United States Environmental Protection Agency Solid Waste And Emergency Response 5401G EPA 510-B-00-008 August 2000 www.epa.gov Operating And Maintaining Underground Storage Tank Systems Practical Help And Checklists Printed on Recycled Paper

Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Embed Size (px)

Citation preview

Page 1: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

United StatesEnvironmental ProtectionAgency

Solid Waste AndEmergency Response5401G

EPA 510-B-00-008August 2000www.epa.gov

Operating AndMaintainingUnderground StorageTank Systems

Practical Help AndChecklists

Printed on Recycled Paper

Page 2: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

DISCLAIMER

This document provides information on operatingand maintaining underground storage tank (UST)systems. The document is not a substitute for U.S.Environmental Protection Agency regulations nor is ita regulation itself — it does not impose legallybinding requirements.

For regulatory requirements regarding UST systems,refer to the Federal regulations governing USTsystems (40 CFR Part 280).

Contents

How to Use This Booklet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Section 1 — Identifying The Equipment At Your UST Facility . . . 3

Section 2 — Release Detection . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

Section 3 — Suspected Or Confirmed Releases . . . . . . . . . . . . 21

Section 4 — Spill And Overfill Protection . . . . . . . . . . . . . . . . . . 24

Section 5 — Corrosion Protection . . . . . . . . . . . . . . . . . . . . . . . 34

Section 6 — Frequent Walk-Through Inspections . . . . . . . . . . . 42

Section 7 — For More Information . . . . . . . . . . . . . . . . . . . . . . . 44

Page 3: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 1

Key Terms Used In ThisBooklet

An UST is an undergroundstorage tank andunderground pipingconnected to the tank that hasat least 10 percent of itscombined volume underground.The federal regulations applyonly to USTs storing petroleumor certain hazardoussubstances.

O&M stands for operation andmaintenance procedures thatmust be followed to keep USTsfrom causing leaks and creatingcostly cleanups.

How To Use This Booklet

Who should read this booklet?

This booklet is for owners and operators ofunderground storage tank systems (USTs).

You are responsible for making sure your USTs do notleak. This booklet can help you meet your USTresponsibilities.

What can this booklet help you do?

# Identify and understand the operation andmaintenance (O&M) procedures you need to followroutinely to make sure your USTs don’t have leaksthat damage the environment or endanger humanhealth.

# Identify good O&M procedures you can use to avoidcleanup costs and liability concerns.

# Maintain useful records of your O&M.

Your UST system is “new” or “upgraded” — is that enough?

Being “new” or “upgraded” is not enough. New and upgraded USTs are made of a complexcollection of mechanical and electronic devices that can fail under certain conditions. Thesefailures can be prevented or quickly detected by following routine O&M procedures. Having anew or upgraded UST system is a good start, but the system must be properly operated andcontinuously maintained to ensure that leaks are avoided or quickly detected.

What should you do with each section of this booklet?

Read through each sectioncarefully and use the checkliststo help you establish clear O&Mprocedures.

By identifying and understandingthe O&M tasks you need toperform routinely, you will ensuretimely repair or replacement ofcomponents when problems areidentified.

Page 4: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 2

Want to help improve this O&M Manual?

We want to continually improve thisO&M Manual with your help!

Send us your feedback.

Let us know if you find any errors,think something needs to be added ordeleted, or have suggestions onformat or checklist changes.

# Send feedback by e-mail [email protected]

# Send feedback by regular mail toOUST Outreach O&M, Mail Code5401G, 1200 PennsylvaniaAvenue, NW, Washington, DC20460

# Or phone your feedback to ourHotline at 1-800-424-9346.

How can you use the following checklists effectively?

This booklet’s pages are 3-hole punched and unbound so you can put all the materials in ahandy 3-ring binder. You can easily remove any of the following checklists from the binder,reproduce them, and then fill them out.

You can select the specific mix of checklists that matches your UST facility. Once you haveyour select group of checklists together, make several copies that you can fill out periodicallyover time.

In this way you can keep track of your O&M activities and know that you’ve done what wasnecessary to keep your UST site safe and clean, avoiding any threats to the environment ornearby people as a result of costly and dangerous UST releases.

Use this booklet often — effective O&M requires constant vigilance.

Note: This booklet describes quality O&M practices put together by a work group ofState and Federal environmental regulators. This booklet is not a federal regulationnor legally binding, but it does provide useful information on effective O&Mprocedures. You should check with your State UST program for information on anyadditional or different O&M practices that may be required in your State. See Section 7 for contact information.

Page 5: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 3

Section 1 — Identifying The Equipment At Your UST Facility

Determine what UST equipment you have at your facility by completing the checklist below.Note that each part of the checklist below refers you to the appropriate section of this O&Mbooklet for relevant information. After you have identified your equipment, proceed to thefollowing sections to identify the O&M actions necessary for your specific UST system.

General Facility Information (optional)Facility Name

Facility ID #

Release Detection (See Section 2 for information on release detection)

A. Release Detection for Tanks

Check at least one for each tank: Tank #1 Tank #2 Tank #3 Tank #4

Automatic Tank Gauging System

Interstitial Monitoring (with secondary containment)

Groundwater Monitoring

Vapor Monitoring

Inventory Control and Tank Tightness Testing (TTT)*

Manual Tank Gauging Only **

Manual Tank Gauging and Tank Tightness Testing (TTT)***

Other Release Detection Method, such as SIR(please specify)

* Allowed only for 10 years after upgrading or installing tank with corrosion protection. TTT required every 5 years.** Allowed only for tanks of 1,000 gallon capacity or less.*** Allowed only for tanks of 2,000 gallon capacity or less and only for 10 years after upgrading or installing tank with

corrosion protection. TTT required every 5 years.

B. Release Detection for Pressurized Piping

Check at least one from A & B for each tank’s piping: Tank #1 Tank #2 Tank #3 Tank #4

A

(Autom atic

Line Leak

Detectors)

Automatic Flow Restrictor

Automatic Shutoff Device

Continuous Alarm

BAnnual Line Tightness Test

Monthly Monitoring*

* Monthly Monitoring for piping includes Interstitial Monitoring, Vapor Monitoring, Groundwater Monitoring, and otheraccepted methods (such as SIR and Electronic Line Leak Detectors)

C. Release Detection for Suction Piping

Check at least one for each tank’s piping: Tank #1 Tank #2 Tank #3 Tank #4

Line Tightness Testing Every Three Years

Monthly Monitoring*

No Release Detection Required For “Safe Suction” **

* Monthly Monitoring for piping includes Interstitial Monitoring, Vapor Monitoring, Groundwater Monitoring, and SIR** No release detection required only if it can be verified that you have a “safe suction” piping system with the following

characteristics:

1) Only one check valve per line located directly below the dispenser;2) Piping sloping back to the tank; and3) System must operate under atmospheric pressure.

Page 6: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 4

Spill and Overfill Protection (See Section 4 for more information)

Check for each tank: Tank #1 Tank #2 Tank #3 Tank #4

Spill Catchment Basin/ Spill Bucket

Check at least one overfill device for each tank:

Automatic Shutoff Device

Overfill Alarm

Ball Float Valve

Corrosion Protection (See Section 5 for more information)A. Corrosion Protection for Tanks

Check at least one for each tank: Tank #1 Tank #2 Tank #3 Tank #4

Coated and Cathodically Protected Steel

Noncorrodible Material (such as Fiberglass Reinforced Plastic)

Steel Jacketed or Clad with Noncorrodible Material

Cathodically Protected Noncoated Steel*

Internally Lined Tank*

Cathodically Protected Noncoated Steel and Internally Lined Tank*

Other Method Used to Achieve Corrosion Protection(please specify):

* These options may be used only for tanks installed before December 22, 1988.

B. Corrosion Protection for Piping

Check at least one for each: Tank #1 Tank #2 Tank #3 Tank #4

Coated and Cathodically Protected Steel

Noncorrodible Material (such as Fiberglass Reinforced Plastic or Flexible Plastic)

Cathodically Protected Noncoated Metal*

Other Method Used to Achieve Corrosion Protection(please specify):

* This option may be used only for piping installed before December 22, 1988.

Any problems filling out this checklist?

If you have trouble filling out this checklist or any following checklist, remember these sources ofassistance you can contact:

# Your UST contractor, the vendor of your equipment, and the manufacturer of your USTequipment should be ready to help you. Look through your records for contact information. Youmay also want to use some of the industry contacts and other contact information provided inSection 7.

# Your State regulatory agency may be able to help you identify equipment or sources ofinformation about your UST equipment. You should, in any event, make yourself aware of anyways in which your State may have additional or different O&M procedures than those presentedin this booklet. See Section 7 for State agency contacts.

Page 7: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV �

Section 2 — Release Detection

What Is Release Detection?

You must be able to determine at leastevery 30 days whether or not your tankand piping are leaking by using properrelease detection methods.

Your release detection method must beable to detect a release from any portionof the tank and connected undergroundpiping that routinely contains product.

Release detection must be installed,calibrated, operated, and maintainedaccording to the manufacturer’sinstructions.

Do You Know If Your Release Detection Is “Certified” To Work AtYour UST Site?

Release detection must meet specific performance requirements. You should havedocumentation from the manufacturer, vendor, or installer of your release detectionequipment showing certification that it can meet performance requirements.

Some vendors or manufacturers supply their own certification, but more often an impartial“third party” is paid to test the release detection equipment and certify that performancerequirements are met. An independent workgroup of release detection experts periodicallyevaluates all third-party certifications, thus providing a free and reliable list of evaluations ofthird-party certifications for various release detection equipment. Frequently updated, thislist is available on the Internet at http://www.nwglde.org (thepublication’s title is List Of Leak Detection Evaluations For Underground Storage TankSystems). If you can’t find the certification anywhere, contact your State regulatory agency(see Section 7 for contacts).

By checking the certification, you may discover the method you use has not been approvedfor use with the type of tank or piping you have or the type of product being stored. Forexample, you may learn from the certification that your method won’t work with manifoldedtanks, certain products, high throughput, or with certain tank sizes.

That’s why you need to make sure your release detection method has clear certificationthat it will work effectively at your site with its specific characteristics.

Page 8: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV �

How Can You Make Sure Your Leak Detection Method Is WorkingAt Your UST Site?

If you don’t understand your O&M responsibilities and don’t know what O&M tasks youmust routinely perform, you may allow your UST site to become contaminated — then youwill face cleanup costs and associated problems.

To avoid these problems use the checklists on the following pages that describe each typeof leak detection method, discuss actions necessary for proper O&M, and note the recordsyou should keep.

Locate the methods of release detection you are using at your facility, review these pages,and periodically complete the checklist. You might want to copy a page first andperiodically fill out copies later.

If you have questions about your release detection system, review your owner’s manual orcall the vendor of your system. Your state or local regulatory agency may be able toprovide assistance as well.

You will find leak detection recordkeeping forms in the following pages of this Section.Keeping these records increases the likelihood that you are conducting good O&M andproviding effective release detection at your UST site. For example, see page 20 for a “30-Day Release Detection Monitoring Record.”

If you ever suspect or confirm a leak, refer to Section 3. Never ignore leak detectionalarms or failed leak detection tests. Treat them as potential leaks!

Page 9: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV �

Automatic Tank Gauging (ATG) Systems (for tanks only)

DescriptionOf ReleaseDetection

An automatic tank gauging (ATG) system consists of a probe permanentlyinstalled in a tank and wired to a monitor to provide information on productlevel and temperature. ATG systems automatically calculate the changes inproduct volume that can indicate a leaking tank.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your ATG system is certified for the types of tanks and storedcontents on which the ATG system is used. Most manufacturers have theirleak detection devices tested and certified by a third party to verify that theirequipment meets specific performance requirements set by regulatory agencies.If you don't have certified performance claims, have the manufacturer providethem to you.

