Upload
others
View
23
Download
0
Embed Size (px)
Citation preview
1
Thematic Unit of Excellence on Computational Materials Science (TUE-CMS)
Solid State and Structural Chemistry Unit Indian Institute of Science
Bangalore 560012
Open Tender Request for Proposal for Datacenter
Reference No. SSCU/TUE/DC/2015-186 dated 26th
June, 2015
2
Table of Contents 1.0 Solution Overview ............................................................................................................... 4
1.1 Physical Components Design .................................................................................... 4
1.2 Existing floor and DC space ...................................................................................... 5
1.3 Detailed Product-wise scope ...................................................................................... 5
1.3.1 Raised floor ....................................................................................................5
1.3.2 Sub structure – pedestal assembly ..................................................................5
1.3.3 Stringers ..........................................................................................................6
1.3.4 Other Non structural Parameters ....................................................................6
1.3.5 Fire Rated Gypsum Partition across the room ................................................7
1.4 Rack Specifications .................................................................................................... 7
1.4.1 Technical specifications: ................................................................................7
1.4.2 PDU - Power Distribution Unit for Rack (N+1) ............................................8
1.4.3 Closed Loop Rack based cooling system .......................................................8
1.4.4 High Performance Liquid Cooling Package – Closed Loop Cooling. ...........8
1.5 Air-Conditioning ........................................................................................................ 9
2.0 Monitoring ......................................................................................................................... 11
3.0 Rear Auto door Opening for Closed Loop Cooling System .............................................. 12
3.1 Precision Air conditioning ....................................................................................... 12
3.2 Air Cooled Chillers: (N+1 Redundancy) ................................................................. 12
3.3 Technical specifications: ......................................................................................... 13
4.0 LOW SIDE WORKS: PUMPS & PIPING ........................................................................ 15
5.0 Security Systems ................................................................................................................ 16
5.1 Fire Detection and alarm System: ............................................................................ 17
5.2 Manual pull station: .................................................................................................. 17
5.3 Very Early Smoke Detection and Alarm [VESDA] SYSTEM ................................ 17
5.3.1 Introduction: .................................................................................................17
5.3.2 Design: ..........................................................................................................17
5.3.3 Principle of Operation: .................................................................................18
5.4 Rodent Repellent System: ....................................................................................... 18
5.5 Water Leak Detection System: ................................................................................. 19
6.0 BUILDING MANAGEMENT SYSTEM (BMS) ............................................................. 19
6.1 SCOPE OF WORK .................................................................................................. 19
6.2 Electrical System ...................................................................................................... 19
7.0 Services Level Agreement (SLA) & Warranty .................................................................. 20
8.0 General terms and conditions: ........................................................................................... 21
9.0 USER ACCEPTANCE TEST CHECK LIST ................................................................... 22
10. CHECK-LIST .................................................................................................................... 22
11. POWER CONSUMPTION CHECK LIST: ...................................................................... 22
12.0 Submission of Proposal.................................................................................................... 23
13.0 PRICE BID TABLE ........................................................................................................ 23
14.0 Likely Time-line .............................................................................................................. 24
15.0 Bill of Quantities .............................................................................................................. 25
15.1 - Air cooled Chiller ................................................................................................ 25
15.2 – Civil Works ......................................................................................................... 28
15.3 – Cooling Racks ..................................................................................................... 28
15.4 – Security products ................................................................................................. 28
15.4.1 Fire Alarm ..................................................................................................28
15.4.2 VESDA .......................................................................................................29
3
15.4.3 Water leak detection system .......................................................................29
15.4.4 Rodent repellent system .............................................................................29
15.4.5 BMS system................................................................................................30
15.5 – PAC Cooling unit ................................................................................................ 30
15.6 – UPS for Pump ..................................................................................................... 31
Bidders may obtain the Request For Proposal (RFP) which includes Technical Specifications and Bill of Quantities from Ms. Bavitha, Room 209, SSCU, INDIAN INSTITUTE OF SCIENCE, C V Raman Ave, Bengaluru, Karnataka 560012. Bidders can also download RFP Documents on this Institute’s website http://www.iisc.ernet.in/tender/index.php however they are required to pay tender fee in the manner as prescribed below along with Bid document. Documents must be in two cover format with technical part and commercial part in two separate sealed covers. They must be superscribed as ‘Technical Bid' and ‘Commercial Bid’. The bids should be accompanied by a nonrefundable DD for Rs. 5,000 / - (Rs. Five Thousand only) drawn in favour of “Registrar, INDIAN INSTITUTE OF SCIENCE” payable at Bangalore.
4
1.0 Solution Overview
IISc SSCU is in need of Tier 3 Data Center (DC) for its HPC server Project. This bid is to
build cooling solution for High Performance Computers (HPC) along with racks, electrical
cabling & Security products for DC. The room dedicated to the data center has an area of
588 sq ft. The floor to ceiling height is only 9 ft and 6 inches. The solution could use all or
part of this space. The scope is for supply, installation and maintenance for a period of 5
years.
The DC area should support presently 7 nos of 800 mm width server rack of 42U. Only 4
racks with a total capacity of 110kW is expected now but provision for possible addition in
future of 3 more racks should be made. Chilled water based cooling solution should be
provided to achieve PUE of 1.5 or lower. UPS power supply from Existing UPS of 2 x 160
kVA will be provided close to the DC. The power distribution from existing UPS output
panel’s to racks including DB installation in Server room and individual socket for racks is
in supplier scope. Dual power source per rack shall be provided.
Two UPS each of capacity 160 kVA and one diesel generator (DG) have already been
installed and supply from these to the data center will be made available.
Closed loop cooling solution ( CLC ) to support 110 kW heat load across 4 racks shall be
provided & should be expandable up to 7 racks without any dependency. The closed loop
cooling solution should be adaptable in case the heat load increases up to a rack density of
35 kW/rack with just addition of cooling unit as in modular datacenters. Dual chiller plant
equal to or not less than 40 Tr actual capacity on ambient temperature 37°C shall be
provided on N + 1 configuration. Open space behind the server room shall be used for
installing chiller plant.
