    DREDGING - for OIL and GAS activities in Canada

    Dredging is an excavation activity or operation usually carried out atleast partly underwater, in shallow seas or fresh water areas with the

    purpose of gathering up bottom sediments and disposing of them at adifferent location.

    In Holland dredging and land reclamation has been ongoing forcenturies, ever since the Frieslanders first settled there.

    GOD CREATED THE WORLDBUT THE

    DUTCH CONSTRUCTED HOLLAND

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    3/35

    DREDGING - for OIL and GAS activities in Canada Dredger categories

    Construction of sacrificial beach islands and sub-sea berms

    Channel and harbour dredging

    Land reclamation and coastal protection

    Tailings transfer, MFT reclamation & mud farming (Oil Sands)

    Excavation of glory holes

    Trenching for pipelines

    Pipe and cable laying and intervention

    Placement of protection/pipeline intervention

    Platform and wellhead intervention

    Land falls and shore approaches

    Environmental clean up and disposal

    Decommissioning

    Innovation, Engineering and Development

    Equipment past present and future John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    4/35

    DREDGING - CATEGORIES MECHANICAL

    BUCKET DREDGERS CLAMSHELL DREDGERS BACK HOE DREDGERS

    HYDRAULIC CUTTER SUCTION DREDGERS SUCTION DREDGERS TRAILING SUCTION HOPPER DREDGERS

    SPECIALTY EQUIPMENT FALL PIPE VESSELS ROCK PLACEMENT EQUIPMENT DEEP WATER GRAB SYSTEMS

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    5/35

    DREDGING - for OIL and GAS activities in Canada Construction of sacrificial beach (artificial) islands

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    6/35

    DREDGING - for OIL and GAS activities in Canada

    Construction of sacrificial beach (artificial) islands

    John M. WaringSNAME Presentation Calgary 2010

    Construction by pump ashore suction dredge andbow discharge from trailer suction hopper dredgers

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    7/35

    DREDGING - for OIL and GAS activities in Canada

    Construction of artificial islands Trailer Suction Hopper Dredge

    John M. WaringSNAME Presentation Calgary 2010

    Stage 1 bottom dumping

    Stage 2 - rainbowing

    Stage 3 pump ashore

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    8/35

    DREDGING - for OIL and GAS activities in Canada Construction of sub-sea berms for caisson deployment

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    9/35

    DREDGING - for OIL and GAS activities in Canada Channel and Harbour Dredging

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    10/35

    DREDGING - for OIL and GAS activities in Canada Rainbowing

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    11/35

    DREDGING - for OIL and GAS activities in Canada Land Reclamation

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    12/35

    DREDGING - for OIL and GAS activities in Canada Reclamation

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    13/35

    DREDGING - for OIL and GAS activities in Canada Coastal protection design and installation

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    14/35

    DREDGING - for OIL and GAS activities in Canada Tailings transfer, MFT reclamation & mud farming (Oil Sands)

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    15/35

    DREDGING - for OIL and GAS activities in Canada Tailings transfer, MFT reclamation & mud farming (Oil Sands)

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    16/35

    DREDGING - for OIL and GAS activities in Canada Excavation of Glory Holes

    John M. WaringSNAME Presentation Calgary 2010

    Glory hole dredging has been achieved using trailer suction hopper dredgerswith extended suction pipes and mechanical Grab Excavating Systems

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    17/35

    DREDGING -for OIL and GAS activities in Canada Excavation of Glory Holes

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    18/35

    DREDGING - for OIL and GAS activities in Canada Trenching for Pipelines

    John M. WaringSNAME Presentation Calgary 2010

    Modern plough design

    Conventional excavation with a draghead

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    19/35

    DREDGING - for OIL and GAS activities in Canada Pipe and Cable laying

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    20/35

    DREDGING - for OIL and GAS activities in Canada Placement of protection

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    21/35

    DREDGING - for OIL and GAS activities in Canada Placement of protection

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    22/35

    DREDGING - for OIL and GAS activities in Canada Platform & Well Head intervention

