31
1 Thematic Unit of Excellence on Computational Materials Science (TUE-CMS) Solid State and Structural Chemistry Unit Indian Institute of Science Bangalore 560012 Open Tender Request for Proposal for Datacenter Reference No. SSCU/TUE/DC/2015-186 dated 26 th June, 2015

Open Tender Request for Proposal for Datacentertejas.serc.iisc.ernet.in/tender/dc_rfp_final_v8.pdf · Request for Proposal for Datacenter Reference No. SSCU/TUE/DC/2015-186 dated

  • Upload
    others

  • View
    23

  • Download
    0

Embed Size (px)

Citation preview

1

Thematic Unit of Excellence on Computational Materials Science (TUE-CMS)

Solid State and Structural Chemistry Unit Indian Institute of Science

Bangalore 560012

Open Tender Request for Proposal for Datacenter

Reference No. SSCU/TUE/DC/2015-186 dated 26th

June, 2015

2

Table of Contents 1.0 Solution Overview ............................................................................................................... 4

1.1 Physical Components Design .................................................................................... 4

1.2 Existing floor and DC space ...................................................................................... 5

1.3 Detailed Product-wise scope ...................................................................................... 5

1.3.1 Raised floor ....................................................................................................5

1.3.2 Sub structure – pedestal assembly ..................................................................5

1.3.3 Stringers ..........................................................................................................6

1.3.4 Other Non structural Parameters ....................................................................6

1.3.5 Fire Rated Gypsum Partition across the room ................................................7

1.4 Rack Specifications .................................................................................................... 7

1.4.1 Technical specifications: ................................................................................7

1.4.2 PDU - Power Distribution Unit for Rack (N+1) ............................................8

1.4.3 Closed Loop Rack based cooling system .......................................................8

1.4.4 High Performance Liquid Cooling Package – Closed Loop Cooling. ...........8

1.5 Air-Conditioning ........................................................................................................ 9

2.0 Monitoring ......................................................................................................................... 11

3.0 Rear Auto door Opening for Closed Loop Cooling System .............................................. 12

3.1 Precision Air conditioning ....................................................................................... 12

3.2 Air Cooled Chillers: (N+1 Redundancy) ................................................................. 12

3.3 Technical specifications: ......................................................................................... 13

4.0 LOW SIDE WORKS: PUMPS & PIPING ........................................................................ 15

5.0 Security Systems ................................................................................................................ 16

5.1 Fire Detection and alarm System: ............................................................................ 17

5.2 Manual pull station: .................................................................................................. 17

5.3 Very Early Smoke Detection and Alarm [VESDA] SYSTEM ................................ 17

5.3.1 Introduction: .................................................................................................17

5.3.2 Design: ..........................................................................................................17

5.3.3 Principle of Operation: .................................................................................18

5.4 Rodent Repellent System: ....................................................................................... 18

5.5 Water Leak Detection System: ................................................................................. 19

6.0 BUILDING MANAGEMENT SYSTEM (BMS) ............................................................. 19

6.1 SCOPE OF WORK .................................................................................................. 19

6.2 Electrical System ...................................................................................................... 19

7.0 Services Level Agreement (SLA) & Warranty .................................................................. 20

8.0 General terms and conditions: ........................................................................................... 21

9.0 USER ACCEPTANCE TEST CHECK LIST ................................................................... 22

10. CHECK-LIST .................................................................................................................... 22

11. POWER CONSUMPTION CHECK LIST: ...................................................................... 22

12.0 Submission of Proposal.................................................................................................... 23

13.0 PRICE BID TABLE ........................................................................................................ 23

14.0 Likely Time-line .............................................................................................................. 24

15.0 Bill of Quantities .............................................................................................................. 25

15.1 - Air cooled Chiller ................................................................................................ 25

15.2 – Civil Works ......................................................................................................... 28

15.3 – Cooling Racks ..................................................................................................... 28

15.4 – Security products ................................................................................................. 28

15.4.1 Fire Alarm ..................................................................................................28

15.4.2 VESDA .......................................................................................................29

3

15.4.3 Water leak detection system .......................................................................29

15.4.4 Rodent repellent system .............................................................................29

15.4.5 BMS system................................................................................................30

15.5 – PAC Cooling unit ................................................................................................ 30

15.6 – UPS for Pump ..................................................................................................... 31

Bidders may obtain the Request For Proposal (RFP) which includes Technical Specifications and Bill of Quantities from Ms. Bavitha, Room 209, SSCU, INDIAN INSTITUTE OF SCIENCE, C V Raman Ave, Bengaluru, Karnataka 560012. Bidders can also download RFP Documents on this Institute’s website http://www.iisc.ernet.in/tender/index.php however they are required to pay tender fee in the manner as prescribed below along with Bid document. Documents must be in two cover format with technical part and commercial part in two separate sealed covers. They must be superscribed as ‘Technical Bid' and ‘Commercial Bid’. The bids should be accompanied by a nonrefundable DD for Rs. 5,000 / - (Rs. Five Thousand only) drawn in favour of “Registrar, INDIAN INSTITUTE OF SCIENCE” payable at Bangalore.

4

1.0 Solution Overview

IISc SSCU is in need of Tier 3 Data Center (DC) for its HPC server Project. This bid is to

build cooling solution for High Performance Computers (HPC) along with racks, electrical

cabling & Security products for DC. The room dedicated to the data center has an area of

588 sq ft. The floor to ceiling height is only 9 ft and 6 inches. The solution could use all or

part of this space. The scope is for supply, installation and maintenance for a period of 5

years.

The DC area should support presently 7 nos of 800 mm width server rack of 42U. Only 4

racks with a total capacity of 110kW is expected now but provision for possible addition in

future of 3 more racks should be made. Chilled water based cooling solution should be

provided to achieve PUE of 1.5 or lower. UPS power supply from Existing UPS of 2 x 160

kVA will be provided close to the DC. The power distribution from existing UPS output

panel’s to racks including DB installation in Server room and individual socket for racks is

in supplier scope. Dual power source per rack shall be provided.

Two UPS each of capacity 160 kVA and one diesel generator (DG) have already been

installed and supply from these to the data center will be made available.

