OPSM 639, C. Akkan 1 OPSM 639 Project Management Introduction to Microsoft Project - Part 2: Developing a Network Plan

OPSM 639 Project Management

  • Upload
    holt

  • View
    48

  • Download
    0

Embed Size (px)

DESCRIPTION

OPSM 639 Project Management. Introduction to Microsoft Project - Part 2: Developing a Network Plan. Developing a Network Plan. Steps Network Diagram view (AoN network). Customizing Network Diagram view. Identifying critical path(s). Overview Report. Current Activities Report. - PowerPoint PPT Presentation

Citation preview

Page 1: OPSM 639 Project Management

OPSM 639, C. Akkan 1

OPSM 639Project Management

Introduction to Microsoft Project - Part 2: Developing a Network Plan

Page 2: OPSM 639 Project Management

OPSM 639, C. Akkan 2

Developing a Network Plan

• Steps1. Network Diagram view (AoN network).

2. Customizing Network Diagram view.

3. Identifying critical path(s).

4. Overview Report.

5. Current Activities Report.

6. Printing a Gantt chart.

7. Creating a Milestone.

Page 3: OPSM 639 Project Management

OPSM 639, C. Akkan 3

Select “Network Diagram”

Developing an Activity-On-Node (AoN) Project Network

These make upthe summary task. You can hide them by clicking on the minus sign.

Page 4: OPSM 639 Project Management

OPSM 639, C. Akkan 4

Customizing Network Diagram

Right-click on the background, then select “Box Styles”

You may want to see different information on the nodes.

Page 5: OPSM 639 Project Management

OPSM 639, C. Akkan 5

Click “More Templates...”

Customizing Network Diagram

Page 6: OPSM 639 Project Management

OPSM 639, C. Akkan 6

Select “New...””

Customizing Network Diagram

Page 7: OPSM 639 Project Management

OPSM 639, C. Akkan 7

Customizing Network Diagram

1.Give a name to your template

Info: You may folllow the changes in your template

2.You may change the cell layout (# rows & # columns) by clicking this icon.

Page 8: OPSM 639 Project Management

OPSM 639, C. Akkan 8

Customizing Network Diagram

2.Check Showlabel in cell.

1.Select the activity

Property such as

“Late finish”

Page 9: OPSM 639 Project Management

OPSM 639, C. Akkan 9

Identifying the Critical PathCritical path indicated by RED boxes To see the details, move

the pointer on to boxes

Page 10: OPSM 639 Project Management

OPSM 639, C. Akkan 10

Viewing Only the Critical PathSelect Critical

Page 11: OPSM 639 Project Management

OPSM 639, C. Akkan 11

Getting an Overview Report

2.Select “Reports”1.Select “View”

Page 12: OPSM 639 Project Management

OPSM 639, C. Akkan 12

Getting an Overview Report

2.Enter “Select”1.Select

“Overview”

Page 13: OPSM 639 Project Management

OPSM 639, C. Akkan 13

Getting an Overview Report

2.Enter “Select”

1.Select “Project

Summary”

Page 14: OPSM 639 Project Management

OPSM 639, C. Akkan 14

Getting an Overview ReportProject Summary Report

Page 15: OPSM 639 Project Management

OPSM 639, C. Akkan 15

1.From “View” menuSelect “Reports”

2.SelectCurrent Activities

3. Select

Print out ES-LS-EF-LF-Slack Times

Page 16: OPSM 639 Project Management

OPSM 639, C. Akkan 16

1.Select “Unstarted Tasks”

2.Edit...

Print out ES-LS-EF-LF-Slack Times

Page 17: OPSM 639 Project Management

OPSM 639, C. Akkan 17

1.From Table option, select “Schedule”

2. “OK”

Print out ES-LS-EF-LF-Slack Times

Page 18: OPSM 639 Project Management

OPSM 639, C. Akkan 18

1. Choose “Unstarted Tasks”

2. “Select”

Print out ES-LS-EF-LF-Slack Times

Page 19: OPSM 639 Project Management

OPSM 639, C. Akkan 19

Report with ES,LS,EF,LF and Slack

Print out ES-LS-EF-LF-Slack Times

Page 20: OPSM 639 Project Management

OPSM 639, C. Akkan 20

Print out a Gantt Chart

Or alternatively,1.Go to View , then

2. Select Gantt Chart

1.Click on “Gantt Chart”

Page 21: OPSM 639 Project Management

OPSM 639, C. Akkan 21

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Right click mouse,when your pointer is on the timescale

2.Select “Timescale”

Page 22: OPSM 639 Project Management

OPSM 639, C. Akkan 22

Print Out a Gantt Chart:Obtaining A Printable Timescale

2.Select “Months”

1.Click on“Major Scale”

Page 23: OPSM 639 Project Management

OPSM 639, C. Akkan 23

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Click on “Minor Scale”

2.Select “Days”

Page 24: OPSM 639 Project Management

OPSM 639, C. Akkan 24

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Arrange the Size of timescale by increasing or decreasing this number.

You can follow the changes in the timescale by observing this area. 2.Click OK.

Page 25: OPSM 639 Project Management

OPSM 639, C. Akkan 25

Print Out a Gantt Chart

1.Select “Print Preview”

Page 26: OPSM 639 Project Management

OPSM 639, C. Akkan 26

Print out a Gantt Chart - 7

Click on “Page Setup...” to set the printoutput styles

Page 27: OPSM 639 Project Management

OPSM 639, C. Akkan 27

Creating a Milestone

1.Right-click on the activity where you want to put

a milestone.

2.Click on the “New Task”

Page 28: OPSM 639 Project Management

OPSM 639, C. Akkan 28

Creating a Milestone

1.Double-click on this new activity

2.Select Advanced.

Page 29: OPSM 639 Project Management

OPSM 639, C. Akkan 29

Creating a Milestone

3. Check Mark task as milestone.

2. Give zeroduration.

1.Give a name to your milestone

Page 30: OPSM 639 Project Management

OPSM 639, C. Akkan 30

Creating a Milestone

1.Click on Predecessors.

2.Choose necessary activities to link your milestone to the network

Page 31: OPSM 639 Project Management

OPSM 639, C. Akkan 31

Creating a Milestone

NOTE: Pay attention to Predecessors column. When you add any new task these numbers are changed automatically; therefore you do not need to change predecessors of each activity.

Page 32: OPSM 639 Project Management

OPSM 639, C. Akkan 32

Creating a Milestone

1.Select “Network View”.Milestone 1 is in the network.Note that its shape is different from regular activities.

Page 33: OPSM 639 Project Management

OPSM 639, C. Akkan 33

Do NOT forget

to save your file as

<username>-PART2.