Ohio Department of Transportation Quarterly Update to Northeast Ohio Areawide Coordinating Agency December 11, 2009

Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Ohio Department of Transportation

Quarterly Update

to

Northeast Ohio Areawide Coordinating Agency

December 11, 2009

Page 2: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Today’s Quarterly Project Update:

Cleveland Innerbelt Project

Cuyahoga River Valley Crossing

Lakefront West

Ohio Department of Transportation

Page 3: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Environmental Impact Statement:

DEIS Approved by ODOT – March 2, 2009

DEIS Approved by FHWA – March 3, 2009

Notice of Availability (DEIS) – March 20, 2009

Public Hearing – April 21, 2009

Close of DEIS Public Comments – 5:00 PM, May 21, 2009

FEIS Approved by ODOT – July 10, 2009

FEIS Approved by FHWA – July 22, 2009

Notice of Availability (FEIS) – July 31, 2009

Record of Decision – September 18, 2009

Cleveland Innerbelt Project

Page 4: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Initial Construction Sequence:

Cuyahoga River Valley (WB) Crossing: 2011-2014

Cuyahoga River Valley (EB) Crossing: 2014-2017

Central Interchange and I-77 Approach: 2017-2021

Cleveland Innerbelt Project

Page 5: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Construction Segments Phase Year of

Expenditure (YOE)

Cost in 2009

(millions)Cost in YOE

(millions)

Construction Contract Group 1:

I-90 westbound from I-90/I-490 to East 9th St. overhead

Detailed Design

Right-of-Way

Construction

2010

2009

2011-2013

$17-18

$41-52

$362-399

$17-22

$41-52

$442-564

Construction Contract Group 2:

I-90 eastbound from I-90/I-490 to East 9th St. overhead

Detailed Design

Right-of-Way

Construction

2011

2012

2014-2016

$26-29

$3

$287-317

$28-36

$3-4

$396-505

Construction Contract Group 3:

A: I-90 WB in Central Interchange from E. 9th St. to E. 22nd St.; E. 22nd St. (part-width);

remove Cedar Ave. bridge over I-90

B: I-77 improvements north of Kingsbury Run Bridge

C: I-90 EB in Central Interchange from E. 9th St. to E. 22nd St.; Carnegie (part-width)

Detailed Design

Construction (A)

Construction (B)

Construction (C)

2014

2017-2018

2021

2019-2020

$21-23

$102-112

$83-92

$46-50

$26-33

$159-202

$154-196

$78-100

Construction Contract Group 4:

A: Easterly Interceptor relocation

B: CSX railroad overhead

C: Norfolk Southern railroad overhead

D: Overheads in Innerbelt Curve: Superior (part-width); St. Clair (closure); Hamilton

(closure); Lakeside (closure); Structure under Superior intersection for the proposed I-90 WB

to Chester ramp

E: Innerbelt Curve north of Superior Ave.

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

Construction (C)

Construction (D)

Construction (E)

2019

2020

2022

2022-2023

2022-2023

2024-2025

2026-2027

$18-20

$14-16

$4-5

$25-28

$28-31

$23-25

$116-127

$28-36

$19-24

$8-10

$51-65

$56-71

$50-64

$279-356

Construction Contract Group 5:

A: Overheads in Innerbelt Trench: Prospect (part-width); Euclid (part-width); Chester (part-

width); Payne (closure)

B: I-90 eastbound in Innerbelt Trench from E. 22nd St. to Superior

C. I-90 westbound in Innerbelt Trench from E. 22nd St. to Superior

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

Construction (C)

2025

2026

2028-2029

2030-2031

2031-2033

$15-17

$12-13

$34-37

$77-85

$54-59

$32-41

$19-24

$90-114

$225-287

$169-216

Construction Contract Group 6:

A: I-77 bridge widening over I-490

B: I-77 improvements south of I-490

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

2022

2023

2021-2024

2025-2026

$6-7

$1

$45-49

$25-28

$12-15

$1-2

$89-113

$58-74

Construction Contract Group 7:

I-71 roadway pavement and bridge deck replacements; I-71 southbound deceleration lane to