Closed loop cooling solution ( CLC ) to support 110 kW heat load across 4 racks shall be

provided & should be expandable up to 7 racks without any dependency. The closed loop

cooling solution should be adaptable in case the heat load increases up to a rack density of

35 kW/rack with just addition of cooling unit as in modular datacenters. Dual chiller plant

equal to or not less than 40 Tr actual capacity on ambient temperature 37°C shall be

provided on N + 1 configuration. Open space behind the server room shall be used for

installing chiller plant.

1.1 Physical Components Design

IISc is in need of Turnkey Implementation of the Data Center including Program

Management Services for Data Center Set Up. The bidder/solution provider shall submit

Detailed Engineering Drawings of various components of Data Center and revise the same

as required till the drawings/design is finally approved by IISc and that also includes all

drawings like air conditioning, electrical system, Fire alarm systems, data cabling etc.

Preparing detailed specifications and supply Installation and Commissioning of the following

critical components for Data Center is required:

Civil – Partition & Raised floor

Electrical System for Data Center cabling from UPS to DC and all cabling within DC

CLC Cooling Systems

Air cooled chiller and piping

Power Distribution and cable management From UPS to Racks

Fire alarm, suppression and VESDA system

5

Water Leak Detection System

Pest Control (Rodent Repellent System)

1.2 Existing floor and DC space

A smaller portion from given space of 12.3Mtr x 4.2Mtr may be used for DC. One fire

rated door out of two provided to be used for server room after building partition wall

across the space. Raised floor of 1500 USF at the height of 300 to 400 mm. Metal steps to

be provided from fire rated door for entry.

1.3 Detailed Product-wise scope

1.3.1 Raised floor

A total of 588 sq ft raised floor with below spec to be provided.

Unitile® USF 1500 Access Floor panel of size 600x600 mm shall be all steel welded

construction, with an enclosed bottom pan of 49 hemispherical and 36 reverse cones and

top plain sheet which are fuse welded at 129 locations to form a panel of an overall

thickness of 35mm. The panel after cleaning, degreasing, phosphating by 11 tank process

is coated with 40-60 micron epoxy coat and is heated to achieve maximum adhesion to the

panel surface and corrosion resistance. The inner empty core of the panel is injected with

a light weight fire retardant, non combustible cementitious compound at high pressure to

fill in all the crevices of the panel and ensures support of not less than 90% of the top

surface area of the panel.

The panel is then laminated with 1.5/2.00 mm thick fire retardant floor grade Antistatic

Laminate / ESD Laminate - PVC / Conductive / Dissipative PVC on a semi -automated

lamination line to ensure maximum bonding to the steel surface. The edges of the

laminated are protected with conductive PVC edge trim 5mm wide on all sides. This edge

trim is mechanically locked and sealed in place to avoid detachment.

1.3.2 Sub structure – pedestal assembly

Sub structure installed to support the panel shall be suitable to achieve a minimum finished

floor height of 300 mm to a maximum of 400 mm from the existing floor level. Pedestal

design shall confirm speedy assembly and removal for relocation and maintenance. The

assembly shall provide easy adjustment of leveling and accurately align panels for a

maximum ± 25 mm in the vertical direction. Pedestals shall support an axial load without

permanent deflection and an ultimate load as laid out in System Performance requirement.

The Pedestal head assembly shall consist of a 75 x 75 x 3.50 mm embossed head

mechanically riveted to a 100 mm long ¾” dia rolled formed stud and 2 check nuts for level

adjustment and arresting vertical movement. The pedestal head shall consist of an anti-

vibrational PVC cap for Panel location.

6

The Pedestal Base assembly shall consist of 22.23 mm OD pipe mechanically locked on a

press for perpendicularity and then welded to a base plate of 100 x 100 x 2 mm thick with

stiffening folds.

The sub structure assembly shall be suitably anchored to the floor with suitable adhesive

or fastener as recommended by the consultant / manufacturer. All steel components shall

be zinc electro plated.

1.3.3 Stringers

The stringer is hot dipped galvanized steel cold rolled construction specially designed with

ribs embossed on 3 sides for strength, lateral stability, and for enhanced rolling loads

performance and to support the panels on all four sides for alignment. The stringer to have

a counter sunk holes at both ends to accommodate bolting of M6 machine screws to the

pedestal head assembly. The stringers shall be 21 x 32 x 0.8 x 570 mm length.

Concentrated Loads :

675 Kgs (1500 lbf ) with a top-surface deflection under load and a permanent set not to

exceed , respectively, 2.54 & 0.25 mm ( 0.10 & 0.010 inch ) according to CISCA A/F,

Section I ‘’ Concentrated Loads’’

Ultimate Concentrated Load:

1690 Kgs (3750 lbf ) without failing according to CISCA A/F, Section II ‘’ Ultimate

Loading’’

1.3.4 Other Non structural Parameters

• Fire Rating :

The Panels shall confirm to Class O & Class 1 Fire Ratings tested as per BS 476 Part 6

(Fire Propagation) & 7 (Surface spread of flame) as also ASTM E84 1998 (Flammability)

and ASTM E136 (Combustibility)

• Electrical Resistivity :

As per ASTM F150/ NFPA 99 / ANSI S7.1/ CEI 61340 but modified for surface to ground

to place one electrode on the floor surface and to attach the other electrode on the

pedestal. Resistance to be tested at 100 / 500 volts:

1. Conductive range : 2.5x104 – 1x 106 Ohms (surface to ground)

2. Static dissipative range : 1x106- 1x109 Ohms (surface to ground)

3. Anti static range : 1x109 – 2x1010 Ohms (surface to surface )

7

• Fabrication Tolerance

A. Floor panel flatness : ± 0.75 mm in any direction

B. Floor panel width or length from specified size : ± 0.50 mm

C. Floor panel squareness : ± 0.38 mm

• Installation Tolerance

A. Overall level before application of any load : ± 1.5 mm over any 5.00 Sqmt

± 6 mm over any size of basic space

B. Panel level : + 0.75 mm before the application of any load

C. Panel Interchangeability installation and removal : shall be interchangeable (except for

field cut panels) and replaceable in any of the four directions at 90º increments

Floor grills of 600 x 600 mm floor grills 4numbers to be provided.

1.3.5 Fire Rated Gypsum Partition across the room

Twin layer of 6 mm Fire resistant gypsum board to be used on both the sides of the wall

stretcher.

