Upload
vikas-razdan
View
222
Download
0
Embed Size (px)
Citation preview
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
1/96
sgb s.ganesh babu.
OPERATION AND
MAINTENANCE OFSUB - STATIONS.
BY
S.GANESH BABU.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
2/96
sgb s.ganesh babu.
MAINTENANCE PHILOSOPOHY OFSUBSTATION EQUIPMENTS
In today's competitive market scenario power utilities areunder tremendous pressure to cut down their maintenancecosts as they form a significant portion of the operationcosts. This has led the utilities to adopt condition-basedmaintenance of the equipments rather than usual
preventive maintenance being carried out at a fixed interval
of time.
TYPES OF MAINTENANCE
Different types of maintenance being done on equipmentsare:
i) Breakdown maintenanceii) Preventive maintenance
iii) Condition based monitoringiv) Reliability centered maintenance
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
3/96
sgb s.ganesh babu.
Breakdown Maintenance
As the name implies the maintenance is carried outwhen the equipment fails. This type of maintenancemay be appropriate for low value items. However forcostly substation equipments, it is not desirable to waittill the breakdown of the equipment, as this costs more
to the utility as well as the availability and reliability ofpower gets affected. The revenue loss due to non-availability of the system shall be much more than thecost of the failed equipment. Therefore identifying thedefect before failure, is more appropriate to plan repair/ replacement.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
4/96
sgb s.ganesh babu.
Preventive Maintenance
The preventive maintenance of equipment is beingmostly adopted by almost all the utilities. In this type ofmaintenance, the equipments are inspected at a pre-determined period. The frequency determined based onthe past experience and also guidance from themanufacturer of the equipment. This type ofmaintenance would require specific period of shut-
down. Maintenance procedure, periodicity ofmaintenance and formats for maintaining records forvarious types of sub-station equipments have beendiscussed separately in detail in a separate section.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
5/96
sgb s.ganesh babu.
Condition Based Monitoring
This type of maintenance technique is adoptedto assess the condition of the equipment. Thecondition of the equipment is assessed based on
different condition monitoring tests. Some ofthe tests are done on on-line and some are doneon off-line. However, this type of maintenance
would need sophisticated testing equipmentsand skills for analyzing the test results.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
6/96
sgb s.ganesh babu.
Reliability Centered Maintenance
This is the recent technique being adopted inmaintenance philosophy. The basic objectives ofreliability-centered maintenance are:
- Maintenance should keep the equipment at desiredlevel of performance
- Optimizing / minimizing the maintenance /shutdown period so as to enhance the availability of the
equipment.
- Deferring / avoiding the replacement of components
and major/minor over-hauls till it is absolutely
necessary.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
7/96
sgb s.ganesh babu.
GENERAL REQUIREMENTS
Preventive maintenance shall be performed at a levelthat assures that the unscheduled outage performance ofCustomer owned equipment is at least as good as that ofthe TOs system to which it is connected.
Each facility owner shall have an established anddocumented program for the maintenance of allequipment critical to the reliable operation of the bulkpower system.
Maintenance programs can vary in range from strictadherence to manufacturers recommendations to RCM(reliability centered maintenance), as appropriate, butshould reflect Good Utility Practice.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
8/96
sgb s.ganesh babu.
Maintenance of equipment shall be
performed such that the facility owner is ableto support any local interconnectionagreements. Loss of a piece of equipment dueto lack of sufficient maintenance can lead to
unnecessary higher operating costs andunnecessarily long outage time, consequentlycompromising transmission reliability.
Additionally, the maintenance of systemspare equipment must not be overlooked.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
9/96
sgb s.ganesh babu.
Substation equipment shall be maintained byqualified personnel in accordance with applicable
industry standards and Good Utility Practice
Incorrect operation of equipment or equipment
failure should be thoroughly investigated anddocumented to determine the root cause of the
problem. Failures of equipment that adverselyimpact the transmission System should be
investigated in collaboration with the affectedtransmission owners.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
10/96
sgb s.ganesh babu.
EQUIPMENT AND FACILITIES
Equipment diagnostic tools and tests can beutilized in the evaluation of the need forrequired maintenance. Examples include
dielectric testing and analysis, breaker timingthermo-graphy scans, and acoustic monitoring.The facility owners plan should be clear as tothe application, as appropriate, of these
diagnostic tools. Pass/fail ranges and testingintervals should be well documented.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
11/96
sgb s.ganesh babu.
Thermo graphy scanning should be incorporated ininspections.
It is a non-contacting operation, which is applied to in-service equipment while energized and carrying load.Problems are detected either as a function of excessive
temperature rise (such as a poor connection) or asubnormal temperature (such as a cool transformerradiator fin signifying a blocked passage).
