Optimization of lng regasification

Embed Size (px)

DESCRIPTION

The initial works in the fields are discussed

Citation preview

  • 5/26/2018 Optimization of lng regasification

    1/30

    1

    OPTIMIZATION OF LNG REGASIFICATION

    TERMINAL PROCESSES

    M. TECH. SEMINAR REPORT

    By

    Shashwat Omar

    (Roll Number 133020005)

    Under the guidance of

    Prof. Ravindra D. Gudi

    DEPARTMENT OF CHEMICAL ENGINEERING

    INDIAN INSTITUTE OF TECHNOLOGY

    BOMBAY400 076

    APRIL, 2014

  • 5/26/2018 Optimization of lng regasification

    2/30

    2

    Acceptance Certificate

    Department of Chemical Engineering

    Indian Institute of Technology Bombay

    The seminar report entitled Optimization of LNG Regasification Terminal

    Processes submitted by Mr. Shashwat Omar (Roll No. 133020005) has been

    corrected to my satisfaction and can be accepted for being evaluated.

    Date: 25-04-2014 Signature

    (Prof. Ravindra D. Gudi)

  • 5/26/2018 Optimization of lng regasification

    3/30

    3

    ACKNOWLEDGEMENT

    First of all, I would like to thank the almighty who gave me the strength to complete

    this report successfully.

    I would like to convey my heartfelt thanks to the Indian Institute of Technology

    Bombay for providing me the opportunity to work on this project and for allowing me

    the access to copious amount of invaluable literature.

    I would like to convey my sincere gratitude to my guide Prof. Ravindra D. Gudi, for

    his invaluable guidance, supervision and encouragement throughout the course of my

    study.

    I thank all my friends and colleagues for their help which contributed to the

    completion of this report.

    At last but not the least, I want to thank my parents for being with me and giving me

    inspiration when I needed it the most.

    Place: Mumbai Shashwat Omar

    Date: 25-04-2014

  • 5/26/2018 Optimization of lng regasification

    4/30

    4

    TABLE OF CONTENTS

    1 Introduction...............................................................................................52 Literature Survey......................................................................................93 Problem Formulation and Work Done so Far......................................234 List of Figures...........................................................................................285 References.................................................................................................29

  • 5/26/2018 Optimization of lng regasification

    5/30

    5

    CHAPTER 1

    INTRODUCTION

    From the tsunami in Japan and Thailand to polar vortex in USA and Canada, the

    effects of global warming are worsening day by day. The main cause of global

    warming is greenhouse gases such as water vapour, Carbon dioxide (CO2) and

    methane (CH4). The concentration of Carbon dioxide and methane in surrounding air

    has increased 148 % and 36 % respectively in the past 250 years due to industrial

    revolution.

    The industrial revolution is caused by big power looms, railways, factories and new

    technologies. Fossil Fuels like petroleum and Coal fulfilled are the major part of the

    energy requirement of this industrial revolution. But in doing so, they have increased

    the concentration of greenhouse gases in the surroundings. With the increasing

    population, the energy requirements are also increasing and knowing the harmful

    effects of fossil fuels, we have to go for clean fuels.

    Natural Gas is one of the clean fuels. It can be found in deep underground rock

    formation or with and proximity to petroleum. It consists of methane (80-90 %) some

    higher alkanes and impurities like carbon dioxide, hydrogen sulphide and nitrogen.

    Figure:1 Emission of combustion by-products from fossil fuels

    (http://www.cleanandaffordable.ca)

  • 5/26/2018 Optimization of lng regasification

    6/30

    6

    Figure 1 shows that, after burning, it generates only small amount of carbon dioxide,

    nitrogen oxide and almost zero emission of sulphur dioxide. So, the use of natural gas

    is getting popular all over the world as a clean environment friendly energy source.

    In figure 2, we can see that the countries with most natural gas reserves are Russia,

    Qatar, Iran, USA, Venezuela and Australia. The most populated countries in the world

    like India, Brazil, China, Indonesia and Pakistan do not have enough natural gas

    production to fulfil their energy needs. So, it is necessary for these countries to import

    natural gas. But, gas can be transported only via pipeline and it is very costly to lay

    pipeline from one country to another and various legal and natural constraints are also

    involved in it.

    Figure: 2 Country wise Natural Gas Reserves in trillion cubic meters

    (http://thomaspmbarnett.com 2012)

    LNG (Liquified Natural Gas) is the solution for this problem. LNG is natural gas

    liquefied at atmospheric pressure when cooled to -162oC. One cubic metre of Natural

    Gas is equal to the 600 cubic metre of LNG. So, for ease of transportation, large

    volume of Natural Gas can be converted into small volume of LNG. LNG is

    colourless, odourless, non-toxic and non-corrosive. LNG is relatively costly to

  • 5/26/2018 Optimization of lng regasification

    7/30

    7

    produce and it should be stored in a cryogenic tank because of its very low

    temperature.

