Operation and Maintenance of Sub - Stations Revised 030909

Embed Size (px)

Citation preview

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    1/96

    sgb s.ganesh babu.

    OPERATION AND

    MAINTENANCE OFSUB - STATIONS.

    BY

    S.GANESH BABU.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    2/96

    sgb s.ganesh babu.

    MAINTENANCE PHILOSOPOHY OFSUBSTATION EQUIPMENTS

    In today's competitive market scenario power utilities areunder tremendous pressure to cut down their maintenancecosts as they form a significant portion of the operationcosts. This has led the utilities to adopt condition-basedmaintenance of the equipments rather than usual

    preventive maintenance being carried out at a fixed interval

    of time.

    TYPES OF MAINTENANCE

    Different types of maintenance being done on equipmentsare:

    i) Breakdown maintenanceii) Preventive maintenance

    iii) Condition based monitoringiv) Reliability centered maintenance

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    3/96

    sgb s.ganesh babu.

    Breakdown Maintenance

    As the name implies the maintenance is carried outwhen the equipment fails. This type of maintenancemay be appropriate for low value items. However forcostly substation equipments, it is not desirable to waittill the breakdown of the equipment, as this costs more

    to the utility as well as the availability and reliability ofpower gets affected. The revenue loss due to non-availability of the system shall be much more than thecost of the failed equipment. Therefore identifying thedefect before failure, is more appropriate to plan repair/ replacement.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    4/96

    sgb s.ganesh babu.

    Preventive Maintenance

    The preventive maintenance of equipment is beingmostly adopted by almost all the utilities. In this type ofmaintenance, the equipments are inspected at a pre-determined period. The frequency determined based onthe past experience and also guidance from themanufacturer of the equipment. This type ofmaintenance would require specific period of shut-

    down. Maintenance procedure, periodicity ofmaintenance and formats for maintaining records forvarious types of sub-station equipments have beendiscussed separately in detail in a separate section.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    5/96

    sgb s.ganesh babu.

    Condition Based Monitoring

    This type of maintenance technique is adoptedto assess the condition of the equipment. Thecondition of the equipment is assessed based on

    different condition monitoring tests. Some ofthe tests are done on on-line and some are doneon off-line. However, this type of maintenance

    would need sophisticated testing equipmentsand skills for analyzing the test results.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    6/96

    sgb s.ganesh babu.

    Reliability Centered Maintenance

    This is the recent technique being adopted inmaintenance philosophy. The basic objectives ofreliability-centered maintenance are:

    - Maintenance should keep the equipment at desiredlevel of performance

    - Optimizing / minimizing the maintenance /shutdown period so as to enhance the availability of the

    equipment.

    - Deferring / avoiding the replacement of components

    and major/minor over-hauls till it is absolutely

    necessary.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    7/96

    sgb s.ganesh babu.

    GENERAL REQUIREMENTS

    Preventive maintenance shall be performed at a levelthat assures that the unscheduled outage performance ofCustomer owned equipment is at least as good as that ofthe TOs system to which it is connected.

    Each facility owner shall have an established anddocumented program for the maintenance of allequipment critical to the reliable operation of the bulkpower system.

    Maintenance programs can vary in range from strictadherence to manufacturers recommendations to RCM(reliability centered maintenance), as appropriate, butshould reflect Good Utility Practice.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    8/96

    sgb s.ganesh babu.

    Maintenance of equipment shall be

    performed such that the facility owner is ableto support any local interconnectionagreements. Loss of a piece of equipment dueto lack of sufficient maintenance can lead to

    unnecessary higher operating costs andunnecessarily long outage time, consequentlycompromising transmission reliability.

    Additionally, the maintenance of systemspare equipment must not be overlooked.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    9/96

    sgb s.ganesh babu.

    Substation equipment shall be maintained byqualified personnel in accordance with applicable

    industry standards and Good Utility Practice

    Incorrect operation of equipment or equipment

    failure should be thoroughly investigated anddocumented to determine the root cause of the

    problem. Failures of equipment that adverselyimpact the transmission System should be

    investigated in collaboration with the affectedtransmission owners.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    10/96

    sgb s.ganesh babu.

    EQUIPMENT AND FACILITIES

    Equipment diagnostic tools and tests can beutilized in the evaluation of the need forrequired maintenance. Examples include

    dielectric testing and analysis, breaker timingthermo-graphy scans, and acoustic monitoring.The facility owners plan should be clear as tothe application, as appropriate, of these

    diagnostic tools. Pass/fail ranges and testingintervals should be well documented.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    11/96

    sgb s.ganesh babu.

    Thermo graphy scanning should be incorporated ininspections.

    It is a non-contacting operation, which is applied to in-service equipment while energized and carrying load.Problems are detected either as a function of excessive

    temperature rise (such as a poor connection) or asubnormal temperature (such as a cool transformerradiator fin signifying a blocked passage).

    Frequency of operation should also be factored into thedetermination of maintenance periodicity. Trending ofequipment performance versus maintenance should beused to re-evaluate maintenance intervals.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    12/96

    sgb s.ganesh babu.

