Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

Embed Size (px)

Citation preview

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    1/9

    O R I G I N A L A R T I C L E

    Optimization of concurrent mining and reclamation plansfor single coal seam: a case study in northern Anhui, China

    Zhenqi Hu   • Wu Xiao

    Received: 1 September 2011 / Accepted: 2 July 2012 / Published online: 19 July 2012

     Springer-Verlag 2012

    Abstract   The extraction of underground ore body inev-

    itably causes a large amount of land subsidence. Currentreclamation technologies in China mainly focus on stable

    subsided land, which means most of the affected lands are

    submerged into water because of the high groundwater

    table in some areas, leading to the loss of soils and inef-

    ficient reclamation. Therefore, a new technology for

    reclaiming unstable subsiding land is being studied for

    restoring farmland as much as possible, based on a case

    study in northern Anhui, China. In consideration of the

    mining plan, subsidence processes in various stages were

    analyzed and some related factors such as vertical subsi-

    dence, post-mining slope, water area, and land use condi-

    tion were also simulated. Due to mining activities, useful

    farmland has gradually decreased to merely 14.4 % of the

    pre-mining area. In this study, the following stages were

    modeled from pre-mining to post-mining: (1) percentage of 

    farmland was 100 % in stage (a) (pre-mining), (2) 72.5 %

    in stage (b), (3) 67.3 % in stage (c), and (4) 14.4 % in stage

    (d) (post-mining). The results show that 86.6 % of culti-

    vated land was submerged into water and lost its capacity

    for cultivation after coal mining. Reclamation plans for

    stages (b), (c), and (d) were made by a traditional recla-

    mation method called ‘‘Digging Deep to Fill Shallow’’.

    Based on scenario simulation of reclamation, the farmland

    reclamation percentages were improved to 78.3, 73.3, and

    40.70 %, respectively. Taking the percentage of reclaimed

    farmland as the preferred standard, concurrent mining and

    reclamation for stage (b) and (c) could increase farmland

    reclamation percentages to 37.6 and 32.6 %, respectively,

    compared with the farmland reclamation percentage of post-mining [reclaiming the land in stage (d)]. The results

    reveal that optimum reclamation time should be at stage

    (b). Therefore, under current technical conditions, con-

    current mining and reclamation could enhance the quantity

    of cultivated land and provide better land protection and

    food security in the mined areas with high groundwater

    table.

    Keywords   Mining subsidence Concurrent mining and reclamation    Land protection  Subsidence prediction     Planning scheme    Optimization

    Introduction

    China is the number one coal production and consumption

    country. The coal outputs exceeded 3 billion tons in 2010,

    accounting for 42 % of the global production (Wang 2009).

    However, mining and utilization of coal may cause serious

    environmental impacts such as coal waste disposal, poi-

    sonous gas emissions, land subsidence, landscape change,

    etc. Comparatively, land subsidence seems to be one of the

    most prominent problems in China, because 92 % of the

    coal output comes from underground mining, with thou-

    sands of underground long wall panels. Underground

    mining activities disturb the surface severely, and this sit-

    uation is even more prominent in east and northeast China

    (Xiao et al.  2009), which are both main coal and agricul-

    tural production regions (called ‘‘Overlap Region’’). The

    Overlap Region covers 40 % of the total farmland in China

    and contains 58 % of national coal production and 45 %

    of food production (Hu and Luo   2006). High-intensity

    extraction of underground coal results in large-scale

    Z. Hu (&)   W. XiaoInstitute of Land Reclamation and Ecological Restoration,

    China University of Mining and Technology (Beijing),

    Beijing 100083, China

    e-mail: [email protected]

     1 3

    Environ Earth Sci (2013) 68:1247–1254

    DOI 10.1007/s12665-012-1822-9

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    2/9

    ground settlement, barren farmland, and a decrease in

    cultivated land. It is estimated that the subsidence area

    extends from 0.2 to 0.33 ha, when 10,000 tons of coal are

    extracted underground. Subsidence is expected to expand

    2  9  104 ha annually throughout China (Hu   1996). Thou-

    sands of hectares of affected land lost the capacity of 

    cultivation because of extraction of a thick coal seam and

    high groundwater table. The depth of ponding water on the

    ground surface could reach 13 m (Wang et al. 2009). Thus,

    farmland loss and degradation caused by underground

    mining activities is serious in China. In fact, coal mine

    production increased over the past 10 years and reached its

    peak with 18.35 % growth rate in 2003 (Fig.  1). It is pre-

    dictable that mining production will continue to expand in

    the foreseeable future, because of rapid economic growth.

