Park Addition $1,250,000

3 Acquisition of approximately 1,600 feetof waterfront and development of necessary

4 access road facilities. (King County)

5 (12) Lakota Beach $ 506,000

6 Acquisition of approximately 50 acres.

7 (King County)

8 (15) Northeast Vashon Island $ 198,000Acquisition of approximately 41 acres

9 including approximately 2000 feet of

10 beach. (King County)

11 C. Lake Waterfront Parks and Beaches $5,541,000

12 (1) Luther Burbank $1,503,000

13 Acquisition and development of approximately55 acres, including approximately 3,000 feet

14 of waterfront. (King County)

15 (5) Northeast Lake Washington $ 278,000

16 Acquisition of approximately 3 acresincluding approximately 400 feet of

17 beach. (King County)

18 (8) North Central West Lake Sammamish $ 532,000

19 Acquisition and development of approximately 10 acres including approximately

20 500 feet of beach. (King County)

21H. Recreation Facilities:

22

23 (4) South Area Park and Athletic Field $3,599,000Acquisition and development of approxi—

24 mately 70 acres for park and recreationalactivities, including major athletic fields

25 along the Green River north of the Tukwila

26 interchange of Interstate 5 freeway.

27 I. Recreation Facilities:

28 (1) Swimming Pools (Outside Seattle) $5,672,000

29 Construction of approximately eight publicswimming pools to be located at or near

30 senior high schools or in multi—purpose

31 community centers. (King County)

32 (2) Enumclaw Golf Course $ 221,000Acquisition of approximately 60 acres toexpand existing golf course. (King County)

—6—

I I

Page 7: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 K. Greenbelts and Scenic Drives:

2 (1) Scenic Highway Development $4,000,000

3 Acquisition of land and easements adjacentto highway right—of—way, along scenic high—

4 ways to be designated by a King County scenichighway system plan, to preserve natural and

5 scenic values; acquisition and development ofapproximately 12 scenic sites for vistas, rest

6 stops, picnicking, etc. (King County)See King County Motion No. 3681 which adopts

7 Scenic Highway Plan. See Section 2 hereoffor duly provided for Projects.

8a. Preservation and enhancement of the

9 Snoqualmie Valley Scenic Corridor.

10 (ii) Tolt River Acquisition. Theacquisition of 39 acres of

11 Snoqualmie Valley riverfrontbottomland which provides in

12 part preservation of theaesthetic and natural values

13 of the valley. $145,000

14 b. Preservation and enhancement of theGreen River Valley Scenic Corridor.

15(ii) Upper Green River Acquisition.

16 Acquisition of approximately 355acres in the upper valley at

17 several locations which providesfor preservation of’ scenic values

18 while providing for future viewpoints and perhaps motorized, non—

19 motorized, and waterway reststops. $796,000

20c. Preservation and enhancement of the

21 Samniamish Valley Scenic Corridor.

22 (ii) Idylwood Addition. Acquisition of7 1/2 acres with lakefront land on Lake

23 Sammamish providing preservation as wellas a potential additional attraction

24 and rest stop—view site for scenicroute users. $360,000

25d. Miscellaneous preservation and enhancement

26 issues.

27 (iii) Juanita Triangle Acquisition.Acquisition of .5 acres within the

28 Lake Washington Scenic Corridornorth of Juanita providing for

29 preservation of roadside aestheticvalues. $ 7,250

30

31

32-7-

33

F ~[*.::*.:

Page 8: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5873

1 e. Preservation and enhancement of theGreen River Valley Scenic Corridor.

(i) Green River Scenic Route Development3 (Interurban). Development of a 16—mile

non—motorized trail which provides a4 continuous non—motorized route through

the lower Green River Scenic Corridor.5 It also connects the (proposed) Grady

Way Scenic Highway with the Green River6 Road Scenic Highway. $385,000

7 1’. Preservation and enhancement of theSammamish Valley Scenic Corridor.

8(i) Sammamish River Scenic Route Development.