    For equipment under warranty all required maintenance tomaintain warranty should be performed. It is suggestedthat equipment performance be reviewed prior to warrantyexpiration.

    Maintenance of equipment should include diagnostics,overhauls and painting as required to maintain systemintegrity. Attention should be given to both the mechanicaland the electrical aspects of the equipment beingmaintained. Use of incorrect lubricants can adversely affectequipment performance.

    Adequate spare parts should be kept on hand to supportmaintenance.

    Manufacturers service bulletins must be acted upon in atimely manner.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    13/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    14/96

    sgb s.ganesh babu.

    The failures in power transformers can be

    broadly classified as:

    specification, design / manufacturing

    deficiency

    Installation / operation / maintenancedeficiency

    Adverse operating conditions

    Aging.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    15/96

    sgb s.ganesh babu.

    The country wide statistics:-

    Design defect 35.7% Manufacturing Problems 28.6%

    Material defect 13.1%

    Transport and storage

    problems 1.2% Incorrect Maintenance 4.8%

    Abnormal over load.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    16/96

    sgb s.ganesh babu.

    Adverse operating conditions

    The life of a transformer is normally dependent on

    the life of insulation. The rate of ageing is related

    to temperature, moisture content and duration of

    loading conditions.

    Life expectancy of transformer will get diminished

    through inadequate protection while operating inthe abnormal conditions such as:

    Sustained overload conditions

    Switching surges Lightning surges

    Transferred surges

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    17/96

    sgb s.ganesh babu.

    Improper maintenance practices.

    Poor / inadequate maintenance in the areas of oilleakage, oil quality, critical accessories such as tapchangers, bushings, protective instruments etc.

    will cause trouble in transformer. In addition to

    this, there are various trouble-shooting problemsencountered in the field, such as moisture,oxidation, solid contamination, gas bubbles, overcurrent, over voltage (transient or dynamic), over

    temperatures, short circuit (mechanical forces)etc., for which sufficient care should be taken tosafeguard the transformer. Preventive maintenanceis strongly recommended to improve the reliability

    of transformer.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    18/96

    sgb s.ganesh babu.

    Suggestions to reduce failures.

    Improved design and manufacturing practice

    By adopting CAD and better shop floormanagement, more reliable units could bemanufactured to eliminate:

    Poor short circuit withstand capability Manufacturing defects including cooling system

    Problems associated with bushings

    OLTC including selector/diverter switch Tertiary winding failure wherever provided

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    19/96

    sgb s.ganesh babu.

    Improved testing method

    Transformer should be simulated to actual servicecondition first by sequential testing and then passingnecessary current which could result into temperature

    rise. Thereafter conduction of all high voltageapplication tests could bring out insulation weakness.Simulated short circuit test if necessary on scaled modeland measurement of magnetic balance and

    magnetization current could reveal abnormality.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    20/96

    sgb s.ganesh babu.

    Problems external to transformer:

    Load management

    By adopting efficient load frequency management systemscould be better controlled avoiding damages andtransformer failure due to:

    Overloading

    Over fluxing and over voltage Hot joints and spark over Frequent feeder tripping due to reflected faults.

    Failure of switchgear and battery:

    This could be avoided by periodic testing and using properduty switch-gear and battery.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    21/96

    sgb s.ganesh babu.

    Permissible limits for transformers for transformers.

    A. Transformer

    oila) BDV

    - At the time of

    first charging

    600 kV (Gap2.5 mm)

    Minimum

    IS1866

    - During O&M 50 kV (Gap2.5 mm)

    Minimum

    IS1866

    b) Moisture

    content

    - At the time of

    first charging

    15 PPM (Max.) IS1866

    - During O&M 25 PPM (Max.) -do-

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    22/96

    sgb s.ganesh babu.

    Permissible limits for transformers

    c) Resistivity at 90

    degree C

    0.1-1012

    Ohm-CM (Min.) IS - 1866

    d) Acidity 0.2 mg KOH/gm (Max.) - do -

    e) IFT at 27 degree C 0.018 N/M (Min.) IS1866

    f) Tan delta at 90 degree

    C

    0.20 (Max.) -do-

    g) flash point 126 Deg. C (Min.) -do-

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    23/96

    sgb s.ganesh babu.

    Permissible limits for transformers

    B) Vibration level for

    reactors

    200 Microns (Peak to Peak)

    60 Microns (Average)

    C) Tan delta for bushing

    at 20 Deg. C

    0.007* IEC137

    D) Capacitance forbushing + 5% variation

    E) IR value for winding 1000 M-Ohm By 5.0/10.0 kV

    Megger

    F) Tan delta for windings

    at 20 Deg. C

    0.007* IEEE/C57.12.

    90.1980

    G) Contact resistance of

    bushing terminal

    connectors

    10 M. Ohm / Connector NGC.UK

    Recomme

    ndations

    H) Turret Neutral CT

    ratio erros

    + 39 IS2705

    T

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    24/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for TransformersS.No.

