Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Audit report
Transition Audit from previous standard revisionIATF 16949
Transition Audit from previous standard revisionISO 9001:2015
OKE South Africa (Pty) Ltd
10 Dawn Road, Montague Gardens7440 Cape TownSouth Africa
Manufacturing site
Part of a corporate scheme? Yes No
Audit date:
From: 07 May 2018 to: 10 May 2018
REF No.: 40600433 IATF-Number: 0246348
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 1 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
1. Certificate recommendationThank you for your cooperation during the recent audit of your organization. This report describes the audit results
including strenghts, opportunities, and weaknesses. These results were presented to your management at the
closing meeting of the audit. You should now use these results to further strengthen your management system. We
look forward to continue our partnership towards sustainable business success.
ISO 9001:2015
Overall evaluation
The management system is mostly effective and fulfills the requirements of the applied standard(s), except for
the identified nonconformities - see action plan(s).
The audit team recommends to DQS in reference to the applied standard:
The issuance of the certificate as soon as implementation of corrective actions has been demonstrated.
IATF 16949
Overall evaluation
The management system is mostly effective and fulfills the requirements of the applied standard(s), except for
the identified nonconformities - see action plan(s).
The audit team recommends to DQS in reference to the applied standard:
The issuance of the certificate as soon as implementation of corrective actions has been demonstrated.
The permanent barrier erected around the Automotive production facility still ensure a complete functional
segregation for automotive production and processing.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 2 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
2. Audit results
2.1 Executive summaryThe audit team confirms that OKE South Africa (Pty) Ltd has implemented and maintains a management system in
accordance with the applied standard(s). Detailed audit results were presented, explained and, as necessary,
discussed with the organization's management during the closing meeting. The following chart provides a graphic
overview of the respective audit findings and evaluations, which are stated explicitly in chapter 3 of this audit report.
IATF 16949
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 3 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
ISO 9001:2015
Rating in 4 levels
NC = major nonconformity was identified, conformity to requirements was not evident or a risk of shipping a nonconforming product to customer was identified.
nc = minor nonconformity was identified, single or isolated deficiencies were identified without impact onto the system's effectiveness
conf = conforming, all requirements are fully met, (with or without potential for improvement)
str = conforming, all requirements are fully met and significant strength was identified, evident through excellent results
All audit findings are based on a sampling process, targeted towards reliable evidence for effective implementation
and compliance of the management system. Where applicable findings and required corrective action plans were or
will be agreed upon with the responsible managers or management representatives, steps have been or will be
defined to resolve such non-conformity. Where applicable findings and required corrective action plans were or will
be agreed upon with the responsible managers or management representatives, steps have been or will be defined
to resolve such non- conformity. Further business aspects may exist, positive or negative, which have not been
reviewed by the audit team. It is the organization´s responsibility to investigate and evaluate the potential impact and
scope of findings, thus continuously ensuring full compliance to the applied standard(s).
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 4 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
2.2 Strength(s) - Exceed(s) the requirements of the standard/specification
No. Standard Requirement Process Statement Evaluation
1 IATF 16949;ISO
9001:2015
6.1 MP - Corporate
development strategy
Deployment plan for BBBEE Planner (risk
“what if plan”), particularly relevant to SA.
Bench mark example in Auditors opinion.
Strength
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 5 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
2.3 Opportunities for improvement and non-conformities
nc = minor nonconformity, NC = Major nonconformity, OFI = Opportunity for improvement
No. Standard Requirement Process Statement Evaluation
1 IATF 16949 4.3.1 MP - Corporate development
strategy
The process to define interfaces with the
remote locations is not fully effective.
nc
2 IATF 16949 7.1.5.2.1 COP - Product Scheduling &
Production
The process to assure reliable measuring
equipment is not fully effective.
nc
3 ISO
9001:2015
6.1 MP - Corporate development
strategy
The process to perform risk analysis is not
fully effective.
1) Risk analysis has not been
documented for Industrial "Product design
and development" process.
