    12-508-97 Production and Operations Management

    MRP-ERP-OM

  • 7/30/2019 OM_MRP-ERP

    2/41

    22-508-97 Production and Operations Management

    INVENTORY

    Idle stock reqd for Production

    Carefully manged to reduce the cost

    EOQ MODEL

    BOM

    FAST/SLOW MOVING ITEM

    OBSOLETE ITEMS

    USE OF I T

  • 7/30/2019 OM_MRP-ERP

    3/41

    32-508-97 Production and Operations Management

    From Aggregate to Master Planning

    Aggregate Production Plan

    Capacity ?

    Master Production Schedule

    Feasibility approved?

    Material Requirement Planning

    Yes

    Yes

    No

    No

    Can we produce 10,000

    equivalent units (total for

    products A, B and C) per month

    for the next year?

    Can we produce 500

    units of A, 600 of B and400 of C per week for the

    next month ?

  • 7/30/2019 OM_MRP-ERP

    4/41

    42-508-97 Production and Operations Management

    Production Plan VS

    Master Production Schedule

    Mid term production planning

    Order promising

    SKU level(stock keeping unit)

    About 3 months

    1 week

    Long term capacity

    decisions

    Product families

    (Equiv. Units)

    12 to 15 months

    1 month

    ProductionPlan

    Objective

    Product

    Horizon

    Timebuckets

    Master ProductionSchedule

  • 7/30/2019 OM_MRP-ERP

    5/41

    52-508-97 Production and Operations Management

    The Aggregate Plan and the Master

    Production Schedule

  • 7/30/2019 OM_MRP-ERP

    6/41

    62-508-97 Production and Operations Management

    When to Order ?Three approaches

    Reorder Point (continuous review system)Constant amount ordered when inventory declines to

    predetermined level

    Periodic Review System(fixed time review period)Order placed for variable amount after fixed passage of time

    Time Phased Order PointMaster Production Schedule

    Material Requirements Planning

    Distribution Requirements Planning

    RE

    ACTIVE

    SYSTEMS

    PROACTIVE

    SYSTEMS

  • 7/30/2019 OM_MRP-ERP

    7/4172-508-97 Production and Operations Management

    Objectives of the Master Production Schedule

    Establish and meet delivery dates

    Determine launch dates for orders

    Optimize the use of available capacity

    Meet the objectives of the aggregate plan

    Make trade-off decisions between production and

    marketing

    Sales

    Purch.

    Operations

    Operations

    Systemic

    Approach

  • 7/30/2019 OM_MRP-ERP

    8/4182-508-97 Production and Operations Management

    Master Production Plan : Inputs

    Inputs to the MPS are :

    Beginning Inventory

    Forecasts for each week of the schedule

    Customer orders (quantities already committed to

    customers)

    Total available capacity for each week of the schedule

  • 7/30/2019 OM_MRP-ERP

    9/4192-508-97 Production and Operations Management

    Developing a MPS

    Identification of individual products.

    Development of an MPS grid for each product in

    real units according to the available data (forecast,

    committed orders, inventory levels, lot sizes, lead

    times) and the specified constraints.

    Rough cut capacity planning in equivalent units (for

    all products).

    Does the plans meet all constraints? (capacitylimits, stock levels, etc.)

  • 7/30/2019 OM_MRP-ERP

    10/41102-508-97 Production and Operations Management

    Developing a MPS

    Forecast of the demand for the products with independent demand

    Firm orders received from the customers for period i.

    Projected on-hand Inventory (i)= Projected on-hand inv. (i - 1)

    + Planned production (i)

    - Max (Forecast (i) ,

    Customer orders (i) )

    Lot size 100 unitsLead time: 1 period

    Periods 1 2 3

    75 85 80

    80 60 55

    Proj. on-hand Inv. 200 120 35 55

    100

    100MPS - Order Release

    ForecastCustomer Orders

    MPS - Order Receipt

  • 7/30/2019 OM_MRP-ERP

    11/41112-508-97 Production and Operations Management

    Period 1 2 3 4

    Forecast250 250 250 250

    Customer

    Orders 230 280 180 150

    Projectedinventory 160 80 30 180

    Planned

    receipts 0 200 200 400

    Plannedreleases 200 200 400

    Product Lot Size LeadTime BeginningInventory

    X12DE 200 1 410

    1) Forecast for products with an independant

    demand2) Committed customer orders

    2a) Identify the Max between forecast and

    customer orders

    3) Planned order receipts for each period:

    4) Projected on-hand inventory (i) = beginning inventory (i - 1)

    + planned order receipts (i) - Max (forecast (i) , customer

    orders (i) )

    5) Planned order releases

    shifted back the

    length of the lead

    time

    Developing a MPS

  • 7/30/2019 OM_MRP-ERP

    12/41122-508-97 Production and Operations Management

    Periods 1 2 3 4 5 6 7 8 9 10

    50 45 45 50 50 50 40 40 40 50

    25 60 15 55 25 35

    Projected on-hand inv 100

    Forecast

    Customer Orders

    Planned Order Receipts

    Planned Order Releases

    Product A

    Preliminary Plan :

    Complete the following MPS

    Product A

    Beginning Inventory = 100 Lot Size: 100 units

    Lead Time: 1 week

    1 equivalent unit

  • 7/30/2019 OM_MRP-ERP

    13/41132-508-97 Production and Operations Management

    Periods 1 2 3 4 5 6 7 8 9 10

    60 120 80 40 30 50 20 20 20 30

    35 150 60 30 25 35

    Proj. on-hand inv. 300

    Forecast

    Customer Orders

    Planned Order Receipts

    Planned Order Releases

    Product B

    Product B

    Beginning Inv. = 300 Lot Size : 100 units

    Lead Time: 1 week

    2 equivalent units

    Preliminary Plan :

    Complete the following MPS

  • 7/30/2019 OM_MRP-ERP

    14/41142-508-97 Production and Operations Management

    Rough Cut Capacity Planning

    Approximate calculation of the capacity required at critical

    work centers to meet the demand in order to check the

    feasibility of a Master Production Schedule.

    When the capacity required exceeds the capacity

    available the MPS must be adjusted before proceeding to

    the MRP.

    Fi l MPS

  • 7/30/2019 OM_MRP-ERP

    15/41152-508-97 Production and Operations Management

    100 0 100 0 100 0 0 100 0 0

    0 0 200 0 200 0 0 0 0 0

    100 0 300 0 300 0 0 100 0 0

    Prod A - Planned Order Releases

    Prod B - Planned Order Releases

    Total

    Products A and B

    Total capacity is 200 equivalent units per period. Establish

    the final MPS for each product.

    Because the total planned order releases of products A and Bis superior to 200 units in periods 3 and 5, we must move the

    release ofone of the two articles to periods 2 and 4.

    We decide, for example, to move the release of product A toperiods 2 and 4.

    We must then complete the final plan for both products.

    Final MPS :

    Rough Cut Capacity Planning

    Fi l MPS

  • 7/30/2019 OM_MRP-ERP

    16/41162-508-97 Production and Operations Management

    Periods 1 2 3 4 5 6 7 8 9 10

    50 45 45 50 50 50 40 40 40 50

    25 60 15 55 25 35

    Proj. on-hand inv. 100 0 100 0 0 100 0

    100 0 0 100 0 0

    Forecast

    Customer Orders

    Planned Order Receipts

    Planned Order Releases

    Product A

    Planned Order Release is moved from period 3 to period 2.

    Consequently, Planned Order Receipts are moved from period4 to period 3.

    Projected on-hand inventories must be recalculated to accountfor the changes.

    50 90 145 90 140 90 50 10 70 20

    1000

    10001000

    1000

    Final MPS :

    Modifications to the Preliminary Plan

    Final MPS

  • 7/30/2019 OM_MRP-ERP

    17/41172-508-97 Production and Operations Management

    Periods 1 2 3 4 5 6 7 8 9 10

    60 120 80 40 30 50 20 20 20 30

    35 150 60 30 25 35

    Proj. on-hand inv. 300 240 90 10 70 40 90 70 50 30 00 0 0 100 0 0 100 0 0 0

    0 0 100 0 0 100 0 0 0 0

    Forecast

    Customer Orders

    Planned Order Receipts

    Planned Order Releases

    Product B

    Since weve made no changes to the planned order releases ofprodcut B, le preliminary and final plans are identical.