Frequency of operation should also be factored into thedetermination of maintenance periodicity. Trending ofequipment performance versus maintenance should beused to re-evaluate maintenance intervals.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
12/96
sgb s.ganesh babu.
For equipment under warranty all required maintenance tomaintain warranty should be performed. It is suggestedthat equipment performance be reviewed prior to warrantyexpiration.
Maintenance of equipment should include diagnostics,overhauls and painting as required to maintain systemintegrity. Attention should be given to both the mechanicaland the electrical aspects of the equipment beingmaintained. Use of incorrect lubricants can adversely affectequipment performance.
Adequate spare parts should be kept on hand to supportmaintenance.
Manufacturers service bulletins must be acted upon in atimely manner.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
13/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
14/96
sgb s.ganesh babu.
The failures in power transformers can be
broadly classified as:
specification, design / manufacturing
deficiency
Installation / operation / maintenancedeficiency
Adverse operating conditions
Aging.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
15/96
sgb s.ganesh babu.
The country wide statistics:-
Design defect 35.7% Manufacturing Problems 28.6%
Material defect 13.1%
Transport and storage
problems 1.2% Incorrect Maintenance 4.8%
Abnormal over load.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
16/96
sgb s.ganesh babu.
Adverse operating conditions
The life of a transformer is normally dependent on
the life of insulation. The rate of ageing is related
to temperature, moisture content and duration of
loading conditions.
Life expectancy of transformer will get diminished
through inadequate protection while operating inthe abnormal conditions such as:
Sustained overload conditions
Switching surges Lightning surges
Transferred surges
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
17/96
sgb s.ganesh babu.
Improper maintenance practices.
Poor / inadequate maintenance in the areas of oilleakage, oil quality, critical accessories such as tapchangers, bushings, protective instruments etc.
will cause trouble in transformer. In addition to
this, there are various trouble-shooting problemsencountered in the field, such as moisture,oxidation, solid contamination, gas bubbles, overcurrent, over voltage (transient or dynamic), over
temperatures, short circuit (mechanical forces)etc., for which sufficient care should be taken tosafeguard the transformer. Preventive maintenanceis strongly recommended to improve the reliability
of transformer.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
18/96
sgb s.ganesh babu.
Suggestions to reduce failures.
Improved design and manufacturing practice
By adopting CAD and better shop floormanagement, more reliable units could bemanufactured to eliminate:
Poor short circuit withstand capability Manufacturing defects including cooling system
Problems associated with bushings
OLTC including selector/diverter switch Tertiary winding failure wherever provided
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
19/96
sgb s.ganesh babu.
Improved testing method
Transformer should be simulated to actual servicecondition first by sequential testing and then passingnecessary current which could result into temperature
rise. Thereafter conduction of all high voltageapplication tests could bring out insulation weakness.Simulated short circuit test if necessary on scaled modeland measurement of magnetic balance and
magnetization current could reveal abnormality.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
20/96
sgb s.ganesh babu.
Problems external to transformer:
Load management
By adopting efficient load frequency management systemscould be better controlled avoiding damages andtransformer failure due to:
Overloading
Over fluxing and over voltage Hot joints and spark over Frequent feeder tripping due to reflected faults.
Failure of switchgear and battery:
This could be avoided by periodic testing and using properduty switch-gear and battery.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
21/96
sgb s.ganesh babu.
Permissible limits for transformers for transformers.
A. Transformer
oila) BDV
- At the time of
first charging
600 kV (Gap2.5 mm)
Minimum
IS1866
- During O&M 50 kV (Gap2.5 mm)
Minimum
IS1866
b) Moisture
content
- At the time of
first charging
15 PPM (Max.) IS1866
- During O&M 25 PPM (Max.) -do-
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
22/96
sgb s.ganesh babu.
Permissible limits for transformers
c) Resistivity at 90
degree C
0.1-1012
Ohm-CM (Min.) IS - 1866
d) Acidity 0.2 mg KOH/gm (Max.) - do -
e) IFT at 27 degree C 0.018 N/M (Min.) IS1866
f) Tan delta at 90 degree
C
0.20 (Max.) -do-
g) flash point 126 Deg. C (Min.) -do-
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
23/96
sgb s.ganesh babu.
Permissible limits for transformers
B) Vibration level for
reactors
200 Microns (Peak to Peak)
60 Microns (Average)
C) Tan delta for bushing
at 20 Deg. C
0.007* IEC137
D) Capacitance forbushing + 5% variation
E) IR value for winding 1000 M-Ohm By 5.0/10.0 kV
Megger
F) Tan delta for windings
at 20 Deg. C
0.007* IEEE/C57.12.