    The process of natural gas exploration to LNG regasification is called LNG supply

    chain. It is divided into four parts natural gas production, Liquefaction, LNG

    transportation and LNG storage and regasification. First of all natural gas is produced

    from gas field wells, and then it is transported to liquefaction plants. These plants are

    built at marine terminals so the LNG can be loaded onto specially made tankers for

    transporting it overseas. After delivering of LNG to importing terminals, the LNG is

    stored into storage tanks, regasified and then sent into pipeline systems for delivery to

    downstream customers. Next, we look at all the four processes one by one -

    Figure: 3 LNG Supply Chain (Deybach 2012)

    Production: - Natural gas is extracted from oil wells or deep rock formations.This gas has impurities like carbon dioxide, nitrogen and hydrogen sulphide

    which should be removed before liquefaction otherwise they will freeze and

    damage the equipment in which phase change is taking place besides it is

    necessary to meet the demand of importer.

    Liquefaction: - In this process, natural gas is converted to LNG via cooling itdown to -162

    o

    C at atmospheric pressure. The volume of natural gas shrinks600 times in the phase change process that means the energy content of 1

  • 5/26/2018 Optimization of lng regasification

    8/30

    8

    cubic metre of LNG at -162oC is same as 1 cubic metre of natural gas

    atmospheric pressure and ambient temperature. So, it becomes easy to

    transport natural gas from one place to another because of less volume.

    LNG Transportation: - LNG is transported in specially designed ships withdouble hulls so as to minimize the risk of potential leakage. There are three

    types of LNG carriers as per the storage tank design membrane tank, IHI

    prismatic and spherical tanks. Some Cargos use Boil -off Gas (BOG) generated

    from the tanks as a fuel to run ships. A cargo can take 2 to 8 days to reach its

    destination. So, it is necessary to calculate the BOG volume consumed by

    cargo to determine actual LNG volume that can be unloaded.

    Storage and Regasification:- At the importing terminal, LNG is unloaded fromcarrier and stored in big cryogenic storage tanks at atmospheric pressure and -

    162oC. The quantity (100,000 m

    3to 160,000 m

    3) and number of storage tanks

    in a terminal depend on the frequency of cargos visiting to terminal and the

    demand of downstream customers. The regasification process consists of

    gradually converting LNG to natural gas at 0oC and 80-100 bar pressure. The

    mechanisms to convert LNG into natural gas depend on the geographical

    nature of terminal and composition of the LNG imported. Sometimes,

    treatment of natural gas can also be done to meet the caloric value demand by

    changing the composition of propane, butane and nitrogen components before

    sending it to customers.

    LNG production, transportation and converting it to natural gas are a costly and

    energy-intensive process. This thesis will focus on optimization of LNG storage

    and regasification operation. However, optimization of the complete LNG supply

    chain is beyond the scope of this thesis. For upcoming and existing LNG

    regasification plants, integration of new technologies with blend of optimization

    will help to minimize costs and maximize profit margins and this thesis will work

    in this direction.

  • 5/26/2018 Optimization of lng regasification

    9/30

  • 5/26/2018 Optimization of lng regasification

    10/30

    10

    operations. We can divide the whole plant into individual equipment and operations

    and then will optimize them separately. First of the lot comes unloading and

    recirculation operation. For most of the LNG regasification terminals, storage tanks

    are located 4-5 km. far from the LNG unloading platform. The LNG transporting

    pipelines must be insulated to keep LNG at liquid state. A running LNG regasification

    plant is operated in two modes: first, when unloading is happening from a LNG

    carrier ship and second, when there is no ship at the LNG unloading platform. In the

    second situation, some LNG is pumped from storage tanks and circulated to

    unloading transportation lines and then comes back to tanks. This is necessary to keep

    transportation lines cool before LNG unloading. In the LNG regasification terminals,

    a constant rate of recirculation is always maintained. It determines the operating cost

    of the LNG pump which is needed to maintain the flow rate into transportation lines.

    However, depending on the LNG send-out flow rate, the handling method and costs

    of BOG to flow into the storage tanks are varied. So, the recirculation flow rate

    should be decided after taking BOG handling cost into account. Park et al. (2010)

    devised an optimal recirculation method to reduce total operating costs by adjusting

    the recirculation flow rate dependent on demand of downstream customers. During

    unloading process, flashed BOG from the pipeline flows into the storage tank. Due to

    increasing amount of BOG, pressure in the storage tank rises. BOG compressor is

    used to maintain pressure in storage tank. BOG from compressor meets the LNG

    transported to the recondenser to meet demands. This BOG inflow rate determines the

    operating cost of the BOG compressor to handle the BOG in the storage tank.