9 Development of’ a trail along the SammamishRiver which provides a non—motorized route

10 through this Scenic Corridor. This alsoprovides a major part of the connection

11 between the Lake Washington Scenic HighwayLoop and Lake Sammamish Scenic Highway

12 Loop. $1,100,000

13 (TOTAL: ((~T~O8r2~))

14 $2,793,250 )

15 SECTION 2. The following projects based on a recommendation

16 from the Executive are hereby found to be duly provided for as

17 contemplated by the Resolution. The approximate dollar amountsindicated herein represent the amount of Forward Thrust bond

18

19 proceeds authorized by the Resolution to complete the Projects.B. Major Urban Parks:

20(6) May Creek $ 615,000

21Acquisition of approximately 145 acres

22 along May Creek Valley. (King County)

23 (7) Cougar Mountain $ 405,000

24 Acquisition and preliminary developmentof approximately 25 acres of’ park and

25 view site on the north summit of CougarMountain together with necessary access

2~ road facilities. (King County)

27 (8) East Green River $ 711,000

28 Acquisition and preliminary developmentof approximately 75 acres in approximately

29 four park sites along the Green River inthe valley east of Auburn with river bank

30 access and river bank easements. (King

31 County)

32 -8—

33

Page 9: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

C. New Community Parks:

(3) Shoreline—South Central Site

Acquisition and development of approximately 22 acres near freeway in thevicinity of North 155th Street. (KingCounty)

(5) Kenmore

Acquisition and development of approximately 15 acres north of the BothellHighway. (King County)

(10) Shoreline — North Central Site

Acquisition and development of approximately 25 acres between Highway 99 andInterstate Highway 5. (King County)

(12) North Meridian

Acquisition of approximately 30 acresof state lane, north of Lake Meridianand west of Soos Creek, on southwestcorner of S.E. 224th and 132nd AvenueS.E. (King County)

0. Improvements to Existing County Parks:

(5) Chelsea Park $ 21,750(17) Marymoor Park $322,500(23) Skyway Park $119,300

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

____________________________ $ 469,000

_______ $ 248,000

______________________________ $ 645,000

______________ $ 193,000

E. Local and Neighborhood Parks in PresentlyUnincorporated Areas:

(4) Acquisition and development of approximately80 neighborhood park sites averaging sevenacres each distributed within school districtboundary areas approximately as follows:(King County) See Section 1 hereof forcompleted Projects.

Approx. No.Area of Sites

Highline ((fl)) 5 (4 to be abandoned)Shoreline ((—i)) 4Bellevue ((v)) 1Renton ((-4)) 3Kent ((—4)) 2Federal Way ((—6)) 3Issaquah 1Northshore ((—2)) 1Auburn 2South Central 2Lake Washington ((—4)) 3Enumclaw 1

TOTAL ((~6)) 28 = ((4TOO8T6~4))$2,139 ,730

—9—

I iii

Page 10: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

587$

F. Puget Sound Waterfront Parks and Beaches:

(7) Richmond Beach Addition $ 110,000

Acquisition of approximately 1,200 feetof beach. (King County)

(8) Dumas Bay $ 328,000

Acquisition and development of approximately 16 acres including approximately300 feet of tidelands. (King County)

(9) Redondo Beach $ 566,000

Acquisition and development of approximately 20 acres of tidelands and back—upland. (King County)

__________________ $

Acquisition and development of approximately 28 acres including approximately1,100 feet of beach. (King County)

Burton Park Addition $ 382,000

Acquisition of approximately 5 acresincluding approximately 850 feet ofbeach. (King County)

6. Lake Waterfront Parks and Beaches:

(6) South Central West Lake Sammamish $ 470,000

Acquisition and development of approximately 18.5 acres including approximately500 feet of beach. (King County)

(9) Lake Meridian $ 917,000

Acquisition and development of approximately 130 acres, including approximately1,400 feet of beach. (King County)

Walking Paths and Trails: $ 900,000

(2) Acquisition and development of walkingpaths and trails outside Seattle andwithin and without the other Cities ofthe County as the Board may determinewith approval of each directly affectedCity. (King County)

(11) Normandy Beach

(13)

497 ,000I

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

I.

— 10 —

Page 11: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 3. Greenbelts and Scenic Drives:

2 (1) Scenic Highway and Development

3 Acquisition of land and easements adjacentto highway right—of—way, along scenic

4 highways to be designated by~ a King Countyscenic highway system plan, to preserve

5 natural and scenic values; acquisitionand development of approximately 12 scenic

6 sites for vistas, rest stops, picnicking,etc. (King County) See King County Motion

7 No. 3681 which adopts Scenic Highway Plan.See Section 1 hereof for completedProjects.

8a. Preservation and enhancement of the

9 Snoqualmie Valley Scenic Corridor.

10 Ci) Snoqualmie Valley Scenic RouteDevelopment. Acquisition and

11 preliminary development of 27 miles ofabandoned railroad right—of—way which

12 in part provides for preservation ofamenities and provides a non—motorized

13 route through this corridor. It alsoconnects the Woodinville—Duvall Scenic

14 Highway with the Scenic Highwayportions of SR—202 and SR—203. $490,000

15(iii) Fall City Acquisition. Acquisition and

16 development of 26 acres of river—frontland near Fall City. This allows for

17 preservation as well as an attraction,rest stop and viewpoint for motorized,

18 non—motorized and waterway users.$150,000

19c. (iii) East Lake Sammamish Blvd. Pedestrian

20 — and Bike Path. Development ofpedestrian and bicycle path along the

21 scenic corridor to view the naturalareas in a leisurely way. $347,000

22d. Miscellaneous preservation and enhancement

23 issues.

24 (i) Preston—Snoqualmie Route Acquisition.Acquisition of 6.7 miles of abandoned

25 railroad right—of—way between Prestonand Snoqualmie which not only provides

26 for preservation of amenities withinthe Raging River and Snoqualmie Valley

27 Corridors, but also will provide anon—motorized route these Scenic

28 Corridors. It will as well provide aconnection between the Raging River

29 Scenic Highway and a Scenic Highwayportion of SR-202. $110,000

30

31

32

33— 11 —

[~**

Page 12: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 (ii) Lake Wilderness Route Acquisition.Acquisition of 2.4 miles of abandoned

2 railroad right—of—way between MapleValley and Lake Wilderness. This is to

3 provide, in part, the connectionbetween the Cedar River Scenic Corridor

4 and the Highway and the Green RiverCorridor and Highway along a more

5 pleasing route for non—motorized users.

6 $110,000(TOTAL: (~2T692yQQO))7 $1,207,000:

8 SECTION 3. Findings. Based on a recommendation from the

9 Executive, the Council hereby finds the following facts that

10 cause certain Projects to be impractical to substantially

11 accomplish. (The amount of Resolution authorized bond proceeds

12 is displayed only once):

13 A. Conditions Changed by Actions of Superior Governmental

14 Authorities:

15 1. After passage of the Resolution, the state Department

16 of Ecology, pursuant to authority granted it by the Shoreline

17 Management Act of 1971, R.C.W. 90.58, appealed King County’s~

18 issuance of permits to construct a boat launch at Seahurst,

19 Park. The Shoreline Hearings Board reversed the decision to~

20 issue permits, thereby making the following Project impractica1~

21 of completion:

22 L(4) Seahurst Park Boat Launching Ramps $ 166,000

23 Development of two ramps at the extremesouth end of park, to include dredging for24 boat access, placement of extensive riprapand construction of parking facilities.

25 (King County)

26 2. After passage of the Resolution, the City of’ Normandy

27 Park, pursuant to rights granted such cities in Section 4 of the

28 Resolution, disapproved of the following Project thereby making

29 it impractical of’ completion:

30 K(4) Puget Sound Boulevard, Shoreline and $1,800,000

31 Marine View ImprovementsLandscaping improvements and construction

32 of approximately 10 view points along theMarine View Scenic Drive between AlkiBeach Park and Dash Point State Park.(King County)

— 12 —

~

Page 13: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

58~’S

1 B. Other Conditions Making Project Completions Impractical:

2 1. After passage of the Resolution, an engineering

3 feasibility study concluded that the Federal Way Park Project

4 (former landfill site) should not be developed because of’

5 unstable soil conditions, contaminated ground water and

6 decomposition resulting in gas generation, thereby making the

7 Project impractical of completion:

8 C(l) Federal Way Park $ 443,000

9 Acquisition and development of 31 acresnear South 353rd Street immediately east

10 of’ Interstate Highway 5. (King County)

11. 2. Cost of acquisition of the following Project exceeded

12 the amount of bond proceeds estimated to be applied thereto,

13 thereby making the completion impractical:

14 C(6) Airport $ 97,000

15 Acquisition of approximately 25 acreswest of airport near Des Moines Way.

16 (King County)

17 F(lO) North Des Moines Beach $ 825,000

18 Acquisition of approximately 22 acresincluding approximately 400 feet of

19 beach. (King County)

20 F(14) East Central Vashon Island $ 429,000

21 Acquisition of approximately 67 acresincluding approximately 1400 feet of

22 beach. (King County)

23 3. Cost of acquisition and development (including

24 required self—contained sewer treatment facilities) exceeded the

25 amount of bond proceeds estimated to be applied thereto, thereby

26 making completion of the following Projects impractical:

27 E. Local and Neighborhood Parks in Presently $ 290,000Unincorporated Areas:

28(4) Acquisition and development of approximately

29 80 neighborhood park sites averaging sevenacres each distributed within school district

30 boundary areas approximately as.follows:(King County See Section 1 hereof for completed

31 Projects.

32 Approx. No.Area of’ Sites

33Highline 4

I :~rr~

Page 14: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 G(7) East Central Lake Sammamish $ 430,000

2 Acquisition and development of approximately 10 acres including approximately

3 1200 feet of beach. (King County)

4 4. The City of Lake Forest Park opposed the following

5 Project, part of which was located within its corporate limits,

6 thereby making completion of the Project impractical:

C(7) McAleer Creek $ 346,000

8

Acquisition and development of approxi

10 mately 43 acres along McAleer Creek Valleyin Shoreline District. (King County)

11 5. Prior incompatible development occured making the

12 following Projects impractical of completion:

13 B(3) Five—Mile Lake Addition $ 543,000

14 Acquisition of approximately 105 acres to

add additional acreage to the existingcounty park at Five—Mile Lake. (King

16 County) Prior bible camp development;school district acquisition.17

C(7) McAleer Creek18 Acquisition and development of approxi—

10 mately 43 acres along McAleer CreekValley in Shoreline District. (King

20 County) Prior residential development.

21 F(lO) North Des Moines Beach $ 825,000

22 Acquisition of approximately 22 acresincludinç approximately 400 feet of23 beach. (King County)

24 G(4) Shoreline Community Beach $260,000

25 Acquisition and development of approxi—mately 3 acres, including approximately

26 300 feet of beach. (King County) Priorrecreational development.

27 G(7) East Central Lake Sammamish

28 Acquisition and development of approxi—

29 mately 10 acres, including approximately1200 feet of beach. (King County) Prior

30 residential development.

31

32

33

— 14 —

I t

Page 15: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

K(4) Puget Sound Boulevard, Shoreline andMarine View Improvements

Landscaping improvements and constructionof approximately 10 view points along theMarine View Scenic Drive between Alki BeachPark and Dash Point State Park. (KingCounty) Prior residential development.

L(3) Seola Beach Boat Launching Ramps

Acquisition and development of approximately 4 acres including approximately200 feet of beach. (King County) Priorresidential development; storm drain andsanitary outfall sewer.

L(5) 20th Avenue Southwest Boat LaunchingRamps

Acquisition and development of approximately 4 acres, including approximately250 feet of beach. (King County) Priorresidential development.

6. After the Resolution, an engineer’s report concluded

the approach road had a grade too steep and was too narrow to

safely develop as a boat launch facility thereby making the

following Project impractical of completion:

L(5) 20th Avenue Southwest Boat Launching Ramps

Acquisition and development of approximately 4 acres including approximately250 feet of beach. (King County)

Total Amount of Impractical Projects: $6,680,000

SECTION 4. Abandonments. Based upon a recommendation from

the Executive and the Findings of Section 3 hereof, the

following Projects are hereby deleted (Project numbers are

referenced to the Resolution; amounts are unexpended balances

abandoned):

B(3) Five—Mile Lake Addition $ 352,622

Acquisition of approximately 105 acresto add additional acreage to the existingcounty park at Five—Mile Lake. (King County)$190,378 of original $543,000 was expended forpurchase of 25 acres prior to determination ofimpractical.

$ 657,000

$ 394,000

1

2

3

4

5

6

7

S

9

I0

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

3.

33— 15 —

I

Page 16: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 C(1) Federal Way Park $ 433,569

2 Acquisition and development of 31 acres nearSouth 353rd Street immediately east of Inter—

3 state Highway 5. (King County)$9,431 of original amount was expended prior

4 to determination of impractical.

5 C(6) Airport $ 95,000

6 Acquisition of approximately 25 acres westof airport near Des Moines Way. (King County)$2,000 of original amount was expended prior todetermination of impractical.

8C(7) McAleer Creek $ 346,000

Acquisition and development of approxi—10 mately 43 acres along McAleer Creek Valley

11 in Shoreline District. (King County)E. Local and Neighborhood Parks in Presently $ 268,828

12 Unincorporated Areas:

13 (4) Acquisition and development of approxi-.mately 80 neighborhood park sites

14 averaging seven acres each distributedwithin school district boundary areas

15 approximately as follows: (King County)See Section 1 hereof for completed

16 Projects.

17 Approx. No.Area of Sites

18Highline 4

19 —

20 $21,172 of original amount was expended prior todetermination of impractical.

21

22 F(lO) North Des Moines Beach $ 806,445Acquisition of approximately 22 acres

23 including approximately 400 feet ofbeach. (King County) $18,555 of

24 original amount was expended prior to

25 determination of impractical.

26 F(l4) East Central Vashon Island $ 428,409Acquisition of approximately 67 acres

27 including approximately 1400 feet of

beach. (King County) $591 of original28 amount was expended prior to determination

29 of impractical.

30 G(4) Shoreline Community Beach $ 260,000Acquisition and development of approxi—

31 mately 3 acres, including approximately

32 300 feet of beach. (King County)

33— 16 —

Page 17: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5~78

G(7) East Central Lake Sammamish $ 412,082

Acquisition and development of approxi-.mately 10 acres, including approximately1200 feet of beach. (King County)$17,918 of original amount was expendedprior to determination of impractical.

K(4) Puget Sound Boulevard Shoreline and $1,800,000Marine View Improvements

Landscaping improvements and constructionof approximately 10 view points along theMarine View Scenic Drive between Alki BeachPark and Dash Point State Park. (King County)

L(3) Seola Beach Boat Launching Ramps $ 654,500

Acquisition and development of approximately 4 acres, including approximately200 feet of beach. (King County) $2,500of original amount was expended prior todetermination of impractical.

L(4) Seahurst Park Boat Launching Ramps 68,000

Development of two ramps at the extremesouth end of park, to include dredgingfor boat access, placement of extensiveriprap and construction of parkingfacilities. (King County) $98,000 oforiginal amount was expended prior todetermination of impractical.

L(5) 20th Avenue Southwest Boat LaunchingRamps

Acquisition and development of approximately 4 acres, including approximately250 feet of beach. (King County) $2,500of original amount was expended prior todetermination of impractical. __________

Amount expended prior to determination ofimpracticality: $ 363,045

Amount available after abandonments: $6,316,955

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

$ 385,545

— 17 —

Page 18: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 SECTION 5. Based upon the findings of the preceding

2 sections, the Legislative Authority hereby finds that bond

3 proceeds in addition to those required for the original Projects

4 have been made available for additional park and recreation

5 facilities contemplated by the Resolution to be construction.

6 The Legislative Authority hereby finds the following additional

projects to be public park and recreational facilities as

8 contemplated by the Resolution and are for a County purpose.

9 The Legislative Authority based on a recommendation from the

10 Executive, hereby specifies, ratifies and approves the

11 expenditure of bond proceeds for the construction of the

12 following additional park and recreation facilities in King

13 County (amounts indicated represent bond proceeds, interest

14 therefrom and matching funds):

15 Projects added by Legislative Authority completed as

16 contemplated:

17 1. Enumclaw Community Allocation $ 0

18 Enumclaw Community Plan Area: Boundedroughly by the Auburn Southeast City

19 Limits, the White River, a line from MudMountain Dam along Enumclaw Mountain to

20 Kanaskat and the Green River Gorge.

21 An amount of $4,759 was expended at theEnumclaw Fairgrounds (See Item #38 in

22 Projects added section.)

23 2. Tennis Courts $ 165,000

24 Construction of tennis courts at thefollowing sites: Luther Burbank, Kellogg

25 Jr. High, Marymoor, Juanita, Meridian Jr.High (Kent). Lighting of two existing

26 tennis courts at Highline High School andresurface existing courts at Tahoma High

27 School.

28 3. Tolt River (McDonald Park) $ 433,352

29 Development of a pedestrian bridge, overnight camping area, primitive camping area

30 together with necessary support facilities.Acquisition of approximately 35 acres

31 abutting the northeast boundary of the

32 existing park.

33 4. Edith Moulton $ 20,223Preliminary development of existing park toinclude parking area, trails and eprimeterfencing.

-18-

Page 19: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5. Point Robinson $ 44,000

Development of existing park to includepicnic areas, trails, parking area andnecessary support facilities.

6. Grandview $ 10,000

Development of existing park to includeminor improvements to two existing soccerfields.

7. Enatai Beach $ 15,000

Improvements to existing fishing pier.Transferred with funds to City of Bellevue.

8. Russell Road Park $ 100,000

Partial funding of City of Kent Park toassist in the development of severalathletic fields on the existing park.

9. Snogualmie Valley Community Allocation $ 24,081

An amount of $24,081 remains in thisproject account to provide park facilitieswithin this Plan area at DuvallCommunity Park.

10. West Central Community Allocation ___________

All funds allocated to this Plan areahave been disbursed to existing or newprojects within the area.

11. Regional Project Allocation $ 161,415

An amount of $161,415 was expended at WhiteCenter Park for construction of a newstadium.

Duvall Park Additional Improvements $ 30,000

Provide access to bailfield and additionalfield improvements.

13. Angle Lake Swimming Piers $ 100,000

Replace deteriorating swimming piers.

14. Boulevard Lanes Additional Improvement $ 3,000

Provide one—half outdoor basketball court.

15. Lakewood Water Quality Study $ 10,000

To determine source and nature of existingpollution.

16. Eight Additional Swimming Pools $5,235,218

Construct swimming pools in the followingschool districts: Northshore, Highline,Issaguah, Tahoma, Enumclaw, Vashon, SouthCentral, Lake Washington.

— 19 —

I I

5878

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

$ 0

12.

Page 20: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878February 2, 1982

Sammamish River Development ___________

Provide additional acquisition to facilitate$1,000,000 EDA project.

18. Logboom Park Development $ 554,399

Develop waterfront park, fishing pier andday moorage.

North Central West Lake Sammamish $ 556,936Acquisition and Development

Acquire and develop an additional 7+ acresadjacent to existing Idyiwood Park.

20. Bellevue #10 Additional Improvements ___________

Children’s playground and ballfieldlighting.

21. Sacajawea Lighting ___________

Provide lighting for existing softball field.

22. Juanita Beach Additional Improvements $ 30,000

Miscellaneous site and swimming. pier improvement.

23. Keough Park Additional Improvements $ 35,000

Provide playground equipment and sitefencing.

24. Fort Dent Additional Improvements $ 100,000

Provide field completion.

25. Bannerwood $ 200,130

Provide athletic fields on existingBellevue School District property.

26. Velodrome Lighting $ 105,000

Provide lighting and additional seatingat Marymoor Park Velodrome.

27. Swimming Pool Improvement $ 30,727

Provide necessary repairs to existingswimming pools.

28. Tahoma #2 $ 15,630

Provide perimeter fencing.

29. Hatchery Park $ 113,000Acquire 20 acres at the confluence ofBig Soos Creek and the Green River.

1

17. $ 25,000

19

$ 88,959

$ 58,000

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32TOTAL $8,264,070

- 20 -

Page 21: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5879

1 Projects added by Legislative Authority:

2 1. Bear Creek Community Allocation (($;2.,.3;3)) $ 82,377

3 Bear Creek Community Plan Area: Boundedroughly by 180th Avenue N.E., Redmond!

4 Fall City Road, the West Snoqualmie ValleyRoad and the Snohomish County line.

$25,000 from North Bear Creek Athletic6 Field and $25,000 from South Bear Creek

Athletic Field are being combined with$32,377 from this project to provide theacquisition and preliminary development8 of an athletic field site for this servicearea. The combined project is named BearCreek AthletIc Field.

10 2. Central Community Allocation $ 196,963

11 Central Community Plan Area: Boundedroughly by Lake Washington, Rainier Avenue,12 Interstate 5, Petrovitsky Road, Cedar GroveRoad, Coalfield Road, the Renton/Issaquah Road

13 and Interstate 90.

14 An amount of $196,963 remains in this project

to provide future park recreational facilities15 within this plan area at the following sites:

16 Issaquah Athletic Facility — $100,000Eastgate Tennis Courts — $25,00017 Lower Cougar Mountain - $25,000

Luther Burbank - $46,963.

18 3. Schoolfield Improvement $ 70,000

19 Provide development of existing school

20 property in the East Central Planning area.

21 4. Eastside Community Allocation $ 48,000

22 Eastside Community Plan Area: Boundedgenerally by Lake Washington, Interstate 90,

23 Lake Samrnamish and the north city limits ofKirkland and Redmond.

24 An amount of$48,000 remains in this project

25 for general improvements at Marymoor Park.

26 5. Federal Way Community Allocation $ 134,809

27 Federal Way Community Plan Area: Boundedby Puget Sound, the King/Pierce County line,

28 West Valley Road and the Kent/Des Moines Road.

29 An amount of $134,809 remains in this projectto provide for future park facilities at Lake

30 Geneva.

31 6. Community Assisted Capital Needs $ 26,654

32 Provide County funds for individual communityassisted park and recreation projects.

—21—

Page 22: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

7 Shoreline Community Allocation $ 126,924

Shoreline Community Plan Area: Boundedby Puget Sound on the west, 145th Streeton the south, Lake Washington and 55thAvenue N.E. on the east and 205th Streeton the north.

An amount of $126,924 remains in thisproject area to provide improvements atthe following locations: North CentralShoreline Master Plan, $14,000; HamlinPark Lighting, $36,424; Richmond BeachSchool Gym, 441,500; and Echo Lake ComfortStation, $35,000.

8. Chelsea Performing Arts Center $ 250,000

The renovation of the surplus ChelseaElementary Scool located at S.W. 146thand 4th Avenue S.W. to provide for aPerforming and Cultural Arts Center inthe Burien Area.

9. North Bear Creek Athletic Field $

This project together with project #10 arenow combined with project #1 to provideathletic fields for this area.

10. South Bear Creek Athletic Field $

This project together with project #9 arenow combined with project #1 to provideathletic fields for this area.

11. East Northshore Athletic Field $ 25,000

Development of land for activerecreational needs including bailfieldseast of the Sammamish River Valley andSR 522.

12. Big Finn Hill $ 96,737

Development of approximately 40 acres ofland presently owned by the Department ofNatural Resources and located at N.E. 138thand Juanita Drive N.E. Primary developmentshall consist of active recreational fields.

13. Brook Lake $ 20,000

Minor site improvements to approximately 20acres of land to be donated to the County bythe Brook Lake Community Club. Land locatedat South 348th and 9th AvenueSouth.

14. Federal Way Neighborhood Park #10 $ 70,000

The acquisition and development of aneighborhood park at an, as yet, undetermined site in the Federal Way Planning Area.

I

5878

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

0

0

— 22 —

Page 23: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

1$

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

1.

15. Fall City Athletic Equipment

Purchase and installation of four soccergoal posts and two baseball backstops atthe undeveloped Fall City Riverfront Park,a site now owned by King County.

16. Athletic Field Lights

Installation of athletic field lighting atthe following County parks: Moshier, Lakota,White Center.

17. Levdansky

Development to existing park to includeactive recreational field and necessarysupport facilities

18. Multi—Purpse Recreational Facility

Study of existing Couinty—owned land inthe vicinity of Grandridge Park to determinefeasibility of developing a sportsmen’srecreation facility.

19. Southeast Central Community Allocation

An amount of $45,021 remains in theproject account to provide future parkfacilities with this Plan area atRavensdale Park.

20. Boat Launch Facilities — South King County

Acquire and construct an undetepmined numberof boat launch facilities at a site or sitesto be determined.

21. Highline #23 Additional Development

To complete full development of Zenithneighborhood park.

22. Agren Water System

Provide well and irrigation system atAgren park.

23. Des Moines Activity Center

Improvements to existing park facilities.

24. Lake Wilderness Additional Improvementand Arboretum

Construction of a trailer pad and provisionof a well.

25. Moshier Park Additional Improvements

Provide fencing and drainage improvements.

— 23 —

$ 20,000

$ 314,000

$ 100,854

$ 20,000

$ 45,021

$ 220,607

$ 51,417

$ 26,927

$ 45,000

$ 90,964

$ 40,000

5878

Page 24: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5878

1 _________________________________________________________________

2

3

4 _____________________________________________________________

5

6

7 ________________________________________________

$

9

10

11

12 ____________________________________________

13

14

15

16

17

18

19

20 _______________________________________________

21

22

23

24

25 ____________

26

27

28

29

30

31 ______________________ _____________

32 ___________________________________________________________

33 __________

26. Pine Lake Additional Improvement

New bathhouse, additional site improvements,improve existing entrance road and new picnicshelter.

27. Enumclaw Golf Course Drainage Improvements

Miscellaneous improvements to original 9—holegolf course and drainage improvements toentire facility.

28. Steel Lake Additional Development

Provide final development of communityathletic facility.

29. Luther Burbank Additional Development

Complete site development and providecaretaker’s residence.

30. East County Community Allocation

An amount of $34,754 remains in this projectaccount to provide future park facilitieswithin this Plan area on the Snoqualmie —

Tanner Section of the Preston-Tanner Trail.

31. Sunset Additional Improvements

Provide parking and minor field improvements.

32. Valley Ridge Additional Development

Renovation and/or light existingathletic fields.

33. White Center Additional Improvements

Provide additional site improvements andgeneral park upgrading.

34. Earlington Neighborhood Park

Provide for the acquisition of a site inthe City of Renton.

35. Greentree

Provide play equipment and other minorsite improvements at a dedicated openspace tract.

36. Eastridge

Provide play equipment and minor siteimprovements at a dedicated open spacetract.

37. Tramp Harbor Dock

The acquisition and partial renovation ofthe existing Chevron Oil dock on VashonIsland.

~

$ 194,103

$ 260,000

$ 828,204

$ 700,000

$ 34,754

$ 48,000

$ 150,000

$ 262,500

$ 52,500

$ 12,000

$ 4,300

$ 215,837

- 24 —

Page 25: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

5d/8

38. Enumclaw Fairgrounds

This project would provide for fairgroundimprovements as indicated in the Fair MasterPlan. These funds are from the East CountyCommunity Allocation ($30,_241) and EnumclawCommunity Allocation ($4,759).

$ 130,000

30

31

32

33~— 25 —

1’

$ 35,000

39. Steel Lake

This project involves the replacement ofexisting piers.

40. Burton Acres $ 100,000

This project involves renovation of theexisting boat launch ramp2 comfort stationand the provision of trails.

41. Dockton $ 178,418

This project involves the renovation ofthe existing boat launch ramp and piers.

42. Lakota Community $ 20,000

This project involves im~p~’ovements to theexisting parking lot.

$5,347,870

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

(TOTAL:

Page 26: Ordinance 05878 - King County, Washington 05878.pdf5878 1 2 (4) Big Finn Hill $ 249,000 Acquisition of’ approximately 60 acres on 3 the east side of Lake Washington near Denny Park

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

ordinances or sections thereof so

repealed:

A. Ordinances:

No. 3977, December 1978

No. 4350, July 1979

No. 4696, January, 1980

No. 5131, October,~l980

1980

indicated are each hereby

the first time this 719~/

day of \3 Lt4,c.c4LA~,, l982~

KING COUNTY COUNCILKING COUNTY, WASHINGTON

I

SECTION 6. Ordinances Repealed.

5878

followingThe1

2

3

4

5

6

7

8

9

10

11

12

13

14

No. 5258, December,

INTRODUCED AND READ for

day o f ______________________ ______

PASSED this /L~, 1—&i _______________ ____

CE Chairman

~ATTE.ST:

ACTiNGDeputy C1e~i~ of the Council

ApPROvgo~this ___________day of’ , 19

Kin~~c~~

- 26 -