The height shall be 9.5 ft from floor to ceiling (approximately). All the windows inside the

server room to be closed with gypsum board to avoid heat conductivity from outside.

Putty works to be carried out on the existing wall and gypsum board and three coat of

water based painting to be carried out.

1.4 Rack Specifications

Server Rack 800 mm Width x 42U Height x 1200mm Depth.: 04 Nos.

These racks will be used to mount and house all server/network/storage devices in the data

center.

The rack has to be designed to meet the safety requirements of the modern data centre.

Both the front and rear door should have a handle with locking options. The rack should

be suitable for baying to a high performance cooling rack. Cable entry should be entered

via the roof plate and via the gland plate without affecting the climatic conditions inside

the rack.

1.4.1 Technical specifications:

Server Equipment Cabinets - 42U - 800 mm Width x 1200 mm Depth equipment cabinets

should have adjustable 19 inch front and rear vertical mounting extrusions which are EIA-

310D and IEC 60297 compliant and allow up to 1190 mm of depth for equipment mounting

(in rack the usable depth is 800 mm due to hot and cold zone within the IP54 sealed

block). Balanced load rating of 1500 kg. Cabinet should be manufactured from materials

and processes that are compliant with the most current TÜV/ISO environmental

8

management standards. The front and rear 19 inch equipment mounting rails and other

internal supporting metals are to be of un-painted galvanized steel. Cabinet shall come

complete with grounding kit, cage nuts and the following features and installed accessories:

Front door –glass door, complete with swivel handle with DIN half profile

cylinder plug and universal key 333, door system with 5 or 6 points. Opening

angle 180°, width of the door must be 75mm smaller than the outer width of

the rack.

Rear door – sheet steel, complete with swivel handle with DIN half profile cylinder

plug and universal key 333 door system with 5 or 6 points. Opening angle 180°,

width of the door must be 75mm smaller than the outer width of the rack.

Air separation frame for air-flow optimization and elimination of bypass air-

flow, consisting of mechanically joint sheets steel panels and equipped with the

sealing rim.

Balanced Load rating 1500 kg

Bottom is flat and enables direct installation of the rack on the floor

Adjustable leveling feet (6 pcs.)

IP54 protection rating when installed (joined to neighboring cooling unit for

closed loop)

Central grounding point

Rack based fire suppression – fitted inside rack with max size of 4U on each

rack.

1.4.2 PDU - Power Distribution Unit for Rack (N+1)

Each Server and Network Rack should be fitted with 2 nos. rack mounted power

Distribution unit with 24 nos. IEC C13 and 6nos. IEC C19 - for Server (high density

racks); PDU shall have the capability to monitor the power consumption of the rack on

which it is mounted.

Protocols: SNMP, Telnet, http etc.

1.4.3 Closed Loop Rack based cooling system

The Data center should be equipped with Liquid Cooling System; it is an air/water heat

exchanger to remove high levels of waste heat from server enclosures and to provide

uniform, effective, affordable cooling for Servers and similar IT equipment (switches etc)

installed in server enclosures. Each liquid cooling system should be a closed unit

consisting of a cooling system and cool either one or two server enclosures.

1.4.4 High Performance Liquid Cooling Package – Closed Loop Cooling.

CLC Rack CW should offer enclosure-based cooling separate from the room air and is

thus also able to reduce the noise level. The unit should be capable of providing cooling

9

for either one or two server racks. The hot server air should be drawn off to the rear of

the server rack. After cooling, it should be expelled at the rear of the rack and is thus

made available to the IT equipment once more.

Unit should be connected to the piping system of chilled water or anti-freeze mixture. It is

suitable for the free-cooling systems because allows warmer water usage. The surface

temperature of the heat exchanger is controlled by valve, which fluently modifies the

cooling capacity in accordance to the actual demand. Variable speed fans help to keep

always the correct airflow for all IT equipment in data center. EC motor technology used

in the fans markedly reduces the annual power consumption.

Both top and bottom connection of the unit is available.

The air-conditioning unit’s design has to be fully compatible to bystanders IT racks from

the perspective of dimensions, material, color, and mechanical coupling elements. The unit

in the row of the cabinets has to enable an installation of cable management, roof

elements, aisle doors etc.

1.5 Air-Conditioning

Air-conditioning unit includes:

- Highly efficient water heat exchanger made of copper pipes and aluminum fins

with a special surface. The oblique position of HX enlarges the surface, and

optimizes the heat transfer.

- Three stacked air filters of filtration class G4 in combustible finish for ecological

disposal. The frame is ready for easy maintenance and filter replacement.

- Five or more hot-swap radial fans with EC motors significantly reducing the

power consumption with fluent speed change and operation feedback to the

control system.

- Controller with software for independent control of all components, running also

in case of interruption of communication between units or central display.

- Minimum Four temperature sensors located in the front and rear side

monitoring the air temperature in the upper and lower part of the space.

Sensors could be calibrated from controller. Controller enables to change the

logic between average and maximal values, and arranges substitutability in case

of failure.

- Two humidity sensors located at the bottom of front and rear part of the unit

for precise monitoring of the room conditions.

- Air-conditioning unit, with “D” in the type code, includes color touch screen in

the front door. 4.3” large display is equipped with special software for

monitoring and control of up to 10 units. It enables communication through

TCP/IP protocol, remote control via Ethernet and implemented webserver, and

10

easy SW upgrading and data downloading via USB disk or SD card. Another

function implementation is possible on special request.

Functions:

- The basic task is to cool down the air from the hot zone of datacenter and

distribute it to the cold zone in front of the IT equipment. The unit is designed

to keep the constant temperature in both zones thanks to the water valve

adjustment and variable fan speed.

- If the humidity in the hot zone is within the limits set by an administrator, then

the unit’s internal logic tries to avoid any condensation of the air moisture,

maximize the cooling efficiency, and minimize influence on the humidity climate

of the room.

- If the measured air humidity is above the set point, then the unit is

automatically switched to the dehumidification mode, and actively supports the

surface condensation to decrease the humidity in the room. The resulted

condensate is discharged to the drainage.

- The unit can be equipped by integrated steam humidifier which increases the

room humidity to the set point.

- Units could be connected to bigger groups under a superior control with

advanced control logic (sequencing, team working, overload start, etc.)

Technical specifications:

Adaptable cooling output : Equal to or greater than 30kW.