2) BBBEE commitment experienced in
South Africa may be of value if included in
the business plan
nc
4 IATF 16949 9.2.2.2 MP - Management system Plan &
Improve Audits
The process to perform internal system
audits is not fully effective.
nc
5 IATF 16949 8.5.4.1 COP - Product Picking batching &
dispatching
The process to assure housekeeping in
the Warehouse (FG store) is not fully
effective.
nc
6 IATF 16949 8.5.1.1 COP - Product Scheduling &
Production
The process to develop the control plan is
not fully effective.
nc
7 IATF 16949 8.3.3.2 COP - Product Scheduling &
Production
The process to develop PFMEA is not
entirely effective. PFMEA 005 date
29-03-2018 rev 6.
nc
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 6 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3. Evaluation of the management system
3.1 Context of the organization
IATF 16949
NC nc conf str not audited
The organization has determined external and internal issues relevant to its purpose
and ability to achieve the intended outcome of its management system.
The organization has determined relevant needs and expectations of interested
parties and determined which needs and expectations are compliance obligations.
The organization has determined its management system scope considering
applicable issues, compliance obligations, boundaries, activities, and functions; (4.3)
supporting functions and CSRs are included in the scope. If applicable, exclusion of
product design and development is justified. (4.3.1, 4.3.2).
For every process all standard requirements have been applied effectively (inputs,
outputs, criteria, indicators, resources, interaction, authority, risk). (4.4) Process
owners are defined and product realization and support processes are reviewed to
evaluate and improve their effectiveness and efficiency. (5.1.1.2, 5.1.1.3).
The organization has documented and implemented processes for the management
of product-safety related product and manufacturing processes. (4.4.1.2).
ISO 9001:2015
NC nc conf str not audited
The organization has determined external and internal issues relevant to its purpose
and ability to achieve the intended outcome of its management system. (4.1)
The organization has determined relevant needs and expectations of interested
parties and determined which needs and expectations are compliance obligations.
(4.2)
The organization has determined its management system scope considering
applicable issues, compliance obligations, boundaries, activities, and functions. (4.3)
For every process all standard requirements have been applied effectively
(inputs,outputs, criteria, indicators, resources, interaction, authority, risk). (4.4)
The system as documented in Horstel Germany has been revised to align with IATF, OKE SA have take the the
Group system, applied & customized it to suit local context. OKE Germany has an influence over the strategic
direction of the OKE SA as well as influence over the development of the QMS. The system as developed is
structured in 4 tiers consisting of a Quality Manual, Procedures, Work instructions (process control documents) and
records.
The process was a revision activity rather than a complete new system. Great effort has been put into the
implementation process, the documented system is still immature as identified in some of the Nc's. The system will
continue to improve as each internal audit and management review is completed. The Quality Manual contains
among other the defined Core Processes, which depicts the processes and their interactions. See Nc related to the
interactions between HO and OKE SA.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 7 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.2 Leadership
IATF 16949
NC nc conf str not audited
Top management demonstrates leadership and commitment with respect to the
management system and take accountability for its effectiveness.
The policies and objectives are established and understood; they are compatible
with context and strategic direction of the organization. (5.1, 5.2). The policies
include at a minimum an anti-bribery policy, an employee code of conduct and an
ethics escalation policy. (5.1.1.1)
Top management ensures customer focus, including awareness for requirements,
risks, opportunities and customer satisfaction.
Organizational roles, responsibilities and authorities are assigned, communicated,
understood and supported by top management. (5.3) This includes personnel with
responsibility and authority to ensure that customer requirements are met and
personnel with authority to stop shipment and stop production to correct quality
problems (across all shifts). (5.3.1, 5.3.2).
ISO 9001:2015
NC nc conf str not audited
Top management demonstrates leadership and commitment with respect to the
management system and take accountability for its effectiveness. (5.1)
The policy and objectives are established and understood; they are compatible with
context and strategic direction of the organization. (5.1, 5.2)
Top management ensures customer focus, including awareness for requirements,
risks, opportunities and customer satisfaction. (5.1)
Organizational roles, responsibilities and authorities are assigned, communicated,
understood and supported by top management. (5.3)
OKE South Africa (Pty) Ltd's current quality policy is dated 05 Feb 2018.