1.1 Physical Components Design
IISc is in need of Turnkey Implementation of the Data Center including Program
Management Services for Data Center Set Up. The bidder/solution provider shall submit
Detailed Engineering Drawings of various components of Data Center and revise the same
as required till the drawings/design is finally approved by IISc and that also includes all
drawings like air conditioning, electrical system, Fire alarm systems, data cabling etc.
Preparing detailed specifications and supply Installation and Commissioning of the following
critical components for Data Center is required:
Civil – Partition & Raised floor
Electrical System for Data Center cabling from UPS to DC and all cabling within DC
CLC Cooling Systems
Air cooled chiller and piping
Power Distribution and cable management From UPS to Racks
Fire alarm, suppression and VESDA system
5
Water Leak Detection System
Pest Control (Rodent Repellent System)
1.2 Existing floor and DC space
A smaller portion from given space of 12.3Mtr x 4.2Mtr may be used for DC. One fire
rated door out of two provided to be used for server room after building partition wall
across the space. Raised floor of 1500 USF at the height of 300 to 400 mm. Metal steps to
be provided from fire rated door for entry.
1.3 Detailed Product-wise scope
1.3.1 Raised floor
A total of 588 sq ft raised floor with below spec to be provided.
Unitile® USF 1500 Access Floor panel of size 600x600 mm shall be all steel welded
construction, with an enclosed bottom pan of 49 hemispherical and 36 reverse cones and
top plain sheet which are fuse welded at 129 locations to form a panel of an overall
thickness of 35mm. The panel after cleaning, degreasing, phosphating by 11 tank process
is coated with 40-60 micron epoxy coat and is heated to achieve maximum adhesion to the
panel surface and corrosion resistance. The inner empty core of the panel is injected with
a light weight fire retardant, non combustible cementitious compound at high pressure to
fill in all the crevices of the panel and ensures support of not less than 90% of the top
surface area of the panel.
The panel is then laminated with 1.5/2.00 mm thick fire retardant floor grade Antistatic
Laminate / ESD Laminate - PVC / Conductive / Dissipative PVC on a semi -automated
lamination line to ensure maximum bonding to the steel surface. The edges of the
laminated are protected with conductive PVC edge trim 5mm wide on all sides. This edge
trim is mechanically locked and sealed in place to avoid detachment.
1.3.2 Sub structure – pedestal assembly
Sub structure installed to support the panel shall be suitable to achieve a minimum finished
floor height of 300 mm to a maximum of 400 mm from the existing floor level. Pedestal
design shall confirm speedy assembly and removal for relocation and maintenance. The
assembly shall provide easy adjustment of leveling and accurately align panels for a
maximum ± 25 mm in the vertical direction. Pedestals shall support an axial load without
permanent deflection and an ultimate load as laid out in System Performance requirement.
The Pedestal head assembly shall consist of a 75 x 75 x 3.50 mm embossed head
mechanically riveted to a 100 mm long ¾” dia rolled formed stud and 2 check nuts for level
adjustment and arresting vertical movement. The pedestal head shall consist of an anti-
vibrational PVC cap for Panel location.
6
The Pedestal Base assembly shall consist of 22.23 mm OD pipe mechanically locked on a
press for perpendicularity and then welded to a base plate of 100 x 100 x 2 mm thick with
stiffening folds.
The sub structure assembly shall be suitably anchored to the floor with suitable adhesive
or fastener as recommended by the consultant / manufacturer. All steel components shall
be zinc electro plated.
1.3.3 Stringers
The stringer is hot dipped galvanized steel cold rolled construction specially designed with
ribs embossed on 3 sides for strength, lateral stability, and for enhanced rolling loads
performance and to support the panels on all four sides for alignment. The stringer to have
a counter sunk holes at both ends to accommodate bolting of M6 machine screws to the
pedestal head assembly. The stringers shall be 21 x 32 x 0.8 x 570 mm length.
Concentrated Loads :
675 Kgs (1500 lbf ) with a top-surface deflection under load and a permanent set not to
exceed , respectively, 2.54 & 0.25 mm ( 0.10 & 0.010 inch ) according to CISCA A/F,
Section I ‘’ Concentrated Loads’’
Ultimate Concentrated Load:
1690 Kgs (3750 lbf ) without failing according to CISCA A/F, Section II ‘’ Ultimate
Loading’’
1.3.4 Other Non structural Parameters
• Fire Rating :
The Panels shall confirm to Class O & Class 1 Fire Ratings tested as per BS 476 Part 6
(Fire Propagation) & 7 (Surface spread of flame) as also ASTM E84 1998 (Flammability)
and ASTM E136 (Combustibility)
• Electrical Resistivity :
As per ASTM F150/ NFPA 99 / ANSI S7.1/ CEI 61340 but modified for surface to ground
to place one electrode on the floor surface and to attach the other electrode on the
pedestal. Resistance to be tested at 100 / 500 volts:
1. Conductive range : 2.5x104 – 1x 106 Ohms (surface to ground)
2. Static dissipative range : 1x106- 1x109 Ohms (surface to ground)
3. Anti static range : 1x109 – 2x1010 Ohms (surface to surface )
7
• Fabrication Tolerance
A. Floor panel flatness : ± 0.75 mm in any direction
B. Floor panel width or length from specified size : ± 0.50 mm
C. Floor panel squareness : ± 0.38 mm
• Installation Tolerance
A. Overall level before application of any load : ± 1.5 mm over any 5.00 Sqmt
± 6 mm over any size of basic space
B. Panel level : + 0.75 mm before the application of any load
C. Panel Interchangeability installation and removal : shall be interchangeable (except for
field cut panels) and replaceable in any of the four directions at 90º increments
Floor grills of 600 x 600 mm floor grills 4numbers to be provided.
1.3.5 Fire Rated Gypsum Partition across the room
Twin layer of 6 mm Fire resistant gypsum board to be used on both the sides of the wall
stretcher.
The height shall be 9.5 ft from floor to ceiling (approximately). All the windows inside the
server room to be closed with gypsum board to avoid heat conductivity from outside.
Putty works to be carried out on the existing wall and gypsum board and three coat of
water based painting to be carried out.
1.4 Rack Specifications
Server Rack 800 mm Width x 42U Height x 1200mm Depth.: 04 Nos.
These racks will be used to mount and house all server/network/storage devices in the data
center.
