Upload
shashank1989
View
307
Download
2
Embed Size (px)
Citation preview
OPERATION RESEARCH QUESTION BANK PART-I
1. Formulate the dual of the following LPP:Maximise : z= 2x1 + 3x2
Subject to Constraints:-x1 + 2x2 ≤ 4 x1 + x2 ≤ 6 x1 + 3x2 ≤ 9x1, x2 0
2. From the following two persons zero sum game find the value of the game:
B 8 -3 7 A 6 -4 5 -2 2 -3
3. A project is characterized by activities A and G and the times required and costs for regular programme for each activity are as follows:
EventActivityEvent
Name ofActivity
Time (weeks)Regular
1123245
2344566
ABCDEFG
5234435
Draw a network for the problem using only time for regular programme activities. Trace the critical path and state how long will it take to complete the project. What would be the cost of completing this project in this fashion? 4 . Solve the following LPP by Simplex method: Maximize : Z = 4X1 + 3X2
Subject to :
2X1 + X2 ≤ 72
X1 + 2X2 ≤ 48
X1 0, X2 0
1
5. Solve the following Transportation Problem :
P Destination Q
R Availability (units)
Origins Cost (Rs.)
Requirement (units)A B C D
2 3 5 1 7 3 4 6
4 1 7 2
5 8 7 14
7
9
18
34
6. An automobile dealer wishes to put 4 repairmen to 4 different jobs. The repairers have some different kinds of skills and exhibit different levels of efficiency from one job to another. The dealer had estimated the number of man hours that are required for each job man combination. This is given in the matrix form as follows:
Jobs A B C D 1 5 3 2 8
2 7 9 2 6
3 6 4 5 7
4 5 7 7 8
7. A company manufactures four products X1, X2, X3, X4 each of which requires resources I, II and III. The data available are as per table given below :
Resource
Products Total availability
(units)X1 X2 X3 X4
IIIIII
Contribution Per unit (Rs.)
1 1 1 16 4 2 12 4 9 10
3 4 6 10
129070
2
It is required to find the quantities of each product that would maximize the contribution
8. Solve the game whose payoff matrix is given by
Play B
1 3 1
Play A 0 -4 -3
1 5 -1
9. You are given the following information:
ProjectEvent
ActivitiesTo event
Name of the activity
PrecedingActivities
EstimatedTime
(months)
1112345
2345566
ABCDEFG
---ABC
D,E
912156302932
Construct a network diagram .
10
ActivityPrecedingActivity
Time Estimates (in weeks )
OptimisticMost
LikelyPessimistic
ABCDEFGH
NoneNone
AAA
B,CD
E,F,G
2108107933
4129157.59
3.55
1226102011975
(i) Determine the critical path(ii) If a 30 weeks deadline is imposed, what is the probability that the project will
be finished within the time limit?(iii) If the project manager wants to be 99% sure that the project is completed on
the scheduled date, how many weeks before that date should be start the
3
project work. (Area of normal curve between z = 0.41 is 0.1591 and the value of z which covers 49% of area is 2.33
11. Determine the optimum strategies and the value of game for the payoff matrix:
B
12. Assume that the time estimates for an activity in a PERT network t0, tp and. tm are 4, 12 and 5 weeks respectively. What is the expected time of the activity and is standard deviation? 13. Determine the value of the following game : Player B A1 Player A A2
14. Using the graphical technique, find the optimal mixed strategies for both players A and B and the value of the game for the following competitive situation.
Player B
B1 B2 B3 B4 B5
A1 Player A A2
15. Consider the following project :
ActivityPredecessor
ActivityActivity duration
(days )
ABCDEFG
--AA
B.CB.C
F
1512734281814
(i) Construct the PERT chart (ii) Determine the project Completion Time.
-2 -4
3 8
5 -1 11 -3 13
-3 9 -5 3 1
4
16. Consider the following LP Problem:
Maximize z = 4x1 + 6x2 + 8x3
Subject to constraints - 4x1 + 2x2 + 2x3 20 3x2 + 6x3 45
and x1, x2 0
Solve this problem using the Simplex algorithm.