Leadership has a "hands on" approach toward the QMS. Several meetings are held to share crucial performance
information. These communication sessions are where process owners share performance information related to
their areas and request resource support form the Leadership team where needed. Leadership is seen as a strong
point at OKE SA.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 8 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.3 Planning
IATF 16949
NC nc conf str not audited
The organization has determined risks and opportunities considering interested
parties and scope of the management system. (6.1) Documented information as
evidence of the result of the risk analysis is retained and the risk analysis includes
lessons learned from product recalls, product audits, field returns and repairs,
complaints, scrap and rework. (6.1.2.1)
The organization has determined and planned suitable actions to assure intended
outcomes, including compliance obligations to address risks and opportunities. (6.1)
The actions include preventive action, a process to lessen the impact of negative
effects of risk and contingency plans. (6.1.2.2, 6.1.2.3).
Annual (at a minimum) objectives (measurable) have been established at all relevant
functions, levels and processes (and are being pursued). (6.2) and they are aligned
with customer requirements. (6.2.2.1)
Action planning to achieve quality objectives is deployed effectively, including the
need for change (who, when, what, how, resources, evaluation of results).
ISO 9001:2015
NC nc conf str not audited
The organization has determined risks and opportunities considering interested
parties and scope of the management system. (6.1)
The organization has determined and planned suitable actions to assure intended
outcomes, including compliance obligations to address risks and opportunities. (6.1)
Objectives (measurable) have been established at all relevant functions, levels and
processes (and are being pursued). (6.2)
Action planning to achieve quality objectives is deployed effectively, including the
need for change (who, when, what, how, resources, evaluation of results). (6.2, 6.3)
The risk assessment tool was successfully applied across all processes resulting in focus on process risks which
were mitigated / met through process controls and concerted efforts. Interested parties and their expectations is
familiar terminology for process owners, and those interviewed had a clear understanding of needs & expectations.
The Leadership team have incorporated those into the KPI's / KPA's of the system monitored through both
effectiveness and efficiency indicators.
ISO 9001:2015 - The risk analysis activity was not applied to the Industrial Product Design and Development
process. See Nc 3 of 7 (6.1).
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 9 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.4 Support
IATF 16949
NC nc conf str not audited
Necessary resources (people, infrastructure, organizational knowledge, environment
for the operation of processes) including monitoring and measuring resources are
determined and provided for the establishment, implementation, maintenance and
continual improvement of the management system.
A multidisciplinary approach including risk identification and risk mitigation for
developing and improving plant, facility and equipment plans is used and methods to
evaluate manufacturing feasibility and to assure process effectiveness are
implemented. (7.1.3.1)
Monitoring and measurement resources include conduction of measurement system
analysis (MSA), a documented process for managing calibration/ verification
activities and fulfillment with internal and external laboratory requirements.
(7.1.5.1.1, 7.1.5.2.1, 7.1.5.3).
Necessary competence and awareness of personnel operating under the
organization's control is ensured. (7.2, 7.3) This includes maintenance of a list of
qualified internal auditors and a documented process to verify their competence
(including fulfillment of CSRs). A documented process for identifying training needs
of employees (including awareness of their impact on product quality and customer
requirements) is implemented and necessary 'on-the-job-training' is provided (7.2.1,
7.2.2).
Effective internal and external communication is determined (who, how, what,
when). (7.4) and a documented process for employee motivation and empowerment
is implemented. (7.3.2)
Documented information (including a quality manual, required documented
processes for the QMS, the organization's processes and their sequence and
interactions and a document indicating where within the organization's quality
management system their customer specific requirements are addressed) is
determined, available, maintained and controlled, ensuring effectiveness of the
management system and its processes. (7.5, 7.5.1.1). This includes a documented
record retention policy and a documented process for managing of engineering
specifications.