90.1980
G) Contact resistance of
bushing terminal
connectors
10 M. Ohm / Connector NGC.UK
Recomme
ndations
H) Turret Neutral CT
ratio erros
+ 39 IS2705
T
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
24/96
sgb s.ganesh babu.
Preventive Maintenance schedule for TransformersS.No.
Tasks assigned Shut Down (SD)Or
Without Shut
Down(WSD)
Periodicity
a. Checking of bushing oil level WSD Monthly
b. Checking of oil level in
Conservator
WSD Monthly
c. Checking of oil level in OLTCConservator
WSD Monthly
d. Checking of cooler oil pumpsand fans
i) Manual actuation WSD Monthly
ii) Auto Starting SD Yearly
e. Checking of oil leaks WSD Monthly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
25/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Transformerscontd
f. Checking condition of Silicagel in breather andregeneration if required
WSD Monthly
g. Measurement of BDV of oil WSD HalfYearly
h. Testing of oil for DGA andother oil parameters
WSD HalfYearly
i. Checking/Topping up of oillevel in oil seal ofbreather
WSD In caseof
requirement
j. Vibration measurements(for Shunt Reactors only)
WSD HalfYearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
26/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Transformerscontdk. Measurement of BDV of
OLTC oilSD Yearly
l. Tan d measurement forBushings SD Yearly
m. i) IR!measurement ofWindings (PolarisationIndex and DA+ Ratio)
SD In 3Years
**
ii) Tan d measurement ofWindings SD In 3
Years**
iii) Measurement ofWindings resistance
SD In 3Years
**
iv) Measurement ofwindings ratio
SD If needed
v) Measurement of short
circuit Impedance
SD If needed.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
27/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Transformerscontd
n. External cleaning ofRadiators
SD Yearly
o. Cleaning of all Bushings SD Yearly
p. Frequency ResponseAnalysis
SD If Reqd.
q. Maintenance of OLTCdriving mechanism
SD Yearly
r. Checking of all remoteindications (STI and Tapposition indicator)
SD Yearly
s. Electrical checking /testing of pressure reliefdevice, Buchholz relay,OLTC surge Relay andchecking/Replacement
of the gaskets of theterminal box
SD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
28/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Transformerscontd
t. Checking/testing ofBuchholz relay byinjecting air or nitrogen
SD Yearly
u. Marshalling boxes ofICT/Reactor of:
SD Yearly
i) Cleaning of Marshallingboxes of ICT/Reactor
and OLTC
SD Yearly
ii) Tightening ofterminations
SD Yearly
iii) Checking of contactors,
space heaters,illumination etc.
SD Yearly
v. Checking and Cleaning ofDiverter Contacts
SD SOS (50,000
Opera
tions)
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
29/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Transformerscontd
w. Checking of oil level andcalibration of OTI, WTI
SD Yearly
x. Filteration /Replacement of Oilof OLTC SD In case ofrequireme
nt
y. Filteration / Degassing of maintank radiator oil
SD In case ofrequireme
nt
z. Testing of bushing CTs.
i) IR valve SD SOS
* Water content, BDV, SP, Resistance, Tan d, IFT.Total Acidity, 2-Furfuraldehyde etc.
** First time after one year from commissioningand then once in every three years.
+ Di-electric Absorption Ratio
! To be measured as per the followingcombinations:
N/E, N/LV and LV/E.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
30/96
sgb s.ganesh babu.
FAILURE OF CIRCUIT BREAKERS
A circuit breaker is considered to have failed,when the breaker fails to operates after acommand is given or unable to interrupt the arcor withstand a system voltage.
interrupting chambers
pre-insertion resistor chambers
grading capacitors
support column including tie/operatingrods
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
31/96
sgb s.ganesh babu.
Dielectric failure inside interrupting chamber due to highmoisture in SF6 gas.
Insulation failure (live to earth) due to accumulation ofmoisture on tie rod during storage.
Failure of mechanical coupling between tie rod andoperating mechanism.
Failure of actuating valves in operating mechanism.
Failure due to foreign particles (eye pieces) insideinterrupter.
Failure due to high transient recovery voltage (TRV).
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
32/96
sgb s.ganesh babu.
Preventive Measures for Avoiding CB
Failures:
Introduction of state-of-the-art condition monitoring checks duringservice such as
Dynamic contact resistance measurement
Dew point measurement of SF6 gas. Contact travel measurement
Operating timings
Tan delta measurement of grading capacitors
Trip/close coil currents measurement
SF6 gas/hydraulic oil/air leakage monitoring.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
33/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
34/96
sgb s.ganesh babu.
Failure of CVTs
Preliminary failure analysis of failed CVTs have revealedthat main reasons of CVT failures are:
High value of tan delta Secondary voltage abnormal
High value of capacitance
Oil leakage Humming sound.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
35/96
sgb s.ganesh babu.