    Tasks assigned Shut Down (SD)Or

    Without Shut

    Down(WSD)

    Periodicity

    a. Checking of bushing oil level WSD Monthly

    b. Checking of oil level in

    Conservator

    WSD Monthly

    c. Checking of oil level in OLTCConservator

    WSD Monthly

    d. Checking of cooler oil pumpsand fans

    i) Manual actuation WSD Monthly

    ii) Auto Starting SD Yearly

    e. Checking of oil leaks WSD Monthly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    25/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Transformerscontd

    f. Checking condition of Silicagel in breather andregeneration if required

    WSD Monthly

    g. Measurement of BDV of oil WSD HalfYearly

    h. Testing of oil for DGA andother oil parameters

    WSD HalfYearly

    i. Checking/Topping up of oillevel in oil seal ofbreather

    WSD In caseof

    requirement

    j. Vibration measurements(for Shunt Reactors only)

    WSD HalfYearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    26/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Transformerscontdk. Measurement of BDV of

    OLTC oilSD Yearly

    l. Tan d measurement forBushings SD Yearly

    m. i) IR!measurement ofWindings (PolarisationIndex and DA+ Ratio)

    SD In 3Years

    **

    ii) Tan d measurement ofWindings SD In 3

    Years**

    iii) Measurement ofWindings resistance

    SD In 3Years

    **

    iv) Measurement ofwindings ratio

    SD If needed

    v) Measurement of short

    circuit Impedance

    SD If needed.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    27/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Transformerscontd

    n. External cleaning ofRadiators

    SD Yearly

    o. Cleaning of all Bushings SD Yearly

    p. Frequency ResponseAnalysis

    SD If Reqd.

    q. Maintenance of OLTCdriving mechanism

    SD Yearly

    r. Checking of all remoteindications (STI and Tapposition indicator)

    SD Yearly

    s. Electrical checking /testing of pressure reliefdevice, Buchholz relay,OLTC surge Relay andchecking/Replacement

    of the gaskets of theterminal box

    SD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    28/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Transformerscontd

    t. Checking/testing ofBuchholz relay byinjecting air or nitrogen

    SD Yearly

    u. Marshalling boxes ofICT/Reactor of:

    SD Yearly

    i) Cleaning of Marshallingboxes of ICT/Reactor

    and OLTC

    SD Yearly

    ii) Tightening ofterminations

    SD Yearly

    iii) Checking of contactors,

    space heaters,illumination etc.

    SD Yearly

    v. Checking and Cleaning ofDiverter Contacts

    SD SOS (50,000

    Opera

    tions)

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    29/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Transformerscontd

    w. Checking of oil level andcalibration of OTI, WTI

    SD Yearly

    x. Filteration /Replacement of Oilof OLTC SD In case ofrequireme

    nt

    y. Filteration / Degassing of maintank radiator oil

    SD In case ofrequireme

    nt

    z. Testing of bushing CTs.

    i) IR valve SD SOS

    * Water content, BDV, SP, Resistance, Tan d, IFT.Total Acidity, 2-Furfuraldehyde etc.

    ** First time after one year from commissioningand then once in every three years.

    + Di-electric Absorption Ratio

    ! To be measured as per the followingcombinations:

    N/E, N/LV and LV/E.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    30/96

    sgb s.ganesh babu.

    FAILURE OF CIRCUIT BREAKERS

    A circuit breaker is considered to have failed,when the breaker fails to operates after acommand is given or unable to interrupt the arcor withstand a system voltage.

    interrupting chambers

    pre-insertion resistor chambers

    grading capacitors

    support column including tie/operatingrods

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    31/96

    sgb s.ganesh babu.

    Dielectric failure inside interrupting chamber due to highmoisture in SF6 gas.

    Insulation failure (live to earth) due to accumulation ofmoisture on tie rod during storage.

    Failure of mechanical coupling between tie rod andoperating mechanism.

    Failure of actuating valves in operating mechanism.

    Failure due to foreign particles (eye pieces) insideinterrupter.

    Failure due to high transient recovery voltage (TRV).

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    32/96

    sgb s.ganesh babu.

    Preventive Measures for Avoiding CB

    Failures:

    Introduction of state-of-the-art condition monitoring checks duringservice such as

    Dynamic contact resistance measurement

    Dew point measurement of SF6 gas. Contact travel measurement

    Operating timings

    Tan delta measurement of grading capacitors

    Trip/close coil currents measurement

    SF6 gas/hydraulic oil/air leakage monitoring.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    33/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    34/96

    sgb s.ganesh babu.

    Failure of CVTs

    Preliminary failure analysis of failed CVTs have revealedthat main reasons of CVT failures are:

    High value of tan delta Secondary voltage abnormal

    High value of capacitance

    Oil leakage Humming sound.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    35/96

    sgb s.ganesh babu.