PerformThese O&MActions

t Use your ATG system to test for leaks at least every 30 days. Most systemsare already programmed by the installer to run a leak test periodically. If yoursystem is not programmed to automatically conduct the leak test, refer to yourATG system manual to identify which buttons to push to conduct the leak test.Testing more often than monthly can catch leaks sooner and reduce cleanupcosts and problems.

t Make sure that the amount of product in your tank is sufficient to run theATG leak test. The tank must contain a minimum amount of product to performa valid leak detection test. One source for determining that minimum amount isthe certification for your leak detection equipment (as discussed above).

t Frequently test your ATG system according to the manufacturer’sinstructions to make sure it is working properly. Don’t assume that yourrelease detection system is working and never needs checking. Read yourowner’s manual, run the appropriate tests, and see if your ATG system is set upand working properly. Most ATG systems have a “test” or “self-diagnosis” modethat can easily and routinely run these checks.

t If your ATG ever fails a test or indicates a release, see Section 3 of thisbooklet for information on what to do next.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your ATG, service all the ATG system components according tothe manufacturer’s service instructions. Tank probes and other componentscan wear out and must be checked periodically. Many vendors recommend orrequire this maintenance activity at least annually.

t Check your ATG system owner’s manual often to answer questions and tomake sure you know the ATG’s operation and maintenance procedures.Call the ATG manufacturer or vendor for a copy of the owner’s manual if youdon’t have one.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep TheseO&MRecords

t Keep results of your ATG system tests for at least 1 year. Your monitoringequipment may provide printouts that can be used as records. Unless you arerecording actual release detection results at least every 30 days and maintainingrecords for at least 1 year, you are not doing leak detection right.

t Keep all records of calibration, maintenance, and repair of your releasedetection equipment for at least 1 year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certification ofyour leak detection equipment described above.

Page 10: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV �

Secondary Containment With Interstitial Monitoring (for tanks & piping)

DescriptionOf ReleaseDetection

Secondary containment is a barrier between the portion of an UST system thatcontains product and the outside environment. Examples of secondarycontainment include an outer tank or piping wall, an excavation liner, and abladder inside an UST. The area between the inner and outer barriers — calledthe interstitial space — is monitored manually or automatically for evidence ofa leak.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your interstitial monitoring equipment and any probes arecertified for the types of tanks, piping, and stored contents on which therelease detection system is used. Most manufacturers have their leakdetection devices tested and certified by a third party to verify that theirequipment meets specific performance requirements set by regulatory agencies.If you don't have certified performance claims, have the manufacturer providethem to you.

PerformThese O&MActions

t Use your release detection system to test for leaks at least every 30 days.Testing more often than monthly can catch leaks sooner and reduce cleanupcosts and problems.

t Frequently test your release detection system according to themanufacturer’s instructions to make sure it is working properly. Don’tassume that your release detection system is working and never needschecking. Read your owner’s manual, run the appropriate tests, and see if yoursystem is set up and working properly. Some interstitial monitoring systemshave a “test” or “self-diagnosis” mode that can easily and routinely run thesechecks.

t If your interstitial monitoring ever fails a test or indicates a release, seeSection 3 of this booklet for information on what to do next.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your release detection system, service all the systemcomponents according to the manufacturer’s service instructions. Tankprobes and other components can wear out and must be checked periodically.Many vendors recommend or require this maintenance activity at least annually.

t Keep interstitial monitoring access ports clearly marked and secured.

t Check your interstitial monitoring system owner’s manual often to answerquestions and to make sure you know the system’s O&M procedures. Callthe system’s vendor or manufacturer for a copy of the owner’s manual if youdon’t have one.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep These O&MRecords

t Keep results of your release detection system tests for at least 1 year.Your monitoring equipment may provide printouts that can be used as records.Unless you are recording actual release detection results at least every 30 daysand maintaining records for at least 1 year, you are not doing leak detectionright.

t Keep all records of calibration, maintenance, and repair of your releasedetection equipment for at least 1 year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certification ofyour leak detection equipment described above.

Page 11: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV �

Statistical Inventory Reconciliation (SIR) (for tanks & piping)

DescriptionOf ReleaseDetection

SIR is a method in which a trained professional uses sophisticated computersoftware to conduct a statistical analysis of inventory, delivery, anddispensing data. You must supply the professional with data every month.The result of the analysis may be PASS, INCONCLUSIVE, or FAIL.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your SIR vendor’s methodology is certified for the types oftanks, piping, and product on which you use SIR. Most vendors have theirleak detection devices tested and certified by a third party to verify that theirequipment meets specific performance requirements set by regulatoryagencies. If you don't have certified performance claims, have the vendorprovide them to you.

PerformThese O&M Actions

t Supply daily inventory data to your SIR vendor at least every 30 days. Thevendor will provide you with your leak detection results after the statisticalanalysis is completed.

t See Section 3 of this manual if your UST system fails a leak test.

t If you receive an “inconclusive” result, you must work with your SIRvendor to correct the problem and document the results of theinvestigation. An inconclusive result means that you have not performed leakdetection for that month. If you cannot resolve the problem, treat theinconclusive result as a suspected release and refer to Section 3.

t If you use an ATG system to gather data for the SIR vendor, periodicallyhave a qualified UST contractor, such as the vendor who installed yourATG, service all the ATG system components according to themanufacturer’s service instructions. Tank probes and other componentscan wear out and must be checked periodically. Many vendors recommend orrequire this maintenance activity at least annually. Do this according tomanufacturer’s instructions. See the checklist for ATG systems on page 7.

t If you stick your tank to gather data for the SIR vendor, make sure yourstick can measure to one-eighth of an inch and can measure the level ofproduct over the full range of the tank’s height. You should check yourmeasuring stick periodically to make sure that you can read the markings andnumbers and that the bottom of the stick is not worn.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep These O&M Records

t Keep results of your SIR tests for at least 1 year. Unless you are keepingrecords of the 30-day release detection results and maintaining those recordsfor at least 1 year, you are not doing leak detection right.

t Keep all vendor performance claims for at least 5 years. This includes thecertification of the SIR method discussed above.

t If you use an ATG system, keep all records of calibration, maintenance,and repair of your release detection equipment for at least 1 year.

t Keep the records of investigations conducted as a result of any monthlymonitoring conclusion of “Inconclusive” or “Fail” for at least 1 year. Thismay include the results of a tightness test performed during the investigation ora re-evaluation based on corrected delivery or dispenser data.

Page 12: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Vapor Monitoring (for tanks & piping)

Description Of ReleaseDetection

Vapor monitoring measures product vapors in the soil at the UST site tocheck for a leak. A site assessment must determine the number andplacement of monitoring wells that make sure a release is detected. NOTE:vapor monitors will not work well with substances that do not easily vaporize(such as diesel fuel).

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your vapor monitoring equipment is certified for the types ofstored contents on which the release detection system is used. Mostmanufacturers have their leak detection devices tested and certified by a thirdparty to verify that their equipment meets specific performance requirementsset by regulatory agencies. If you don't have certified performance claims, havethe manufacturer provide them to you.

Perform These O&M Actions

t Use your release detection system to test for leaks at least every 30 days.Testing more often than monthly can catch leaks sooner and reduce cleanupcosts and problems. Be sure you check all of your vapor monitoring wells.

t See Section 3 of this manual if your UST system fails a leak test.

t Frequently test your release detection system according to themanufacturer’s instructions to make sure it is working properly. Don’tassume that your release detection system is working and never needschecking. Some electronic vapor monitoring systems have a “test” or“self-diagnosis” mode. If you have components (such as monitoringequipment, probes or sensors) for your vapor monitoring system, read yourmanual and test your equipment to see if it is working properly.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your release detection system, service all the systemcomponents according to the manufacturer’s service instructions. Probesand other components can wear out and must be checked periodically. Manyvendors recommend or require this maintenance activity at least annually.

t Keep your vapor monitoring wells clearly marked and secured.

t Check your vapor monitoring system owner’s manual often to answerquestions and to make sure you know the system’s operation andmaintenance procedures. Call the system’s vendor or manufacturer for acopy of the owner’s manual if you don’t have one.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep These O&M Records

t Keep results of your release detection system tests for at least 1 year.Your monitoring equipment may provide printouts that can be used as records.Unless you are recording actual release detection results at least every 30 daysand maintaining records for at least 1 year, you are not doing leak detectionright.

t Keep all records of calibration, maintenance, and repair of your releasedetection equipment for at least 1 year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certification ofyour leak detection equipment described above.

Page 13: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Groundwater Monitoring (for tanks & piping)

DescriptionOf ReleaseDetection

Groundwater monitoring looks for the presence of liquid product floating onthe groundwater at the UST site. A site assessment must determine thenumber and placement of monitoring wells that make sure a release isdetected. NOTE: this method cannot be used at sites where groundwater ismore than 20 feet below the surface.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure any automated groundwater monitoring equipment is certifiedfor the types of stored contents on which the release detection system isused. Most manufacturers have their leak detection devices tested andcertified by a third party to verify that their equipment meets specificperformance requirements set by regulatory agencies. If you don't havecertified performance claims, have the manufacturer provide them to you.(Manual devices such as bailers are not generally certified.)

PerformThese O&M Actions

t Use your release detection system to test for leaks at least every 30 days.Testing more often than monthly can catch leaks sooner and reduce cleanupcosts and problems. Be sure you check all of your groundwater monitoringwells.

t See Section 3 of this manual if your UST system fails a leak test.

t Frequently test your automated release detection system according tothe manufacturer’s instructions to make sure it is working properly. Don’tassume that your release detection system is working and never needschecking. Some electronic groundwater monitoring systems have a “test” or“self-diagnosis” mode. If you have components (such as monitoringequipment, probes or sensors) for your vapor monitoring system, read yourmanual and test your equipment to see if it is working properly. Manual devicesshould be periodically checked to make sure they are working properly.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your release detection system, service all the systemcomponents according to the manufacturer’s service instructions. Probesand other components can wear out and must be checked periodically. Manyvendors recommend or require this maintenance activity at least annually.

tt Keep your groundwater monitoring wells clearly marked and secured.

tt Check your groundwater monitoring system owner’s manual often toanswer questions and to make sure you know the system’s operationand maintenance procedures. Call the system’s vendor or manufacturer for acopy of the owner’s manual if you don’t have one.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep These O&M Records

t Keep results of your release detection system tests for at least 1 year.Your monitoring equipment may provide printouts that can be used as records.Unless you are recording actual release detection results at least every 30 daysand maintaining records for at least 1 year, you are not doing leak detectionright.

t Keep all records of calibration, maintenance, and repair of your releasedetection equipment for at least 1 year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certification ofyour leak detection equipment described above.

Page 14: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Inventory Control And Tank Tightness Testing (for tanks only)

DescriptionOf ReleaseDetection

This temporary method combines monthly inventory control with periodic tank tightnesstesting. Inventory control involves taking measurements of tank contents and recordingthe amount of product pumped each operating day, measuring and recording tankdeliveries, and reconciling all this data at least once a month. This combined methodalso includes tightness testing, a sophisticated test performed by trained professionals.

NOTE: This combination method can only be used temporarily for up to 10 years afterinstalling a new UST or for up to 10 years after your tank meets the corrosion protectionrequirements.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your tank tightness testing is certified for the types of tanks and storedcontents on which the tightness test is used. Most tightness test methods are certifiedby a third party to verify that they meet specific performance requirements set by regulatoryagencies. If you don't have certified performance claims, have the tightness tester providethem to you.