Besides the above following problems werealso observed in one make of CVT:
Snapping of bellow connection
Burning of damping resistor
Burning/failure of lightning arrestor Failures of capacitor stacks
Blackening of insulating oil in EMU tank
The only remedial measures suggested to avoidfailures is to do the proper condition monitoringchecks of CVTs at site.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
36/96
sgb s.ganesh babu.
FAILURES OF SURGE ARRESTORS
Analysis of failure of surge arrestors haverevealed failures mostly due to prematuredegradation of ZnO discs. To minimize the
failure of surge arrestors it is suggested thatsurge arrestors are monitored online forpresence of third harmonic resistive current in
the leakage current flowing through surgearrestors. Leakage current up to 500 micro Ampis generally considered within acceptable limits.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
37/96
sgb s.ganesh babu.
MAINTENANCE TECHNIQUES
The maintenance techniques to be adoptedshould meet the following criteria:
Field staff should be able to carry out such tests
and interpret the test results Testing procedure to be evolved after detailed
discussions with the supplier of the equipmentand testing equipment
written procedure to be made available to theoperating staff
Preventive maintenance schedule for surge arrestors
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
38/96
sgb s.ganesh babu.
Preventive maintenance schedule for surge arrestors
Sl.
No
Tasks assigned Shut down /
without shut
down
periodicity
1. Checking of leakage
current, 3rdharmonic
resistive current
WSD Yearly.
2. Testing of counters SD Yearly
3. Cleaning of LA insulator SD Yearly.
4. Measurement of
capacitance and tan
delta.
SD Yearly.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
39/96
sgb s.ganesh babu.
GENERAL CHECKS / MAINTENANCE INSPECTION
The equipment should be inspected at the regular intervalas per the guidelines. In addition the manufacturerguidelines should also be followed. The general checksnormally required to be done are:
General cleaningCleansing of all insulators ofCB/CT/CVT/Isolators for salt/dirt deposition, if any.
Dust protectioneven though the operating mechanismare made of steel and surface treated, still some rusting maytake place. If any rust stains are observed the same may becleaned with emery paper and paint the same against therust protection. For protection against rust, grease G ortectyl 506 is suggested.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
40/96
sgb s.ganesh babu.
Tightness checkAt the time of first
inspection, all bolted joints on thebreaker and operating mechanism shallbe tightened up. All the wiring joints inthe terminal box of the operating
mechanism shall be re-tightened at theregular intervals. Re-tightening has to berepeated only after bigger overhauls. Any
SF6 gas leakage has to be detected withsuitable gas leak detector.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
41/96
sgb s.ganesh babu.
LubricationBearings of the breaker andoperation mechanism of isolators and breaker
are to be lubricated with grease G after majoroverhauls.
Treatment of gasketsAny gasket opened onceshould be replaced by new one. All sealingsurfaces and O-rings shall be sparsely greased ofappropriate type for better sealing against this
surface and at the same time providingprotection against rusting/corrosion.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
42/96
sgb s.ganesh babu.
Treatment of contact surfaces
Copper surfaces should be cleaned and madeoxide / sulphate free. If required, to be cleanedwith cloth and solvent (Trichloroethane) or steel
brushing. After steel brushing, the surface needto be cleaned for loose particles and dust withthe dry cloth / solvent (Trichloroethane)
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
43/96
sgb s.ganesh babu.
Silver contact surfaces if required to becleaned, the same to be done with soft
cloth and solvent (Trichloroethane).Steel brushing or grinding is notpermitted.
Aluminum contact surfaces should becleaned with steel brush and emerycloth. Afterwards, clean it with dry
cloth and apply a thin layer ofpetroleum jelly.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
44/96
sgb s.ganesh babu.
Moving contact surfaces:Silvered: Cleaned if necessary, with soft clothand solvent (tri-chloro ethane). No steelbrushing.
Non silvered: Cleaned as silvered surfaces, canbe steel brushed. After steel brushing they shall
be thoroughly cleaned from loose particles anddust.
Lubrication: Lubricant - Grease K is applied in a
very thin layer on the surfaces of the movingcontact and the puffer cylinder. The superfluousgrease is carefully removed.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
45/96
sgb s.ganesh babu.
CONDITION BASED MONITORINGTECHNIQUESCIRCUIT BREAKERS
Operating timings measurement Contact resistance measurement Contact travel measurement Dew point measurement of SF6 gas/air
Tan delta measurement of grading capacitors Vibration measurement Operational lock-out checks Trip/close coil current measurement SF6 gas/hydraulic oil Air leakage monitoring SF6 gas leakage test
P i ibl li i f CB
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
46/96
sgb s.ganesh babu.