    Therefore, recirculation flow rate creates a trade-off between the cost of BOG

    compressor and operating cost of the recirculation flow pump. If the necessary

    recirculation flow rate is high, the pump operating cost increases, but the compressor

    operating cost decreases due to the reduction of BOG inflow and vice-versa.

    After unloading, LNG is stored in cryogenic storage tanks. These are of different

    kinds based on the natural climate and necessity. The most popular one is full

    containment tank. LNG is characterized by its density. Less dense LNG tends to have

    lower chain hydrocarbon content and less calorific value and denser LNG tends to

    have higher chain hydrocarbon content and high calorific value. During the unloading

    operation, terminal operators have to face three different cases. In the first case,

    incoming LNG is lighter than the LNG stored in the tank to be filled. A complete mix

  • 5/26/2018 Optimization of lng regasification

    11/30

    11

    of two LNG quantities is ensured by tank bottom filling operation with a limited BOG

    generation and stratification risk is eliminated which can potentially lead to a rollover

    event. For the second case, incoming LNG is heavier than the stored in storage tank.

    By tank top filling operation, stratification and risk of rollover is avoided but it

    usually results in excessive BOG production and tank pressure increases as shown in

    figure 5.

    Figure: 5Total Boil-off gas flowrate and pressure evolutions during tank top filling

    in a 120,000 m3LNG tank (Zellouf and Portannier 2011)

    The last situation is tank bottom filling with a heavy LNG under a light stored LNG

    heel producing less BOG but leading to stratification which will need to be managed

    in order to avoid rollover. Figure 6 shows how a stratification profile looks like inside

    a tank. Rollover phenomenon is the overturning of two LNG stratified layers.

    Figure: 6Characterization of LNG stratification (Zellouf and Portannier 2011

  • 5/26/2018 Optimization of lng regasification

    12/30

    12

    Rollover occurs when the two LNG layers densities equalizes mainly further to the

    LNG expansion in the lower layer due to the heat ingress. It is accompanied by a

    sudden rise in BOG which is due to the sudden release of the energy accumulated in

    the lower density layer through time.

    Zellouf and Portanni er (2011)showed that by optimizing the operating pressure in

    the storage tank, the total BOG rate generated during filling can be reduced by about

    half. This can be done in three easy steps. First, pre-cooling of the tank heel before

    unloading occurs by lowering the operating pressure. Secondly, before unloading, the

    operating pressure is increased above the atmospheric pressure to sub-cool the LNG

    and this pressure is maintained throughout the unloading process. Third, once tank is

    filled, the pressure is then lowered progressively to the atmospheric value.

    Figure: 7Pressure optimization of BOG rate during tank filling of heavy LNG

    under/over light heel LNG at a filling rate of 10,000 m3/h, obtained using the GDF

    SUEZ LNG MASTER software(Zellouf and Portannier 2011)

    Figure 7 shows that by operating pressure optimization, the total BOG rate generated

    during filling can be decreased by about 50 %. This highlights the advantages gained

    from this procedure, not only in terms of the costs saving by reducing compressor

    input, but also in terms of avoiding the use of safety equipments like flares.

    Deshpande et al. (2011)presented a lumped parameter model in order to predict time

    for the rollover phenomenon and to investigate its sensitivity to heat and mass transfer

    coefficients. The originality about this work is its ability to estimate heat and mass

  • 5/26/2018 Optimization of lng regasification

    13/30

    13

    transfer coefficients from the real time data using an inverse methodology. The real

    time data of Level, Temperature and density from storage tanks is assimilated in order

    to estimate heat and mass transfer coefficients from the densities of the stratified

    layers. Then, the optimized heat and mass transfer coefficients are used in prediction

    of time of rollover as shown in figure 8.

    Figure: 8procedure used to infer HTC and MTC from the real time LTD data

    profile (Deshpande et al. 2011)

    BOG generation is uncalled for but inevitable in a LNG regasification terminal. BOG

    generation happens in LNG storage tanks and all LNG transporting lines due to some

    heat ingress. Querol et al. (2010)proposed number of methods to handle BOG so as

    to minimize the operating cost.

    Figure: 9Diagram of the unloading procedure of a LNG regasification terminal(Querol et al. 2010)

  • 5/26/2018 Optimization of lng regasification

    14/30

    14

    As seen in figure 9, during the unloading operation, heat is absorbed by the carrier

    (QC), tank (QT), unloading arms (QA) and LNG transporting lines (QL). For a normal

    LNG regasification terminal with BOG generation at its worst case and normal case,

    these methods are discussed to handle BOG

    Flaring: This is used when there is no other option to handle BOG and safetyof equipment and plant is necessary. No additional investment is needed for it

    because it is installed compulsorily in each terminal.

