75
Introduction Background Unreliable grid Off-grid Conclusions On Using Storage and Genset for Mitigating Power Grid Failures Sahil Singla ISS4E lab University of Waterloo Collaborators: S. Keshav, Y. Ghiassi-Farrokhfal 1 / 27

On Using Storage and Genset for Mitigating Power Grid Failures

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

On Using Storage and Genset forMitigating Power Grid Failures

Sahil SinglaISS4E lab

University of Waterloo

Collaborators: S. Keshav, Y. Ghiassi-Farrokhfal

1 / 27

Page 2: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

1 / 27

Page 3: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

1 / 27

Page 4: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Power outages

• Developing countries:* Large demand-supply gap* Two-to-four hours daily outage

is common1

• Developed countries:* Storms, lightning strikes,

equipment failures* Eg. Sandy

1Tongia et al., India Power Supply Position 2010. Centre for Study ofScience, Technology, and Policy CSTEP, Aug 2010

2 / 27

Page 5: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Power outages

• Developing countries:* Large demand-supply gap* Two-to-four hours daily outage

is common1

• Developed countries:* Storms, lightning strikes,

equipment failures* Eg. Sandy

1Tongia et al., India Power Supply Position 2010. Centre for Study ofScience, Technology, and Policy CSTEP, Aug 2010

2 / 27

Page 6: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Diesel generator

• A residential neighbourhood augments grid power

• Usually from a diesel generator (genset)

• High carbon footprint!

3 / 27

Page 7: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Diesel generator

• A residential neighbourhood augments grid power

• Usually from a diesel generator (genset)

• High carbon footprint!

3 / 27

Page 8: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Storage battery

• What if the battery goes empty during an outage?• Storage is expensive!

4 / 27

Page 9: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Storage battery

• What if the battery goes empty during an outage?

• Storage is expensive!

4 / 27

Page 10: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Storage battery

• What if the battery goes empty during an outage?• Storage is expensive!

4 / 27

Page 11: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery-genset hybrid system

• Use battery to meet demand

• If battery goes empty, turn on genset

• Both benefits

5 / 27

Page 12: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Goals

We wish to study:

(a) Minimum battery size to eliminate the use of genset

(b) Trade-off between battery size and carbon footprint

(c) Scheduling power between battery and genset

6 / 27

Page 13: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Goals

We wish to study:

(a) Minimum battery size to eliminate the use of genset

(b) Trade-off between battery size and carbon footprint

(c) Scheduling power between battery and genset

6 / 27

Page 14: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Goals

We wish to study:

(a) Minimum battery size to eliminate the use of genset

(b) Trade-off between battery size and carbon footprint

(c) Scheduling power between battery and genset

6 / 27

Page 15: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

6 / 27

Page 16: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Factors

0 2 4 6 8 10 12

2

4

6

8

10x 10

5

Power outage duration in hours

Battery

level in

Wh

Figure: Battery trajectories

• Battery size

• Charging rate

• Demand duringoutage

• Outage duration

• Inter-outageduration

7 / 27

Page 17: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Factors

0 2 4 6 8 10 12

2

4

6

8

10x 10

5

Power outage duration in hours

Battery

level in

Wh

Figure: Battery trajectories

• Battery size

• Charging rate

• Demand duringoutage

• Outage duration

• Inter-outageduration

7 / 27

Page 18: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Related Work

• Mostly empirical* Both sizing and scheduling

• Analytical work usually assumes stationarity of demand

• No analytical work on battery sizing vs carbon trade-off

• Wang et al.2 do battery sizing for renewables – do notmodel grid unreliability

2Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

8 / 27

Page 19: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Related Work

• Mostly empirical* Both sizing and scheduling

• Analytical work usually assumes stationarity of demand

• No analytical work on battery sizing vs carbon trade-off

• Wang et al.2 do battery sizing for renewables – do notmodel grid unreliability

2Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

8 / 27

Page 20: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Related Work

• Mostly empirical* Both sizing and scheduling

• Analytical work usually assumes stationarity of demand

• No analytical work on battery sizing vs carbon trade-off

• Wang et al.2 do battery sizing for renewables – do notmodel grid unreliability

2Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

8 / 27

Page 21: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Related Work

• Mostly empirical* Both sizing and scheduling

• Analytical work usually assumes stationarity of demand

• No analytical work on battery sizing vs carbon trade-off

• Wang et al.2 do battery sizing for renewables – do notmodel grid unreliability

2Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

8 / 27

Page 22: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Notation

• Discrete time model

• a(t) is arrival in time slot t

• A(s, t) is arrival in time s to t

Name DescriptionB Battery storage capacityC Battery charging rate

x(t) Grid availability 0 or 1d(t) Power demandb(t) Battery state of chargebd(t) Battery deficit charge = B − b(t)l(t) Amount of loss of power