    Thus, the quantity of subsided agricultural land will con-

    tinue to rise.

    According to the Annual Bulletin issued by the Ministry

    of Land and Resource (MLR) in 2008, cultivated land was

    decreased to 1.22  9  108 ha at the end of December 2008,

    with merely 0.09 ha farmland per capita (Fig.  2). Conse-

    quently, the Chinese government also retains the amount of 

    1.2  9  108 ha farmland as a base red line to ensure food

    security in 2020. How the limited cultivated land resources

    are protected is particularly important at this stage of rapid

    economic growth.

    Abandoned mine site hazards assessment (Kim et al.

    2006,  2009) and mine land reclamation have been exten-

    sively studied by many scholars (Bascetin  2007; Wu et al.

    2009; Xiao et al.   2011). Approximately, 60 % of theworld’s coal production comes from underground mines,

    and China accounts for much of the worldwide under-

    ground operations (Table  1). Comparatively, the other four

    main coal production countries such as USA, India,

    Australia, and Russia adopt less underground mining.

    Therefore, farmland subsidence and related reclamation are

    relatively less of a concern in these countries (Bell et al.

    2005). The impact of subsidence may vary from site to site

    due to differences in geology and soil conditions. For

    example, Illinois, USA, also a typical coal and agricultural

    production overlap region, has maximum subsidence of 

    about 3 m (Darmody et al.   1992; Darmody   1995), thus,making reclamation work much easier as compared to

    China. In addition, reclamation strategies are much more

    diverse outside of China where agricultural land resources

    and population pressures are not as pressing.

    Since the 1980s, China’s land reclamation has made

    considerable progress in restoring subsidence land with

    different methods (Hu 1994a, b); they are:

    (a) ‘‘Digging Deep to Fill Shallow’’: The technology

    divides the subsidence-prone area into two parts: deep

    and shallow, then makes the deep area deeper by an

    excavator for digging a fish pond, and the excavated

    soil is moved to the shallow part for reclamation of 

    cultivate land. Hydraulic dredge pumping is one of 

    the ‘‘Digging Deep to Fill Shallow’’ methods.

    (b) Directly reconditioning: If there is no water in some

    shallow subsidence areas and the subsurface water

    level is not very high, the method of directly

    reconditioning the subsided land can be used. Usu-

    ally, the subsided land is leveled by bulldozers or

    often by manual work. If the slope of the subsided

    land is large, terraces should be used.

    Fig. 1   Coal yield and growth rate from 1990 to 2010 in China

    Fig. 2   Cultivated land quantity variation from 2001 to 2008 in China

    Table 1   Percentage of coal production by mining method in 2006

    Country Underground (%) Surface (%) Total (Mt)

    China 95 5 2,380

    USA 31 69 1,054

    India 19 81 447

    Australia 22 78 405

    Russia 309

    South Africa 257

    Germany 197

    Indonesia 195

    Poland 156

    Total world 60 40 6,195

    1248 Environ Earth Sci (2013) 68:1247–1254

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    3/9

    (c) Filling: A type of landfill method, filling subsidence

    land with some filling materials such as coal wastes

    and fly ash.

    (d) Drainage: Establishment of a system of drains such as

    a trench can make the impounded water drain away

    and lower the subsurface water level so that the

    subsidence land is relatively raised.

    Both filling and non-filling methods are good earthwork 

    measures and well applied in China. However, all recla-

    mation works were focused on stable subsided land, which

    means subsidence reaches the final settlement condition

    after the excavation of coal is completed. In this situation,

    more than half of the subsided land was already submerged

    in water and the fertilized topsoil was lost permanently. The

    manner of reclamation is a kind of post-mining retreatment;

    it leads to a low percentage of farmland reclamation and

    inevitably increases the reclamation cost. Therefore, it is

    necessary to develop a new technology that could take

    measures for advance planning, conservation, and man-agement before land subsidence falls below the water table.