    Recondenser: All the regasification terminals have this equipment to handlethe total amount of generated BOG in the normal case.

    BOG compressor: This equipment is installed to compress BOG as per therequirement of recondenser and LNG carrier pressure.

    Most of the LNG terminals buy the electricity supplied by the state or national grid. In

    the plant, LNG is converted into natural gas which is a very good fuel and it can be

    used to generate electricity inside the terminal. For generation of electricity, a

    cogeneration power plant should be set up. In this gas fired power plant, gas will enter

    inside the equipment at very high pressure and will be burned. The burned gases will

    generate heat and pressure that will be used to rotate a Gas turbine. By rotation of this

    Gas turbine, electricity will be generated. The hot gases after burning can be used for

    producing hot water from cold water in a heat exchanger. This cogeneration plant are

    very effective in terms of energy saving and cost minimization. In addition to that,

    Variable costs occurring due to the submerged combustion vaporiser could be reduced

    if submerged combustion and heat recovered from cogeneration plant are integrated.

    This equipment succeeds to obtain nearly 100 % efficiency in reducing electricity bill

    of LNG terminal and its energy dependence on outer sources.

    In the LNG storage tank the liquid temperature is approximately -162oC and the

    pressure is nearly above the atmospheric pressure. Part of LNG stored in tanks is

    continuously evaporated into BOG (Boil-Off Gas) because of heat transfer from

    surroundings. This BOG should be removed by compressors because it is necessary to

    maintain tank pressure within a safe range. However, excessive operation of

    compressors spends excess energy, and even sometimes generates excess BOG. So,

    proper handling of BOG is essential for the safe and efficient LNG terminal operation.

    Shin et al. (2008)proposed an empirical BOR (boil off rate) model and a simplified

  • 5/26/2018 Optimization of lng regasification

    15/30

    15

    dynamic tank model. Proposed algorithm generates an optimal operation schedule for

    BOG compressors which minimizes the power consumption given potential failure of

    one of the operating compressors.

    They used following empirical equation in order to estimate the rate of BOG

    generation in a LNG storage tank

    (2-1)

    Where,

    CR= rollover coefficient ( 1)

    BS= boil off rate on specification (h-1

    )

    L= LNG density (kg/m3)

    VL= LNG volume (m3)

    K1 = correction factor for the offset of the tank pressure from the LNG vapour

    pressure

    K2= correction factor for the LNG temperature

    K3= correction factor for the ambient temperature

    A range of correction of correction factors was definedbased on real situations and

    also defined an equation for calculating LNG vapour pressure from a Antoine model

    equation. Using all these equations, the BOG generation rate can be calculated from

    the tank pressure. Under the assumption that, LNG volume is very large so the

    temperature and volume rate of change will be very slow and thus can be taken as

    constant. So, for a target steady state tank pressure P s, the target compressor load F0

    can be calculated using the MILP optimization problem solving. A simple dynamic

    model based on the ideal gas law is used for the prediction of the tank pressure change

    which can be effectively applied to safety analysis for preparing against the potential

    failure of one of the running compressors. Based on a case study, the performance

    evaluation indicated that the energy consumption could be reduced by half as

    compared with the conventional method by operating the tanks at a higher pressure

    within the safe range.

  • 5/26/2018 Optimization of lng regasification

    16/30

    16

    As indicated in the paper, the recondenser is the heart of a LNG regasification

    terminal. Like, for a body when heart stops beating, it becomes dead. Same is true for

    a LNG plant. Recondenser is the most vital equipment of LNG terminal. It converts

    BOG to LNG and gives positive head to High pressure pumps. In storage tanks, LNG

    is at 1 bar pressure and -1620C. It is send to recondenser at 8 bar pressure, so it

    becomes subcooled. This energy difference between subcooled and boling state is

    used to condense BOG into LNG inside recondenser. BOG recovery is an essential

    thing and also from that perspective, this equipment is pretty valuable. Yajun et al.

    (2012)proposed an optimized control theory to control pressure and level inside the

    recondenser and optimum flow rate of LNG to condense BOG. In the figure 10, it is

    showed that in some existing BOG terminals, pressure is controlled via recondenser

    pressure controller PIC-1 and to prevent High Pressure pumps from cavitations by

    regulating the pressure control valves PCV-1 and PCV-2 also used for LNG

    bypassing.

    Condensing LNG flow rate is maintained by the control valve FCV. The Condensing

    LNG flow rate is governed by the following equation:

    (2-2)

    Flow rate is fixed by the ratio calculation module in FX1. Where, Q LNG (m3/h) is

    volumetric flow rate of condensing LNG, (Nm3/h) is standard volume flow ofBOG; (MPa) is pressure of HP suction header: is 0.58, a parameter referringto LNG composition.