    Besides the above following problems werealso observed in one make of CVT:

    Snapping of bellow connection

    Burning of damping resistor

    Burning/failure of lightning arrestor Failures of capacitor stacks

    Blackening of insulating oil in EMU tank

    The only remedial measures suggested to avoidfailures is to do the proper condition monitoringchecks of CVTs at site.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    36/96

    sgb s.ganesh babu.

    FAILURES OF SURGE ARRESTORS

    Analysis of failure of surge arrestors haverevealed failures mostly due to prematuredegradation of ZnO discs. To minimize the

    failure of surge arrestors it is suggested thatsurge arrestors are monitored online forpresence of third harmonic resistive current in

    the leakage current flowing through surgearrestors. Leakage current up to 500 micro Ampis generally considered within acceptable limits.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    37/96

    sgb s.ganesh babu.

    MAINTENANCE TECHNIQUES

    The maintenance techniques to be adoptedshould meet the following criteria:

    Field staff should be able to carry out such tests

    and interpret the test results Testing procedure to be evolved after detailed

    discussions with the supplier of the equipmentand testing equipment

    written procedure to be made available to theoperating staff

    Preventive maintenance schedule for surge arrestors

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    38/96

    sgb s.ganesh babu.

    Preventive maintenance schedule for surge arrestors

    Sl.

    No

    Tasks assigned Shut down /

    without shut

    down

    periodicity

    1. Checking of leakage

    current, 3rdharmonic

    resistive current

    WSD Yearly.

    2. Testing of counters SD Yearly

    3. Cleaning of LA insulator SD Yearly.

    4. Measurement of

    capacitance and tan

    delta.

    SD Yearly.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    39/96

    sgb s.ganesh babu.

    GENERAL CHECKS / MAINTENANCE INSPECTION

    The equipment should be inspected at the regular intervalas per the guidelines. In addition the manufacturerguidelines should also be followed. The general checksnormally required to be done are:

    General cleaningCleansing of all insulators ofCB/CT/CVT/Isolators for salt/dirt deposition, if any.

    Dust protectioneven though the operating mechanismare made of steel and surface treated, still some rusting maytake place. If any rust stains are observed the same may becleaned with emery paper and paint the same against therust protection. For protection against rust, grease G ortectyl 506 is suggested.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    40/96

    sgb s.ganesh babu.

    Tightness checkAt the time of first

    inspection, all bolted joints on thebreaker and operating mechanism shallbe tightened up. All the wiring joints inthe terminal box of the operating

    mechanism shall be re-tightened at theregular intervals. Re-tightening has to berepeated only after bigger overhauls. Any

    SF6 gas leakage has to be detected withsuitable gas leak detector.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    41/96

    sgb s.ganesh babu.

    LubricationBearings of the breaker andoperation mechanism of isolators and breaker

    are to be lubricated with grease G after majoroverhauls.

    Treatment of gasketsAny gasket opened onceshould be replaced by new one. All sealingsurfaces and O-rings shall be sparsely greased ofappropriate type for better sealing against this

    surface and at the same time providingprotection against rusting/corrosion.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    42/96

    sgb s.ganesh babu.

    Treatment of contact surfaces

    Copper surfaces should be cleaned and madeoxide / sulphate free. If required, to be cleanedwith cloth and solvent (Trichloroethane) or steel

    brushing. After steel brushing, the surface needto be cleaned for loose particles and dust withthe dry cloth / solvent (Trichloroethane)

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    43/96

    sgb s.ganesh babu.

    Silver contact surfaces if required to becleaned, the same to be done with soft

    cloth and solvent (Trichloroethane).Steel brushing or grinding is notpermitted.

    Aluminum contact surfaces should becleaned with steel brush and emerycloth. Afterwards, clean it with dry

    cloth and apply a thin layer ofpetroleum jelly.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    44/96

    sgb s.ganesh babu.

    Moving contact surfaces:Silvered: Cleaned if necessary, with soft clothand solvent (tri-chloro ethane). No steelbrushing.

    Non silvered: Cleaned as silvered surfaces, canbe steel brushed. After steel brushing they shall

    be thoroughly cleaned from loose particles anddust.

    Lubrication: Lubricant - Grease K is applied in a

    very thin layer on the surfaces of the movingcontact and the puffer cylinder. The superfluousgrease is carefully removed.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    45/96

    sgb s.ganesh babu.

    CONDITION BASED MONITORINGTECHNIQUESCIRCUIT BREAKERS

    Operating timings measurement Contact resistance measurement Contact travel measurement Dew point measurement of SF6 gas/air

    Tan delta measurement of grading capacitors Vibration measurement Operational lock-out checks Trip/close coil current measurement SF6 gas/hydraulic oil Air leakage monitoring SF6 gas leakage test

    P i ibl li i f CB

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    46/96

    sgb s.ganesh babu.

    Permissible limits for CBsA ).Dew point of SF6

    gas

    Dew point values as per Annexure

    II

    B) Dew point ofoperating air

    -45 Deg. C at ATM. Pressure

    C) CB Operating

    timings

    400 kV 220 kV

    a) Closing time(Max.) 150 MS 200 MS

    b) Trip time (Max.) 25 MS 35 MS

    c) Close/trip time,

    Pole discrepancy

    Phase to Phase

    (Max.)

