OPERATIONAL PLAN 2016/17
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 1
Operational Plan Performance Report In accordance with the Local Government Regulation 2012 Council is required to prepare and
adopt an annual operational plan for each financial year. The operational plan states how Council
will progress the implementation of the Corporate Plan 2013 – 2018 during the period of the
2015/16 Financial Year.
Performance is reported quarterly through Operational Plan reviews and is monitored to ensure all
tasks and services are on track to be delivered.
Overall, of the 76 measurable items in the four themes, Community, Economy, Environment and
Governance, 2 were completed in the first quarter as at 30 September 2016. Further details are
provided in the below report.
0
5
10
15
20
25
30
Community Economy Environment Governance
Unsatisfactory Marginal Satisfactory Completed Pending
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 2
1.0 COMMUNITY A vibrant, inclusive and healthy community with access to services and facilities which reflect its unique character, role and needs.
Major Initiatives and Key Operational Activities
Unsatisfactory
Marginal
Satisfactory
Pending
Completed
Water Security Strategy – continue implementation of approved strategy
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Three (3) of the four (4) sub-program areas of the Cairns Water Security Strategy are underway. Actions around program supporting projects and the Bahana Mulgrave Water Supply Scheme are well advanced. The Demand Management Program is now progressing and expecting to accelerate. Actions around the Barron River Water Supply Scheme are not yet scheduled to commence.
Demand management education and communications programs – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: • Communication / Marketing “Thrive” Campaign developed and launched in September –
analytics and feedback demonstrate very positive community acceptance • Engaged with James Cook University to initiate plans for further opportunities and program
development • Pilot water education activity developed and trailed at FLEC Day with students / teachers • Community education and engagement workshop event planned for October (NWW)
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 3
Expand Water & Waste alliance with other stakeholders
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The Demand Management Strategy includes an initiative to work with water-related stakeholders. Implemention planning to progress this initiative is under development. Terms of Reference for the Far North Queensland Water Alliance have been developed and are to be presented to the FNQROC board. This alliance is part of the Queensland Water Regional Alliance Program (QWRAP) meeting on at least a quarterly basis. Current initiatves include collaborative discussions with regulating bodies (Department of Environment and Heritage Protection). Cairns Townsville Mackay water alliance continues to progress a number of initiatives including: collaborative approach to design standards and a comprehensive review of benchmarking and operational efficiency opportunities.
Munro Martin Parklands – to be completed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Project Completed.
New Cairns Performance Arts Centre (CPAC) – to be constructed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: 1. Tower Crane Erected 2. State Government budget has provisioned $15m. Federal Government has announced
$10m in funding (National Stronger Regions) 3. Steering Meeting on 13th October to review Project Costs (FAC) and Additional Scope (BOH
changes) 4. Construction Programme; a. Concrete sub-structure complete – November 2016 b. Concrete External walls – Commence November 2016 – early 2017 c. Theatre Seats delivered to site – Mid 2017
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 4
5. Recent unseasonal rain has delayed the works. The Contractor is approximately 34 days behind programme due to weather and other delays (additional asbestos, groundwater)
6. Overall construction progress approximately 10% complete.
Shields Street Heart Project Stage 2 – to be constructed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Construction underway.
Review and prioritise safety improvements for cyclists on roundabouts
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Desktop review complete (#5105865). Blackspot application completed and submitted to Department of Transport and Main Roads for roundabout upgrades ($350K funding 2017/18)
Street lighting upgrades
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Street lighting upgrades completed at Florence Street and Grafton Street (Munro Martin Park). Street lighting upgrades at Spence Street and Abbott Street almost complete. Design commenced for Florence Street between Grafton and Abbott Street (Cairns Acquarium). Lighting to be upgraded at Bunda Street within Council managed area near Cairns Central Shopping Centre. Designs also commenced for upgrade of street lighting at Windarra Street and Varley Street pedestrian crossing. Various Rate 2 street lighting upgrades will be delivered by Christmas – refer #4563789.
Alley Park Sporting Precinct Master Plan – Stage 1 to be completed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Stage 1 practical completion reached.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 5
School of Arts building construction – to be completed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Tenders for fit-out were opened on the 26th August and issued to 5 companies. Tender process is due to be completed in late October.
Cairns Regional Councils 2012/17 Public Art Project Delivery to include: • Shields Street Heart Project – to progress • Edmonton Leisure Centre – Finalise • Indigenous Art Trail (Collins Av Bridge) - commence
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Shields St Heart – Stage 1 nearing completion. Artists and major work have been selected for stage two. Construction has begun. Edmonton Leisure Centre – Work is in progress and due for completion in October and launched in early November. Indigenous Art Trail – No public art opportunities for Collins Ave Bridge in selected design option. Alternative opportunities to be considered.