Permissible limits for CBsA ).Dew point of SF6
gas
Dew point values as per Annexure
II
B) Dew point ofoperating air
-45 Deg. C at ATM. Pressure
C) CB Operating
timings
400 kV 220 kV
a) Closing time(Max.) 150 MS 200 MS
b) Trip time (Max.) 25 MS 35 MS
c) Close/trip time,
Pole discrepancy
Phase to Phase
(Max.)
3.33 MS 3.33 MS
- Break to break
(Max.) of same
2.5 MS 2.5 MS
Dew point values
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
47/96
sgb s.ganesh babu.
Dew point values.BHEL -15 -36 At the time of
commissioning
-7 -29 During O&M
-5 -27 Critical
M&G -- -39 At the time of
commissioning
-32 During O&M
CGL -15 -35 At the time ofcommissioning
-10 -31 During O&M
ABB -15 -35 At the time of
commissioning-5 -26 During O&M
NGEF -15 -36 At the time of
commissioning
-7 -29 During O&M
-5 -27 Critical
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
48/96
sgb s.ganesh babu.
Note:Dew point of SF6 gas varies with
pressure at which measurement is carried out.So it is to be ensured that if measurement isdone at pressure other than atmospheric
pressure, it needs to be converted to theatmospheric pressure as given.
Ci it B k ti d
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
49/96
sgb s.ganesh babu.
Circuit Breakers continued
D) PIR time
BHEL make 12-16 MS ManufacturersRecommen
dations
CGL make 8-12 MS
ABB make 8-12 MS -do-
NGEF make 8-12 MS
M&G make 8-12 MS
TELK make 8-12 MS
ABB make (HVDC) 8-12 MS
B k td
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
50/96
sgb s.ganesh babu.
Breakers contdE) PIR opening time
prior to opening
of main contacts
(ABB, CGL,
NGEF make CBs)
5 MS (Min.) at rated
pressure
F) Pir and main
contacts overlap
time [BHEL,
M&G, ABB(imported) make
CBs]
5 MS (Min.) at rated
pressure
G) Tan delta of
grading
capacitors
0.007 at 20 Deg. C
H) Capacitance of
gradingcapacitors
Within + 10% / - 5%
of the rated value
IEC 358
I) Contact
resistance of CB
150 M. Ohm
J) Contact
resistance of CB
terminal
connector
10 M. Ohm per
connector
NGC, UK
recommendations
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
51/96
sgb s.ganesh babu.
Breakers Contd
K) IR value:
1. Phaseearth 1000 M Ohm (Min.) by
5.0 / 10.0 kV Megger
2. Across open
contacts
1000 M Ohm (Min.) by
5.0/10.0 kV Megger
3. Control cables 50 M Ohm (Min.) by 0.5
kV Megger
B k i d
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
52/96
sgb s.ganesh babu.
Breakers continued
L) Pressure switch
settings
- SF6 gaspressure
switches
Within + 0.1 Bar of setvalue
- Operating air
pr. Switches
Within + 0.1 Bar of set
value
- Operating oil
pr. Switches
Within + 1.0 Bar of set
value
M) BDV of oil used
for MoCB
- At the time offilling
40 kV at 2.5 mm Gap(Min.)
Mfgs.Recommendation
- During O&M 20 kV at 2.5 mm Gap.
(Min.)
Mfgs.
Recommendation
Preventive Maintenance schedule for Circuit
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
53/96
sgb s.ganesh babu.
Breakers
S.No. Tasks assigned Shut Down
(SD) OrWithout
Shut Down
(WSD)
Periodi
city
A. SF6 CIRCUIT BREAKERS
a. Checking of SF6 gas pressures
(wherever pr. Gauges provided)
WSD Monthly
b. Checking of oil leaks from Grading
Capacitors
SD Monthly
c. SF6 gas leakage test SD Yearly
d. Dew Point measurement of SF6 gas SD 2 Yearly@
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
54/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
55/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
56/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Circuit Breakers
B. AIR BLAST CIRCUIT
BREAKERS
a. Checking breaker air pressure WSD Monthly
b. Air (Pressure) Leakage check WSD Monthly
c. Dew Point Measurement of
operating air at the outlet of Air
Drier
WSD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
57/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Circuit Breakers
C. MOCBs
a. Checking for oil leakage/oil
level
WSD monthl
y
b. Testing of oil for BDV WSD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
58/96
Preventive Maintenance schedule for Circuit Breakers
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
59/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Circuit Breakers
e. Functional checks, duty cycle
operation including rapid re-
closing (0-0 3s-CO)
SD Yearly
f. Checking of all operation lock-
outs
SD Yearly
g. Checking of all interlocks SD Yearly
h. Checking of pressure settings SD Yearly
i. Cleaning of Breaker Interrupter,Support insulators, PIRs and
Grading Capacitors
SD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
60/96
Preventive Maintenance schedule for Circuit Breakers
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
61/96
sgb s.ganesh babu.