    3.33 MS 3.33 MS

    - Break to break

    (Max.) of same

    2.5 MS 2.5 MS

    Dew point values

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    47/96

    sgb s.ganesh babu.

    Dew point values.BHEL -15 -36 At the time of

    commissioning

    -7 -29 During O&M

    -5 -27 Critical

    M&G -- -39 At the time of

    commissioning

    -32 During O&M

    CGL -15 -35 At the time ofcommissioning

    -10 -31 During O&M

    ABB -15 -35 At the time of

    commissioning-5 -26 During O&M

    NGEF -15 -36 At the time of

    commissioning

    -7 -29 During O&M

    -5 -27 Critical

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    48/96

    sgb s.ganesh babu.

    Note:Dew point of SF6 gas varies with

    pressure at which measurement is carried out.So it is to be ensured that if measurement isdone at pressure other than atmospheric

    pressure, it needs to be converted to theatmospheric pressure as given.

    Ci it B k ti d

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    49/96

    sgb s.ganesh babu.

    Circuit Breakers continued

    D) PIR time

    BHEL make 12-16 MS ManufacturersRecommen

    dations

    CGL make 8-12 MS

    ABB make 8-12 MS -do-

    NGEF make 8-12 MS

    M&G make 8-12 MS

    TELK make 8-12 MS

    ABB make (HVDC) 8-12 MS

    B k td

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    50/96

    sgb s.ganesh babu.

    Breakers contdE) PIR opening time

    prior to opening

    of main contacts

    (ABB, CGL,

    NGEF make CBs)

    5 MS (Min.) at rated

    pressure

    F) Pir and main

    contacts overlap

    time [BHEL,

    M&G, ABB(imported) make

    CBs]

    5 MS (Min.) at rated

    pressure

    G) Tan delta of

    grading

    capacitors

    0.007 at 20 Deg. C

    H) Capacitance of

    gradingcapacitors

    Within + 10% / - 5%

    of the rated value

    IEC 358

    I) Contact

    resistance of CB

    150 M. Ohm

    J) Contact

    resistance of CB

    terminal

    connector

    10 M. Ohm per

    connector

    NGC, UK

    recommendations

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    51/96

    sgb s.ganesh babu.

    Breakers Contd

    K) IR value:

    1. Phaseearth 1000 M Ohm (Min.) by

    5.0 / 10.0 kV Megger

    2. Across open

    contacts

    1000 M Ohm (Min.) by

    5.0/10.0 kV Megger

    3. Control cables 50 M Ohm (Min.) by 0.5

    kV Megger

    B k i d

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    52/96

    sgb s.ganesh babu.

    Breakers continued

    L) Pressure switch

    settings

    - SF6 gaspressure

    switches

    Within + 0.1 Bar of setvalue

    - Operating air

    pr. Switches

    Within + 0.1 Bar of set

    value

    - Operating oil

    pr. Switches

    Within + 1.0 Bar of set

    value

    M) BDV of oil used

    for MoCB

    - At the time offilling

    40 kV at 2.5 mm Gap(Min.)

    Mfgs.Recommendation

    - During O&M 20 kV at 2.5 mm Gap.

    (Min.)

    Mfgs.

    Recommendation

    Preventive Maintenance schedule for Circuit

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    53/96

    sgb s.ganesh babu.

    Breakers

    S.No. Tasks assigned Shut Down

    (SD) OrWithout

    Shut Down

    (WSD)

    Periodi

    city

    A. SF6 CIRCUIT BREAKERS

    a. Checking of SF6 gas pressures

    (wherever pr. Gauges provided)

    WSD Monthly

    b. Checking of oil leaks from Grading

    Capacitors

    SD Monthly

    c. SF6 gas leakage test SD Yearly

    d. Dew Point measurement of SF6 gas SD 2 Yearly@

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    54/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    55/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    56/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Circuit Breakers

    B. AIR BLAST CIRCUIT

    BREAKERS

    a. Checking breaker air pressure WSD Monthly

    b. Air (Pressure) Leakage check WSD Monthly

    c. Dew Point Measurement of

    operating air at the outlet of Air

    Drier

    WSD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    57/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Circuit Breakers

    C. MOCBs

    a. Checking for oil leakage/oil

    level

    WSD monthl

    y

    b. Testing of oil for BDV WSD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    58/96

    Preventive Maintenance schedule for Circuit Breakers

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    59/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Circuit Breakers

    e. Functional checks, duty cycle

    operation including rapid re-

    closing (0-0 3s-CO)

    SD Yearly

    f. Checking of all operation lock-

    outs

    SD Yearly

    g. Checking of all interlocks SD Yearly

    h. Checking of pressure settings SD Yearly

    i. Cleaning of Breaker Interrupter,Support insulators, PIRs and

    Grading Capacitors

    SD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    60/96

    Preventive Maintenance schedule for Circuit Breakers

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    61/96

    sgb s.ganesh babu.