Installed fans: 4 Minimum

Air throughput: Equal to or greater than 3800 m³/h

Cooling output : Equal to or greater than 30 kW

Air intake temperature: 35°C

Water inlet temperature: as required

Medium: Water

Coolant throughput: approx. 60 l/min

Pressure loss: approx. 1 bar

Voltage: 208/230 V, 1~, 50 Hz, 400 V, 3~, N, 50 Hz

11

Colour: NA

Usable installation height: free (standard: 42 U)

Dimensions: WxHxD: 300 or 600 x 2000 x 1200 mm

Touch screen display, Connection hose, bottom/top:

2.0 Monitoring 8 intelligent ports (output/input, 0-5V) with auto sense on main device with 4

expansion ports

Expandable solutions through expanders connected in daisy-chain with patch

cables

Intelligent port presented by RJ-45 for connection and extension by patch cable

Options to upload picture and with a function grab & drop able to place sensors

icon in

Multi language with a possibility to create own language version inside of device

80 virtual sensors for connecting and reading a values from SNMP devices,

Modbus devices and Ping

Email, SNMP trap, Modbus control, skype call & sms, speech

Support a sending keep alive emails in configurable interval

SNMP v1, v2 & v3

Support DHCP and NTP

Fully embedded TCP/IP and web-server with Linux OS

A standalone product without any external hardware and software

dependencies.

Configurable User & group management for login protected by password

Network Management System Integration.

Free Firmware Updates

History for measured values, able to show a graphs and statistics by day, week,

month and year (average, high and low data)

4 levels of thresholds, advance setting with (alarm report off) calender

Internal Syslog with options to send a logs to the external syslog

Status indicators on front panel (Power, Connectivity, Sensors online and

threshold status)

USB 2.0 port for options to connect GSM modem for sending alarm SMS

without requirements of 3rd party SW

Support Modbus RTU and TCP/IP

Built in speaker

Support dual one-wire probes (temperature & humidity)

1U Rack Mount Standard

Network interface - 100 Mbps Full Duplex

Operating environment – Temperature: -35°C – 80°C; Humidity: 20% - 80%

(Non-Condensing)

12

Power consumption less than 2 Watt

Battery backed time of day clock for an accurate system date and time

Power Adapter with C-14 socket and Power cord

3.0 Rear Auto door Opening for Closed Loop Cooling System

All closed looped racks should be fitted with automatic door opening kit for the back door.

Door should automatically open in case of Alarm on temperature. The auto door control

unit should be connected on SNMP TCP/IP for monitoring and control.

3.1 Precision Air conditioning

Computer Room AC (CRAC/PAC): EC fans with highly advanced digital controller to take

care server room cooling requirements & controlling humidity. Gas based unit to be

quoted with 15 mtr copper piping works. SNMP card should be provided. 9 mm thick

Nitrate rubber mate should be passed under the raised floor on the true surface of

insulation.

Make: Emerson / Stulz / Uniflair / Conteg / Climaveneta

Capacity – 3 or 4 TR with 1+1 redundancy

3.2 Air Cooled Chillers: (N+1 Redundancy)

The design of the Chiller of actual capacity of 40 TR or higher has the following

specifications. Chillers should have all protections and interlock arrangement like LP,

HP, OP, Safety thermostat (Anti freezing) in the evaporator, phase reversal, water flow

switch in chilled water lines, chilled water pump. The interlocks shall be provided with

indicating lamps or flags on the control panel in the air conditioning plant room. All these

shall have by-pass push button switches.

Chiller will be used in cooling water for Liquid cooling racks chiller should have compact

design with control components on the front and air intake via the right-hand side panel,

air outlet via the left-hand side panel. It should be pressure-sealed system. It should have

Digital thermostat for temperature control with set point and actual value display. It should

have a tank and pumps to supply adequate water to the cooling racks.

Two separate UPSs (1+1 in parallel) of 20kVa with 15 Mins battery backup for each UPS

should be provided for chilled water distribution such as pumps, Make of the UPS – Eaton

, Emerson , APC, Socomec.

There must be an insulated storage tank of 1000 Ltr capacity to take care of the cooling

during power failure.

Formatted: Font: Bold

Formatted: Line spacing: single

13

3.3 Technical specifications:

Application details Specifications

Criticality (Normal/High) High

Heat load 140 kW / Equal to or greater than 40 TR actual

capacity

Chiller Capacity 140 kW / equal to or greater than 40 TR x 2

Cooling media specification Soft water

Required media temperature As required or 7 deg.C

Required media flow rate and

pressure per chiller

minimum of 400 lpm at pressure of 3 kg/sq. cm.

Type of flow (constant or varying) Constant

Location of chiller wrt to machine

(horizontal and vertical distance)

Not to exceed 40 meters head

Media quality Treated soft water

Allowed media hold-up volume in

piping per chiller

Up to 50 liters per chiller

Installation site (Indoor or outdoor) Out-door

Min and max ambient temperature at

site

120C to 400C

Ambient air quality

(normal/dusty/saline/acidic)

Normal

State / city where chiller is being

installed

Bangalore

Ventilation at site (good/poor) Good

Recommendation for ventilation (if

poor)

None

Clearance around chiller (in meters) 1.5 to 2 m

Recommended interconnect piping MS Pipes

14

MOC

Recommended interconnecting pipe

dia

3” dia

Recommended piping insulation MOC TF quality Thermocole

Recommended piping insulation

thickness

2” – 50mm

Recommended piping accessories As per std practice

Recommended interlocks from chiller

to process

SNMP

Remote control panel for chiller NA

Rated Chiller Cooling Capacity (TR /

KW)

Equal to or greater than 40 TR

No. of chillers for this project Equal to or greater than 40 TR x 2

Refrigerant R 407C

Rated media temperature As required

Operating media temperature range As required or 70C to 120C

Tolerance for rated media

temperature (+/-)

+/- 20C

Rated media flow rate @ pressure per

chiller

400lpm @ 4 bar

Rated ambient temperature 380C

Min and Max operating ambient

temperature

120C to 450C

Type of compressor Scroll

No. of compressors per chiller >3

Type of condenser Air cooled

15

No. of condensers per chiller 3

Type of evaporator Shell and tube

No. of evaporators per chiller Minimum 2

Media reservoir holding capacity

(liter) per chiller

1000 liter External Tank

No. of pumps per chiller 1

Chiller inlet outlet dia and end

connection type

2.0” dia BSP female connector

No. of skids per chiller 1

Dimension of each chiller package (W)2550 x 2550(D) x 2300(H)

Power supply 3 PH, 415 V, 50 HZ

Energy consumption in KWh / Amps Approximately 1.2 kW per TR.