    The improved plan and technology could raise the farmland

    percentage and lower reclamation costs. This research takes

    a colliery located on the eastern plain in China as an

    example, to analyze and simulate subsidence processes

    according to the geological condition and mining system,

    and optimize concurrent mining and reclamation planning.

    Basic information in the study area and research

    methods

    Basic information in the study area

    The study area is located in the northern part of Anhui

    Province in eastern China, covering about 24.1 ha. It is a

    typical plain mining area in eastern China, with flooded

    subsidence lands and densely populated villages. The nat-

    ural elevation is ?30 to ?32 m above mean sea level, with

    an average of   ?31.0 m. The underground water table is

    about 2 m below the soil surface, and the ground is flat

    with a slope of 0–2. The climate is humid continental,

    typical of that of eastern China, with great inter-annual

    variability of precipitation. Most precipitation falls

    between June and September. Because of its humid cli-

    mate, abundant sunshine, and four distinct seasons, it is one

    of the most important grain production areas in China.

    The main coal seams in this area are named nos. 4 and 6,

    with an average thickness of about 2.2 and 2.8 m, res-

    pectively. The buried depths of coal seams are about

    350–450 m and 380–550 m, respectively. The dip angle of 

    coal seams varies from 3   to 15. The overburden has

    a thick alluvial strata reaching 120–160 m, and the

    compaction of soil caused by the loss of water makes the

    subsidence factor reach 0.96 (Table  2). A schematic of a

    typical geological section is shown in Fig. 3.

    The eight panels referring to no. 6 coal seam were

    extracted from March 1997 to the end of 2004 leading to a

    maximum subsidence depth of 2.5 m. The subsided land

    was reclaimed to some fish ponds and farmlands with

    original elevation in 2005. Excavation of the no. 4 coal

    seam commenced in January 2007; four panels were

    included and will last till September 2012. The layout of 

    panels and mining schedule are illustrated in Fig. 4   and

    Table 3. Thus, the influence of the mining activity in the

    study area could be treated as a single coal seam (no. 4)

    extraction. This paper analyzed the dynamic evolution of 

    ground condition and land use to optimize the concurrent

    mining and reclamation.

    Research methods

    Dynamic mining subsidence prediction and geological

    information system (GIS) were used in this paper; the

    process of dynamic scenario simulation was derived

    according to the specific geological condition and mining

    schedule in different stages. Mining subsidence prediction

    Table 2   Basic parameters for surface movement and deformation

    prediction

    Parameters Value

    Coefficient of the initial mining (q) 0.96

    Coefficient of the repeated mining (q0) 1.20

    Horizontal movement coefficient (b) 0.3

    Influence propagation angle tangent (tgb) 1.80The displacement distance (S ) 0.03H0

    Subsidence velocity factor (c) 11.6

    Influence angle (h) 89

    Fig. 3   Schematic of typical geological section in the study area

    Environ Earth Sci (2013) 68:1247–1254 1249

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    4/9

    system (MSPS), developed by China University of Mining

    and Technology, was chosen to analyze the mining impact,

    and Arcinfo, released by Environmental Systems Research

    Institute (ESRI), was chosen for ground analysis and sim-

    ulation. The procedures are as follows:

    1. Acquisition of original terrain data

    According to the information provided by Hengyuan

    colliery, the topographic map surveyed in 2005 by the total

    station was adopted, which contains elevation points and

    isograms.

    2. Acquisition of subsidence information in various

    stages

    After decades of research, some useful theories and

    methods of mining subsidence prediction (Konthe   1959;

    Peng and Luo   1991) such as profile function, influence

    function, and probability integration method have been

    produced. In the recent 30 years, deterministic (mecha-

    nistic) methods including finite element method and

    boundary element method based on rock mechanics were

    presented (Kratzsch  1983). In deterministic modeling, the

    in situ mechanical properties of rocks are of particular

    importance. Probability integration method, developed

    from random medium theory, is the most mature andapplied prediction model in China; the software (MSPS)

    used in this paper was programmed based on this theory.

    Dynamic subsidence prediction was also applied, utilizing

    one of the most widely used time functions proposed by

    Knothe (1959):

     f ð xÞ ¼ 1  ect 

    where   t   is the time that elapsed from the opening of the

    cavity and c  is the subsidence velocity factor, whose value

    depends on the characteristics of the ground and on the

    units in which the time is expressed.