PerformThese O&M Actions

t Take inventory readings and record the numbers at least each day that product isadded to or taken out of the tank. You may want to use the “Daily Inventory Worksheet”provided for you on the next page.

t Reconcile the fuel deliveries with delivery receipts by taking inventory readings before and after each delivery. Record these readings on a “Daily Inventory Worksheet”(see next page).

t Reconcile all your data at least every 30 days. Use a “Monthly Inventory Record” (seepage 14 for an example).

t Have a tank tightness test conducted at least every 5 years. This testing needs to beconducted by a professional trained in performing tank tightness testing.

t See Section 3 of this manual if your tank fails a tightness test or if fails twoconsecutive months of inventory control.

t Ensure that your measuring stick can measure to the nearest one-eighth inch andcan measure the level of product over the full range of the tank’s height. You shouldcheck your measuring stick periodically to make sure that you can read the markings andnumbers and that the bottom of the stick is not worn.

t Ensure that your product dispenser is calibrated according to local standards or toan accuracy of 6 cubic inches for every 5 gallons of product withdrawn.

t Measure the water in your tank to the nearest one-eighth inch at least once a monthand record the results on the reconciliation sheet. You can use a paste that changescolor when it comes into contact with water.

t Make sure employees who run, monitor, or maintain the release detection systemknow exactly what they have to do and to whom to report problems. Develop andmaintain regular training programs for all employees.

Keep These O&MRecords

t Keep results of your release detection system tests for at least 1 year. Yourmonitoring equipment may provide printouts that can be used as records. Unless you arerecording actual release detection results at least every 30 days and maintaining recordsfor at least 1 year, you are not doing leak detection right.

t Keep the results of your most recent tightness test.

t Keep all certification and performance claims for tank tightness test performed atyour UST site for at least 5 years.

Page 15: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

DAILY INVENTORY WORKSHEETFACILITY NAME: _________________________________________

YOUR NAME: _________________________________________

DATE: _________________________________________

TANK IDENTIFICATION

Type of Fuel

Tank Size in Gallons

END STICK INCHES

AMOUNT PUMPED� � � � �

Totalizer Reading

Totalizer Reading

Totalizer Reading

Totalizer Reading

Totalizer Reading

Totalizer Reading

Totalizer Reading

Totalizer Reading

TODAY'S SUM OFTOTALIZERS

Previous Day's Sum of Totalizers

AMOUNT PUMPED TODAY

DELIVERY RECORD� � � � �

Inches of Fuel Before Delivery

Gallons of Fuel BeforeDelivery

(from tank chart)

Inches of Fuel After Delivery

Gallons of Fuel After Delivery(from tank chart)

GALLONS DELIVERED(STICK)[Gallons "After"

� Gallons "Before"]

GROSS GALLONSDELIVERED (RECEIPT)

Page 16: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

MONTHLY INVENTORY RECORDMONTH/YEAR :_______/______ TANK IDENTIFICATION & TYPE OF FUEL:____________________________

FACILITY NAME:_________________________________________________

DATE OF WATER CHECK: ________ LEVEL OF WATER (INCHES):______

DATE

STARTSTICK

INVENTORY(GALLONS)

GALLONSDELIVERED

GALLONS PUMPED

BOOK INVENTORY(GALLONS)

END STICK INVENTORY___________________________

(INCHES) (GALLONS)

DAILY OVER (+)OR SHORT (��)

["End" �� "Book"]INITIALS

1 (+) (-) (=)

2 (+) (-) (=)

3 (+) (-) (=)

4 (+) (-) (=)

5 (+) (-) (=)

6 (+) (-) (=)

7 (+) (-) (=)

8 (+) (-) (=)

9 (+) (-) (=)

7 (+) (-) (=)

8 (+) (-) (=)

9 (+) (-) (=)

10 (+) (-) (=)

11 (+) (-) (=)

12 (+) (-) (=)

13 (+) (-) (=)

14 (+) (-) (=)

15 (+) (-) (=)

16 (+) (-) (=)

17 (+) (-) (=)

18 (+) (-) (=)

19 (+) (-) (=)

20 (+) (-) (=)

21 (+) (-) (=)

22 (+) (-) (=)

23 (+) (-) (=)

24 (+) (-) (=)

25 (+) (-) (=)

26 (+) (-) (=)

27 (+) (-) (=)

28 (+) (-) (=)

29 (+) (-) (=)

30 (+) (-) (=)

31 (+) (-) (=)

TOTAL GALLONS PUMPED > TOTAL GALLONS OVER OR SHORT >

LEAK CHECK: Compare these numbersDrop the last two digitsfrom the TOTAL GALLONSPUMPED number and enter here: _____________ + 130 = ____________ gallons

Is the "TOTAL GALLONS OVER OR SHORT" LARGER than "LEAK CHECK" result? YES NO (circle one)

If your answer is "YES" for 2 MONTHS IN A ROW, notify the regulatory agency as soon as possible.

KEEP THIS PIECE OF PAPER ON FILE FOR AT LEAST 1 YEAR

Page 17: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Manual Tank Gauging (for tanks 1,000 gallons or less only)

DescriptionOf ReleaseDetection

This method may be used only for tanks of 1,000 gallons or less capacitymeeting certain requirements. These requirements (tank size, tankdimension, and test time) are found in the manual tank gauging record onthe next page. Manual tank gauging involves taking your tank out ofservice for the testing period (at least 36 hours) each week, during whichthe contents of the tank are measured twice at the beginning and twice atthe end of the test period. The measurements are then compared toweekly and monthly standards to determine if the tank is tight.

HaveCertificationFor YourReleaseDetectionMethod

None required.

PerformThese O&M Actions

t Once a week, record two inventory readings at the beginning of thetest, allow the tank to sit undisturbed for the time specified in the“Manual Tank Gauging Record” on the next page, and record twoinventory readings at the end of the test (use any form comparable tothe one on the following page).

t Reconcile the numbers weekly and record them on a “Manual TankGauging Record” (see the next page).

t See Section 3 of this manual if your tank fails the weekly standard.

t At the end of 4 weeks, reconcile your records for the monthlystandard and record the result on a “Manual Tank Gauging Record”(see the next page).

t See Section 3 of this manual if your tank fails the monthly standard.

t Ensure that your measuring stick can measure to the nearest one-eighth inch and can measure the level of product over the full rangeof the tank’s height. You should check your measuring stick periodicallyto make sure that you can read the markings and numbers and that thebottom of the stick is not worn.

t Make sure employees who run, monitor, or maintain the releasedetection system know exactly what they have to do and to whom toreport problems. Develop and maintain regular training programs for allemployees.

Keep These O&M Records

t Keep your manual tank gauging records for at least 1 year. Unless youare recording actual release detection results weekly and at least every 30days and maintaining records for at least 1 year, you are not doing leakdetection right.

Page 18: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

MANUAL TANK GAUGING RECORD MONTH _______________ YEAR _________TANK IDENTIFICATION: _____________________________

PERSON COMPLETING FORM:______________________________Circle your tank size, test duration, and weekly/monthly standards in the table below: FACILITY NAME:_______________________________________

Tank Size MinimumDurationOf Test

Weekly Standard(1 test)

Monthly Standard(4-test average)

Compare your weekly readings and the monthly average of the 4weekly readings with the standards shown in the table on the left.

If the calculated change exceeds the weekly standard, the UST maybe leaking. Also, the monthly average of the 4 weekly test resultsmust be compared to the monthly standard in the same way.

If either the weekly or monthly standards have been exceeded, theUST may be leaking. As soon as possible, call your implementingagency to report the suspected leak and get further instructions.

up to 550 gallons 36 hours 10 gallons 5 gallons

551-1,000 gallons(when tank diameter is 64")

44 hours 9 gallons 4 gallons

551-1,000 gallons(when tank diameter is 48")

58 hours 12 gallons 6 gallons

551-1,000 gallons (also requiresperiodic tank tightness testing)

36 hours 13 gallons 7 gallons

1,001-2,000 gallons (also requiresperiodic tank tightness testing)

36 hours 26 gallons 13 gallons

Start Test (month, day,

and time)

FirstInitialStick

Reading

SecondInitialStick

Reading

AverageInitial

Reading

InitialGallons(convertinches togallons)

[a]

End Test (month, day, and

time)

FirstEndStick

Reading

SecondEndStick

Reading

AverageEnd

Reading

EndGallons(convertinches togallons)

[b]

ChangeIn TankVolume

In Gallons+ or (—)[a—b]

Tank Passes Test

(circleYES or NO)

Date:Time: AM/PM

Date: Time: AM/PM

Y N

Date:Time: AM/PM

Date:Time: AM/PM

Y N

Date:Time: AM/PM

Date:Time: AM/PM

Y N

Date:Time: AM/PM

Date:Time: AM/PM

Y N

KEEP THIS PIECE OF PAPER ON FILE FOR AT LEAST 1 YEAR To see how close you are to the monthlystandard, divide the sum of the 4 weekly

readings by 4 and enter result here >

Y N

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Page 19: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Manual Tank Gauging And Tank Tightness Testing (for tanks 2,000 gallons or less only)

DescriptionOf ReleaseDetection

This temporary method combines manual tank gauging with periodic tank tightnesstesting. It may be used only for tanks of 2,000 gallons or less capacity. Manual tankgauging involves taking your tank out of service for the testing period (at least 36hours) each week, during which the contents of the tank are measured twice at thebeginning and twice at the end of the test period. The measurements are thencompared to weekly and monthly standards to determine if the tank is tight. Thiscombined method also includes tightness testing, a sophisticated test performed bytrained professionals.

NOTE: This combination method can only be used temporarily for up to ten years afterinstalling a new UST or for up to 10 years after your tank meets the corrosionprotection requirements.

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your tank tightness testing is certified for the types of tanks and storedcontents on which the tightness test is used. Most tightness test methods are certifiedby a third party to verify that they meet specific performance requirements set byregulatory agencies. If you don't have certified performance claims, have the tightnesstester provide them to you.

PerformThese O&M Actions

t Once a week, record two inventory readings at the beginning of the test, allow thetank to sit undisturbed for the time specified in the “Manual Tank Gauging Record”on page 16, and record two inventory readings at the end of the test (use any formcomparable to the one on page 16).

t Reconcile the numbers weekly and record them on a “Manual Tank GaugingRecord” (see page 16).

t See Section 3 of this manual if your tank fails the weekly standard.

t At the end of 4 weeks, reconcile your records for the monthly standard and recordthe result on a “Manual Tank Gauging Record” (see page 16).

t See Section 3 of this manual if your tank fails the monthly standard.

t Conduct a tank tightness test at least every 5 years. This testing needs to beconducted by a professional trained in performing tank tightness testing.

t See Section 3 of this manual if your tank fails the tightness test.

t Ensure that your measuring stick can measure to the nearest one-eighth inch andcan measure the level of product over the full range of the tank’s height. You shouldcheck your measuring stick periodically to make sure that you can read the markings andnumbers and that the bottom of the stick is not worn.

t Make sure employees who run, monitor, or maintain the release detection systemknow exactly what they have to do and to whom to report problems. Develop andmaintain regular training programs for all employees.

Keep These O&MRecords

tt Keep your manual tank gauging records for at least 1 year. Unless you are recordingactual release detection results at least weekly and every 30 days and maintaining recordsfor at least 1 year, you are not doing leak detection right.

tt Keep the results of your most recent tightness test.

tt Keep all certification and performance claims for tank tightness test performed atyour UST site for at least 5 years.

Page 20: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Automatic Line Leak Detection (for pressurized piping only)

DescriptionOf ReleaseDetection

Automatic line leak detectors (LLDs) are designed to detect a catastrophicrelease from pressurized piping. Automatic LLDs must be designed to detecta leak at least as small as 3 gallons per hour at a line pressure of 10 psi within1 hour. When a leak is detected, automatic LLDs must shut off the productflow, restrict the product flow, or trigger an audible or visual alarm. NOTE:Automatic LLDs need to be installed and operated as close as possible to the tank (LLDs are designed to detect a leak and restrict flow only between thedetector and the dispenser).

