55
Orange Line Bus Rapid Transit Project Plan Update Metro Transit July 2014

Orange Line Bus Rapid Transit Project Plan Update · uly 2014 Page 3 METR range ine BRT Proect Plan pdate List of Figures Figure 1. Map of METRO Orange Line Alignment and Stations

  • Upload
    vanmien

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

Orange Line Bus Rapid TransitProject Plan Update

Metro TransitJuly 2014

METRO Orange Line BRT

Project Plan Update

July 2014Page 2

Contents1 Background 42 Scope 6 2.1 Mode 2.2 Stations 2.3 Guideway 2.4 RightofWayNeeds 2.5 Technology 2.6 FareCollection 2.7 BrandingandMarketing 3 Service Planning 34 3.1 GarageandTerminals 3.2 RunTimeandFrequency 3.3 Service Structure 3.4 Fleet 3.5 Ridership 4 Budget and Funding 38 4.1 CapitalandOperatingCosts 4.2 FundingDistribution 5 Schedule 406 CoordinationwithConcurrentProjects 40 6.1 I-35WLakeTransitAccessProject 6.2 I-494/35WInterchangeVisionLayout 6.3 66thStreetReconstruction 7 EnvironmentalProcess 428 AgencyPartners 42 AppendixA:Stations Appendix B: Service Planning

MetroTransitBRT/SmallStartsProjectOffice707 16th Avenue SouthMinneapolis,MN55454www.metrotransit.org/OrangeLineAdoptedbyMetropolitanCouncilonJuly9,2014

CoverphotocourtesyoftheMinnesotaDepartmentofTransportation.

ForadditionalinformationontheOrangeLine,pleasecontactChristinaMorrisonat612-349-7690orbrtprojects@metrotransit.org.

July 2014 Page 3

METRO Orange Line BRT

Project Plan Update

List of FiguresFigure1.MapofMETROOrangeLineAlignmentandStations 4

Figure2.MapofExistingandPlannedMETROSystemandArterialBRTCorridors 5

Figure3.ExistingRoute535StopGroups andPotentialStationLocations 7

Figure4.PhotosofExistingMARQ2Operations 7

Figure5.LakeStreetStationPreferredPlatformLocationandConnectingBusStops 8

Figure6.PlanofLakeStreetStationPlatformsfromI-35WLevel 9

Figure7.RenderingofLakeStreetStationPlazaatStreetLevel 9

Figure8.RenderingofLakeStreetStationPlatformsatI-35WLevel 10

Figure9.46thStreetStationExistingPlatformLocationandConnectingBusStops 11

Figure10.AerialViewof46thStreetStation 11

Figure11.66thStreetAlternativesforPlatformLocations 12

Figure12.66thStreetStationPreferredPlatformLocationsandConnectingBusStops 13

Figure13.ConceptualDesignforNorthboundPlatformat66thStreetStation 13

Figure14.ConceptualDesignforSouthboundPlatformat66thStreetStation 13

Figure15.ConceptualElevationsforNorthboundPlatformat66thStreetStation 14

Figure16.ConceptualElevationsforSouthboundPlatformat66thStreetStation 15

Figure17.AmericanBoulevardAlternativesforPlatformLocations 17

Figure18.ComparisonofOptions1A,3A,and3B 19

Figure19.76thStreetStationPreferredPlatformLocationsandConnectingBusStops 21

Figure20.AmericanBoulevardStationPreferredPlatformLocationsandConnectingBusStops 21

Figure21.98thStreetAlternativesforPlatformLocations 22

Figure22.98thStreetStationPreferredPlatformLocationandConnectingBusStops 25

Figure23.ConceptualDesignforCombinedNorthboundandSouthboundPlatformat98thStreetStation 25

Figure24.PossiblesitesforBurnsvilleTransitStationGateExpansion 26

Figure25.ConceptsforConnectingMARQ2andI-35WTransitAdvantages 27

Figure26.KnoxAvenueRouting 30

Figure27.98thStreetRouting 30

Figure28.BurnsvilleRoutingforSiteAlternatives 31

Figure29.METROBlueLineTicketVendingMachine 33

Figure30.METROOrangeLineVehicleBranding 33

Figure31.METROOrangeLineConceptRouteMapandConnectingService 35

Figure32.METROOrangeLineEstimatedNorthboundRunTimes 36

Figure33.METROOrangeLineEstimatedSouthboundRunTimes 37

Figure34.METROOrangeLineEstimatedOperatingCosts 38

Figure35.METROOrangeLineProposedFundingDistribution 38

Figure36.METROOrangeLineEstimatedCapitalCosts 39

July 2014Page 4

METRO Orange Line BRT

Project Plan Update

1 BackgroundMETROOrangeLineisaplannedbusrapidtransit(BRT)line between Minneapolis, Richfield, Bloomington,and Burnsville. The Orange Line will benefit existingriders and attract new riders by improving transitaccess, service, and reliability on the I-35W corridor.Additionally, an identifiable, high-amenity brand willincrease the visibility of transit and leverage serviceimprovements.

All-day,frequentBRTservicewillcomplementlocalandexpressbus routesalong I-35W,providingcompetitiverunning times for station-to-station trips and a newoption for reverse-commute markets. Both BRT andexpress riders will benefit from stations, runningwaytechnology,andserviceimprovements.TheOrangeLinewouldprovide10-minutepeakfrequencyand15-minuteoff-peakfrequency,atleast16hoursperday,sevendaysaweek.

As a part of theMETRO system, the Orange Linewillconnectpeopleacrosstheregiontojobcenters,housingoptions, transit stations, and key destinations in theI-35Wcorridor.TheOrangeLinewillimproveaccessto162,000jobsand64,000residents,including30,000jobsand40,000residentsoutsideofdowntownMinneapolis.Byprovidinganewtransportationoptionandexpandingaccessibility, BRT service will also promote compact,walkabledevelopmentinthestationareas.

The I-35W corridor provides critical access into andthroughDowntownMinneapolisaswellasjobcentersinMidtownMinneapolis,alongtheI-494Corridor,andatsuburbannodes.I-35Wisaheavily-usedtransportationcorridor, having carried approximately 210,000 dailyvehicles and 14,000 daily transit riders in 2012. TheOrangeLinewillbuildonincrementaltransitinvestmentsmade over the past 40 years. Existing population andemployment densities, income and auto deficienciesdensities, access to critical transit connections, andexpected growth justify continued improvement ofstation-to-stationOrangeLineservice.1

1 METRO Orange Line Bus Rapid Transit Existing ConditionsReport, Section 1.3

Figure 1. Map of METRO Orange Line Alignment and Stations

July 2014 Page 5

METRO Orange Line BRT

Project Plan Update

Figure 2. Map of Existing and Planned METRO System and Arterial BRT Corridors

July 2014Page 6

METRO Orange Line BRT

Project Plan Update

2 Scope

2.1 Mode

Between1992and2010,manytransitalternativesandimprovementswerestudiedintheI-35Wcorridor2,including:

• bus(nobuild);• lightrailtransitintheI-35Wmedian,orontheSooLineRailroadcorridor;• high-occupancyvehiclelanes;• transportationdemandmanagementstrategies;• improvedfeederbusservice;• busrapidtransit;• high-occupancytolllanes;and• expressbus.

FollowingaMnDOTI-35WBRTstudyin2005,incrementalstationinvestmentbegunin2008aspartoftwoprojects:freeway reconstruction in theCrosstownCommonsarea,and theUrbanPartnershipAgreement.The46thStreetandDowntown stations have beenoperational since 2010 and currently servemany I-35Wexpress and limited-stopbusroutes.Thelocally-preferredalternativeforthiscorridor,HighwayBRT,wasadoptedintotheregional2030 TransportationPolicyPlanin2010.

2.2 Stations

2.2.1 Downtown Stations: Operational

IndowntownMinneapolis,OrangeLinebrandingwillbeintegratedintoexistingtransitstopgroupsonMarquetteAvenueand2ndAvenue(MARQ2).Stopgroupassignmentshavenotyetbeendetermined,however,apairofstations(northboundon2ndAvenueandsouthboundonMarquetteAvenue)isexpectedinthevicinityof5th,7th,9th,and11thStreets.

2.2.2 Lake Street Station: 60% Design

TheplannedLakeStreetStationinMinneapolisispartofamajorinvestmentinroadway,bridge,transitandaccessibilityimprovementsforusers.Thetwo-storymedianstationwillbefullyADAaccessibleandprovideasignificantupgradeincomfortandsafetyoverexistingbusstops.ItwouldalsoallowbothOrangeLineandexpressbusestoaccessthestationdirectlyfromtheMnPASSlane,greatlyincreasingservicelevelsandreliabilityatLakeStreet.Parallelsideplatformswithpassinglaneswillallowmultiplebusestomovethroughtheareawithoutdelay.Thestationwouldconnectwithexistinglocalbusserviceatthestreetlevel,inadditiontoplannedLakeStreetBRTandrailintheMidtownGreenway.

The 35WLakeTransit/AccessProjectincludesanumberofroadwaydesignchangesbetweenI-94and32ndStreet,aswell as the constructionof an online BRT station at Lake Street, a southboundmanaged lane fromdowntownMinneapolisto42ndStreet,conversionofthenorthboundpriceddynamicshoulderlanetoafullmanagedlane,andnumerousstreetscapelocalimprovements.TheprojectisbeingledbyHennepinCountyinpartnershipwiththeCityofMinneapolis,MetropolitanCouncil,MetroTransit,andMnDOT.2 METRO Orange Line Bus Rapid Transit Existing Conditions Report, Section 2.1, Table 4: Transit Alternatives Studied during Past Environmental Work in the I-35W Corridor.

July 2014 Page 7

METRO Orange Line BRT

Project Plan Update

Figure 3. Existing Route 535 Stop Groups and Potential Downtown Station Locations Figure 4. Photos of Existing MARQ2 Operations

July 2014Page 8

METRO Orange Line BRT

Project Plan Update

A public engagement process has been underway for several years in the Lake Street area. A Project AdvisoryCommittee(PAC),comprisedofresidents,businessowners,communityinstitutionsandpolicymakers,meetsmonthlyandadvisespartneragencies.TheLakeStreetBRTStationismovingintofinaldesignin2014.

Short-term Improvements

The existing Lake Street bus stops on I-35W are some of themost austere and uncomfortable waiting areas inthesystem,plaguedbyacombinationof issues:exposedconditions, freewaycongestionandnoise,deterioratinginfrastructure,alackofmaintenance,andasignificantreductionofnorthboundbusservicein2011.

Severalnear-termsolutionsshouldbecoordinatedtoprovideaclearpathfromthecurrentconditionstothesignificantinvestmentofOrangeLineBRT.

• Installpermanenttrashreceptacles.• Replacetherideralertsignagefrequently.Inadequatematerialscreateuncertaintyforpassengersusingthe

station,andindicatesabandonmentofthestop.• Refurbishthesouthboundshelter,orreplaceitwithstockavailableelsewhereinthesystem.Alarger,welllit

shelterwouldprovidegreatersecurityandseparationfromtraffic.• CoordinateMnDOT, City, andMetro Transit staff to visit the site and assess damaged infrastructure (e.g.

fencing)andovergrownvegetation.• Provide informationonsiteabout the35LakeTransit/AccessProjectandOrangeLineplanning to inform

customersaboutlong-termimprovements,andtobetterengagetransitridersintheplanningprocess.• WorkwithMnDOTtocoordinatetransitaccesstoandthroughtheareaduringconstruction.

Figure 5. Lake Street Station Preferred Platform Location and Connecting Bus Stops

July 2014 Page 9

METRO Orange Line BRT

Project Plan Update

selected freeway level brt platformp r o j e c t p a r t n e r s :Hennepin countycity of minneapolismn/dot metro transit

seH Inc.ee&K, a perkins eastman companycH2m Hill Zan assoc.

Figure 6. Plan of Lake Street Station Platforms from I-35W Level

LAKE STREET STATION

3

Figure 7. Rendering of Lake Street Station Plaza at Street Level

July 2014Page 10

METRO Orange Line BRT

Project Plan Update

2.2.3 46th Street Station: Operational

46thStreetStationinMinneapolis,whichopenedin2010,wasthefirstonlineBRTstationtobeconstructedintheTwinCities.LocatedbetweenthenorthboundandsouthboundlanesofI-35W,theconfigurationallowsbusestopickupanddropoffcustomerswithoutleavingthefreeway.CustomerswillboardOrangeLineandexpressbusesonthefreewaylevel,andtransfertolocalbusesonthe46thStreetbridge.

Short-term Improvements

Because of the single cross-over platformdesign at 46th Street, buses are required to stop at gate arms beforecrossingintothe46thStreetStation.TheEMTRACgatearmsystemiscurrentlyonlyinstalledonMetroTransitbuses,andthereforelimitedserviceisprovidedtothestation.BusesnotequippedwithEMTRACexperiencea45-seconddwellpenaltytoenterthefacility.InadvanceofOrangeLineservice,MetroTransitshouldrevisitMVTAandSouthwestTransitserviceto46thStreetStation, inparttobolstermid-dayandreversecommuteoptionsforcustomerswhocurrentlywaitupto30minutesforaMetroTransitbuswhileotherprovidersbypassthestation.

• Explorereducingdwelltimefornon-EMTRACbusesatthe46thStreetgatearms.Thecurrentwaitforthesebusesis45seconds,however,areductionto15secondscouldattracttheotherproviders,whichwouldinturnimprovetransitserviceandincreaseridershipatthe46thStreetStation.

PLATFORM

18

Figure 8. Rendering of Lake Street Station Platforms at I-35W Level

July 2014 Page 11

METRO Orange Line BRT

Project Plan Update

Figure 9. 46th Street Station Existing Platform Location and Connecting Bus Stops

Figure 10. Aerial View of 46th Street Station

July 2014Page 12

METRO Orange Line BRT

Project Plan Update

2.2.4 66th Street Station: Conceptual Design

Theplanned66thStreetStationinRichfieldisasmallerneighborhoodstationthatwillcatertowalking,bikingandbustransfers.DuetotherecentreconstructionofI-35Wover66thStreet,thenorthboundandsouthboundplatformswillbelocatedonI-35Wrampsinsteadofinmedianofthefreeway.Long-term,whenthebridgeneedstobereconstructed,a66thStreetOrangeLinestationcouldberelocatedtotheI-35Wmedian.