    Value of QLNGwill be transformed into the setting point of FIC-1. The normal high

    set point of recondenser liquid level is 60 %. Once liquid level exceeds 60 %, LIC-2

    will sendout signal to LCV to send high pressure make up gas inside recondenser to

    lower the liquid level. This move will increase the pressure of recondenser and can

    also prevent sufficient amount of LNG not to enter recondenser. If the level still keeps

    on rising, there is a interlocked level controller LT-2 which will automatically give

    HH-SD a signal to shut down control valve XV-1. When the recondenser level goes

    below the set point, LIC-1 could start override control to reduce BOG flow rate

    entering into recondenser.

  • 5/26/2018 Optimization of lng regasification

    17/30

  • 5/26/2018 Optimization of lng regasification

    18/30

    18

    Figure: 11Optimized control system to BOG recondenser (Yajun et al. 2012)

    Pressure will be controlled by the new valve PIC-3. If pressure inside the recondenser

    keeps on increasing PC-1 sends signal to PCV-1 to open and decrease the pressure.

    When PCV-1 is fully open and pressure inside recondenser still keeps on increasing,

    then pressure controller PIC-2 gives command to PCV-3 to vent BOG. For the

    condition of decreasing pressure inside recondenser, PC-1 will send signal to PCV-1

    to close and if this move is not sufficient then, PCV-4 will operate PCV-2 and make

    up gas will enter recondenser and maintain the pressure. For liquid level control,

    LCV-1 and LCV-2 will come into use now. When the required LNG output is more

    than summation of BOG condensate and condensing LNG stream, the liquid level will

    drop down. The liquid controller LIC-1 will increase the opening of valve LCV-1 andLCV-2 to maintain a desired liquid level. Conversely, in the case of liquid level rise,

    the opening of LCV-1 and LCV-2 will be decreased.

    The advantage of this control is LNG storage tank pressure is held constant.

    Recondenser comes into normal position sooner. It is more energy efficient because

    makeup is not entered into system frequently. New system can operate at a flexible

    operating pressure of recondenser. BOG can be totally liquefied even for the low flow

    rate of LNG.

  • 5/26/2018 Optimization of lng regasification

    19/30

    19

    High pressure Pumps are used to pressurize LNG that comes out of recondenser to

    100-100 bar pressure. This high pressure is required because after LNG is converted

    into natural gas, it must be transported over a long distance. These pumps can be 4-5

    in numbers based on the capacity of the plant. These pumps take considerable amount

    of energy to run. A single stage and multi-stage cryogenic pump is shown in figure

    12. Presently, most of the LNG terminals have high pressure pumps running on fixed

    speed motors and produce a single flow versus head curve at that speed. These pumps

    are controlled by throttling the discharge pressure with a control valve or bypassing a

    portion of the flow to a secondary stream. Pumps running on a fixed speed have a

    single Best Efficiency Point (BEP) at which the pump is designed to run at the rated

    point. Pump flows that are throttled by reduction of the discharge pressure run off of

    the BEP and therefore the efficiency is reduced. The efficiency and range of operation

    for cryogenic pumps can be improved by used of variation of motor speed.

    Figure: 12Multistage and Single Stage High Pressure Cryogenic Pumps(Lovelady

    et al. 2008)

    Lovelady et al. (2008)showed that by adjusting the speed user can accurately control

    the operating characteristics of the pump over a greater range with better overall

    efficiency. Efficiency of pump operation at off design flow points can be improved by

    varying the pump speed to a point on the pump hydraulic curve which matches the

  • 5/26/2018 Optimization of lng regasification

    20/30

    20

    BEP to the desired flow rate. This paper discussed how the variable speed operation

    of cryogenic pumps resulted in improved operating costs with more effective control

    of the output flow and head. In addition, the paper also discussed other design, control

    and economic benefits of utilizing variable speed motors at LNG terminals.

    The vaporizers are used in LNG regasification terminal to convert LNG to natural gas.

    High pressure LNG at about -1600C comes into the vaporizer and it is vaporized until

    a suitable temperature is achieved. This temperature is generally close to 0oC and it

    can vary according to the demand of customers. There are several types of vaporizers

    that can be used according to the climate, cost and easily available vaporization fluid.

