8
By Irwin Rapoport CEG CORRESPONDENT The Ohio Department of Transportation (ODOT) will spend more than $330 million over the next five years to complete the Cleveland Opportunity Corridor project. The project is divided into three sections that are designed to help improve the public transporta- tion system and stimulate and sup- port planned economic growth in the areas between I-490/I-77 and University Circle in the city of Cleveland. The area between I-490 and University Circle includes a part of Cleveland known as the “Forgotten Triangle” due to the lack of economic activity. “This effort opens the potential for new economic development, new jobs and a new identity for the community,” stated an ODOT Web page for the project. “The city of Cleveland and Greater Cleveland Partnership (GCP) are working together to develop an economic development plan for the project study area that supports Connecting Cleveland 2020 Citywide Plan. The Opportunity Corridor would support these efforts through enhanced mobility, direct access to the freeways and the University Circle area, new frontage for potential develop- ment, improved visibility and improved multi-modal access.” The Opportunity Corridor study identified key needs of the project and was years in the making. Starting in 2004, ODOT had an HNTB consultant team conduct the Opportunity Corridor Study. “The purpose is to improve the roadway network within a histori- cally underserved, economically depressed area within the city of Cleveland,” stated the Web page. “The Opportunity Corridor Steering Committee, formed in 2005, includes representatives from ODOT, the City of Cleveland, Cuyahoga County, GCP, area Community Development Corporations (CDC), Greater Cleveland Regional Transit Authority, Northeast Ohio Regional Sewer District, residents, business owners and other local stakeholders.” Nothing is being left to chance and the project is following a 14- step process that outlines project development from concept through completion. According to the Web page, “In July 2011, the Steering Committee identified the Recommended Preferred Alternative based on input gathered from the city of Cleveland, CDCs, neighborhood stakeholders and the general pub- lic. The RPA would build a 35- mph boulevard-type road with a median and traffic signals. It also would include new pedestrian and bicycle paths, tree lawns, landscap- ing and vehicular, pedestrian and rail bridges. The project details and impacts were formally presented and discussed at an October 2013 Public Hearing.” The project will open up land for economic development and having consulted stakeholders and a local architectural firm, eight to 10 potential development sites throughout the community benefit area of the project for future re-use have been identified “To date, two of the develop- ment districts have preliminary master land use plans,” stated the Web site. “The conceptual road- way plans have been reviewed with each of the CDC partners for feedback to determine that the effort is moving in the right direc- tion and remains consistent with the community’s overall master plan and the [city’s] proposed land use plan. “During the NEPA process it was determined that the city had a master plan for the Kenneth L. Johnson Recreation Center, which is along the Opportunity Corridor,” it added. “The preferred alignment of the Opportunity Corridor was adjusted to mitigate impacts to the neighborhood and recreation cen- ter plans. The project has commit- ted $500,000 to the Kenneth L. Johnson Recreation Center expan- sion plans, which have stalled due to lack of funding.” ODOT is working hard to ensure that local residents will have an opportunity to find employment via job and job train- ing programs through Ohio Means Jobs. “The project has committed $500,000 to Ohio Means Jobs for on-the-job training, which is esti- mated to train approximately 80 residents,” stated the Web site. “In addition to this commitment, four residents will be given 8,500 hours of on-the-job training on the Section 1 project. Additional hours will be available on Sections 2 and 3 of the project. There also will be ‘community ambassadors’ hired to reach out to the community and identify and assist those who are interested in job training. Finally, at least 20 percent of the project workforce must be residents with- in project area in Cleveland Wards 4, 5 or 6.” ODOT is purchasing land for right-of-way and will require the relocation of residents due to the construction. Every effort is being made to ensure that this process is being handled properly and with minimal impact on those affected by it. “ODOT will implement a vol- untary residential relocation pro- gram to allow some residents whose homes are not directly impacted by the project to be eligi- ble for relocation assistance,” stat- ed the Web page. “Voluntary relo- cations will be offered assistance and benefits that match those pro- vided to the required relocations.” Amanda McFarland, public information officer of ODOT’s District 12 (Cuyahoga, Lake and Geauga counties), pointed out that the process is going well. “The relocation process has begun and is currently ongoing for all relocation parcels,” she said. “All relocations are following the ODOT’s $330M Project to Bring New Opportunities OHIO STATE EDITION A Supplement to: Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640 “The Nation’s Best Read Construction Newspaper… Founded in 1957.” October 10 2015 Vol. XVIII • No. 21 6 24 199 23 4 4 30 30 30 422 68 68 22 22 50 35 25 50 52 6 6 27 22 80 80 90 76 71 71 75 70 75 71 77 77 74 70 70 see ODOT page 4 ODOT Photo Construction crews were busy with paving operations on East 105th Street between Cedar and Quincy Avenues.