    3. Construction of dynamic ground subsidence model

    Dynamic ground subsidence model can be constructed

    in two phases: raster interpolation and superimposition.

    (a) Raster interpolation

    Interpolation predicts values for cells in a raster from a

    limited number of sample data points. It can be used to

    predict unknown values for any geographic point data:

    elevation, rainfall, chemical concentrations, noise levels,

    and so on. Since the obtained original terrain data and

    dynamic subsidence information in step (1) and step (2)

    were presented as points and isograms, interpolation was

    then adopted by Arcinfo to achieve comprehensive raster

    information. The vector information (points and isograms)

    was converted to raster data format automatically by

    Arcinfo.

    (b) Superimposition

    Superimposition between interpolated raster data of step

    (1) and step (2) could generate a state of ground subsi-

    dence. By using this method, dynamic ground subsidence

    could be produced for different mining stages.

    4. Analysis and monitoring

    The dynamic ground subsidence model for each panel

    and various stages could be determined and analyzed based

    on mining plan. Temporal and spatial dynamic changes of 

    the ground could be monitored, including vertical subsi-

    dence, extent of water area, land use change, slopes, and

    aspects of surface in each mining stage. Virtual reclama-

    tion schemes at different stages were produced. Finally, the

    percentage of restored farmland was considered as the

    preferred standard to optimize the schemes.

    Fig. 4   Layout of no. 4 coal seam workface

    Table 3   Mining schedule of no. 4 coal seam

    Number of 

    panel

    Mining time Average

    depth (m)

    Average seam

    thickness (m)

    452 2007.1–2007.12 280 2.2

    453-1 2009.12–2010.6 280 2.3

    453-s2 2010.11–2011.3 280 2.3

    454 2011.9–2012.9 300 2.0

    455 2008.4–2009.7 250 2.1

    1250 Environ Earth Sci (2013) 68:1247–1254

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    5/9

    Results and analysis

    Scenario simulation

    1. Original terrain data

    The study area is 24.1 ha, with a north–south length of 

    about 1,100 m and east–west width of about 220 m

    (Fig. 5). The surface was roughly flat before extraction of no. 4, with the elevation between 30 and 32 m and slope

    between 0 and 2. The study area was good farmland with

    aquaculture ponds on both sides.

    2. Mining subsidence prediction at various stages

    Prediction of ground subsidence associated with under-

    ground mining based on the shape of the final settlement

    trough of the ground surface could be insufficient. Surface

    subsidence due to mining is a dynamic process which

    obeys mechanical principles (Saids   1995). Particularly,

    dynamic processes of land use change and water ponds

    distribution in temporal and spatial domain could provide amore intuitive and rational vision for the manager and

    engineer in the coal and grain overlap region. Character-

    istics and timing of mining subsidence could be monitored

    through dynamic prediction. The prediction parameters are

    indicated in Table 2.

    In consideration of the mining schedule and layout, the

    study area was divided into four stages as shown below:

    (A) two panels 452 and 455 were mined completely in

    July 2009,

    (B) panels 452, 455, and 453-1 were mined completely in

    September 2010,

    (C) panels 452, 455, 453-1, and 453-2, were mined

    completely in March 2011,

    (D) panels such as 452, 455, 453, and 454 were all mined

    completely in September 2012.

    Movement and deformation at various stages were rep-resented as subsidence isograms and deformation isograms.

    The study area is located in eastern China, a region with

    thick alluvium on the near surface and a high underground

    water table (the groundwater table is 1–3 m below the soil

    surface). According to previous studies, cracks derived

    from deformation have a small influence on the utility of 

    the cultivated land surface. The most significant impacts to

    cultivated land were submergence into water caused by

    vertical subsidence, and soil erosion and deterioration

    caused by additional slope at the edges of the subsidence

    basin (Hu et al.  1997). Therefore, dynamic vertical subsi-

    dence based on temporal and spatial distributions wastreated as a major consideration for scenario simulation.