9 / 27

Page 23: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Notation

• Discrete time model

• a(t) is arrival in time slot t

• A(s, t) is arrival in time s to t

Name DescriptionB Battery storage capacityC Battery charging rate

x(t) Grid availability 0 or 1d(t) Power demandb(t) Battery state of chargebd(t) Battery deficit charge = B − b(t)l(t) Amount of loss of power

9 / 27

Page 24: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Notation

• Discrete time model

• a(t) is arrival in time slot t

• A(s, t) is arrival in time s to t

Name DescriptionB Battery storage capacityC Battery charging rate

x(t) Grid availability 0 or 1d(t) Power demandb(t) Battery state of chargebd(t) Battery deficit charge = B − b(t)l(t) Amount of loss of power

9 / 27

Page 25: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Background

• Analogy between loss of packet and loss of power3

B

Buffa(t) C

B

b(t)C d(t)

Pr{b(t) ≤ 0} = Pr{bd(t) ≥ B}= Pr{Buffer ≥ B} = Pr{l(t) > 0}

3Ardakanian et al., On the use of teletraffic theory in power distributionsystems. In Proceedings of e-Energy

10 / 27

Page 26: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Background

• Analogy between loss of packet and loss of power3

B

Buffa(t) C

B

b(t)C d(t)

Pr{b(t) ≤ 0} = Pr{bd(t) ≥ B}= Pr{Buffer ≥ B} = Pr{l(t) > 0}

3Ardakanian et al., On the use of teletraffic theory in power distributionsystems. In Proceedings of e-Energy

10 / 27

Page 27: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic demand

Choices for demand model:

• Constant average demand E [d(t)]

• Markov model* Most results assume stationarity

• Network calculus* Worst case analysis

• Stochastic network calculus

11 / 27

Page 28: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic demand

Choices for demand model:

• Constant average demand E [d(t)]• Markov model

* Most results assume stationarity

• Network calculus* Worst case analysis

• Stochastic network calculus

11 / 27

Page 29: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic demand

Choices for demand model:

• Constant average demand E [d(t)]• Markov model

* Most results assume stationarity

• Network calculus* Worst case analysis

• Stochastic network calculus

11 / 27

Page 30: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic Network Calculus

• Example: Design a door* Model human heights

Pr{height ≤ 6ft} = p0Pr{height > 6ft + σ} ≤ (1− p0)e−λσ = εg(σ)

• Interested in modeling cumulative demand* Statistical sample path envelope

Pr

{sups≤t{A(s, t)− G(t − s)} > σ

}≤ εg(σ)

12 / 27

Page 31: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic Network Calculus

• Example: Design a door* Model human heights

Pr{height ≤ 6ft} = p0

Pr{height > 6ft + σ} ≤ (1− p0)e−λσ = εg(σ)

• Interested in modeling cumulative demand* Statistical sample path envelope

Pr

{sups≤t{A(s, t)− G(t − s)} > σ

}≤ εg(σ)

12 / 27

Page 32: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic Network Calculus

• Example: Design a door* Model human heights

Pr{height ≤ 6ft} = p0Pr{height > 6ft + σ} ≤ (1− p0)e−λσ = εg(σ)

• Interested in modeling cumulative demand* Statistical sample path envelope

Pr

{sups≤t{A(s, t)− G(t − s)} > σ

}≤ εg(σ)

12 / 27

Page 33: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic Network Calculus

• Example: Design a door* Model human heights

Pr{height ≤ 6ft} = p0Pr{height > 6ft + σ} ≤ (1− p0)e−λσ = εg(σ)

• Interested in modeling cumulative demand

* Statistical sample path envelope

Pr

{sups≤t{A(s, t)− G(t − s)} > σ

}≤ εg(σ)

12 / 27

Page 34: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Stochastic Network Calculus

• Example: Design a door* Model human heights

Pr{height ≤ 6ft} = p0Pr{height > 6ft + σ} ≤ (1− p0)e−λσ = εg(σ)

• Interested in modeling cumulative demand* Statistical sample path envelope

Pr

{sups≤t{A(s, t)− G(t − s)} > σ

}≤ εg(σ)

12 / 27

Page 35: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

12 / 27

Page 36: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Modeling

• Transformation and effective demand

de(t) = [d(t) + C](1− x(t))= [d(t) + C]xc(t)

13 / 27

Page 37: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Modeling

• Transformation and effective demand

de(t) = [d(t) + C](1− x(t))= [d(t) + C]xc(t)

13 / 27

Page 38: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in absence of genset

Using an amendment of Wang et al.4

Pr{l(t) > 0} ≤ min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))

• Goal is to size battery such that probability of loss of poweris at most ε∗, thus

min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))≤ ε∗

=⇒ B ≥

(supτ≥0

(G(τ)− Cτ) + εg−1 (ε∗)