    Preventive Maintenance schedule for Circuit Breakers

    F. CONTROL CABINET

    a. Checking of tightness of all cable

    terminations in MB

    SD Yearly

    b. Checking of door sealing gasket

    and replacement thereof, if

    necessary

    WSD Yearly

    c. Repainting of metallic surfaces (ifrequired)

    WSD Yearly

    d. Checking of space heater WSD Yearly

    @ At time of commissioning then after 6 months and one & halfyears of commissioning and thereafter once in every twoyears.

    * For All HV/EHV Circuit Breakers only** For 400 kV BHEL, CGL make CBs only

    + First time after one year from commissioning and then once inevery three years.

    M i t T h i f I t t

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    62/96

    sgb s.ganesh babu.

    Maintenance Techniques for Instrument

    Transformer

    Instrument transformers are generally the most reliableEHV network equipment. However, violentfailure/blasting due to primary insulation of instrument

    transformers may lead to considerable damage tonearby equipments and O&M personals. In order toavoid violent failures following maintenance techniqueshave been adopted like measurement of tan delta and

    capacitance, insulation measurements, DGAmonitoring, recovery voltage measurement etc.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    63/96

    sgb s.ganesh babu.

    Tan Delta and Capacitance Measurement

    (CT/CVT)

    Testing mode for CTs: CTs provided with test stepshave to be tested in UST mode whereas CT with test

    step are to be tested in GST mode. Before carryingout the test it may be ensured that jumpers aredisconnected and CT/CVT porcelene housing /insulators are thoroughly cleaned.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    64/96

    sgb s.ganesh babu.

    Testing mode for CVTs:

    HF panel and neutral terminal of EMU transformerare to be disconnected and isolated from groundbefore carrying out the test. The testing kit which is

    similar as used for grading capacitors for CB is to beconnected between HV/HF points andmeasurements are done in UST mode. In the eventof test values deviating from the base values,

    individual capacitor stacks are to be tested in USTmode.

    Secondary Winding Resistance (CTs)

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    65/96

    sgb s.ganesh babu.

    Secondary Winding Resistance (CTs)Testing procedure

    After ensuring, necessary precautions have been taken,connect leads of O meter between different terminals ofCT secondary course. Select the range of O meter as per

    pre-commissioning / factory test results. Followingprecautions are considered essential:

    Test links should be open in the CT MB prior tomeasurement of secondary resistance

    It should be ensured that associated CTs are not incharged condition. For example main and tie CTs for

    differential relays should not be in charged condition. Any earth provided in the secondary circuit of CT should

    be removed prior to measurement.

    Secondary voltage measurement for CVTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    66/96

    sgb s.ganesh babu.

    Secondary voltage measurement for CVTs

    Failure of capacitor elements in C1 or C2 sideresults in change in output voltage. Regular andclose monitoring of secondary voltages using 0.2

    or 0.5 accuracy class multi meters, secondaryvoltage change can be monitored. If voltage of aparticular phase CVT drifts by more than + 1volts, it requires thorough investigation.

    P i ibl li it f CT

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    67/96

    sgb s.ganesh babu.

    Permissible limits for CTsA) IR value

    1. Primary

    earth 1000 M

    Ohm (Min.) by5.0/10.0 kV Megger

    2. Secondaryearth 50 MOhm (Min.) by 0.5 kV

    Megger

    3. Control cables 50 M-Ohm (Min.) by 0.5 kVMegger

    B) Tan delta value 0.007*at 20 Deg. C

    C) Terminal Connector 10 M-Ohm per connector NGC, UK

    Recomme

    ndations

    D) CT ratio errors + 3% - Protection cores IS2705

    + 1% - Metering cores -do-

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    68/96

    Preventive maintenance schedule of CTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    69/96

    sgb s.ganesh babu.

    Preventive maintenance schedule of CT s

    e. CT ratio test SD If needed

    f. DGA and testing of other parameters

    of oil

    SD If needed

    g. Thermo - vision Scanning of CT and

    Top dome

    WSD Yearly

    h. Checking of Bellow Expansion WSD Monthly

    i. Visual inspection CT for oil leakage

    and crack in Insulator etc.

    WSD Monthly

    Preventive maintenance schedule of CTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    70/96

    sgb s.ganesh babu.

    MARSHALLING BOX

    a. Checking of oil leakage WSD Monthly

    b. Checking of healthiness of gaskets WSD Monthly

    c. Checking of space heater &

    Illumination

    WSD Yearly

    d. Checking the tightness of all

    connections including earthing

    SD Yearly

    e. Cleaning of marshalling box and

    junction box

    * First time after one year from

    commissioning and then once in every

    three years.

    SD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    71/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    72/96

    Preventive Maintenance Schedule for CVTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    73/96

    sgb s.ganesh babu.