Preventive Maintenance schedule for Circuit Breakers
F. CONTROL CABINET
a. Checking of tightness of all cable
terminations in MB
SD Yearly
b. Checking of door sealing gasket
and replacement thereof, if
necessary
WSD Yearly
c. Repainting of metallic surfaces (ifrequired)
WSD Yearly
d. Checking of space heater WSD Yearly
@ At time of commissioning then after 6 months and one & halfyears of commissioning and thereafter once in every twoyears.
* For All HV/EHV Circuit Breakers only** For 400 kV BHEL, CGL make CBs only
+ First time after one year from commissioning and then once inevery three years.
M i t T h i f I t t
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
62/96
sgb s.ganesh babu.
Maintenance Techniques for Instrument
Transformer
Instrument transformers are generally the most reliableEHV network equipment. However, violentfailure/blasting due to primary insulation of instrument
transformers may lead to considerable damage tonearby equipments and O&M personals. In order toavoid violent failures following maintenance techniqueshave been adopted like measurement of tan delta and
capacitance, insulation measurements, DGAmonitoring, recovery voltage measurement etc.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
63/96
sgb s.ganesh babu.
Tan Delta and Capacitance Measurement
(CT/CVT)
Testing mode for CTs: CTs provided with test stepshave to be tested in UST mode whereas CT with test
step are to be tested in GST mode. Before carryingout the test it may be ensured that jumpers aredisconnected and CT/CVT porcelene housing /insulators are thoroughly cleaned.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
64/96
sgb s.ganesh babu.
Testing mode for CVTs:
HF panel and neutral terminal of EMU transformerare to be disconnected and isolated from groundbefore carrying out the test. The testing kit which is
similar as used for grading capacitors for CB is to beconnected between HV/HF points andmeasurements are done in UST mode. In the eventof test values deviating from the base values,
individual capacitor stacks are to be tested in USTmode.
Secondary Winding Resistance (CTs)
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
65/96
sgb s.ganesh babu.
Secondary Winding Resistance (CTs)Testing procedure
After ensuring, necessary precautions have been taken,connect leads of O meter between different terminals ofCT secondary course. Select the range of O meter as per
pre-commissioning / factory test results. Followingprecautions are considered essential:
Test links should be open in the CT MB prior tomeasurement of secondary resistance
It should be ensured that associated CTs are not incharged condition. For example main and tie CTs for
differential relays should not be in charged condition. Any earth provided in the secondary circuit of CT should
be removed prior to measurement.
Secondary voltage measurement for CVTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
66/96
sgb s.ganesh babu.
Secondary voltage measurement for CVTs
Failure of capacitor elements in C1 or C2 sideresults in change in output voltage. Regular andclose monitoring of secondary voltages using 0.2
or 0.5 accuracy class multi meters, secondaryvoltage change can be monitored. If voltage of aparticular phase CVT drifts by more than + 1volts, it requires thorough investigation.
P i ibl li it f CT
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
67/96
sgb s.ganesh babu.
Permissible limits for CTsA) IR value
1. Primary
earth 1000 M
Ohm (Min.) by5.0/10.0 kV Megger
2. Secondaryearth 50 MOhm (Min.) by 0.5 kV
Megger
3. Control cables 50 M-Ohm (Min.) by 0.5 kVMegger
B) Tan delta value 0.007*at 20 Deg. C
C) Terminal Connector 10 M-Ohm per connector NGC, UK
Recomme
ndations
D) CT ratio errors + 3% - Protection cores IS2705
+ 1% - Metering cores -do-
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
68/96
Preventive maintenance schedule of CTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
69/96
sgb s.ganesh babu.
Preventive maintenance schedule of CT s
e. CT ratio test SD If needed
f. DGA and testing of other parameters
of oil
SD If needed
g. Thermo - vision Scanning of CT and
Top dome
WSD Yearly
h. Checking of Bellow Expansion WSD Monthly
i. Visual inspection CT for oil leakage
and crack in Insulator etc.
WSD Monthly
Preventive maintenance schedule of CTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
70/96
sgb s.ganesh babu.
MARSHALLING BOX
a. Checking of oil leakage WSD Monthly
b. Checking of healthiness of gaskets WSD Monthly
c. Checking of space heater &
Illumination
WSD Yearly
d. Checking the tightness of all
connections including earthing
SD Yearly
e. Cleaning of marshalling box and
junction box
* First time after one year from
commissioning and then once in every
three years.