Chiller safety interlock list HP, LP, COMP OLR, FAN OLR, PUMP OLR,

WATER LEVEL, AFT, FAN CYCLING, SPP

Others PLC FOR SEQUENCING OF CHILLERS

Communication interface : SNMP

4.0 LOW SIDE WORKS: PUMPS & PIPING

This should conform to Tier 3 standards. The piping should take into account the

possibility of both chillers operating at the same time in future. Also it should provide for

the addition of a third chiller for future expansion.

The pumps should be selected as per the total water requirement (Q) for

the cooling racks keeping in mind the min/max. Water required in chiller

cooler.

While selecting/designing the pump, proper balancing to be done between

the flow required for all cooling racks and cooler water flow requirement.

16

The selection of the pump should be such that all cooling racks and chiller

cooler should get designed water flows.

The pump head should be selected as per the inlet pressure required in

cooling rack after taking into account piping head losses, cooling rack air-

water heat exchanger pressure drop etc.

At least one identical pump is to be provided for redundancy.

The pump shall be capable of developing the required total head at rated

capacity.

The pump shall run smoothly without undue noise and vibration.

Suction & discharge connection shall be flanged

Pump impeller shall be dynamically and statically balanced.

All accessories required for proper and safe operation shall be furnished

with the pump.

The power rating of pump motor shall be adequate for the requirement, and

shall be clearly specified in the technical bid.

Make and type of pump, along with all details of shaft, impeller, sealing,

coupling, nozzle orientation and flange drilling shall be submitted in the

technical bid.

The vendor shall furnish routine and type test certificate of the pump in

original as per IS 5120. HQ characteristic curve also to be submitted.

Chillier system to be used in cooling water for rack-based cooling system

specified above is required to be provided by the vendor.

The system should have the ability to automatically shut down or start

modules according to the heat dissipation requirement at the cooling racks.

Supply and return pipes including headers from chillers & pumps other than

inside Data Centre should be In MS.

All pipes shall be insulated using thermo cole sleeves of adequate thickness

to avoid condensation on pipes.

Provide a protection coating for chillers and pumps.

5.0 Security Systems

The DC is a mission critical facility with 24/7 operations. Server room should be designed

with Integrated Fire alarm, VESDA, water leakage detection & Rodent repellent system.

17

5.1 Fire Detection and alarm System:

Fire Detection system is a firsthand safety tool to detect the fire, if present, and raise an

alarm so as to initiate action. All the detectors are connected to an Analogue Fire Alarm

Panel, which indicates the Detector on Fire.

5.2 Manual pull station:

In case any fire occurs in the building premises and one wants the hooter to alert the

people in the building to assemble in the safe assembly point, one can pull the nearest

manual pull station. Panel needs to be RESET to bring back to normal condition.

S.N

O Description Model

Quanti

ty Unit

1 Supply & installation of 4 Zone Conventional Fire

alarm panel with Battery Back

Notifier/Ravel 1 Nos

2 Supply & Installation of multi Sensor Smoke detector

with Base plate

Notifier /

Ravel 12 Nos

3 Supply & Installation of Strobe with Electronic

Hooter

Insyin 2 Nos

4 Supply & installation of Response Indicator Insyin 4 Nos

5 Supply & installation of Manual Call point with back

box

Insyin 2 Nos

6 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 150 Nos

5.3 Very Early Smoke Detection and Alarm [VESDA] SYSTEM

5.3.1 Introduction:

The VESDA is a programmable, intelligent controlled, self-contained air sampling smoke

detector. The VESDA or the very early smoke detection system that provides the highest

sensitivity appropriate for detecting a complete range of smoke particles produced in

incipient stage and real fires involving natural or synthetic materials. It comprises of an

air sampling system, filter assembly, aspiration system, detector and control system.

5.3.2 Design:

The VESDA uses a unique technology, an intense broadband light source (XENON Strobe

Light) in order to closely emulate the spectrum and intensity of sunlight itself. The

system has a photoelectric receiver which is used to gather the scattered light having a

18

broadband spectrum. This broadband spectra response makes the detector respond to all

particle sizes. The smoke particles produced during real or incipient fire shall depend on

the fuels involved and combustion temperatures. Thus a broadband spectrum method of

detection performs well for a complete range of fuels and through the process of fire.

S.N

O Description Model

Quantit

y Unit

1 Supply & installation Aspiration detector for Server Room

-Xtralis VF250 Xtralis 1 Nos

2 Supply & Installation of Power Supply Unit with Battery

back-up Xtralis 1 Nos

3 Supply & installation air termination Nozzle & capillary

tubes Xtralis 6 Nos

4 Supply & Installation of 25mm PVC trunk Conduit with

accessories ISI 20 Nos

5 Supply of laying of 2 core 1.5sqmm FRLS Armode cable ISI 15 Nos

6 Supply & Installation Electronic hooter ISI 1 Nos

The VESDA system is protecting the Server of the DC with very early warning of smoke

detection and alarm. The air sampling is done in all the three voids of the Server room

and the Network room i.e., below the false floor, room void and above the false ceiling.

This gives very early warning in case of fire in any of these three voids.

5.3.3 Principle of Operation:

The aspirator draws the air from the protected areas through the air-sampling network,

through the multi stage filter assembly to screen out the large airborne dust particles and

through the specially constructed detector head where it is exposed to a broadband

spectrum of light. Light scattered by the particles pass through a series of optical

components to an extremely sensitive solid-state light receiver. The receiver converts

the light energy into an electronic signal representing the level of smoke in the air sample.

The receiver sends this signal to a microprocessor where it is processed and presented on

the bar graph display as one of many lighted segments. This activates the alarm indication

when appropriate.

5.4 Rodent Repellent System:

Ultrasonic Frequency sound wave based system has to be installed in DC & UPS Room

S.N

O Description Model

Quantit

y Unit

1 Supply & installation of Rodent

repellent panel

C

System 1 Nos

2 Supply & Installation of High frequency

Transducer

C

System 12 Nos

19

3 Supply of laying of 2 core 1.5sqmm

FRLS cable ISI 250 Nos

5.5 Water Leak Detection System:

The Water Leak Detection system is to be installed for the Server Room.

