Page 1: Offshore Power Cable Installation

ICOE: Halifax 11/2014

Page 2: Offshore Power Cable Installation

Offshore cable installation is organized into 3 Sectors ◦ 1. Array: Interconnecting a grid of offshore wind turbines

via a subsea cable system 33KV with 66KV being developed

◦ 2. Export: Connecting an offshore windfarm to an onshore power grid via a subsea cable system HVAC or HVDC

◦ 3. Interconnect: Connecting 2 or more power grids

via a subsea cable system HVDC or HVAC

Export & Interconnect projects are similar, Different vessels, equipment and expertise is required for Array market

Interconnect

2

Page 3: Offshore Power Cable Installation

Export/Interconnect Cable (HVDC) ◦ Weight will be comparable to HVAC, but will consist of

two cables adding an additional wrinkle to cable handling.

Export/Interconnect Cable (HVAC) range ◦ Diameter: 200mm-225mm (appx 8”-9”) ◦ Weight in air: 80kg/m to 90kg/m. (176-200lbs/m.) ◦ Minimum Bend Radius: 3.3m

Array Cable range ◦ Diameter:100mm-150mm (appx 4”-5”) ◦ Weight in air: 21kg/m to 58kg/m. (46-127lbs/m.) ◦ Minimum Bend Radius: 2.2m

Array Cable

Export/Interconnect (left)

Array Cable

(right)

Note: As there is little/no marine cable manufacturing in North America - offshore cable comes from Europe or Asia – if

it is not transported on the installation vessel cost effective shipping, transfer and storage is required

Export/Interconnect Cable

Page 4: Offshore Power Cable Installation

4

Page 5: Offshore Power Cable Installation

5

Cable Shipping & Transport

Export/Interconnect Main Lay Vessel

Array Main Lay Vessel

Cable Burial/ROV Vessel

Cable Storage Facility

Cable Maintenance Vessel

Personnel Transfer Vessel(s)

Guard Vessel(s)

Shipyard Access for Modifications, Mobilization, Demobilization

Cable Manufacturing Facility with ocean access

Page 6: Offshore Power Cable Installation

6 Photo: Global Marine

Page 7: Offshore Power Cable Installation

7

Page 8: Offshore Power Cable Installation

- Health & Safety - Project Engineering - Project Asset Management - Fleet Operations Mgmt - Vessel/Barge Operations - Safe and efficient operation all working decks - Contract Compliance -Operational readiness of back deck equipment. -Operational readiness of Subsea equipment. - ROV operations. - Management of Survey office/equipment. - Calibration/Operation of all Survey equipment/data. - Project data management - Operations & Maintenance

Developing these resources is a major market challenge

Page 9: Offshore Power Cable Installation

9

Source: Crown Estate

Page 10: Offshore Power Cable Installation

10

Source: Friends of the Supergrid

Page 11: Offshore Power Cable Installation

11

On- Land Offshore

Page 12: Offshore Power Cable Installation

[email protected]

Photo: Global Marine