)I(Pr{xc(t)=1}>ε∗)

4Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

14 / 27

Page 39: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in absence of genset

Using an amendment of Wang et al.4

Pr{l(t) > 0} ≤ min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))

• Goal is to size battery such that probability of loss of poweris at most ε∗,

thus

min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))≤ ε∗

=⇒ B ≥

(supτ≥0

(G(τ)− Cτ) + εg−1 (ε∗)

)I(Pr{xc(t)=1}>ε∗)

4Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

14 / 27

Page 40: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in absence of genset

Using an amendment of Wang et al.4

Pr{l(t) > 0} ≤ min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))

• Goal is to size battery such that probability of loss of poweris at most ε∗, thus

min

(Pr{xc(t) > 0}, εg

(B − sup

τ≥0(G(τ)− Cτ)

))≤ ε∗

=⇒ B ≥

(supτ≥0

(G(τ)− Cτ) + εg−1 (ε∗)

)I(Pr{xc(t)=1}>ε∗)

4Wang et al., A Stochastic Power Network Calculus for IntegratingRenewable Energy Sources into the Power Grid. IEEE JSAC

14 / 27

Page 41: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in presence of genset

• Reduce carbon footprint

• For large gensets

carbon emission ∼∑

t

l(t)

• Scheduling becomes trivial (we’ll come back later)

15 / 27

Page 42: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in presence of genset (contd.)

• Goal is to estimate expected total loss (carbon emission)

• Under some assumptions:

E

[T∑

t=1

l(t)

]≈ min

( T∑t=1

E[d(t)xc(t)

],

Pr{max([De(s, t)− C(t − s)− B]+

)> 0}.

T∑t=1

E [d(t)])

16 / 27

Page 43: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Sizing in presence of genset (contd.)

• Goal is to estimate expected total loss (carbon emission)

• Under some assumptions:

E

[T∑

t=1

l(t)

]≈ min

( T∑t=1

E[d(t)xc(t)

],

Pr{max([De(s, t)− C(t − s)− B]+

)> 0}.

T∑t=1

E [d(t)])

16 / 27

Page 44: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Data set

• 4500 Irish homes

• Randomly selected 100 homes

• Two-state on-off Markov model for outage

ON OFF

λ

µ

17 / 27

Page 45: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Data Fitting

Use data set to compute ‘best’ parameters:

• Envelope G = σ + ρt

• Exponential distribution to model εg fails

• Weibull distribution to model εg

• Hyper-exponential distribution to model εg

18 / 27

Page 46: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Data Fitting

Use data set to compute ‘best’ parameters:

• Envelope G = σ + ρt

• Exponential distribution to model εg fails

• Weibull distribution to model εg

• Hyper-exponential distribution to model εg

18 / 27

Page 47: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Data Fitting

Use data set to compute ‘best’ parameters:

• Envelope G = σ + ρt

• Exponential distribution to model εg fails

• Weibull distribution to model εg

• Hyper-exponential distribution to model εg

18 / 27

Page 48: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Data Fitting

Use data set to compute ‘best’ parameters:

• Envelope G = σ + ρt

• Exponential distribution to model εg fails

• Weibull distribution to model εg

• Hyper-exponential distribution to model εg

18 / 27

Page 49: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Results (absence of genset)

−4 −3.5 −3 −2.5 −20

1

2

3

4

5

6

7

8x 10

5

Logarithm of target power loss probability log10

ε∗

Battery

siz

e B

∗ in W

h

Dataset quantile

Ideal De model

Weibull dist.

Hyper−exp dist.

ε∗ =

2.7

*10

−4

19 / 27

Page 50: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Results (presence of genset)

0 1 2 3 4 5

x 105

2

4

6

8

10

12x 10

5

Battery size in Wh

Avera

ge c

arb

on e

mis

sio

n in a

week in W

h

Our bound

Ideal De model

Dataset quantile

Battery−less bound

III (B

>C

)

II (

B<

C)

I (B

=0)

20 / 27

Page 51: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

20 / 27

Page 52: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Motivation

• Off-grid industry using genset: how to improve efficiency?

• For small gensets, rate of fuel consumption

k1G + k2d(t)

• Storage battery can help!

21 / 27

Page 53: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Motivation

• Off-grid industry using genset: how to improve efficiency?

• For small gensets, rate of fuel consumption

k1G + k2d(t)

• Storage battery can help!

21 / 27

Page 54: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Motivation

• Off-grid industry using genset: how to improve efficiency?

• For small gensets, rate of fuel consumption

k1G + k2d(t)

• Storage battery can help!

21 / 27

Page 55: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Problems

(a) Given a genset size, how to size battery and schedulepower?

(b) How to jointly size battery and genset?

We talk only about the former in this presentation

22 / 27

Page 56: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Problems

(a) Given a genset size, how to size battery and schedulepower?