    Final MPS :

    Modifications to the Preliminary Plan

  • 7/30/2019 OM_MRP-ERP

    18/41

  • 7/30/2019 OM_MRP-ERP

    19/41192-508-97 Production and Operations Management

    On-hand

    inventory

    Inventory of tables

    Time

    Quantity

    Demand for the tables

    Time

    Reorder Point System VS MRP

  • 7/30/2019 OM_MRP-ERP

    20/41202-508-97 Production and Operations Management

    Reorder Point System VS MRP

    Quantity

    Inventory of the table legs

    Quantity

    Demand for the table legs

  • 7/30/2019 OM_MRP-ERP

    21/41212-508-97 Production and Operations Management

    Objectives of MRP

    Calculate with precision the quantities of components,

    parts and raw material that must be produced or

    purchased in order to realize the MPS

    HOW MANY ?

    To determine when to release production or to place

    the orders in order to receive the required units at the

    right moment WHEN ?

    M t i l R i t Pl i

  • 7/30/2019 OM_MRP-ERP

    22/41222-508-97 Production and Operations Management

    Material Requirements Planning :

    Information Structure

    - Stocks on hand- Safety stocks

    - Lot sizes

    - Economic Order Quantities

    - Lead time

    Item Master

    File

    ForecastsCustomer

    Orders

    Bill of

    MaterialMRP

    MPS

    Aggregate

    Planning

  • 7/30/2019 OM_MRP-ERP

    23/41232-508-97 Production and Operations Management

    Bill of Materials (BOM)

    X

    Y (3) Z (2)

    Y (1)W (2)

    Level 0

    Level 1

    Level 2

    For each product X we need 3 Y and 2 ZFor each product Z we need 2 W and 1 Y

    Product Structure Tree

    Parent

    ParentComponent

    Component

  • 7/30/2019 OM_MRP-ERP

    24/41242-508-97 Production and Operations Management

    ProblemsS&H (2007) p.515 #3 - S&H (2004) p.628 #3

    Item Lead Time Amount on

    Hand

    Direct

    Components

    End 1 0 L(2), C(1), K(3)

    L 2 10 B(2), J(3)

    C 3 15 G(2), B(2)

    K 3 20 H(4), B(2)

    B 2 30

    J 3 30

    G 3 5

    H 2 0

  • 7/30/2019 OM_MRP-ERP

    25/41252-508-97 Production and Operations Management

    MRP Matrix

    Note: The book from Stevenson shows the projected inventory at the

    beginning of the period, this is not the usual way to do it, so we will

    always show the projected inventory at the END of the period

  • 7/30/2019 OM_MRP-ERP

    26/41262-508-97 Production and Operations Management

    MRP calculation process

    Always process the items in the order of their low level

    code: level 0 level 1 level 2

    When an item appears at different levels of the product

    structure(s), the lowest level (highest number) is the level

    that we must use.

    Gross requirements for an item are calculated by:

    Multiplying the quantity of the planned order

    release(s) of the parent(s) of the item by thequantity required as per the BOM for the

    specific parent-component relationship(s).

  • 7/30/2019 OM_MRP-ERP

    27/41

    272-508-97 Production and Operations Management

    Lot Sizing in MRP Systems

    Lot-for-lot (L4L) ordering policy

    Minimum order quantity (Ex: Min 250)

    Multiple order quantity (Ex: X100)

    Economic order quantity (Ex: 350; annual demand: 4 200)

    Periodic order quantity (Ex: 2 months)

  • 7/30/2019 OM_MRP-ERP

    28/41

    282-508-97 Production and Operations Management

    Example

    A company is manufacturing several office supply items

    among which we have:Clipboard

    Lapdesk

    etc.

  • 7/30/2019 OM_MRP-ERP

    29/41

    292-508-97 Production and Operations Management

    Product Structure

    Top clip (1) Bottom clip (1)

    Pivot (1) Spring (1)

    Rivets (2)

    Finished clipboard Pressboard (1)

    Clipboard

  • 7/30/2019 OM_MRP-ERP

    30/41

    302-508-97 Production and Operations Management

    Product Structure Tree

    Clipboard Level 0

    Level 1

    Level 2Spring

    (1)Bottom Clip

    (1)Top Clip

    (1)Pivot

    (1)

    Rivets(2)

    Clip Assy(1)

    Pressboard(1)

  • 7/30/2019 OM_MRP-ERP

    31/41

    312-508-97 Production and Operations Management

    MRP: Example (cont.)