Mann Street Cycleway – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Project 75% complete. Driveways, tree removal and replacement to be followed by street scaping.
Walker Road Sporting Precinct Stage 2 – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Works well advanced 70% complete. Practical completion expected March 2017. Funding
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 6
Agreement with State finalised. Currently finalising surface works and club amenities building.
Green Space, Our Place Program – 15 volunteer groups under to be initiated
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: 16 new Green Space Groups have been established in the last quarter. Program is proving to be a huge success with it scurrent focus now on establishing a Tracks and Trials Volunteer group.
Develop an improvement plan for the Holloways Beach Foreshore
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: First draft plan established following initial consultation. Further road design needs to be incorporated into the plan over the next 2 months. It is planned to submit a draft to the Executive Team in December and seek Council approval to conduct further community consultation in February 2017.
Gordonvale Library refurbishment – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The Tender stage is complete and Project Launch Approval (PLA) submitted for CEO approval. Commencement of works to be confirmed for mid-November start.
Libraries First 5 Forever Stage 3 – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: First 5 Forever Grant Project is travelling well having formed extensive partnerships for program delivery 16/17. Community programs in place have been successful and improvements made. A full report will be submitted to Council November 2016.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 7
Robotics and Coding Workshops – to be developed and delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Coding and Robotics Grant is progressing well with a team being allocated and staff trained. National Coding Week September events were held in partnership with State Library of Queensland. Sessions have been well received and attended by the community.
Investigate and identify 2 remote locations for self-serve library kiosks
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Scheduled completion third Quarter pending appointment of Libraries Business Strategy position.
Tech Savvy Seniors QLD – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Final Tech Savvy Seniors QLD workshops were delivered in September. Grant funding has been acquitted. The program has been thoroughly successful with bookings and feedback for workshops well received in the community. A full report will be subbmitted to Council November 2016.
Cannon Park Master Plan – to be commenced
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The Steering Committee has been established for the project. Flanagan Consulting Group has been engaged to prepare the master plan.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 8
CairnsPlan 2016 – First Review
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Council resolved to make an amendement to the CairnsPlan 2016 in July 2016. Council sought early feedback from the community and development industry in July and August 2016.
Erosion Prone Area Study – to be prepared to inform amendments to the CairnsPlan 2016
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The Erosion Prone area will be part of the Coastal Hazard Adaptation Strategy which will be commencing in Q2. It is expected that this will be delivered in Q4.
Integrated Transport Study (Light Rail) – Scoping Study – to be commenced
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Discussions held and briefing from Sunshine Coast Council to full Council. Light rail conference attended.
Rectangular Stadium Scoping Study – to be commenced
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Pending, no comment.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 9
Animal Management education and awareness campaign
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Roll-out print, radio, digital and social messaging to address nuisance barking. Design and install of Animal Management vehicle branding continuing with installation expected in the next quarter. Work continuing to deliver community dog walks, building on last year’s events, as well as community workshops to support responsible pet ownership.
New Flood ALERT station and Flood Camera at Freshwater Creek – to be completed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Equipment on order from suppliers. PO received by consultant. Deliver date December 2016.
Resilience Scorecard Project – a resilience framework for understanding our community
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Community survey completed. LDMG Workshops conducted – analysis of results currently underway
Skilling for Work Queensland – recruit and complete 12 traineeships
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Commenced with 11 trainees in July / August 2016 (variation required to contract).
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 10
2.0 ECONOMY A strong, diversified and sustainable regional economy that supports the growth of new and existing industry and business activities whilst enhancing local lifestyle and providing long term employment opportunities.
Major Initiatives and Key Operational Activities
Unsatisfactory
Marginal
Satisfactory
Pending
Completed
Smart Metering / Intelligent Water Network – progress the rollout / trial
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Expression of Interest (EOI) shortlisting and associated workshops are complete. Progress briefing to Executive team and Council Water and Waste Committee was provided in September. Development of the Request for Tender (RFT) document has commenced and is expected to be completed by mid-October.
City Centre Alive – Shields Street Stage 2, CBD footpath renewals and the Suburban Enhancement Program
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Works progressing to schedule on budget.
Cairns CBD Transport Model – to be reviewed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Draft report completed (#5177272), currently being reviewed. Final report expected end of October 2016.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 11
Development of Cultural Tourism Presentation and Promotion Strategy – Cairns Culture on the Map – to progress
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: A new online Cairns Cultur Map facilitating access to information by residetns, tourists and visitors to cultural businesses, organisations, amenities and activities is currently in web development phase and is on track for completion in early 2017.