S.N

O Description Model

Quantit

y Unit

1 Supply & installation 2 Zone water

leakage panel

C

System 1 Nos

2 Supply & Installation sensor cable

20Mtr roll

C

System 2 Nos

6.0 BUILDING MANAGEMENT SYSTEM (BMS) 6.1 SCOPE OF WORK

The general scope of work to be carried out under this BMS subhead is illustrated in

Specifications.

The following equipments are to be monitored via MODBUS card in system

Two number of Chiller

Two number of 160Kva UPS – Existing

2 nos. 20kVa UPS

Two numbers of PAC units

CLC / MCL rack unit

Fire alarm

Main Electrical panel – Existing

Cabling should be done from all the above system and connected on one system provided

by IISc. The SNMP based monitoring system should be load on the system and monitoring

of all those should be done.

The software should able to show the performance of the respective equipments on single

screen.

6.2 Electrical System

Main electrical panel and UPS Main DB is available in SSCU/IISc new building.

Power cabling for Chillers to be taken from main electrical panel . Necessary switch

gears should be provided for chiller operation.

Existing 2 x 160 kVA UPS power provided at UPS Output DB in Electrical room. The

same power should be tapped for Sub distribution at server room. SDB board should be

20

provided at server room and individual MCB should be provided per racks power source .

Dual source should be provided per racks. DC socket with lock socket should provided.

Two new earth pits shall be made and tapped for UPS output wiring.

The Power to Server via two SDB’s & Power to Chiller should be metered and monitored

in

BMS.

7.0 Services Level Agreement (SLA) & Warranty

The Supplier warrants that all the goods are new, unused, and of the most recent

or current models, and that they incorporate all recent improvements in design and

materials, unless provided otherwise in the Contract.

The bidder has to ensure that the solution proposed delivers an uptime guarantee

of 99% of the entire system on a yearly basis. For every extra day of downtime

above 1%, the warranty should be extended by twice that duration. In the event of

failure of any of the sub-systems or components of the proposed solution, the

bidder has to ensure that the defects are rectified within two full working days. All

these conditions need to be satisfied. During the warranty period, vendor will have

to undertake comprehensive maintenance of the entire equipment and accessories

supplied by the vendor at the place of installation of the equipment.

The defects, if any, during the guarantee/warranty period are to be rectified free of

charge by arranging free replacement wherever necessary.

A letter of commitment for support for seven years from the OEM for every item

should be enclosed in the cover for Technical bid. Offers will be rejected if they are

not accompanied by the letter from OEM.

IISc will have the right to impose a penalty of 0.5% of PO value per week for delay

under any of the following conditions:

a) Delay in delivery of equipment beyond scheduled delivery period.

b) Delay in successful installations/commissioning of system beyond scheduled period.

The maximum penalty for non-performance will be 5% of the total cost. On reaching

this limit in any year, the bidder will be considered in breach of the contract. The

penalty will not apply if the delay is caused by IISc.

Training for general system/equipment maintenance with documentation including

tasks such as starting and shutting down the chiller, adding water to the storage

tank, starting the internal cooling units and any other required functions.

Technical support for all equipment running and maintenance.

The vendor must submit the name of the service engineers employed by them who

are competent to service the data center equipment along with their contact details

21

in India. Working knowledge of starting, shutting down and maintenance need to be

provided to IISc DC administration team.

8.0 General terms and conditions: 1. Any item not specifically mentioned in the specification but is required for successful

implementation of the data center (DC) solution (in the option of the vendor) must be

brought to our notice and quoted accordingly.

2. Delivery, installation and execution (job completion) period will be 6 weeks from the

date of PO. Performance Bank Guarantee (PBG) of a total of 10% of the value of the

quoted amount in commercial tender is required. This will be retained until the completion

of three years from the date when the installation is completed and warranty begins for

the bidder who is successful in getting the order.

3. The vendor immediately after the award of the work shall prepare a detailed plan of

installation as proposed to be followed by placement of the equipment, etc.

4. The installation should be done by certified and trained engineers for DC followed by

comprehensive user training.

5. If OEM is not the direct bidder in that case OEM has to issue MAF (Manufacturer's

authorization form) to partner along with services guaranty letter to IISc that in case of

partner failing to do installation, OEM would take installation & support responsibility.

6. OEM should provide an undertaking that OEM is responsible for 3 year performance

guarantee.

7. Payment will be made subject to satisfactory and successful installation and acceptance

certificate issued by IISc.

8. If the prices offered are not competitive or are higher than the market prices then we

reserve the right to cancel part or whole of the tender.

9. 3-years on-site comprehensive warranty should be provided. Provide Annual

Maintenance Contract (AMC) Charges for 4th, 5th, 6th & 7th years separately as a

percentage of total cost.

10. Vendor to quote item wise price. IISc may decide to increase/decrease the number of

items at the time of negotiation based on budget availability. IISc may or may not order

the optional items mentioned in the tender.

11. Along with the hard copy of the technical bid a soft copy containing all details in the

hard copy should also be enclosed.

22

9.0 USER ACCEPTANCE TEST CHECK LIST (All the below test results should be demonstrated on live)

Sl. No. Test Item Complied

1 Chiller starting and stabilization time

2 Time required for temperature to reach the optimal value (inside the

rack) when starting for the first time (when water is not previously

chilled)

3 Temperature inside the rack when power fails in the first 15 minutes

4 Rate of temperature rise when power fails during the first 15 minutes

10. CHECK-LIST (If you can provide more information/s or drawings explaining your solutions, please

provide it as separate items and label it with index.)

Sl No. Description Information

1 Chiller make, model number, power consumption,

capacity, maximum time for stabilization of cooling

2 Details of units (heat exchanger) within data center

3 Details of Precision air conditioner within data center

4 Details of monitoring

5 Details of low-side works

6 Details of pump

7 Details of UPS or several UPS to support pump

8 Details of Cold water tank

9 Details of fire alarm

10 Details of Water leakage detection

11. POWER CONSUMPTION CHECK LIST:

Sl

No.