Ohio 21 2015

Embed Size (px)

DESCRIPTION

Ohio 21 2015

Citation preview

Page 1: Ohio 21 2015

By Irwin RapoportCEG CORRESPONDENT

The Ohio Department ofTransportation (ODOT) will spendmore than $330 million over thenext five years to complete theCleveland Opportunity Corridorproject. The project is divided intothree sections that are designed tohelp improve the public transporta-tion system and stimulate and sup-port planned economic growth inthe areas between I-490/I-77 andUniversity Circle in the city ofCleveland.The area between I-490 and

University Circle includes a part ofCleveland known as the“Forgotten Triangle” due to thelack of economic activity. “This effort opens the potential

for new economic development,new jobs and a new identity for thecommunity,” stated an ODOTWeb page for the project. “The cityof Cleveland and GreaterCleveland Partnership (GCP) areworking together to develop aneconomic development plan forthe project study area that supportsConnecting Cleveland 2020Citywide Plan. The OpportunityCorridor would support theseefforts through enhanced mobility,direct access to the freeways andthe University Circle area, newfrontage for potential develop-ment, improved visibility andimproved multi-modal access.”The Opportunity Corridor study

identified key needs of the projectand was years in the making.Starting in 2004, ODOT had anHNTB consultant team conductthe Opportunity Corridor Study.“The purpose is to improve the

roadway network within a histori-

cally underserved, economicallydepressed area within the city ofCleveland,” stated the Web page.“The Opportunity Corridor

Steering Committee, formed in2005, includes representativesfrom ODOT, the City ofCleveland, Cuyahoga County,GCP, area CommunityDevelopment Corporations(CDC), Greater ClevelandRegional Transit Authority,Northeast Ohio Regional SewerDistrict, residents, business ownersand other local stakeholders.” Nothing is being left to chance

and the project is following a 14-step process that outlines projectdevelopment from conceptthrough completion.According to the Web page, “In

July 2011, the Steering Committeeidentified the RecommendedPreferred Alternative based oninput gathered from the city of

Cleveland, CDCs, neighborhoodstakeholders and the general pub-lic. The RPA would build a 35-mph boulevard-type road with amedian and traffic signals. It alsowould include new pedestrian andbicycle paths, tree lawns, landscap-ing and vehicular, pedestrian andrail bridges. The project details andimpacts were formally presentedand discussed at an October 2013Public Hearing.”The project will open up land

for economic development andhaving consulted stakeholders anda local architectural firm, eight to10 potential development sitesthroughout the community benefitarea of the project for future re-usehave been identified“To date, two of the develop-

ment districts have preliminarymaster land use plans,” stated theWeb site. “The conceptual road-way plans have been reviewed

with each of the CDC partners forfeedback to determine that theeffort is moving in the right direc-tion and remains consistent withthe community’s overall masterplan and the [city’s] proposed landuse plan.“During the NEPA process it

was determined that the city had amaster plan for the Kenneth L.Johnson Recreation Center, whichis along the Opportunity Corridor,”it added. “The preferred alignmentof the Opportunity Corridor wasadjusted to mitigate impacts to theneighborhood and recreation cen-ter plans. The project has commit-ted $500,000 to the Kenneth L.Johnson Recreation Center expan-sion plans, which have stalled dueto lack of funding.”ODOT is working hard to

ensure that local residents willhave an opportunity to findemployment via job and job train-

ing programs through Ohio MeansJobs.“The project has committed

$500,000 to Ohio Means Jobs foron-the-job training, which is esti-mated to train approximately 80residents,” stated the Web site. “Inaddition to this commitment, fourresidents will be given 8,500 hoursof on-the-job training on theSection 1 project. Additional hourswill be available on Sections 2 and3 of the project. There also will be‘community ambassadors’ hired toreach out to the community andidentify and assist those who areinterested in job training. Finally, atleast 20 percent of the projectworkforce must be residents with-in project area in Cleveland Wards4, 5 or 6.”ODOT is purchasing land for