    Preventive Maintenance Schedule for CVT s

    VISUAL CHECKING OF

    EARTHING HF POINTa. Visual checking of earthing HF point

    (in case it is not being used for

    PLCC)

    SD Yearly

    b. Checking for any breakage or cracks SD Yearly

    c. Checking of oil leaks WSD Monthly

    d. Cleaning of CVT capacitor stacks

    and tightness of terminalconnections

    SD Yearly

    e. Capacitance and Tandmeasurement

    CVT

    SD Once in 3

    years

    Preventive Maintenance Schedule for CVTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    74/96

    sgb s.ganesh babu.

    Preventive Maintenance Schedule for CVTs

    f. Measurement of voltage atmetering points in control

    Room

    WSD Monthly

    g. Testing of EMU tank oil for

    BDV

    SD Once in

    6

    years

    h. Thermo - vision Scanning of

    Capacitor stacks

    WSD Yearly

    Preventive Maintenance Schedule for CVTs

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    75/96

    sgb s.ganesh babu.

    Preventive Maintenance Schedule for CVT s

    MARSHALLING BOX

    a. Checking of spacer heater &

    Illumination

    WSD Yearly

    b. Checking and tightness of all

    connections including earth

    connections

    SD Yearly

    c. Cleaning of marshalling box

    and junction box

    SD Yearly

    d. Checking of healthiness ofgaskets SD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    76/96

    Table 14Comparison of Gas Limits

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    77/96

    sgb s.ganesh babu.

    Table 14. Comparison of Gas Limits

    Gas

    Dobble 95% Norm

    PPM

    IEEE Limits

    PPM

    Hydrogen 511 200

    Methane 134 100

    Ethane 26 30

    Ethylene 17 30

    Acetylene 0.6 1

    CO 1,749 3,000CO2 15,485 30,000

    Total

    Combustibles2,024 3,360

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    78/96

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    79/96

    sgb s.ganesh babu.

    OLTC MAINTENANCESCHEDULE

    I nsp. I nspection check Remarks.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    80/96

    sgb s.ganesh babu.

    freq Item

    Dail

    y

    Digital

    counter onthe driving

    mechanism

    No. of tap

    changingOpns.

    Conducted.

    Records the cumulative no. of Opns

    carried out .

    Tap changerconservator

    Oil level. If low, top up new tested oil. If level

    goes up without adding oil, report to

    the manufacturer.

    ExplosionVent.

    Diaphragm

    Plate.

    Replace if cracked or broken.

    Space heater

    in the driving

    mechanism

    ---- Heater to be switched on, if ambient

    temp. goes below 20 deg C, and

    switched off when exceeds 30 deg C

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    81/96

    sgb s.ganesh babu.

    yrly

    or

    every

    5000

    Opns.

    Oil inthe

    divertor

    switch

    BDVof

    Oil.

    Replace or filter if BDV is lessthan 24 KV,at gap 2.5mm between

    spheres of 12.7mm(IS:335).

    Increase inspection frequency, if

    oil deteriorates faster.

    yearly Gasket Joints. Oil Leak Tighten the bolts evenly or replace

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    82/96

    sgb s.ganesh babu.

    the gaskets.

    yearly O rings in thebevel gear box

    Oil leak Replace O rings if leak isobserved. Dip the O rings in

    transformer oil before use.

    Yearly Universal joints

    and otherdriving Shaft

    parts.

    --- Apply Grease to prevent rusting.

    Use servo Gem EP2, or anyequivalent.

    Yearly Gas vent on theconservator

    --- Clean if clogged with carbon orDust particles.

    Yearly Gas and oiloperated relay

    Correct

    working

    Rectify defects if any.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    83/96

    sgb s.ganesh babu.

    Yearly Aux. Relay andcontactors.

    Rusting of core, dirt on

    contacts, chattering etc.,Clean or

    replace.

    Yearly Timer relays Time settings Adjust if the

    values are

    disturbed.

    Yearly Control CableConnections.

    For loose connections at

    relay, rotary and push

    button switches, Hand

    operation and interlockswitch, Motor, Aux.

    Transformer, TB terminals

    Tighten the

    connections.

    yearly Lubricating

    i

    Low oil level. Add or Replace oil.

    I N 68 (Bh H d l 68

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    84/96

    sgb s.ganesh babu.

    in

    the gear box

    of driving

    mechanism.

    Iso No.68,(Bharat Hydrol 68

    BP, Enklo 68HP, Servo

    System 68, I.O.C Perfecto 68

    Castrol)

    Yearly Electrical

    DrivingMechanism

    More than 2 Meg

    ohms,measured

    at 20 deg C with

    500 volt meggar.

    Low meggar value calls for

    investigation and rectify.

    Yearly Feed back

    data

    ---- To be given to the

    manufactureras per his proforma.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    85/96

    sgb s.ganesh babu.

    50,000

    operations or 5

    years since

    commissioning,

    which ever is

    earlier.

    Divertor

    Switch

    Contact

    compartment

    Thickness

    of Arcing

    contacts.