ISO 9001:2015
NC nc conf str not audited
Necessary resources (people, infrastructure, organizational knowledge, environment
for the operation of processes) including monitoring and measuring resources are
determined and provided for the establishment, implementation, maintenance and
continual improvement of the management system. (7.1)
Necessary competence and awareness of personnel operating under the
organization's control is ensured. (7.2, 7.3)
Effective internal and external communication is determined (who, how, what,
when). (7.4)
Documented information is determined, available, maintained and controlled,
ensuring effectivenes of the management system and its processes. (7.5)
The infrastructure established throughout the operation was appropriate in design and was maintained effectively to
ensure CSR were met for product safety as well as the related services level expectations. Staff at all levels were
observed to be well trained and displayed a very clear understanding of requirements and were confident during the
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 10 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
interviews. Communication was effective throughout the sampled processes and activities. Good levels of discipline
and attention to detail was noted throughout the facility.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 11 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.5 Operation
a) Planning operation
IATF 16949
NC nc conf str not audited
All operational processes needed to meet product and service requirements,
including customer- specific requirements, logistics requirements, manufacturing
feasibility and project planning, are planned, implemented and controlled effectively.
(8.1) Confidentiality of customer-contracted products and projects is ensured (8.1.2)
Effective customer communication (language agreed with the customer, specified
computer language and format), ensures that all relevant requirements related to
product and services are determined, reviewed and confirmed (special
characteristics, manufacturing feasibility).
The organization has established, implemented and maintains an effective design
and development process for products and manufacturing process (planning, input,
special characteristics, monitoring, validation, prototype program, product approval
process, output, FMEA, reliability, etc.), ensuring subsequent provision of compliant
product and services. (8.3, 8.3.2.1). A multidisciplinary approach is used and the
necessary product design skills are ensured (8.3.2.1, 8.3.2.2)
The organization uses a process for assuring quality of products that use embedded
software and retains documented information of a software development capability
self- assessment) (8.3.2.3). Suppliers of software or products with embedded
software are required to implement and maintain a process for software assurance
and this process is assessed? (8.4.2.3.1)
Externally provided processes, products and services are effectively controlled,
including a documented process for supplier monitoring, a second party audit
process, supplier development and pass down of all applicable statutory and
regulatory requirements. (8.4, 8.4.2.4, 8.4.2.5, 8.4.3)
ISO 9001:2015
NC nc conf str not audited
All operational processes needed to meet product and service requirements,
including customer-specific requirements, are planned, implemented and controlled
effectively. (8.1)
Effective customer communication ensures that all relevant requirements related to
product and service are determined, reviewed and confirmed. (8.2)
The organization has established, implemented and maintains an effective design
and development process, ensuring subsequent provision of compliant product and
services. (8.3)
Externally provided processes, products and services are effectively controlled,
including selection and evaluation of external providers. (8.4)
Samples of the results show that a structured planning process is in place for preparation of product realization, test
and final approvals. The control also indicates effective interface & support from Germany in the project phase.See
Nc against 8.5.1.1 for controls that need attention.
ISO 9001:2015 Product design and development process included in the audit on 10 May 2018.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 12 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
b) Controlling operation
IATF 16949
NC nc conf str not audited
The organization has ensured controlled conditions for all production and service
provision operations, including post- delivery activities. (8.5) Controlled conditions
include development of control plans, standardized work documents, verification of
job set- ups, verification after shutdown, production scheduling, identification/
traceability, preservation and control of changes and temporary changes (8.5.1.
8.5.2, 8.5.3, 8.5.4, 8.5.6).
Monitoring and measuring activities are suitable to support controlled conditions,
including prevention of human error (8.5) and a system for production tooling
management and a documented total productive maintenance system is
implemented and maintained. (8.5.1.5, 8.5.1.6)
A process for feedback of information from service (service concerns, field failure
test analysis) and to fulfill with service agreements with customer is implemented.