The rack has to be designed to meet the safety requirements of the modern data centre.
Both the front and rear door should have a handle with locking options. The rack should
be suitable for baying to a high performance cooling rack. Cable entry should be entered
via the roof plate and via the gland plate without affecting the climatic conditions inside
the rack.
1.4.1 Technical specifications:
Server Equipment Cabinets - 42U - 800 mm Width x 1200 mm Depth equipment cabinets
should have adjustable 19 inch front and rear vertical mounting extrusions which are EIA-
310D and IEC 60297 compliant and allow up to 1190 mm of depth for equipment mounting
(in rack the usable depth is 800 mm due to hot and cold zone within the IP54 sealed
block). Balanced load rating of 1500 kg. Cabinet should be manufactured from materials
and processes that are compliant with the most current TÜV/ISO environmental
8
management standards. The front and rear 19 inch equipment mounting rails and other
internal supporting metals are to be of un-painted galvanized steel. Cabinet shall come
complete with grounding kit, cage nuts and the following features and installed accessories:
Front door –glass door, complete with swivel handle with DIN half profile
cylinder plug and universal key 333, door system with 5 or 6 points. Opening
angle 180°, width of the door must be 75mm smaller than the outer width of
the rack.
Rear door – sheet steel, complete with swivel handle with DIN half profile cylinder
plug and universal key 333 door system with 5 or 6 points. Opening angle 180°,
width of the door must be 75mm smaller than the outer width of the rack.
Air separation frame for air-flow optimization and elimination of bypass air-
flow, consisting of mechanically joint sheets steel panels and equipped with the
sealing rim.
Balanced Load rating 1500 kg
Bottom is flat and enables direct installation of the rack on the floor
Adjustable leveling feet (6 pcs.)
IP54 protection rating when installed (joined to neighboring cooling unit for
closed loop)
Central grounding point
Rack based fire suppression – fitted inside rack with max size of 4U on each
rack.
1.4.2 PDU - Power Distribution Unit for Rack (N+1)
Each Server and Network Rack should be fitted with 2 nos. rack mounted power
Distribution unit with 24 nos. IEC C13 and 6nos. IEC C19 - for Server (high density
racks); PDU shall have the capability to monitor the power consumption of the rack on
which it is mounted.
Protocols: SNMP, Telnet, http etc.
1.4.3 Closed Loop Rack based cooling system
The Data center should be equipped with Liquid Cooling System; it is an air/water heat
exchanger to remove high levels of waste heat from server enclosures and to provide
uniform, effective, affordable cooling for Servers and similar IT equipment (switches etc)
installed in server enclosures. Each liquid cooling system should be a closed unit
consisting of a cooling system and cool either one or two server enclosures.
1.4.4 High Performance Liquid Cooling Package – Closed Loop Cooling.
CLC Rack CW should offer enclosure-based cooling separate from the room air and is
thus also able to reduce the noise level. The unit should be capable of providing cooling
9
for either one or two server racks. The hot server air should be drawn off to the rear of
the server rack. After cooling, it should be expelled at the rear of the rack and is thus
made available to the IT equipment once more.
Unit should be connected to the piping system of chilled water or anti-freeze mixture. It is
suitable for the free-cooling systems because allows warmer water usage. The surface
temperature of the heat exchanger is controlled by valve, which fluently modifies the
cooling capacity in accordance to the actual demand. Variable speed fans help to keep
always the correct airflow for all IT equipment in data center. EC motor technology used
in the fans markedly reduces the annual power consumption.
Both top and bottom connection of the unit is available.
The air-conditioning unit’s design has to be fully compatible to bystanders IT racks from
the perspective of dimensions, material, color, and mechanical coupling elements. The unit
in the row of the cabinets has to enable an installation of cable management, roof
elements, aisle doors etc.
1.5 Air-Conditioning
Air-conditioning unit includes:
- Highly efficient water heat exchanger made of copper pipes and aluminum fins
with a special surface. The oblique position of HX enlarges the surface, and
optimizes the heat transfer.
- Three stacked air filters of filtration class G4 in combustible finish for ecological
disposal. The frame is ready for easy maintenance and filter replacement.
- Five or more hot-swap radial fans with EC motors significantly reducing the
power consumption with fluent speed change and operation feedback to the
control system.
- Controller with software for independent control of all components, running also
in case of interruption of communication between units or central display.
- Minimum Four temperature sensors located in the front and rear side
monitoring the air temperature in the upper and lower part of the space.
Sensors could be calibrated from controller. Controller enables to change the
logic between average and maximal values, and arranges substitutability in case
of failure.
- Two humidity sensors located at the bottom of front and rear part of the unit
for precise monitoring of the room conditions.
- Air-conditioning unit, with “D” in the type code, includes color touch screen in
the front door. 4.3” large display is equipped with special software for
monitoring and control of up to 10 units. It enables communication through
TCP/IP protocol, remote control via Ethernet and implemented webserver, and
10
easy SW upgrading and data downloading via USB disk or SD card. Another
function implementation is possible on special request.
Functions:
- The basic task is to cool down the air from the hot zone of datacenter and
distribute it to the cold zone in front of the IT equipment. The unit is designed
to keep the constant temperature in both zones thanks to the water valve
adjustment and variable fan speed.
- If the humidity in the hot zone is within the limits set by an administrator, then
the unit’s internal logic tries to avoid any condensation of the air moisture,
maximize the cooling efficiency, and minimize influence on the humidity climate
of the room.
- If the measured air humidity is above the set point, then the unit is
automatically switched to the dehumidification mode, and actively supports the
surface condensation to decrease the humidity in the room. The resulted
condensate is discharged to the drainage.
- The unit can be equipped by integrated steam humidifier which increases the
room humidity to the set point.
- Units could be connected to bigger groups under a superior control with
advanced control logic (sequencing, team working, overload start, etc.)
Technical specifications:
Adaptable cooling output : Equal to or greater than 30kW.