right-of-way and will require therelocation of residents due to theconstruction. Every effort is beingmade to ensure that this process isbeing handled properly and withminimal impact on those affectedby it.“ODOT will implement a vol-

untary residential relocation pro-gram to allow some residentswhose homes are not directlyimpacted by the project to be eligi-ble for relocation assistance,” stat-ed the Web page. “Voluntary relo-cations will be offered assistanceand benefits that match those pro-vided to the required relocations.”Amanda McFarland, public

information officer of ODOT’sDistrict 12 (Cuyahoga, Lake andGeauga counties), pointed out thatthe process is going well.“The relocation process has

begun and is currently ongoing forall relocation parcels,” she said.“All relocations are following the

ODOT’s $330M Project to Bring New Opportunities

OHIO STATE EDITION A Supplement to:

Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

October 102015

Vol. XVIII • No. 21

624

199

23

4

4

3030 30

422

68

68

22

22

50

3525

50

52

6

6

27

22

80

80

90

7671

7175

70

75

71

77

77

74

70

70

see ODOT page 4

ODOT PhotoConstruction crews were busy with paving operations on East 105th Street between Cedar andQuincy Avenues.

Page 2: Ohio 21 2015

Page 2 • October 10, 2015 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

PRE-OWNED, JOB READY EQUIPMENT NOW AVAILABLE! Cincinnati • Mt. Orab • Hilliard • Reynoldsburg • Lexington • Louisville

Call Brad Kent at 513-266-7761 or on our USED EQUIPMENT HOTLINE: 888.BOBCATS

Parts • Sales • Service • Rental • Training

To See More Machines, Please visit us online at www.bobcat-ent.com

2011 S150 Bobcat Loader, 665 Hrs, Open ROPS, CN 95760 ............................................................................................$24,000

2012 S630 Bobcat Loader, 1200 Hrs, Cab Heat & Air, PowerQuick Tatch, Keyless, CN 94338....................................$32,000

2011 S650 Bobcat Loader, 1660 Hrs, Cab Heat & Air, PowerQuick Tatch, 2 Speed, CN 95099 ..................................$36,500

2011 S770 Bobcat Loader, 1520 Hrs, Cab Heat & Air, 2Speed, ACS Controls, CN 93400 ..................................$46,000

2012 T750 Bobcat Track Loader, 1865 Hrs, Cab Heat & Air,High Flow, 2 Speed, CN 95771 ......................................$49,000

2012 T870 Bobcat Track Loader, 1300 Hrs, Cab Heat & Air,High Flow, CN 95008 ......................................................$58,500

2014 DA30 Doosan Articulated Truck, 500 Hrs, CN 90330..............................................................................................$328,800

2014 DX420LC-3 Doosan Excavator, 850 Hrs, CN 90363 ................................................................................................$258,880

P I T T S B U R G H P H I L A D E L P H I A W A S H I N G T O N D .C . T O R O N T O

ILL RIGS FOR RENTDRILL RIGS FOR RENT1.800.PILE.USA -or- www.ecanet.com

AUTHORIZED DEALER:

EQUIPMENT CORPORATION OF AMERICA

B U I L D I N G F O U N D A T I O N S S I N C E 1 9 1 8

PHILADELPHIAPO Box 387Aldan, PA 19018P 610.626.2200F 610.626.2245

PITTSBURGHPO Box 306Coraopolis, PA 15108P 412.264.4480F 412.264.1158

WASHINGTON, D.C.6300 Foxley RoadUpper Marlboro, MD 20772P 301.599.1300F 301.599.1597

TORONTO166 Bentworth AveToronto, Ontario M6A 1P7P 416.787.4259F 416.787.4362

Page 3: Ohio 21 2015

Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • October 10, 2015 • Page 3

Page 4: Ohio 21 2015

Page 4 • October 10, 2015 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

Effort Opens Potential for New Economic Development requirements of the Federal Uniform Relocation Assistanceand Real Property Acquisition Policies Act. New develop-ment that will result from the Opportunity Corridor is beingcoordinated through the city of Cleveland Planning Officewith help from the neighborhood Community DevelopmentCorporations (CDCs) and the Greater Cleveland Partnership(GCP).”