(8.5.5)
The organization ensures release of conforming product and service by planned
arrangements effectively, including layout inspection and functional testing,
appearance items, verification and acceptance of conformity of externally provided
products and services and fulfillment with statutory/ regulatory requirements and
acceptance criteria. (8.6, 8.6.1 - 8.6.6)
Nonconforming process output is identified and controlled to prevent unintended use
or delivery. (8.7) This includes control of suspect, reworked and repaired products,
customer notification, a documented process for disposition of nonconforming
products and customer authorization for any kind of concessions including
respective records (8.7.1).
ISO 9001:2015
NC nc conf str not audited
The organization has ensured controlled conditions for all production and service
provision operations, including post-delivery activities. (8.5)
Monitoring and measuring activities are suitable to support controlled conditions,
including prevention of human error. (8.5)
The organization ensures release of conforming product and service by planned
arrangements effectively. (8.6)
Nonconforming process output is identified and controlled to prevent unintended use
or delivery. (8.7)
The controlled conditions experience during this audit included, the availability of information that describes the
characteristics of the product, the availability of work instructions, as necessary, the use of suitable equipment, the
availability and use of monitoring and measuring equipment, the implementation of monitoring and measurement,
and the implementation of product release, delivery and post- delivery activities. Non-conformities were raised in
production, see Nc's against 8.3.3.2; 8.5.4.1 & 8.5.1.1 for controls that need attention.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 13 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.6 Performance evaluation
IATF 16949
NC nc conf str not audited
The organization has determined adequate measuring and monitoring provisions to
evaluate performance and effectiveness of its management system, including
customer satisfaction. (9.1) This includes process studies on all manufacturing
processes to verify process capability, including action plans for unstable or not
capable characteristics. (9.1.1.1)
The organization has determined and implemented processes needed to evaluate
fulfilment of its compliance obligations and maintains knowledge and understanding
of its compliance status. (9.1) Appropriate statistical tools are identified and applied.
(9.1.1.2, 9.1.1.3).
Customer satisfaction is monitored through continual evaluation of internal and
external performance indicators (as a minimum: delivered part quality, customer
disruptions, field returns, recalls, and warranty, delivery schedule performance and
customer notifications). (9.1.2.1)
An internal audit program, including system audits, manufacturing process audits
and product audits, is planned (annual program, considering all shifts, etc.) and
deployed effectively by competent personnel, ensuring compliance and suitability of
the management system. (9.2) If applicable, it includes a software development
capability assesment.
Top management performs at least annually a management review to ensure
continuing suitability, adequacy and effectiveness of its management system,
including alignment with the strategic direction of the organization. (9.3) All required
review inputs (9.3.2.1) are addressed and top management establishes an action
plan when customer performance targets are not met (9.3.3.1).
ISO 9001:2015
NC nc conf str not audited
The organization has determined adequate measuring and monitoring provisions to
evaluate performance and effectiveness of its management system, including
customer satisfaction. (9.1)
The organization has determined and implemented processes needed to evaluate
fulfilment of its compliance obligations and maintains knowledge and understanding
of its compliance status. (9.1)
An internal audit program is planned and deployed effectively by competent
personnel, ensuring compliance and suitability of the management system. (9.2)
Top management performs management review to ensure continuing suitability,
adequacy and effectiveness of its management system, including alignment with the
strategic direction of the organisation. (9.3)
Date of last management review 17 Apr 2018
Management review is not a single meeting rather a series of monthly meetings aimed at reviewing and improving
the QMS. Input requirements of the ISO/TS and the customer are reflected.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 14 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
3.7 Improvement
IATF 16949
NC nc conf str not audited
The organization determines and selects opportunities for improvement and
implements necessary actions to achieve the intended outcomes of its management
system.
Complaints and improvement proposals are registered and treated effectively. (10.2)
This includes analysis on customer complaints and field failures, communication to
the customer of the results and if required, a warranty management process
including a method for warranty part analysis. (10.2.5, 10.2.6)
Corrective action is implemented effectively and appropriately, eliminating causes for
nonconformity with risk identification and evaluation of corrective action
effectiveness. (10.2) This includes documented processes for problem solving
(10.2.3) and use of error-proofing methodologies (10.2.4).