    Some of them are Open Rack vaporizer (ORV), Fired heater with Shell and Tube

    vaporizer, Submerged Combustion Vaporizer (SCV), Intermediate Fluid Vaporizer,

    Ambient Air Vaporizer etc. It is the most important process to select the right

    vaporizer system in designing a LNG terminal as the regasifying costs contribute

    major portion of an LNG terminal operation. Low operating cost with high reliability

    of the regasifying system is a key parameter for a successful operation of an LNG

    receiving terminal. I n-Soo Chun (2008) reviewed ORV performance and optimum

    heat recovery temperature under harsh seawater temperature. The practical

    optimization of vaporization with the unfavourable seawater conditions in winter isdiscussed. An economic comparison between conventional vaporization and

    optimized vaporization is also discussed. As shown in figure 13, an ORV is a

    vaporizer in which LNG flows inside a heat-transfer tube and exchanges heat with

    seawater that flows outside the heat-transfer tube to gasify the LNG. The LNG flows

    in form an inlet nozzle near the bottom and passes through an inlet manifold and a

    header pipe to be sent to a set of panels which each of them consisting of a curtain-

    like array of heat-transfer tubes. LNG exchanges heat with seawater that flows

    downward in a flim-like manner utside the heat-transfer tubes as it flows upward

    inside the heat-transfer tubes. This operation results in normal temperature gas to be

    sent out from an outlet nozzle via an outlet header and manifold pipe.

  • 5/26/2018 Optimization of lng regasification

    21/30

    21

    Figure: 13Schematic of an Open Rack Vaporizer (Egashira 2013)

    The paper discussed that for achieving low cost vaporization and to minimize impact

    on the environment, ORVs and SCVs should be combined as a backup. The seawater

    temperature drops to 0oC after it is used for LNG vaporization, which is not

    recommended for operational purpose especially during the winter. The following

    parameters were investigated for the vaporization optimization:

    Performance of ORV with the lower seawater temperature Optimum seawater operating temperature Economic combination of ORV and SCV

    Economic justification of seawater heating Overall economic assessment of vaporization facility

    In figure 14, it is shown that seawater requirement abruptly increases as the

    temperature of inlet seawater decreases, while seawater requirement is constant after a

    certain point even though its temperature increases. As the temperature of seawater

    decreases below design temperature, the SCV operation and seawater heating process

    need to be operated. This results an increase in operating cost. Fuel gas requirements

  • 5/26/2018 Optimization of lng regasification

    22/30

    22

    for the operation of SCVs increase linearly during the winter as the recovered heat

    from seawater decreases.

    Figure: 14Economic Analysis of different Seawater Temperature(In-Soo Chun

    2008)

    The results showed that, for selection of optimum vaporization method, designconstraints with unfavourable seawater temperature have been successfully solved

    with heating up seawater. This results in heat recovery increment from cold seawater.

    Unless otherwise, the seawater cannot be used when its temperature is lower than the

    design temperature.

  • 5/26/2018 Optimization of lng regasification

    23/30

    23

    CHAPTER 3

    Problem Formulation and Work Done so Far

    In this thesis, we consider the problem of optimizing LNG regasification terminal

    processes. The scope of the optimization that we seek spans from the upstream

    operations of unloading LNG cargos at the jetty to the downstream system that sends

    out natural gas to customers. Given a schedule of LNG carriers to the terminal and

    demand of downstream customers, a typical LNG regasification terminal has

    unloading arms, storage tanks, Low pressure pumps, BOG compressor, Recondenser,

    High pressure pumps and vaporizers as its main unit operations. The key decisions for

    optimization are related to recirculation operation, BOG maintenance and handling,Recondensing BOG, vaporization of LNG. After going through, several research

    papers in field of optimization of LNG process, it is seen that no work has been done

    to optimize the whole plant in an integrated manner. The works are done in individual

    sub-systems such as optimization of storage tank BOG handling, optimization of

    recirculation operation and optimization of recondenser operation. This work will

    attempt an integrated look at the entire plant, based on mass & energy balances, and

    will also consider minimizing external work that may be necessary to maintain phase

    of the LNG at appropriate points. As such therefore, this work proposes to optimize

    the entire LNG regasification plant by formulating an optimization problem having

    objective function as minimization of power consumption and maximization of profit.

    In the first phase of the work, we look at optimizing the wait time of LNG cargos

    given a schedule of their arrival to the terminal. According to demand, constant

    discharge of LNG from each storage tank is assumed. The terminal consists of two

    jetties and four LNG storage tanks. A cargo can be assigned to any one of the jetty

    based on the availability of space there and total storage tank volume. Once assigned

    to a jetty, a cargo will unload its contents to 4 tanks assuming constant discharge flow

    rate. There can be three cases for this operation. First, both the jetties have cargos.

    Second, one jetty has cargo and one does not. Third, both the jetties do not have any

    cargo at a time. The total unloading time of a cargo will depend on the amount of

    LNG in it, constant unloading rate from the cargo and total volume of the storage

    tanks. It is essential to minimize unloading time of a LNG cargo because the profit of

  • 5/26/2018 Optimization of lng regasification

    24/30

    24

    operating a LNG terminal is based on the demand of Natural Gas from customers and

    demand cannot be fulfilled without supply. Secondly, there is a maximum time limit

    in which a cargo has to be unloaded otherwise there will be a huge penalty on

    terminal for every minute of delay.