Installed fans: 4 Minimum
Air throughput: Equal to or greater than 3800 m³/h
Cooling output : Equal to or greater than 30 kW
Air intake temperature: 35°C
Water inlet temperature: as required
Medium: Water
Coolant throughput: approx. 60 l/min
Pressure loss: approx. 1 bar
Voltage: 208/230 V, 1~, 50 Hz, 400 V, 3~, N, 50 Hz
11
Colour: NA
Usable installation height: free (standard: 42 U)
Dimensions: WxHxD: 300 or 600 x 2000 x 1200 mm
Touch screen display, Connection hose, bottom/top:
2.0 Monitoring 8 intelligent ports (output/input, 0-5V) with auto sense on main device with 4
expansion ports
Expandable solutions through expanders connected in daisy-chain with patch
cables
Intelligent port presented by RJ-45 for connection and extension by patch cable
Options to upload picture and with a function grab & drop able to place sensors
icon in
Multi language with a possibility to create own language version inside of device
80 virtual sensors for connecting and reading a values from SNMP devices,
Modbus devices and Ping
Email, SNMP trap, Modbus control, skype call & sms, speech
Support a sending keep alive emails in configurable interval
SNMP v1, v2 & v3
Support DHCP and NTP
Fully embedded TCP/IP and web-server with Linux OS
A standalone product without any external hardware and software
dependencies.
Configurable User & group management for login protected by password
Network Management System Integration.
Free Firmware Updates
History for measured values, able to show a graphs and statistics by day, week,
month and year (average, high and low data)
4 levels of thresholds, advance setting with (alarm report off) calender
Internal Syslog with options to send a logs to the external syslog
Status indicators on front panel (Power, Connectivity, Sensors online and
threshold status)
USB 2.0 port for options to connect GSM modem for sending alarm SMS
without requirements of 3rd party SW
Support Modbus RTU and TCP/IP
Built in speaker
Support dual one-wire probes (temperature & humidity)
1U Rack Mount Standard
Network interface - 100 Mbps Full Duplex
Operating environment – Temperature: -35°C – 80°C; Humidity: 20% - 80%
(Non-Condensing)
12
Power consumption less than 2 Watt
Battery backed time of day clock for an accurate system date and time
Power Adapter with C-14 socket and Power cord
3.0 Rear Auto door Opening for Closed Loop Cooling System
All closed looped racks should be fitted with automatic door opening kit for the back door.
Door should automatically open in case of Alarm on temperature. The auto door control
unit should be connected on SNMP TCP/IP for monitoring and control.
3.1 Precision Air conditioning
Computer Room AC (CRAC/PAC): EC fans with highly advanced digital controller to take
care server room cooling requirements & controlling humidity. Gas based unit to be
quoted with 15 mtr copper piping works. SNMP card should be provided. 9 mm thick
Nitrate rubber mate should be passed under the raised floor on the true surface of
insulation.
Make: Emerson / Stulz / Uniflair / Conteg / Climaveneta
Capacity – 3 or 4 TR with 1+1 redundancy
3.2 Air Cooled Chillers: (N+1 Redundancy)
The design of the Chiller of actual capacity of 40 TR or higher has the following
specifications. Chillers should have all protections and interlock arrangement like LP,
HP, OP, Safety thermostat (Anti freezing) in the evaporator, phase reversal, water flow
switch in chilled water lines, chilled water pump. The interlocks shall be provided with
indicating lamps or flags on the control panel in the air conditioning plant room. All these
shall have by-pass push button switches.
Chiller will be used in cooling water for Liquid cooling racks chiller should have compact
design with control components on the front and air intake via the right-hand side panel,
air outlet via the left-hand side panel. It should be pressure-sealed system. It should have
Digital thermostat for temperature control with set point and actual value display. It should
have a tank and pumps to supply adequate water to the cooling racks.
Two separate UPSs (1+1 in parallel) of 20kVa with 15 Mins battery backup for each UPS
should be provided for chilled water distribution such as pumps, Make of the UPS – Eaton
, Emerson , APC, Socomec.
There must be an insulated storage tank of 1000 Ltr capacity to take care of the cooling
during power failure.
Formatted: Font: Bold
Formatted: Line spacing: single
13
3.3 Technical specifications:
Application details Specifications
Criticality (Normal/High) High
Heat load 140 kW / Equal to or greater than 40 TR actual
capacity
Chiller Capacity 140 kW / equal to or greater than 40 TR x 2
Cooling media specification Soft water
Required media temperature As required or 7 deg.C
Required media flow rate and
pressure per chiller
minimum of 400 lpm at pressure of 3 kg/sq. cm.
Type of flow (constant or varying) Constant
Location of chiller wrt to machine
(horizontal and vertical distance)
Not to exceed 40 meters head
Media quality Treated soft water
Allowed media hold-up volume in
piping per chiller
Up to 50 liters per chiller
Installation site (Indoor or outdoor) Out-door
Min and max ambient temperature at
site
120C to 400C
Ambient air quality
(normal/dusty/saline/acidic)
Normal
State / city where chiller is being
installed
Bangalore
Ventilation at site (good/poor) Good
Recommendation for ventilation (if
poor)
None
Clearance around chiller (in meters) 1.5 to 2 m
Recommended interconnect piping MS Pipes
14
MOC
Recommended interconnecting pipe
dia
3” dia
Recommended piping insulation MOC TF quality Thermocole
Recommended piping insulation
thickness
2” – 50mm
Recommended piping accessories As per std practice
Recommended interlocks from chiller
to process
SNMP
Remote control panel for chiller NA
Rated Chiller Cooling Capacity (TR /
KW)
Equal to or greater than 40 TR
No. of chillers for this project Equal to or greater than 40 TR x 2
Refrigerant R 407C
Rated media temperature As required
Operating media temperature range As required or 70C to 120C
Tolerance for rated media
temperature (+/-)
+/- 20C
Rated media flow rate @ pressure per
chiller
400lpm @ 4 bar
Rated ambient temperature 380C
Min and Max operating ambient
temperature
120C to 450C
Type of compressor Scroll
No. of compressors per chiller >3
Type of condenser Air cooled
15
No. of condensers per chiller 3
Type of evaporator Shell and tube
No. of evaporators per chiller Minimum 2
Media reservoir holding capacity
(liter) per chiller
1000 liter External Tank
No. of pumps per chiller 1
Chiller inlet outlet dia and end
connection type
2.0” dia BSP female connector
No. of skids per chiller 1
Dimension of each chiller package (W)2550 x 2550(D) x 2300(H)
Power supply 3 PH, 415 V, 50 HZ
Energy consumption in KWh / Amps Approximately 1.2 kW per TR.