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your release detection equipment is certified for the types ofpiping and stored contents on which the release detection system is used.Most manufacturers have their leak detection devices tested and certified by athird party to verify that their equipment meets specific performancerequirements set by regulatory agencies. If you don't have certified performanceclaims, have the manufacturer provide them to you.

PerformThese O&M Actions

t Frequently test your automatic LLDs according to the manufacturer’sinstructions to make sure it is working properly. Don’t assume that yourrelease detection system is working and never needs checking. Somemonitoring systems have a “test” or “self-diagnosis” mode.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your release detection system, service all the systemcomponents according to the manufacturers’ service instructions.Components can wear out and must be checked periodically. Many vendorsrecommend or require this maintenance activity at least annually.

t See Section 3 of this manual if your LLD detects a leak.

t Make sure employees who run, monitor, or maintain the release detectionsystem know exactly what they have to do and to whom to reportproblems. Develop and maintain regular training programs for all employees.

Keep These O&M Records

t For at least a year, keep the annual test that demonstrates that the LLD isfunctioning properly.

t If used for monthly monitoring, keep results of your release detectionsystem tests for at least 1 year. Your monitoring equipment system mayprovide printouts that can be used as records. Unless you are recording actualrelease detection results at least every 30 days and maintaining records for atleast 1 year, you are not doing leak detection right.

t Keep all records of calibration, maintenance, and repair of your releasedetection equipment for at least 1 year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certification ofyour leak detection equipment described above.

Page 21: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Line Tightness Testing (for piping only)

DescriptionOf ReleaseDetection

This method uses a periodic line tightness test to determine if your pipingis leaking. Tightness testing can be performed by either a trainedprofessional or by using a permanently installed electronic system(sometimes connected to an automatic tank gauging system).

HaveCertificationFor YourReleaseDetectionMethod

t Make sure your line tightness testing or permanently installedelectronic system is certified for the types of piping and storedcontents on which the release detection system is used. Most tightnesstest methods and release detection equipment have been tested andcertified by a third party to verify that the equipment or services meetspecific performance requirements set by regulatory agencies. If you don'thave certified performance claims, have the tightness tester or equipmentmanufacturer provide them to you.

PerformThese O&M Actions

t If line tightness testing is used for pressurized piping, the test must beconducted at least annually.

t If line tightness testing is used for suction piping, the test must beconducted at least every three years. “Safe suction” piping as describedat the bottom of page 3 may not need release detection testing.

t This tightness testing must be conducted by a professional trained inperforming line tightness testing or by using a permanently installedelectronic system.

t See Section 3 of this manual if your piping fails the tightness test or ifthe electronic system indicates a leak.

t Periodically have a qualified UST contractor, such as the vendor whoinstalled your release detection system, service all the systemcomponents according to the manufacturers’ service instructions.Components can wear out and must be checked periodically. Many vendorsrecommend or require this maintenance activity at least annually.

t Make sure employees who run, monitor, or maintain the releasedetection system know exactly what they have to do and to whom toreport problems. Develop and maintain regular training programs for allemployees.

Keep These O&M Records

t Keep results of your release detection system tests for at least 1 year.Your monitoring equipment may provide printouts that can be used asrecords. Unless you are recording actual release detection results at leastevery 30 days and maintaining records for at least 1 year, you are not doingleak detection right.

t If you use a permanently installed electronic system, keep all recordsof calibration, maintenance, and repair of your equipment for at least 1year.

t Keep all performance claims supplied by the installer, vendor, ormanufacturer for at least 5 years. These records include the certificationof your leak detection equipment described above.

Page 22: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

30-Day Release Detection Monitoring Record(may be used for monitoring wells, interstitial monitoring, and automatic tank gauging)

RELEASE DETECTION METHOD:___________________________________

FACILITY NAME:___________________________________

Date YourName

UST System (Tank & Piping)(Enter “N” for NO RELEASE DETECTED or “Y” for a SUSPECTED

OR CONFIRMED RELEASE)

UST # UST # UST # UST #

KEEP THIS PIECE OF PAPER AND ANY ASSOCIATED PRINTOUTS ONFILE FOR AT LEAST 1 YEAR FROM THE DATE OF THE LAST ENTRY

Page 23: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 21

Section 3 — Suspected Or Confirmed Releases

You need to be fully prepared to respond to releases BEFORE they may occur. You needto know what to do when release detection methods indicate a suspected or confirmedrelease. Be ready to take the following steps, as appropriate.

Stop The Release

# Take immediate action to prevent the release of more product.

# Turn off the power to the dispenser and “bag” the nozzle.

# Make sure you know where your emergency shutoff switch is located.

# Empty the tank, if necessary, without further contaminating the site. You may need theassistance of your supplier or distributor.

Contain The Spill Or Overfill

Contain, absorb, and clean up any surface spills or overfills. You should keep enoughabsorbent material at your facility to contain a spill or overfill of petroleum products unt ilemergency response personnel can respond to the incident. The suggested suppliesinclude, but are not limited to, the following:

# Containment devices, such as containment booms, dikes, and pillows.

# Absorbent material, such as kitty litter, chopped corn cob, sand, and sawdust. (Be sureyou properly dispose of used absorbent materials.)

# Mats or other material capable of keeping spill or overfill out of nearby storm drains.

# Spark-free flash light.

# Spark-free shovel.

# Buckets.

# Reels of “caution tape,” traffic cones, and warning signs.

# Personal protective gear.

Also, identify any fire, explosion or vapor hazards and take action to neutralize thesehazards.

Page 24: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 22

Call For Help

Contact your local fire or emergency response authority. Make sure you have these crucialtelephone numbers prominently posted where you and your employees can easily seethem. See the next page for a form you can copy and post.

Report To Authorities

If you observe any of the following, contact your State’s underground storage tankregulatory authority to report a suspected or confirmed release as soon as possible (within24 hours):

# Any spill or overfill of petroleum that exceeds 25 gallons or that causes a sheen onnearby surface water. (Spills and overfills under 25 gallons that are contained andimmediately cleaned up do not have to be reported. If they can’t be quickly cleaned upthey must be reported to your regulatory agency.)

# Any released regulated substances at the UST site or in the surrounding area — suchas the presence of liquid petroleum; soil contamination; surface water or groundwatercontamination; or petroleum vapors in sewer, basement, or utility lines.

# Any unusual operating conditions you observe — such as erratic behavior of thedispenser, a sudden loss of product, or an unexplained presence of water in the tank.However, you are not required to report if:

C The system equipment is found to be defective, but not leaking, and is immediatelyrepaired or replaced.

# Results from your release detection system indicate a suspected release. However, youare not required to report if:

C The monitoring device is found to be defective and is immediately repaired,recalibrated, or replaced and further monitoring does not confirm the initialsuspected release, or

C In the case of inventory control, a second month of data does not confirm the initialresult.

The next page contains a blank list for names and phone numbers of important contacts. Fill out this information for your facility so that you will know who to call in case of anemergency. Remove this page from the manual, copy it, fill it out, and post it in a prominentplace at your facility.

Copy the next page and update it often. Make sure everyone atyour UST facility is familiar with this list of contacts.

Page 25: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 23

Release ResponseImportant Contact Information

Contact Name Phone #

State UST Agency:

Local UST Agency:

Fire Department:

Ambulance:

Police Department:

Repair Contractor:

Other Contacts:

U Release Response Checklist

‘ Stop the release: Take immediate action to prevent the release of more product. Turn off the

power to the dispenser and “bag ” the nozzle. Make sure you know w here your emergen cy shutoff

switch is loc ated. Em pty the tank , if necess ary, without fu rther con tamina ting the site

‘ Contain the s pill or overfill: Contain, absorb, and clean up any surface releases. Identify any fire,

explosion or vapor hazards and take action to neutralize these hazards.

‘ Call for help and to report suspected or confirmed releases: Contact your local fire or

eme rgency re spons e author ity. Contact you r State’s un dergrou nd stora ge tank regulatory a uthority

within 24 hours.

Page 26: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

What’s The Difference?

Spill Protection: A spill bucket is installed at the fillpipe to contain the drips and spills offuel that can occur when thedelivery hose is uncoupled from thefill pipe after delivery.

Overfill Protection: Equipment is installed on the USTthat is designed to stop productflow, reduce product flow, or alertthe delivery person during deliverybefore the tank becomes full andbegins releasing petroleum into theenvironment.

Section 4 — Spill And Overfill Protection

The purpose of spill and overfill protectionequipment is to eliminate the potential for arelease during fuel deliveries. The equipmentmust be in working order and used properly to provide adequate protection from spills andoverfills.

Even the best spill and overfill protectionequipment can become faulty over time if notproperly operated and maintained.

Only one gallon of fuel leaking each weekfrom a poorly maintained spill bucket canresult in up to 195 tons of contaminated soil ina year.

Improper maintenance of the spill bucket atthe UST site pictured below contributed tosignificant contamination of soil andgroundwater.

The following pages in this section focus on how you can routinely make sure your spill andoverfill equipment is operating effectively.

Page 27: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

If your UST never receivesdeliveries of more than 25 gallonsat a time, the UST does not needto meet the spill protectionrequirements. Many used oil tanksfall into this category. Even thoughthese USTs are not required tohave overfill protection, you shouldconsider using overfill protection as part of good UST systemmanagement.

Examples of Spill Buckets

What Are The Basics Of Spill Protection?

Your USTs must have catchment basins — alsocalled spill buckets — installed at the fill pipe tocontain spills that may occur as a result of fueldeliveries.

� The spill bucket is designed to temporarilycontain product spills that might occur duringfuel delivery. To contain a spill, the spill bucketmust be liquid tight.

� The spill bucket is not designed to containfuel for long periods of time and must bequickly emptied and contents disposed ofproperly.

� Spill buckets need to be largeenough to contain any fuel that mayspill when the delivery hose isuncoupled from the fill pipe. Spillbuckets typically range in size from 5gallons to 25 gallons.

� If you use a checklist for correctfilling practices (see page 33), spillsshould be eliminated or reduced tovery small volumes that your spillbucket can easily handle.

How do you maintain your spill bucket?

The checklist below provides information on properly maintaining your spill bucket.

� Spill Bucket O&M Checklistt Keep your spill bucket empty of liquids.

Some spill buckets are equipped with a valve that allows you to drain accumulated fuel intoyour UST. Others may be equipped with a manual pump so fuel can be put into your UST bypumping it through the fill pipe. However, keep in mind that when you pump out or drain yourspill bucket into your UST, any water and debris may also enter the UST. If a basin is notequipped with drain valve or pump, then any accumulated fuel or water must be removedmanually and disposed of properly.

t Periodically check your spill bucket to remove any debris.Debris could include soil, stones, or trash.

t Periodically check to see if your spill bucket is still liquid tight.Have a qualified UST contractor inspect your spill bucket for signs of wear, cracks, or holes.Based on this inspection, the contractor may suggest a test to determine if the spill bucket istight or needs repair or replacement.

Page 28: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

If your UST never receivesdeliveries of more than 25 gallonsat a time, the UST does not needto meet the overfill protectionrequirements. Many used oil tanksfall into this category. Even thoughthese USTs are not required tohave overfill protection, you shouldconsider using overfill protection as part of good UST systemmanagement.

What Are The Basics Of Overfill Protection?

Your USTs must have overfill protection installedto help prevent the overfilling of tanks.

Three types of overfill protection devices arecommonly used:

� Automatic Shutoff Devices

� Overfill Alarms

� Ball Float Valves

Each of these forms of overfill protection isdiscussed in detail on the following pages.

How Can You Help The Delivery Person Avoid Overfills?

To protect your business, you must make every effort to help the delivery person avoidoverfilling your UST.