Lessons are being learned via consultation process andcommunity input that will be applied to future road con-struction/urban redevelopment projects.

“Since this project took nearly 10 years to get through the

environmental phase of the project, it is very important tohave good documentation of major decisions made through-out the process,” said McFarland. “Once construction fund-ing was identified for the Opportunity Corridor project, thoseindividuals and groups opposed to the project came out andvoiced their questions and concerns over issues that werealready addressed during the environmental process. It wasvery helpful to be able to respond to those questions whenthere was documentation. Some of their concerns, includingthe inclusion of cul-de-sacs along the corridor, were furtherlooked into and removed from the project entirely.”

In April, 2013, the Federal Highway Administration coor-

dinated a project cost estimate review and it is estimated thatthe project will cost $331.3 million, based on “all currentlyknown work required to build the project, including the costsof final design, project administration and management, landacquisition, utility relocation, implementation of environ-mental commitments and mitigation measures, and con-struction activities.”

McFarland noted that ODOT’s project management teamis responsible for overseeing all aspects of the projects,including on-time delivery and on budget.

ODOT is using this project to give new employees oppor-tunities to learn about managing new projects.

“We do have a new transportation civil engineer workingon the project,” said McFarland. “Erin Spahr started workingfor the department in January and the Opportunity Corridorwas the first project she was assigned to. We also collaboratewith high schools and colleges, not on a specific projectbasis, but to give students a chance to learn about what wedo at ODOT on the planning and construction aspects ofcivil engineering.”

The overall work will require a serious relocation of utili-ties—gas, electrical, cable and communications, water andsewer pipes, and storm drains.

“ODOT receives utility plans from the respective utilitycompanies within the footprint of the project,” saidMcFarland. “The existing utilities will be plotted on the proj-ect plans along with the proposed utilities that will beinstalled by ODOT’s contractor. We coordinated with theutility companies before the project began to explain whatwould need relocated—when and where—and we’re hold-ing regular meetings with utility companies to ensureprogress and the meeting of schedules. ODOT can only payfor relocation or adjustment of publicly owned utilities. Forprivately owned utilities, ODOT can pay for the relocation

ODOT PhotoA bird’s-eye view of the paving operations along East105th Street between Cedar and Quincy Avenues,shows the progress.

see ODOT page 6

ODOT from page 1

HUDSON6681 Chittenden RoadHudson, Ohio 44236P: (330) 655-5900F: (330) 655-5969

COLUMBUS3155 E. 17th AvenueColumbus, Ohio 43219P: (614) 475-2880F: (614) 475-0069

CINCINNATI8131 Regal Lane

West Chester, Ohio 45069P: (513) 777-5556F: (513) 777-4494

www.themcleancompany.com

Page 5: Ohio 21 2015

Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • October 10, 2015 • Page 5

Hat’s Off to

Highway Equipment Company

We’re proud to have Highway Equipment Company as part of the Allied Distributor network providing our valued customers in the greater Canton, Ohio area with the:

• Full-line of Rammer, AR Series™ , Hy-Ram® hydraulic hammers, Ho-Pac® vibratory compactor/drivers including the Skid-Pac™, Pedestal Breaker System™ boom systems, Contractor’s Mechanical Grapple demolition and material/waste handling systems, AMS Series mobile shears and Grip-Lug® grouser bars.

• Factory authorized parts and service to keep those Allied products productive and on the job.

1405 Timken Place SWCanton, Ohio 44706Tel: 330-915-8391Fax: [email protected]

Hat’Highway Equipment Company

s Off Hat’to

Highway Equipment Company

Of ent Company

any

Highway Equipment Company

Highway Equipment Company

ent Company

any

e’re proud to ha WAllied Distributor network providing our valued customers in the greater Canton, Ohio area with the:

ave Highway Eq p t C network providing our va

greater Canton, Ohio area with the:

e’re proud to have Highway Equipment Company as part of the Allied Distributor network providing our valued customers in the

• Full-line of Rammerhammers, Ho-Pac®

including the Skid-Pac™, Pedestal Breaker System™ boom systems, Contractor’demolition and material/waste handling systems, AMS Series mobile shears and