When nonconformities have occurred the organization has reacted to control and
provide correction. Defined corrective action from previous audit has been
implemented effectively.
Considering the results from analysis, evaluation and management review, the
organization continually improves suitability, adequacy and effectiveness of its
management system. (10.3) Therefore, a documented process is implemented,
including methodology, objectives, measurement, effectiveness, required
documented information, a manufacturing process improvement plan and a risk
analysis. (10.3.1)
ISO 9001:2015
NC nc conf str not audited
The organization determines and selects opportunities for improvement and
implements necessary actions to achieve the intended outcomes of its management
system. (10.1)
Complaints and improvement proposals are registered and treated effectively. (10.2)
Corrective action is implemented effectively and appropriately, eliminating causes
for nonconformity with risk identification and evaluation of corrective action
effectiveness. (10.2)
When nonconformities have occurred the organization has reacted to control and
provide correction. Defined corrective action from previous audit has been
implemented effectively. (10.2)
Considering the results from analysis, evaluation and management review, the
organization continually improves suitability, adequacy and effectiveness of its
management system. (10.3)
There has been progress with the improvements of the management systems and processes. There is a defined
process for continual improvement, this is based upon actions identified with the analysis of performance and
generally aims at improving productivity, quality of products and processes, reduction of line start- ups and
downtime, Improvement of housekeeping, Optimization of business processes through an improvement of
communication and information flow.
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 15 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
4. Further audit results
4.1 Sampling bases for employees
Management personnel 5 thereof interviewed 5 = 100%
Employees without management authority 18 thereof interviewed 10 = 56%
Total employees 23 thereof interviewed 15 = 65%
Since time of audit planning, total number of employees has not changed.
4.2 Audited shifts
Does the organization work in multiple shifts? Yes No
Working shift Process Start End Audited Reason if not audited
1 COP - Product Scheduling &
Production
06:30 14:30 yes
2 COP - Product Scheduling &
Production
14:30 22:30 yes
3 COP - Product Scheduling &
Production
22:30 06:30 yes
4.3 List of relevant processes
Process: Performance indicator(s): Targets achieved?
Actions Remarks Audited
MP - Corporate
development strategy
Unknown yes Monthly & Weekly
meetings
yes
MP - Personnel
development
Unknown partially Monthly & Weekly
meetings
yes
MP - Management
system Plan &
Improve Audits
Unknown yes Monthly & Weekly
meetings
yes
MP - Internal
communication
Unknown yes Monthly & Weekly
meetings
yes
ISO 9001 - COP -
Product design &
Project Mgmt (Mgmt
of CSR)
Unknown Non Automotive yes
COP - Marketing (RL)
& Process design
(RL)
Unknown yes Monthly & Weekly
meetings
yes
COP - Customer
acquisition & service
Unknown yes Monthly & Weekly
meetings
yes
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 16 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
Process: Performance indicator(s): Targets achieved?
Actions Remarks Audited
COP - Product
Scheduling &
Production
Unknown yes Monthly & Weekly
meetings
yes
COP - Order
processing
Unknown yes Monthly & Weekly
meetings
yes
COP - Product
Picking batching &
dispatching
Unknown yes Monthly & Weekly
meetings
yes
SP - Control of Non
conforming outputs
Unknown yes Monthly & Weekly
meetings
yes
SP - Acquisition (RL) Unknown yes Monthly & Weekly
meetings
yes
MP - Cont Imp CIP Unknown yes Monthly & Weekly
meetings
yes
SP - Maintenance &
repair
Unknown yes Monthly & Weekly
meetings
yes
SP - QA-Processes Unknown yes Monthly & Weekly
meetings
yes
SP - Information
systems provision &
maintenance (RL)
Unknown yes Monthly & Weekly
meetings
yes
MP - Environment &
energy management
process
Unknown yes Monthly & Weekly
meetings
yes
ISO 9001 - COP -
Product Scheduling &
Production
Unknown yes Monthly & Weekly
meetings
Non Automotive
Production
yes
Targets achieved: How frequently are process targets archieved?