Chiller safety interlock list HP, LP, COMP OLR, FAN OLR, PUMP OLR,
WATER LEVEL, AFT, FAN CYCLING, SPP
Others PLC FOR SEQUENCING OF CHILLERS
Communication interface : SNMP
4.0 LOW SIDE WORKS: PUMPS & PIPING
This should conform to Tier 3 standards. The piping should take into account the
possibility of both chillers operating at the same time in future. Also it should provide for
the addition of a third chiller for future expansion.
The pumps should be selected as per the total water requirement (Q) for
the cooling racks keeping in mind the min/max. Water required in chiller
cooler.
While selecting/designing the pump, proper balancing to be done between
the flow required for all cooling racks and cooler water flow requirement.
16
The selection of the pump should be such that all cooling racks and chiller
cooler should get designed water flows.
The pump head should be selected as per the inlet pressure required in
cooling rack after taking into account piping head losses, cooling rack air-
water heat exchanger pressure drop etc.
At least one identical pump is to be provided for redundancy.
The pump shall be capable of developing the required total head at rated
capacity.
The pump shall run smoothly without undue noise and vibration.
Suction & discharge connection shall be flanged
Pump impeller shall be dynamically and statically balanced.
All accessories required for proper and safe operation shall be furnished
with the pump.
The power rating of pump motor shall be adequate for the requirement, and
shall be clearly specified in the technical bid.
Make and type of pump, along with all details of shaft, impeller, sealing,
coupling, nozzle orientation and flange drilling shall be submitted in the
technical bid.
The vendor shall furnish routine and type test certificate of the pump in
original as per IS 5120. HQ characteristic curve also to be submitted.
Chillier system to be used in cooling water for rack-based cooling system
specified above is required to be provided by the vendor.
The system should have the ability to automatically shut down or start
modules according to the heat dissipation requirement at the cooling racks.
Supply and return pipes including headers from chillers & pumps other than
inside Data Centre should be In MS.
All pipes shall be insulated using thermo cole sleeves of adequate thickness
to avoid condensation on pipes.
Provide a protection coating for chillers and pumps.
5.0 Security Systems
The DC is a mission critical facility with 24/7 operations. Server room should be designed
with Integrated Fire alarm, VESDA, water leakage detection & Rodent repellent system.
17
5.1 Fire Detection and alarm System:
Fire Detection system is a firsthand safety tool to detect the fire, if present, and raise an
alarm so as to initiate action. All the detectors are connected to an Analogue Fire Alarm
Panel, which indicates the Detector on Fire.
5.2 Manual pull station:
In case any fire occurs in the building premises and one wants the hooter to alert the
people in the building to assemble in the safe assembly point, one can pull the nearest
manual pull station. Panel needs to be RESET to bring back to normal condition.
S.N
O Description Model
Quanti
ty Unit
1 Supply & installation of 4 Zone Conventional Fire
alarm panel with Battery Back
Notifier/Ravel 1 Nos
2 Supply & Installation of multi Sensor Smoke detector
with Base plate
Notifier /
Ravel 12 Nos
3 Supply & Installation of Strobe with Electronic
Hooter
Insyin 2 Nos
4 Supply & installation of Response Indicator Insyin 4 Nos
5 Supply & installation of Manual Call point with back
box
Insyin 2 Nos
6 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 150 Nos
5.3 Very Early Smoke Detection and Alarm [VESDA] SYSTEM
5.3.1 Introduction:
The VESDA is a programmable, intelligent controlled, self-contained air sampling smoke
detector. The VESDA or the very early smoke detection system that provides the highest
sensitivity appropriate for detecting a complete range of smoke particles produced in
incipient stage and real fires involving natural or synthetic materials. It comprises of an
air sampling system, filter assembly, aspiration system, detector and control system.
5.3.2 Design:
The VESDA uses a unique technology, an intense broadband light source (XENON Strobe
Light) in order to closely emulate the spectrum and intensity of sunlight itself. The
system has a photoelectric receiver which is used to gather the scattered light having a
18
broadband spectrum. This broadband spectra response makes the detector respond to all
particle sizes. The smoke particles produced during real or incipient fire shall depend on
the fuels involved and combustion temperatures. Thus a broadband spectrum method of
detection performs well for a complete range of fuels and through the process of fire.
S.N
O Description Model
Quantit
y Unit
1 Supply & installation Aspiration detector for Server Room
-Xtralis VF250 Xtralis 1 Nos
2 Supply & Installation of Power Supply Unit with Battery
back-up Xtralis 1 Nos
3 Supply & installation air termination Nozzle & capillary
tubes Xtralis 6 Nos
4 Supply & Installation of 25mm PVC trunk Conduit with
accessories ISI 20 Nos
5 Supply of laying of 2 core 1.5sqmm FRLS Armode cable ISI 15 Nos
6 Supply & Installation Electronic hooter ISI 1 Nos
The VESDA system is protecting the Server of the DC with very early warning of smoke
detection and alarm. The air sampling is done in all the three voids of the Server room
and the Network room i.e., below the false floor, room void and above the false ceiling.
This gives very early warning in case of fire in any of these three voids.
5.3.3 Principle of Operation:
The aspirator draws the air from the protected areas through the air-sampling network,
through the multi stage filter assembly to screen out the large airborne dust particles and
through the specially constructed detector head where it is exposed to a broadband
spectrum of light. Light scattered by the particles pass through a series of optical
components to an extremely sensitive solid-state light receiver. The receiver converts
the light energy into an electronic signal representing the level of smoke in the air sample.
The receiver sends this signal to a microprocessor where it is processed and presented on
the bar graph display as one of many lighted segments. This activates the alarm indication
when appropriate.
5.4 Rodent Repellent System:
Ultrasonic Frequency sound wave based system has to be installed in DC & UPS Room
S.N
O Description Model
Quantit
y Unit
1 Supply & installation of Rodent
repellent panel
C
System 1 Nos
2 Supply & Installation of High frequency
Transducer
C
System 12 Nos
19
3 Supply of laying of 2 core 1.5sqmm
FRLS cable ISI 250 Nos
5.5 Water Leak Detection System:
The Water Leak Detection system is to be installed for the Server Room.