    There are two approaches used in the literature for scheduling problems formulation:

    continuous and discrete. There are uniform slots for a job in continuous approach and

    variable length slots for discrete time approach. For the LNG cargo scheduling

    formulation, we will adopt a continuous time approach. The benefit of using this

    approach is, it has fewer time slots as compared to the discrete time formulation and

    less variables. Having said that, nonlinearities in the system is also introduced and we

    need to accommodate that in the solution procedure. The following figure shows the

    structure of jetty and storage tanks.

    Figure 15: Block diagram of LNG unloading operation

    I ndex notations & constraints:

    i = jetty (1,2)

    j= cargos (1,.... , N)

    k = Number of tanks (1,2,3,4)

    m = Number of slots (1,2,3...........,M)

  • 5/26/2018 Optimization of lng regasification

    25/30

    25

    , If jth cargo is assigned to ith jetty in its mth slot.

    At a time, one jetty can have only one cargo. So,

    (3-1)

    The same constraint can be written for ship. At a time, a ship can be boarded to only

    one of the jetties. So,

    (3-2)

    Now, after completion of unloading of a cargo another cargo should be assigned to

    the jetty. For that,

    =Start time of the unloading of cargo at ith jetty in its mth slot.

    End time of the unloading of cargo at ith jetty in its mth slot

    (3-3)

    Processing time of the jth cargo at ith jetty in its mth slot.

    Then,

    (3-4)

    (3-5)

    Where, =Processing time in the unloading

    All of the tanks can be filled from both of the jetties or from the single one which will

    be based on the availability of cargos. Given there is no tank at its highest level, The

    feed to tank coming from each jetty will be divided into four parts otherwise, that tank

    will not be filled.

    Volume of cargos to be taken as

    Volume of tanks to be taken as

  • 5/26/2018 Optimization of lng regasification

    26/30

    26

    Let the fraction of feed stream divided to each tank is

    (3-6)

    and (3-7)

    Now mass balance equation for a single tank can be written as,

    (3-8)

    Additional Constraints:

    (3-9)

    (3-10)

    Let where, kland (3-11)

    (3-12)

    (3-13)

    Objective Function: minimization of standing time of the LNG carrier which is

    (3-14)

  • 5/26/2018 Optimization of lng regasification

    27/30

    27

    Where,

    Tss(j) = standing time of jth cargo

    Tar(j) = arrival time of jth cargo

    It is essential to maintain the same level in each tank during the operation of terminal

    because in the case of outlet pump failure of one or two tanks, we can send LNG out

    from the rest of the tanks. Similarly, If there is a problem in upstream of the tank, we

    can take LNG into rest of the tanks. So for that the objective function should be

    Minimize

    +

  • 5/26/2018 Optimization of lng regasification

    28/30

    28

    LIST OF FIGURES

    Figure No. Title Page No.

    1 Emission of combustion by-products from fossil fuels 5

    2 Country wise Natural Gas Reserves in trillion cubic meters 6

    3 LNG Supply Chain 7

    4 Dahej LNG regasification terminal of Petronet LNG Ltd. 9

    5 Total Boil-off gas flowrate and pressure evolutions during tank

    top filling in a 120,000 m3LNG tank

    11

    6 Characterization of LNG stratification 11

    7 Pressure optimization of BOG rate during tank filling of heavyLNG under/over light heel LNG at a filling rate of 10,000 m

    3/h,

    obtained using the GDF SUEZ LNG MASTER software

    12

    8 procedure used to infer HTC and MTC from the real time LTD

    data profile 13

    9 Diagram of the unloading procedure of a LNG regasification

    terminal

    13

    10 Existing control system to BOG recondenser 17

    11 Optimized control system to BOG recondenser 18

    12 Multistage and Single Stage High Pressure Cryogenic Pumps 19

    13 Schematic of an Open Rack Vaporizer 21

    14 Economic Analysis of different Seawater Temperature 22

    15 Block diagram of LNG unloading operation 24

  • 5/26/2018 Optimization of lng regasification

    29/30

    29

    REFERENCES:

    1. Ahuja M.M. (2005). A general presentation on Dahej LNG terminal, (personalcommunication).

    2. Aspelund, a., Gundersen, T., Myklebust, J., Nowak, M. P., & Tomasgard, a.(2010). An optimization-simulation model for a simple LNG process. Computers

    & Chemical Engineering, 34(10), 16061617.