Four possible platform concepts were evaluated in 2013, two northbound and two southbound. Each site wascomparedusingspecificevaluationcriteriafoundinAppendixA.

NorthboundConceptAandSouthboundConceptDwerefoundtobemostsuitablewhen comparing traffic movementsand pedestrian access. The BRT stationconceptualdesignandpedestrianneedswillinformthe66thStreet(CountyRoad53)roadwayredesign,forwhichplanningiscurrentlyunderway.

Concept Description Pros Cons

A NorthboundNearside66th St on exit ramp

Morepedestrianspace,goodvisibility,existing535busstop,landadjacenttothesoutheastquadrantisownedbyCity

Re-entryintotrafficcouldbeanissue,trafficstackingnearside

BNorthboundFarside66th St on entrance ramp

CouldreducedelayatsignalFartherfromconnectingservice,lessvisible,constrainedspaceforplatform,lesspedestrianspace

C SouthboundNearside66th St on exit ramp Goodvisibility,existing535busstop

Re-entryintotrafficcouldbeanissuewithstackingnearside,heavysouthboundtowestboundturnmovement,mostconstrainedsite

DSouthboundFarside66th St on entrance ramp

Couldreducedelayatsignal,eastboundtosouthboundfreerightturnproducesfast-movingvehicletraffic

Fartherfromconnectingservice,lessvisible,constrainedspaceforplatform,lesspedestrianspace

Figure 11. 66th Street Alternatives for Platform Locations

July 2014 Page 13

METRO Orange Line BRT

Project Plan Update

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

LEFT T

UR

N LA

NE

EXISTING SIDEWALK

TH

RU

/RIG

HT T

UR

N LA

NE

I-35

W

EXISTING EDGE OF CURB

EXISTING SOUND WALL

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRIVATE PROPERTY

MONUMENT SIGNWITH VERTICAL LIGHT ELEMENT,TVM & DISPLAY MONITOR

ENCLOSED SHELTER

LEAN RAILS/BENCHES

BICYCLE RACKSUNDER SHELTER ROOF

COVERED SHELTER

66TH STREET

TACTILE EDGECONTINUOUS ATPLATFORM

EXTENTS OF CANOPY ROOF

12’

PROPOSED20’ R

12’ 16’

EXIS

TIN

G C

UR

B T

O R

EM

AIN

EXIS

TIN

G C

UR

B T

O R

EM

AIN

NEW

CO

NC

RET

E95’

PLA

TFO

RM

LEN

GT

H

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

EXISTING SIDEWALK

TH

RU

LA

NE I-35

W

EXISTING EDGE OF CURB

EXISTING SOUND WALL

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRIVATE PROPERTY

LEAN RAILS/BENCHES

COVERED SHELTER

66TH STREET

TACTILE EDGECONTINUOUS AT

PLATFORM

EXTENTS OF CANOPY ROOF

N

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCTP

RO

DU

CE

D B

Y A

N A

UT

OD

ES

K S

TU

DE

NT

PR

OD

UC

T

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

ENCLOSED SHELTER

MONUMENT SIGNWITH VERTICAL

LIGHT ELEMENT,TVM & DISPLAY

MONITOR

BICYCLE RACKS

BU

S/T

HR

U LA

NE

RETAINING WALLS

85’

PLA

TFO

RM

LEN

GT

H

12’ 12’ 12’

PROPO

SED

20’ R

EXIS

TIN

G C

UR

B T

O R

EM

AIN

RE-A

LIG

N C

UR

B (

+/-

) 4’

WEST

NEW

CO

NC

RET

E

REAL TIMEDISPLAY MONITOR

EXISTING SOUND WALL

Figure 12. 66th Street Station Preferred Platform Locations and Connecting Bus Stops

Figure 13. Conceptual Design for Northbound Platform at 66th Street Station

Figure 14. Conceptual Design for Southbound Platform at 66th Street Station

July 2014Page 14

METRO Orange Line BRT

Project Plan Update

1/32" = 1'-0"5

66th NB Elevation 1/32" = 1'-0"

266th SB Elevation

1/32" = 1'-0"3

98th N & S Elevation

1/32" = 1'-0"4

98th Porkchop Elevation

1/32" = 1'-0"1

98th Porkchop Elevation from 98th

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

12’24

MONUMENT SIGN WITH VERTICAL

LIGHT ELEMENT, TVM & DISPLAY MONITOR

66TH STREET

NORTH BOUND PLATFORM

Figure 15. Conceptual Elevations for Northbound Platform at 66th Street Station

July 2014 Page 15

METRO Orange Line BRT

Project Plan Update

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

1/32" = 1'-0"5

66th NB Elevation 1/32" = 1'-0"

266th SB Elevation

1/32" = 1'-0"3

98th N & S Elevation

1/32" = 1'-0"4

98th Porkchop Elevation

1/32" = 1'-0"1

98th Porkchop Elevation from 98th

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

1/32" = 1'-0"5

66th NB Elevation 1/32" = 1'-0"

266th SB Elevation

1/32" = 1'-0"3

98th N & S Elevation

1/32" = 1'-0"4

98th Porkchop Elevation

1/32" = 1'-0"1

98th Porkchop Elevation from 98th

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

1/32" = 1'-0"5

66th NB Elevation 1/32" = 1'-0"

266th SB Elevation

1/32" = 1'-0"3

98th N & S Elevation

1/32" = 1'-0"4

98th Porkchop Elevation

1/32" = 1'-0"1

98th Porkchop Elevation from 98th

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

1/32" = 1'-0"5

66th NB Elevation 1/32" = 1'-0"

266th SB Elevation

1/32" = 1'-0"3

98th N & S Elevation

1/32" = 1'-0"4

98th Porkchop Elevation

1/32" = 1'-0"1

98th Porkchop Elevation from 98th

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

MONUMENT SIGN WITH VERTICAL

LIGHT ELEMENT, TVM & DISPLAY MONITOR

12’ 24

66TH STREET

SOUTH BOUND PLATFORM

Figure 16. Conceptual Elevations for Southbound Platform at 66th Street Station

July 2014Page 16

METRO Orange Line BRT

Project Plan Update

2.2.5 76th Street and American Boulevard Stations: Planning

Station improvements for the American Boulevard area are integrated into planning for the larger I-494/35Winterchangedesign.TheexistingKnoxAvenuepark-and-ride lot inRichfield,builtonMnDOT right-of-wayneededfortheplannedinterchange,willberelocatedandreplacedwithanewparkingrampneartheAmericanBoulevardstation.The2013processforstationplanningwascompletedaspartoftheI-494/35WInterchangeVisionLayoutDevelopmentledbyMnDOT.

The494/35WTechnicalAdvisoryCommittee(TAC)firstreviewedthreepreliminaryconceptsdevelopedduringpriorinterchangeplanning in2010.Basedon thispriorwork, theTAC further refinedconcepts,aswell asaddingnewlocationsanddesignsthatwerenotpreviouslyconsidered.Fouroptions,showninthetablebelow,werethenstudiedbasedonagreed-uponevaluationcriteriainthreecategories:transitstationdesign,busoperations,andtransitriderbenefit.

The ratingswerebasedona simple relativecomparisonofpositive,neutral andnegative impacts to thedefinedevaluationcriteria.AcopyofthecriteriaandevaluationmatrixisincludedinAppendixA.TheTACgroupcomparedtheseratings,discussedindividualvariations,andreachedconsensusonrelativebenefitandimpactofeachconcept.Concepts1A,3A,and3Bwereselectedtobedevelopedinfurtherdetail.

ThesethreedetailedconceptsconsideredtwodifferentapproachestotheOrangeLinealignment.Inthefirstoption,theOrangeLinewouldstayonI-35W,stoppingatanewtwo-storymedianstation,similartotheexistingBRTstation

Concept Description Pros Cons

1

1A:MedianStationonI-35WunderedgeofAmericanBoulevard Bridge 1B:MedianStationonI-35Wcentered under American Boulevard Bridge 1C:MedianStationoverI-35W,atAmerican Boulevard level

Efficientbusoperations,goodstationvisibilityfromfreeway,eliminatesverticalcirculationbetweenstations(1C),couldbeusedbyotherI-35Wtransitprovidersandroutes

Noiselevelsonfreewayplatforms,requiresmajorroadwaywideningandbridgemodification,verticalcirculationtowersneeded,difficultpeakmerge movement to 66th Street shoulderstation,RichfieldisnotservedbyastationatAmerican

2 MedianStationonI-35Wat81stStreet

Efficientbusoperations,goodstationvisibilityfromfreeway,nobridgemodificationneededatAmerican,couldbeusedbyotherI-35Wtransitprovidersandroutes

Noiselevelsonfreewayplatforms,requiresmajorroadwaywidening,verticalcirculationtowersneeded,Richfieldisnotservedbyastationat81st,longtransittransferdistancebetweenOrangeLineandAmericanBoulevard,dependentonaparkingfacilitycloseadjacenttoI-35W,requiresanewskywaytoconnecttoparkingfacilityandlocalstreets

July 2014 Page 17

METRO Orange Line BRT

Project Plan Update

Figure 17. American Boulevard Alternatives for Platform Locations

July 2014Page 18

METRO Orange Line BRT

Project Plan Update

on I-35Wat46thStreet.Theotheroptionswouldbring theOrangeLine to twosidewalk-adjacent stationsalongthealignmentofKnoxAvenuethroughSouthtown,viaeither82ndStreetand76thStreet(Concept3A)oracenter-running transit ramp to American Boulevard (3B). The 3A/3B “Knox Alignment” would require establishing newrightofwaybetweenAmericanBoulevard and I-494, and connectingKnoxAvenueunder I-494 toRichfield. ThisconfigurationallowsforstationsinbothBloomingtonandRichfield,andtheunderpasswouldaccommodatebicyclesandpedestriansinadditiontotransit,providinganewregionallinkacrossthehighwayandbetterconnectingjobs,housing,andredevelopmentareas.

Options1A,3A,and3Bwerestudiedinfurtherdetailtobetterunderstandqualitieslikepedestrianinfrastructure,transitserviceandoperability,accesstodestinationsandhousing,integrationwithplannedredevelopment,andcost.3Bwaseliminatedduringthisprocessduetomuchhigherestimatedcostswithoutclearbenefitsoveroption3A.AdditionalinformationontheevaluationofthesethreealternativesisavailableinAppendixA.

Concept Description Pros Cons

3

3A:TwoKnoxAvenuestations,using76thand82ndStreets 3B:TwoKnoxAvenuestations,using76thStreetandaT-rampinto the American Boulevard Bridge

Goodstationvisibilityfromlocalstreets,at-gradewaitingareas,shorterwalkdistancestomajordestinations,twostationsincreasehousingandjobswithin½milewalkshed,bringstransitclosertoheartofPennAmericanDistrict,nobridgemodificationorROWneededatAmericanandI-35W(3A),Richfieldisbetterservedbytransit,improvedtransfersandreducedoperationalcostforcrosstownroutes,multipleoptionsforparkingfacilitylocation,opportunitytoaddnewpedestrian/bikeconnectionacrossI-494

RequiresROWthroughSouthtownproperty,requiresmajorroadwaywideningandbridgemodification(3B),mergestillneededfrom98thtoT-rampnorthbound(3B),requiresrelocationof42”watermainbetweenAmericanandI-494,longertraveltimesforOrangeLine,reducesdevelopmentbenefitseastof35W

4CombinedparkingstructureandstationwestofI-35Wat81stStreet,withT-rampintostation

DirecttransitaccessfromI-35Wtoparkingstructure,transitstationandparkandridearecollocated,eliminatesneedforseparateverticalcirculation,couldbeusedbyotherI-35Wtransitprovidersandroutes

Requiresmajorroadwaywideningandbridgemodification,longtransittransferdistancebetweenOrangeLineandAmericanBoulevard,dependentonaparkingfacilitycloseadjacenttoI-35W,difficultpeak merge movement to 66th Streetshoulderstation,RichfieldisnotservedbyastationsouthofAmerican

July 2014 Page 19

METRO Orange Line BRT

Project Plan Update

BEST BUY

SOUTHTOWN

I-494

I-35W

AMERICAN BLVD

PENN

AVE

LYND

ALE AVE

76TH ST

KNO

X AVEPENN AMERICAN DISTRICT

ORANGE LINE AMERICAN BOULEVARD ALIGNMENT ALTERNATIVES

1: I-35W Alignment3: Knox Avenue Alignment3A: 82nd Street TSP3B: American Boulevard Ramp

Figure 18. Comparison of Options 1A, 3A, and 3B

Concept 3A Concept 1A

BRTTravelTimebetween98thand66th

9 – 11 min (45-55%fasterthanRoute535)

7 – 8 min (52-58%fasterthanRoute535)

Housing&Jobswithin½Mileofstation(s)

12,800Residents 13,100Jobs

4,600Residents 8,300Jobs

Streetoperations

Transitpriorityandcoordinationofsignalsisneeded.Requestremovalof“norightturnonred”at76thStexit

NorthboundmergefromAmericanto66thisnotpossibleduringtheAMPeak(1.25miles)

Serviceimplicationsforconnectingroutes

Route540stayson76thStreet,Route542staysonAmericanBoulevard

Route540bendssouthtoAmericanBoulevardforonemiletointersectstation

Preliminaryestimatesfortransitcosts $30M $36M

July 2014Page 20

METRO Orange Line BRT

Project Plan Update

The I-494/35W Interchange TAC recommendedOption 3A tomove forward for the further study, informing theinterchangedesignandthelocationofafuturepark-and-ridefacility.RoutingtheOrangeLineviaKnoxAvenue,using76thand82ndStreet,providesabetteropportunitytointegratefrequent,reliabletransitintoagrowingneighborhood.Thetwo-stationconfigurationprovidesseveralbenefitstothecorridor:

• Enhancingthetransitcustomerexperience.Eachsitewouldprovidecomfortable,sidewalk-adjacentstations,withopportunitiesforlandscaping,publicart,bicycleparking,transitconnections,andenhancedstreetscape.

