PRODUCT INFORMATION PI - 32.26
Seite 1601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
Operating Unit BE 500
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 2 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
Summary
1. Description 3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1. Overview of the Menu Structure and Operating Functions 4. . . . . . . 1.2. System Overview 5. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Features 6. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Planning notes 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1. Maximum line lengths between BZ 500 LSN and BE 500 7. . . . . . . .
4. Ordering 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.1. Basic Equipment 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2. Installation Accessories 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5. Device Layout 8. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.1. Block Diagram BE 500 9. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2. Description of the Control Electronics BEB 10 9. . . . . . . . . . . . . . . . . 5.3. Description of the Connection Board BAB 10 9. . . . . . . . . . . . . . . . . .
6. Installation 10. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.1. Installation notes 10. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2. Dimensions 10. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3. Cable Ducts 11. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.4. Connections on the BAB 10 Board 12. . . . . . . . . . . . . . . . . . . . . . . . . . . 6.5. Power Supply 12. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7. Programming 13. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8. Commissioning 14. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9. Maintenance and Services 15. . . . . . . . . . . . . . . . . . . . . . . . . 9.1. Service Accessories 15. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.2. Documentation 15. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
10. Technical Data 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10.1. Norms and Regulations 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10.2. Dimensions/Weight/Colour 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10.3. Environmental Conditions1. 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10.4. Serial Interface 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10.5. Indication Time of Malfunction Signal 17. . . . . . . . . . . . . . . . . . . . . . . . . 10.6. Power Supply 17. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11. Abbreviations 18. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12. Memos 19. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 3 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
1. Description
The operating unit BE 500 is a supplementary equipment to the Fire Alarm Cen-tral Station BZ 500 LSN (see PI - 32.05).The control and indicating surface is identical with that of the BZ 500 LSN.All operating processes can be carried out on the BE 500 the same as on the BZ500 LSN.A maximum of three BE 500 can be connected to a BZ 500 LSN.
Key Switch(optional)
Operating Keys
Summationdisplay
Display
The indication panel is an LCD-Display with 2 lines (2 x 40 digits) withbackground illumination that is switched on when pressing a key.Light emitting diodes are used for the summation display.
The operation of the control unit is carried out with membrane keys, each keypunch being confirmed acoustically.
The BE 500 can be equipped with 2 key switches, each with 2 key positions(optional).The switch occupation can be programmed at random.e.g. Switch 1: Switchover from day to night service
Switch 2: Toggling of the local alert
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 4 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
1.1. Overview of Menu Structure and Operating Functions
Input of the User Code
FurtherFunctionsReset Mainten.Switch -off Control
Controlgroups
Sounder
Switchpoints
Switchpoints
Detectors/Zones
Controlgroups
TU Trans-mission
unit
Sounders
Switch points
Controlgroups
Extinguishingareas
Zones
Malfunctioncentralfunction
Earth
Detectors/Zones
Controlgroups
Sounders
Performlamp test
Go to a date/event
Print events
Select/searchevents
Input ofdate/time
Alarm memory
Changeoperator code
Display statusof
alarm counter
Block outdetectors/zones
DisplaySoftwareRelease
Sounders
TUTransmis-sion unit
Extinguishingareas
TUTransmission
unit
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 5 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
1.2. System Overview
Possibility to connect a maximumof three BE 500 to BZ 500 LSNusing one serial 20 mA interface(SM 20) for each BE 500.
Automatic Fire Detectors (LSN)
LSN
-Loo
p
FBFBE 500 BAT 100 LSN
230 V
BZ 500 LSN
SM 20
SM 20
SM 20
COM 1
COM 2
COM 3
ANNE 10
LSN-Loop
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 6 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
2. Features
Operating and display panel is identical with the BZ 500 LSN.
Up to 3 BE 500 LSN are connectable to one BZ 500 LSN.
Simultaneous operation and indication onto the several BE 500 is possiblewithin the Local SecurityNetwork LSN.
Keypad panel with acoustic confirmation of each key pressing.
Display (2- lines with 40 signs per line) with backlight illumination.
