Offshore Deployment

Flexible Pipe & Cable Handling

SEM REV Subsea Cable

Spooling & Deployment

February to July 2015

Product Handling Solutions

Flowline Specialists designs, engineers and manufactures equipment handling solutions for the renewable energy and manufacturing industry and oil & gas sectors.

• Cable deployment and recovery

• Decommissioning

• Onshore spooling

• Flexible pipe and umbilical handling

Products & Services

Under rollers 300Te hub driveTensioners

Linear cable engines Shaft drive spooler with level winds Experienced Technicians

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Cables:

600m of 86mm cable approx. 13Te

with one connector

Connector weights approx. 1Te each

1250m of 102mm cable approx.

30Te with two connectors

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Reel selection

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Reel design and modification

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Reel modification

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Design of reel cradles

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Manufacture of reel cradles

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Modifications to shaft drive spooler

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Transpooling of cables

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Securing end connectors

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Design of spreader beam

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Load testing of spreader beam

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Load out

of reels

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Arrival of reels at client site

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Deck layout

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Deck layout

SEM REV Subsea Cable Spooling & Deployment

February to July 2015

Installation

SEM REV Subsea Cable Spooling & Deployment

February to July 2015