OM Lecture 17

Embed Size (px)

Citation preview

  • 7/30/2019 OM Lecture 17

    1/23

    LINE BALANCINGByArun Mishra

  • 7/30/2019 OM Lecture 17

    2/23

    Line Balancing

    Definition: the apportionment of sequential

    work activities into work stations in order to gain

    a high uti l ization of labour and equipment and

    therefore minimize idle time.

    Arranging a production line so that there is an

    even flow of production from one work station to

    the next, so that there are no delays at any work

    station that will leave the next work station withidle time.

  • 7/30/2019 OM Lecture 17

    3/23

    Introduction : What is line balancing?

  • 7/30/2019 OM Lecture 17

    4/23

    Introduction : What is line balancing?

  • 7/30/2019 OM Lecture 17

    5/23

    Objectives of Line Balancing

    Capacity Minimization of total idle time (maximization of the use of the

    line).

    Minimization of product flow-time.

    Balance the levels of capacity used at the workstations. Cost

    Minimization of the machinery costs, tools or idle equipment.

    Minimization of the costs of materials or reworks.

    Minimization of the costs by adjustment and change.

    Organizational-social

    Job Enrichment

    Modifications at the Line balancing

  • 7/30/2019 OM Lecture 17

    6/23

    Line Balance : Simple

    Example

    1 2 3 4

    25 mins5 mins 15 mins 10 mins

    Constraint

    Overburden

    This operator

    must WAIT for

    operator 2

    Overproduction which

    causes the other 6wastes

    Waiting

    Over-processing

    Inventory

    Rework

    Transportation Motion

    This operator

    must WAIT for

    operator 3

    5

    10

    15

    20

    25

    1 2 3 4

    mins

  • 7/30/2019 OM Lecture 17

    7/23

    Line Balance : Simple

    Example

    5

    10

    15

    20

    25

    Redistribute the work

    1 2 3 4

    15 mins15 mins 15 mins 10 mins

    Promotes one-piece FLOW

    Avoidsoverburden

    Minimises the 7wastes

    ReducesVariation

  • 7/30/2019 OM Lecture 17

    8/23

    Line Balancing Procedure in Assembly

    Layouts

    i. Step 1 : Determine what tasks must be performed tocomplete one unit of a finished product and thesequence in which the tasks must be performed. Drawthe precedence diagram.

    ii. Step 2 : Estimate the task time (amount of time it takesa worker to perform each task).

    iii. Step 3 : Determine the cycle time (the amount of timethat would elapse between products coming off the endof the assembly line if the desired hourly production

    were being produced.)iv. Step 4 : Assign each task to a worker and balance the

    assembly line. This process results in determining thescope of each workers job or which tasks that he or shewill perform.

  • 7/30/2019 OM Lecture 17

    9/23

    Terminologies used in Line Balancing

    Tasks: element of work or activity.

    Task Precedence: Indicated the sequence in which tasksmust be performed. Except the beginning task, all other

    tasks have preceding tasks.

    Task times: The amount of time required for an

    automated machine or a well-trained work to perform a

    task.

    Work station: Physical location where a particular set of

    tasks is performed. It could be either machine or

    equipment operated by a worker or robot.

    Work Centre: A physical location where two or moreidentical workstations are located in order to provide the

    need production capacity.

    Productive time per hour: The duration a work station

    or machine is working in each hour. It is always lesserthan actual available time.

  • 7/30/2019 OM Lecture 17

    10/23

    Tool used in line balancing to display elemental

    tasks and sequence requirements

    A Simple Precedence

    Diagrama b

    c d e

    0.1 min.

    0.7 min.

    1.0 min.

    0.5 min. 0.2 min.

    Precedence Diagram

  • 7/30/2019 OM Lecture 17

    11/23

    Cycle Time (CT) is the time interval at whichcompleted products leave the production line.

    Determination of cycle time (CT)

  • 7/30/2019 OM Lecture 17

    12/23

    Determination of the Ideal or Theoretical

    Minimum Number of Workers Required in the

    Line

    workperperiodpertimeAvailable

    periodperrequired

    unitsOutput

    task timeor

    operationTotal

    .productionline/

    assy.theinrequired

    workersof.nominimumltheoreticaorIdeal

    CT

    t

    CT

    1XtN

    The least number of work stations that can provide the

    required production. The formulae is;

  • 7/30/2019 OM Lecture 17

    13/23

    Balancing Efficiency

    An efficient line balancing will minimize the amount ofidle time.

