3
  OPERATIONS MANAGEMENT - I ASSIGNMENT REPORT Scharffen Berger Chocolate Maker (A) Submitted by Group 7 MADHAVI BHOYAR 2014PGPM011 DEBASMITA MOHANTY 2014PGPM014 MANI RAJ 2014PGPM029 VENKAT 2014PGPM062 VISHAL PALIWAL 2014PGPM064 

OM-I Submission Mumbai Campus Group 7

  • Upload
    madhavi

  • View
    216

  • Download
    0

Embed Size (px)

DESCRIPTION

Operation Management

Citation preview

  • OPERATIONS MANAGEMENT - I

    ASSIGNMENT REPORT

    Scharffen Berger Chocolate Maker (A)

    Submitted by Group 7

    MADHAVI BHOYAR 2014PGPM011

    DEBASMITA MOHANTY 2014PGPM014

    MANI RAJ 2014PGPM029

    VENKAT 2014PGPM062

    VISHAL PALIWAL 2014PGPM064

  • Executive Summery

    Scharffen Berger was founded in 1996 by two friends, Robert Steinberg and John

    Scharffenberger.

    The chocolates from the company had received a good response from the market.

    By 2000, Steinberg and Scharffenberger faced huge demand for their chocolates and

    they realised that they need to add capacity in order to meet the demand.

    At the end of 2003, Harris was recruited to lead the business and manage the

    companys growth.

    In 2005, they had ordered a ball mill, custom manufactured machine that promised

    to increase the capacity while retaining the original taste.

    Problem Description

    Scharffen Bergers current maximum capacity is approximately 40,000 kg equivalent

    to 29 conches.

    The current capacity is not able to meet the growing market demand, this lead to

    lost sales opportunity. Distributors and retailers also feel the shortage of goods and

    loss of sales which will lead to dissatisfaction.

    Even after adding a ball mill in the production process the output will not meet the

    forecasted demand.

    Harris has to decide how to increase the capacity but he does not have exact sales

    forecast, so he does not wants to add extra capacity which will not be useful. At the

    same time, he does not want to miss the opportunity to capture a huge market

    share.

    Analysis

    Current production process has a bottle neck in conche process it takes most

    amount of time which limits the production capacity

    There are few production processes that that are underutilised, if all the processes

    are utilised to the maximum possible the increased demand could met to an extent.

    Many of the processes run only one shift, to add extra capacity we can use them for

    more than one shits.

    After a point the existing machines would not be able to meet the growing demand

    then Harris has to take a call to add capacity to meet growing demand.

  • Final Recommendation

    Addition of ball mill does not solve the problem as the bottle neck shifts to

    melanguer which can be overcome by increasing the no of shifts melanguer works

    for.

    Then the bottle neck shifts to winnower which is underutilised so we need to use it

    at full capacity.

    Then the bottle neck shifts to roaster which runs only for one shift if we use it for

    more than one shift the capacity will increase.

    Like this we can utilise all the available resources to the maximum possible under the

    process requirements.

    After a time, effective utilisation of resources does not help and if the demand

    increases by a huge margin as being anticipated, Harris has to take a call to add

    capacity so that they do not have to chase the demand. There is risk involved in this

    but if they do not add capacity then a part of market which could be easily captured

    will be lost.