    John M. WaringSNAME Presentation Calgary 2010

    Material placed mechanically Material placed with a fall pipe

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    23/35

    DREDGING - for OIL and GAS activities in Canada Landfalls and Shore Approaches

    John M. WaringSNAME Presentation Calgary 2010

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    24/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - for OIL and GAS activities in Canada Environmental cleanup and disposal

    Pollution Recovery System

    Designed to remove oil and chemicals from vessels lying on the sea bed in very deep water without using divers.Currently depths of 500 meters can be obtained and greater depthsdown to 4000 meters are envisaged.

    Artificial island constructed to placeenvironmentally sensitive materials.

    Disc cutter developed for removing

    polluted materials.

    Trailer suction hopper dredgewith modified suction pipearms for collecting surface oil.

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    25/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - for OIL and GAS activities in Canada So what is new in the dredging business since our days in the Canadian Beaufort?

    HEALTH & SAFETY PROGRAMS

    QUALITY MANAGEMENT SYSTEMS

    TRAINING

    ENVIRONMENTAL MANAGEMENT SYSTEMS

    INNOVATION, RESEARCH & DEVELOPMENT

    FLEET REPLACEMENT PROGRAMS

    http://www.geovisie.nl/gallery/Bjorvika-tunnel-Oslo-Norway/Scradewayhttp://www.geovisie.nl/gallery/Bjorvika-tunnel-Oslo-Norway/Scradeway
  • 8/11/2019 Offshore Dredging+Boskails.pdf

    26/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - GOING DEEPERInnovation, Engineering & Development

    Concept designs are currently being engineered to excavate materialand place protection at depths of more than 250 meters below sea level

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    27/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING EXCAVATING HARDER MATERIALS

    Pipeline trenching is now possible inseabed soils with UCS values up to 30MPa in harsh metocean conditions andenvironmentally sensitive areas.Hard soil is normally dredged by meansof a Cutter Suction Dredger.

    Special drag heads (ripper drag heads)are developed for large Trailing SuctionHopper Dredgers for the dredging ofharder soil.

    Innovation, Engineering &Development

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    28/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - EQUIPMENT PAST

    DArtagan 28200 kw

    J.F.J DeNul 27240 kw

    Cristobal Colon 46000 M3

    Leif Eriksson 46000 M3Ham 318 37293 M3

    Cornelius Zanen 8000 M3 W. D. Gateway 6000 M3

    Beaver MackenzieGeopotes X 10000 M3

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    29/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING EQUIPMENT PRESENT

    DArtagan 28200 kw

    J.F.J DeNul 27240 kw

    Cristobal Colon 46000 M3

    Leif Eriksson 46000 M3Ham 318 37293 M3

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    30/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - FLEET REPLACEMENT PROGRAMS

    Willem van Oranje

    Gateway

    A new generation

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    31/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - Innovation, Engineering and Development

    Dynamically Positioned Fallpipe Vessel (DPFV)Carrying capacity 24,000 ton

    Under Construction

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    32/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - Innovation, Engineering and Development

    Side stone dumping

    Cable layingDiving SupportSalvageHeavy lift & transport Pipeline shore approach construction (pipe-pull)

    Multi-purpose vessels for

    offshore project support

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    33/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - Innovation, Engineering and Development

    Development of remote controlledsub-sea excavating equipment

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    34/35

    John M. WaringSNAME Presentation Calgary 2010

    DREDGING - Innovation, Engineering and Development Under development special equipment for shallow water pipe laying

  • 8/11/2019 Offshore Dredging+Boskails.pdf

    35/35

    John M Waring

    DREDGING when SIZE MATTERSDArtagan 28200 kw

    J.F.J DeNul 27240 kw

    Cristobal Colon 46000 M3

    Leif Eriksson 46000 M3Ham 318 37293 M3