Use A Checklist On Correct Filling Practices

If correct filling practices are used, you will not exceed the UST’s capacity — see page 33for a checklist on correct filling procedures. Overfills are caused when the delivery personmakes a mistake, such as ignoring an overfill alarm.

Use Signs, Alert Your Delivery Person

The delivery person should know what type of overfill device is present on each tank atyour facility and what action will occur if the overfill device is triggered — such as a visualand/or audible alarm or that the product flow into the tank will stop or slow significantly.

Educate and alert your delivery person by placing a clear sign near your fill pipes, inplain view of the delivery person. An example of such a sign follows on the next page.

Page 29: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

DELIVERY PERSON — AVOID OVERFILLS

� An overfill alarm is used for overfill protection at this facility.

� Do not tamper with this alarm in any attempt to defeat its purpose.

� When the tank is 90% full, the overfill alarm whistles and a red light flashes.

� If you hear the alarm whistle or see the red light flashing,

STOP THE DELIVERY IMMEDIATELY!

Make Sure You Order The Right Amount

Also, you need to make sure you’ve ordered the right amount of product for delivery.Order only the quantity of fuel that will fit into 90% of the tank. For example, if you have a10,000 gallon tank with 2,000 gallons already in the tank, you would order at the most a7,000 gallon delivery (90% of 10,000 is 9,000 gallons; subtracting the 2,000 gallons alreadyin the tank leaves a maximum delivery of 7,000 gallons). Use the checklist formula on page33 below. Do your homework right and you reduce the chance of overfills.

Page 30: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

You should not use an automatic shutoffdevice for overfill protection if your USTreceives pressurized deliveries.

What Should You Do To Operate And Maintain Your Automatic Shutoff Device?

The automatic shutoff device is a mechanical deviceinstalled in line with the drop tube within the fill pipe riser.It slows down and then stops the delivery when theproduct has reached a certain level in the tank. It shouldbe positioned so that the float arm is not obstructed andcan move through its full range of motion.

When installed and maintained properly, the shutoffvalve will shut off the flow of fuel to the UST at 95% ofthe tank’s capacity or before the fittings at the top of thetank are exposed to fuel.

� Basic O&M Checklist For Automatic Shutoff Devicest A qualified UST contractor periodically checks to make sure that the automatic shutoff device is

functioning properly and that the device will shut off fuel flowing into the tank at 95% of the tankcapacity or before the fittings at the top of the tank are exposed to fuel:

� Make sure the float operates properly.

� Make sure that there are no obstructions in the fill pipe that would keep the floating mechanismfrom working.

t You have posted signs that the delivery person can easily see and that alert the delivery person tothe overfill warning devices and alarms in use at your facility.

Page 31: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

What Should You Do To Operate And Maintain YourElectronic Overfill Alarm?

This type of overfill device activates an audible and/or visual warningto delivery personnel when the tank is either 90% full or is within oneminute of being overfilled. The alarm must be located so that itcan be seen and/or heard from the UST delivery location. Oncethe electronic overfill alarm sounds, the delivery person hasapproximately one minute to stop the flow of fuel to the tank.

Electronic overfill alarm devices have no mechanism to shut off orrestrict flow. Therefore, the fuel remaining in the delivery hose afterthe delivery has been stopped will flow into the tank as long as thetank is not yet full.

� Basic O&M Checklist For Overfill Alarmst A qualified UST contractor periodically checks your electronic overfill alarm to make sure that it is

functioning properly and that the alarm activates when the fuel reaches 90% of the tank capacity oris within one minute of being overfilled:

� Ensure that the alarm can be heard and/or seen from where the tank is fueled.

� Make sure that the electronic device and probe are operating properly.

t You have posted signs that the delivery person can easily see and that alert the delivery person tothe overfill warning devices and alarms in use at your facility.

Page 32: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

You should not use a ball float valve for overfill protection if any of the following apply:

� Your UST receives pressurized deliveries.� Your UST system has suction piping.� Your UST system has single point (coaxial) stage 1 vapor recovery.

What Should You Do To Operate And Maintain Your Ball Float Valve?

The ball float valve — also called a float vent valve — isinstalled at the vent pipe in the tank and restricts vapor flowin an UST as the tank gets close to being full. The ball floatvalve should be set at a depth which will restrict vapor flowout of the vent line during delivery at 90% of the UST’scapacity or 30 minutes prior to overfilling.

As the tank fills, the ball in the valve rises, restricting theflow of vapors out of the UST during delivery. The flow rateof the delivery will decrease noticeably and should alert thedelivery person to stop the delivery.

For ball float valves to work properly, the top of the tank must be air tight so that vaporscannot escape from the tank. Everything from fittings to drain mechanisms on spill bucketsmust be tight and be able to hold the pressure created when the ball float valve engages.

� Basic O&M Checklist For Ball Float Valvest A qualified UST contractor periodically checks to make sure that the ball float valve is functioning

properly and that it will restrict fuel flowing into the tank at 90% of the tank capacity or 30 minutesprior to overfilling:

� Ensure that the air hole is not plugged.

� Make sure the ball cage is still intact.

� Ensure the ball still moves freely in the cage.

� Make sure the ball still seals tightly on the pipe.

tt You have posted signs that the delivery person can easily see and that alert the delivery person tothe overfill warning devices and alarms in use at your facility.

Page 33: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

� Spill And Overfill O&M Checklist

SpillBucket

t Keep your spill bucket empty of liquids.Some spill buckets are equipped with a drainage valve which allows you to drainaccumulated fuel into to your UST. Others can be equipped with a manual pump so fuelcan be put into your UST by pumping it through the fill pipe. However, keep in mind thatwhen you pump out or drain your spill bucket into your UST, any water and debris may alsoenter the UST. If a spill bucket is not equipped with a drain valve or pump, then anyaccumulated fuel or water must be removed manually and disposed of properly.

t Periodically check your spill bucket to remove any debris.Debris could include soil, stones, or trash.

t Periodically check to see if your spill bucket is still liquid tight.Have a qualified UST contractor inspect your spill bucket for signs of wear, cracks, orholes. Based on this inspection, the contractor may suggest a test to determine if the spillbucket is tight or needs repair or replacement.

AutomaticShutoffDevices

t A qualified UST contractor periodically checks to make sure that the automatic shutoffdevice is functioning properly and that the device will shut off fuel flowing into the tank at95% of the tank capacity or before the fittings at the top of the tank are exposed to fuel:

& Make sure the float operates properly.

& Make sure that there are no obstructions in the fill pipe that would keep the floatingmechanism from working.

t You have posted signs that the delivery person can easily see and that alert the deliveryperson to the overfill warning devices and alarms in use at your facility.

OverfillAlarms

t A qualified UST contractor periodically checks your electronic overfill alarm to make surethat it is functioning properly and that the alarm activates when the fuel reaches 90% of thetank capacity or is within one minute of being overfilled:

& Ensure that the alarm can be heard and/or seen from where the tank is fueled.

& Make sure that the electronic device and probe are operating properly.

t You have posted signs that the delivery person can easily see and that alert the deliveryperson to the overfill warning devices and alarms in use at your facility.

Ball Float Valves

t A qualified UST contractor periodically checks to make sure that the ball float valve isfunctioning properly and that it will restrict fuel flowing into the tank at 90% of the tankcapacity or 30 minutes prior to overfilling:

& Ensure that the air hole is not plugged.

& Make sure the ball cage is still intact.

& Ensure the ball still moves freely in the cage.

& Make sure the ball still seals tightly on the pipe.

t You have posted signs that the delivery person can easily see and that alert the deliveryperson to the overfill warning devices and alarms in use at your facility.

Page 34: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

What Are Your Responsibilities For Correct Filling Practices?

As an owner or operator you are responsible for ensuring that releases due to spilling oroverfilling do not occur during fuel delivery.

As part of this responsibility, you must:

� Ensure that the amount of product to be delivered will fit into the available empty spacein the tank; and

� Ensure that the transfer operation is monitored constantly to prevent overfilling andspilling.

One way help ensure the above requirements are met is to follow the checklist on the nextpage. The checklist describes necessary activities before, during, and after a fuel delivery.

Page 35: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

� Correct Filling Checklist

What To DoBeforeFilling Your USTs

t Post clear signs that alert delivery persons to the overfill devices and alarms in use at yourfacility.

t Make and record accurate readings for product and water in the tank before fuel delivery.

t Order only the quantity of fuel that will fit into 90% of the tank.

REMEMBER, the formula for determining the maximum amount of gasoline toorder is:

(Tank capacity in gallons X 90% ) — Product currently in tank = Maximum amount offuel to order

Example: (10,000 gal X 0.9 ) — 2,000 gal = 7,000 gal maximum amount to order

t Ensure fuel delivery personnel know the type of overfill device present at the tank and whatactions to perform if it activates. For example, use sample sign on page 28 of this chapter.

t Review and understand the spill response procedures.

t Verify that your spill bucket is empty, clean, and will contain spills.

What To DoWhile Your USTs Are BeingFilled

t Keep fill ports locked until the fuel delivery person requests access.

t Have an accurate tank capacity chart available for the fuel delivery person.

t The fuel delivery person makes all hook-ups. The person responsible for monitoring thedelivery should remain attentive and observe the entire fuel delivery, be prepared to stopthe flow of fuel from the truck to the UST at any time, and respond to any unusual condition,leak, or spill which may occur during delivery.

t Have response supplies readily available for use in case a spill or overfill occurs (seeSection 3).

t Provide safety barriers around the fueling zone.

t Make sure there is adequate lighting around the fueling zone.

What To DoAfter Filling Your USTs

t Following complete delivery, the fuel delivery person is responsible for disconnecting allhook-ups.

t Return spill response kit and safety barriers to proper storage locations.

t Make and record accurate readings for product and water in the tank after fuel delivery.

t Verify the amount of fuel received.

t Make sure fill ports are properly secured.

t Ensure the spill bucket is free of product and clean up any small spills.

Page 36: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Section 5 — Corrosion Protection

To prevent leaks, all parts of your UST system that are underground and routinely containproduct need to be protected from corrosion. The UST system includes the tank, piping,and ancillary equipment, such as flexible connectors, fittings, and pumps. Unprotectedmetal UST components can deteriorate and leak when underground electrical currents actupon them.

One way to protect UST components fromcorrosion is to make them with nonmetallic,noncorrodible materials, such as USTs madeof (or clad or jacketed with) fiberglass reinforcedplastic (FRP) or other noncorrodible materials —as illustrated by the FRP tank on the right.Noncorrodible USTs like these do not requireO&M for corrosion protection.

UST components made from metal, however,that routinely contain product and are in directcontact with the ground need corrosion protection provided by cathodic protection or (insome cases) lining the interior of the tank, as described below. These options requireO&M.

NOTE: Metal tanks or piping installed after December 22, 1988 must have a dielectriccoating (a coating that does not conduct electricity) in addition to the cathodicprotection described below.

Cathodic Protection Using Sacrificial Anode Systems

Sacrificial anodes are buried and attached to USTcomponents for corrosion protection — asillustrated on the right by an anode attached to atank. Anodes are pieces of metal that are moreelectrically active than steel, and thus they sufferthe destructive effects of corrosion rather than thesteel they are attached to.

Cathodic Protection Using Impressed Current Systems

An impressed current system — as shown onthe right — uses a rectifier to provide directcurrent through anodes to the tank or piping toachieve corrosion protection. The steel isprotected because the current going to thesteel overcomes the corrosion-causing currentflowing away from it. The cathodic protectionrectifier must always be on and operatingto protect your UST system from corrosion.

Page 37: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Corrosion Protection Using Internal Lining Of The Tank

This corrosion protection option applies only totanks installed before December 22, 1988.These older tanks can be internally lined bytrained professionals to meet the corrosionprotection requirements — as shown on theright, in which a professional follows industrycodes to safely and effectively line a tank’sinterior.