Jennings

Detailed Design

Construction

2024

2027

$6

$61-68$11-15

$152-194

Totals All phases 2010-2033 $1.6-1.7 billion $2.7 to $3.5 billion

Page 6: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Construction Segments Phase Year of

Expenditure (YOE)

Cost in 2009

(millions)Cost in YOE

(millions)

Construction Contract Group 1:

I-90 westbound from I-90/I-490 to East 9th St. overhead

Detailed Design

Right-of-Way

Construction

2010

2009

2011-2013

$17-18

$41-52

$362-399

$17-22

$41-52

$442-564

Construction Contract Group 2:

I-90 eastbound from I-90/I-490 to East 9th St. overhead

Detailed Design

Right-of-Way

Construction

2011

2012

2014-2016

$26-29

$3

$287-317

$28-36

$3-4

$396-505

Construction Contract Group 3:

A: I-90 WB in Central Interchange from E. 9th St. to E. 22nd St.; E. 22nd St. (part-width);

remove Cedar Ave. bridge over I-90

B: I-77 improvements north of Kingsbury Run Bridge

C: I-90 EB in Central Interchange from E. 9th St. to E. 22nd St.; Carnegie (part-width)

Detailed Design

Construction (A)

Construction (B)

Construction (C)

2014

2017-2018

2021

2019-2020

$21-23

$102-112

$83-92

$46-50

$26-33

$159-202

$154-196

$78-100

Construction Contract Group 4:

A: Easterly Interceptor relocation

B: CSX railroad overhead

C: Norfolk Southern railroad overhead

D: Overheads in Innerbelt Curve: Superior (part-width); St. Clair (closure); Hamilton

(closure); Lakeside (closure); Structure under Superior intersection for the proposed I-90 WB

to Chester ramp

E: Innerbelt Curve north of Superior Ave.

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

Construction (C)

Construction (D)

Construction (E)

2019

2020

2022

2022-2023

2022-2023

2024-2025

2026-2027

$18-20

$14-16

$4-5

$25-28

$28-31

$23-25

$116-127

$28-36

$19-24

$8-10

$51-65

$56-71

$50-64

$279-356

Construction Contract Group 5:

A: Overheads in Innerbelt Trench: Prospect (part-width); Euclid (part-width); Chester (part-

width); Payne (closure)

B: I-90 eastbound in Innerbelt Trench from E. 22nd St. to Superior

C. I-90 westbound in Innerbelt Trench from E. 22nd St. to Superior

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

Construction (C)

2025

2026

2028-2029

2030-2031

2031-2033

$15-17

$12-13

$34-37

$77-85

$54-59

$32-41

$19-24

$90-114

$225-287

$169-216

Construction Contract Group 6:

A: I-77 bridge widening over I-490

B: I-77 improvements south of I-490

Detailed Design

Right-of-Way

Construction (A)

Construction (B)

2022

2023

2021-2024

2025-2026

$6-7

$1

$45-49

$25-28

$12-15

$1-2

$89-113

$58-74

Construction Contract Group 7:

I-71 roadway pavement and bridge deck replacements; I-71 southbound deceleration lane to

Jennings

Detailed Design

Construction

2024

2027

$6

$61-68$11-15

$152-194

Totals All phases 2010-2033 $1.6-1.7 billion $2.7 to $3.5 billion

• Innerbelt Curve

• 2022-2027CCG4

• Innerbelt Trench

• 2028-2033CCG5

• I-77 South

• 2021-2026CCG6

• I-71 South

• 2027CCG7

Page 7: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

ODOT’s 1st Value-Based Design-Build Project:

Since 1996 ODOT has used a Low-Bid Design Build Process

to Deliver 80 Projects worth over $400 million

2009 – ODOT received legislative approval to develop and use

a Value-Based Design-Build Process and an increase in the

biennium Design-Build limit from $250 million to $1 billion.

Cuyahoga River Valley Crossing

Page 8: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Design-Build Advantages:

Reduce Delivery Time: Design & Construction Overlap

Improve Constructability: Designed to Contractor’s Strengths

Optimize Costs: Market Based Material Selection

Reduce Conflicts: Single Entity Responsible for Design and

Construction

Cuyahoga River Valley Crossing

Page 9: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Recently Completed Tasks:

Aesthetic and Urban Design

Subcommittee Recommendations – October 22, 2009

City Planning Commission Approval – November 6, 2009

File Plan Package – December 1, 2009

Cuyahoga River Valley Crossing

Page 10: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Upcoming Tasks:

Plans, Specifications & Estimate to FHWA – January 2010

Federal Authorization – February 2010 < 365 Days!