Summary displays via LEDs.
The BE 500 can be equipped with 2 key switches with 2 switch positions at eachkey switch.
The key functions are free programmable.e.g. switch 1: Day/Night mode
switch 2: switch of the alarm transmission to the fire brigade
Power supply via the BZ 500 LSN or by the integrated power supply unit (230V).
Stromversorgung des internen Summers, bei Stromausfall oder bei Störung derseriellen Schnittstelle, für ca. 1 Stunde gewährleistet (entspricht VDE 0833).
VdS-Approval No.: G 298 054
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 7 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
3. Planning notes
3.1. Maximum line lengths between BZ 500 LSN and BE 500
3.1.1. With power supply from the BZ 500 LSN (0V, 12V DC)
Output voltage BZ 500: UBZ = 10,8V (min.) allowed voltageInput voltage BE 500: UBE = 10,2V (min.) drop 0,6 V
Diameter of the wire/ wire cross section maximum line length
0,6 mm ∅ ca. 20 m
0,8 mm ∅ ca. 30 m
1,0 mm2 ca. 50 m
1,4 mm2 ca. 100 m
Line resistence: 2 x RL/2 < 1,5 Ω
3.1.2. With power supply via the integrated mains supply (230V AC)
Maxium line length: 1000m
4. Ordering
4.1. Basic Equipment
Order Number DU* Designation
3.002.120.306 ST Operating Panel BE 500
* DU = Delivery Unit, ST = Piece
4.2. Installation Accessories
Order Number DU* Designation
2.798.020.102 ST Installation Cable J -Y (ST) Y 2x2x0,6
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 8 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
5. Device Layout
The BE 500 consists of: housing cover control and indicating panel 2 modules: - control electronics BEB 10
- connection board BAB 10 housing bottom
Control andindicatingpanel
Connectionboard BAB 10
Cable duct forNYM 3x1,5Terminal clamp for
screen wire
Cable duct fordata lines
Housingbottom
BE 500 without cover
Control electronicsBEB 10
Sheet metal cagefor EMC screening
Front plate slit into parking position
Slot forparkingposition
Slot forparkingposition
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 9 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
5.1. Block Diagram BE 500
10,2 Vup to
14,8 V
Connection board BAB 10
serialinterface
230 V
or
Control electronics BEB 10 withcontrol and indicating equipment
20-pole 10-pole
5.2. Description of the Control Electronics BEB 10
Processor system
LCD display, 2 lines with 40 digits each, background illumination
LED summation indicators
Membrane keypad
2 key switches (optional)
no earth recognition
Programming via interface and BZ 500 LSN
Software-Download via interface and BZ 500 LSN
1 serial interface 20mA
5.3. Description of the Connection Board BAB 10
Connection of all inputs and outputs
Power supply
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 10 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
6. Installation
6.1. Installation notes
Installation of the devices must occur in dry, maintained interior rooms. Theenvironmental requirements are to be heeded (see page 16).
The operating and display elements should be at eye level.
Use only the installation material recommended by UC-ST;otherwise, interference immunity cannot be guaranteed.
Do not startup a operating panel moist with dew.
Fit a ferrite sleeve onto the mains cable (230 V) NYM 3x1,5.
Clip a clap ferrite onto the data cable.
When working with the printed circuit boards, the usual precautions for C-MOStechnology are to be heeded.
Caution! ESD (electrostatic discharge)The usual measures and regulations with regard to static electricity dischargeare to be heeded!
The appropriate connection requirements stipulated by the local authorities (firedepartment) are to be heeded.
The installation, additionally to the BE 500, of a remote display panelBAT 100 LSN which is to function as individual LED display for zones, shouldbe side by side with the housing of the BE 500.
