Upload
madhavi
View
216
Download
0
Embed Size (px)
DESCRIPTION
Operation Management
Citation preview
OPERATIONS MANAGEMENT - I
ASSIGNMENT REPORT
Scharffen Berger Chocolate Maker (A)
Submitted by Group 7
MADHAVI BHOYAR 2014PGPM011
DEBASMITA MOHANTY 2014PGPM014
MANI RAJ 2014PGPM029
VENKAT 2014PGPM062
VISHAL PALIWAL 2014PGPM064
Executive Summery
Scharffen Berger was founded in 1996 by two friends, Robert Steinberg and John
Scharffenberger.
The chocolates from the company had received a good response from the market.
By 2000, Steinberg and Scharffenberger faced huge demand for their chocolates and
they realised that they need to add capacity in order to meet the demand.
At the end of 2003, Harris was recruited to lead the business and manage the
companys growth.
In 2005, they had ordered a ball mill, custom manufactured machine that promised
to increase the capacity while retaining the original taste.
Problem Description
Scharffen Bergers current maximum capacity is approximately 40,000 kg equivalent
to 29 conches.
The current capacity is not able to meet the growing market demand, this lead to
lost sales opportunity. Distributors and retailers also feel the shortage of goods and
loss of sales which will lead to dissatisfaction.
Even after adding a ball mill in the production process the output will not meet the
forecasted demand.
Harris has to decide how to increase the capacity but he does not have exact sales
forecast, so he does not wants to add extra capacity which will not be useful. At the
same time, he does not want to miss the opportunity to capture a huge market
share.
Analysis
Current production process has a bottle neck in conche process it takes most
amount of time which limits the production capacity
There are few production processes that that are underutilised, if all the processes
are utilised to the maximum possible the increased demand could met to an extent.
Many of the processes run only one shift, to add extra capacity we can use them for
more than one shits.
After a point the existing machines would not be able to meet the growing demand
then Harris has to take a call to add capacity to meet growing demand.
Final Recommendation
Addition of ball mill does not solve the problem as the bottle neck shifts to
melanguer which can be overcome by increasing the no of shifts melanguer works
for.
Then the bottle neck shifts to winnower which is underutilised so we need to use it
at full capacity.
Then the bottle neck shifts to roaster which runs only for one shift if we use it for
more than one shift the capacity will increase.
Like this we can utilise all the available resources to the maximum possible under the
process requirements.
After a time, effective utilisation of resources does not help and if the demand
increases by a huge margin as being anticipated, Harris has to take a call to add
capacity so that they do not have to chase the demand. There is risk involved in this
but if they do not add capacity then a part of market which could be easily captured
will be lost.