• Putting transitwhere peoplewant to be. KnoxAvenuemaximizeswalk access tomajor destinations andhousing,andminimizesimpactstoexistingtransitridersbyprovidingstationsonbothsidesofI-494.

• Integratingtransitintoexistingandplanneddevelopment.Becauseofconcurrentroadway,transitway,andlanduseplanning,thereisarareopportunitytoproactivelyplacethestationsinproximitymoredevelopablelandandexistingdevelopment.Thismaximizesthelong-termlandusebenefitsofhavingastationandbuildsonstrongexistingridership.

• Eliminatinglong-termoperationalissues.Evenundercurrentcongestion,mergingfromamedianstationatAmericanBoulevardtoashoulderstationat66thStreethasbeendeemedoperationallyinfeasible,particularlyintheAMpeakperiod.ThismaneuverwouldrequireOrangeLineservicereductionstoAmericanBoulevardorto66thStreetduringthebusiestpartoftheday.

• Reducingcapital,maintenance,andoperatingcost.Option3AislesscostlythanbothOptions1Aand3B,whilestillvastlyimprovingtransitserviceandaccess.Connectingeast-westbusroutesareabletorunsimplified,griddedroutes,reducingbusoperatingcostsandpassengerdelay.Street-levelstationseliminatetheneedforelevators,stairs,andskyways,reducingannualmaintenanceneedsandcosts.

• Expandingoptionsformeetingparkandridedemand.Twostationswidenthesearchareaforlocatingapark-and-ridefacility,andincreaseopportunitiesforjointdevelopmentorshared-useparking.

Concurrent Land Use Planning

TheKnoxAvenuealignmentbuildsoncityplanningfocusedonthelong-termredevelopmentofthePenn American District,andareaalongAmericanBoulevardprimarilybetweenPennAvenueandI-35W.Withitsfavorablelocationintheregion,thePennAmericanareadevelopedasaretailshoppinghubmorethan40yearsagoduringthefirstphaseofsuburbangrowth intheTwinCities.Shifts intheeconomyandchangingmarketpreferences,alongwiththeprevalenceofagingbuildingsandlargeamountsof landdevotedtoparkingintheDistrict,presentsignificantopportunitiesforredevelopment.

The PennAmericanDistrictPlanwasadoptedbytheCityofBloomingtoninJanuary2014,helpingtheDistrictmeetitspotentialbydefiningaclearvisiontoguideredevelopmentandinvestmentsinpublicinfrastructure.KeyelementsofthePennAmericanvisioninclude:

• Addingnew,pedestrian-friendlystreetsandcreatingsmallerdevelopmentblocksasredevelopmentoccurs;• Increasingdevelopmentintensityanddiversifyingthemixoflanduses;• Improvingthequalityandcharacterofbuildingsandpublicspaces;• Increasingmobilitythroughtargetedimprovementstoroads,bikeways,andsidewalks;and• Leveragingtheproposedsubstantialinvestmentsintransitandtransportationinfrastructure.

July 2014 Page 21

METRO Orange Line BRT

Project Plan Update

Figure 19. 76th Street Station Preferred Platform Locations and Connecting Bus Stops

Figure 20. American Boulevard Station Preferred Platform Locations and Connecting Bus Stops

July 2014Page 22

METRO Orange Line BRT

Project Plan Update

2.2.6 98th Street Station: Conceptual Design

98th Street Station inBloomington is informedbyapreliminary stationdesign thatwasdeveloped in2011. ThisoriginaldesignassumedthatthesouthboundplatformwouldbelocatedonDupontAvenueSouthat98thStreet,about1,700feetfromtheplannednorthboundplatformatSouthBloomingtonTransitCenter.Aconcentrateddesigneffortin2013providedadditionalguidanceonwhetherthisoriginaldesignisfeasible,ifadditionalcomponentswereneeded,orifalternatelocationsforthedesignedsouthboundplatformshouldbeconsidered.Eightalternativeswerestudiedfornorthboundandsouthboundplatformlocations.

Figure 21. 98th Street Alternatives for Platform Location

Concept and

DescriptionPros Cons

A

Northbound,nearsideinline 98th Street

Quickaccessforbuses,adjacenttoexistingstation,shorttransferdistance,eliminatespedestrian-vehicleconflicts,easiertomaintainadjacenttotransitcenter,personalsafety/visibility

Futureinterchangedesignmayrequirerelocatingstation,needtoadddirectpedestrianaccessto98th

BNorthbound,shoulderonline35W

Quickaccessforbuses,eliminatespedestrian-vehicleconflicts

Gradeissues,verticalcirculationandskywayneededtoSBTC,futureinterchangedesignmayrequirerelocatingstation

July 2014 Page 23

METRO Orange Line BRT

Project Plan Update

Concept and

DescriptionPros Cons

CSouthbound,farsideinlineDupontAve

AccesstoHOVonrampforbuses,fastertransferstowestboundbuses(NormandaleCollege),fasterthrough-travelfortransitridersgoingtoBurnsville,ridersstillhaveoptionofgoingdirectlytoSBTConexpressroutes

DistancefromSBTCandparkandride,novisualtiestotransitcenter,notlegibleaspartofanorth/southpair,impactonadjacentresidentialproperty,minimalspaceforstationplatform,multipledifficultpedestriancrossingstoaccessstation

D

Southbound,inline 98th Street betweenDupontand35W

Fasterthrough-travelfortransitridersgoingtoBurnsville,ridersstillhaveoptionofgoingdirectlytoSBTConexpressroutes,somevisualtietoSBTC

DistancefromSBTCandparkandride,notlegibleaspartofanorth/southpair,leftturnfromexitrampintofarrightlaneof98th,adjacenttosideofbuilding,noHOVadvantageatonramp,highPMpeaktrafficeastboundon98th,multipledifficultpedestriancrossingstoaccessstation,moredifficulttransfertowestboundtransit

E

Southbound,nearsideinline exit ramp

AccesstoHOVonrampforbuses,fastertransferstowestboundbuses(NormandaleCollege),fasterthrough-travelfortransitridersgoingtoBurnsville,ridersstillhaveoptionofgoingdirectlytoSBTConexpressroutes,somevisualtietoSBTC

DistancefromSBTCandparkandride,notlegibleaspartofanorth/southpair,fast-movingtrafficturningrightonto98th,multipledifficultpedestriancrossingstoaccessstation,requiresthemostroadwaymodificationoftherampand98th

FSouthbound,farsideinlineon ramp

Fasterthrough-travelfortransitridersgoingtoBurnsville,ridersstillhaveoptionofgoingdirectlytoSBTConexpressroutes,somevisualtietoSBTC

Gradeissues,distancefromSBTCandparkandride,notlegibleaspartofanorth/southpair,leftturnfromexitrampintofarrightlaneof98th,noHOVadvantageatonramp,highPMpeaktrafficeastboundon98th,multipledifficultpedestriancrossingstoaccessstation,moredifficulttransfertowestboundtransitand98thStreetdestinations,potentialrightofwayissues

GSouthbound,shoulderonline35W

Quickaccessforbuses,eliminatespedestrian-vehicleconflicts

Gradeissues,verticalcirculationandskywayneededtoSBTC,moredifficulttransfertowestboundtransitand98thStreetdestinations,potentialrightofwayissues

H

Southbound,nearsideinline 98th Street

Routeissimilartoexisting465,eliminatespedestrian-vehicleconflicts,createsasingletransithubwithdirectaccesstobustransfers,easiertomaintainadjacenttotransitcenter,legibleaspartofanorth/southpair,personalsafety/visibility,bringsridersdirectlybacktopark-and-ride,bestaccessto98th/Lyndaledestinations,relativelylowcosttoaddontotonorthboundplatform

LongesttimepenaltyforridersgoingthroughtoBurnsville,multipleturnstogetintostation,combinednorthbound/southboundplatformmayconfuseriders,trafficsignaldelay

July 2014Page 24

METRO Orange Line BRT

Project Plan Update

Short-term Improvements

Thepark-and-ridefacilityatSouthBloomingtonTransitCenterisovercapacityduringtheschoolyear,withcommutervehicles regularly spilling intocommercialand institutionalareasadjacent to thesite3. SBTChaspopularexpressservicetodowntownMinneapolisandtheUniversityofMinnesota,andparkingdemandhasquicklyoutstrippedtheavailablespaces.WhilethedevelopmentofanAmericanBoulevardpark-and-ridefacilityshouldhelprelievebroaderparkingdemandinSouthBloomingtonlong-term,usercomplaintsandillegalparkinghavebecomecommonplace,acceleratingtheneedtofindnear-termsolutionsatthisstation.Duringthe2013conceptualdesignwork,additionalissueswereraised,includingchangingassumptionsaboutthedesignofafutureinterchange,thestatusandpossiblerestrictionson the transit centerparcel4, future landuse intensification,andbicycleandpedestrian connectionsacrossI-35W.Toprovidecoordinatedandcomprehensivetransportationandlanduseplanning,a98thStreetStationAreaPlanshouldbedeveloped.3 2013 Annual Regional Park-and-Ride System Report. 201 vehicles were counted at South Bloomington, a facility with only 195 designated parking spaces.4 The park and ride was purchased with the Right-of-way Acquisition Loan Fund (RALF) to landbank for a proposed full interchange at 98th Street. Because MnDOT is unable to purchase highway right-of-way until a road is programmed for construction, many acres which will are needed for future road right-of-way have been lost to development. To address this, the 1982 Minnesota legislature established a revolving loan fund program to acquire undeveloped property threatened by development that is located within an officially-mapped metropolitan highway right-of-way. The transit center was proposed as an interim use until which time that the interchange is reconstructed and an online bus station can be constructed.

TheOrangeLineisnotproposedtoserveNormandaleCollegedirectly,butratherconnecttoimprovedcross-townbusservicetoincreaseoveralltransitaccess,viaeithertheAmericanBoulevardor98thStreetstation,orboth.Itiscriticalthat98thStreetStationplanningcarefullyconsiderthisconnectionbecause17%ofalldaily535tripsin2012beganorendedatNormandaleCollege.Additionally,expressroutes597and465complementserviceinthesouthernportionoftheproposedroute,especiallyatSouthBloomingtonTransitCenter,whereimportantconnectionstolocalbusesaremade.

Various ridership benefits and impacts were weighed and evaluated by a subset of the Orange Line TechnicalAdvisoryCommittee.Ratingswerebasedonasimplerelativecomparisonofpositive,neutralandnegativeimpactstothedefinedevaluationcriteria.AcopyofthecriteriaandevaluationmatrixisincludedinAppendixA.Thegroupcomparedtheseratings,discussed individualvariations,andreachedconsensusonrelativebenefitand impactofeachconcept.Overall,ConceptAandHwerepreferredintheevaluationbecausetheyprovidethesafestandmostlegibleenvironmentforpassengersmakingbustransfersandwalkingtodestinations,andbecauseoftheproximitytotheexistingtransitcenterandparkandride.Arecenttransitridersurveyreinforcedthedesiretocreateasingletransithub,withstrongconnectionstolocalandexpressroutes:

Most Important for 98th Street Station Design

• Ease of transfer to other routes• Speed of service to Burnsville • Close proximity to park and ride

Least Important for 98th Street Station Design

• Bike parking and pedestrian infrastructure • Convenient to walk to destinations east of 35W• Ease of transfer to Normandale College

Route 18 34%

Route 465 20%

Route 539 25%

Route 554 5%

Route 597 16%

Which other routes do you use at 98th Street Station?

Which other routes do you use at 98th Street Station?

July 2014 Page 25

METRO Orange Line BRT

Project Plan Update

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

PR

OD

UC

ED

BY

AN

AU

TO

DE

SK

ST

UD

EN

T P

RO

DU

CT

PRODUCED BY AN AUTODESK STUDENT PRODUCT

THRU LANE

EXISTING PLATFORMS

BUS/THRU LANE

MONUMENT SIGN WITH VERTICAL LIGHT ELEMENT, TVM & DISPLAY MONITOR

ENCLOSED SHELTERBICYCLE RACKSUNDER SHELTER ROOF

98TH STREET

TACTILE EDGECONTINUOUS AT

PLATFORM

I-35W

NEW PEDESTRIAN ACCESSSOUTH BOUND PLATFORM NORTH BOUND PLATFORM

SITE LIGHTINGLEAN RAILS/BENCHES

RETAINING WALLS &STORM DRAINAGE STRUCTURES

EXISTING DRAINAGE SWALETO REMAIN

NEW PEDESTRIANACCESS

EXISTINGTRANSITBUILDING

PARK & RIDE PARKING

PARK & RIDE PARKING

296’ 14’

14’

16’ 6’

SOUTH BLOOMINGTONTRANSIT CENTER

Figure 22. 98th Street Station Platform Location and Connecting Bus Stops

Figure 23. Conceptual Design for Northbound and Southbound Platform at 98th Street Station

July 2014Page 26

METRO Orange Line BRT

Project Plan Update

2.2.7 Burnsville Transit Station: Conceptual Design

BurnsvilleTransitStation,ownedandoperatedbyMVTA,isahigh-quality,existingstationandpark-and-ridefacilitythatprovideskeyconnectionstothesouthmetro.It isthelargestparkandridealongI-35WSouth,andthethirdlargestintheregionalparkandridesystem.BusloadingandlayoverspaceatBurnsvilleTransitStationiscurrentlyatapremium,withadditionalservicesplanned.DesignworkisneededaspartoftheOrangeLineprojecttoexploreoptionsforaccommodatingBRT.

TwolocationsarebeingconsideredtoserveasaBRTstation inBurnsville:expandingBurnsvilleTransitStationbyaddinganOrangeLineplatform,orprovidingnewtransitstationcapacityatthesouthwestcornerofNicolletAvenueandHighway13.Thelattersite,referredtoasthe“TravelersTrail”site,isasurfaceparkinglotonMnDOTrightofwaythatpredatestheopeningofBurnsvilleTransitStation.TheTravelersTrailsitehasalimited-usepermitthatrestrictsittobeusedonlyfortransitpurposes,makingitundevelopableforotherlanduses.