6.2. Dimensions
270
270
75
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 11 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
6.3. Cable Ducts
Cable duct surface mounted
Cable duct into the device
Cable duct flush mounted
free space with adepth of 14,5 mm, for cable duct
Cable duct forNYM 3x1,5
Cable duct fordata lines
248
186
138
69
(24)
123
21
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 12 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
6.4. Connections on the BAB 10 Board
Input
10V...15V- +
ST1
(CURRENT)
ON
BE oFF ON
DOWN LOAD
SD
O-
SD
O+
SD
I-S
DI+
CT
SO
V3
ST2T500
L1 N
SINE
1 2 3
Power supply of the BZ 500 LSN (input voltage 10,2 -14,8 V)
230 VVoltagesupply
MAINS
Mainsfuse
Inputs forkey switches
Flat cable connections to the BEB 10
Break jumper for measuring the device voltage and current
Serial 20mA interface for connecting the BZ 500 LSN
To programming via opto coupler V.24 interface (OVS)
When loading a new program of the BZ 500LSN, the jumper must be positioned on ON
(not for programming).
CTR
E10E11E12OV2
E4E5E6OV1
X2 X1
6.5. Power Supply
The power supply can be derived either from the BZ 500 LSN (0 V, 12 V) or from thebuilt - in mains supply (230 V) of the BAB 10.
In case of power failure, there is a gold condensator for the power supply (approx.1 hour) of the internal buzzer, therefore, an STB surveillance is not required.
Generally, an STN surveillance is not necessary.
Detailled connections: see installation manual BE 500 and con-nection manual EMZ / BMZ
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 13 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
7. Programming
If a BE 500 is connected to a COM 1 interface of the BZ 500 LSN, theprogramming of the BE 500 must be carried out via OVS.
When connecting the BE 500 to COM 2 and COM 3, the programming can becarried out directly with the BZ 500 LSN (or via OVS).
For the interfaces COM 2 and COM 3, the Interface Expansion Unit ERSE 10must be incorporated into the BZ 500 LSN.
Before connecting the PC/Laptop to the PC- inlet, a possibly plugged in interfacemodule SM 20 must be removed from the COM 1 interface of the BZ 500 LSN.
First remove mains supply from the BZ 500 LSN.
COM1
COM2
COM3
Slo
t SM
20
(ZA
LE
)(w
ith
ER
SE
)(w
ith
ER
SE
)
PC inlet
BZ 500 LSNANNE 10
Slo
t SM
20S
lot S
M20
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 14 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
8. Commissioning
Program the BE 500with the BZ 500.
The wires are connected.The connection between BZ 500 LSN
and BE 500 is made.
green ”OperationLED” is alight
YES
Switch on mains supply for BE 500.
Carry out test:Check operating functions.
Put on housing cover, tighten screwsof the housing and apply seal to the
screw.
NO Analyse andeliminate error .
Reset messages on the BZ 500 LSN(confirm).
The BE 500 is ready for operation.
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 15 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
9. Maintenance and Services
Maintenance and inspection work should be carried out regularly bytechnically competent personnel.The regulations of the DIN VDE 0833 are to be applied.
Measuring points of the device voltage and currentRemove the jumper (STROM) set by the manufacturer from the connection boardBAB 10 and connect a measuring device to the two pins.
Eingang
10V...15V- +
E10E11E12
OV2
E4E5E6
OV1X2 X1
ST1
(STROM)
EIN
B
E AUS EIN
DOWN LOAD
SD
O-
SD
O+
SD
I-S
DI+
CT
SO
V3
ST2
T500SINE
1 2 3
Separation jumper for device voltage and current measuring
9.1. Service Accessories
Pos. Ref. Number DU* Designation
01 3.002.389.678 PAK Safety lead seal (1 PAK = 10 Pieces)
* DU = Delivery Unit, ST = Piece, PAK = Package
9.2. Documentation
Pos. Ref. Number DU* Designation
01 3.002.219.470 ST Operating instructions BZ 500 LSN / BE 500
02 30.0221.8156 ST Connection Manual AHB EMZ / BMZ
* DU = Delivery Unit, ST = Piece
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 16 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
10. Technical Data
10.1. Norms and Regulations
The BE 500 complies with the respective European norms (standards)and regulations for security systems (Sec.Sys.).