    The balance efficiency can be calculated as:

    NCT

    t

    timesnworkstatiobyInput

    timetaskofOutput

    FFBE(i)

    workersofnumberActual

    workersofnumberminimumlTheoreticaFFBE(ii)

    Where, t = sum of the actual worker times or task times to complete one unit.

    CT= cyclic time; N= No. of workers or work stations.

  • 7/30/2019 OM Lecture 17

    14/23

    Line Balancing Procedure (Steps)

    Calculate the cyclic time and determine the theoretical

    minimum number of workstations.

    Compute the total actual number of workstation (N)

    required by rounding up the theoretical number of

    workstations to the next higher integer value.

    Assign the tasks to the workstations beginning with

    station1. Tasks are assigned to work stations moving fromleft to right through the precedence diagram.

    Before assigning each task to a workstation, use the

    following criteria to determine which tasks are eligible to

    be assigned to a workstation. All preceding tasks in the sequence have been assigned

    already.

    The task time does not exceed the time remaining at the

    workstation.

    If no task are eligible to be assigned to a particular

  • 7/30/2019 OM Lecture 17

    15/23

    Line Balancing Procedure (Steps) Conti

    After each task assignment, determine the time

    remaining at the current work station by subtractingthe sum of times for tasks already assigned to the

    work station from the cycle time.

    When there is a tie between two tasks (parallel tasks)

    to be assigned, use one of these rules:

    Assign the task with the longest task time.

    Assign the task with greatest number of followers.

    If there is still a tie, choose one task arbitrarily.

    Continue assignment of tasks until all tasks havebeen assigned to workstations.

    Calculate the idle time (or balance delay), percent

    idle time and efficiency of balancing the line.

  • 7/30/2019 OM Lecture 17

    16/23

    Line Balancing Methods

    The various line balancing methods or

    techniques used are:

    1. Heuristic methods

    2. Linear Programming3. Dynamic Programming

    4. Computerized line-balancing

    Heuristic and Computer based technique are most widelyused for solving large scale line balancing problems.

  • 7/30/2019 OM Lecture 17

    17/23

    Heuristic Method

    Thumb rule method which gives asatisfactory rather than optional

    solution to the line balancing problem.

    Acceptable when optimizing solutionsare not feasible or are too costly to

    obtain.

    In this work elements are groupedsuch that the cyclic time is not violated

    & the preceding diagram is used to

    group the activities as per the

  • 7/30/2019 OM Lecture 17

    18/23

    Types of Heuristic Methods

    Incremental Utilization Heuristic:

    Assigns tasks to a workstation in the order of task

    precedence one at a time until the utilization of

    workstation in 100% or as near to 100% as

    possible.

    This method is appropriate when one or moretask times is equal to or greater than the cyclic

    time.

    Longest-task time-Heuristic:

    Adds tasks to workstations one at a time in the

    order of task precedence.

    Tasks with shorter times are kept pending for

    assignment later to fine tune the balancing

    solution.

  • 7/30/2019 OM Lecture 17

    19/23

    Computerized Line Balancing

    Use of software packages that will balance

    large line quickly.

    Examples are; COMSOAL (Computer

    Method for Sequencing Operations for

    Assembly Lines), GEs ASYBL (AssemblyLine Configuration Program)

    They use various heuristics or rules are;

    Ranked positional weight

    Longest operational time

    Shortest operational time

    Most number of followings

    Least number of following tasks.

  • 7/30/2019 OM Lecture 17

    20/23

    Problem The precedence diagram for assembly activities A to

    G is shown below. The element time required for the

    activities are shown in the diagram in minutes. Theline operates for 7 hrs. Per day and an output of 550

    units per day is desired.

    Calculate Cycle time & theoretical min. number of workers.

    Group the tasks into an appropriate no. of work stations. Calculate the balance efficiency.

    A B C

    D

    E

    F G

    0.65 Min. 0.40 Min. 0.30 Min.

    0.20 Min.

    0.45 Min.

    0.40 Min. 0.30 Min.

    S l i

  • 7/30/2019 OM Lecture 17

    21/23

    Solution

    CT =

    Available time per period

    Output units required per period =

    7x60

    550 = 0.76 mts

    N = t

    CT=

    0.76

    0.65+0.4+0.3+0.2+0.45+0.4+0.3=

    0.76

    2.7= 3.552

    Ideal Time = CT Work station time

    Balance Efficiency:

    NCT

    t

    timesnworkstatiobyInput

    timetaskofOutputFFBE(i)

    =

    0.76x4

    2.7x 100 = 88.81%

  • 7/30/2019 OM Lecture 17

    22/23

  • 7/30/2019 OM Lecture 17

    23/23