17. Assign the Typists to the Departments such that the total number of letters typed is maximum represents a situation where a given typist can be assigned to the particular department.
X Y Z A Typist B C 18. Consider the following projects activities :
ActivityPredecessor Activity
ABCDEFG
--AA
B,CB,C
F
Construct the PERT chart for the project.19. For the PERT chart Determine the project completion time
(i) What is the critical path?(ii) What are the critical activities?
D A 28 G 12 B E 5 20 10
5
1
2
5
3
6
4 7
14 C H F 16
20. Solve the game with the following pay-off matrix Player B
B1 B2 B3 B4 B5
A1
Player A A2 A3
A4
21. Consider the transportation problem shown in the tableau below:
To
From Destination
SupplierK L M N
Source
Demand
A
B
C
200
- 6 5 8
15 21 24 7
9 10 12 11
300 100 200
300
200
300
Solve this problem so that the total cost of transporting good from all Sources to destination is minimum.
22. Given the following payoff matrix, find the value of the game and strategies both the players can play. Player B
B1 B2 B3 B4
A2 3 2 4 0 A2 3 4 2 4
A3 4 2 4 0
A4 0 4 0 8
9 10 5 2 11
7 1 -3 3 5
13 6 -1 12 10
8 3 2 -3 4
6
23. Using North west Corner rule and MODI solve the transportation problem with unit transportation costs, availability and demand as given below:
Destinations D1 D2 D3 D4Availability
(in units)
Origin
Demand(in units)
01
02
03
6 2 8 9
12 6 16 12
4 6 18 4
40 50 130 60
80
80
120
280
24. The following table gives data on Normal time, Crash time, Normal cost and Crash cost of a project
ActivityNormalTime
(in weeks)
CrashTime
(in weeks)
NormalCost
(in Rs.)
CrashCost
(in Rs.)
1-22-32-42-53-44-65-6
3354433
2334121
300752001201009060
45075300120190130110
(i) Draw the network and find out the critical path and the normal project duration .
(ii) Find out the total float associated with each activity.(iii) If the indirect costs are Rs. 100 per week, find out the optimum duration by
crashing and the corresponding projects costs.(iv) With the crash durations indicated, what would be the minimum crash
duration possible, ignoring indirect costs?25. Solve the following Transportation problem by taking the initial basic feasible Solution by North West Corner Rule
From To 1 2 3 4 Supply 1
2
3
4
13 14 12 11
12 11 14 13
10 12 15 13
11 13 12 14
120
120
60
80
7
5
Demand
15 14 11 12
160 120 80 40
20
400
26. Obtain the optimal assignment from the following table: I II III IV
A
B
C
D
27. Determine the optimal strategies for both the players and the value of the game from the following payoff matrix. Player A a1 a2 a3 a4
b1
Player B b2
b3
8. The details of a small project are given below: Draw the network
Activity A B C D E F G
Dependence
Duration (in days)
Activity
Dependence
Duration (in days)
- - - B,C A C E
9 4 7 8 7 5 10
H I J K L
E D,F,H E I,J G
8 6 9 10 2
29. The owner of a Machine shop has four machinists available to assign to jobs for the day. Four jobs are offered with an expected profit in rupees for each machinist on each machinist on each job as follows: Jobs A B C D
1 62 78 50 101
Machinists 2 71 84 61 73
3 87 92 111 71
4 48 64 87 77 Determine the assignment of machinists to jobs that will result in a maximum
160 130 175 190
135 120 130 160
140 110 125 170
50 50 80 80
4 4 4 4
3 4 2 4
1 3 9 2
8
Profit.