WorkingcloselywithMVTA,CityofBurnsville,DakotaCounty,andMnDOT,MetroTransitwillevaluatebothsitesindetailin2014tofindthebestfitforshort-andlong-termneeds.Evaluationcriteriawill includefactorsliketransitvehiclecapacity,layoverneeds,ridership,existingandanticipatedbustripvolumes,park-and-ridedemand,pedestrianandvehicleaccess,abilitytoconnecttolocalandcomplementaryI-35Wroutes,transitaccessandcirculation,physicalandoperationalconstraints,andopportunitiesforsharedinfrastructureandmaintenance.

In2014,apreferredlocationwillbechosenandconceptualdesignwillbecompleted.Thisdesignplanwillidentifythelayoutofthestationarea,includingshelters,platformsandloadingarea,layoverarea,technologycomponents,roadwaychanges,andimpactstopedestrian,bike,vehicle,andtransitcirculation.

Figure 24. Possible sites for Burnsville Transit Station Gate Expansion

July 2014 Page 27

METRO Orange Line BRT

Project Plan Update

2.3 Guideway

2.3.1 Downtown

OrangeLinewillusethetransitadvantagesonMarquetteAvenueand2ndAvenue(MARQ2)indowntownMinneapolis,providingfasterserviceandtheabilitytomovemorepeoplethroughdowntownatpeaktimes.In2009,MarquetteAvenueand2ndAvenueSouthwerereconstructedtoprovideside-by-sidebus-onlylanesandaccommodate80%ofexpressbustripsindowntownMinneapolis.

InaccordancewiththeAccessMinneapolisDowntownActionPlan,severalimprovementsbetweenI-35WandMARQ2arecurrentlyunderstudy.MetroTransit,theCityofMinneapolis,MnDOTareexploringthefeasibilityofextendingthe I-35Wmanaged lane intodowntownbothnorthboundandsouthbound,providingamoreseamless, reliableconnectionbetween the freewayand the local streetnetwork.BRTaccess shouldconnect toMARQ2asdirectlyaspossible,andmayrequirechangestostriping,signalsand/orramps in theareaboundedby10thStreet,12thStreet,MarquetteAvenueandPortlandAvenue.AtaminimumthesechangeswouldprovidespeedandreliabilityimprovementsforOrangeLinebuses,buttheycouldpotentiallyprovidebenefittootherMARQ2busesaswell.Apreferredconceptandplanning-leveldesignwillbeproducedin2014.

Figure 25. Concepts for Connecting MARQ2 and I-35W Transit Advantages

July 2014Page 28

METRO Orange Line BRT

Project Plan Update

Concept Description Pros Cons

A

Northbound,10thStreetbus-onlyexit ramp into intersectionwith10thStreetbus-onlywestboundcontraflowlane

Busstaysinmanagedlaneintodowntown,greenspaceisonexistingrightofway,minimalgradingneeded,noparkingimpacted,nostructureneeded,tieinto4th/10thsignal,redistributestransitonstreetwithlowerAADT(8,700at2ndAve)

Impactsedgeofgreenspace,signalworkneededat4thand3rd,requires10thStcontraflowlane,needtorelocateorshiftbikelanebetween2ndand4th,twocurbcutsonnorthsideof10thbetween2ndand3rdforsurfaceparkinglot,eliminatessouthernstopsonMARQ2

B

Southbound,10thStreetassignmentofHOVtocenterlaneintoHOVentranceramp

Putsbusincentermanagedlane,eliminatesconflictofsouthboundleft-turningbusesonMarquetteAveandnorthboundright-turningbusesoff1stAve,nosignalworkneeded,noparkingimpacted,exploreremovingHOVrampat12thandreplacewithgeneralpurposeentranceramp,redistributestransitonstreetwithlowerAADT(8,700at2ndAve)

EliminatessouthernstopsonMARQ2,somegeneralpurposetrafficwillneedtobereassignedto12thSt

C

Southbound,11thStreetflyoverbus-only entrance ramp with11thStreetbus-onlyeastboundcontraflowlane

Putsbusincentermanagedlane,eliminatesconflictofsouthboundleft-turningbusesonMarquetteAveandnorthboundright-turningbusesoff1stAve

Bridgecostsfor11thandFlyover,mayneedtomodifybridge,reduceslengthofHOVlaneonI-35W,signalworkneeded,reduces10thStreetcapacity–mayrequire10thentranceramptomergeintoonelaneatpointofflyoverssouthbound,parking,hotelloading,andcabstandimpacts,eliminatessouthernstopsonMARQ2,segmenthashighestAADTof3streets(19,400at2ndAveand29,200at3rdAve)

D

Southbound,12thStreetflyoverHOVentrance ramp and 12th Street general purposeentranceramp

PutsbusandHOVincentermanagedlane,keepsexistingMARQ2patternandstops,maybeenoughROWtomake10thStgeneralpurposeentrance2lanes,minimalgradingneededtoconvertexistingHOVtogeneralpurpose,lowerAADTthan11thSt(7,900to10,300betweenMarquetteandI-35W)

Bridgecostsforflyover,mayrequire10th entrance ramp to merge into 1 laneatpointofflyoverssouthbound,Southboundleft-turningbusesonMarquetteAvestillconflictwithnorthboundright-turningbusesoff1stAve,exploremovingnorthbound1stAvebusestoGrantSt

July 2014 Page 29

METRO Orange Line BRT

Project Plan Update

2.3.2 I-35W

TheOrangeLinealignmentwilluseacombinationofmanagedlanes,bus-onlyshoulders,dedicatedtransitguideway,HOVrampbypasslanes,andshortsegmentsofmixedtraffic.

Center-running Managed Lanes

Northofthe66thStreet,METROOrangeLinebuseswillusecenter-runningMnPASSlanes,whichhelpmaintaintrafficflow,reducecongestionandgiveasafe,reliablecommutetothoseridingtransit,travelinginacarpoolorvanpool,orusingaMnPASStransponder.Thepricedhigh-occupancylanesexistonI-35WfromHighway13toapproximately22ndStreetnorthbound,and42ndStreettoHighway13southbound.Asnotedabove,MetroTransit,theCityofMinneapolis,MnDOTarestudyingtheextensionofmanagedlanestoconnectintodowntownMinneapolis.

OnemajorgapintheI-35Wmanagedlanesystem,betweendowntownand42ndStreetsouthbound,isbeingplannedbyMnDOTforimplementationwiththeOrangeLineandthe35LakeTransit/AccessProject.Thispavementreclamationprojectwillalsoconvertthenorthboundpriced-dynamicshoulderlaneintoafullmanagedlane.

Bus-only Shoulders

Southof46thStreet,allOrangeLinestationsarelocatedeitherontheoutsideshoulderorinofflinelocations.Thetransitwaywilluseacombinationofbus-onlyshouldersandhigh-occupancyvehiclebypassrampsthroughthissectionoftheprojecttomaintainreliability.

Withmorethanthreetimesthenumberofmilesthanallothermetroareascombined,theTwinCitiesisaleaderintheuseofbus-onlyshoulders.Whileacost-effectivewayforbusestoavoidtraffic,therearecertainconditionsunderwhichoperatorsmaychosenottousetheshoulder.Operatorsconsiderthefollowingfactorswhendecidingwhethertouseabus-onlyshoulder:

• Roadconditions.Sinkingdraincovers,potholesorotherroaddefectscaninterruptuse;• Weather.Heavysnow,slushandicemustbeadequatelyclearedtoallowforsafeoperations;• Obstructions.Roaddebris, stalledmotoristsandconstructionvehiclesareunavoidableobstacles thatprevent

busesfromusingshoulders;• Traffic.Bus-onlyshouldersmayonlybeusedwhentraffichasslowedtolessthan35milesperhour(themaximum

speedis15milesperhourgreaterthantraffic,withamaximumspeedof35milesperhour);and• Othervehicles.Extra-widevehiclesinmixed-trafficcanpreventtheuseofbus-onlyshouldersbecauseofclearance

issues.Emergencyvehiclesalsotakepriority. Between 98th Street and 82nd Street, bus shoulders do not yet exist. Bridge piers at certain locationsmay preventexpansionoftheshoulderwithoutsignificantgradechangesandretainingwalls.However,overtimeCityofBloomingtonhasacquiredlandadjacenttobothsidesofI-35Wforfutureexpansionneeds.AdditionaldiscussionisneededwiththeCityandMnDOTtounderstandthelong-termneedsfortransitadvantagesinthisareashouldcongestiongrowenoughtomakethemergetoandfromthemanagedlaneinfeasible.BetweentheMinnesotaRiverBridgeand98thStreetStation,travelingnorthbound,thereisanexistingclimbinglanefortrucktrafficthatshouldbestudiedtoaccommodatetransitifabus-onlyshoulderispursued.

River Bridge Crossing

MnDOTisadvancingtheengineeringfortheI-35WMinnesotaRiverBridgereplacementprojectinpreparationforaspring

July 2014Page 30

METRO Orange Line BRT

Project Plan Update

of2017letting.High-levelscopingdonein2014shouldaimtopreserveandenhancetransitadvantagesforOrangeLinebusesandexpressbuses.Bothacenter-runningmanagedlaneandanoutsidebusshoulder shouldbe included in thedesignof theplannedbridge.

2.3.3 76th Street, Knox Avenue, and 82nd Street

Southboundfrom66thStreet,theOrangeLinewillusethebus-onlyshoulderandexitat76thStreet.Buseswillturnrightonto76thandleftontoKnoxAvenue,andcontinuedownto82ndStreetwhereitre-entersI-35W.

Northbound from 98th Street, buses will use either themanagedlaneorafuturebus-onlyshouldertoexitat82ndStreet, turning left onto 82nd Street and right onto KnoxAvenue.Buseswillthenturnrightonto76thStreetandleftontoI-35W,usingtheHOVrampbypasstoenterthebus-onlyshoulder.

The cross-section of Knox Avenue between AmericanBoulevardand76thStreetwillbedesignedindetailthisyear,workingtominimizepropertyandaccessimpactstoexistingdevelopment. It will include, at a minimum, a dedicatedtransit guideway as well as a new bicycle and pedestrianconnectionacrossI-494.WorkingwiththeCitiesofRichfieldandBloomington,MetroTransitwilldeterminetheinterestandfeasibilityofotherimprovementsforthisnewunderpass,includingthepotentialtoaddgeneralpurposetravellanesorstreetscapeenhancements.

This routing is similar to the current Route 535, whichutilizes76th,KnoxAvenue,and82ndStreet.BecauseofthededicatedguidewayandnewKnoxAvenuerightofway,theOrangeLinewillpassthroughsevenfewertrafficsignalsthanthe535,resultinginatimesavingsofbetween45%and55%forBRTthroughthisarea.

2.3.4 98th Street

SouthboundbuseswilltravelviaI-35Wto98thStreet,AldrichAvenue,99thStreet,andBloomingtonFreewayRoadtonewOrangeLineplatform.Leavingthestation,buseswillturnleftonto98thStreettoloopdirectlyintosouthboundI-35W.ThisrouteissimilartohowRoute465currentlyoperates.

Figure 26. Knox Avenue Routing

Figure 27. 98th Street Routing

July 2014 Page 31

METRO Orange Line BRT

Project Plan Update

Northbound,buseswill exit at98thStreetdirectly to the sameOrangeLineplatform, then re-enternorthboundI-35W.AHOVrampbypassentranceisavailablenorthbound.

2.3.5 Highway 13 and Nicollet Avenue

Routingwillbedeterminedin2014withtheevaluationandselectionofapreferredplatformlocationinBurnsville.Twooptionsareshownabove.

Figure 28. Burnsville Routing for Site Alternatives

July 2014Page 32

METRO Orange Line BRT

Project Plan Update

2.4 Right of Way Needs

2.4.1 Knox Avenue Guideway and Park and Ride

KnoxAvenue is apublic street inRichfieldnorthof I-494,and inBloomington southofAmericanBoulevard.ThealignmentofKnoxAvenuebetweenAmericanandI-494wasneverplatted.Itisaprivately-ownedservicedrivefortheSouthtownshoppingcenter.MetroTransitcurrentlyusesthisservicedrivetoreachbusstopswithintheproperty.Approximatelytwoacres(900linearfeet)areneededtoestablishapublicly-ownedtransitwayalongtheKnoxAvenuealignmentbetweenAmericanBoulevardandI-494.

Theplannedpark-and-ridefacilitynearAmericanBoulevardwillbestudiedinmoredetailduring2014.MetroTransitwillbedevelopingalistofpreferredlocationsforapproximately500parkingspacestomeetpreviouspark-and-ridedemandforecastsandmitigateparkinglostthroughinterchangeconstruction.Thisanalysiswillalsoevaluateothersupportfacilityneedssuchasdriverfacilitiesorbusturnaroundandlayoverneeds,andworkwithpropertyownerstounderstandinterestandviabilityofajointdevelopmentventure.

Thecombinationofthetransitwayandpark-and-ridefacilityareexpectedtoimpact1to3parcelsofprivateproperty,dependingondesign,placement,andpropertyownerinterestinjointdevelopmentorjointuse.

2.4.2 Lake Street Station

Aportionoftherightofwayneededtobuildthe35LakeTransitAccessProject(highwayandtransitcomponents)willbeassumedbytheOrangeLine.Exactparcelacquisitionwillbeidentifiedintheproject’senvironmentalassessment,whichincludestheLakeStreetStationinitsscope.

2.5 Technology

OrangeLineBRTwillbuildonprevioustechnologyinfrastructurealongthecorridor.Technologyhasaffectedallaspectsofapassenger’strip,suchasupdatedinformationabouttheavailabilityofparkingatpark-and-rides,next-busarrivalinformation,estimatedtraveltimes,web-basedtripplanningtools,real-timetransitinformation,andrechargeablefarecards.

Real-time Information

Next-bus arrival information is currently available onmonitors and annunciators on 2nd Avenue andMarquetteAvenuesdowntown,aswellasatthe46thStreetStationandSouthBloomingtonTransitCenter.Visualandaudioreal-timeinformationwillbeaddedatallremainingOrangeLineplatforms.