It may help you to see your corrosion protection options displayed in the following table.

Corrosion Protection ChoicesOption Description

Noncorrodible Material The tank or piping is constructed of noncorrodible material.

Steel Tank Clad or Jacketedwith a Noncorrodible Material

Examples of cladding or jacket material include fiberglass andurethane. Does not apply to piping.

Coated and CathodicallyProtected Steel Tanks orPiping

Steel tank and piping is well-coated with a dielectric material andcathodically protected.

Cathodically ProtectedNoncoated Steel Tanks orPiping

This option is only for steel tanks and piping installed beforeDecember 22, 1988. Cathodic protection is usually provided by animpressed current system.

Internal Lining of Tanks This option is only for steel tanks installed before December 22,1988. A lining is applied to the inside of the tank. Does not apply topiping.

Combination of CathodicallyProtected Steel and InternalLining of Tanks

This option is only for steel tanks installed before December 22,1988. Cathodic protection is usually provided by an impressedcurrent system. Does not apply to piping.

Other Methods Used toAchieve Corrosion Protection

If you have tanks or piping that do not meet any of the descriptionsabove, check with your state UST agency to see if your UST systemmeets the requirements for corrosion protection. You also will needto ask about the operation, maintenance, and recordkeepingrequirements applicable to this type of UST system.

NOTE: In addition to tanks and piping, all other metal components in direct contact with theground that routinely hold product — such as flexible connectors, swing joints, fittings, andpumps — must also be cathodically protected.

Use the O&M Checklist on the next page. Following the Checklist lookfor recordkeeping forms and discussions of special corrosionprotection situations.

Page 38: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

� Basic O&M Checklist For Corrosion Protection

SacrificialAnode CathodicProtectionSystems

You need to have a periodic test conducted by a qualified corrosion tester to makesure your cathodic protection system is adequately protecting your UST system.This test needs to be conducted:

t Within 6 months of installation.

t At least every 3 years after the previous test.

t Within 6 months after any repairs to your UST system.

& Make sure that the professional tester is qualified to perform the test and follows astandard code of practice to determine that test criteria are adequate.

& If any test indicates that your tanks are not adequately protected, you need to have acorrosion expert examine and fix your system.

& Testing more frequently can catch problems before they become big problems.

t You need to keep the results of at least the last two tests on file. See the next pagefor a cathodic protection test recordkeeping form.

ImpressedCurrentCathodicProtectionSystems

You need to have a periodic test conducted by a qualified corrosion tester to makesure your cathodic protection system is adequately protecting your UST system.This test needs to be conducted:

t Within 6 months of installation.

t At least every 3 years after the previous test.

t Within 6 months after any repairs to your UST system.

& Make sure that the professional tester is qualified to perform the test and follows astandard code of practice to determine that test criteria are adequate.

& If any test indicates that your tanks are not adequately protected, you need to have acorrosion expert examine and fix your system.

& Testing more frequently can catch problems before they become big problems.

t You need to keep the results of at least the last two tests on file. See next page fora cathodic protection test recordkeeping form.

t You need to inspect your rectifier at least every 60 days to make sure that it isoperating within normal limits.

& This inspection involves reading and recording the voltage and amperage readoutson the rectifier. You or your employees can perform this periodic inspection.

& Make sure that your cathodic protection professional provides you with the rectifier’sacceptable operating levels so that you can compare the readings you take with anacceptable operating level. If your readings are not within acceptable levels, youmust contact a cathodic protection professional to address the problem.

t You need to keep records of at least the last 3 rectifier readings. See page 39 for a“60-Day Inspection Results” recordkeeping form.

t You should have a trained professional periodically service your impressedcurrent system.

t Never turn off your rectifier!

Internally Lined Tanks

t Within 10 years after lining and at least every 5 years thereafter, the lined tank must beinspected by a trained professional and found to be structurally sound with the liningstill performing according to original design specifications. Make sure the professionalperforming the inspection follows a standard code of practice.

t Keep records of the inspection (as specified in industry standards for lininginspections).

Page 39: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Record for Periodic Testing of Cathodic Protection Systems(for use by a qualified cathodic protection tester)

TEST DATE:____/____/____ FACILITY NAME/ID:_____________________________

NOTE: Provide site sketch as directed on the back of this page.

Cathodic Protection (CP) Tester Information:

Name: ________________________________ Phone Number: ________________________

Address: _________________________________________________________________________

Testing must be conducted by a qualified CP tester. Indicate your qualifications as a CP tester:

Identify which of the following testing situations applies:

t Test required within 6 months of installation of CP system (installation date was ___/___/___)

t Test required at least every 3 years after installation test noted above

t Test required within 6 months of any repair activity – note repair activity and date below:

Indicate which industry standard you used to determine that the Cathodic Protection test criteria are

adequate: ___________________________________

Cathodic Protection Test Method Used (check one)

100 mV Cathodic Polarization Test

-850 mV Test (Circle 1 or 2 below)

1) Polarized Potential (“instant off”) 2) Potential with CP Applied , IR Drop Considered

Note: All readings taken must meet the -850 mV criteria to pass

Other Accepted Method (please describe):

Is the Cathodic Protection System working properly? Yes No (circle one)

If answer is “No” go to the directions at the bottom on the back of this page.

My signature below affirms that I have sufficient education and experience to be a cathodic protectiontester; I am competent to perform the tests indicated above; and that the results on this form are acomplete and truthful record of all testing at this location on the date shown.

CP Tester Signature: _______________________________ Date:_____________

KEEP THIS PAPER ON FILE FOR AT LEAST SIX YEARS

Page 40: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Site Sketch: Provide a rough sketch of the tanks and piping, the location of each CP test,and each voltage value obtained (use space below or attach separate drawing). Voltagereadings through concrete or asphalt do not provide accurate readings and are notacceptable. Perform sufficient testing to evaluate the entire UST system.

If CP System fails test, you must have a corrosion expert fix the system.If the answer was “NO” indicating that your CP system is not working, you must have acorrosion expert investigate and fix the problem. A corrosion expert has additionaltraining, skills, and certification beyond the corrosion tester who filled out the bulk of thisform. A corrosion expert must be 1) accredited/certified by NACE International (TheCorrosion Society) as a corrosion specialist or cathodic protection specialist, or 2) be aregistered professional engineer with certification or licensing in corrosion control. As longas you have the UST, be sure you keep a record that clearly documents what thecorrosion expert did to fix your CP system.

KEEP THIS PAPER ON FILE FOR AT LEAST SIX YEARS

Page 41: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

60-Day Inspection Results for Impressed Current Cathodic Protection SystemsFACILITY NAME:_______________________________________________________________

AMP RANGE RECOMMENDED:____________________________________________________

VOLTAGE RANGE RECOMMENDED:_________________________________________________

Date Your Name VoltageReading

Amp Reading

Is Your System RunningProperly? (Yes/No)

� If the rectifier voltage and/or amperage output(s) are outside the recommendedoperating levels, contact a cathodic protection expert to address the problem.

� Never turn off your rectifier.

� KEEP THIS RECORD FOR AT LEAST 6 MONTHS AFTER THE DATE OF THE LASTREADING

Page 42: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

Some Special Corrosion Protection Situations

What if you have an STI-P3 tank with a PP4 test station?

If you have a PP4 test station installed with an STI-P3 tank, you may perform the periodictesting of your cathodic protection system by using the meter provided to you with the PP4test station.

� Don’t forget to record the result of the reading and keep at least the last two results.

� If your test readings do not pass, you must take action to correct the problem. Call yourinstaller and ask that the corrosion expert who designed the system examine it andcorrect the problem.

What if you combine internal lining and cathodic protection?

If you chose the combination of internal lining and cathodic protection for meeting corrosionprotection requirements on your UST, you may not have to meet the periodic inspectionrequirement for the lined tank. However, you must always meet the requirements forchecking and testing your cathodic protection system as described in the Basic O&MChecklist For Corrosion Protection on the page 36. The 10-year and subsequent 5-year inspections of the lined tank are not required if the integrity of the tank was ensuredwhen cathodic protection was added. You should be able to show an inspectordocumentation of the passed integrity assessment.

Example 1:If you have cathodic protection and internal lining applied to your tank at the same time,periodic inspections of the lined tank are not required because an integrity assessment ofthe tank is required prior to adding the cathodic protection and internal lining.

Example 2:If you had cathodic protection added to a tank in 1997 that was internally lined in 1994 andthe contractor did not perform an integrity assessment of the tank at the time cathodicprotection was added (or you cannot show an inspector documentation of the passedintegrity assessment), then periodic inspections of the lined tank are required because youcannot prove that the tank was structurally sound and free of corrosion holes when thecathodic protection was added. The lined tank needs to be periodically inspected becausethe lining may be the only barrier between your gasoline and the surrounding environment.

What if you have a double-walled steel UST with interstitial monitoring and cathodicprotection?

If you have a cathodically protected double-walled steel tank and you use interstitialmonitoring capable of detecting a breach in both the inner and outer wall or ingress ofproduct and water as your method of leak detection, then you should monitor your cathodicprotection system within six months of installation and following any activity that couldaffect the CP system.

Page 43: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

2SHUDWLQJ $QG 0DLQWDLQLQJ 867 6\VWHPV ��

If you are using impressed current cathodic protection, you still need to perform the 60-daychecks of your recifier to make sure that it is operating within normal limits.

� Testing the cathodic protection system more frequently may help catch problemsquicker.

� If your test readings do not pass, you must take action to correct the problem. Call yourinstaller and ask that the corrosion expert who designed the system examine it andcorrect the problem.

� Don’t forget to keep at least the last two results of your cathodic protection testing.

Do all UST sites need corrosion protection?

A corrosion expert may be able to determine that the soil at an UST site is not conducive tocorrosion and will not cause the tank or piping to have a release during its operating life. Ifso, you must keep a record of that corrosion expert’s analysis for the life of the tank orpiping to demonstrate why your UST has no corrosion protection.

Page 44: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating and Maintaining USTs 42

Section 6 — Frequent Walk-Through Inspections

You should conduct basic walk-through inspections of your facility at least monthly tomake sure that your essential equipment is working properly and that you have releaseresponse supplies on hand.

These inspections would not be as thorough as following the O&M checklists presentedearlier in this booklet, but they can provide a quick overview you can do more often thanthe longer checklists. You might think of this level of inspection as sort of like thedashboard indicators we respond to in our automobiles that provide us with status warningslike “low battery.”

When you perform your walk-through inspection you should quickly check at least thefollowing:

# Release Detection System: Is your release detection equipment working properly? Forexample, did you run a quick “self-test” of the ATG to verify it’s working properly? Or didyou check your manual dip stick to make sure it’s not warped or worn?

# Spill Buckets: Are spill buckets clean, empty, and in good shape?

# Overfill Alarm (if you have one): Is your overfill alarm working and easily seen orheard?

# -Impressed Current Cathodic Protection System (if you have one): Is your cathodicprotection system turned on? Are you checking your rectifier at least every 60 days?

# Fill and Monitoring Ports: Are covers and caps tightly sealed and locked?

# Spill and Overfill Response Supplies: Do you have the appropriate supplies forcleaning up a spill or overfill?

In addition, good UST site management should also include the following quick visualchecks:

# Dispenser Hoses, Nozzles, and Breakaways: Are they in good condition and workingproperly?

# Dispenser and Dispenser Sumps: Any signs of leaking? Are the sumps clean andempty?

# Piping Sumps: Any signs of leaking? Are the sumps clean and empty?

If you find any problems during the inspection, you or your UST contractor need to takeaction quickly to resolve these problems and avoid serious releases.

A frequent walk-through checklist is provided for your use on the next page.

Page 45: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 43

U Frequent Walk-Through Inspection Checklist

Date of Inspection

Release Detection System: Inspect for

proper operation.