30. To solve the following transportation problem. Obtain the initial solution by VAM method.
SourceDestination
1 2 3 4 Supply
A
B
C
7 3 8 5
5 2 6 11
3 6 5 2
160
180
100
Demand 40 100 120 180 440
31. A small project consisting of eight activities has the following characteristics :
Activity A B C D E F G H
Preceeding
ActivityTime aEstimates m(in weeks) b
- - A A A B,C D E,F G 2 13 10 8 7 9 3 5 6 4 15 12 9 8 10 4 5 812 23 26 10 9 17 5 5 10
a- most optimistic, m- most likely, b- most pessimistic. Draw PERT, find critical path and project completion time.
32. The following table gives the activities in a Project:
ActivityTime(days)
NormalTime
(Days)
CrashCost(Rs.)
Normal CrashCost(Rs.)
1-21-32-32-43-44-54-65-76-7
202510125105108
17258625353
600200300400300300600500400
720200440700420600900800700
Draw the activity network of the project.(i) Find the total float and free float for each activity.
9
(ii) Using the above information crash the activity step by step until all the paths are critical.
33. Solve the following Transportation Problem:
Plants
P1 P2 P3 P4 P5 P6 Demand
Warehouses W1
W2
W3
W4
W5
5 7 13 10 9 8
8 6 14 13 22 15
12 10 9 11 14 26
5 18 12 14 20 7
6 3 5 4 14 9
300
200
400
600
700
Supply 500 300 600 200 400 200 2,200
34. Find the initial basic feasible solution by Vogel’s approximation method find the cost that allocation.
To
From
Distribution CentreSupply
D1 D2 D3 D4
P1
Plants P2
P3
Demand
2 3 5 1
7 3 4 6
4 1 6 2
5 8 7 15
7
10
18
35. Find the optimum assignment for the following problem.
M/C
A B C D
1
Job 2
3
7 4 8 5
4 6 10 6
9 3 7 2
3 6 9 6
10
4
36. Draw the Network for the following project.
Activity Immediate Predecessor activities
ABCDEFG
StartStartStart
ACA
B,D,E
37. Solve the following transportation problem and obtain optimum solution.
To Availability
X Y Z W
From A B C D
3 3 5 45 1 3 36 4 4 34 1 4 2
15351219
Demand 21 26 17 17
38. Draw the PERT NETWORK for the following case, Identify the critical path. Find the expected project completion time.
ActivityImmediatePrecedence
Requirement
Time Required in Days
OptimisticMost likely
Pessimistic
ABCDEFGHIJKL
-ABADAFG
C,E,HG
L,I,JA
342317101015210
477558701020715
51012139217010251220
11
39. Solve the game given in the table below.
B
40. Four computer programming hobs have to be assigned to four programmers. Time taken by each programmer on each job is shown in the table below. Find an optimum assignment. Programmers
P1 P2 P3 P4 A Job B
C
D 41. Draw the network for the following activities and precedence relationship.
Activity Immediate predecessor activity
ABCDEFGH
---ABB
D,C,EF,G
42. Find the value of the following game:
Player B
Player A 2 1
-1 0
9 3 7 2
4 4 10 5
4 6 9 6
7 4 8 5
12
43. Determine the basic feasible solution and optimum solution for the following transportation problem: Destinations
D1 D2 D3 D4 D5 Supply
P1 12 9 10 9 6 50
P2 3 5 5 7 7 40
P3 5 3 11 9 11 10 P4 8 2 10 11 2 80 40 40 20 60 20 180
44. Draw the network consisting of the following activities. Find the critical path, project duration, variance of the critical path.
Duration (Days)
Activity t0 tm tp
1-21-42-32-53-64-54-75-66-87-8
4351325622
697474111255
28151571161730148
45. Apply North-West corner rule to the following TP To D1 D2 D3 Availability 01 2 3 4 10
From 02 1 2 3 18
03 5 4 3 12
Requirement 15 20 546. Draw an arrow diagram to represent the following project.