Develop new Library partnerships to deliver learning and technology workshops across the region
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: This is a work in progress with one professional partner expressing interest for the first quarter 2017.
Local Government Infrastructure Plan – to be finalised
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The State Interest Review has been undertaken and approval to commence public notification has been received subject to compliance with a number of conditions.
Cairns City Centre Master Plan Review – to be commenced
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Council resolved to commence the preparation of the master plan in August 2016. Tender documentation has been prepared and tenders sought in September 2016.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 12
Future of Tropical Economies Conference – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Council has made the decision not to proceed to deliver Future of Tropical Economies Conference in 2016/17.
Innovation Awards – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Award ceremony to be held in November.
Local Area Economic Plans for Babinda and Gordonvale – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Tender documentation has been prepared and tenders sought in September 2016.
TNQ Events Prioritisation Strategy - implementation
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Cairns Action Plan 2015-2020 action items currently being implemented. Key highlights to date include delivery of public facing executive summary document and the establishment of the TNQ Major Events Advisory Group.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 13
3.0 ENVIRONMENT A sustainable, well managed and healthy environment that provides a balance between built infrastructure and the conservation of our world heritage features and natural and cultural resources.
Major Initiatives and Key Operational Activities
Unsatisfactory
Marginal
Satisfactory
Pending
Completed
Waste Management Strategy – Stage 1 to be implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Pre-project planning is underway.
Water Demand Management Strategy – continue implementation
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Implementation Plan underway with high priority for Intelligent Water Network and Smart Water Metering progressing. Emphasis also being given to water conservation with high use consumers. Community consultation to continue.
Waste Transfer Station Master Plan – implement Stage 1
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: ARUP is currently undertaking Stage 1 of the Waste Transfer Station Master Plan consultance. Due for completion in November 2016.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 14
Education Program delivery to schools – Waste and Recycling and Water Conservation
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Seeking to leverage off best practice school education program developed by Gold Coast Water. Adaptation to the tropical environment to be carried out in conjunction with expert educational consultants.
Tree Management Database – to be implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Database being used by Inner City Precinct. Implementation across the region will occur with Cairns Works Maintenance as part of the Tree Management and Maintenance guidelines, which are currently being developed.
Solar powered LED lights installed at boat ramps
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Boat ramp audit completed – refer #5105997 & #5139850. Worksinclude new solar powered light at Machans Beach boat ramp.
LED lights and lanterns used on street lighting and traffic signal projects
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: LED lights being stalled on various recent street lighting projects – e.g. Florence Street and Grafton Street (Munro Martin Park), Spence Street, and on traffic signal upgrade projects – e.g. Grafton / Florence Street intersection.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 15
Cairns Beach Sand Mitigation and Erosion Plan – to be reviewed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: This work has now incorporated into the Coastal Hazard Adaption Study (CHAS), being led by Planning and Environment. Tenders for Stage 1 and 2 of the CHAS have been called.
Collins Avenue Bridge Renewal – to be constructed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Construction underway.
New access from Redlynch Connector Road (Portelli Road) – to be constructed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Road opened to traffic on 4 October 2016. Remaining works include street lighting and landscaping.
Logomeir Road Extension – to be constructed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Works progressing.
Reef Guardian Action Plan 2016/17 – to be prepared
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Draft report is being finalised and will be presented to Council in November.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 16
ECOfiesta and ECOweek 2017 – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Planning underway for event delivery in May 2017.
State of Environment Report 2015/2016 – to be prepared
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Draft report being prepared and will be finalised in December.
Litter Management Plan – to be prepared
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Draft complete. Further consultation being undertaken.
Energy Management Plan – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Report to December Planning and Environment meeting.
Community Sustainability Grants 2016/2017 - to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Grants underway and will be presented to Council in December.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 17
2016 Asbestos Audit – to be completed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: 98% complete, completion of physical aud anticipated end of November.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 18
4.0 GOVERNANCE An efficient organisation providing best practice service delivery through leadership and policy making and the effective management of people, assets and finances.
Major Initiatives and Key Operational Activities
Unsatisfactory
Marginal
Satisfactory
Pending
Completed
Deliver a balanced budget and sustainable long term financial plans
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: 2016/17 Budget adopted by Council on 27 June 2016 with balanced budget through forecast period.
Achieve milestones laid out in the Connected Customers Program which will see the staged delivery of improved online services for our customers
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Design for MyCairns app progressing to plan. Community Wi-Fi proposal approved by eTeam, will be tabled at Council in November.