Spill Buckets: Ensure spill buckets are

clean and em pty.

Overfil l Alarm: Inspect for proper operation.

Can a delivery person hear or see the alarm

when it alarms?

Impressed Current System: Inspect for

proper operation.

Fill and Monitoring Ports: Inspect a ll

fill/monitoring ports an d other a ccess points

to make s ure that the covers and caps are

tightly sealed and locked.

Spill and Overfill Response Supplies:

Inven tory an d insp ect th e em erge ncy spill

response supplies. If the supplies are low,

restock the supplies. Inspect supplies for

deterioration and improper functioning.

Dispenser Hoses, Nozzles, and

Breakaw ays: Inspect for loose fittings,

deterioration, obvious signs of leakage, and

improper functioning.

Dispenser and Dispenser Sumps: Open

each dispenser and inspect all visible piping,

fittings, and couplings for any signs of

leakag e. If any wate r or produ ct is prese nt,

remove it and dispose of it properly. Remo ve

any debris from the sump.

Piping Sumps: Inspect all visible piping,

fittings, and couplings for any signs of

leakag e. If any wate r or produ ct is prese nt,

remove it and dispose of it properly. Remo ve

any debris from the sump.

Your initials in each box below the date of the inspection indicate that the device/system wasinspected and OK on that date.

Page 46: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 44

Section 7 — For More Information

This section identifies UST program contacts and other resources that can helpanswer your questions and provide you with information about good USTmanagement.

Internet Resources

Government Links# Directory of State UST Program Contacts: http://www.epa.gov/oust/states/statcon1.htm# Directory of State UST Program Internet Sites:

http://www.epa.gov/oust/states/stateurl.htm# U.S. Environmental Protection Agency’s Office of Underground Storage Tanks Home

Page: http://www.epa.gov/oust. To go directly to the compliance assistance section ofthe Home page go to : http://www.epa.gov/swerust1/cmplastc/index.htm

# Tanks Subcommittee of the Association of State and Territorial Solid WasteManagement Off icials (ASTSWMO): http://www.astswmo.org/tanks.htm

# New England Interstate Water Pollution Control Commission (NEIWPCC): http://www.neiwpcc.org/educate.html#links

Professional And Trade Association Links# American Petroleum Institute (API): http://www.api.org/ # American Society of Testing and Materials (ASTM): http://www.astm.org/index.html# Fiberglass Tank and Pipe Institute (FTPI): http://www.fiberglasstankandpipe.com# NACE International - The Corrosion Society: http://www.nace.org/# National Fire Protection Association (NFPA) : http://www.nfpa.org# Petroleum Equipment Institute (PEI): http://www.pei.org# Steel Tank Institute (STI): http://www.steeltank.com/# Underwriters Laboratories (UL): http://www.ul.com

Free Informative Publications Available

The publications listed below are free and available from the U.S. Environmental ProtectionAgency (EPA). You can access these publications in the following ways.

C Go to EPA’s Web site at http://www.epa.gov/swerust1/pubs/index.htm to order, read, ordownload documents online.

C Call EPA's toll-free RCRA/Superfund Hotline at (800) 424-9346 and order free copies orask questions.

C Write and ask for free publications by addressing your request to EPA’s publicationdistributor: National Service Center for Environmental Publications (NSCEP), Box 42419,Cincinnati, OH 45242.

C For free copies, call EPA’s publication distributor’s toll-free number at (800) 490-9198 orfax (513) 489-8695.

C Fax-on-Demand: Dial (202) 651-2098 on your fax to access over 220 UST documents.

Catalog Of EPA Materials On USTsAn annotated list of UST materials, including ordering information. Most of the leaflets, booklets,videos, and software items listed provide UST owners and operators with information to help themcomply with federal UST req uirements (32 page s).

Page 47: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 45

Musts For USTs: A Summary Of Federal Regulations For Underground Storage Tank SystemsPlain langu age sum ma ry of fe dera l UST requ irem ents for ins tallatio n, rele ase detection , spill, overfill,and corrosion protection, corrective action, closure, reporting and recordkeeping. Updated & revised1995 (36 pages).

Straight Talk On Tanks: Leak Detection Methods For Petroleum Underground Storage TanksExplains federal regulatory requirements for leak detection and briefly describes allowable leakdetection meth ods. Updated & revised 199 7 (28 pages).

Getting The Most Out Of Your Automatic Tank Gauging SystemTrifold leaflet provides UST owners and operators with a basic checklist they can use to m ake suretheir automatic tank gauging systems work effectively and provide compliance with federal leakdetection requirements.

Doing Inventory Control Right: For Underground Storage TanksBoo klet d esc ribes how owners a nd op erato rs of UST s can use inven tory co ntrol a nd pe riodictightness testing to temporarily meet federal leak detection requirements. Contains recordkeepingforms (16 pag es).

Manual Tank Gauging: For Small Underground Storage TanksBooklet provides simple, step-by-step directions for conducting manual tank gauging for tanks 2,000gallons or smaller. Contains recordke eping forms (12 pa ges).

List Of Leak Detection Evaluations For UST SystemsA summary of specifications, based on third-party certifications, for over 275 systems that detectleaks from USTs and their piping. Each summary provides information on such items as certifieddetectable leak rate/threshold, test period duration, product applicability, calibration requirements,restrictions on the use of the device, and so on.

List Of Integrity Assessment Evaluations For USTsA list o f integ rity ass essme nt pro cedures that h ave b een successfully e valua ted and ce rtified by aqualified independent third party to meet specified performance criteria.

Introduction To Statistical Inventory Reconciliation: For Underground Storage TanksBooklet describes how Statistical Inventory Reconciliation (SIR) can meet federal leak detectionrequirements (12 pa ges).

Are You Upgrading An Underground Storage Tank System?Trifold leaflet can help UST owners and operators make sound decisions about choosing tankintegrity assessment methods and upgrading USTs to meet 1998 deadline requirements.

Closing Un derground Storage Tan ks: Brief FactsTrifold leaflet presents “brief facts” on properly closing USTs in order to comply with federal closurerequirements.

Underground Storage Tanks: Requirements And OptionsTrifold leaflet alerts UST owners and operators who are “nonmarketers” (who do not sell storedpetroleum) that they need either to find alternatives to managing their USTs or to make decisionsabout UST compliance.

Dollars And Sense: Financial Responsibility Requirements For Underground Storage TanksBooklet sum marizes the "financial responsibility" required of UST ow ners and operators (16 pa ges).

List Of Known Insurance Providers For Underground Storage TanksProvides UST owners and operators with a list of insurance providers who may be able to help themcomply with financial responsibility requirements by providing suitable insurance mechanisms (12pages).

An Overview Of Underground Storage Tank Remediation OptionsInformation about technologies for remediating petroleum contamination in soil and groundwater (26pages ).

Controlling US T Cleanup CostsFact sh eet series on the cle anup p rocess includes : Hiring a C ontracto r, Nego tiating the Co ntract,Interpreting the Bill, Mana ging the P rocess , and Understanding Contractor Code Words (10 pages).

Page 48: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 46

Key

UST = Underground Storage TankLUST = Leaking UST

Pay-For-Performance Cleanups: Effectively Managing Underground Storage Tank CleanupsBooklet explores potential advantages of using pay-for-performance cleanup agreements to reduce thecost and time of cleanups and more effe ctively manage cleanup resourc es (32 pages).

Financing Underground Storage Tank Work: Federal And State Assistance ProgramsBooklet identifies potential sources of financial assistance to cover the costs of upgrading, replacing, orclosing a n UST , or of clean ing up an UST release ( 23 pag es). Revised and updated, March 1999.

State Regulatory Agency Contact List

Please note that contact information frequently changes. The information below, even if not exactlycorrect on the day you want to use it, should get you pointed in the right direction. Regularlyupdated contact information can be found by calling EPA’s RCRA/Superfund Hotline at (800) 424-9346. Also, you can get updated Web addresses from EPA’s Web site athttp://www.epa.gov/oust/states/statcon1.htm

AlabamaAlabama Dept. of Environmental

ManagementGroundwater Branch/UST Prog.P.O. Box 301463Montgomery, AL 36130-1463UST Phone: (334) 271-7759

LUST Phone: (334) 270-5613Fax: (334) 270-5631(Street address: 1400 Coliseum

Blvd., ZIP: 36110-2059)

AlaskaAlaska Dept. of Environmental

Conservation410 Willoughby Ave.Juneau, AK 99801-1795Phone: (907) 465-5200Fax: (907) 465-5218

ArkansasArkansas Dept. of Environmental

QualityRegulated Storage Tanks DivisionP.O. Box 8913Little Rock, AR 72209-8913Phone: (501) 682-0999Fax: (501) 682-0880(Street address: 8001 National

Drive, ZIP: 72209)

ArizonaUST ContactArizona Dept. of Environmental

QualityWaste Programs DivisionUST & Program Support Section3033 North Central Ave.Phoenix, AZ 85012-2905Phone: (602) 207-4255Fax: (602) 207-4346

LUST ContactArizona Dept. of Environmental

QualityWaste Programs Division

UST Corrective Action Section3033 North Central Ave.Phoenix, AZ 85012-2905Phone: (602) 207-4303Fax: (602) 207-4346

CaliforniaCalifornia State Water Resources

Control BoardUST ProgramP.O. Box 944212Sacramento, CA 94244-2120Phone: (916) 227-4313Fax: (916) 227-4349(Street address: 2014 T Street, Suite 130, ZIP: 95814)

ColoradoColorado Dept. of Labor and

Employment Oil Inspection Section1515 Arapahoe St.Tower 3, Suite 610Denver, CO 80202-2117Phone: (303) 620-4300Fax: (303) 620-4028

ConnecticutConnecticut Dept. of Environmental

ProtectionBureau of Waste ManagementUST ProgramState Office Bldg.79 Elm StreetHartford, CT 06106-5127UST Phone: (860) 424-3374

LUST Phone: (860) 424-3376Fax: (860) 424-4061

DelawareDelaware Dept. of Natural

Resources & EnvironmentalControl

Early Compl. & Detect. IncentiveProgram

UST Branch391 Lukens Dr., Riveredge ParkNew Castle, DE 19720Phone: (302) 395-2500Fax: (302) 395-2601

District of ColumbiaDC Dept. of HealthEnvironmental Health Admin.Bur. Of Hazardous Materials & Toxic

SubstancesUST Division, 5th Floor51 N Street, NEWashington, DC 20002Phone: (202) 535-2525/-2500Fax: (202) 442-4808

FloridaFlorida Dept. of Environmental ProtectionWaste ManagementBur. of Petroleum Storage SystemsTwin Towers Office Bldg.Room 403, MS 45252600 Blair Stone RoadTallahassee, FL 32399-2400Phone: (850) 488-3935Fax: (850) 414-1521

GeorgiaGeorgia Dept. of Natural ResourcesEnvironmental Protection Div.UST Management Program4244 International ParkwaySuite 110Atlanta, GA 30354Phone: (404) 362-2687Fax: (404) 362-2654

Page 49: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 47

HawaiiHawaii Dept. of Health Solid and Hazardous Waste Br.919 Ala Moana Blvd.Suite 212Honolulu, HI 96814Phone: (808) 586-4226Fax: (808) 586-7509

IdahoIdaho Div. of Environmental QualityUST Program1410 North HiltonBoise, ID 83706Phone: (208) 373-0502Fax: (208) 373-0576

IllinoisUST Contact:Illinois Office of State Fire MarshalDiv. of Petroleum & Chemical Safety1035 Stephenson Dr.Springfield, IL 62703Phone: (217) 785-5878Fax: (217) 782-1062

LUST Contact:Illinois EPA, Bureau of LandDiv. of Remediation Mgmt.LUST Section1021 North Grand Ave. EastSpringfield, IL 62794-9276Phone: (217) 782-6762Fax: (217) 524-4193