    3. Scenario simulation at various stages

    Based on the local conditions, the local government set

    the criteria for subsidence damage: the land becomes a

    permanent water area when the vertical subsidence reaches

    2.0 m, and the land becomes a seasonal water area when

    the vertical subsidence reaches 1.5 m. The criteria were

    validated through field measurement in this research, and

    ground elevations of  ?29.0 and  ?29.5 m were defined as

    permanent and seasonal water criteria. These validated

    criteria would benefit temporal and spatial analyses. Thedevelopment of ponding areas at various mining stages is

    subdivided into four stages, as shown in Fig.  6.

    Stage (A) (2007.1–2009.7): Excavation of coal at panels

    452 and 455 were completed. Mining activities only

    reached a super-critical level in strike orientation and were

    sub-critical in inclination orientation because two panels,

    Fig. 5   Pre-mining TIN in the study area

    Fig. 6   Changes of water area at various stages

    Environ Earth Sci (2013) 68:1247–1254 1251

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    6/9

    453 and 454, were not mined. Thus, vertical subsidence on

    the ground was not serious and created no ponding area.

    Stage (B) (2009.8–2010.9): Excavation of panel 453-1.

    In this stage, water rose in the ground and expanded

    gradually until September 2010.

    Stage (C) (2010.9–2011.3): After a slight break, the

    extraction of panel 453-2 made the situation even worse.

    However, the water area, including both perennial and

    seasonal, changed slowly.

    Stage (D) (2011.4–2012.10): Panel 454 was the final

    panel in this mining area. Its excavation led to a severe water

    expansion in the ground, because the mining reached a super-

    critical level both in inclination and strike orientation.

    According to dynamic ground subsidence simulation,

    land use change was analyzed (Fig. 7). (a), (b), (c), and

    (d) correspond to the four mining stages of (A), (B), (C),

    and (D). Although the excavation of panel 452 and 455

    impacted the ground, it did not change the land use because

    there was no water accumulation on the surface (Fig.  8).

    Along with the excavation of panel 453-1, water gradually

    rose in the ground and finally reached 20.6 ha, accounting

    for 85.6 % of the study area; the area of cultivated land

    Fig. 7   Land use changes at various stages on the ground

    Fig. 8   Reclamation layout and

    elevation at various stages

    exception of the stage A without

    reclamation work 

    1252 Environ Earth Sci (2013) 68:1247–1254

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    7/9

    decreased to 3.5 ha, only accounting for 14.4 % of the

    study area. The proportions of cultivated land were 100,

    72.5, 67.3, and 14.4 %, respectively, corresponding to the

    four mining stages. This shows that the excavation of no. 4

    coal seam led to a lot of farmland loss because of water

    accumulation due to mining subsidence.

    Optimization of reclamation plans and analysis

    Dynamic ground scenario simulation provides a vision to

    understand the development of subsidence in the ground.

    If reclamation work was launched after all the mining

    activities had ended, a lower percentage of farmland res-

    toration would be produced because most of the land would

    subside into water and lack of filling materials. Further-

    more, the existence of large areas of water may make the

    reclamation work more difficult and increase reclamation

    costs. Because of submergence of important topsoil into

    water, the reclaimed land might have poor soil condition

    due to lack of topsoil. Therefore, reasonable reclamationtime and the best reclamation plan seem to be particularly

    important in a high underground water table area.

    1. Optimization of reclamation plan

    Following are the basic principles for making a con-

    current mining and reclamation plan:

    (a) Reclamation earthwork adopted ‘‘Digging Deep to

    Fill Shallow’’ technology.

    (b) Filling materials from outside of the study area for

    reclaiming the subsided land were not used.

    (c) Dynamic subsidence prediction for every stages wasadopted and the elevation of reclaimed land at every

    reclamation stage should be rational to ensure that the

    reclaimed land could withstand the impact of follow-

    ing settlements.

    According to the considerations above, different stages

    of mining reclamation measures were taken into account.

    The extraction level of panel 452 and 455 had less impact

    on agriculture in stage (a); therefore, only reclamation in

    stages (b), (c), and (d) was considered. The layout anddesigned elevation are shown in Fig. 8. The percentage of 

    reclaimed farmland reaches 78.3, 73.3 and 40.7 % at the

    stage (b), (c), and (d), respectively.

    2. Result analysis

    Extracting a horizontal layered ore body is a continuous,

    slow, and gradual subsidence process. The manner and

    extent were different in various stages. Table 4  shows the

    advantages, disadvantages, and the reclamation efficiency

    at various stages.