TransitridersarealsoabletoaccesstheinformationusingNexTriponline,onamobiledevice,orbyphone.

Transit Signal Priority

Transit Signal Priority (TSP) is planned in areas where the Orange Line will intersect general purpose traffic. IncoordinationwiththeCitiesofRichfieldandBloomington,HennepinCounty,andMnDOT,MetroTransitwillpursue

July 2014 Page 33

METRO Orange Line BRT

Project Plan Update

TSP or other transit advantages in the followingareas:

• Variousdowntown locations,dependingonpreferredroutingfromI-35WtoMARQ2;

• Northboundandsouthboundat66thStreetfromtheexitramps;

• Removalofthe“norightonred”restrictionsouthbound at 76th Street from the exitramp;

• Northbound and southbound at AmericanBoulevard;

• Westbound on 82nd Street from the exitrampandwestbound(coordinatedsignals);

• Eastbound on 76th Street between KnoxAvenue and the I-35W entrance ramp(coordinatedsignals);

• Southbound left-turn at 98th Street fromtheexitrampandeastboundsignalon98thStreet;

• Southboundramp-meterdumponentrancerampfrom98thStreettoI-35W;and

• NorthboundatI-35WandBurnsvilleParkway,ifTravelersTrailischosenaspreferredsite.

2.6 Fare Collection

TheOrangeLinewillhaveentirelyoff-boardfarecollection,withfullticketvendingmachinesandfarevalidationateverystationplatform.MarquetteAvenuesouthboundstopswillalsoreceiveoff-boardticketvendingmachines.Noticketvendingmachinesarerequiredatnorthboundstationson2ndAvenue,sincealmostallridersgetoffatthesepoints,withveryfewboardings.

2.7 Branding and Marketing

The Orange Line vehicles,signage, wayfinding, andstation platforms will includethe regional METRO branding.Exterior design and colorscheme will be consistentwith METRO Red, Blue, andGreen Lines, which are easilydistinguishable from local andexpress routes serving thosestations.

Figure 29. METRO Blue Line Ticket Vending Machine

Figure 30. METRO Orange Line Vehicle Branding

July 2014Page 34

METRO Orange Line BRT

Project Plan Update

3 Service Planning

3.1 Garage and Terminals

TheOrangeLineisplannedtooperateoutoftheplannedexpansionatHeywoodGarageat560SixthAvenueNorthinMinneapolis,andwillbeginitstripatthedowntownterminalon1stStreetSouthjustwestof2ndAvenueSouthinMinneapolis.ThesouthernterminusforalltripsistheBurnsvilleTransitStationarea.

3.2 Run Time and Frequency

AnOrangeLinetripisestimatedatabout35to40minutesoneway,70to80minutesroundtrip.Aroutemapandconnectingservice isshowninFigure31.Thefollowingassumptionshavebeenmadeforthispreliminary levelofcorridorserviceplanning:

• 10-minutefrequencyduringpeakhourstoenableeasytransfers;• 15-minutefrequencyinoff-peakhoursandalldayonweekends;• Farecollectionwillbedoneentirelyoff-boardwithrovingfareinspectiontominimizedwelltimesatstations;• Riderscanboardatanyofthreedoors;and• Sixty-foot,articulatedbuseswillbeusedtomaximizepassengercapacity.

3.3 Service Structure

AllOrange Line tripswill runbetween2ndAvenue and2nd Street inMinneapolis andBurnsville Transit Station,stoppingateverystation.Therewillbeno“shortline”routes,deviations,orbranches.

Muchoftheconnectingserviceinthecorridoralreadyprovidesfrequent,convenientfeederservicetoplannedOrangeLinestations,however,someservicerestructuringandimprovementswillbeneededinRichfieldandBloomingtontoimprovecrosstownrouting.TheserecommendedchangesreplacebranchesofthecurrentRoute535,aswellasmakingoperationsmoreefficient.AllnewcrosstownserviceproposediswithinthesamebudgetsavedbyreplacingRoute535operations.DetailedmapsoftheseproposedroutechangesareshowninAppendixB.

3.4 Fleet

TheOrange Line is expected to requirenine sixty-foot articulatedBRTbuses at peaktimes. Elevenbuseswill bepurchasedtoprovidetwosparesforthisuniquesubfleet.

3.5 Ridership

Basedonpreliminaryridershipforecastingcompletedin2011,andupdatedwith2012serviceandfacilitiesplanning,theestimated2030dailyridershipforMetroOrangeLineis10,100.The2030dailyridershipforallotherremainingI-35Wexpressroutesisapproximately10,500riders,foratotalof20,600dailytransitridersthatbenefitingfromBRTguidewayandstationimprovements.

Toreflectrecentserviceplanningandnew2040localforecasts,MetroTransitwillpreparenewridershipforecastsin2014,withtheintentiontousethisforecastingaspartofaSmallStartsevaluation.

July 2014 Page 35

METRO Orange Line BRT

Project Plan Update

DowntownMinneapolis

METROORANGE

Minneapolis

I-35

W

Hw

y 65

Rts. 21, 53

ROUTE

Hwy 62

I-494

I-35

W

DOWNTOWN ZONE

Washington

46th St

66th St

N

NORTH

P Park and Ride

Downtown Zone

Time Point

Point of Interest

Non-stop Route

Local Service

Fares: Off-Peak/Peak

T Timed Transfer

Bus only shoulder

Ramp meter bypass

Designated Stop

Franklin

EFFECTIVE: 09/2019?

I-35W BUS RAPID TRANSIT

I-35

W

82nd St

W 98th St

Bloomington

Richfield

2nd

A

ve S

1st St S2nd St S

11th St S

12th St S3r

d A

ve S

7th St S

Fra

nce

Ave

South Bloomington Transit Center

T

Lake St

P

Rts. 4, 538, 541, 542, METRO Orange

Rts. 18, 465, 541, 549 554, 597, METRO Orange Line

BloomingtonIndustrial Area

JD 02/18/14

American Blvd

$1.75/$2.25

I-35W & Lake St

Chi

cago

Ave

I-35

W

Hwy 13

Nic

olle

t Ave

Burnsville

Burnsville Transit StationP

Rts. 421, 426, 444, 460, 465-U,METRO Orange

Mar

quet

te

Av

eAll Orange Line trips stop at: Lake St., 46th St., 66th St., 76th St.,American Blvd., 98th St. andBurnsville Stationin both directions.

Draft Map, For Discussion Only

T

NormandaleCollege

P

P

I-35W & 66th St

Knox & American Blvd

Rts. 515, 558, METRO Orange

I-35W & 46th St

Rts. 11, 46, 146,METRO Orange,465?, 490?, 684?

578, 597

PP

I-35W & 66th St.

I-35W & Lake St.,I-35W & 46th St.

E 98th St

Minnesota River

Marquette / 2nd Ave S Bus Stops:

Marquette Ave: Group D:NS of 4th, 6th, 8th, 10th 2nd Ave: Group G:FS of 11th, 9th, 7th, 5th

8th St S

4th St S

Old Shakopee

Rd

Rt. 549Rt. 549

Rt. 549Norm

Vill.

Pen

n A

ve

Best Buy, Inc

Southtown Mall

Southdale

Lynd

ale

Ave

Rt. 515

Rt. 540

Rt. 542

American Blvd

77th St76th St

Rt. 46

Rt.

4

Rt.

4

(Replaces Rt 535 - American Blvd. & Knox Ave. Version,

New Connecting Routes)

METRO Orange Line stops at new On-Line Stations in the Median of I-35Wassumed to be inplace at both locations.

All I-35W Routes Stop Here

except 133, 135

METRO Orange Lineserves stops on ramps to/from I-35W at 66th St.

Kno

x A

ve

Rts. 540, METRO Orange

Knox & 76th St

NorthboundSouthbound

American BlvdRt. 542

Kno

x A

ve

82nd St

76th St

I-35

W

Blo

omin

gton

F

reew

ay R

d Dup

ont A

ve

S. Bloomington TCI-35W &98th St.

NorthboundSouthbound

To Burnsville

P

To Minneapolis

99th St

Lynd

ale

Ave

To

No

rma

nd

ale

C

oll

eg

e

Ald

rich

Ave

98th StRt. 539

New TransitAdvantageHere

I-35

WMETRO Orange Line stops at new stations onKnox Ave (extended)at 76th St. and atAmerican Blvd.

To Burnsville

To Minneapolis

I-35

W

I-494

P

P

Rt. 540

Southtown

Best Buy, Inc

Rts. 4, 538, 539, 542

Knox AvDetail

The shorterdowntown loop shown is possibleif layover can beswaped with Rt. 675- saves 1 minute.

904

Pen

n A

ve

New Transit Advantage:Bus - only Shoulder Lanes in bothdirections are recommended here

Lynd

ale

Lynd

ale

Pen

n A

veR

t. 5

41

Rt.

54

1

90th St

Figure 31. METRO Orange Line Concept Route Map and Connecting Service

July 2014Page 36

METRO Orange Line BRT

Project Plan Update

Rt. 904

‐Orange Line

‐Propo

sed ‐ V

ia Kno

x Av

e.DR

AFT 1

NODE ‐ N

ODE MILES, R

UNNING TIM

ESNORT

HBO

UND

AM PEA

KAv

erage

MIDDAY

Average

PM PEA

KAv

erage

NIGHT

Average

NODE

TONODE

VIA

MILES

RUN TIM

ESpeed

RUN TIM

ESpeed

RUN TIM

ESpeed

RUN TIM

ESpeed

BTS

*SBTC

Nicollet A

ve, H

wy 13

, I‐35W

 No., 98th St. Exit

4.24

736

.37

36.3

736

.37

36.3

SBTC

KNAM

I‐35W

 North, 82n

d St. Exit, 82

nd, Kno

x Av

e2.65

531

.84

39.8

531

.84

39.8

KNAM

KN76

Knox Ave.

0.42

125

.21

25.2

125

.21

25.2

KN76

66ST

76th St., I‐35

W North, 66th St. Exit

1.54

330

.83

30.8

330

.83

30.8

66ST

46ST

I‐35W

 North, I‐35W

 HOT Lane

,  Bu

s Lane 

3.36

540

.35

40.3

540

.34

50.4

46ST

I3LA

I‐35W

 North, I‐35W

 HOT Lane

,  Bu

s Lane 

2.00

340

.03

40.0

340

.03

40.0

LAKE

 ST

2A11

I‐35W

 North, 11th St.

1.80

521

.64

27.0

521

.64

27.0

2A11

7S2A

2nd Av

e S 

0.31

29.3

29.3

29.3

29.3

7S2A

*2S2S

2nd Av

e S., 2nd

 St.

0.54

48.1

310

.84

8.1

310

.8

Layover P

oints *

TOTA

L Ro

ute =

16.86

3528

.932

31.6

3528

.931

32.6

NODE NAM

ES:

Runn

ing tim

es assum

e Transit Signal Prio

rity for b

uses and

 proof of

paym

ent (PO

P) off‐vehicle fare collection.

BTS

Burnsville Transit Statio

n (Nicollet A

ve north of H

wy. 13)

SBTC

South Bloo

mington

 Transit Ce

nter (I‐35W

 North Exit a

t 98th St.)

KNAM

Knox Ave.at A

merican

 Blvd.

KN76

Knox Ave. at 7

6th St.

66ST

I‐35W

 at 6

6th St. (On Exit Ra

mp.)

46ST

I‐35W

 at 4

6th St. (On Bu

s Lane off  High

 Occup

ancy Toll or H

OT Lane

.)LAKE

  ST

I‐35W

 at Lake St. (On Bu

s Lane off  High

 Occup

ancy Toll or H

OT Lane

.)2A

112n

d Av

e S.  at 1

1th ‐ 1

0thSt.

7S2A

2nd Av

e S Bu

s Lane at 7th St. S.

2S2S

2nd Av

e S  at 2

nd St S

. (Do

wntow

n Term

inal)

Last Upd

ated

:10

/3/13

John

 Dillery

Scen

ario w/all trips o

perate M

inne

apolis ‐ B

urnsville

Figu

re 3

2. M

ETRO

Ora

nge

Line

Esti

mat

ed N

orth

boun

d R

un T

imes

July 2014 Page 37

METRO Orange Line BRT

Project Plan Update

Rt. 904

‐Orange Line

 ‐Propo

sed ‐ V

ia Kno

x Av

e.DR

AFT 1

NODE ‐ N

ODE MILES, ESTIM

ATED

 RUNNING TIM

ESSO

UTH

BOUND

AM PEA

KAv

erage

MIDDAY

Average

PM PEA

KAv

erage

NIGHT

Average

NODE

TONODE

VIA

MILES

RUN TIM

ESpeed

RUN TIM

ESpeed

RUN TIM

ESpeed

RUN TIM

ESpeed

2ST

*MAR

Q2n

d Av

e S, 1st St.,

0.51

310

.23

10.2

47.7

310

.22A

VS4ST

Marqu

ette Ave.

MAR

QMAR

QMarqu

ette Ave.

0.32

29.6

29.6

29.6

29.6

4ST

8ST

MAR

Q12

STMarqu

ette Ave, 12th St.

0.48

47.2

39.6

47.2

39.6

8ST

3AVS

123A

LAKE

 ST

12th St., I‐35

W Sou

th1.65

333

.03

33.0

333

.03

33.0

LAKE

 ST

46ST

I‐35W

 Sou

th, I‐35W

 HOT Lane

,  Bu

s Lane 

2.00

340

.03

40.0

340

.03

40.0

46ST

66ST

I‐35W

 Sou

th, 66th St. Exit. 

3.38

540

.65

40.6

540

.64

50.7

66ST

KN76

I‐35W

 Sou

th, 76th St. Exit, 76

th St., Kno

x Av

e. 

1.37

327

.43

27.4

327

.43

27.4

KN76

KNAM

Knox Ave.

0.42

125

.21

25.2

125

.21

25.2

KNAM

SBTC

Knox Ave., 82

nd St., I‐35

W Sou

th,  

2.83

628

.36

28.3

724

.36

28.3

98th St. Exit, 98th St., , A

ldrich Av

e., T Cen

ter

SBTC

*BT

S99

th St., Bloom

ington

 Freew

ay Rd., 98th St., 

4.71

1028

.310

28.3

1028

.310

28.3

I‐35W

 So, Hwy. 13, Nicollet A

ve. 