IndianaIndiana Dept. of Environmental

Mgmt.Office of Environmental ResponseUST SectionP.O. Box 6015Indianapolis, IN 46206-6015UST Phone: (317) 308-3064LUST Phone: (317) 308-3080Fax: (317) 308-3086(Street address: 2525 N. Shadeland

Ave., ZIP: 46219)

IowaIowa Dept. of Natural ResourcesEPD/ UST SectionWallace State Office Bldg.502 East 9th St.Des Moines, IA 50319-0034Phone: (515) 281-8135Fax: (515) 281-8895

KansasKansas Dept. of Health &

EnvironmentBureau of Environmental

RemediationStorage Tank SectionForbes Field, Bldg. 740Topeka, KS 66620

Phone: (785) 296-1678Fax: (785) 296-6190

KentuckyKentucky Division of Waste

ManagementUST Branch14 Reilly RoadFrankfort, KY 40601Phone: (502) 564-6716Fax: (502) 564-1939

LouisianaLouisiana Dept. of Environmental

QualityOffice of Environ. AssessmentsUST DivisionP.O. Box 82178Baton Rouge, LA 70884-2178Phone: (225) 765-0243Fax: (225) 765-0366(Street Address:7290 Bluebonnet

Blvd., ZIP: 70810)

MaineMaine Dept. of Environmental

ProtectionBur. of Remediation and Waste

ManagementOil & Hazardous Waste Facilities

Regulation Div.Ray Bldg., 17 State House StationAugusta, ME 04333-0017Phone: (207) 287-2651Fax: (207) 287-7826

MarylandMaryland Dept. of EnvironmentWaste Management Admin.Oil Control Program2500 Broening HighwayBaltimore, MD 21224Phone: (410) 631-3442Fax: (410) 631-3092

MassachusettsUST Contact:Massachusetts Dept. of Fire

ServicesUnderground Storage Tank ProgramP.O. Box 1025, State RoadStow, MA 01775Phone: (978) 567-3300Fax: (978) 567-3199

LUST Contact:Massachusetts Dept. of

Environmental ProtectionBur. of Waste Site CleanupResponse & Remed. Div.One Winter StreetBoston, MA 02108Phone: (617) 556-1044Fax: (617) 292-5530

MichiganMichigan Dept. of Environmental QualityStorage Tank DivisionP.O. Box 30157Lansing, MI 48909-7657Phone: (517) 373-8168Fax: (517) 335-2245

MinnesotaMinnesota Pollution Control AgcyUnderground Storage Tank Sys.520 Lafayette Road NorthSt. Paul, MN 55155-4194UST Phone: (651) 297-8367LUST Phone: (651) 297-8574Fax: (651) 297-8676

MississippiMississippi Dept. of Environmental QualityOffice of Pollution ControlUST ProgramP.O. Box 10385Jackson, MS 39289-0385Phone: (601) 961-5171Fax: (601) 354-6612(Street address: 2380 Hwy 80 West,ZIP: 39204)

MissouriMissouri Dept. of Natural ResourcesHazardous Waste ProgramTanks SectionP.O. Box 176Jefferson City, MO 65102-0176Phone: (573) 751-6822Fax: (573) 526-8922

MontanaMontana Dept. of Environmental QualityRemediation DivisionP.O. Box 200901Helena, MT 59620-0901Phone: (406) 444-1420Fax: (406) 444-1901(Street address: 2209 Phoenix Ave.)

NebraskaUST Contact:Nebraska State Fire MarshalFlammable Liquid Storage Tank Division246 South 14th StreetLincoln, NE 68508-1804Phone: (402) 471-9465Fax: (402) 471-3118

LUST Contact:Nebraska Dept. of Environmental QualityWater Quality DivisionLUST/ER Section1200 N St., Suite 400Box 98922Lincoln, NE 68509Phone: (402) 471-4230Fax: (402) 471-2909

Page 50: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 48

NevadaNevada Dept. of Conservation &

Natural ResourcesEnvironmental Protection DivBureau of Corrective Action333 W. Nye LaneCarson City, NV 89706-0851Phone: (775) 687-5872Fax: (775) 687-6396

New HampshireNew Hampshire Dept. of

Environmental ServicesOil Remediation & Compliance

BureauP.O. Box 956 Hazen DriveConcord, NH 03301Phone: (603) 271-3644Fax: (603) 271-2181

New JerseyNew Jersey Dept. of Environmental

ProtectionResponsible Party Site Remediation401 East State St. (CN-028)Trenton, NJ 08625-0028Phone: (609) 292-8761Fax: (609) 633-1454

New MexicoNew Mexico Environment Dept.UST BureauP.O. Box 261101190 St. Francis Dr.Harold Runnels Bldg.Santa Fe, NM 87502-0110Phone: (505) 827-0188Fax: (505) 827-0310

New YorkNew York Dept. of Environmental

ConservationBulk Storage Section50 Wolf Road, Rm 360Albany, NY 12233-3750Phone: (518) 457-4351Fax: (518) 457-4332

North CarolinaNorth Carolina Dept. of Environment

& Natural ResourcesDiv. of Waste ManagementUST SectionP.O. Box 29616Raleigh, NC 27626-0616Phone: (919) 733-8486Fax: (919) 733-9413(Street Address: 2728 Capital Blvd.,

ZIP: 27604)

North DakotaNorth Dakota Dept. of HealthDiv. of Waste ManagementUST Program1200 Missouri Ave.

P.O. Box 5520Bismarck, ND 58506-5520Phone: (701) 328-5166Fax: (701) 328-5200

OhioOhio Dept. of CommerceDiv. of State Fire MarshalBureau of UST RegulationsP.O. Box 6876606 Tussing RoadReynoldsburg, OH 43068-9009Phone: (614) 752-7938Fax: (614) 752-7942

OklahomaOklahoma Corp. CommissionPetroleum Storage Tank Div.P.O. Box 52000-20002101 North Lincoln Blvd.Oklahoma City, OK 73152-2000UST Phone: (405) 521-3107LUST Phone: (405) 521-3503Fax: (405) 521-6576

OregonOregon Dept. of Environmental

QualityUST Program811 SW Sixth Ave.8th FloorPortland, OR 97204Phone: (503) 229-5913Fax: (503) 229-6954

PennsylvaniaUST Contact:Pennsylvania Dept. of Environmental

ProtectionBur. of Watershed Conserv.Div. of Storage TanksP.O. Box 8762Harrisburg, PA 17105-8762Toll-free UST: 1-800-42TANKSPhone: (717) 772-5599Fax: (717) 772-5598(Street Address: 400 Market St.,

10th Floor)

LUST Contact:Pennsylvania Dept. of Environmental

ProtectionBur. of Land Recycling & Waste

ManagementStorage Tank Cleanup ProgramP.O. Box 8471Harrisburg, PA 17105-8471Phone: (717) 783-7509Fax: (717) 787-0884(Street Address: 400 Market St.,14th

Floor)

Rhode IslandRhode Island Dept. of Environmental

ManagementOffice of Waste Management

UST/LUST Section235 Promenade St.Providence, RI 02908-5767Phone: (401) 222-2797Fax: (401) 222-3812

South Carolina South Carolina Dept. of Health and

Environmental ControlDiv. of UST Management2600 Bull St.Columbia, SC 29201Phone: (803) 898-4350Fax: (803) 898-4330

South DakotaSouth Dakota Dept. of Environment and

Natural ResourcesUST ProgramJoe Foss Bldg.523 East CapitolPierre, SD 57501Phone: (605) 773-3296Fax: (605) 773-6035

TennesseeTennessee Dept. of Environment and

ConservationDivision of USTs4th Floor, L & C Tower401 Church St.Nashville, TN 37243-1541Phone: (615) 532-0945Fax: (615) 532-0938

TexasUST Contact:Texas Natural Resources Conservation

CommissionRegistration and Evaluation Div.Technical Services SectionMC: 135P.O. Box 13087Austin, TX 78711-3087Phone: (512) 239-2182Fax: (512)2 39-1422

LUST Contact:Texas Natural ResourcesConservation CommissionRemediation DivisionPST Responsible Party Remediation

SectionMC: 137P.O. Box 13087Austin, TX 78711-3087Phone: (512) 239-2200Fax: (512) 239-2216(Street address:12100 Park 35 Circle,

ZIP:78753)

Page 51: Operating And Maintaining Underground Storage … And Maintaining Underground Storage ... provides information on operating and maintaining underground storage tank ... By identifying

Operating And Maintaining UST Systems 49

UtahUtah Dept. of Environmental QualityDiv. of Environmental Response and

RemediationUST BranchP.O. Box 144840Salt Lake City, UT 84114-4840Phone: (801) 536-4100Fax :(801) 359-8853(Street address: 168 North 1950

West,1st Floor, ZIP 84116)

VermontVermont Agency of Natural

ResourcesDept. of Environmental ConservationWaste Management Div.UST Program103 South Main St.West Bldg.Waterbury, VT 05671-0404Phone: (802) 241-3888Fax: (802) 241-3296

VirginiaVirginia Dept. of Environmental

QualityUST ProgramP.O. Box 10009Richmond, VA 23240-0009UST Phone: (804) 698-4313LUST Phone: (804) 698-4269Fax: (804) 698-4266

WashingtonWashington State Dept. of EcologyToxics Cleanup ProgramP.O. Box 47600Olympia, WA 98504-7600Phone: (360) 407-7170Fax: (360) 407-7154(Street address:300 Desmond Dr.,

Lacey, WA, ZIP:98503)

West VirginiaUST Contact:West Virginia Div. of Environmental

ProtectionOffice of Waste ManagementUST Unit1356 Hansford St.Charleston, WV 25301-1401Phone: (304) 558-6371Fax: (304) 558-2387

LUST Contact:West Virginia Div. of Environmental

ProtectionOffice of Environmental Remed.LUST Unit1356 Hansford St.Charleston, WV 25301-1401Phone: (304) 558-2508Fax: (304) 558-0256

WisconsinUST CONTACT:Wisconsin Dept. of CommerceBur. of Storage Tank RegulationP.O. Box 7837Madison, WI 53707-7837Phone: (608) 266-7874Fax: (608) 261-7725(Street address: 201 West

Washington Ave., 3rd Floor,ZIP:53703)

LUST Contact:Wisconsin Dept. of Natural

ResourcesBur. of Remed. & Redev.P.O. Box 7921Madison, WI 53707-7921Phone: (608) 267-7533Fax: (608) 267-7646

WyomingWyoming Dept. of Environmental

QualityWater Quality DivisionHerschler Bldg.-4th Floor West122 West 25th St.Cheyenne, WY 82002Phone: (307) 777-7096Fax: (307) 777-5973

U.S. Territories

American SamoaAmerican Samoa Environmental

Protection AgencyOffice of the GovernorAmerican Samoa GovernmentATTN: UST/LUST ProgramPago Pago, AS 96799Phone: 011-684-639-2304Fax: 011-684-633-5801

Northern Mariana IslandsDiv. of Environmental QualityCommonwealth of Northern Mariana

IslandsP.O. Box 1304Saipan, MP 96950Phone: 011-670-664-8550Fax: 011-670-664-8540

GuamGuam Environmental Protection

AgencyP.O. Box 22439 GMFBarrigada, GU 96921Phone: 011-671-475-1609Fax: 011-671-475-1618

Puerto RicoEnvironmental Quality BoardCommonwealth of Puerto RicoP.O. Box 11488Santurce, PR 00910Phone: (787) 767-8109Fax: (787) 767-1962

Virgin IslandsVirgin Islands Dept. of Planning and

Natural Resources1118 Water Gut HomesChristianstedSt. Croix, VI 00820-5065Phone: (340) 773-0565Fax: (340) 773-9310