(b) How to jointly size battery and genset?

We talk only about the former in this presentation

22 / 27

Page 57: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery usage

Theorem: Problem same as minimizing genset operation time

• Offline optimal given by a mixed IP

• General offline problem NP-hard

• Online Alternate scheduling

• Competitive ratiok1

GC + k2

k1 + k2

23 / 27

Page 58: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery usage

Theorem: Problem same as minimizing genset operation time

• Offline optimal given by a mixed IP

• General offline problem NP-hard

• Online Alternate scheduling

• Competitive ratiok1

GC + k2

k1 + k2

23 / 27

Page 59: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery usage

Theorem: Problem same as minimizing genset operation time

• Offline optimal given by a mixed IP

• General offline problem NP-hard

• Online Alternate scheduling

• Competitive ratiok1

GC + k2

k1 + k2

23 / 27

Page 60: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery usage

Theorem: Problem same as minimizing genset operation time

• Offline optimal given by a mixed IP

• General offline problem NP-hard

• Online Alternate scheduling

• Competitive ratiok1

GC + k2

k1 + k2

23 / 27

Page 61: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Battery usage

Theorem: Problem same as minimizing genset operation time

• Offline optimal given by a mixed IP

• General offline problem NP-hard

• Online Alternate scheduling

• Competitive ratiok1

GC + k2

k1 + k2

23 / 27

Page 62: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Savings

• Before:

k1GT + k2

T∑t=1

d(t)

• After (under some assumptions):

k1GT1C

1C + 1

E [d(t)]

+ k2

T∑t=1

d(t)

Beyond a small value, independent of battery size!

24 / 27

Page 63: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Savings

• Before:

k1GT + k2

T∑t=1

d(t)

• After (under some assumptions):

k1GT1C

1C + 1

E [d(t)]

+ k2

T∑t=1

d(t)

Beyond a small value, independent of battery size!

24 / 27

Page 64: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Savings

• Before:

k1GT + k2

T∑t=1

d(t)

• After (under some assumptions):

k1GT1C

1C + 1

E [d(t)]

+ k2

T∑t=1

d(t)

Beyond a small value, independent of battery size!

24 / 27

Page 65: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Result

25 / 27

Page 66: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Outline

Introduction

Background

Unreliable grid

Off-grid

Conclusions

25 / 27

Page 67: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Summary

• Power grid unreliable or absent* Genset has high carbon footprint

• Storage battery expensive* Reduce the size

• Minimum battery size required to avoid genset

• Trade-off between battery size and genset carbon footprint

• Power scheduling to improve genset efficiency

26 / 27

Page 68: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Summary

• Power grid unreliable or absent* Genset has high carbon footprint

• Storage battery expensive* Reduce the size

• Minimum battery size required to avoid genset

• Trade-off between battery size and genset carbon footprint

• Power scheduling to improve genset efficiency

26 / 27

Page 69: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Summary

• Power grid unreliable or absent* Genset has high carbon footprint

• Storage battery expensive* Reduce the size

• Minimum battery size required to avoid genset

• Trade-off between battery size and genset carbon footprint

• Power scheduling to improve genset efficiency

26 / 27

Page 70: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Summary

• Power grid unreliable or absent* Genset has high carbon footprint

• Storage battery expensive* Reduce the size

• Minimum battery size required to avoid genset

• Trade-off between battery size and genset carbon footprint

• Power scheduling to improve genset efficiency

26 / 27

Page 71: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Summary

• Power grid unreliable or absent* Genset has high carbon footprint

• Storage battery expensive* Reduce the size

• Minimum battery size required to avoid genset

• Trade-off between battery size and genset carbon footprint

• Power scheduling to improve genset efficiency

26 / 27

Page 72: On Using Storage and Genset for Mitigating Power Grid Failures

Introduction Background Unreliable grid Off-grid Conclusions

Limitations & Future Work

• Past predicts future

• Battery model: size and charging rate independent

• Lack of data from developing countries

• Technical assumptions

27 / 27

Page 73: On Using Storage and Genset for Mitigating Power Grid Failures

Appendix

27 / 27

Page 74: On Using Storage and Genset for Mitigating Power Grid Failures

Results (absence of genset)

−4 −3.5 −3 −2.5 −20

0.5

1

1.5

2

2.5x 10

6

Logarithm of target power loss probability log10

ε∗

Battery

siz

e B

∗ in W

h

Dataset quantile

MSM bound

Kesidis bound

Hyper−exp dist.

ε∗ =

2.7

*10

−4

27 / 27

Page 75: On Using Storage and Genset for Mitigating Power Grid Failures

Three modes

Three modes of battery-genset hybrid system operation:

1. Demand met by battery only2. Demand met by genset only3. Demand simultaneously met by battery and genset

27 / 27