S.N
O Description Model
Quantit
y Unit
1 Supply & installation 2 Zone water
leakage panel
C
System 1 Nos
2 Supply & Installation sensor cable
20Mtr roll
C
System 2 Nos
6.0 BUILDING MANAGEMENT SYSTEM (BMS) 6.1 SCOPE OF WORK
The general scope of work to be carried out under this BMS subhead is illustrated in
Specifications.
The following equipments are to be monitored via MODBUS card in system
Two number of Chiller
Two number of 160Kva UPS – Existing
2 nos. 20kVa UPS
Two numbers of PAC units
CLC / MCL rack unit
Fire alarm
Main Electrical panel – Existing
Cabling should be done from all the above system and connected on one system provided
by IISc. The SNMP based monitoring system should be load on the system and monitoring
of all those should be done.
The software should able to show the performance of the respective equipments on single
screen.
6.2 Electrical System
Main electrical panel and UPS Main DB is available in SSCU/IISc new building.
Power cabling for Chillers to be taken from main electrical panel . Necessary switch
gears should be provided for chiller operation.
Existing 2 x 160 kVA UPS power provided at UPS Output DB in Electrical room. The
same power should be tapped for Sub distribution at server room. SDB board should be
20
provided at server room and individual MCB should be provided per racks power source .
Dual source should be provided per racks. DC socket with lock socket should provided.
Two new earth pits shall be made and tapped for UPS output wiring.
The Power to Server via two SDB’s & Power to Chiller should be metered and monitored
in
BMS.
7.0 Services Level Agreement (SLA) & Warranty
The Supplier warrants that all the goods are new, unused, and of the most recent
or current models, and that they incorporate all recent improvements in design and
materials, unless provided otherwise in the Contract.
The bidder has to ensure that the solution proposed delivers an uptime guarantee
of 99% of the entire system on a yearly basis. For every extra day of downtime
above 1%, the warranty should be extended by twice that duration. In the event of
failure of any of the sub-systems or components of the proposed solution, the
bidder has to ensure that the defects are rectified within two full working days. All
these conditions need to be satisfied. During the warranty period, vendor will have
to undertake comprehensive maintenance of the entire equipment and accessories
supplied by the vendor at the place of installation of the equipment.
The defects, if any, during the guarantee/warranty period are to be rectified free of
charge by arranging free replacement wherever necessary.
A letter of commitment for support for seven years from the OEM for every item
should be enclosed in the cover for Technical bid. Offers will be rejected if they are
not accompanied by the letter from OEM.
IISc will have the right to impose a penalty of 0.5% of PO value per week for delay
under any of the following conditions:
a) Delay in delivery of equipment beyond scheduled delivery period.
b) Delay in successful installations/commissioning of system beyond scheduled period.
The maximum penalty for non-performance will be 5% of the total cost. On reaching
this limit in any year, the bidder will be considered in breach of the contract. The
penalty will not apply if the delay is caused by IISc.
Training for general system/equipment maintenance with documentation including
tasks such as starting and shutting down the chiller, adding water to the storage
tank, starting the internal cooling units and any other required functions.
Technical support for all equipment running and maintenance.
The vendor must submit the name of the service engineers employed by them who
are competent to service the data center equipment along with their contact details
21
in India. Working knowledge of starting, shutting down and maintenance need to be
provided to IISc DC administration team.
8.0 General terms and conditions: 1. Any item not specifically mentioned in the specification but is required for successful
implementation of the data center (DC) solution (in the option of the vendor) must be
brought to our notice and quoted accordingly.
2. Delivery, installation and execution (job completion) period will be 6 weeks from the
date of PO. Performance Bank Guarantee (PBG) of a total of 10% of the value of the
quoted amount in commercial tender is required. This will be retained until the completion
of three years from the date when the installation is completed and warranty begins for
the bidder who is successful in getting the order.
3. The vendor immediately after the award of the work shall prepare a detailed plan of
installation as proposed to be followed by placement of the equipment, etc.
4. The installation should be done by certified and trained engineers for DC followed by
comprehensive user training.
5. If OEM is not the direct bidder in that case OEM has to issue MAF (Manufacturer's
authorization form) to partner along with services guaranty letter to IISc that in case of
partner failing to do installation, OEM would take installation & support responsibility.
6. OEM should provide an undertaking that OEM is responsible for 3 year performance
guarantee.
7. Payment will be made subject to satisfactory and successful installation and acceptance
certificate issued by IISc.
8. If the prices offered are not competitive or are higher than the market prices then we
reserve the right to cancel part or whole of the tender.
9. 3-years on-site comprehensive warranty should be provided. Provide Annual
Maintenance Contract (AMC) Charges for 4th, 5th, 6th & 7th years separately as a
percentage of total cost.
10. Vendor to quote item wise price. IISc may decide to increase/decrease the number of
items at the time of negotiation based on budget availability. IISc may or may not order
the optional items mentioned in the tender.
11. Along with the hard copy of the technical bid a soft copy containing all details in the
hard copy should also be enclosed.
22
9.0 USER ACCEPTANCE TEST CHECK LIST (All the below test results should be demonstrated on live)
Sl. No. Test Item Complied
1 Chiller starting and stabilization time
2 Time required for temperature to reach the optimal value (inside the
rack) when starting for the first time (when water is not previously
chilled)
3 Temperature inside the rack when power fails in the first 15 minutes
4 Rate of temperature rise when power fails during the first 15 minutes
10. CHECK-LIST (If you can provide more information/s or drawings explaining your solutions, please
provide it as separate items and label it with index.)
Sl No. Description Information
1 Chiller make, model number, power consumption,
capacity, maximum time for stabilization of cooling
2 Details of units (heat exchanger) within data center
3 Details of Precision air conditioner within data center
4 Details of monitoring
5 Details of low-side works
6 Details of pump
7 Details of UPS or several UPS to support pump
8 Details of Cold water tank
9 Details of fire alarm
10 Details of Water leakage detection
11. POWER CONSUMPTION CHECK LIST:
Sl
No.