SD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
71/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
72/96
Preventive Maintenance Schedule for CVTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
73/96
sgb s.ganesh babu.
Preventive Maintenance Schedule for CVT s
VISUAL CHECKING OF
EARTHING HF POINTa. Visual checking of earthing HF point
(in case it is not being used for
PLCC)
SD Yearly
b. Checking for any breakage or cracks SD Yearly
c. Checking of oil leaks WSD Monthly
d. Cleaning of CVT capacitor stacks
and tightness of terminalconnections
SD Yearly
e. Capacitance and Tandmeasurement
CVT
SD Once in 3
years
Preventive Maintenance Schedule for CVTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
74/96
sgb s.ganesh babu.
Preventive Maintenance Schedule for CVTs
f. Measurement of voltage atmetering points in control
Room
WSD Monthly
g. Testing of EMU tank oil for
BDV
SD Once in
6
years
h. Thermo - vision Scanning of
Capacitor stacks
WSD Yearly
Preventive Maintenance Schedule for CVTs
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
75/96
sgb s.ganesh babu.
Preventive Maintenance Schedule for CVT s
MARSHALLING BOX
a. Checking of spacer heater &
Illumination
WSD Yearly
b. Checking and tightness of all
connections including earth
connections
SD Yearly
c. Cleaning of marshalling box
and junction box
SD Yearly
d. Checking of healthiness ofgaskets SD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
76/96
Table 14Comparison of Gas Limits
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
77/96
sgb s.ganesh babu.
Table 14. Comparison of Gas Limits
Gas
Dobble 95% Norm
PPM
IEEE Limits
PPM
Hydrogen 511 200
Methane 134 100
Ethane 26 30
Ethylene 17 30
Acetylene 0.6 1
CO 1,749 3,000CO2 15,485 30,000
Total
Combustibles2,024 3,360
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
78/96
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
79/96
sgb s.ganesh babu.
OLTC MAINTENANCESCHEDULE
I nsp. I nspection check Remarks.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
80/96
sgb s.ganesh babu.
freq Item
Dail
y
Digital
counter onthe driving
mechanism
No. of tap
changingOpns.
Conducted.
Records the cumulative no. of Opns
carried out .
Tap changerconservator
Oil level. If low, top up new tested oil. If level
goes up without adding oil, report to
the manufacturer.
ExplosionVent.
Diaphragm
Plate.
Replace if cracked or broken.
Space heater
in the driving
mechanism
---- Heater to be switched on, if ambient
temp. goes below 20 deg C, and
switched off when exceeds 30 deg C
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
81/96
sgb s.ganesh babu.
yrly
or
every
5000
Opns.
Oil inthe
divertor
switch
BDVof
Oil.
Replace or filter if BDV is lessthan 24 KV,at gap 2.5mm between
spheres of 12.7mm(IS:335).
Increase inspection frequency, if
oil deteriorates faster.
yearly Gasket Joints. Oil Leak Tighten the bolts evenly or replace
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
82/96
sgb s.ganesh babu.
the gaskets.
yearly O rings in thebevel gear box
Oil leak Replace O rings if leak isobserved. Dip the O rings in
transformer oil before use.
Yearly Universal joints
and otherdriving Shaft
parts.
--- Apply Grease to prevent rusting.
Use servo Gem EP2, or anyequivalent.
Yearly Gas vent on theconservator
--- Clean if clogged with carbon orDust particles.
Yearly Gas and oiloperated relay
Correct
working
Rectify defects if any.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
83/96
sgb s.ganesh babu.
Yearly Aux. Relay andcontactors.
Rusting of core, dirt on
contacts, chattering etc.,Clean or
replace.
Yearly Timer relays Time settings Adjust if the
values are
disturbed.
Yearly Control CableConnections.
For loose connections at
relay, rotary and push
button switches, Hand
operation and interlockswitch, Motor, Aux.
Transformer, TB terminals
Tighten the
connections.
yearly Lubricating
i
Low oil level. Add or Replace oil.
I N 68 (Bh H d l 68
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
84/96
sgb s.ganesh babu.
in
the gear box
of driving
mechanism.
Iso No.68,(Bharat Hydrol 68
BP, Enklo 68HP, Servo
System 68, I.O.C Perfecto 68
Castrol)
Yearly Electrical
DrivingMechanism
More than 2 Meg
ohms,measured
at 20 deg C with
500 volt meggar.
Low meggar value calls for
investigation and rectify.
Yearly Feed back
data
---- To be given to the
manufactureras per his proforma.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
85/96
sgb s.ganesh babu.
50,000
operations or 5
years since
commissioning,
which ever is
earlier.