    If reclamation measures were taken too early (stage a),

    the influence of underground extraction would not betransmitted to the ground completely or the effect may not

    be sufficient to interrupt normal agricultural activities. This

    means increased costs and more interruption of agricultural

    activities. The reclamation project needs to accommodate

    subsequent settlement, including vertical subsidence, tilts,

    horizontal deformation and curvatures. Conversely, if rec-

    lamation measures are taken too late (stage d), most of the

    topsoil will sink below the water table and soil resources

    cannot be guaranteed for reclamation. This increases both

    reclamation costs and construction difficulties, and may

    lead to a very low percentage of farmland reclamation and

    poor farmland productivity. Therefore, the most appropri-ate stages would be stage (b) and stage (c), when panel 453

    was under mining. At this stage, the land began to

    Table 4   Optimization and comparison of reclamation plans in various stages

    Stages Mining condition Condition before

    reclamation

    Advantages Disadvantages Percentage

    of reclaimed

    farmland

    (%)

    (a) 452 and 455 Start of subsidence,

    no water area

    Most of the topsoil resources

    available, high percentage

    of reclaimed farmland

    High reclamation costs, occupying

    the land for so long a period

    influences normal agricultural

    work, more residual subsidence

    (b) 452, 455, and 453–1 Water area rise, with

    less area

    More topsoil could be

    protected, high percentage of 

    reclaimed farmland

    High reclamation costs, partial

    residual subsidence influence

    78.3

    (c) 452, 455, and 453 Subsidence increases,

    water area expands,

    but with a low

    proportion

    More topsoil could be

    protected, high percentage of 

    reclaimed farmland

    High reclamation costs, partial

    residual subsidence influence

    73.3

    (d) 452, 455, 453, and

    454

    Most of the area

    submerged into water,

    little farmland exists

    Stable ground, less residual

    settlement exists

    No topsoil resource, low percentage

    of reclaimed land

    40.7

    Environ Earth Sci (2013) 68:1247–1254 1253

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    8/9

    submerge into water and the land reclaimed at this stage

    could save a lot of soil and guarantee high percentage of 

    farmland reclamation.

    Conclusions

    1. Based on mining schedule and geological condition,dynamic scenarios of land subsidence due to coal

    mining are simulated by dynamic subsidence predic-

    tion and spatial analysis for a horizontal layered single

    coal seam. This paper simulated three stages of land

    subsidence caused by underground mining. The failure

    mode, damage area, and degree of damage were ana-

    lyzed quantitatively. The results revealed that: the

    percentage of farmland decreased gradually from 100

    to merely 14.4 % from pre-mining to post-mining due

    to mining subsidence (the four stages correspond to

    100, 72.5, 67.3, and 14.4 %, respectively). If recla-

    mation measures were adopted until the ground sta-bilized, 86.6 % of cultivated land would submerge into

    water and lead to a low percentage of reclaimed

    farmland (40.7 %).

    2. Based on the scenario simulation, a virtual reclamation

    plan was under consideration for three mining stages.

    Farmland reclamation percentages were 78.3, 73.3,

    and 40.7 % corresponding to stage (b), stage (c), and

    (d).

    3. Taking the percentages of reclaimed farmland as the

    preferred standard, the farmland reclamation percent-

    ages at stages (b) and (c) could be increased to 37.6

    and 32.6 %, respectively, compared against delaying

    reclamation until the land stabilizes [stage (d)].

    Consequently, restoring subsided land in stage (b) or

    stage (c) would decrease construction difficulty, pro-

    tect the topsoil maximally, and enhance farmland

    reclamation percentage. The optimum reclamation

    time was at stage (b).

    In summary, research shows that using dynamic subsidence

    prediction with reclamation scenario simulation and taking

    the percentage of reclaimed farmland as the preferred

    standard, the best concurrent mining and reclamation time

    and plan can be obtained.

    Acknowledgments   The research has been supported by nonprofit

    industry research and special funds provided by the Ministry of Land

    and Resources in China, approval no. 200911015-03. The authors

    offer their special thanks for the research and valuable assistance

    provided by Anhui Wanbei Coal Group and Anhui Hengda Ecological

    Construction Engineer Co., Ltd. Special thanks also go to Dr. R.G.