, AR Series™ , Hy-Ram mer r, AR Series™ , Hy-Ram® y compactor/drivers vibrator

including the Skid-Pac™, Pedestal Breaker System™ parGlas Mechanic ntractor’ ’s Mechanic

demolition and material/waste handling systems, AMS Series mobile shears and

, AR Series™ , Hy-Ram® hydraulic y compactor/drivers

including the Skid-Pac™, Pedestal Breaker System™ elpp

systems, AMS Series mobile shears and Grip-Lug® grouser bars.

y authorized parts and • Factorvice to keep those Allied ser

products productive and on the job.

systems, AMS Series mobile shears and grouser bars.

y authorized parts and vice to keep those Allied

products productive and on

Page 6: Ohio 21 2015

only if the private utility has a compensable right. All otherutility relocations are the responsibility of the respective util-ity owner.”Utility relocation for both public- and privately-owned

utilities is currently on-going via the work being done onSection 1. To prepare for the work that will be done onSection 2, said McFarland, “we are planning to remove theremaining residential structures and as many commercialstructures that are cleared.”The work for Section 1—$20.9 million—was awarded to

a joint venture consisting of McTech Corporation/Perk

Company Inc. They will widen the existing East 105th Streetfrom Quebec Avenue to north of Chester Avenue.Construction began in the spring of 2015, and is expected tobe complete in the fall of 2017. The work includes pavementremoval, excavation, waterline installation, electrical work,drainage and paving operations.The contracts for the second and third sections have not

been tendered yet.ODOT announced in June 2015, that there is a change to

the Section 2 procurement process, which is now a valuebased design-build contract.“By using this method,” stated an ODOT project Web site,

“ODOT can better evaluate each team’s approach to the proj-ect. This change will have minimal, to no impact, on theoverall completion date of the project.”The work for this section — $30 million—will see new

roadway from the Quebec Avenue to East 93rd Street and theconstruction of a new bridge over Quincy Avenue.Construction is expected to begin in the spring of 2016 andbe completed in the fall of 2018. Section 3 — $220 million — also a value based design-

build contract, will see new roadway built between East 93rdStreet and the I-490/East 55th Street intersection. The workis expected to begin in 2017 and be delivered in 2019.“The value based design-build bid opening date for

Section 2 is scheduled for mid-February, 2016, and forSection 3, in the calendar year 2017 or 2018,” saidMcFarland. “In value based design-build contracting, thedesign-build contract is awarded to the bidder with the bestvalue score. Best value scores are determined based on acombination of bid price and a technical qualificationsassessment. By using this method, ODOT can better evalu-ate each team’s approach to the project.” ODOT has held information sessions for contractors for

Section 2 and has provided materials for the contractors tobetter prepare their bids.“Prospective bidders also have ODOT’s prebid question

process available to them during the bidding process,” saidMcFarland, who added that ODOT determines the best pro-curement process for each project on a case-by-case basis.ODOT expects to award the contract for Section 2 in early2016.The basic design for all three sections was prepared by

ODOT engineers and HNTB. The key design featuresinclude a 35 mile-per-hour urban boulevard; 1.4 mi. (2.25km) of existing alignment; 2.2 mi. (3.54 km) of new align-ment; four new roadway bridges; two new pedestrianbridges; one new railroad grade separation; mast arm trafficsignals at intersections; a multi-purpose path on the southside; sidewalks on the north, LED lighting; and landscaping. “After undergoing nearly 10 years of planning,” said

McFarland, “the Federal Environmental ImpactStatement/Record of Decision was approved by the FederalHighway Administration on May 1, 2014. Since a majorityof the project will be design-build, the time frame for com-pletion of the design is still ongoing.”ODOT will be removing hazardous materials within the

roadway right-of-way limits. When the work is done, thenew roadways will be able to handle close to 45,000 vehiclesdaily and cover traffic demands for the next 20 years.

(This story also can be found on ConstructionEquipment Guide’s Web site at www.constructionequip-mentguide.com.) CEG

Key Design Features Include Four New Roadway Bridges

ODOT PhotoThe Perk Company installing lighting conduit alongEast 105th Street in July 2015.

ODOT from page 4

Page 6 • October 10, 2015 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

Page 7: Ohio 21 2015

Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • October 10, 2015 • Page 7

800.392.2686

YOUR SOURCE FOR

SALES AND RENTALS CRAWLER TRUCKS, STUMP CUTTERS

AND FORESTRY MULCHERS

Page 8: Ohio 21 2015

Page 8 • October 10, 2015 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide