ORC 5519.05 R/W to be Monumented and Preserved
• ORC 5519.05 requires ODOT to promptly monument the right of way that is acquired.
• ODOT shall definitely and accurately ascertain and monument the roads and highways on the state highway system.
• All monuments shall be preserved or reset in their exact location.
• Non performing the setting or resetting of monuments is a violation of the ORC 5519.05
2010 Specification Training
Memorandum of Understanding of newly acquired highway R/W
• Was established between the Board of Registration for P.E.’s and P.S.’s and ODOT
• Monuments are to be set or reset based on the right of way plan information.
• These monuments may be reset by any Professional Surveyor licensed in the State of Ohio.
2010 Specification Training
Construction and Materials Specifications
107.10 Protection and Restoration of Property
2008 Specification Training
Inventory of Monuments Set
• Requires coordination and communication between project engineer and construction contractors surveyor.
• Construction contractor makes reasonable effort to verify all R/W monuments shown in R/W plans before earthmoving activities.
• Contractors submits signed and sealed report, prepared by a professional surveyor, identifying all monuments within the project limits.
• The Report is necessary to protect the contractor.
• NO Report the Contractor is responsible for protecting and resetting ALL monuments as per the R/W plan at their expense.
2010 Specification Training
2010 Specification Training
Protection and Restoration of Property
Any permanent Right-of-Way Monuments or property monuments on or outside the Right-of-Way limits and not enclosed within a temporary easement for the project will be the Contractor’s responsibility to protect. Upon completion of the final grading replace any Right-of-Way Monuments destroyed during or by construction activities. A quantity for replacement of Right-of-Way Monuments expected to be destroyed that are within a temporary easement will be paid under Item 604.
Monument Setting• During construction the Contractor will construct the
Monument Assemblies and Reference Monuments per item 604.
• Reference the latest revision of the Standard Construction Drawing RM-1.1
• All R/W Monuments, Monument Assemblies and Reference Monuments are to be set under the direct supervision of a Professional Surveyor licensed in the State of Ohio.
• Contractor’s surveyor is required to submit a signed and sealed report identifying any monuments set or reset.
2010 Specification Training
Monument Assembly, Reference and Right of
Way
2010 Specification Training
Brett Shearer
614-728-6142