    Darmody (University of Illinois at Urbana-Champaign), Dr. Richard

    Barnhisel (Executive Secretary of American Society of Mining and

    Reclamation), Dr. S.K. Chong (Southern Illinois University at Car-

    bondale) and Mr. Steve Hewitt for their comments and editing.

    References

    Bascetin A (2007) A decision support system using analytical

    hierarchy process (AHP) for optimal environmental reclamation

    of an open-pit mine. Environ Geol 52:663–672

    Bell FG, Donnelly LJ, Genske DD, Ojeda J (2005) Unusual cases of 

    mining subsidence from Great Britain, Germany and Colombia.

    Environ Geol 47:620–631

    Darmody RG (1995) Modeling agricultural impacts of longwall minesubsidence: a GIS approach. Int J Min Reclam Environ 9(2):

    63–68

    Darmody RG, Hetzler RT, Simmons FW (1992) Coal mine

    subsidence: effects of mitigation on crop yields. Int J Min

    Reclam Environ 6(4):187–190

    Hu ZQ (1994a) The technique of reclaiming subsidence areas by use

    of a hydraulic dredge pump in Chinese coal mines. Int J Min

    Reclam Environ 8(4):137–140

    Hu ZQ (1994b) Land reclamation plan for mining subsidence. Mining

    survey 2:134–139

    Hu ZQ (1996) Subsidence land management and reclamation in coal

    mining areas. Coal Industry Press, Beijing

    Hu ZQ, Luo YM (2006) Problems, reasons and countermeasures for

    environmental quality and food safety in the overlapped areas of 

    crop and mineral production. Sci Technol Rev 24(3):93–94Hu ZQ, Hu F, Li JH, Li HX (1997) Impact of coal mining subsidence

    on farmland in eastern China. Int J Min Reclam Environ

    11(2):91–94

    Kim KD, Lee S, Oh HJ, Choi JK, Won JS (2006) Assessment of 

    ground subsidence hazard near an abandoned underground coal

    mine using GIS. Environ Geol 50:1183–1191

    Kim KD, Lee S, Oh HJ (2009) Prediction of ground subsidence in

    Samcheok city, Korea using artificial neural networks and GIS.

    Environ Geol 58:61–70

    Konthe S (1959) Observation of surface movement under influence of 

    mining and their theoretical interpretation. Proc European Congr

    on Ground Movement (Leeds, UK)

    Kratzsch H (1983) Mining Subsidence Engineering. Springer-Verlag,

    Berlin

    Peng SS, Luo Y (1991) Subsidence prediction in Illinois coal basin.In: Proc. 10th Int Conf on Ground Control in Mining, West

    Virginia University, Morgantown, West Virginia, pp 212–219

    Saids I (1995) Dynamic subsidence prediction over longwall mining

    in Abu-Tartur mines. Land Subsidence Proceedings of the

    Fifth International Symposium on Land Subsidence, Egypt,

    pp 161–166

    Wang XZ (2009) Actively respond to challenges of the financial

    crisis, promote healthy and sustainable development of coal

    industry: International Coal Summit 2009 Speech. China Coal

    Industry Association, Beijing

    Wang ZL, Zhang QB, Li R (2009) Study on flood resources

    comprehensive utilization and ecological restoration technology

    of coal mining depressed area. J Nat Resour 24(7):1156–1162

    Wu QY, Pang JW, Qi SZ, Li YP, Han CC, Liu TX, Huang LM (2009)

    Impact of coal mining subsidence on the surface landscape inLongkou city, Shandong Province on China. Environ Earth Sci

    59:783–791

    Xiao W, Hu ZQ, Xu XL, Fu YH (2009) Cost definite method of land

    reclamation in coal mining area. J Coal Sci Eng 35:175–179

    Xiao W, Hu ZQ, Gong BK, Zhang PP, Han B (2011) Visualization of 

    the characteristics of mining subsidence with the consideration

    of topography: a case study in China. Int J Min Miner Eng

    3(1):16–25

    1254 Environ Earth Sci (2013) 68:1247–1254

     1 3

  • 8/16/2019 Optimization of concurrent mining and reclamation plans for single coal seam: a case study in northern Anhui, China

    9/9

    Reproducedwithpermissionof thecopyrightowner. Further reproductionprohibitedwithoutpermission.