Layover P

oints *

TOTA

L Ro

ute =

17.67

4026

.539

27.2

4225

.238

27.9

NODE NAM

ES:

Runn

ing tim

es assum

e Transit Signal Prio

rity for b

uses and

 proof of

2S2S

2nd Av

e S at 2nd

 St S

. (Do

wntow

n Term

inal)

paym

ent (PO

P) off‐vehicle fare collection.

MA8

SMarqu

ette Ave. &

 8th St. S

Note: con

necting bu

s service between SBTC

 and

 Normandale College is 

123A

12th St. & 3rd Ave S.

assumed

 to be as freq

uent as R

oute 535

 (in 20

13) for very conven

ient se

rvice. 

LAKE

 ST

I‐35W

 & Lake St. (On Bu

s Lane off  the med

ian of I‐35

W.)

Normandale College has often

 gen

erated

 20%

 of total ride

s on Ro

ute 53

5. 

46ST

I‐35W

 & 46th St. (On Bu

s Lane off  High

 Occup

ancy Toll or H

OT Lane

.)66

STI‐3

5W & 66th St. (On Exit Ra

mp.)

KN76

Knox Ave. at 7

6th St.

KNAM

Knox Ave.at A

merican

 Blvd.

SBTC

South Bloo

mington

 Transit Ce

nter (I‐35W

 & 98th St.)

BTS

Burnsville Transit Statio

n (Nicollet A

ve north of H

wy. 13)

Last Upd

ated

:10

/3/13

John

 Dillery

Scen

ario w/all trips o

perate M

inne

apolis ‐ B

urnsville

Figu

re 3

3. M

ETRO

Ora

nge

Line

Esti

mat

ed S

outh

boun

d Ru

n Ti

mes

July 2014Page 38

METRO Orange Line BRT

Project Plan Update

4 Budget and Funding

4.1 Capital and Operating Costs

CapitalcostsareshowninFigure36,andarecalculatedfortheanticipatedmid-yearofconstructionactivities,2017.Estimatedoperatingcostsareshownbelowinyear-of-expendituredollars.

4.2 Funding Distribution

Thefollowingsourcesareanticipatedforcapitalprojectfunding.

• 50%FederalSmallStartsorotherfederalprograms;• 30%Localtransitsalestax,distributedthroughtheCountiesTransitImprovementBoard;• 10%StateorMetropolitanCouncil;and• 10%localfunding,withsourcesanddistributiontobedetermined.

OperatingfundsareexpectedtoincludeamixofMetropolitanCouncil(viatheMotorVehicleSalesTax),CountiesTransitImprovementBoard(viathelocaltransitsalestax),andfareboxrevenues.

Figure 34. METRO Orange Line Estimated Operating Costs

2019 2020 2021 2022 2023

Metropolitan Council $2,267,856 $2,250,921 $2,257,566 $2,262,396 $2,265,291

Farebox Revenues $2,053,398 $2,242,673 $2,441,835 $2,651,318 $2,871,577

Counties Transit Improvement Board $2,267,856 $2,250,921 $2,257,566 $2,262,396 $2,265,291

$6,589,110 $6,744,514 $6,956,967 $7,176,111 $7,402,158

Total Orange Line Operating Costs

Total Orange Line Operating Revenues

Proposed Orange Line Funding Distribution

Cost by SourcePre 2014

Expenditures2014 2015 2016 2017 2018 2019

Federal 5309 New Starts $67,713,700 $14,852,865 $34,462,400 $18,398,435

Federal CMAQ $7,000,000 $7,000,000

State $14,673,400 $7,000,000 $3,836,700 $3,836,700

Metropolitan Council $652,293 $352,293 $300,000

CTIB $45,100,000 $10,500,000 $8,800,000 $8,800,000 $8,500,000 $8,500,000

Local (Source To Be Determined) $15,558,300 $3,008,300 $3,850,000 $4,850,000 $3,850,000

Total Orange Line Project Capital Cost $150,697,693 $352,293 $300,000 $17,500,000 $15,645,000 $38,339,565 $47,812,400 $30,748,435

0.2% 0.2% 11.6% 10.4% 25.4% 31.7% 20.4%Percent of Funding by Year

Figure 35. METRO Orange Line Proposed Funding Distribution

July 2014 Page 39

METRO Orange Line BRT

Project Plan Update

10 GUIDEWAY & TRACK ELEMENTS (route miles)

10.01 Guideway: At‐grade exclusive right‐of‐way

10.04 Guideway: Aerial structure

10.08 Guideway: Retained cut or fill

TOTAL COST BY STANDARD COST CATEGORY 10

20 STATIONS, STOPS, TERMINALS, INTERMODAL (number)

20.01 At‐grade station, stop, shelter, mall, terminal, platform

20.02 Aerial station, stop, shelter, mall, terminal, platform

20.06 Automobile parking multi‐story structure

20.07 Elevators, escalators

TOTAL COST BY STANDARD COST CATEGORY 20

30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS

30.04 Storage or Maintenance of Way Building

TOTAL COST BY STANDARD COST CATEGORY 30

40 SITEWORK & SPECIAL CONDITIONS

40.01 Demolition, Clearing, Earthwork

40.02 Site Utilities, Utility Relocation

40.03 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments

40.04 Environmental mitigation, e.g. wetlands, historic/archeologic, parks

40.05 Site structures including retaining walls, sound walls

40.06 Pedestrian / bike access and accommodation, landscaping

40.07 Automobile, bus, van accessways including roads, parking lots

40.08 Temporary Facilities and other indirect costs during construction

TOTAL COST BY STANDARD COST CATEGORY 40

50  SYSTEMS

50.02 Traffic signals and crossing protection

50.05 Communications

50.06 Fare collection system and equipment

50.07 Central Control

TOTAL COST BY STANDARD COST CATEGORY 50

60 ROW, LAND, EXISTING IMPROVEMENTS

60.01 Purchase or lease of real estate  

TOTAL COST BY STANDARD COST CATEGORY 60

70 VEHICLES (number)

70.04 Bus

TOTAL COST BY STANDARD COST CATEGORY 70

80 PROFESSIONAL SERVICES (applies to Cats. 10‐50)

80.01 Preliminary Engineering

80.02 Final Design

80.03 Project Management for Design and Construction

80.04 Construction Administration & Management 

80.05 Professional Liability and other Non‐Construction Insurance 

80.06 Legal; Permits; Review Fees by other agencies, cities, etc.

80.07 Surveys, Testing, Investigation, Inspection

80.08 Start up

TOTAL COST BY STANDARD COST CATEGORY 80

Subtotal (60 ‐ 80)

Subtotal (10 ‐ 80)

90 UNALLOCATED CONTINGENCY

Subtotal (10 ‐ 90)

100  FINANCE CHARGES

Total Project Cost (10 ‐ 100)

Transit station bridge over Lake Street, managed lane flyover out from Downtown Minneapolis, Interstate bridges over Knox Avenue guideway $23,520,000

Standard Cost Categories DescriptionTotal Cost Estimate for Orange Line Project

Knox Ave guideway between American and 76th, bus‐only exit ramp into Downtown Minneapolis, Lake St pavement

$6,170,000

Lake Street grade‐separated station $13,700,000

$40,460,000

66th St, 98th St, American Blvd, and 76th St stations, and gate expansion at Burnsville Transit Station

$8,420,000

Retaining walls $10,770,000

Heywood Garage expansion for BRT fleet $3,760,000

$29,120,000

American Blvd park and ride facility $7,000,000

inc.

66th and 98th Street stations $400,000Major utility relocation at Lake Street and under the Knox Avenue guideway, minor utilities elsewhere

$7,260,000

Drainge/stormwater management for Lake St and Knox Ave Stations  $11,620,000

$3,760,000

66th and 98th Street stations $280,000

66th and 98th Street stations, traffic management for Knox Avenue $2,860,000

$23,235,300

66th and 98th Street stations $60,0001% of construction budget assumed for enhancements $755,300

TVMs for MARQ2 (6), 46th (2), 66th (2), 98th (2), American (2), 76th (2) $1,320,000

$680,000

$2,190,000

$120,000

$70,000

11 Articulated BRT buses (9 peak buses & 2 spares) $9,840,000

$16,420,000

Construction Subtotal (10 ‐ 50) $98,765,300

ROW acquisition for American Boulevard Park & Ride, Knox Avenue guideway, and  $16,420,000

$2,766,293

$3,219,000

$1,732,000

$9,840,000

$1,870,000

inc.

$15,192,293

$3,230,000

$1,620,000

$755,000

$150,697,593

$150,697,593

$41,452,293

$140,217,593

$10,480,000

Figure 36. METRO Orange Line Estimated Capital Costs

July 2014Page 40

METRO Orange Line BRT

Project Plan Update

5 ScheduleThe project is currently in the pre-project development phase, although some individual stationwork has beenadvancedmorequicklytomeetspecificdeadlinesforMnDOTbridgeandroadwayreconstruction.Forexample,theLakeStreetStationiscurrentlyunder60%designandismovingintofinaldesignin2014.

ThefollowingtimelineisanticipatedforMETROOrangeLineimplementation:

• Pre-ProjectDevelopment:early2014• ApplytotheFederalSmallStartsProgram:mid-2014• ProjectDevelopment:2014-2015• Engineering:2015-2016• Construction:2016-2019• OpenforService:late2019

6 Coordination with Concurrent Projects

6.1 I-35W Lake Transit Access Project

TheI-35WLakeTransitAccessProjectincludesanumberofroadwaydesignchangesbetweenI-94and32ndStreet,aswell as theconstructionofanonlineBRTstationat LakeStreetand streetscape improvements. It isbeing ledbyHennepinCountyinpartnershipwiththeCityofMinneapolis,MetropolitanCouncil,MetroTransit,andMnDOT.Environmental processes and funding between Orange Line and the Transit Access Project are being closelycoordinated,andtheLakeStreetstationwillbebidaspartofthelargerroadwayandbridgecontract.

Arobustpublicengagementprocesshasbeenunderway forseveralyears in thisprojectarea.AProjectAdvisoryCommittee(PAC),comprisedofresidents,businessowners,communityinstitutionsandpolicymakers,meetsmonthly.ThePAChasadvisedpartneragenciesas theLakeStreetBRTStationmoved intofinaldesign in2014.Additionalinformationonthemeetingsandproposedstationdesigncanbefoundattheprojectwebsiteatwww.35lake.com.

6.2 I-494/35W Interchange Vision Layout

TheI-494/35Winterchange,constructedoverfiftyyearsago,supportsmorethan500,000dailyvehiclesandservesasakeyaccesspointforcrossingthemetropolitanarea.Hightrafficvolumesandeconomicgrowthhaveledtolongstandingcongestion,safety,andfloodingissuesattheinterchange.In2013,MnDOTinitiatedanI-494/35WInterchangeVisionLayoutprocesstostudyalternativestoimprovesafety,reducecongestion,allowforfuturedevelopment,andimproveaccesstotransit.ThisworkwascompletedinconjunctionwiththeCitiesofRichfieldandBloomington,MetropolitanCouncil,MetroTransit,MinnesotaValleyTransitAuthority,andtheFederalHighwayAdministration.

Asaresultofthetechnicalstudyandpublicinput,aturbineinterchangeconceptwiththreeloopsandtheOrangeLineKnoxAvenuealignmentandstationshavebeencarriedforwardforadditionaldesign.MetroTransitwillcontinuetoworkcloselywithMnDOTtointegratethedesignandenvironmentalprocessesforofthetransitcomponentsandinterchange.

July 2014 Page 41

METRO Orange Line BRT

Project Plan Update

6.3 County State Aid Highway 53 (66th Street) Reconstruction

HennepinCountyisworkingwiththeCityofRichfieldtodevelopapreliminarydesignplanforthereconstructionof66thStreettoimprovesafetyforpedestrians,bicyclistsandvehicles,andtoimprovetheconditionofthepavement.Theprojectwillreplacethedeterioratingroadwayandsidewalks.TheprojectextendsfromXerxesAvenueto16thAvenueSouth,andincludestheplanned66thStreetOrangeLineStationatI-35W.

TheRichfieldTransportationCommission,withsignificant involvementfrommembersoftheCityCouncil,variousotheradvisoryCommissions,theRichfieldChamberofCommerce,andHennepinCountyandCityStaff,conductedmultiplevisioningsessionsandpublicopenhousesfortheprojectin2013and2014.Planswillbepreparedin2014and2015,leadingtostreetconstructionbetween2016and2018.

July 2014Page 42

METRO Orange Line BRT

Project Plan Update

7 Environmental Process TheI-35Wcorridorhasalonghistoryofintegratedtransitinvestment,andtheOrangeLineplanningreflectsadditionalopportunitiestoimplementtransitimprovementsincoordinationwithupcomingroadwayandbridgeprojects.

Environmental impacts andbenefits related to Lake Street Station infrastructure arebeing consideredunder thelargerscopeofthe35LakeTransitAccessProject,whichincludesroadway,transit,andbridgeimprovementsalongI-35Wfrom46thStreettoI-94.TheFederalHighwayAdministration(FHWA),incooperationwithMnDOT,ispreparingan Environmental Assessment (EA) for the 35 Lake project, and FHWA has requested that the Federal TransitAdministration(FTA)becomeaCooperatingAgency.TheserviceimpactsandbenefitsoftheLakeStreetStationwillbeconsideredunderthescopeoftheOrangeLineenvironmentalprocess.

Similarly,designfortheI-494/35WInterchangehasbeencloselycoordinatedwithBRTplanning.Originally,amedianstationwasenvisionedatAmericanBoulevard,anditwasexpectedthatthisstationwouldfollowaparallelprocesstotheEAapproachatLakeStreet.However,asstationplanningprogressedin2013,thepreferredconfigurationevolvedfrom onemedian freeway station to two at-grade neighborhood stations,with the capital-intensive investmentsshiftingfromthecenterofI-35WtoKnoxAvenueandtheproposedunderpassatI-494.Duetothepreferreddesignand thecurrent lackof funding tobeginenvironmentalworkon the interchange, the infrastructureof these twostationsandtheKnoxAvenueguidewayshouldbe includedunderthescopeoftheOrangeLinedocumentratherthan coordinated throughan interchangedocument.Designand constructionphasingwill continue tobe closelycoordinatedwithMnDOTandFHWA.