    Product Structure Record

    Clipboard

    Lapdesk

    Pressboard(2)

    Trim(3)

    Beanbag(1)

    Glue(4 oz)

    Level 0

    Level 0

    Pressboard(1)

    Clip Assy(1)

    Rivets(2) Level 1

    Level 1

  • 7/30/2019 OM_MRP-ERP

    32/41

    322-508-97 Production and Operations Management

    ITEM: PRESSBOARD LLC: 1 PERIOD

    LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

    Gross Requirements

    Scheduled Receipts

    Projected on Hand 150

    Net Requirements

    Planned Order Receipts

    Planned Order Releases

    ITEM: CLIPBOARD LLC: 0 PERIOD

    LOT SIZE: L4L LT: 1 1 2 3 4 5

    Planned Order Releases 100 100 100

    ITEM: LAPDESK LLC: 0 PERIOD

    LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

    Planned Order Releases 50 50

    MRP: Example (cont.)

    M.P.S.

    M.R

    .P.

  • 7/30/2019 OM_MRP-ERP

    33/41

    332-508-97 Production and Operations Management

    M.P.S.

    M.R

    .P.

    ITEM: PRESSBOARD LLC: 1 PERIOD

    LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

    Gross Requirements 100 100 200 100 0

    Scheduled Receipts

    Projected on Hand 150

    Net Requirements

    Planned Order Receipts

    Planned Order Releases

    ITEM: CLIPBOARD LLC: 0 PERIOD

    LOT SIZE: L4L LT: 1 1 2 3 4 5

    Planned Order Releases 100 100 100

    ITEM: LAPDESK LLC: 0 PERIOD

    LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

    Planned Order Releases 50 50

    x2 x2

    x1 x1x1

    MRP: Example (cont.)

  • 7/30/2019 OM_MRP-ERP

    34/41

    342-508-97 Production and Operations Management

    M.P.S.

    M.R

    .P.

    ITEM: PRESSBOARD LLC: 1 PERIOD

    LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

    Gross Requirements 100 100 200 100 0

    Scheduled Receipts

    Projected on Hand 150 50 50 0 0 0Net Requirements 50 150 100

    Planned Order Receipts 100 150 100

    Planned Order Releases 100 150 100

    ITEM: CLIPBOARD LLC: 0 PERIOD

    LOT SIZE: L4L LT: 1 1 2 3 4 5

    Planned Order Releases 100 100 100

    ITEM: LAPDESK LLC: 0 PERIOD

    LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

    Planned Order Releases 50 50

    MRP: Example (cont.)

    MRP E l ( t )

  • 7/30/2019 OM_MRP-ERP

    35/41

    352-508-97 Production and Operations Management

    Planned Order Report

    PERIOD

    ITEM 1 2 3 4 5

    Clipboard 100 100 100

    Lapdesk 50 50

    Pressboard 100 150 100

    MRP: Example (cont.)

    Item Lot size LT

    Prod ct A 200 1

    Product A

  • 7/30/2019 OM_MRP-ERP

    36/41

    Product A 200 1

    MPS 1 2 3 4 5 6

    25 25 25 25 25 25

    30 20 15 10 5

    Projected inventory 135 105 80 55 30 5 180

    200

    Order releases 200

    Item Lot size LT

    Product Z 500 2

    MPS 1 2 3 4 5 630 30 30 30 30 30

    35 20 15 20 10 5

    Projected inventory 135 100 70 40 10 480 450

    500

    Order releases 500

    Item Lot size LT

    Sub-ass. B 1 500 2

    MRP 1 2 3 4 5 6

    Gross Requirements Prod. A 0 0 0 0 400 0

    Gross Requirements Prod. Z 0 0 1 500 0 0 0

    0 0 1 500 0 400 0

    Projected inventory 200 200 200 200 200 1 300 1 300

    1 300 200

    1 500 1 500

    Planned Order Releases 1 500 1 500

    Item Lot size LT

    Component C 4 500 1

    MRP 1 2 3 4 5 6

    Gross Requirements Prod. A 0 0 0 0 200 0

    Gross Requirements Sub-ass. B 4 500 0 4 500 0 0 0

    4 500 0 4 500 0 200 0

    Projected inventory 4 600 100 100 100 100 4 400 4 400

    4 400 100

    4 500 4 500

    Planned Order Releases 4 500 4 500

    Item Lot size LT

    Component D 10 000 1

    MRP 1 2 3 4 5 6

    Gross Requirements Prod. Z 0 0 1 000 0 0 0

    Gross Requirements Sub-ass. B 6 000 0 6 000 0 0 0

    6 000 0 7 000 0 0 0

    Projected inventory 6500 500 500 3 500 3 500 3 500 3 500

    6 500

    10 000

    Planned Order Releases 10 000

    Sales Forecast

    Customer Orders

    Gross Req. Tot.