Yes = 100% over or near 100%
Mostly = over 85%
Partially = over 50%
No = under 50%
4.4 Customer related performance
IATF-OEM Product quality Shipment Status Verified Evidences
Toyota Boshoku OK OK OK Report for April
Actions if target not achieved:
Lear OK OK OK Internal measures
Actions if target not achieved:
Adient OK OK OK Internal measures
Actions if target not achieved:
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 17 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
4.5 Applicable OEM Customer specific requirements
CSR Revision Customer New SupplierCode Audited
SQAM 2006 Toyota Boshoku no SE01-1 yes
SQTS Aug 2012 Lear no Various yes
JCS 2901 Rev.4 Adient no Various yes
4.6 Remote locations
Ref.No. Name Address Employees
Report review
Other CB
40600435 OKE Group GmbH 7 Nobel Strasse, Horstel, Germany 3 2018-04-24 TUV Rheinland
Audited to standard: ISO/TS 16949:2009 (Audit completion date: 12 May 2017), Last internal system audit to standard: IATF 16949
Scheduled audit date for transition to IATF 16949: 21 May 2018
Functions: Contract Review; Engineering; Information Technology; Laboratory; Marketing; Policy making; Process design; Production
equipment development; Purchasing; Strategic planning; Supplier management; Testing
Audited interfaces: The system as documented in Horstel Germany has been revised to align with IATF, OKE SA have take the the Group
system, applied & customized it to suit local context. The control also indicates effective interface & support from Germany in the project
phase.
4.7 Extended manufacturing sitesNone
4.8 Supported sitesNone
4.9 Evaluation of the previous certification cycle
For the evaluation of the following items, the auditing reports of the last three years were reviewed and evaluated:
System or recertification audit date 15 Jun 2016
1st Surveillance audit date 08 Jun 2017
2nd Surveillance audit date
The overall system performance for the past
certification cycle demonstrates the continued
effectiveness of the system.
Yes, management review records indicate achievement of
established objectives and continuous improvement
Yes, trends of corrective action records indicate effectiveness
and continuous improvement.
Internal audits and corrective action Yes No
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 18 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
records show continued conformance of
the management system to selected
standards.
Similar findings had been identified
repeatedly during the previous certification
period.
Yes No
During the previous certification period,
certificates had been issued under
constraints, suspended or special audits
had been conducted due to certain defects.
Yes No
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 19 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
5. Next steps
5.1 Process to resolve nonconformities / findings
Nonconformities, identified during an audit, shall be closed with evidence of effectiveness within defined time lines.
Open nonconformities jeopardize the conformity of the certified management system. When nonconformities cannot
be resolved, existing certifications may be suspended or withdrawn.
Decertification process
During the audit nonconformities may be identified. They are recorded and reported to the customer
as soon as possible, at the latest during the closing meeting. It is the customer's responsibility to
define and implement corrective action for resolving the nonconformity.
10 May 2018
As soon as possible and within 20 days after the audit, immediate measures and root cause
analyses shall be forwarded to the Lead Auditor for evaluation, along with the respective evidence.
30 May 2018
As soon as possible and within 60 days after the audit, systemic corrective actions and their
verification shall be forwarded to the Lead Auditor for evaluation, along with the respective evidence.
09 Jul 2018
As soon as possible and within 90 days after the audit, the Lead Auditor shall evaluate the
effectiveness of systemic corrective actions by reviewing evidence. For major nonconformities such
review shall be performed by a follow-up audit at the organization’s site. For minor nonconformities
such review may be performed either by a follow-up audit on site or by remote review of evidence,
such as records.
08 Aug 2018
Verification of nonconfirmities needed through follow-up audit: Yes No
Audit type: Document review (off-site audit)
Planned date: 09 Jul 2018 - 09 Jul 2018
Total number of audit days: 0.5
Identified potential opportunities for improvement shall be evaluated internally and incorporated into the continual
improvement process as deemed beneficial.
