Open-House Public Meeng October 5, 2017 | 5 p.m. - 7 p.m. STIP Project No. U-5907 Cornelius and Davidson Mecklenburg County Pos Street Extension to Sloan Street, Muluse Path on Pos Street, and Roundabout at Sloan Street / Griffith Street Public Meeng Purpose This public meeng is part of the N.C. Department of Transportaon’s process to keep you, the public, involved throughout the project development process. The purpose of this public meeng is to gather input on the proposed improvements. Next Steps There is lack of connecvity in the local road system through Davidson. The purpose of the project is to add an alternave route between N.C. 115 and Griffith Street for mulple modes. This project includes three elements: Extension of Pos Street to Sloan Street. Three concepts have been developed (see back). The various opons were considered to minimize impacts to properes and resources. Addion of a 10-foot wide asphalt muluse trail on Pos Street from N.C. 115 (N. Main Street to Griffith Street). Construcon of a roundabout at the intersecon of Sloan Street and Griffith Street. For More Informaon, Please Contact: Sean Epperson, P.E. NCDOT Division 10 Project Team Lead 716 W. Main Street Albemarle, NC 28001 Phone: (704) 983-4400 Email: [email protected] Teresa Gresham, P.E. Kimley-Horn Project Manager 421 Fayeeville Street, Suite 600 Raleigh, NC 27601 Phone: (919) 677-2194 Email: [email protected] Project Descripon Provide comments by October 19, 2017. Comments received will be taken into consideraon as the project develops. Final designs will begin following the public meeng. The Environmental document will be completed in Spring 2018. Right-of-way is ancipated to begin in Fall 2018. Construcon is ancipated to begin in Winter 2019/2020. Potenal Impacts The extension opons are ancipated to result in residenal relocaons (one relocaon for Alternave 1, three relocaons for Alternave 2, two relocaons for Alternave 3). The roundabout is ancipated to require two relocaons. The muluse trail will impact property, but is not expected to relocate residences. Nearby Projects STIP Project U-5873 improves the intersecon of Pos Street and N.C. 115 (N. Main Street). The proposed muluse trail connects Project U-5907 with Project U-5873, creang a connuous pedestrian and bicycle path along Pos Street. Project Descripon (Connued) Connecting people, products and places safely and efficiently, with customer focus, accountability and environmental sensitivity to enhance the economy and vitality of North Carolina.

Open House Public Meeting · 2018. 7. 6. · Open-House Public Meeting October 5, 2017 | 5 p.m. - 7 p.m. STIP Project No. U-5907 Cornelius and Davidson Mecklenburg County Potts Street

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Open-House Public Meeting October 5, 2017 | 5 p.m. - 7 p.m.

    STIP Project No. U-5907 Cornelius and Davidson Mecklenburg County

    Potts Street Extension to Sloan Street, Multiuse Path on Potts Street, and

    Roundabout at Sloan Street / Griffith Street

    Public Meeting Purpose

    This public meeting is part of the N.C. Department of Transportation’s process to keep you, the public, involved throughout the project development process. The purpose of this public meeting is to gather input on the proposed improvements.

    Next Steps

    There is lack of connectivity in the local road system through Davidson.

    The purpose of the project is to add an alternative route between N.C. 115 and Griffith Street for multiple modes.

    This project includes three elements:

    • Extension of Potts Street to Sloan Street. Three concepts have been developed (see back). The various options were considered to minimize impacts to properties and resources.

    • Addition of a 10-foot wide asphalt multiuse trail on Potts Street from N.C. 115 (N. Main Street to Griffith Street).

    • Construction of a roundabout at the intersection of Sloan Street and Griffith Street.

    For More Information, Please Contact:

    Sean Epperson, P.E. NCDOT Division 10 Project Team Lead 716 W. Main Street Albemarle, NC 28001 Phone: (704) 983-4400 Email: [email protected]

    Teresa Gresham, P.E. Kimley-Horn Project Manager

    421 Fayetteville Street, Suite 600 Raleigh, NC 27601

    Phone: (919) 677-2194 Email: [email protected]

    Project Description

    Provide comments by October 19, 2017. Comments received will be taken into consideration as the project develops.

    Final designs will begin following the public meeting. The Environmental document will be completed in Spring 2018. Right-of-way is anticipated to begin in Fall 2018. Construction is anticipated to begin in Winter 2019/2020.

    Potential Impacts

    The extension options are anticipated to result in residential relocations (one relocation for Alternative 1, three relocations for Alternative 2, two relocations for Alternative 3). The roundabout is anticipated to require two relocations. The multiuse trail will impact property, but is not expected to relocate residences.

    Nearby Projects

    STIP Project U-5873 improves the intersection of Potts Street and N.C. 115 (N. Main Street). The proposed multiuse trail connects Project U-5907 with Project U-5873, creating a continuous pedestrian and bicycle path along Potts Street.

    Project Description (Continued)

    Connecting people, products and places safely and efficiently, with customer focus,

    accountability and environmental sensitivity to enhance the economy and vitality of North Carolina.

    mailto:[email protected]:[email protected]

  • Potts Street Extension — Alternative 1

    Potts Street Extension — Alternative 2

    Potts Street Extension — Alternative 3

  • COMMENT SHEET NAME:

    ADDRESS:

    E-MAIL:

    Do you have a preferred alternative?

    Do you have any other comments or questions on the proposed design?

    Please submit comments by October 19th to:

    Teresa Gresham, P.E. Kimley-Horn

    421 Fayetteville Street, Suite 600 Raleigh, NC 27601

    Open-House Public Meeting October 5, 2017 | 5 p.m. - 7 p.m.

    STIP Project No. U-5907

    Cornelius and Davidson

    Mecklenburg County

    Potts Street Extension to Sloan Street,

    Multiuse Path on Potts Street, and Roundabout at Sloan Street / Griffith Street