Uponadoption,thisProjectPlanUpdatewillprovidethebasisforMetroTransittotransmitaformalprojectdescriptiontoFTA.FTAwillreviewtheprojectscope,previousplanning,publicengagementanddecision-makingprocessestodate,andpotentialenvironmental impacts,andproposeaNationalEnvironmentalProtectionAct (NEPA)ClassofActionforenvironmentaldocumentation.

8 Agency PartnersMetroTransitisthetransitauthorityandaserviceoftheMetropolitanCouncil,theTwinCities’metropolitanplanningorganization.MetroTransit is theproject leadforplanning,projectdevelopment,engineering,anddesign.MetroTransitwillalsobetheoperatoroftheline.MetroTransitandMetropolitanCouncilownandoperatetheexistingdowntownstations,46thStreetStation,SouthBloomingtonTransitCenterandHeywoodGarage.

MinnesotaDepartmentofTransportation(MnDOT)iscloselyinvolvedintheengineeringandconstructionofhighwayBRTinthecorridor,aswellasaprojectleadforboththe35LakeTransitAccessProjectandI-494/35WInterchangeVisionLayout.MnDOTownsandoperatesI-35WandStateHighway13,aswellasandassociatedramps,signals,andrightofway.

MinnesotaValleyTransitAuthority (MVTA) is thepublic transportationagency forAppleValley,Burnsville,Eagan,Rosemount,andSavage.MVTAalsoownsandoperatesBurnsvilleTransitStation,aswellasoperatingserviceonmanyI-35Wexpressroutes.

HennepinCountyisthecurrentleadfor60%designoftheLakeStreetTransitStation,and85%oftheOrangeLinealignmentrunsthroughHennepinCounty.LakeStreet,98thStreet,and66thStreetareallHennepinCountyRoads.HennepinCountyRegionalRailAuthoritywasestablishedasaseparatepoliticalentitytoplan,designandimplementlightrailtransitinHennepinCounty,buthasbeenheavilyinvolvedintheplanningofbusrapidtransitaswell.

July 2014 Page 43

METRO Orange Line BRT

Project Plan Update

Dakota County contains 15%of theOrange Line alignment. TheDakota County Regional RailroadAuthoritywasformedtoplan,acquire,constructandoperaterailroads,includinglightrailtransit.InadditiontoLRT,theRegionalRailroadAuthorityoverseesthecontinuingdevelopmentandimplementationofMETRORedLinebusrapidtransitintheCedarAvenueCorridor.

TheCitiesofMinneapolis,Richfield,Bloomington,Burnsvillearecriticalpartnersinstationdesign,serviceplanning,andlanduseplanning.TheyalsoownandmaintainthefollowinglocalstreetsegmentsthatarepartoftheOrangeLinealignment:Marquetteand2ndAvenue(Minneapolis),76thStreetandKnoxAvenue(Richfield),KnoxAvenue,82ndStreet,AldrichAvenue,99thStreet,andBloomingtonFerryRoad(Bloomington),andNicolletAvenue(Burnsville).

TheCountiesTransit ImprovementBoard (CTIB) is comprisedoffivecounties:Anoka,Dakota,Hennepin,RamseyandWashington.Theboardhasutilizedaquarter-cent sales taxandamotorvehicle sales tax,permittedby theLegislature, to invest inandadvancetransitprojectsbyawardingannualcapitalandoperatinggrants.TheBoardworksincollaborationwiththeMetropolitanCouncilandCarverandScottcounties.

AllpartnersparticipateinthetechnicaladvisoryandpolicyadvisorycommitteesfortheOrangeLineproject.

1 METRO Orange Line BRT Project Plan AppendicesAppendixA:Stations

Appendix B: Service Planning

METRO Orange Line BRT Project Plan Update

APPENDIX A

July 2014

Evaluation Criteria for 66th Street Platform Options

Transit Station Criteria

• ConstructionCost–Comparativecostofroadwaycomponents,anyTSP,andtransitstations.• Traveltime—Minimizetraveltimeforbusestravelingstationtostation,andthelengthoftheroute.• NeighborhoodCompatibility–Thetransitstationfootprintfitwithinexistingnoisewalls.• ProximitytoLocalStreets–Minimizedistancetocrossstreetsandconnectingbusservice.• Visibility–Visibletotransitandautomobileusersfrom66thStreet.

Bus Operations Criteria

• BusTravelTime–Mustbereliable,stayonschedule,andmeetriderexpectations.• Maintenance–Designminimizesspecializedmaintenanceatthestation,andsimplifiesfrequent,year-round

maintenance.

Transit User Criteria

• Transfertime–Amountoftimetocompleteatransferfromalocalbustostationplatform,andviceversa.• PersonalSafety–Potentialconflictpoints/crossingsforpedestriansandvehicles,visibilityintoandoutofthe

station,minimizingisolation,andpreventingobscuredsightlines.• Legibility–Stationsarelegibletothosethatarenewtotransit.• Triptime–Minimizetraveltimeimpactsonexistingtransitriders.

Evaluation Criteria for American Boulevard Platform Options

Transit Station Criteria

• FreewayTrafficOperations and Speed– Impacton freewayoperations, and the ability of buses to reachmainlinespeeds.

• ConstructionCost–Comparativecostofroadwaycomponentsandtransitstation.• CompetitiveforFunding–Designpositionstheprojectstocompeteforavailablefundingfromavarietyof

sources,includingfederaltransitdollars.• Traveltime—Minimizetraveltimeforbusestravelingstationtostation,andthelengthoftheroute.• RoadwayCompatibility—Thetransitstationlocationandfootprintarecompatiblewithfutureinterchange

conceptsandphasing.• ProximitytoLocalStreets–Minimizedistancetocrossstreetsandconnectingbusservice.• LandUse—LocationisconsistentwiththeCity’slanduseplan/developmentplans,andisproximatetoland

withredevelopmentpotential.• Expandability–Abilitytoexpand/relocatethetransitfacilitytoaccommodatefuturetransitgrowth.• Right-of-Way Required – Estimated impact/magnitude of additional right-of-way required for facility, and

July 2014

METRO Orange Line BRT Project Plan Update

APPENDIX A

costsassociated.• Access–Improvestransitaccessfortransit-dependentpeople.• AffordableHousing–Improvesaccesstoaffordablehousing.• Visibility–Visibletotransitandautomobileusers,fromlocalstreetsandthehighway.• Developmentpotential—Minimizeimpactondevelopment,andmaximizedevelopmentpotential.

Bus Operations Criteria

• BusTravelTime–Mustbereliable,stayonschedule,andmeetriderexpectations.• Bus Transfer Complexity – The number of potential conflict points and delays between different service

providersusingthetransitstation.• SpecialOperations–Theexistenceofspecialmaneuversortrafficoperations.• CoordinationwithOtherTransitProviders–Astationplatformthatcanbeaccessedandusedbyothertransit

services(e.g.MVTA).• Maintenance–Designminimizesspecializedmaintenanceatthestation,andsimplifiesfrequent,year-round

maintenance.• RouteStructure—Optimizebusroutestructurestoavoidloopsandreducetransfers.

Transit Rider User Criteria

• ProximitytoDestinations–Locationofthetransitstationmustbeinproximitytoriders’actualoriginsanddestinationswithinthisarea(housing,shopping,andemployment).

• Transfertime–Amountoftimetocompleteatransferfromalocalbusfromabusstoptostationplatform.• PersonalSafety–Potentialconflictpoints/crossingsforpedestriansandvehicles,visibilityintoandoutofthe

station,minimizingisolation,andpreventingobscuredsightlines.• Legibility–Stationsarelegibletothosethatarenewtotransit.• Amenities–Abilitytoprovidestationenhancements,likepedestrianamenities,bicycleparking,landscaping,

andpublicart.• Triptime–Minimizeimpactsonexistingtransitriders.

Evaluation Criteria for 98th Street Platform Options

Transit Station Criteria

• FreewayTrafficOperationsandSpeed–Impactonfreewayoperationsandtheabilityofbusesmergeintoandoutofguideway.

• ConstructionCost–Comparativecostofroadwaycomponentsandtransitstation.• Traveltime—Minimizetraveltimeforbusestravelingstationtostation,andthelengthoftheroute.• Roadway Compatibility– The transit station location and footprint are compatiblewith existing roadway,

METRO Orange Line BRT Project Plan Update

APPENDIX A

July 2014

turningmovements,andtrafficflow.• ProximitytoLocalStreets–Minimizedistancetocrossstreetsandconnectingbusservice.• Expandability–Abilitytoexpandorrelocatethetransitfacilitytoaccommodatefuturetransitgrowth.• PropertyImpacts–Additionalright-of-wayrequiredforfacility,andcostsassociated.• Visibility–Visibletotransitandautomobileusers,fromlocalstreetsandthehighway.

Bus Operations Criteria

• BusTravelTime–Mustbereliable,stayonschedule,andmeetriderexpectations.• Bus Transfer Complexity – The number of potential conflict points and delays between different service

providersusingthetransitstation• SpecialOperations–Theexistenceofspecialmaneuversortrafficoperations.• CoordinationwithOtherTransitProviders–Astationplatformthatcanbeaccessedandusedbyothertransit

servicesifdesired(e.g.MVTA).• Maintenance–Designminimizesspecializedmaintenanceatthestation,andsimplifiesfrequent,year-round

maintenance.• RouteStructure—Optimizebusroutestructurestoavoidloopsandreducetransfers.

Transit User Criteria

• Transfertime–Amountoftimetocompleteatransferfromalocalbustostationplatform,andviceversa.• PersonalSafety–Potentialconflictpoints/crossingsforpedestriansandvehicles,visibilityintoandoutofthe

station,minimizingisolation,andpreventingobscuredsightlines.• Legibility–Stationsarelegibletothosethatarenewtotransit.

• Triptime–Minimizetraveltimeimpactsonexistingtransitriders.

Evaluation of Three Options for American Boulevard Area

Service Impacts Analysis

DATE: March19,2014 TO: I-494/35WVisionLayoutTAC FROM: KateChristopherson&ChristinaMorrison,BRT/SmallStartsProjectOffice SUBJECT: ServiceImpactsAnalysisofAmericanBoulevardStationAlternatives

Background

ThreelocationswereevaluatedforMETROOrangeLine’sAmericanBoulevardStation.ThefirstalternativeisanonlinestationonI-35WbelowtheAmericanBoulevardbridge.Thesecondalternativeisanonlinestationat81stStreet.Thethirdalternativewouldconsistoftwoofflineat-gradestationsatKnoxAvenueandAmericanBoulevard,andatKnoxAvenueand76thStreet.Becausethesecondalternativeisnotbeingrecommendedforfurtherstudy,onlythefirstandthirdalternativesaredetailedinthisServiceImpactsAnalysis.

July 2014

METRO Orange Line BRT Project Plan Update

APPENDIX A

Figure 1. American Boulevard Station Location and Alignment Alternatives

Service

TheOrangeLineisexpectedtoreplacethelimited-stopRoute535,operatingat15-minutefrequencyall-day,andprovidingroughly130tripsperdayinthisarea.SometripsonI-35Wexpressroutes(e.g.Route467)mayusethestationdependingonstationlocationandfurthertransitmarketanalysis.MetroTransit’slocalandexpressrouteswilllikelyberestructuredtosupportOrangeLineserviceopeninginthisarea.

MVTAdoesnot currently serve this vicinityandexpects tocontinue to runabout150 tripsperday through thisarea(460,464,and465),witharoundone-thirdofthosetripsservinganAmericanBoulevardOrangeLineStation.Numberoftripsservingthisstationcouldchangebasedonexactstationlocation,alignment,traveltime,andfunding.

Speed

ThebiggestserviceadvantageofbuildinganonlinestationatI-35WandAmericanBoulevardisspeed.Thebuswouldnothavepassthroughtrafficsignalsinthisalternative,however,runtimesshouldbefurtherrefinedwithfieldcheckstodeterminethefeasibilityofmergepatternsfromtheshoulderat98thStreet,toanonlinestationatAmerican,andbacktotheshoulderat66thStreet.

BEST BUY

SOUTHTOWN

I-494

I-35W

AMERICAN BLVD

PENN

AVE

LYND

ALE AVE

76TH ST

KNO

X AVEPENN AMERICAN DISTRICT

ORANGE LINE AMERICAN BOULEVARD ALIGNMENT ALTERNATIVES

1: I-35W Alignment3: Knox Avenue Alignment3A: 82nd Street TSP3B: American Boulevard Ramp

METRO Orange Line BRT Project Plan Update

APPENDIX A

July 2014

MovingthestationtoaKnoxAvenuealignmentandaddinga76thStreetstationaddsruntimetotheOrangeLine.TransitSignalPriority(TSP)oradedicatedtransitramptoAmericanBoulevardcanhelpminimizethetimepenalty.

InAlternative3A,thenorthboundbuswouldexitI-35Won82ndStreet,turnlefton82nd,andturnrightonKnoxtostopattheKnox/Americanintersection.KnoxAvenuewouldbeextendedunderI-494inordertoconnecttoRichfield.BRTwouldstopatKnox/76thbeforeturningrightonto76thStreetandexitingbackontoI-35W.Withouttransit-signalpriority (TSP),MetroTransitestimates this routewould take11minutes.Becauseonly threeof thesevensignalswouldbenefitfromTSP,thereisminimalreductionofdelaywithTSP.

InAlternative3B,thenorthboundbususesacenter-runningT-Ramp,exitingdirectlyontoAmericanBoulevardusingatransit-onlysignal.TheOrangeLinewouldthenturnleftonAmericanBoulevardandrightontoKnox,stoppingonthenorthsideoftheintersection.WithorwithoutTSP,thisvariationisestimatedtotakeabout8minutes.AswithAlternative1,feasibilityofmergepatternsshouldbecheckedinthefield.

