14
OPSI Annual Meeting October 13, 2015

OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

Embed Size (px)

DESCRIPTION

3 Problem CP rules virtually eliminate ability of summer demand response (DR) to continue as capacity resources Why? 1.Elimination of Base Capacity in 20/21 2.Performance Criteria – New Measurement & Verification (M&V)

Citation preview

Page 1: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

OPSI Annual Meeting

October 13, 2015

Page 2: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

2

Session 6

Reliability Pricing Model:Are Further Changes Necessary?

Reluctantly…yes

But States should also be thinking beyond RPM

Page 3: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

3

Problem

CP rules virtually eliminate ability of summer demand response (DR) to continue as capacity resources

Why?

1. Elimination of Base Capacity in 20/21 2. Performance Criteria – New Measurement &

Verification (M&V)

Page 4: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

4

Issue #1 – Elimination of Base Capacity

RPM - Limited & Summer Extended DR• Summer peaking system and summer available demand resources Least cost procurement

• Capped total amount

CP through 19/20 - Base Capacity (similar to Limited & Extended Products)

• Summer peaking system and summer available resources Least cost procurement

• Capped total amount

CP 20/21 and beyond – NO Base Capacity• PJM procuring year round for summer peak

Page 5: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

5

ISSUE #2 – M&V

TODAYPeak Load Contribution (PLC)

• Customers billed for capacity based on PLC• DR performance measured relative to PLC

DR customers commit to a Firm Service Level (FSL)• Customer’s level of uninterruptible service• Must drop to that level when dispatched• Customers receive credit for difference between FSL and PLC

Page 6: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

6

ISSUE #2 – M&V

FUTURE UNDER CP• Customers still billed for capacity based on PLC• DR as CP measured against estimate of what customer

would have consumed (i.e. “winter demand” not PLC)• DR as CP participation limited to lesser of summer or

winter capability• Why? – customers must commit to both an FSL (i.e. level of uninterruptible service) AND to reducing load from their winter demand.

• Winter peak often well below summer peak, so most load’s ability to provide DR will be reduced

• This will cause many customers to “leave MWs on the table” in summer, or exit market & peak shave

Page 7: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

7

ISSUE #2 M&V

Example- Customer has 1 MW PLC which sets capacity costs- Customer can reduce to zero in summer, shut down in winter, so already at zero consumption

- Today: Customer can commit to DR, register 1 MW to get to FSL of zero- Hedged capacity costs through interruptible portion of load

- Under CP: Customer can no longer serve as a capacity resource because limited to “lesser of”- Customer not consuming in winter, but still paying for 1 MW of capacity year round

- PJM will have to procure 1 MW of other resources to replace lost customer, even though that 1 MW not needed in winter

Page 8: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

8

IMPACTRange of potential DR that could exit market: 3,300 – 7,600MW.

• 27% of DR from HVAC which can’t perform in the winter• Roughly 3,300 MWs

• 18/19 BRA, only 38% of DR offered as capacity performance • If other 62% doesn’t convert to CP roughly 7,645 MWs of DR lost

• In 18/19 BRA, 6,252 MWs of DR offered as Base Capacity ONLY, no commitment to CP at any price

• Existing “Annual DR,” at its peak represented 68% of DR offers• If 68% switches to CP, remaining 32% (3,547MW) could be lost.• HOWEVER Annual DR subject to different penalties and under

current M&V, so should not expect full 68% to transition to CP

Page 9: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

9

IMPACT

Capacity Cost Impact of Losing 3,330 – 7,600 MWs of DR

• Previous PJM RPM scenario analysis

• Loss of 3,000 MWs of capacity = $946 million to $1.8 billion increase in annual capacity costs

• Loss of 6,000 MWs of capacity = $1.9 - $3.3 billion increase in annual capacity costs

Page 10: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

10

IMPACT

Market Efficiency• RPM no longer least cost alternative to meeting reliability

• Procuring year round for a summer peak

Reliability• 1000s of MWs of customers converting to peak shaving a unique challenge to PJM operators

Economic• Capacity: $1 - $3 Billion above increases already seen in 18/19 BRA

• Energy: Potential increase in uplift because of lost control & transparency of DR that converts to peak shaving

Page 11: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

11

SOLUTIONS

1. Reinstate Base Capacity2. Keep a summer only product, but with CP

penalty structure3. Fix M&V rules so full value of summer

reduction capabilities captured4. Seasonal procurement5. Others?

**Stakeholder Process Before**** 20/21 BRA in May 2017**

Page 12: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

12

Order 745 is the…..

BUT… •Regardless of SCOTUS decision•Regardless of whether DR is wholesale or retail•Regardless of M&V rulesReality is….•Demand response in some form is needed for reliability and efficient market outcomes

For demand response in any form…•Need customer engagement

Page 13: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

13

Changes Outside RPM

To future proof your utilities from…•Whatever happens with Order 745 •Unfavorable DR participation rules•Demand or emission reduction targets•Increasing choices (solar, distributed generation, EE, etc)

Key is…•Customer engagement at all levels

Page 14: OPSI Annual Meeting October 13, 2015. 2 Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be

14

Changes Outside RPM

Successful customer engagement…•Allows customers and utilities to deal with market changes, whether GOOD or BAD

Keys to successful customer engagement…•Provide incentives for utilities to invest in new technology• E.g. cost recovery for investments in energy intelligence software and cloud computing technology