Components Maximum power consumption

per unit

(in kW)

Total Power

(Quantity × Power)

in kW

1 Chiller

2 Internal heat exchanger

units

3 Water circulating pump

4 UPS

23

5 PAC unit

6 Fire detection

7 Rodent protection

8 Water leakage detection

Grand Total(exclude those

which overlap in the power

consumption)

12.0 Submission of Proposal

The proposal should be submitted in two separate covers, one containing technical

specification and the other one the price details. The vendor name, the nature of the

envelope (either technical specifications or commercial/price bid) must be clearly

mentioned on top of each of the envelope. The sealed proposals must be addressed to

SSCU, IISc-Bangalore. The proposals should be submitted to Ms. Bavitha, Room 209,

SSCU, IISc.

Prices should NOT be given anywhere in the technical bid. Mention of prices in technical

bid may result in disqualification. A copy of the Price bid with prices masked but giving all

other details should be enclosed along with the technical bid.

The prices can be quoted either in foreign denominations or in INR. Provide itemized

pricing for each item. Please specify the statutory taxes and duties, if any. Please note

that IISc, being an academic institution with University status is eligible for customs duty

exemption.

Price bid to be given in following format

13.0 PRICE BID TABLE Sl

No. Components Qty Unit Price Total Price

1 Chiller

2 Internal heat exchanger

units

3 Water circulating pump

4 2 x 20Kva UPS

5 PAC unit

6 Fire detection- VESDA &

Smoke alarm

7 Rodent protection

8 Water leakage detection

24

9 Electrical system

10 BMS System

Grand Total (INR,

before tax)

Taxes (state type of tax)

Grand Total (INR)

(including tax)

Grand Total (USD, before

tax)

Taxes (state type of tax)

Grand Total (USD)

(including tax)

INR price to be specified with applicable TAX separately.

Wherever multiple options have been offered mention details for each option.

Vendor to quote item wise price. IISc may decide to increase/decrease node count

at the time of negotiation based on budget availability.

SBI price of dollar on the last date for submitting of tender will be considered for all

calculation regarding price comparison.

14.0 Likely Time-line

Last date for receiving queries

by e-mail

Technical queries may be sent

to [email protected] and

[email protected] with

subject line showing “TUE-

CMS DC: Technical Query”

Commercial queries may also be

sent to the above email address,

with subject line “TUE-CMS

DC: Commercial Query”

:

1st July 2015 10.00 am

25

Site visit to inspect

infrastructure

: 30th June 2015 10.00 am

Pre-bid meeting : 6th July 2015 3.00 pm

Last date for submission of bids : 13th July 2015 12 noon

EMD : Rs. 5 lakhs in favor of IISc, in the form of DD, in the name of

Registrar, Indian Institute of Science

15.0 Bill of Quantities

The following are provided for general guidance. However, if any additional

items and/or quantities are required they should be mentioned in addition to

those listed below and quoted. Any item given below which is not required

may be omitted. The following list may be modified as per the vendor's

requirement.

15.1 - Air cooled Chiller

Sr. No. DESCRIPTION QUANTITY

1.0

Supply, Installation, Testing and Commissioning of Air-cooled chillers

comprising of 2 nos Scroll type compressors, Condenser cooling coils,

condenser fans, Shell and tube Chiller etc,.

Ref. Capacity – Equal to or higher than 40 TR 2

Chilled Water O/I Temp - 7/12 deg.C

Fouling Factor Chiller - 0.000018 MKS Units

Chilled Water Flow : 107 Usgpm

Condenser Air temp = 35.6 OC

2.0

Supply, installation, testing and commissioning of End suction

centrifugal pump for primary chilled water circulation with drive motor,

flexible coupling and vibration isolators as per specification with

following Tech Data:

2

Water Qty : 107 US GPM

Static Head : 80 Feet

Impeller : Bronze

Formatted: Justified

26

Speed : 1500 Rpm

Seal : Mechanical

3.0

Supply, installation, testing and commissioning of End suction

centrifugal pump for Secondary chilled water circulation with drive

motor, flexible coupling and vibration isolators as per specification with

following Tech Data:

2

Water Qty : 75 US GPM

Static Head : 100 Feet

Impeller : Bronze

Speed : 1500 Rpm

Seal : Mechanical

4.0

Supply, installation, testing and commissioning of Chilled water piping

with MS 'C' class pipe complete with all accessories such as bends,

elbows, flanges, nut bolts, air purging valves, de-scaling Tee with MS

Angle & Rod Supporting work etc. of following sizes and insulated with

TF quality thermocole and covered with AL cladding.

80 mm dia 50

65 mm dia 6

50 mm dia 6

40 mm dia 20

5.0

Supply, Installation, Testing and commissioning of Drain piping carried

out of Hard drawn pipes 9mm thick nitrile rubber insulation as per

specification. This includes opening of a hole in the wall and closing of

the hole after the work.

25mm dia 25

20mm dia 25

6.0

Supply, Installation, Testing and commissioning of Insulated Butterfly

valves together with accessories like flanges, fasteners, etc.,with

necessary Nitrile rubber insulation.

80 mm dia 10

7.0

Supply, Installation, Testing and commissioning of Insulated wafer type

Check Valves together with necessary accessories like flanges,

fasteners, with necessary Nitrile rubber insulation.

80 mm dia 4

8.0

Supply, Installation, Testing and commissioning of 2 Way Motorized

Valve with suitable On/Off actuator fitted and necessary Nitrile rubber

insulation.

27

50 mm dia RO

9.0

Supply, Installation, Testing and commissioning of Insulated Y strainer

with drain plugs and suitable supports. The strainer shall be complete

with necessary accessories like flanges, fasteners, etc. with necessary

Nitrile rubber insulation.

80 mm dia 5

50 mm dia brass Y stainers (20 mesh) 5

10.0 Supply, Installation, Testing and commissioning of Drain cock with

necessary Nitrile rubber insulation.

25mm dia 5

11.0

Supply, Installation, Testing and commissioning of insulated automatic

Air Vent complete with pipe nipples, 20 mm NB ball valve, etc. with

necessary Nitrile rubber insulation.

5

12.0

Supply, Installation, Testing and commissioning of Pressure gauge &

thermometer complete with suitable Nipple piece of suitable length to

suit the Insulation Thickness with adapter for pressure gauge.