Mobility Program which will see the staged implementation of improved tools for employees in the field to increase productivity – to be implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Mobile devices deployed to outdoor workers. CRM app for staff deployed for trial. Further device and app roll-out planned for Q2. Requirements for ‘mobile work mgt’ solution complete; solution design underway. Planning for ‘mobile smart forms’ will commence Q2.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 19
Customer Request Management Processes – to be reviewed and implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Customer Request Mmanagement (CRM) process review project on track and achieving desired goals. CRM refresher training for Permit Compliance and Local Laws Compliance has been conducted. Permit Compliance CRM processes have been reviewed and implemented and Local Laws Compliance processes have been reviewed and new processes in final stages of testing. Review of Water and Wastewater processes currently being completed.
Project Management Framework – to be implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Project Management Framework Phase 1 completed and training provided to relevant staff.
Manunda Library – new lease to be negotiated
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Lease negotiations to commence 2nd and 3rd Quarter due to Lease expory May 2017.
Sustainable digitisation plan for the significant library collections – to be developed and delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: This project will progress upon the appointment of the Business Strategy position currently in the recruitment process.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 20
Comprehensive Community Safety Model – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Preliminary draft developed. Draft framework presented to Acting CEO and General Managers. Further work requested before submitting a final draft to the Executive Team in December. Proposed to put to Council in December 2016.
Cairns Regional Council Heritage Presentation, Promotion and Conservation Program to include:
• ANZAC Centenary Trail – to be delivered • World War Two Command Centre / Scout Hat – to commence • Cairns Regional Gallery CMP Implementation Strategy – to progress
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: ANZAC Centenary Trail research and graphic design completed and project launch on 25 November. Project brief for CMP and Interpretive plan for WW11 Command Centre complete awaiting confirmation of site handover. Maintenance and conservation of Cairns Regional Gallery ongoing and on track.
Strategic Plans • Corporate Plan 2017-2022 – to be completed • Cairns Regional Council Four Year Cultural Plan & Cultural Services – to be
delivered • Community Development Framework – to be developed • Parks & Leisure Strategic Plan – to be revised • Council’s Cycling and Pedestrian Strategy – to be reviewed • Libraries 4 year Strategic Business Plan 2016-2020 – to be developed • Water and Waste’s Strategic Plan – to be implemented • Learning and Organisational Development Business Plan – to be developed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 21
Comments: Corporate Plan 2017-2022 – Benchmarking has been conducted on other Corporate Plans. The survey results from OurCairns are being analysed to be used in the development of the Corporate Plan. Cairns Regional Council Culture Strategy – Discussion paper has been distributed to arts and cultural organisations with face-to-face consultation currently underway. Library Strategic Plan is pending and will be developed in line with Council’s Corporate Plan to ensure critical elements are captured. The current Plan is under review. Community Development Framework completed and endorsed. Parks, Leisure and Community Development Strategic Plan will not commence until the completion of the Corporate Plan. Cycling and Pedestrian Strategy currently in the review phase. Water and Waste Strategic Plan initial rollout with staff has occurred. Quarterly monitoring currently being developed. Further implementation to follow. Learning and Organisational Development Plan has been drafted and is currently being workshopped across Council.
Sugarworld Waterpark – new lease to be finalised
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Project completed. Contract awarded to Belgravia Leisure.
Manual handling training to Councils high risk manual handling areas – to be implemented
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Not commenced.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 22
Annual Training and Excellence Awards – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Training and Excellence Awards date has been set for 22nd November 2016. Nominations are currently being received by Learning and Organisational Development team. Nominations close 26 October 2016.
Legislative compliance framework – to be developed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Review of the capabilities of the LGAQ framework system are being investigated with analysis to begin into the sections of legislation applicable to Cairns Regional Council.
Our Cairns Community Engagement project – to be undertaken
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: The Our Cairns project was undertaken throughout August and September with 6446 people responding to the community survey, and two forums undertaken attended by 100 residents and 90 key stakeholders which yielded hundreds of ideas for consideration in the Corporate Plan. The results of the surveys and workshops will be presented to council at a workshop on 7 November
Negotiate Councils 2012 Enterprise Bargaining Agreement under the framework of 2016 Award Structure when released
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Negotiations have not yet commenced. Interim Award has been released but negotiations have not yet commenced. Final Modern Award release expected to be in November.
OPERATIONAL PLAN 2016 – 2017
1st Quarterly Reporting
#5056825 P a g e | 23
Workplace Health and Safety ‘Safety Circle’ training program – to be delivered
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Phase 1 of the supervisors training has been rolled out with catch up sessions to be completed on 18 Oct. Employees sessions and phase 2 of the Supervisors training will be rolled out over the period 18 Oct – 4 Nov 16.
Voice of the Customer Program – to be reviewed
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Comments: Review has not been initiatied as yet. Scheduled to start in November 2016.