S&C Draft of 5/26/10. Operating Performance Update. Production Milestones. June 26, 2012 First Nickel test briquettes were sintered. August 18, 2012 Single largest batch of slurry sent from the Mine (18,980 t), exceeding the Financial Completion target of 674 t/h. September 9, 2012 - PowerPoint PPT Presentation
Citation preview
INTERNAL
Operating Performance Update
S&C Draft of 5/26/10
2INTERNAL
Production Milestones• June 26, 2012
First Nickel test briquettes were sintered.
• August 18, 2012 Single largest batch of slurry sent from the Mine (18,980 t), ex-
ceeding the Financial Completion target of 674 t/h.
• September 9, 2012 First Cobalt test briquettes were sintered.
• September 13, 2012 Operating permit granted.
• November 1, 2012 5 Autoclaves on line with dual slurry feed pumps
• November 8, 2012 First international shipment of refined nickel (40 t)
• November 13, 2012 First international shipment of refined cobalt (168 t)
2
3INTERNAL
Production Achievements to November 30, 2012
3
• Mixed Sulphides to Refinery:
Ni+Co contained, t 6,900
• Nickel Reduced, t
5,512
• Cobalt Reduced, t
488
• Amsul Produced, t
10,695
Note: The Project achieved “Commencement of Commercial Production” as described in the Finance Documents on November 26, 2012.
INTERNAL
PAL Overview
• Autoclaves PAL Autoclave Operating Hours
• Operated approximately 1,788 hours in November
Ore Throughput in the PAL Autoclaves• Processed 191,085 tonnes in November
• PAL Mixed Sulphide Production Produced approximately 1,763 tonnes of mixed sul-
phides (ni+co contained) in November
4
5INTERNAL
Refinery Overview
5
• Sulphide Leaching In November we processed 1,694 tonnes of nickel and
cobalt contained in mixed sulphides
• Nickel Reduction In November we reduced 1,592 tonnes of nickel pow-
der
• Cobalt Reduction In November we reduced 164 tonnes of cobalt pow-
der
• Metals Handling Produced 1,199 tonnes of nickel briquettes in No-
vember Produced 100 tonnes of cobalt briquettes in Novem-
ber
6INTERNAL
Operating Performance – PAL Ramp-Up Curve
6
7INTERNAL
Operating Performance – Refinery Ramp-Up Curve
7
8INTERNAL
Operating Performance – Ore Throughput
8
9INTERNAL
Operating Performance – Nickel Produced
9
10INTERNAL
Nickel Quality Analysis
10
• Nickel meets LME spec for all elements except silicon.
• Silicon contamination has occurred from late October and into November as Si level in Refinery solution has increased.
• Refinery is currently progressing initiatives to purge silicon from the circuit.
INTERNAL
Questions?
S&C Draft of 5/26/10