Pressure Gauge 10

Stem type thermometer 4

13.0

Supply, Installation, Testing and commissioning of Insulated Ball valves

together with accessories like flanges, fasteners, etc., with necessary

Nitrile rubber insulation.

50 mm dia 10

14.0

Floor insulation 13 mm - nitrile rubber stuck with synthetic rubber

adhesive with Joints sealed with 50 mm wide 3 mm thick self adhesive

nitrile rubber tape.

50

15.0

Supply, installation, testing and commissioning of 500 Lts Sintex Tank -

HDPE Expansion tank with 3m height steel structural work with

provision for quick fill and float.

1

16.0

Supply, installation, testing and commissioning of 1000 Lts fabricated

out 6mm thick MS plate for Hot / Cold well Tank and insulated with TF

quality EPS slabs and covered with Aluminium cladding.

1

28

15.2 – Civil Works

Sr.

No. DESCRIPTION QUANTITY UNIT

01 Raised floor with 400mm height , 1500USF , 600mm X 600mm

Tiles 588 Sqft

02 Perforated grills 600mm X 600mm 4 Nos

03 9mm Nitrate Rubber mate pasted on the floor below raised

floor 625 Sq ft

04

Fire rated gyb board partition - The basic stretchers made of

aluminium c angles . Both sides are fitted with twin 6mm fire

rated gyb board . The partition to be from ceiling to floor -

All windows to be closed with the gyb board.

200 Sqft

05 Construction of Chillier bed with brick and cement mortar 120 Sqft

15.3 – Cooling Racks

Sr. No. DESCRIPTION QUANTITY UNIT

01 Server Rack 800 Width X 2000 Height (42U) X 1200Depth 4 Nos

In rack the usable depth is 800mm due to hot and cold zone

within the IP54 sealed block.

Front & Rear door –glass door, complete with swivel handle with

DIN half profile cylinder plug - Balanced Load rating 1500 kg

Each Server and Network Rack should be with 2 nos-24 nos.

IEC C13 and 6nos. IEC C19 -

02 Cooling units should be same size of server racks and installed

side by side. As required Nos

The cooling units should have front blowing fans with deflector . Not less than

30kw units

The capacity of each units shall be not less than 30kw cooling

capacity

In built fire suppressions kit for each of the rack provided.

Temperature, Humidity , Water leakage , auto door opening ckt

shall be built in. The control module should be communicating to

BMS system via MODBUS

15.4 – Security products

15.4.1 Fire Alarm

S.N Description Model Qty Unit

1 Supply & installation 4 Zone Conventional Fire alarm

panel with Battery Back

Notifier/

Ravel 1 Nos

29

2 Supply & Installation of multi Sensor Smoke detector

with Base plate

Notifier /

Ravel 12 Nos

3 Supply & Installation of Strobe with Electronic Hooter Insyin 2 Nos

4 Supply & installation Of Response Indicator Insyin 4 Nos

5 Supply & installation Manual Call point with back box Insyin

2 Nos

6 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 150 Nos

15.4.2 VESDA

S.N. Description Model Qty Unit

1 Supply & installation of Aspiration detector for Server

Room -Xtralis VF250 Xtralis 1 Nos

2 Supply & Installation of Power Supply Unit with Battery

back-up Xtralis 1 Nos

3 Supply & installation of air termination Nozzle & capillary

tubes Xtralis 6 Nos

4 Supply & Installation of 25mm PVC trunk Conduit with

accessories ISI 20 Nos

5 Supply of laying of 2 core 1.5sqmm FRLS Armoured cable ISI 15 Nos

6 Supply & Installation of Electronic hooter ISI 1 Nos

15.4.3 Water leak detection system

S.N Description Model Qty Unit

1 Supply & installation of 2 Zone water leakage panel C System 1 Nos

2 Supply & Installation of sensor cable 20Mtr roll C System 2 Nos

15.4.4 Rodent repellent system

S.N Description Model Quantit

y Unit

1 Supply & installation of Rodent repellent panel C System 1 Nos

2 Supply & Installation of High frequency Transducer C System 12 Nos

3 Supply of laying of 2 core 1.5sqmm FRLS cable ISI 250 Nos

30

15.4.5 BMS system

Sr. No. DESCRIPTION QTY UNIT

01 Modbus based BMS system to connect the following equipments -

With desktop PC 1 Set

02 Chiller - 2Nos , UPS - 4Nos , PAC -1 , Racks cooling unit -1 , Fire

alarm , Three power meter

15.5 – PAC Cooling unit

No. Description Qty Unit

High Precision Air conditioners

1 Supply of Uniflair make PAC units (Bottom Discharge); DX-Air cooled

PACs complete with direct drive motors and Fans with backward

curved blades, Expansion Valve, Scroll Compressors for power

savings, hydrophilic fins for IDU, fan speed controller for ODU,

Water leak detector, Clock card, Sequencing and RS485 card supplied

with the system. EU2/EU4 filters is provided. Unit offered will be

suitable for eco friendly R407 C; Dirty filter alarm, heater, humidifier

are part of the system. PAC will be pre-charged with N2.

4.5TR PAC units as per above specs. Max CFM @ 2905 / unit (PAC

Units without Heater & Humidifier, with Thermostatic expansion

valve and EU2 filters) 2 Nos

2 Low Side Works for High Precision AC Units

Supply & Installation of MS stand suitable for raised floor of 400 mm

clear height. 1 Nos

Leak testing and Refrigerant filling with R 407 C 64 Kg

Power cabling from indoor to outdoor units considering 18RMt per

unit. 18 RMt

Cables for Sequencing of units, 10 RMt per unit 10 RMt

Humidifier line (Consider 10RMT per unit) 10 RMt

Drain line with insulation (Consider 10RMT per unit) 10 RMt

Cu piping interconnecting indoor and outdoor (20RMT per Ckt.) 15 RMt

Insulation of Copper pipe 15 RMt

31

15.6 – UPS for Pump

SL No UPS Specification

01 2 x 20kVA UPS

02 On Line double conversation UPS

03 IGBT Charger & Inverter

04 UPS operation in parallel mode.

05 3 Phase input and single phase output

06 Input 415 V +/- 15%

07 Input voltage harmonic destruction less < 5%

08 Output Voltage 230V 50Hz

09 Efficiency above 92% at full load.

10 Each Battery bank to support 15mins at full 20kVA Load.