Table 1. Estimated Run Times (in Minutes), Northbound during peak hour1

Without TSP With TSP No. of Signals

Travel Distance

Average Speed

% faster than Route 535

Route535(existing) 18:00 - 14 5.7mi 19 mph -Alternative1 5:30 - 0 4.1mi 44 mph 72%fasterAlternative3A 11:15 11:00 7 4.7mi 25 mph 38%fasterAlternative3B 8:00 8:00 4 4.6mi 33 mph 56%faster

Pedestrian Access

Althoughthereare4,623residentsand8,118employeeswithinone-halfmileofAlternative1(seeTable2),thereislittlepedestrianinfrastructure.PedestrianscanaccessSouthtownShoppingCenter,GeneseeApartments,SouthtownOfficeCenter,fiveautodealerships,ExtendedStayAmericaHotel,REI,andresidentialhomessouthof82ndStreet(showninblueonFigure2).BestBuyHeadquartersandotherdestinationsnorthofI-494wouldnotbeaccessible.

Alternative3greatly improvespedestrianaccess.Addinga second stationandmoving the stationsoff the I-35Walignmentbringsabout8,172additional residentsand4,990additionalemployeeswithinahalfmilewalkof theOrange Line. In addition to the businesses, institutions, and residences in Alternative 1, Best BuyHeadquarters,MinnesotaSchoolofBusiness,USBank,PennAvenuebusinesses,andresidentialareasinRichfieldareaccessibleinAlternative3(showningreenbelow).

Table 2. Existing Residents and Jobs within Half-Mile of Stations in Alternatives 1 and 32

Alternative 1 Alternative 3Residents 4,623 12,795Jobs 8,118 13,108

1 Assumptions: Existing travel time based on schedule; 20-second dwell time for bus at Orange Line station(s); 10% time savings with TSP, per signal; times rounded to nearest 15 seconds; I-35W east and west ramps (at 76th and 82nd) are coordinated; American Boulevard signal is coordinated east-west. Regional Transitway Guidelines state that BRT should be at least 20% faster than existing service.2 Source: 2011 ACS Five-Year Survey and Longitudinal Employer-Household Dynamics (LEHD)

July 2014

METRO Orange Line BRT Project Plan Update

APPENDIX A

Figure 2. Half-mile walkshed from stations, using existing sidewalks

Anothermeasureofaccessistocalculatethetotalplannedtriptimeforbusriders,combiningOrangeLinetraveltimeandwalktimetotheirdestination.ThisfactorisparticularlyimportantinahighwayBRTcorridor,wheredestinationsarenotlocatedimmediatelyadjacenttothestation.UnderAlternative1,theOrangeLinetriptoAmericanBoulevardisfaster,butwalkdistancestomajordestinationsarelonger.Table3estimatessomeofthesecombinedtriplengths.Alternatives3Aand3BhavedifferenttraveltimesdependingwhichOrangeLinestationisclosertothedestination(AmericanBoulevardor76thStreet).Forexample,atripfrom98thStreetStationtoBestBuywouldtakeabout23½minutesusingAlternative1,or10minuteswithAlternative3A.

Table 3. Net Access to Sample Destinations, in minutes of travel

Transit time Walk time98th St to OL Station

Best Buy Kohl’s MN School of Business

Genesee Apts

GN Resound

HOM

Alternative1 3:30 19:00 10:00 25:00 10:00 17:00 7:00Alternative3A 8:00 – 9:00 1:00 6:00 5:00 6:00 15:00 10:00Alternative3B 3:30 – 5:00 1:00 6:00 5:00 6:00 15:00 10:00

BEST BUY

SOUTHTOWN

I-494

I-35W

AMERICAN BLVD

PENN

AVE LYND

ALE AVE

76TH ST

KNO

X AVE

PENN AMERICAN DISTRICT

BEST BUY

SOUTHTOWN

I-494

I-35W

AMERICAN BLVD

PENN

AVE LYND

ALE AVE

76TH ST

KNO

X AVE

PENN AMERICAN DISTRICT

METRO Orange Line BRT Project Plan Update

APPENDIX A

July 2014

Impacts to Existing Riders

OrangeLine service should improve transit access forexisting riders in the I-494/35Warea,whileattractingnewriders.Table4showsRoute535boardingsatbusstopswithinahalfmileoftheproposedstationlocations.

Table 4. Bus stop boardings on Route 535 within Half-Mile of Stations in Alternatives 1 and 33

Alternative 1 Alternative 3Northbound 26 419Southbound 11 40TOTAL 37 459

Intheareanear76thStreet,KnoxAvenue,andPennAvenueinRichfield,theproposedrelocationofthestationandpark-and-ridetoAmericanBoulevardandI-35Wcouldimpactalargenumberofexistingnorthboundboardings.Ofthese,itcanbeassumedthatabout150boardingsareridersthathavedriventothepark-and-ride,4 and the remaining peoplewalkorbiketothestop,ortransferfromanotherbus.

3 Source: September 2012 Metro Transit data4 Knox Avenue parking utilization information from Metro Transit’s 2012 Annual Regional Park-and-Ride System Report.

July 2014

METRO Orange Line BRT Project Plan Update

APPENDIX B

541Route

Bloomington

NormandaleCollege

W. 98th St

Pen

n A

ve

N

NORTH

Normandale

Village

Nor

man

dale

Blv

d W. 90th St

Pop

lar B

ridge

So

uth

tow

n

Kno

x A

ve

W. 98th St

Normandale Village

Normandale VillageRoute AB Terminal

90th St

Fra

nce

Ave

Rt.

58

9

Rt. 542

84th St.

Rt. 542

American BlvdRts. 4, 538, 541, 542,METRO Orange Line

W. 98th St

Road

Rts

. 4

,5

38

T

B

Pen

n A

ve

P

Fares: Off-Peak/Peak

$1.75/$2.25

T

Park and Ride

Timepoint

Timed Transfer

Bus Stop

Point of Interest

Limited Service

Layover Point

Rt. 549

EFFECTIVE: 2019?

(I-35W Orange Line BRT Plan 2019 - Replaces part of Rt. 535 and 539)

Operated by ?

Rt.

53

7

Nor

man

dale

Blv

d A BA

Concept for Discussion Only

OxboroPlaza

JD 02/14/14

Small Bus -Cycle: 90 min. off-peak, 120 minutes, peak

Frequency proposed Peak/Off Peak:30 min. / 30 min. or 30-60 min.

B

AM

PM

B

AB

W. 94th St

Nes

bitt

Ave

A

A

Rts. 538, 540W 76th St.

American Blvd Station

1.11

1.80

1.611.60

1.02

1.78

1.08

0.00 are node to node miles

So Bloomington TC -- A route = 8.8 35 15.1So Bloomington TC -- B route = 8.7 35 14.9A -- E Route = 10.5 42 15.0B -- E Route = 10.4 42 14.9

College

View

Little Rd

PM

AM

ME

TR

O

Ora

ng

e

Lin

e

Rt.

4

Lynd

ale

Ave

Lynd

ale

Ave

86th St.

Rt. 542American Blvd

Rt. 538

W. 98th St

W. 99th St

102nd St

Nic

olle

t Ave

104th St

Por

tland

2nd

Ave

S

E

DE

E

E

South BloomingtonTransit Center

98th St

Blo

omin

gton

Fre

eway

Rd

99th St

Ald

rich

Ave

I-35

W P

Layover at Gate C

Route E Terminal

Layover nextto city parkon 102nd St

Lynd

ale

Ave

T

Ald

rich

Rt. 549

Rt. 549

Lynd

ale

Ave

TSouth Bloomington Transit CenterP

Rts. 18, 541, 549, 554, 597, MVTA Rt. 465,METRO Orange Line

ME

TR

O

Ora

ng

e

Lin

e

I-35

WI-

35W

1.80

1.78

1.08 1.10

82nd St.

Cub Foods

Toro, Inc

1.45

1.45

1.80 1.80

1.23

2.25

Route Miles Minutes MPH

I-35

W

ToDowntown Minneapolis

P

METRO Orange Line BRT Project Plan Update

APPENDIX B

July 2014

54224th Ave

Nicollet Ave

Portland Ave

12th Ave

I-35W

Penn Ave

France Ave

Hwy 100

Am

eric

an

Blv

d

84th

St

Hwy 77A

mer

ican

Richfield

T

I-49

4

Stanley

82nd

St

Rts. 5, 553

Rt. 552

Rts. 18, 554

Rt.

5

Rt. 541Rt. 4

I-49

4

84th

St

Am

eric

an B

lvd

NNorth

Penn Ave

A

B

AB

Southtown Mall

Lyndale Ave

Rt. 553

Rts. 538, 541

METRO Orange Line

$1.75/$2.25

Route

Rt. 537

Thomas

Target,

Rainbow

Best Buy, Inc

EFFECTIVE: 2019?

(Route with METRO Orange Line

Knox Ave. American Blvd. Station

Update Connecting Routes)

Wells Fargo Plaza

8100 Northland Dr

Knox Ave

Fares: Off-Peak/Peak

Time Point

Point of Interest

Layover Point

Timed TransferT

Pull-Out

Pull-In Route

Bloomington

AB

AB

Rt. 4

Lyndale Ave

1.43

1.00

1.15

1.36

1.97

1.59

1.471.84

1.80

ToDowntownMinneapolis

Concept for Discussion Only

T

Am

eric

an

Blv

d

I-35W

82nd

St

Rts. 4, 538, 541, 542,METRO Orange Line

American Blvd Station

76th

St

AB

NormandaleLakeOffice Park83

rd S

t

84th

St

American Blvd

Normandale Lake

Rts. 588, 589

Am

eric

an B

lvd

Norman Center

Rt.

54

0

Gre

en V

alle

y D

r

A B

Norman Pointe Office Park

Rt.

54

0

Rt. 589

Normandale

Lake

Norman Center Dr

Route A, B Terminal

Am

eric

anB

lvd

Gre

en V

alle

y D

r

56

00

56

01

NO

RM

AN

PO

INTE II

82

00

NO

RM

AN

DA

LE

L

AK

E

84

00

85

00

80

00

83

00

W 8

4th

St.

PM

AM

C D

American Blvd

Normandale

Lake Blvd

83rd

JD 02/18/14

Ma

ll o

f A

me

ric

a24th Ave S

Lind

auLa

Mall of America Terminal

D

rop

off

are

a

L

ayo

ve

r a

rea

Pic

k U

p a

t G

ate

D

Rts.: 5, 54, 415,444, 515,

538, 539, 540, 542,METRO Blue Line,METRO Red Line

Mall of America

D

1.10

1.10

0.00 are node to node miles

Mall of America -- A route = 7.3 29 15.1Mall of America -- B route = 7.7 32 14.4

Route Miles Minutes MPH

Small Bus -Cycle: 90 min. off-peak, 75 minutes, peak

Frequency proposed Peak/Off Peak:15 min. / 30 min. or 30-60 min.

July 2014

METRO Orange Line BRT Project Plan Update

APPENDIX B

549Route

France A

veBloomington

NormandaleCollege

W. 98th St

JeffersonHigh School

ValleyWest

Penn A

ve

CreeksideCommunity

Center

OxboroPlaza

Nicollet A

ve

KennedyHigh

School

Old Sha

kope

e

N

NORTH

Portland A

ve

Old C

edar Ave.Lyndale A

ve

I-35

W

Penelope 35 Apts

Old Shakopee Rd

NormandaleVillage

Norm

andale Blvd

New

ton

Normandale CollegeF

rance Ave

98th StD

riveway

Old

Sha

kope

e

24th Ave S

.

Mall of America

26th Ave S

.

82nd St.Rts.: 5, 54, 415, 444, 515, 538, 540, 542, 549

Metro Blue LineMetro Red Line

Mall of America

E

Mall ofAmerica

24th Ave. S

.

Mall of America - Terminal

Drop off area Layover areaPick up at Gate C

82nd St.26th Ave S

.

10th Ave S

86th St.

Valley West

France A

ve

Old Shakopee Rd

Cub

Foods

Va

lle

y

West

Central

Drivew

ay

P

Rts. 18, 541, 549, 554, 597MVTA Rt. 465,METRO Orange Line

South BloomingtonTransit Center

T

Aldrich

99th St

Rt. 5

52

Rt. 5

53

Rts

. 18

, 55

4

Rt. 5

41

Rt. 5

97

W. 98th StE. 98th St

Bloom

. Fw

y. Rd

Rts

. 465, 5

97

ME

TR

O O

range L

ine

Rt. 597

W. 102nd St

98th St

Bloom

ingtonF

reeway R

d

99th St

Aldrich A

ve

I-35W

South Bloominton Transit Center

P

Eastbound: Gate D

Westbound: Gate D

Lyndale Ave

B

P

Fares: Off-Peak/Peak

$1.75/$2.25

T

Park and Ride

Timepoint

Timed Transfer

Bus Stop

Point of Interest

Layover Point

Rt. 597

(Orane Line BRT -Replaces Route 539 MOA - Normandale Vil.Creekside Eastbound via Penn Ave to 98th St.,New Terminal Letters, new eastbound to MOA)

C

A

Rt. 538

Concept for Discussion Only

JD 02/18/14

B

A

B

France A

veR

t. 53

7

W. 98th St

Normandale Village

Normandale Village

Norm

andaleB

lvd

Rts. 539, 549, 589, 597

Rts. 539 and 549 interline here.

B

B

Lindau La.

Lindau La.

ARt. 541

EFFECTIVE: 2019?

Operated by ?

A

0.00 are node to node miles

So Bloomington TC -- A route = 2.4 8 18.0

So Bloomington TC -- B route = 3.5 12 17.5

Mall of America -- A Route = 7.0 26 16.2

Mall of America -- B Route = 8.1 35 13.9

Mall of Am. via 94th St B Rt. = 9.2 40 13.8

Route Miles Minutes MPH

1.63

1.33

0.50

0.80

W. 94th St

James

Limited Service

1.10

1.18

1.00

2.381.05

2.41

1.91

1.361.16

1.24

1.70

2.26

Route via 94th St:

Westbound AM Peak

Eastbound PM Peak