    3. Chun, I., Lee, S., & Meeting, A. S. (2008). Optimized Vaporization ConditionsProcess with Unfavorable Design, 6175.

    4. Chun, I. S., & Kim, C. H. (2006). Practical optimization of LNG terminalprocess. InAIChE Annual Meeting, Conference Proceedings .

    5. Deybach F. (2012). Background information on Liquefied Natural Gas, cfafg,GDF Suez LNG.

    6. Deshpande, K. B., Zimmerman, W. B., Tennant, M. T., Webster, M. B., &Lukaszewski, M. W. (2011). Optimization methods for the real-time inverse

    problem posed by modelling of liquefied natural gas storage. Chemical

    Engineering Journal, 170(1), 4452.

    7. Egashira, S. (2013). LNG Vaporizer for LNG Re-gasification Terminal, (32), 6469.

    8. http://www.cleanandaffordable.ca/#clean9. http://thomaspmbarnett.com/globlogization/2012/7/20/chart-of-the-day-

    economists-listing-of-top-15-natural-gas-re.html

    10.Kim, H., Kim, I. H., & Yoon, E. S. (2010). Multi-objective Design of CalorificValue Adjustment Process using Process Simulators. Industrial & Engineering

    Chemistry Research,49(6), 28412848.

    11.Li, Y., Chen, X., & Chein, M.-H. (2012). Flexible and cost-effective optimizationof BOG (boil-off gas) recondensation process at LNG receiving terminals.

    Chemical Engineering Research and Design, 90(10), 15001505.

    12.Lim, G., & Park, L. (2005). LNG Terminal Operator s Design Feedbacks andTechnical Challenges.

    13.Lovelady, J., Wong, J., & Minton, B. (2008). LNG Pump applications withvariable speed motor controls at LNG regasification terminals. In ACS National

    Meeting Book of Abstracts .

  • 5/26/2018 Optimization of lng regasification

    30/30

    30

    14.Miana, M., Hoyo, R. del, Rodriglvarez, V., Valds, J. R., & Llorens, R. (2010).Calculation models for prediction of Liquefied Natural Gas (LNG) ageing during

    ship transportation.Applied Energy , 87(5), 16871700.

    15.Munawar, S. A., Bhushan, M., Gudi, R. D., & Belliappa, A. M. (2003). CyclicScheduling of Continuous Multiproduct Plants in a Hybrid, (10), 58615882.

    16.Munawar, S. A., & Gudi, R. D. (2005). A Multilevel, Control-TheoreticFramework for Integration of Planning, Scheduling, and Rescheduling. Industrial

    & Engineering Chemistry Research, 44(11), 40014021.

    17.zelkan, E. C., DAmbrosio, A., & Teng, S. G. (2008). Optimizing liquefiednatural gas terminal design for effective supply-chain operations. International

    Journal of Production Economics, 111(2), 529542.

    doi:10.1016/j.ijpe.2007.02.028

    18.Pardevised k, C., Lee, C.-J., Lim, Y., Lee, S., & Han, C. (2010). Optimization ofrecirculation operating in liquefied natural gas receiving terminal.Journal of the

    Taiwan Institute of Chemical Engineers, 41(4), 482491.

    19.Pinto, J. M., & Grossmann, I. E. (1994). Optimal Cyclic Continuous SchedulingOf Multistage Multiproduct, 18(9).

    20.Querol, E., & Gonzalez-Regueral, B. (2010). Boil off gas (BOG) management inSpanish liquid natural gas (LNG) terminals. Applied Energy , 87(11), 33843392.

    21.Chapter 7 - LNG Plant and Regasification Terminal Operations, In Handbook ofLiquefied Natural Gas, edited by Saeid Mokhatab, John Y. Mak, Jaleel V.

    Valappil and David A. Wood, Gulf Professional Publishing, Boston, 2014, Pages

    297-320, ISBN 9780124045859

    22.Sonmez, E., Kekre, S., & Nicola, A. S. (n.d.). Model-based Analysis of LiquefiedNatural Gas Regasification Technologies Working Paper, (Eia 2007), 128.

    23.Wook Shin, M., Jang, N., Shin, D., Han, C., Hyoung Choi, S., & Yoon, E. S.(2009).Proceedings of the 1st Annual Gas Processing Symposium .Proceedings

    of the 1st Annual Gas Processing Symposium (pp. 171178).

    24.Yan, M., & Hu, J. G. (2008). Advanced modeling of LNG receiving andregasification terminals. In Conference Proceedings - 2009 AIChE Spring

    National Meeting and 5th Global Congress on Process Safety .

    25.Zellouf, Y., & Portannier, B. (2011). First step in optimizing LNG storages foroffshore terminals. Journal of Natural Gas Science and Engineering, 3(5), 582590.