- VdS (Acceptance No.: G 298054)- EN 54- ISO- DIN 14675- VDE 0833- EMC norm 89/336/EWG- Ö-Norm
10.2. Dimensions/Weight/Colour
Dimensions (H x W x D): 270 x 270 x 75 mmWeight: approx. 2,3 kgColour of housing: light greyColour of cover: light greyColour of control panel: white-grey
10.3. Environmental Conditions1.
Environmental class II (EN 54/2)Protection type IP 30 (EN 60529/DIN VDE 0470 Part 1)Protection class I (EN 60950/DIN VDE 0106 Part 1)EMC interference emission DIN EN 50081-1EMC interference immunity DIN EN 50130-4Environmental temperature -5°C . . . +45°CStoring temperature -20°C . . . +60°C
10.4. Serial Interface
Interface: 20 mA (opto coupler interface)Transmission rate- with ZALE 10 (BZ 500 LSN): 9600 bit/s- with ERSE 10 (BZ 500 LSN): 19200 bit/sInstallation cable: J-Y (ST) Y 2 x 2 x 0,6
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 17 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
10.5. Indication Time of Malfunction Signal
Indication of malfunction signal: 1 hour (buzzer)
10.6. Power Supply
10.6.1.Mains Voltage: 230 AC (-15% ... +10%)
Mains cable: NYM 3 x 1,5mm2
Mains frequency: 50HzMains voltage securing: M 10AMains fuse (SINE): T500Primary converter (230V AC). 14V/ 0,5 APower consumption: 5 W (230V AC), fully equippedProtection class: I
10.6.2.Power Supply from the BZ 500 LSN
Input voltage UExtern 10,2V DC . . . 14,8V DC
Current consumption with input voltage UExtern 14,8 V DC
Normal current without FBF 65 mA
Normal current with FBF 75 mA
Alarm current (incl. display illumination) 120 mA
Alarm current (incl. display illumination and FBF) 140 mA
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 18 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
11. Abbreviations
AHB = Anschaltehandbuch / Connection manual
ANNE = Anschaltung-Netzgerät -Einheit / Connection mains unit
aP = auf Putz / over plaster (surface mounted)
BAB 10 = Bedienfeld -Anschaltung-BZ / Connection of Control Panel BZ
BAT 100 = Bedien- u. Anzeigeteil Tableau / Control and indicating equipment
BE = Bedieneinheit / Operating unit
BEB 10 = Bedienfeld -Elektronik -BZ / Control electronics BZ
BMZ = Brandmeldezentrale / Fire panel
BR = Brücke / Jumper
DIN = Deutsches Institut f. Normung / German institute for standardizing
EMV = Elektromagnetische Verträglichkeit / Electromagnetic compatibility
EN = Europa Norm / European standard
ERSE = Erweiterung-Schnittstellen-Einheit / Expansion for interface unit
Ext = Extern / external
FBF = Feuerwehrbedienfeld / Fire service control console
GMA = Gefahrenmeldeanlage / Security system
ISO = International Standardizing Organization
LED = Light emitting diode (Leuchtdiode)
LSN = Lokales Sicherheits Netzwerk / Local Security Network
OVS = Optokoppler V.24 Schnittstelle / Optocoupler V.24 interface
PI = Produktinformation / Product information
SDI = Serielle Daten In / Serial data in
SDO = Serielle Daten Out / Serial data out
SM = Schnittstellenmodul / Interface module
uP = unter Putz / under plaster (flush mounted)
ÜE = Übertragungseinrichtung / Transmission equipment
VDE = Verband Deutscher Elektrotechniker e.V. /Association of german electrotechnicians
VdS = VdS Schadenverhütung GmbH / German council for prevention of loss
ZALE = Zentrale -Anzeige-LSN-Einheit / Central LSN Indication Unit
PI - 32.26Product Information Operating Panel BE 500 LSN
Seite 19 von 20
601-4.998.148.494A4.en / 28.12.2004
ST-FIR/ PRM1 / deh
12. Memos
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Page 20 of 20
Bosch Security SystemsRobert -Koch-Str. 100D-85521 Ottobrunn
Info -ServiceTelephone: +49 89 6290 - 1039Fax: +49 89 6290 - 1039