ActivityA B C D E F G H I J K
Immediate - A - B,C C G,H D B F G E,I,J
13
Predecessor :
47. Solve the following transportation problem.
To
W1 W2 W3 W4 Capacity
F1 5 7 3 8 300
From F2 4 6 9 5 500
F3 2 6 4 5 200
Requirement 200 300 400 100 1000
48. The following table gives the jobs of a network along with their time estimates.
Duration days
Jobi-j
OptimisticMost likely
Prssimistic
1-21-62-32-43-54-56-75-87-8
326253314
65251169419
1514308171527728
Draw the project network and find the critical path.
49. Use Vogel’s Approximation method to obtain an initial basic feasible solution.
Cost of Transport
D1 D2 D3 D4 Availability
01
02
03
5 8 3 6
4 5 7 4
6 2 4 6
30
50
20
Requirement 30 40 20 10 100
14
50. A project consists of 9 jobs the following precedence relations and estimates of time. Draw a project network.
Job A B C D E F G H I
Predecessor - - A,B A,B B D,E C,F D,E G,H
Time (day) 15 10 10 10 5 5 20 10 15
51. (i) Explain a two person zero-sum game with examples. (ii) What are the different steps in managerial decision making? Explain with an example.
52. A project consists of the following 12 jobs. Draw a project Network and determine the critical path.
Job 1-2 2-3 2-4 3-4 3-5 4-6 5-8 6-7 6-10 7-9 8-9 9-10Duration 2 7 3 3 5 3 5 8 4 4 1 7
53. The following table gives the activities of a construction project and duration (in days )
Activity 1-2 1-3 2-3 2-4 3-4 4-5
Duration 20 25 10 12 6 10
Draw the network diagram and find the critical path. 54. Solve the following transportation problem with unit transportation costs given as
under: Destinations
Origins D1 D2 D3 D4 Supply 01
02
03
40 25 22 33
44 35 30 30
38 38 28 30
100
30
70
Demand 40 20 60 30
55. A project has the following characteristics and time estimates. Optimistic time (a) Most likely time (m), Pessimistic time (b) Construct a PERT network. Find the critical path.
Activity 1-2 2-3 2-4 3-5 4-5 4-6 5-7 6-7 7-8 7-9 8-10 9-10
a 1 1 1 3 2 3 4 6 2 4 1 3
b 5 3 5 5 4 7 6 8 6 8 3 7
15
m 1.5 2 3 4 3 5 5 7 4 6 2 5
56. The following table gives the activities of a project and their duration in days.
Activity 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8Duration 7 6 14 5 11 7 11 4 18
57. Solve the following transportation problem, with given cost coefficients: Destination
D1 D2 D3 D4 Availabilities
01
Origins 02
03
15 10 17 18
16 13 12 13
12 17 20 11
20
60
70 Requirements 30 30 40 50
58. (i) Explain the use of probability in Decision theory. (i) Explain, with suitable illustrative examples, decision making under uncertainty
59. The following table gives the activities of construction project and duration.Activity 1-2 1-3 1-4 2-4 2-5 3-4 4-5
Duration (days) 3 2 6 5 7 2 4 60. Solve the following transportation problem, with the following costs of transportation, demand and supply : Destination
D1 D2 D3 D4 D5 Supply
01
02
03
10 15 20 20 40
20 40 15 30 30
30 35 40 55 25
50
100
150Demand 25 115 60 30 70
61. A network diagram with PERT time estimates, is given below. Find the critical path and also determine the project completion time and is variance . 6-12-30 5-11-17
2-5-8 3-6-15 1-4-7
3-6-15 2-5-14 4-19 -28
16
1
2
6
3
4
5
7
8
3-9-27
62. Discuss the solution of the following game, with pay-off for player A
Player B
Player A
63. Solve the following transportation problem with the following information on costs, supply and demand: Destination
D1 D2 D3 D4 Supply01
Origins 02
03
2 2 2 1
10 8 5 4
7 6 6 8
3
7
5
Demand 4 3 4 4
Prepared byProf. L .M. Alphonse Ligori
17