Components Maximum power consumption
per unit
(in kW)
Total Power
(Quantity × Power)
in kW
1 Chiller
2 Internal heat exchanger
units
3 Water circulating pump
4 UPS
23
5 PAC unit
6 Fire detection
7 Rodent protection
8 Water leakage detection
Grand Total(exclude those
which overlap in the power
consumption)
12.0 Submission of Proposal
The proposal should be submitted in two separate covers, one containing technical
specification and the other one the price details. The vendor name, the nature of the
envelope (either technical specifications or commercial/price bid) must be clearly
mentioned on top of each of the envelope. The sealed proposals must be addressed to
SSCU, IISc-Bangalore. The proposals should be submitted to Ms. Bavitha, Room 209,
SSCU, IISc.
Prices should NOT be given anywhere in the technical bid. Mention of prices in technical
bid may result in disqualification. A copy of the Price bid with prices masked but giving all
other details should be enclosed along with the technical bid.
The prices can be quoted either in foreign denominations or in INR. Provide itemized
pricing for each item. Please specify the statutory taxes and duties, if any. Please note
that IISc, being an academic institution with University status is eligible for customs duty
exemption.
Price bid to be given in following format
13.0 PRICE BID TABLE Sl
No. Components Qty Unit Price Total Price
1 Chiller
2 Internal heat exchanger
units
3 Water circulating pump
4 2 x 20Kva UPS
5 PAC unit
6 Fire detection- VESDA &
Smoke alarm
7 Rodent protection
8 Water leakage detection
24
9 Electrical system
10 BMS System
Grand Total (INR,
before tax)
Taxes (state type of tax)
Grand Total (INR)
(including tax)
Grand Total (USD, before
tax)
Taxes (state type of tax)
Grand Total (USD)
(including tax)
INR price to be specified with applicable TAX separately.
Wherever multiple options have been offered mention details for each option.
Vendor to quote item wise price. IISc may decide to increase/decrease node count
at the time of negotiation based on budget availability.
SBI price of dollar on the last date for submitting of tender will be considered for all
calculation regarding price comparison.
14.0 Likely Time-line
Last date for receiving queries
by e-mail
Technical queries may be sent
to [email protected] and
[email protected] with
subject line showing “TUE-
CMS DC: Technical Query”
Commercial queries may also be
sent to the above email address,
with subject line “TUE-CMS
DC: Commercial Query”
:
1st July 2015 10.00 am
25
Site visit to inspect
infrastructure
: 30th June 2015 10.00 am
Pre-bid meeting : 6th July 2015 3.00 pm
Last date for submission of bids : 13th July 2015 12 noon
EMD : Rs. 5 lakhs in favor of IISc, in the form of DD, in the name of
Registrar, Indian Institute of Science
15.0 Bill of Quantities
The following are provided for general guidance. However, if any additional
items and/or quantities are required they should be mentioned in addition to
those listed below and quoted. Any item given below which is not required
may be omitted. The following list may be modified as per the vendor's
requirement.
15.1 - Air cooled Chiller
Sr. No. DESCRIPTION QUANTITY
1.0
Supply, Installation, Testing and Commissioning of Air-cooled chillers
comprising of 2 nos Scroll type compressors, Condenser cooling coils,
condenser fans, Shell and tube Chiller etc,.
Ref. Capacity – Equal to or higher than 40 TR 2
Chilled Water O/I Temp - 7/12 deg.C
Fouling Factor Chiller - 0.000018 MKS Units
Chilled Water Flow : 107 Usgpm
Condenser Air temp = 35.6 OC
2.0
Supply, installation, testing and commissioning of End suction
centrifugal pump for primary chilled water circulation with drive motor,
flexible coupling and vibration isolators as per specification with
following Tech Data:
2
Water Qty : 107 US GPM
Static Head : 80 Feet
Impeller : Bronze
Formatted: Justified
26
Speed : 1500 Rpm
Seal : Mechanical
3.0
Supply, installation, testing and commissioning of End suction
centrifugal pump for Secondary chilled water circulation with drive
motor, flexible coupling and vibration isolators as per specification with
following Tech Data:
2
Water Qty : 75 US GPM
Static Head : 100 Feet
Impeller : Bronze
Speed : 1500 Rpm
Seal : Mechanical
4.0
Supply, installation, testing and commissioning of Chilled water piping
with MS 'C' class pipe complete with all accessories such as bends,
elbows, flanges, nut bolts, air purging valves, de-scaling Tee with MS
Angle & Rod Supporting work etc. of following sizes and insulated with
TF quality thermocole and covered with AL cladding.
80 mm dia 50
65 mm dia 6
50 mm dia 6
40 mm dia 20
5.0
Supply, Installation, Testing and commissioning of Drain piping carried
out of Hard drawn pipes 9mm thick nitrile rubber insulation as per
specification. This includes opening of a hole in the wall and closing of
the hole after the work.
25mm dia 25
20mm dia 25
6.0
Supply, Installation, Testing and commissioning of Insulated Butterfly
valves together with accessories like flanges, fasteners, etc.,with
necessary Nitrile rubber insulation.
80 mm dia 10
7.0
Supply, Installation, Testing and commissioning of Insulated wafer type
Check Valves together with necessary accessories like flanges,
fasteners, with necessary Nitrile rubber insulation.
80 mm dia 4
8.0
Supply, Installation, Testing and commissioning of 2 Way Motorized
Valve with suitable On/Off actuator fitted and necessary Nitrile rubber
insulation.
27
50 mm dia RO
9.0
Supply, Installation, Testing and commissioning of Insulated Y strainer
with drain plugs and suitable supports. The strainer shall be complete
with necessary accessories like flanges, fasteners, etc. with necessary
Nitrile rubber insulation.
80 mm dia 5
50 mm dia brass Y stainers (20 mesh) 5
10.0 Supply, Installation, Testing and commissioning of Drain cock with
necessary Nitrile rubber insulation.
25mm dia 5
11.0
Supply, Installation, Testing and commissioning of insulated automatic
Air Vent complete with pipe nipples, 20 mm NB ball valve, etc. with
necessary Nitrile rubber insulation.
5
12.0
Supply, Installation, Testing and commissioning of Pressure gauge &
thermometer complete with suitable Nipple piece of suitable length to
suit the Insulation Thickness with adapter for pressure gauge.