    Replace all the contacts if

    thickness of any one of the

    arcing tips is reduced to 2mm.

    To be done in the presence of

    authorized company rep.

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    86/96

    sgb s.ganesh babu.

    Every 10years Tap Selector Electric discharges on thesurface of insulators,condition of fasteners,

    moving and stationery

    contacts, smooth operation of

    a gears and other moving

    parts.

    Report tomanufacturer if any

    thing abnormal is

    observed.

    Battery and Battery Charger

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    87/96

    sgb s.ganesh babu.

    Following test may be carried out for determining thehealth of battery/battery charger.

    Capacity test/discharge test of battery bank

    Measurement of impendence of battery cell

    Checking of electrolyte level and topping up with DMwater

    Checking of emergency DC lighting to control room

    Checking of electrical connection of charger panel fortightness and cleaning

    Checking of electrical connection of battery for tightness

    Checking of tightness of all electrical connection of DCdistribution board

    Preventive Maintenance Schedule for Isolatorsand Earth Switches

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    88/96

    sgb s.ganesh babu.

    and Earth SwitchesS. No. Tasks assigned Shut Down (SD) Or

    Without Shut

    Down (WSD)

    Periodicity

    A. Operating Mechanism

    a. Linkages including transmission gears SD Yearly

    b. Stopper bolts SD Yearly

    c. Cleaning of auxiliary switch contact &

    greasing with silicon grease

    SD Yearly

    d. Lubrication of operating mechanism,hinges, lock joints on levers,

    bearings

    SD Yearly

    e. Checking of all mounting bolts for

    tightness

    WSD Yearly

    Preventive Maintenance Schedule for Isolators and Earth Switches

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    89/96

    sgb s.ganesh babu.

    B. MAIN CONTACTS

    a. Cleaning and lubrication ofmain controls

    SD Yearly

    b. Alignment SD Yearly

    c. Main contact resistancemeasurement

    SD Once in2 yrs.

    d. Tightness of bolds, Nuts and

    pins etc.

    SD Yearly

    e. Cleaning of support insulators

    and checking of insulator

    cracks, if any

    SD Yearly

    Preventive Maintenance Schedule for Isolators and Earth Switches

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    90/96

    sgb s.ganesh babu.

    C. EARTH SWITCH

    a. Checking and Alignment ofearthing blades

    SD Yearly

    b. Cleaning of contacts SD Yearly

    c. Contact resistance SD Yearly

    d. Operation of earthing switch SD Yearly

    e. Checking of alumunium Copper

    flexible conductor

    SD Yearly

    f. Checking of earth connections of

    structure and MOM box

    SD Yearly

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    91/96

    PREVENTIVE MAINTENANCESCHEDULE

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    92/96

    sgb s.ganesh babu.

    FOR WAVE TRAPS

    S.No.

    Tasks assigned Shut Down(SD) Or

    Without Shut

    Down (WSD)

    Periodicity

    a. Tightness & Cleanliness SD Yearly

    b. General inspection / cleaning of

    tuning unit

    SD Yearly

    A PROCEDURE FOR FILLING OF

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    93/96

    sgb s.ganesh babu.

    EQUIPMENT FAILURE REPORT (EFR)

    Whenever there is a failure of any equipment or part of anyequipment during operation and maintenance which may

    result in the outage of the said equipment the EFR is

    required to be filled up.

    Each failure report has to be given a specific report numberfollowed by the name of the sub-station / serial number of

    the failed equipment and date of failure.

    Time of occurrence of equipment failure or noticing of

    failed equipment also to be written. Mention to be made as to when the fault was discovered i.e.

    during testing, commissioning, operation and

    maintenance.

    Name of the main equipment which has failed may be

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    94/96

    sgb s.ganesh babu.

    given along with the name of the manufacturer / supplier /

    sub-vendor.

    Specify the type of faulty unit/equipment as given by themanufacturer for example in breakers it could be SF6

    3AT3/3AT2; SF6 HPL, ABCB DLF 245 NC2 etc.

    Specify the item designation i.e. bay name in which faulty

    equipment was erected / located, including the Sr. No. /Badge Number as given on the name plate.

    Specify the faulty component in the unit and the part

    number as per the O&M manual of the manufacturer

    Specify the type of failure i.e. burnt / flashover / mal-operation / mechanical fault / open circuit / short circuit /

    operating error / setting etc.

    Specify short / brief description of occurrence off l d h f

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    95/96

    sgb s.ganesh babu.

    fault and cause thereof

    Specify the remedial action taken.

    Specify the reference of the document from which

    part number / fault diagnosis has been done, so

    that it may help in analysis of fault.

    Equipment failure may occur during tripping /due to suspected fault / mal-functioning of some

    other equipment. Report number therefore to be

    specified.

    The above documents should be signed by themaintenance engineer and counter signed by the

    substation in -charge.

    Th k

  • 8/12/2019 Operation and Maintenance of Sub - Stations Revised 030909

    96/96

    Thank you,

    Wish you all a successfulprofessional career