5.2 Next regular audit planning
Type of audit: Surveillance Audit
Planned date for next audit:
(non-binding estimate of audit days)
03 Jun 2019 - 04 Jun 2019
(week or month, if appropriate)
For IATF 16949: 2, ISO 9001:2015: 1 audit day(s) in total, performed by 1
auditor(s). For applicable standards calculated as 100% value of IAF
mandatory document for audit duration.
The estimated amount of time for
verification of action plans for the
next audit/year is:
2 hour(s)
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 20 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
Main emphasis will be on the
following subjects:
Further enhancement of IATF requirements. Audit of maintenance to verify the
completion of the implementation role out.
None
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 21 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
6. Audit and Certification Data
6.1 Audit and Certification data
Current scope of certification/registration IATF 16949 + ISO 9001:2015:
Manufacturing of plastic profiles
ISO 9001:2015:
Design and manufacture of plastic and
silicone extruded products and plastic
injection moulded products.
Current scope in English language IATF 16949 + ISO 9001:2015:
Manufacturing of plastic profiles
ISO 9001:2015:
Design and manufacture of plastic and
silicone extruded products and plastic
injection moulded products.
Primary IAF / EA code EAC 14
Non-applicability of product design yes
Are there any outsourced processes? no
Did the organization use a consultant? no
6.2 Certificate, logos and their use
The following changes are necessary:
There was a change in support functions.
Certificate, certification logos and marks of DQS and Accrediation bodies are being used appropriately
6.3 Changes, identified during the audit
The following changes (e.g. company name, address, scope, number of employees, etc.) were identified during
the audit:
Type of change Existing information in DQS database New information obtained during audit
State Western Cape No data available
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 22 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
Please remember to inform DQS immediately of any significant changes to your management system. We will
analyse the changes and inform you about the possible impact to your certification.
6.4 Fulfillment of audit objectives and audit schedule
Audit objectives and audit schedule were fulfilled without changes
6.5 Audit data
Name of the organisation(client): OKE South Africa (Pty) Ltd
Division
Main address: 10 Dawn Road, Montague Gardens, 7440 Cape Town, South Africa
Ref. No.: 40600433
Audit type: 1. Transition Audit from previous standard revision
Surveillance frequency (mth): 12
Date of audit: 07 May 2018 to 10 May 2018
Total number of audit days: 3.5
Date of last stage 1 audit:
Date of previous stage2 / initial audit: 13 Jun 2016 to 15 Jun 2016
Exclusions, if applicable: Customer is responsible for product design
Total number of employees of ref.no. above: 23
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 23 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany
6.6 Contact data
Management Representative: Nico Van Reenen
Telephone: +27 21 551 2464
E-Mail: [email protected]
Lead-Auditor: Mark Christopher Ilsley
Audit days: 3.50
Telephone: +27 21 5569801
E-Mail: [email protected]
DQS Customer service person: Ilse Johansson
Telephone: +27 11 787 0060
E-Mail: [email protected]
Report last version date: 31 Jul 2018
Lead Auditor: Mark Christopher Ilsley
This report was provided to the management of the audited organization on 10 May 2018
by personal handover electronically by other means (please specify)
DisclaimerDQS maintains ownership of this report. The content of this report and all information received in relation to the audit and certification of the
audited organization will be treated confidential and not disclosed to third parties. For exceptions e.g. disclosure to accreditation body refer to
DQS Certification and Assessment Regulations.
This report is considered as final by the audit team, if you do not get any adverse information from DQS within 14 days after the last audit day.
The recommendation of the audit team is subject to review and approval by DQS technical certification experts (veto power person) , who take
binding certification decision within 120 days. An appeal process is defined in DQS Certification and Assessment Regulations. Should DQS
obtain any information indicating nonconformity of the certified management system, DQS will notify the certified organization timely and initiate
investigation and evaluation of such information.
Distribution:DQS
OKE South Africa (Pty) Ltd
Report OKE South Africa (Pty) Ltd
#Ref. 40600433
confidential
Version 10 May 2018
Page 24 of 24
DQS Holding GmbH
August-Schanz-Str. 21, 60433 Frankfurt a.M., Germany