Pressure Gauge 10
Stem type thermometer 4
13.0
Supply, Installation, Testing and commissioning of Insulated Ball valves
together with accessories like flanges, fasteners, etc., with necessary
Nitrile rubber insulation.
50 mm dia 10
14.0
Floor insulation 13 mm - nitrile rubber stuck with synthetic rubber
adhesive with Joints sealed with 50 mm wide 3 mm thick self adhesive
nitrile rubber tape.
50
15.0
Supply, installation, testing and commissioning of 500 Lts Sintex Tank -
HDPE Expansion tank with 3m height steel structural work with
provision for quick fill and float.
1
16.0
Supply, installation, testing and commissioning of 1000 Lts fabricated
out 6mm thick MS plate for Hot / Cold well Tank and insulated with TF
quality EPS slabs and covered with Aluminium cladding.
1
28
15.2 – Civil Works
Sr.
No. DESCRIPTION QUANTITY UNIT
01 Raised floor with 400mm height , 1500USF , 600mm X 600mm
Tiles 588 Sqft
02 Perforated grills 600mm X 600mm 4 Nos
03 9mm Nitrate Rubber mate pasted on the floor below raised
floor 625 Sq ft
04
Fire rated gyb board partition - The basic stretchers made of
aluminium c angles . Both sides are fitted with twin 6mm fire
rated gyb board . The partition to be from ceiling to floor -
All windows to be closed with the gyb board.
200 Sqft
05 Construction of Chillier bed with brick and cement mortar 120 Sqft
15.3 – Cooling Racks
Sr. No. DESCRIPTION QUANTITY UNIT
01 Server Rack 800 Width X 2000 Height (42U) X 1200Depth 4 Nos
In rack the usable depth is 800mm due to hot and cold zone
within the IP54 sealed block.
Front & Rear door –glass door, complete with swivel handle with
DIN half profile cylinder plug - Balanced Load rating 1500 kg
Each Server and Network Rack should be with 2 nos-24 nos.
IEC C13 and 6nos. IEC C19 -
02 Cooling units should be same size of server racks and installed
side by side. As required Nos
The cooling units should have front blowing fans with deflector . Not less than
30kw units
The capacity of each units shall be not less than 30kw cooling
capacity
In built fire suppressions kit for each of the rack provided.
Temperature, Humidity , Water leakage , auto door opening ckt
shall be built in. The control module should be communicating to
BMS system via MODBUS
15.4 – Security products
15.4.1 Fire Alarm
S.N Description Model Qty Unit
1 Supply & installation 4 Zone Conventional Fire alarm
panel with Battery Back
Notifier/
Ravel 1 Nos
29
2 Supply & Installation of multi Sensor Smoke detector
with Base plate
Notifier /
Ravel 12 Nos
3 Supply & Installation of Strobe with Electronic Hooter Insyin 2 Nos
4 Supply & installation Of Response Indicator Insyin 4 Nos
5 Supply & installation Manual Call point with back box Insyin
2 Nos
6 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 150 Nos
15.4.2 VESDA
S.N. Description Model Qty Unit
1 Supply & installation of Aspiration detector for Server
Room -Xtralis VF250 Xtralis 1 Nos
2 Supply & Installation of Power Supply Unit with Battery
back-up Xtralis 1 Nos
3 Supply & installation of air termination Nozzle & capillary
tubes Xtralis 6 Nos
4 Supply & Installation of 25mm PVC trunk Conduit with
accessories ISI 20 Nos
5 Supply of laying of 2 core 1.5sqmm FRLS Armoured cable ISI 15 Nos
6 Supply & Installation of Electronic hooter ISI 1 Nos
15.4.3 Water leak detection system
S.N Description Model Qty Unit
1 Supply & installation of 2 Zone water leakage panel C System 1 Nos
2 Supply & Installation of sensor cable 20Mtr roll C System 2 Nos
15.4.4 Rodent repellent system
S.N Description Model Quantit
y Unit
1 Supply & installation of Rodent repellent panel C System 1 Nos
2 Supply & Installation of High frequency Transducer C System 12 Nos
3 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 250 Nos
30
15.4.5 BMS system
Sr. No. DESCRIPTION QTY UNIT
01 Modbus based BMS system to connect the following equipments -
With desktop PC 1 Set
02 Chiller - 2Nos , UPS - 4Nos , PAC -1 , Racks cooling unit -1 , Fire
alarm , Three power meter
15.5 – PAC Cooling unit
No. Description Qty Unit
High Precision Air conditioners
1 Supply of Uniflair make PAC units (Bottom Discharge); DX-Air cooled
PACs complete with direct drive motors and Fans with backward
curved blades, Expansion Valve, Scroll Compressors for power
savings, hydrophilic fins for IDU, fan speed controller for ODU,
Water leak detector, Clock card, Sequencing and RS485 card supplied
with the system. EU2/EU4 filters is provided. Unit offered will be
suitable for eco friendly R407 C; Dirty filter alarm, heater, humidifier
are part of the system. PAC will be pre-charged with N2.
4.5TR PAC units as per above specs. Max CFM @ 2905 / unit (PAC
Units without Heater & Humidifier, with Thermostatic expansion
valve and EU2 filters) 2 Nos
2 Low Side Works for High Precision AC Units
Supply & Installation of MS stand suitable for raised floor of 400 mm
clear height. 1 Nos
Leak testing and Refrigerant filling with R 407 C 64 Kg
Power cabling from indoor to outdoor units considering 18RMt per
unit. 18 RMt
Cables for Sequencing of units, 10 RMt per unit 10 RMt
Humidifier line (Consider 10RMT per unit) 10 RMt
Drain line with insulation (Consider 10RMT per unit) 10 RMt
Cu piping interconnecting indoor and outdoor (20RMT per Ckt.) 15 RMt
Insulation of Copper pipe 15 RMt
31
15.6 – UPS for Pump
SL No UPS Specification
01 2 x 20kVA UPS
02 On Line double conversation UPS
03 IGBT Charger & Inverter
04 UPS operation in parallel mode.
05 3 Phase input and single phase output
06 Input 415 V +/- 15%
07 Input voltage harmonic destruction less < 5%
08 Output Voltage 230V 50Hz
09 Efficiency above 92% at full load.
10 Each Battery bank to support 15mins at full 20kVA Load.