    Planned Order Receipts

    Net Requirements

    Net Requirements

    Gross Req. Tot.

    Order Receipts

    Planned Order Receipts

    Gross Req. Tot.

    Net Requirements

    Planned Order Receipts

    Sales Forecast

    Customer Orders

    Order Receipts

    Component C

    (1)

    Sub.-Ass. B

    (2)

    Component C(3)

    Component D(4)

    Product A

    Component D

    (2)

    Sub.-Ass. B

    (3)

    Component C

    (3)Component D

    (4)

    Product Z

    Month

  • 7/30/2019 OM_MRP-ERP

    37/41

    0 1 2 3 4 5

    Gross Requirements 75 350 200 750 1000

    Lot-for-lot (L4L) ordering policy

    Net Requirements 75 350 200 750 1000

    Planned order receipts 75 350 200 750 1000

    Projected on-hand inventory 0 0 0 0 0 0

    Fixed-size lot ordering policy (Ex: 500)

    Net Requirements 75 125 375 875

    Planned order receipts 500 500 500 1000

    Projected on-hand inventory 0 425 75 375 125 125

    Minimum order quantity (Ex: Min 250)

    Net Requirements 75 175 125 625 1000Planned order receipts 250 250 250 625 1000

    Projected on-hand inventory 0 175 75 125 0 0

    Multiple order quantity (Ex: X100)

    Net Requirements 75 325 125 675 975

    Planned order receipts 100 400 200 700 1000

    Projected on-hand inventory 0 25 75 75 25 25

    Economic order quantity (ex: 700; Ann. Dem: 4200)

    Net Requirements 75 675 975

    Planned order receipts 700 700 1400

    Projected on-hand inventory 0 625 275 75 25 425

    Periodic order quantity (2 months)

    Net Requirements 75 200 1000

    Planned order receipts 425 950 1000

    Projected on-hand inventory 0 350 0 750 0 0

    Month

  • 7/30/2019 OM_MRP-ERP

    38/41

    382-508-97 Production and Operations Management

    Establishing the Minimum Planning Horizon

    9 periods

    4 periods

    7 periods

    A

    B C

    D(2) E

    Lead Time = 2 periods

    Lead Time = 3 periods

    Lead Time = 2 periods Lead Time = 4 periods

    Lead Time = 2 periods

  • 7/30/2019 OM_MRP-ERP

    39/41

    392-508-97 Production and Operations Management

    Establishing the Minimum Planning Horizon

    A

    B

    C

    D(2)

    E

    LT = 2 periods

    LT = 3 periods

    LT = 2 periods

    LT = 4 periods

    LT = 2 periods

    LT 2 3 4 5 6 7 8 9 10

    A Assembly 2 100 100

    B Purchase 2 100 100

    C Assembly 3 100 100

    D Purchase 2 200 200

    E Purchase 4 100 100

    Periods

    MPS / MRP PROCESS

  • 7/30/2019 OM_MRP-ERP

    40/41

    402-508-97 Production and Operations Management

    Billofmaterials

    MPS / MRP PROCESSPlanned Order Receipt

    Planned Order Release

    Ref.: adapted from D. A. Turbide, MRP+, Industrial Press, 1993.

    Level 0

    Planned Order Release

    Supplier

    Gross Requirements

    Net Requirements

    Planned Order Receipt

    Level 2

    Planned Order Release

    Gross Requirements

    Net Requirements

    Planned Order Receipt

    Level 1 On-hand Inv.

    Lot Sizing

    Lead time

    MPS

    Mate

    rialsRequirementPlanning

    Minimum

    Planning

    Horizon

    ERP

  • 7/30/2019 OM_MRP-ERP

    41/41

    ERP

    EXTN OF MRP

    ENTIRE ORGANIZATION IS USED

    IT MUST

    WASTEFUL WORK IS ELIMINATED

    INFORMATION AT FINGER TIP