Divertor
Switch
Contact
compartment
Thickness
of Arcing
contacts.
Replace all the contacts if
thickness of any one of the
arcing tips is reduced to 2mm.
To be done in the presence of
authorized company rep.
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
86/96
sgb s.ganesh babu.
Every 10years Tap Selector Electric discharges on thesurface of insulators,condition of fasteners,
moving and stationery
contacts, smooth operation of
a gears and other moving
parts.
Report tomanufacturer if any
thing abnormal is
observed.
Battery and Battery Charger
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
87/96
sgb s.ganesh babu.
Following test may be carried out for determining thehealth of battery/battery charger.
Capacity test/discharge test of battery bank
Measurement of impendence of battery cell
Checking of electrolyte level and topping up with DMwater
Checking of emergency DC lighting to control room
Checking of electrical connection of charger panel fortightness and cleaning
Checking of electrical connection of battery for tightness
Checking of tightness of all electrical connection of DCdistribution board
Preventive Maintenance Schedule for Isolatorsand Earth Switches
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
88/96
sgb s.ganesh babu.
and Earth SwitchesS. No. Tasks assigned Shut Down (SD) Or
Without Shut
Down (WSD)
Periodicity
A. Operating Mechanism
a. Linkages including transmission gears SD Yearly
b. Stopper bolts SD Yearly
c. Cleaning of auxiliary switch contact &
greasing with silicon grease
SD Yearly
d. Lubrication of operating mechanism,hinges, lock joints on levers,
bearings
SD Yearly
e. Checking of all mounting bolts for
tightness
WSD Yearly
Preventive Maintenance Schedule for Isolators and Earth Switches
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
89/96
sgb s.ganesh babu.
B. MAIN CONTACTS
a. Cleaning and lubrication ofmain controls
SD Yearly
b. Alignment SD Yearly
c. Main contact resistancemeasurement
SD Once in2 yrs.
d. Tightness of bolds, Nuts and
pins etc.
SD Yearly
e. Cleaning of support insulators
and checking of insulator
cracks, if any
SD Yearly
Preventive Maintenance Schedule for Isolators and Earth Switches
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
90/96
sgb s.ganesh babu.
C. EARTH SWITCH
a. Checking and Alignment ofearthing blades
SD Yearly
b. Cleaning of contacts SD Yearly
c. Contact resistance SD Yearly
d. Operation of earthing switch SD Yearly
e. Checking of alumunium Copper
flexible conductor
SD Yearly
f. Checking of earth connections of
structure and MOM box
SD Yearly
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
91/96
PREVENTIVE MAINTENANCESCHEDULE
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
92/96
sgb s.ganesh babu.
FOR WAVE TRAPS
S.No.
Tasks assigned Shut Down(SD) Or
Without Shut
Down (WSD)
Periodicity
a. Tightness & Cleanliness SD Yearly
b. General inspection / cleaning of
tuning unit
SD Yearly
A PROCEDURE FOR FILLING OF
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
93/96
sgb s.ganesh babu.
EQUIPMENT FAILURE REPORT (EFR)
Whenever there is a failure of any equipment or part of anyequipment during operation and maintenance which may
result in the outage of the said equipment the EFR is
required to be filled up.
Each failure report has to be given a specific report numberfollowed by the name of the sub-station / serial number of
the failed equipment and date of failure.
Time of occurrence of equipment failure or noticing of
failed equipment also to be written. Mention to be made as to when the fault was discovered i.e.
during testing, commissioning, operation and
maintenance.
Name of the main equipment which has failed may be
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
94/96
sgb s.ganesh babu.
given along with the name of the manufacturer / supplier /
sub-vendor.
Specify the type of faulty unit/equipment as given by themanufacturer for example in breakers it could be SF6
3AT3/3AT2; SF6 HPL, ABCB DLF 245 NC2 etc.
Specify the item designation i.e. bay name in which faulty
equipment was erected / located, including the Sr. No. /Badge Number as given on the name plate.
Specify the faulty component in the unit and the part
number as per the O&M manual of the manufacturer
Specify the type of failure i.e. burnt / flashover / mal-operation / mechanical fault / open circuit / short circuit /
operating error / setting etc.
Specify short / brief description of occurrence off l d h f
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
95/96
sgb s.ganesh babu.
fault and cause thereof
Specify the remedial action taken.
Specify the reference of the document from which
part number / fault diagnosis has been done, so
that it may help in analysis of fault.
Equipment failure may occur during tripping /due to suspected fault / mal-functioning of some
other equipment. Report number therefore to be
specified.
The above documents should be signed by themaintenance engineer and counter signed by the
substation in -charge.
Th k
8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909
96/96
Thank you,
Wish you all a successfulprofessional career