Request for Qualification – February 2010

Request for Proposals – March 2010

Selection and Authorization – Fall 2010

Construction 2011-2014.

Cuyahoga River Valley Crossing

Page 11: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Bicycle and Pedestrian:

Abbey Avenue – Bicycle Lanes (W 11th St to W 20th St)

Towpath Trail – Multi-purpose Trail (University Ave)

Lorain-Carnegie Bridge – Bicycle Lanes (Extend to Ontario St)

East 9th Street – Multi-purpose Trail (Canal Rd to Broadway)

Broadway – Multi-purpose Trail (E 9th St to Carnegie Ave)

Cuyahoga River Valley Crossing

Page 12: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Transit:

Strongsville Park-N-Ride Lot Expansion: Completed

North Olmsted Park-N-Ride Lot Expansion: Completed

Westlake Park-N-Ride Lot Expansion: 2010

ODOT/GCRTA on-going discussions regarding potential

additional capital and operational improvements

Promote OhioRideshare

Cuyahoga River Valley Crossing

Page 13: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Sustainability:

Green Bulkhead (Habitat Pockets) – 2 Locations Eastside

Ring Chamber Pipes (Aeration) – Outfalls

Stormwater Separation – No new flow added to combined

sewer system. Portion of existing stormwater diverted away

from combined sewer system.

Stormwater Best Management Practices (BMP’s)

Cuyahoga River Valley Crossing

Page 14: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Sustainability:

Aesthetic Lighting to Use LED’s

Traffic Signals to Use LED’s

Sign Lighting to be Eliminated through use of High Reflectivity

Sheeting

Cuyahoga River Valley Crossing

Page 15: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Sustainability:

Recycled Materials – Construction Materials Recycled as a

Matter of Economics (Concrete, Asphalt, Steel, etc.).

Reuse of Materials – Medina Block Pavers and Sandstone

Blocks reused on project or stored for reuse along Towpath

Trail.

Cuyahoga River Valley Crossing

Page 16: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Maintenance of Traffic:

Temporary Additional Lanes on I-490 (I-90 to I-77) and on I-77

(I-490 to I-90).

Alternate Route Plan or ARP (I-490 & I-77) must be in place

whenever longer term lane closures are implemented on I-90.

Minimum of 2 lanes in each direction must be maintained on I-

90 at all times (except when overnight or weekend closures

are permitted). In all cases the ARP’s must be in place first.

Cuyahoga River Valley Crossing

Page 17: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Cuyahoga River Valley Crossing

Page 18: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Cuyahoga River

Valley Crossing

Page 19: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Cuyahoga River Valley Crossing

Page 20: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490
Page 21: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Cuyahoga River Valley Crossing

Page 22: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Cuyahoga River

Valley Crossing

Page 23: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Upcoming Tasks:

Detail Design of Pedestrian Underpasses – Underway

Rehabilitation of Pedestrian Underpasses – Summer/Fall 2010

Preliminary Engineering Report – December 2009

Environmental Clearance (CE-4) – May 2010

Initiate Detail Design – Summer 2010

Lakefront West

Page 24: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Construction Sequence:

Rehabilitation of Pedestrian Underpasses: Summer/Fall 2010

Multi-Use Trail: 2011

West 73rd St Underpass: 2012 – 2013

All Other Connections: 2013 – 2014

W 25th/28th St, W 45th/49th St, W 54th St/Division Ave

Mainline Reconstruction – TBD based on availability of funds.

City of Cleveland responsible for balance over $49.8 million

already committed by the TRAC.

Lakefront West

Page 25: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 26: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 27: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 28: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 29: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 30: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 31: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 32: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 33: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490

Lakefront West

Page 34: Ohio Department of Transportation Quarterly Update to ... · 11.12.2009  · Construction Contract Group 6: A: I-77 bridge widening over I-490 B: I-77 improvements south of I-490